Two-way dense rib cavity floor pipeline installation method
By customizing the junction box and L-shaped pull tabs to construct a three-dimensional fixing system and a side wall glass magnesium board positioning device, the problems of junction box displacement and glass magnesium board sealing were solved, high-precision pipeline installation and structural integrity were achieved, the cross-sectional dimensions of the secondary ribs were ensured to avoid leakage, and the construction process was optimized.
Patent Information
- Application Number
- CN202510661225.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-22
- Publication Date
- 2025-09-12
AI Technical Summary
In the existing technology, the junction box is prone to displacement or inward collapse during the hydropower installation construction phase. The gap position on the glass magnesium board is not sealed tightly, which poses a risk of leakage. The glass magnesium board is not effectively positioned, and the cross-sectional size of the secondary rib beams around the cavity board cannot be guaranteed after concrete pouring.
A three-dimensional fixing system is constructed using customized junction boxes and L-shaped pull tabs, and symmetrical holes are opened on the side wall glass magnesium board to match the side wall glass magnesium board positioning device. Bidirectional stress balance is achieved through water-stop gaskets and connecting sleeves to ensure the fixation of the junction box and the sealing of the glass magnesium board.
It improves the installation quality of the junction box, enhances the overall sealing and structural integrity of the glass magnesium board, ensures the accurate cross-sectional dimensions of the secondary rib beam, avoids the risk of leakage, shortens the construction period, and reduces common quality defects and rework.
Smart Images

Figure CN120625784A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, in particular to a method for installing pipelines in a bidirectional dense-rib cavity floor. Background Art
[0002] The dense rib cavity floor is a new type of structural system that combines the advantages of reinforced concrete floor and dense rib cavity slab. It is mainly composed of bottom plate 1, top plate 2 and side wall plate. The side wall plate is a side wall glass magnesium plate 3. Figure 1 shown.
[0003] Utility piping installation typically occurs after the cavity floor baseplate is laid, ensuring the complete installation of the piping system before the top slab is closed. Currently, plumbing installation typically involves on-site drilling. After the dense-ribbed cavity floor baseplate is installed, holes are drilled in the baseplate according to the designed locations. Terminal boxes for the utility lines are embedded within the holes and sealed with cement mortar. Because the boxes rely solely on the baseplate for support, quality defects such as box displacement or indentation can easily occur during wiring and equipment tightening during the plumbing and electrical installation phase. Furthermore, the sidewall glass magnesium panels are connected to the edges of the baseplate and cover plate via prefabricated slots. When the piping system is connected to the terminal boxes, it must penetrate the sidewalls, creating a structural gap at the bottom of the panels. The cement mortar seal at this location is difficult to achieve due to the discontinuous interface, posing a risk of leakage. If the sidewall glass magnesium panels are not properly positioned, the cross-sectional dimensions of the secondary rib beams surrounding the cavity panel cannot be guaranteed after concrete pouring. Summary of the Invention
[0004] The present invention aims to provide a method for installing pipelines in a bidirectional dense-rib cavity floor slab, so as to solve the problems in the prior art that the junction box is prone to displacement or inward collapse during the water and electricity installation construction stage, the gap position on the glass magnesium board is not tightly sealed, there is a risk of leakage, the glass magnesium board is not effectively positioned, and after the concrete is poured, the cross-sectional dimensions of the secondary rib beams around the cavity board cannot be guaranteed.
[0005] The present invention is achieved by adopting the following technical solutions:
[0006] The present invention provides a method for installing pipelines in a bidirectional dense-rib cavity floor, comprising the following steps:
[0007] S1: Install the cavity plate bottom plate;
[0008] S2: Make custom wire boxes;
[0009] Step S2 specifically includes:
[0010] S201: Prepare the wire box;
[0011] S202: Fixing support members at both ends of the wiring box, and extending one end of the support member toward the outside of the wiring box to obtain a customized wiring box;
[0012] S3: Install and secure the custom junction box;
[0013] A hole is opened on the bottom plate, and the customized wire box is placed in the hole. After the customized wire box is placed in the hole, the support members on both sides of the wire box are attached to the top surface of the bottom plate, and then the second pull tab is fixed to the bottom plate to form a three-dimensional fixing system;
[0014] S4: Install the side wall glass magnesium board and the top board, and install the side wall glass magnesium board vertically between the bottom board and the top board;
[0015] S5: Holes are opened symmetrically on the glass magnesium plates on the side walls of the secondary rib beam casting space;
[0016] S6: Making a side wall glass magnesium board positioning device; wherein the side wall glass magnesium board positioning device includes a wire tube, a water stop gasket and a connecting sleeve, and the water stop gasket is sleeved on the wire tube and fixedly connected to the wire tube;
[0017] S7: Install the side wall glass magnesium board positioning device;
[0018] Pass one end of the two wire tubes through the holes on the side wall glass magnesium board on both sides of the secondary rib beam casting space, insert the end of the wire tube into the secondary rib beam casting space from the inner side of the side wall glass magnesium board, place the connecting sleeve in the secondary rib beam casting space, insert the ends of the two wire tubes into the two ends of the connecting sleeve respectively, and make the water stop gasket contact with the side wall glass magnesium board. At this time, the water stop gasket is in contact with the inner side of the side wall glass magnesium board; then fix the two wire tubes to the connecting sleeve.
[0019] As the preferred technical solution:
[0020] In step S202, the support member adopts an L-shaped pull tab;
[0021] Step S202 specifically includes: fixing an L-shaped pull tab at each end of the wiring box, the L-shaped pull tab includes a first pull tab and a second pull tab that are perpendicular to each other, and affixing one side of the first pull tab to the side of the wiring box and fixedly connecting it to the wiring box. At the same time, the second pull tab is extended to the outside of the wiring box, and the second pull tab is arranged horizontally to obtain a customized wiring box.
[0022] As the preferred technical solution:
[0023] The L-shaped pull tab may be an elastic pull tab.
[0024] As the preferred technical solution:
[0025] Step S1 specifically includes:
[0026] S101: Setting up a formwork support frame and laying a formwork on the formwork support frame. Position reference lines are drawn on the formwork, and the position reference lines divide the installation areas of each base plate.
[0027] S102: Hoist the base plate onto the formwork;
[0028] S103: Review the template elevation and flatness;
[0029] S104: Before the baseboard is officially laid, the baseboard fixing parts are affixed in the installation area of the baseboard;
[0030] S105: Arrange the base plates according to the position reference lines on the template in accordance with the design layout drawing, place each base plate within the installation area divided by the position reference lines, and ensure that the outer edge of the bottom of the base plate is consistent with the edge of the corresponding position reference line.
[0031] As the preferred technical solution:
[0032] The bottom plate fixing piece may be, but is not limited to, a double-sided tape, as long as it can fix the bottom plate in a designated position.
[0033] As the preferred technical solution:
[0034] The formwork support frame includes multiple vertical poles. In step S102, when multiple base plates are hoisted at one time, the multiple base plates are first placed on the formwork in an overlapping manner. At this time, the four corner points of the base plates are placed exactly at the center positions corresponding to the four vertical poles to achieve balanced transfer of the upper load;
[0035] Before hoisting multiple base plates at a time, mark the pole points on the template to facilitate accurate hoisting.
[0036] As the preferred technical solution:
[0037] In step S104, bottom plate fixing members are attached to the four sides of the bottom surface of the bottom plate on the template at positions corresponding to the template to form a plurality of rectangular frames.
[0038] As the preferred technical solution:
[0039] Step S4 specifically includes: vertically installing the side wall glass magnesium board between the bottom plate and the top plate, so that the upper and lower sides of the side wall glass magnesium board are respectively installed in the prefabricated card grooves at the ends of the top plate and the bottom plate, and positioning the side wall glass magnesium board.
[0040] As the preferred technical solution:
[0041] Step S5 specifically includes: using a hole opener to open holes in the side wall glass magnesium board according to the electrical professional design drawings.
[0042] As the preferred technical solution:
[0043] Step S6: When manufacturing the side wall glass magnesium board positioning device, threaded holes are pre-opened on the ends of the two wire tubes and the connecting sleeve, and the wire tubes are fixedly connected to the connecting sleeve by screwing fasteners into the corresponding threaded holes.
[0044] As the preferred technical solution:
[0045] The fasteners may be set screws.
[0046] As the preferred technical solution:
[0047] The bidirectional dense-rib cavity floor slab pipeline installation method further includes:
[0048] S8: Check and compound the side wall glass magnesium board and the side wall glass magnesium board positioning device.
[0049] As the preferred technical solution:
[0050] The bidirectional dense-rib cavity floor slab pipeline installation method further includes:
[0051] S9: Thread the wires into the conduit according to the electrical design drawings to complete the installation of water and electricity pipelines.
[0052] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0053] 1. The present invention constructs a three-dimensional fixing system through L-shaped pull tabs and self-tapping screws. The L-shaped pull tabs support the junction box and fix the junction box by fixing the L-shaped pull tabs to the base plate. This solves the problems of weak pre-buried fixation and positioning deviation of the water and electricity terminal junction box, and improves the installation quality of the junction box.
[0054] 2. The present invention adopts a high-precision seamless plate interlocking process, symmetrically opens holes on the side wall glass magnesium plates on both sides of the secondary rib beam casting space, and cooperates with the side wall glass magnesium plate positioning device to achieve bidirectional stress balance, thereby enhancing the overall sealing and structural integrity of the side wall glass magnesium plates, ensuring that the side wall glass magnesium plates fit well with the top plate and the bottom plate and the joints are tight, solving the problems of loose joints between the side wall glass magnesium plates and the top plate and the bottom plate and cracking of the side wall glass magnesium plates due to late grooving, avoiding cracking of the side wall glass magnesium plates due to pipeline grooving in the later stage, ensuring the accuracy of the cross-sectional dimensions of the secondary rib beams around the cavity plate, ensuring that the cross-sectional dimensions of the secondary rib beams meet the design requirements, and at the same time ensuring the flatness of the top plate and the secondary rib beams; and relying on the water-stop gasket to enhance the tightness of the sealing, avoiding the risk of leakage and slurry leakage.
[0055] 3. This invention optimizes the construction process, innovatively integrating pipeline pre-laying with a high-precision seamless plate interlocking process to complete pipeline laying in advance and ensure plate fit. The unique symmetrical hole structure, supplemented by a sidewall glass magnesium plate positioning device and a bidirectional stress balance system, is equipped with modular customized equipment and process reengineering technology. This technical system achieves millimeter-level positioning accuracy, effectively reducing common quality defects, effectively avoiding the risk of structural cracking, and eliminating the potential for grout leakage. It also provides precise controllable cross-sectional dimensions, reduces rework, improves efficiency, and shortens the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] Figure 1 This is a structural diagram of a dense-rib cavity floor in the prior art.
[0057] Figure 2 The present invention provides a flow chart of the method for installing pipelines in a bidirectional dense-ribbed cavity floor.
[0058] Figure 3 This is a schematic diagram of the installation of the customized junction box described in the present invention (top view).
[0059] Figure 4 for Figure 3 Cross-section view in the AA direction.
[0060] Figure 5 This is a schematic diagram of the installation of the side wall glass magnesium board positioning device described in the present invention (side view).
[0061] Figure 6 It is a structural schematic diagram of the side wall glass magnesium board positioning device of the present invention.
[0062] Icons: 1-bottom plate, 2-top plate, 3-side wall glass magnesium board, 4-secondary rib beam casting space, 5-customized junction box, 501-junction box, 502-L-shaped pull tab, 503-self-tapping screw, 504-first pull tab, 505-second pull tab, 6-side wall glass magnesium board positioning device, 601-wire pipe, 602-waterstop gasket, 603-connecting sleeve, 604-threaded hole. DETAILED DESCRIPTION
[0063] To make the objectives, technical solutions, and advantages of the embodiments of the present invention more clear, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.
[0064] Example 1
[0065] like Figure 2As shown, this embodiment provides a bidirectional multi-rib cavity floor pipeline installation method, including the following steps:
[0066] S1: Install cavity plate bottom plate 1;
[0067] Step S1 specifically includes:
[0068] S101: erecting a pin-key scaffolding as a formwork support frame, and laying a formwork on the formwork support frame, with position reference lines drawn on the formwork, which divide the installation areas of each base plate 1;
[0069] S102: hoisting the base plate 1 onto the template;
[0070] S103: Review the template elevation and flatness;
[0071] S104: Before the base plate is officially laid, double-sided tape is pasted on the installation area of the base plate 1;
[0072] S105: Arrange the base plates 1 according to the position reference lines on the template in accordance with the design layout drawing, and place each base plate 1 within the installation area divided by the position reference lines, while ensuring that the outer edge of the bottom of the base plate 1 coincides with the edge of the corresponding position reference line.
[0073] In step S104, double-sided tape is pasted on the four sides of the bottom surface of the base plate 1 at positions corresponding to the template to form a plurality of rectangular frames. The width of the double-sided tape is 2 cm.
[0074] The formwork support frame includes multiple vertical poles. In step S102, when multiple base plates 1 are hoisted at one time, the multiple base plates 1 are first overlapped and placed on the formwork. At this time, the four corner points of the base plate 1 are required to be exactly located at the center position of the four vertical poles to achieve balanced transfer of the upper load. Therefore, before hoisting multiple base plates 1 at one time, the vertical pole points are first marked on the formwork to facilitate accurate hoisting.
[0075] S2: Make custom wire box 5;
[0076] Step S2 specifically includes:
[0077] S201: Prepare a wire box 501; the wire box 501 is an existing 86-type wire box with a size of 79mm*79mm*100mm;
[0078] S202: An L-shaped pull tab 502 is fixedly connected to each end of the wiring box 501. The L-shaped pull tab 502 includes a first pull tab 504 and a second pull tab 505 that are perpendicular to each other. One side of the first pull tab 504 is affixed to the side of the wiring box 501 and fixedly connected to the wiring box 501. At the same time, the second pull tab 505 is extended outward from the wiring box 501 and arranged horizontally to obtain the customized wiring box 5. The fixed connection method can be welding.
[0079] S3: Install and fix the customized junction box 5;
[0080] A hole is opened on the bottom plate 1, and the customized wire box 5 is placed in the hole. After the customized wire box 5 is placed in the hole, the second pull tabs 505 on both sides of the wire box 501 are attached to the top surface of the bottom plate 1, and the second pull tabs 505 are fixed to the bottom plate 1 by self-tapping screws 503 to form a three-dimensional fixing system. Figure 3 and Figure 4 shown.
[0081] In this way, a customized junction box 5 is designed and manufactured, and fixed to the inner structure of the base plate 1. During the wiring operation and equipment tightening during the water and electricity installation construction phase, quality defects such as displacement or inward collapse of the junction box 501 can be avoided.
[0082] The L-shaped pull tab 502 may be an elastic pull tab.
[0083] S4: Install the side wall glass magnesium board 3 and the top board 2;
[0084] Step S4 specifically includes: vertically installing the side wall glass magnesium board 3 between the bottom plate 1 and the top plate 2, so that the upper and lower sides of the side wall glass magnesium board 3 are respectively installed in the prefabricated card grooves at the ends of the top plate 2 and the bottom plate 1, and positioning the side wall glass magnesium board 3.
[0085] S5: Open holes on the side wall glass magnesium plate 3 on both sides of the secondary rib beam casting space 4;
[0086] Step S5 specifically includes: according to the electrical professional design drawings, using a hole opener to open holes on the side wall glass magnesium board 3, and the holes on the side wall glass magnesium board 3 on both sides of the secondary rib beam casting space 4 are opened symmetrically.
[0087] S6: Making a side wall glass magnesium plate positioning device 6;
[0088] Step S6 specifically includes:
[0089] S601: Prepare the components of the side wall glass magnesium plate positioning device 6, including the wire tube 601, the water stop gasket 602 and the connecting sleeve 603;
[0090] S602: Slide the water-stop gasket 602 onto the wire pipe 601 and securely connect it to the wire pipe 601. Figure 6shown.
[0091] In step S602 , the wire tube 601 and the water-stopping gasket 602 are made of metal, and the water-stopping gasket 602 is welded to the wire tube 601 .
[0092] S7: Install the side wall glass magnesium plate positioning device 6;
[0093] Step S7 specifically includes: passing one end of the two wire tubes 601 through the holes on the side wall glass magnesium board 3 on both sides of the secondary rib beam casting space 4, inserting the end of the wire tube 601 into the secondary rib beam casting space 4 from the inner side of the side wall glass magnesium board 3, placing the connecting sleeve 603 in the secondary rib beam casting space 4, inserting the ends of the two wire tubes 601 into the two ends of the connecting sleeve 603, and making the water stop gasket 602 contact with the side wall glass magnesium board 3. At this time, the water stop gasket 602 is in contact with the inner side of the side wall glass magnesium board 3; then fixing the two wire tubes 601 to the connecting sleeve 603, as shown in FIG. Figure 5 shown.
[0094] The inner side of the side wall glass magnesium board 3 refers to the side thereof facing the bottom plate 1 , and the outer side of the side wall glass magnesium board 3 refers to the side thereof facing the secondary rib beam casting space 4 .
[0095] In step S6, when manufacturing the side wall glass magnesium board positioning device 6, threaded holes 604 are pre-opened on the ends of the two wire tubes 601 and the connecting sleeve 603. In step S7, when installing the side wall glass magnesium board positioning device 6, the threaded holes 604 on the two are aligned, and then the tightening screws are screwed into the corresponding threaded holes 604 to fix the wire tube 601 and the connecting sleeve 603.
[0096] In this way, the connection point between the wire tube 601 and the connecting sleeve 603 is set in the middle of the secondary rib beam casting space 4. The wire tubes 601 on both sides cooperate with the water-stop gasket 602 to form a symmetrical pulling force on the side wall glass magnesium board 3, positioning the side wall glass magnesium board 3, and ensuring the accuracy of the secondary rib beam cross-sectional dimensions and the tightness of the sealing.
[0097] The side wall glass magnesium board 3 is made of high-precision board, which is seamlessly embedded with the bottom plate 1 and the top plate 2, so that the side wall glass magnesium boards 3 on both sides are of the same height, and the height of all the top plates 2 is consistent. In addition, the side wall glass magnesium boards 3 on both sides are symmetrically opened with a hole opener, which can ensure that the side wall glass magnesium boards 3 on both sides are still of the same height after the side wall glass magnesium board positioning device 6 is installed, and the height of all the top plates 2 is consistent, which is conducive to the subsequent pouring of secondary rib concrete. The top surface of all the top plates 2 is flush with the top surface of the secondary rib beam to form a complete horizontal surface.
[0098] S8: Check and recheck the side wall glass magnesium board 3 and the side wall glass magnesium board positioning device 6.
[0099] S9: Thread the wires into the line pipe 601 according to the electrical design drawings to complete the installation of the water and electricity pipelines.
[0100] Figure 6 Where D is the sum of the thickness of the side wall glass magnesium plate 3 and 1 / 2 of the secondary rib width.
[0101] The present invention constructs a three-dimensional fixing system by using L-shaped pull tabs 502 and self-tapping screws 503, thereby solving the problems of weak pre-embedded fixation and positioning deviation of the water and electricity terminal box 501 and improving the installation quality of the box 501.
[0102] The present invention adopts a high-precision seamless plate interlocking process, symmetrically opens holes on the side wall glass magnesium plates 3 on both sides of the secondary rib beam casting space 4, and cooperates with the side wall glass magnesium plate positioning device 6 to achieve bidirectional stress balance, thereby enhancing the overall sealing and structural integrity of the side wall glass magnesium plates 3, ensuring that the side wall glass magnesium plates 3 fit well with the top plate 2 and the bottom plate 1 and the joints are tight, solving the problems of loose joints between the side wall glass magnesium plates 3 and the top plate 2 and the bottom plate 1 and cracking of the side wall glass magnesium plates 3 during late groove opening, avoiding cracking of the side wall glass magnesium plates 3 due to pipeline groove opening in the late stage, ensuring the accuracy of the cross-sectional dimensions of the secondary rib beams around the cavity plate, ensuring that the cross-sectional dimensions of the secondary rib beams meet the design requirements, and at the same time ensuring the flatness of the top plate 2 and the secondary rib beams; and enhancing the sealing tightness with the water-stop gasket 602 to avoid the risk of leakage.
[0103] This invention optimizes the construction process, innovatively integrating pipeline pre-laying with a high-precision seamless plate-joining process to complete pipeline laying ahead of time and ensure plate fit. The unique symmetrical hole structure, supplemented by a sidewall magnesium glass plate positioning device (6) and a bidirectional stress balance system, is complemented by modular customized equipment and process reengineering technology. This technical system achieves millimeter-level positioning accuracy, effectively reducing common quality defects, effectively avoiding the risk of structural cracking, and eliminating potential leakage. It also provides precise controllable cross-sectional dimensions, reduces rework, improves efficiency, and shortens the construction period.
[0104] The foregoing description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Those skilled in the art will readily appreciate that various modifications and variations of the present invention are possible. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of the present invention are intended to be within the scope of protection of the present invention.
Claims
1. A method for installing pipelines in a bidirectional dense-rib cavity floor, characterized by: The following steps are involved: S1: Install the cavity plate bottom plate; S2: Make custom wire boxes; Step S2 specifically includes: S201: Prepare the wire box; S202: Fixing support members at both ends of the wiring box, and extending one end of the support member toward the outside of the wiring box to obtain a customized wiring box; S3: Install and secure the custom junction box; A hole is opened on the bottom plate, and the customized wire box is placed in the hole. After the customized wire box is placed in the hole, the support members on both sides of the wire box are attached to the top surface of the bottom plate, and then the second pull tab is fixed to the bottom plate to form a three-dimensional fixing system; S4: Install the side wall glass magnesium board and the top board, and install the side wall glass magnesium board vertically between the bottom board and the top board; S5: Holes are opened symmetrically on the glass magnesium plates on the side walls of the secondary rib beam casting space; S6: Making a side wall glass magnesium board positioning device; wherein the side wall glass magnesium board positioning device includes a wire tube, a water stop gasket and a connecting sleeve, and the water stop gasket is sleeved on the wire tube and fixedly connected to the wire tube; S7: Install the side wall glass magnesium board positioning device; Pass one end of the two wire tubes through the holes on the side wall glass magnesium board on both sides of the secondary rib beam casting space, insert the end of the wire tube into the secondary rib beam casting space from the inner side of the side wall glass magnesium board, place the connecting sleeve in the secondary rib beam casting space, insert the ends of the two wire tubes into the two ends of the connecting sleeve respectively, and make the water stop gasket contact with the side wall glass magnesium board. At this time, the water stop gasket is in contact with the inner side of the side wall glass magnesium board; then fix the two wire tubes to the connecting sleeve.
2. The method for installing pipelines in a bidirectional dense-ribbed cavity floor according to claim 1, characterized in that: In step S202, the support member adopts an L-shaped pull tab; Step S202 specifically includes: fixing an L-shaped pull tab at each end of the wiring box, the L-shaped pull tab includes a first pull tab and a second pull tab that are perpendicular to each other, and affixing one side of the first pull tab to the side of the wiring box and fixedly connecting it to the wiring box. At the same time, the second pull tab is extended to the outside of the wiring box, and the second pull tab is arranged horizontally to obtain a customized wiring box.
3. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 1, characterized in that: Step S1 specifically includes: S101: Setting up a formwork support frame and laying a formwork on the formwork support frame. Position reference lines are drawn on the formwork, and the position reference lines divide the installation areas of each base plate. S102: Hoist the base plate onto the formwork; S103: Review the template elevation and flatness; S104: Before the baseboard is officially laid, the baseboard fixing parts are affixed in the installation area of the baseboard; S105: Arrange the base plates according to the position reference lines on the template in accordance with the design layout drawing, place each base plate within the installation area divided by the position reference lines, and ensure that the outer edge of the bottom of the base plate is consistent with the edge of the corresponding position reference line.
4. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 3, characterized in that: The formwork support frame includes multiple vertical poles. In step S102, when multiple base plates are hoisted at one time, the multiple base plates are first placed on the formwork in an overlapping manner. At this time, the four corner points of the base plates are placed exactly at the center positions corresponding to the four vertical poles to achieve balanced transfer of the upper load; Before hoisting multiple base plates at a time, mark the pole points on the template to facilitate accurate hoisting.
5. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 3, characterized in that: In step S104, bottom plate fixing members are attached to the four sides of the bottom surface of the bottom plate on the template at positions corresponding to the template to form a plurality of rectangular frames.
6. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 1, characterized in that: Step S4 specifically includes: vertically installing the side wall glass magnesium board between the bottom plate and the top plate, so that the upper and lower sides of the side wall glass magnesium board are respectively installed in the prefabricated card grooves at the ends of the top plate and the bottom plate, and positioning the side wall glass magnesium board.
7. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 1, characterized in that: Step S5 specifically includes: using a hole opener to open holes in the side wall glass magnesium board according to the electrical professional design drawings.
8. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 1, characterized in that: Step S6: When manufacturing the side wall glass magnesium board positioning device, threaded holes are pre-opened on the ends of the two wire tubes and the connecting sleeve, and the wire tubes are fixedly connected to the connecting sleeve by screwing fasteners into the corresponding threaded holes.
9. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 1, characterized in that: Also includes: S8: Check and compound the side wall glass magnesium board and the side wall glass magnesium board positioning device.
10. The method for installing pipelines in a bidirectional multi-ribbed cavity floor according to claim 9, characterized in that: Also includes: S9: Thread the wires into the conduit according to the electrical design drawings to complete the installation of water and electricity pipelines.