Buffer-type rapid response device for blowout preventer control systems and its usage method

By designing a buffer-based rapid response device, the problems of prolonged response time and hydraulic shock in the blowout preventer control system during deep and ultra-deep well exploration have been solved, achieving rapid response of the blowout preventer and stable operation of the equipment, reducing wear and malfunctions.

CN120684129BActive Publication Date: 2026-11-17RONGSHENG MASCH MFG LTD OF HUABEI OILFIELD HEBEI
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510633042.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-05-16
Publication Date
2026-11-17
Estimated Expiration
2045-05-16

AI Technical Summary

Technical Problem

Existing blowout preventer control systems have prolonged response times in deep and ultra-deep well exploration, and the hydraulic fluid exerts a strong impact on the downstream components of the rotary valve, leading to wear and failure, making it difficult to meet wellhead safety control requirements.

Method used

A buffered fast response device is adopted, including a blowout preventer control valve, a pilot rotary valve, a pilot drive, and a buffer control valve. The pilot drive controls the switching of the pilot rotary valve, and the buffer control valve precisely controls the hydraulic fluid flow and adjusts the switching time of the blowout preventer control valve to reduce the impact of hydraulic fluid on the blowout preventer and downstream components.

Benefits of technology

This enables rapid response of the blowout preventer, reduces the impact of hydraulic fluid on the blowout preventer and downstream components, reduces wear and failure, and improves system stability and equipment lifespan.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120684129B_ABST
    Figure CN120684129B_ABST
Patent Text Reader

Abstract

This invention discloses a buffer rapid response device and its usage method for a blowout preventer (BOP) control system, relating to the field of well control technology in oil and gas drilling. It includes: a BOP control valve, a pilot rotary valve, a pilot drive, and a buffer control valve. The BOP control valve has a first inlet, a first control port, a second control port, a first outlet, and a second outlet. The pilot rotary valve has a second inlet, a third outlet, and a fourth outlet. The buffer control valve includes a buffer valve block, a first buffer valve, and a second buffer valve. The first and second buffer valves are mounted on the buffer valve block. The first buffer valve controls the flow rate of pilot hydraulic fluid entering the first control port, and the second buffer valve controls the flow rate of pilot hydraulic fluid entering the second control port. The device has a simple structure, is easy to use, effectively ensures the BOP response time, and effectively guarantees the normal operation and service life of the equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of well control technology for oil and gas drilling, and in particular to a buffer rapid response device and its usage method for a blowout preventer control system. Background Technology

[0002] In oil exploration operations, the blowout preventer (BOP) control system is crucial for the safe and effective control of the wellhead BOP, ensuring the smooth progress of oil extraction and the safety of personnel and equipment. Currently, most BOP control systems rely on operating a three-position four-way rotary valve to open and close the wellhead BOP.

[0003] As oil exploration expands into deep and ultra-deep wells, the diameter and pressure rating of wellhead blowout preventers (BOPs) are continuously increasing, significantly increasing the fluid volume required to switch them on and off. Under these circumstances, rapid response time becomes even more critical for wellhead safety.

[0004] The existing method of controlling the blowout preventer (BOP) switching using a rotary valve has revealed several drawbacks. Firstly, to meet the demand for large fluid volumes, the size and diameter of the rotary valve are constantly increasing. This increased size drastically increases the difficulty of operating the rotary valve handle, making it difficult to fully engage and thus prolonging the BOP response time. Secondly, the increased diameter causes a strong "water hammer effect" from the hydraulic fluid on downstream components of the rotary valve during opening and closing. This impact can cause premature wear and even malfunction of downstream components and the BOP, severely affecting the normal operation and service life of the equipment.

[0005] In summary, traditional blowout preventer (BOP) control methods are no longer sufficient to meet the current requirements for wellhead safety control in oil exploration. The existence of these problems urgently necessitates the research and development of new BOP control methods to address them. Summary of the Invention

[0006] The purpose of this invention is to provide a buffered rapid response device and its usage method for a blowout preventer control system, so as to solve the problems existing in the prior art. It has a simple structure, is easy to use, effectively ensures the response time of the blowout preventer, and effectively ensures the normal operation and service life of the equipment.

[0007] To achieve the above objectives, the present invention provides the following solution:

[0008] This invention provides a buffered rapid response device for a blowout preventer (BOP) control system, comprising: a BOP control valve, a pilot rotary valve, a pilot actuator, and a buffer control valve. The BOP control valve has a first inlet, a first control port, a second control port, a first outlet, and a second outlet. The first inlet is connected to a hydraulic source, the first outlet is connected to the open chamber of the BOP, and the second outlet is connected to the closed chamber of the BOP. The pilot rotary valve has a second inlet, a third outlet, and a fourth outlet. The second inlet is connected to the pilot hydraulic source, the third outlet is connected to the first control port to allow pilot hydraulic fluid to be introduced into the first control port, thereby switching the BOP control valve to a state where the first inlet and the first outlet are connected, and the fourth outlet is connected to the second control port to allow... The pilot hydraulic fluid is introduced into the second control port, thereby switching the blowout preventer control valve to connect the first inlet and the second outlet. The pilot drive is connected to the pilot rotary valve to drive the pilot rotary valve to switch to connect the second inlet and the third outlet, or to connect the second inlet and the fourth outlet. The buffer control valve includes a buffer valve block, a first buffer valve, and a second buffer valve. The first buffer valve and the second buffer valve are installed on the buffer valve block. The first buffer valve is located on the pipe connecting the third outlet and the first control port to control the flow rate of the pilot hydraulic fluid entering the first control port. The second buffer valve is located on the pipe connecting the fourth outlet and the second control port to control the flow rate of the pilot hydraulic fluid entering the second control port.

[0009] Preferably, it further includes a remote control panel, a first flow monitoring valve, and a second flow monitoring valve. The first flow monitoring valve is disposed on a pipe that connects the first outlet to the open chamber of the blowout preventer, and the second flow monitoring valve is disposed on a pipe that connects the second outlet to the closed chamber of the blowout preventer. The remote control panel is connected to the first flow monitoring valve, the second flow monitoring valve, the buffer control valve, and the pilot drive electrical signal.

[0010] Preferably, it further includes a first pressure reducing valve, which is disposed on the pipeline connecting the first inlet and the hydraulic source and is capable of adjusting the pressure value of the hydraulic fluid passing through the first pressure reducing valve to a first preset pressure value.

[0011] Preferably, it also includes a second pressure reducing valve, which is disposed on the pipeline connecting the second inlet and the pilot hydraulic source and can adjust the pressure value of the hydraulic fluid passing through the second pressure reducing valve to a second preset pressure value.

[0012] Preferably, it further includes a gas source processing component, a three-position five-way reversing valve, a gas source pressure gauge, and a gas source pressure sensor. The gas source pressure gauge and the gas source pressure sensor are disposed on the gas source processing component and the pipeline connecting the gas source. The three-position five-way reversing valve is disposed on the pipeline connecting the gas source processing component and the first pressure reducing valve. The three-position five-way reversing valve is electrically connected to the remote control panel.

[0013] Preferably, the air source treatment component includes a filter, a pressure regulator, a pressure gauge, and a lubrication device. The air outlet of the filter is connected to the pressure regulator. The end of the pressure regulator away from the filter is connected to the pressure gauge. The end of the pressure gauge away from the pressure regulator is connected to the lubrication device. The end of the lubrication device away from the pressure gauge is connected to the three-position five-way reversing valve.

[0014] Preferably, it further includes a pilot pressure gauge and a pilot pressure sensor, wherein the pilot pressure gauge and the pilot pressure sensor are disposed on the pipeline between the second pressure reducing valve and the pilot hydraulic source, and the pilot pressure sensor is electrically connected to the remote control panel.

[0015] Preferably, it also includes a blowout preventer switch pressure gauge and a blowout preventer switch pressure sensor, wherein the blowout preventer switch pressure gauge and the blowout preventer switch pressure sensor are disposed on the pipeline between the first pressure reducing valve and the blowout preventer control valve, and the blowout preventer switch pressure sensor is electrically connected to the remote control panel.

[0016] Preferably, it also includes an unloading valve and a storage tank, wherein the unloading valve is disposed on the pipeline connecting the drain port of the pilot rotary valve and the storage tank.

[0017] The present invention also provides a method of using the buffer fast response device for a blowout preventer control system as described above, comprising the following steps:

[0018] When the blowout preventer (BOP) opens, the pilot drive switches the pilot rotary valve, connecting the second inlet to the third outlet. Hydraulic fluid from the pilot hydraulic source flows through the third outlet to the first control port of the BOP control valve. Upon receiving the pilot hydraulic fluid, the first control port switches the BOP control valve, connecting the first inlet to the first outlet. Hydraulic fluid flows from the hydraulic source through the first inlet and outlet to the BOP's opening chamber, pushing the BOP open. If the BOP control valve starts too quickly, causing a significant water hammer effect in the control manifold and BOP assembly, the first buffer valve reduces the corresponding pilot hydraulic fluid flow, extending the switching time of the BOP control valve and reducing the water hammer effect. Conversely, if the BOP control valve starts too slowly, the first buffer valve increases the pilot hydraulic fluid flow, pushing the BOP control valve to switch quickly.

[0019] During the blowout preventer (BOP) closing operation, the pilot drive switches the pilot rotary valve, connecting the second inlet to the fourth outlet. Pilot hydraulic fluid flows through the fourth outlet to the second control port of the BOP control valve. Upon receiving the pilot hydraulic fluid, the second control port switches the BOP control valve, connecting the first inlet to the second outlet. Hydraulic fluid flows from the hydraulic source through the first inlet and second outlet to the BOP's closing chamber, pushing the BOP to close. If the BOP control valve starts too quickly, causing a significant water hammer effect in the control manifold and BOP assembly, the second buffer valve reduces the corresponding pilot hydraulic fluid flow, extending the switching time of the BOP control valve and reducing the water hammer effect. Conversely, if the BOP control valve starts too slowly, the second buffer valve increases the pilot hydraulic fluid flow, pushing the BOP control valve to switch quickly.

[0020] The present invention achieves the following technical effects compared to the prior art:

[0021] The purpose of this invention is to provide a buffered rapid response device and its method of use for a blowout preventer (BOP) control system. By controlling the switching of the pilot rotary valve through a pilot drive, different connection states of the BOP control valve can be accurately controlled, realizing the opening and closing actions of the BOP. Simultaneously, the buffered control valve precisely controls the flow rate of the pilot hydraulic fluid entering the control port of the BOP control valve, effectively adjusting the switching time of the BOP control valve, reducing the impact of hydraulic fluid on the BOP and downstream components, reducing wear and malfunctions, and improving system stability. Attached Figure Description

[0022] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0023] Figure 1 This is a schematic diagram of the structure of the buffer fast response device for the blowout preventer control system provided by the present invention.

[0024] Figure 2 This is a schematic diagram of the buffer fast response device for a blowout preventer control system provided by the present invention.

[0025] Figure 3 A schematic diagram of the buffer control valve structure in the buffer rapid response device for the blowout preventer control system provided by the present invention.

[0026] Figure 4 A schematic diagram of the blowout preventer control valve structure in the buffer fast response device for the blowout preventer control system provided by the present invention.

[0027] Figure 5 This is a schematic diagram of the flow monitoring valve structure in the buffer fast response device for the blowout preventer control system provided by the present invention.

[0028] In the diagram: 1. Pilot rotary valve; 2. Buffer control valve; 21. First buffer valve; 22. Second buffer valve; 23. Buffer valve block; 3. Blowout preventer control valve; 31. First inlet; 32. First control port; 33. Second control port; 4. Blowout preventer opens hydraulic fluid output pipeline; 5. Blowout preventer closes hydraulic fluid output pipeline; 6. First flow monitoring valve; 7. First pressure reducing valve; 8. Air source treatment assembly; 9. Pilot pressure gauge; 10. Three-position five-way directional valve; 11. Air source pressure gauge; 12. Blowout preventer switch pressure gauge; 13. Second pressure reducing valve; 14. Unloading valve; 15. Pilot drive; 16. Blowout preventer switch pressure sensor; 17. Air source pressure sensor; 18. Pilot pressure sensor; 19. Remote control panel. Detailed Implementation

[0029] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0030] The purpose of this invention is to provide a buffered rapid response device and its usage method for a blowout preventer control system, so as to solve the problems existing in the prior art. It has a simple structure, is easy to use, effectively ensures the response time of the blowout preventer, and effectively ensures the normal operation and service life of the equipment.

[0031] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0032] Example 1

[0033] This invention provides a buffered fast response device for a blowout preventer control system, such as... Figures 1-5As shown, the system includes: a blowout preventer control valve 3, a pilot rotary valve 1, a pilot actuator 15, and a buffer control valve 2. The blowout preventer control valve 3 has a first inlet 31, a first control port 32, a second control port 33, a first outlet, and a second outlet. The first inlet 31 is connected to a hydraulic power source. The first outlet is connected to the blowout preventer's open hydraulic fluid output pipe 4 via the blowout preventer and to the blowout preventer's open chamber. The second outlet is connected to the blowout preventer's close hydraulic fluid output pipe 5 via the blowout preventer's close chamber. The pilot rotary valve 1 has a second inlet, a third outlet, and a fourth outlet. The second inlet is connected to a pilot hydraulic power source. The third outlet is connected to the first control port 32 to allow pilot hydraulic fluid to be introduced into the first control port 32, thereby switching the blowout preventer control valve 3 to a state where the first inlet 31 is connected to the first outlet. The fourth outlet is connected to the second control port 33 to allow pilot hydraulic fluid to be introduced into the second control port 33, thereby switching the blowout preventer control valve 3 to a state where the blowout preventer is connected to the first inlet 31 and the first outlet. The control valve 3 switches to a state where the first inlet 31 is connected to the second outlet; the pilot drive 15 is connected to the pilot rotary valve 1 to drive the pilot rotary valve 1 to switch to a state where the second inlet is connected to the third outlet, or to a state where the second inlet is connected to the fourth outlet; the buffer control valve 2 includes a buffer valve block 23, a first buffer valve 21, and a second buffer valve 22. The first buffer valve 21 and the second buffer valve 22 are mounted on the buffer valve block 23. The first buffer valve 21 is located on the pipe connecting the third outlet and the first control port 32 to control the flow rate of the pilot hydraulic fluid entering the first control port 32. The second buffer valve 22 is located on the pipe connecting the fourth outlet and the second control port 33 to control the flow rate of the pilot hydraulic fluid entering the second control port 33. By controlling the switching of the pilot rotary valve 1 through the pilot drive 15, the different connection states of the blowout preventer control valve 3 can be accurately controlled to realize the opening and closing actions of the blowout preventer. Meanwhile, the buffer control valve 2 precisely controls the flow rate of the pilot hydraulic fluid entering the control port of the blowout preventer control valve 3, which can effectively adjust the switching time of the blowout preventer control valve 3, reduce the impact of hydraulic fluid on the blowout preventer and downstream components, reduce wear and failure, and improve system stability.

[0034] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes a remote control panel 19, a first flow monitoring valve 6, and a second flow monitoring valve. The first flow monitoring valve 6 is installed on a pipe connecting the first outlet to the open chamber of the blowout preventer, and the second flow monitoring valve is installed on a pipe connecting the second outlet to the closed chamber of the blowout preventer. The remote control panel 19 is electrically connected to the first flow monitoring valve 6, the second flow monitoring valve, the buffer control valve 2, and the pilot drive 15. By installing the first flow monitoring valve 6 and the second flow monitoring valve, the flow rate of hydraulic fluid flowing to the open and closed chambers of the blowout preventer can be monitored in real time. The remote control panel 19 is electrically connected to these components, allowing the operator to remotely acquire flow data in real time and control the buffer control valve 2 and the pilot drive 15 based on the flow rate, achieving more precise and convenient operation control and further improving the system's response speed and stability.

[0035] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes a first pressure reducing valve 7. The first pressure reducing valve 7 is disposed on the pipeline connecting the first inlet 31 to the hydraulic source and can regulate the pressure value of the hydraulic fluid passing through the first pressure reducing valve 7 to a first preset pressure value. The first pressure reducing valve 7 can regulate the high-pressure hydraulic fluid from the hydraulic source to a first preset pressure value suitable for blowout preventer control, providing stable and appropriate pressure functional hydraulic fluid for the normal opening and closing of the blowout preventer, ensuring that the blowout preventer can work reliably under different operating conditions, and avoiding damage to the blowout preventer and related components due to excessive or unstable pressure.

[0036] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes a second pressure reducing valve 13. The second pressure reducing valve 13 is disposed on the pipeline connecting the second inlet to the pilot hydraulic source and can regulate the pressure of the hydraulic fluid passing through the second pressure reducing valve 13 to a second preset pressure value. The second pressure reducing valve 13 can regulate the pressure of the pilot hydraulic source to the second preset pressure value and output stable pilot hydraulic fluid, providing suitable pilot power for the control of the pilot rotary valve 1 and the blowout preventer control valve 3, ensuring the accuracy and stability of the pilot control link, and improving the reliability of the entire control system.

[0037] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes an air source processing component 8, a three-position five-way directional valve 10, an air source pressure gauge 11, and an air source pressure sensor 17. The air source pressure gauge 11 and the air source pressure sensor 17 are installed on the pipeline connecting the air source processing component 8 and the air source. The three-position five-way directional valve 10 is installed on the pipeline connecting the air source processing component 8 and the first pressure reducing valve 7. The three-position five-way directional valve 10 is electrically connected to the remote control panel 19. The air source processing component 8 processes the air source entering the system to ensure the quality of the air source and provide stable and reliable power support for the system. After the three-position five-way directional valve 10 is electrically connected to the remote control panel 19, the first pressure reducing valve 7 can be operated locally through the three-position five-way directional valve 10, or its working state can be controlled through the remote control panel 19, realizing remote control functionality and enhancing the convenience and flexibility of system operation.

[0038] In a preferred embodiment, the gas source treatment component 8 includes a filter, a pressure regulator, a pressure gauge, and a lubrication device. The outlet of the filter is connected to the pressure regulator, the end of the pressure regulator furthest from the filter is connected to the pressure gauge, the end of the pressure gauge furthest from the pressure regulator is connected to the lubrication device, and the end of the lubrication device furthest from the pressure gauge is connected to a three-position five-way directional valve 10. The filter removes impurities from the gas source, preventing them from entering the system and damaging components. The pressure regulator adjusts the gas source pressure to ensure the system uses a gas source with a suitable pressure. The pressure gauge displays the gas source pressure in real time, allowing operators to easily understand the gas source status. The lubrication device lubricates the gas, reducing friction and wear between components. This connection method ensures that the gas source, after multiple processing steps, meets the requirements for stable system operation, improving the system's service life and reliability.

[0039] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes a pilot pressure gauge 9 and a pilot pressure sensor 18. The pilot pressure gauge 9 and pilot pressure sensor 18 are installed on the pipeline between the second pressure reducing valve 13 and the pilot hydraulic source. The pilot pressure sensor 18 is electrically connected to the remote control panel 19. The pilot pressure gauge 9 can visually display the pressure value of the pilot hydraulic source after passing through the second pressure reducing valve 13, allowing the operator to directly observe the pilot hydraulic pressure. The pilot pressure sensor 18, electrically connected to the remote control panel 19, can transmit pilot pressure data to the remote control panel 19 in real time. The operator can promptly obtain pressure information and make adjustments according to the actual situation, ensuring stable and normal pilot hydraulic system pressure, thereby guaranteeing the accuracy and reliability of the entire control system.

[0040] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes a blowout preventer switch pressure gauge 12 and a blowout preventer switch pressure sensor 16. The pressure gauge 12 and pressure sensor 16 are installed on the pipeline between the first pressure reducing valve 7 and the blowout preventer control valve 3. The pressure sensor 16 is electrically connected to the remote control panel 19. The pressure gauge 12 displays the hydraulic pressure before entering the blowout preventer control valve 3 in real time, allowing operators to easily monitor the pressure status before the valve. The pressure sensor 16 transmits pressure data to the remote control panel 19 in real time, enabling operators to make corresponding adjustments based on the pressure conditions, ensuring that the blowout preventer opens and closes under appropriate pressure conditions, thus improving the accuracy and safety of blowout preventer control.

[0041] In a preferred embodiment, the buffer rapid response device for the blowout preventer control system further includes an unloading valve 14 and a liquid storage tank. The unloading valve 14 is disposed on the pipe connecting the drain port of the pilot rotary valve 1 and the liquid storage tank. The unloading valve 14 can discharge the pilot pressure in the pilot rotary valve 1. When the system stops working or performs certain operations, the pressure in the pilot rotary valve 1 and related components is released to protect the system components and avoid pressure residue from damaging the components. At the same time, the liquid storage tank can collect the discharged liquid to realize energy recovery and rational utilization, and improve the safety and overall performance of the system.

[0042] In a preferred embodiment, the hydraulic power source and the pilot hydraulic power source are the same high-pressure hydraulic source. Using a single high-pressure hydraulic source reduces the number of hydraulic sources and the corresponding piping layout in the system, making the entire device more compact and saving space and cost. Simultaneously, it reduces the number of switching points between hydraulic sources and potential leakage points, improving the system's reliability and stability. Furthermore, maintenance is more convenient, as only a single high-pressure hydraulic source needs maintenance, reducing the complexity and workload of maintenance work and improving equipment efficiency.

[0043] In a preferred embodiment, the pilot drive 15 can be pneumatically controlled, hydraulically controlled, or electrically controlled.

[0044] The present invention also provides a method of using a buffer fast response device for a blowout preventer control system as described in Embodiment 1, comprising the following steps:

[0045] 1. Device Startup and Initialization

[0046] Start all relevant equipment, including hydraulic power sources, air source processing components, etc.

[0047] The system can be started via remote control panel 19 (if remote start function is available) or local operation (components involving local operation such as gas source processing component 8, three-position five-way reversing valve 10, etc.).

[0048] The air source treatment component 8 begins operation. The filter filters the compressed air entering the system, removing impurities. The pressure regulator adjusts the air pressure to a suitable value, and the pressure gauge displays the real-time pressure. The lubrication device adds lubricating oil mist to the compressed air. The treated air source provides stable and reliable power support to the system through the three-position five-way directional valve 10. Simultaneously, the first pressure reducing valve 7 and the second pressure reducing valve 13 regulate the pressure of the hydraulic source and the pilot hydraulic source to the first and second preset pressure values, respectively. Various pressure gauges in the system, such as the pilot pressure gauge 9, the air source pressure gauge 11, and the blowout preventer switch pressure gauge 12, begin to display the corresponding pressure values ​​in real time for operator reference.

[0049] 2. Blowout preventer opening operation

[0050] Based on actual needs, the operator issues a blowout preventer opening command via the remote control panel 19, and the signal is transmitted to the pilot drive 15.

[0051] When the pilot drive 15 is activated, it drives the pilot rotary valve 1 to switch states, so that the second inlet and the third outlet are connected. The hydraulic fluid of the pilot hydraulic source is reduced by the second pressure reducing valve 13 and becomes a stable pilot hydraulic fluid, which flows through the third outlet to the first control port 32 of the blowout preventer control valve 3.

[0052] After the first control port 32 receives the pilot hydraulic fluid, the blowout preventer control valve 3 switches its state, connecting the first inlet port 31 to the first outlet port. At this time, the functional hydraulic fluid, adjusted to the first preset pressure value by the first pressure reducing valve 7, flows from the hydraulic source through the first inlet port 31 and the first outlet port to the opening chamber of the blowout preventer, pushing the blowout preventer to open.

[0053] During this process, the first flow monitoring valve 6 monitors the flow rate of the functional hydraulic fluid flowing into the blowout preventer opening chamber in real time and transmits the flow data to the remote control panel 19, which the operator can view. If the flow rate is abnormal (too fast or too slow), the pilot hydraulic fluid flow rate entering the first control port 32 can be adjusted by controlling the buffer control valve 2 through the remote control panel 19 based on this data, thereby achieving precise control.

[0054] 3. Blowout preventer shutdown operation

[0055] The operator issues a blowout preventer shutdown command via remote control panel 19, and the signal is transmitted to pilot drive 15.

[0056] The pilot drive 15 switches the pilot rotary valve 1 to connect the second inlet and the fourth outlet, and the pilot hydraulic fluid flows through the fourth outlet to the second control port 33 of the blowout preventer control valve 3.

[0057] After the second control port 33 receives the pilot hydraulic fluid, the blowout preventer control valve 3 switches its state, connecting the first inlet port 31 to the second outlet port. The functional hydraulic fluid, regulated by the first pressure reducing valve 7, flows from the hydraulic source through the first inlet port 31 and the second outlet port to the blowout preventer's closing chamber, pushing the blowout preventer to close.

[0058] The second flow monitoring valve monitors the flow rate of functional hydraulic fluid flowing into the blowout preventer's closing chamber in real time and transmits the data to the remote control panel 19. The operator can then control the buffer control valve 2 via the remote control panel 19 to adjust the pilot hydraulic fluid flow rate into the second control port 33, ensuring the blowout preventer closes smoothly and quickly.

[0059] 4. Monitoring and adjustment during equipment operation

[0060] During the operation of the device, the operator constantly observes the data of each pressure gauge, namely the pilot hydraulic pressure displayed by the pilot pressure gauge 9, the air source pressure displayed by the air source pressure gauge 11, and the hydraulic pressure before entering the blowout preventer control valve 3 displayed by the blowout preventer switch pressure gauge 12, to ensure that each pressure is within the normal operating range.

[0061] At the same time, the flow data transmitted from the first flow monitoring valve 6 and the second flow monitoring valve can be obtained in real time through the remote control panel 19 to monitor the flow of hydraulic fluid to the opening and closing chambers of the blowout preventer.

[0062] If the BOP control valve 3 starts too quickly, causing a large "water hammer effect" in the control manifold and BOP assembly (which can be judged by flow monitoring data or by observing the system operation status), the flow monitoring valve will send a signal to the remote control panel 19. The remote control panel 19 will automatically control the buffer control valve 2 to reduce the corresponding pilot hydraulic fluid flow, prolong the switching time of the BOP control valve 3, and reduce the "water hammer effect".

[0063] If the BOP control valve 3 starts too slowly, the remote control panel 19 will control the buffer control valve 2 to automatically increase the pilot hydraulic fluid flow, pushing the BOP control valve 3 to quickly switch direction to meet the actual working requirements.

[0064] 5. The device stops working.

[0065] After completing the relevant work, the pilot drive 15 is first controlled by the remote control panel 19 to put the pilot rotary valve 1 in the appropriate state and stop the input of pilot hydraulic fluid to the control port of the blowout preventer control valve 3.

[0066] Next, the unloading valve 14 is operated to release the pilot pressure in the pilot rotary valve 1 and the blowout preventer control valve 3, protecting system components and preventing damage from residual pressure. The discharged liquid flows into the storage tank, achieving energy recovery.

[0067] Shutting down the hydraulic power source, air source treatment component 8, and other related equipment will stop the entire system from working.

[0068] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.

Claims

1. A cushion quick response device for a blowout preventer control system, characterized by: include: The blowout preventer control valve (3) has a first inlet (31), a first control port (32), a second control port (33), a first outlet and a second outlet. The first inlet (31) is used to communicate with a hydraulic source, the first outlet is used to communicate with the open chamber of the blowout preventer, and the second outlet is used to communicate with the closed chamber of the blowout preventer. A pilot rotary valve (1) has a second inlet, a third outlet and a fourth outlet. The second inlet is connected to the pilot hydraulic power source. The third outlet is connected to the first control port (32) so that pilot hydraulic fluid can be introduced into the first control port (32) to switch the blowout preventer control valve (3) to the state where the first inlet (31) is connected to the first outlet. The fourth outlet is connected to the second control port (33) so that pilot hydraulic fluid can be introduced into the second control port (33) to switch the blowout preventer control valve (3) to the state where the first inlet (31) is connected to the second outlet. A pilot drive (15) is connected to the pilot rotary valve (1) to drive the pilot rotary valve (1) to switch its state to connect the second inlet to the third outlet, or to connect the second inlet to the fourth outlet; and A buffer control valve (2) is provided, comprising a buffer valve block (23), a first buffer valve (21), and a second buffer valve (22). The first buffer valve (21) and the second buffer valve (22) are mounted on the buffer valve block (23). The first buffer valve (21) is located on a pipe that connects the third outlet to the first control port (32) to control the flow rate of the pilot hydraulic fluid entering the first control port (32). The second buffer valve (22) is located on a pipe that connects the fourth outlet to the second control port (33) to control the flow rate of the pilot hydraulic fluid entering the second control port (33).

2. A snubbing quick response device for a blowout preventer control system as defined in claim 1, wherein: It also includes a remote control panel (19), a first flow monitoring valve (6) and a second flow monitoring valve. The first flow monitoring valve (6) is installed on the pipe that connects the first outlet to the open chamber of the blowout preventer. The second flow monitoring valve is installed on the pipe that connects the second outlet to the closed chamber of the blowout preventer. The remote control panel (19) is electrically connected to the first flow monitoring valve (6), the second flow monitoring valve, the buffer control valve (2) and the pilot drive (15).

3. The buffered rapid response device for a blowout preventer control system according to claim 2, characterized in that: It also includes a first pressure reducing valve (7), which is installed on the pipeline connecting the first inlet (31) and the hydraulic source and can adjust the pressure value of the hydraulic fluid passing through the first pressure reducing valve (7) to a first preset pressure value.

4. The buffered rapid response device for a blowout preventer control system according to claim 3, characterized in that: It also includes a second pressure reducing valve (13), which is installed on the pipeline that connects the second inlet to the pilot hydraulic source and can adjust the pressure value of the hydraulic fluid passing through the second pressure reducing valve (13) to a second preset pressure value.

5. The buffered rapid response device for a blowout preventer control system according to claim 4, characterized in that: It also includes a gas source processing component (8), a three-position five-way reversing valve (10), a gas source pressure gauge (11) and a gas source pressure sensor (17). The gas source pressure gauge (11) and the gas source pressure sensor (17) are installed on the gas source processing component (8) and the gas source connecting pipe. The three-position five-way reversing valve (10) is installed on the pipe connecting the gas source processing component (8) and the first pressure reducing valve (7). The three-position five-way reversing valve (10) is electrically connected to the remote control panel (19).

6. The buffered rapid response device for a blowout preventer control system according to claim 5, characterized in that: The gas source processing component (8) includes a filter, a pressure regulator, a pressure gauge, and a lubrication device. The outlet of the filter is connected to the pressure regulator. The end of the pressure regulator away from the filter is connected to the pressure gauge. The end of the pressure gauge away from the pressure regulator is connected to the lubrication device. The end of the lubrication device away from the pressure gauge is connected to the three-position five-way reversing valve (10).

7. The buffered rapid response device for a blowout preventer control system according to claim 6, characterized in that: It also includes a pilot pressure gauge (9) and a pilot pressure sensor (18), which are disposed on the pipeline between the second pressure reducing valve (13) and the pilot hydraulic source, and the pilot pressure sensor (18) is electrically connected to the remote control panel (19).

8. The buffered rapid response device for a blowout preventer control system according to claim 7, characterized in that: It also includes a blowout preventer switch pressure gauge (12) and a blowout preventer switch pressure sensor (16), which are installed on the pipeline between the first pressure reducing valve (7) and the blowout preventer control valve (3). The blowout preventer switch pressure sensor (16) is electrically connected to the remote control panel (19).

9. The buffered rapid response device for a blowout preventer control system according to claim 8, characterized in that: It also includes an unloading valve (14) and a liquid storage tank, wherein the unloading valve (14) is disposed on the pipe connecting the drain port of the pilot rotary valve (1) and the liquid storage tank.

10. A method of using a buffer fast response device for a blowout preventer control system as described in any one of claims 1 to 9, characterized in that: Includes the following steps: When the blowout preventer (BOP) is opened, the pilot drive (15) drives the pilot rotary valve (1) to switch states, connecting the second inlet and the third outlet. The hydraulic fluid from the pilot hydraulic source flows through the third outlet to the first control port (32) of the BOP control valve (3). After receiving the pilot hydraulic fluid, the first control port (32) switches states, connecting the first inlet (31) and the first outlet. The hydraulic fluid flows from the hydraulic source through the first inlet (31) and the first outlet to the BOP. The opening chamber of the device pushes the blowout preventer to open; if the start speed of the blowout preventer control valve (3) is too fast, resulting in a large "water hammer effect" in the control manifold and blowout preventer assembly, the first buffer valve (21) reduces the corresponding pilot hydraulic fluid flow, prolongs the switching time of the blowout preventer control valve (3), and reduces the "water hammer effect"; if the start speed of the blowout preventer control valve (3) is too slow, the first buffer valve (21) increases the pilot hydraulic fluid flow, pushing the blowout preventer control valve (3) to switch quickly; When the blowout preventer (BOP) is closed, the pilot drive (15) drives the pilot rotary valve (1) to switch states, connecting the second inlet to the fourth outlet. The pilot hydraulic fluid flows through the fourth outlet to the second control port (33) of the BOP control valve (3). After receiving the pilot hydraulic fluid, the second control port (33) switches states, connecting the first inlet (31) to the second outlet. The hydraulic fluid flows from the hydraulic source through the first inlet (31) and the second outlet to the BOP. The chamber is closed, pushing the blowout preventer to close; if the blowout preventer control valve (3) starts too quickly, causing a large "water hammer effect" in the control manifold and blowout preventer assembly, the second buffer valve (22) reduces the corresponding pilot hydraulic fluid flow, prolongs the switching time of the blowout preventer control valve (3), and reduces the "water hammer effect"; if the blowout preventer control valve (3) starts too slowly, the second buffer valve (22) increases the pilot hydraulic fluid flow, pushing the blowout preventer control valve (3) to switch quickly.