High-altitude partial load type steel corridor and construction technology thereof
Through the combined design of suspension supports, main load-bearing frames, secondary load-bearing frames, connecting cross bars and the pouring of concrete, the connection strength problem of the high-altitude load-bearing steel corridor during assembly was solved, achieving efficient and safe construction results and enhancing the overall strength and stability of the corridor.
Patent Information
- Application Number
- CN202511130415.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-13
- Publication Date
- 2025-10-10
AI Technical Summary
In the existing technology, the connection strength of high-altitude shared-load steel corridors cannot be guaranteed during assembly. It is necessary to improve the connection strength between the buildings on both sides to improve the overall strength of the corridor, and it is necessary to reinforce the strength between the assembled parts to improve safety and construction efficiency after installation.
A combination design of hanging supports, main load-bearing frames, auxiliary load-bearing frames, connecting cross bars, reinforcement mechanisms, support mechanisms and pouring mechanisms is adopted. The main load-bearing frames and auxiliary load-bearing frames are fixed and reinforced through sliding connections and pouring of concrete, and the support of the connecting cross bars is enhanced. The overall strength of the corridor is improved by utilizing the coordination of prefabricated casting blocks and pouring holes.
It has achieved efficient assembly of high-altitude load-sharing steel corridors, improved construction efficiency and safety, enhanced the connection strength of the corridors and the stability after installation, and reduced the risks of high-altitude operations and the cost of temporary support systems.
Smart Images

Figure CN120759333A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The application belongs to the technical field of building construction, and specifically relates to a high-altitude split load type steel corridor and a construction process thereof. BACKGROUND
[0002] With the development of modern buildings towards high-rise and complexity, steel corridors are widely used as a structure connecting two or more high-rise buildings. The steel corridor not only needs to meet the traffic function, but also needs to bear the complex mechanical requirements such as wind load and earthquake action. At present, large-span steel corridors mostly adopt integral hoisting or segmented assembly process, but the construction efficiency and safety become the industry pain points due to the limitation of lifting equipment capacity and site conditions. In recent years, although the fusion of BIM technology and modular construction improves the precision, it still cannot fundamentally solve the problems of high risk of high-altitude operation and high cost of temporary support system. Therefore, a split load type steel corridor is needed to improve the construction efficiency.
[0003] Publication No. CN222120496U discloses a split type building steel corridor structure, which comprises two corridor pre-installation parts fixedly connected with a building structure main body and a corridor main body fixedly installed between the two corridor pre-installation parts. The corridor pre-installation part is fixedly installed on the building structure main body through a connecting rod. A bracket is fixedly arranged on the building structure main body, and a sliding support is arranged on the bracket. The bottom of the corridor pre-installation part is arranged on the sliding support. The corridor main body comprises a truss lower chord and a truss upper chord fixedly connected through a plurality of vertical support rods. Inclined support rods are arranged on both sides of the two ends of the truss upper chord. An upper connecting end, a lower connecting end and an inclined support connecting end are arranged on the corridor pre-installation part. The high-altitude assembly is performed in a three-section splicing manner. The two sections of the end part are used as supports to lift the middle part, thereby reducing the construction cost, shortening the high-altitude operation time and improving the safety of the high-altitude operation personnel.
[0004] However, the device cannot guarantee the connection strength during assembly, and the strength of the connection between the two buildings needs to be improved to improve the strength of the whole corridor. In addition, the strength between the assembled parts needs to be reinforced to improve the strength of the corridor after installation. SUMMARY
[0005] To solve the problems in the background art, the application provides a high-altitude split load type steel corridor and a construction process thereof.
[0006] To achieve the above-mentioned object, the present invention provides the following technical solution: a high-altitude load-sharing steel corridor, comprising a suspension support, wherein the outside of the suspension support is movably connected to a main load-bearing frame, the outside of the suspension support is movably connected to a secondary load-bearing frame, the top of the secondary load-bearing frame is fixed with a corridor frame, the inside of the main load-bearing frame is movably connected to a connecting cross bar, a reinforcement mechanism is installed on the outside of the secondary load-bearing frame, one end of the reinforcement mechanism is provided with a support mechanism, and the top of the main load-bearing frame is provided with a casting mechanism; The reinforcement mechanism includes a first reinforcement frame, a first pouring trough, and a second reinforcement frame. The first reinforcement frame is movably connected to the outside of the auxiliary load-bearing frame, and a first pouring trough is provided on the top of the first reinforcement frame. The second reinforcement frame is movably connected to the inside of the auxiliary load-bearing frame, and a second pouring trough is provided on the top of the second reinforcement frame. The support mechanism includes an installation groove, a sliding groove and a prefabricated casting block. The installation groove is opened at the top of the second reinforcement frame. The second reinforcement frame is provided with a sliding groove inside. The prefabricated casting block is movably connected inside the sliding groove.
[0007] Preferably, a reinforcement slot is provided on the outside of the connecting cross bar, a third casting groove is provided on the top of the connecting cross bar, the outer wall of the first reinforcement frame fits the inner wall of the auxiliary load-bearing frame, the first reinforcement frame and the auxiliary load-bearing frame are slidingly connected, and the second reinforcement frame and the auxiliary load-bearing frame are slidingly connected.
[0008] Preferably, the outer wall of the first reinforcement frame fits the inner wall of the second reinforcement frame, the first reinforcement frame and the second reinforcement frame are slidably connected, two groups of reinforcement slots and third casting troughs are provided, and the reinforcement slots and third casting troughs are symmetrically distributed about the central axis of the connecting cross bar.
[0009] Preferably, the outer wall of the precast casting block fits the inner wall of the sliding groove, the precast casting block and the sliding groove are slidingly connected, and the precast casting blocks are provided in several groups, and the precast casting blocks are distributed in an array.
[0010] Preferably, the pouring mechanism includes a first pouring hole, a support block and a second pouring hole, the first pouring hole is opened at the top of the main load-bearing frame, a support block is fixed to the outside of the suspension support, a second pouring hole is opened at the top of the support block, reinforcing ribs are fixed to the inside of the support block, a conveying hole is opened inside the support block, and a reinforcement groove is opened inside the support block.
[0011] Preferably, the support blocks are provided in several groups, and the support blocks are distributed at equal intervals about the central axis of the suspension support. The reinforcing ribs are provided in four groups, and the reinforcing ribs are distributed symmetrically about the central axis of the second pouring hole.
[0012] Preferably, the delivery holes are provided in several groups, the delivery holes are distributed at equal intervals, the delivery holes are in a "[" shape, and the output ends of the delivery holes are connected to a reinforcement groove.
[0013] Preferably, the main load-bearing frames are provided in several groups, and the main load-bearing frames are distributed in an array about the central axis of the suspension support. The main load-bearing frames are in a "double-limb H" shape, and the auxiliary load-bearing frames are provided in two groups, and the auxiliary load-bearing frames are symmetrically distributed about the central axis of the suspension support.
[0014] Preferably, the inner wall of the main load-bearing frame fits into the outer wall of the connecting cross bar, the main load-bearing frame and the connecting cross bar are slidingly connected, the auxiliary load-bearing frame and the connecting cross bar are slidingly connected, two groups of connecting cross bars are provided, and the connecting cross bars are symmetrically distributed about the central axis of the main load-bearing frame.
[0015] The present invention also provides a high-altitude shared-load steel corridor construction process, comprising the following steps: S1. Embed the suspension supports in the shear walls on both sides of the building, leaving the support blocks exposed. Place multiple sets of main load-bearing frames side by side on the ground, and place two sets of secondary load-bearing frames at the ends on the left and right sides, so that the slots of the two sets of secondary load-bearing frames align with the slots of the main load-bearing frames. Insert the connecting crossbar into the main and secondary load-bearing frames and center them. S2, slide the first reinforcement frame and the second reinforcement frame so that the sliding end of the first reinforcement frame is away from the sliding end of the second reinforcement frame, and insert the first reinforcement frame and the second reinforcement frame into the reinforcement slots opened by the corresponding connecting cross bars respectively. After completing the insertion and connection of the first reinforcement frame, the second reinforcement frame and the reinforcement slots, pour concrete into the reinforcement slots and the first casting trough through the third casting trough, so that after the concrete solidifies, the first reinforcement frame and the connecting cross bar, and the second reinforcement frame and the connecting cross bar are connected, thereby fixing the multiple groups of main load-bearing frames between the two groups of secondary load-bearing frames, and thus completing the assembly of the split main load-bearing frames; S3. After the first reinforcement frame and the second reinforcement frame are inserted and fixed to the connecting cross bar, the precast casting block is inserted into the sliding groove through the installation groove, and concrete is poured inside the precast casting block. After the pouring is completed, it is slid between the second reinforcement frame and the first reinforcement frame, and multiple groups of precast casting blocks are arranged. After the sliding groove is filled, after the concrete inside the precast casting block solidifies, the connecting cross bars on both sides are supported by the first reinforcement frame and the second reinforcement frame and the solidified multiple groups of precast casting blocks, thereby improving the strength of the main load-bearing frame, the auxiliary load-bearing frame and the connecting cross bar after assembly; S4, and by setting up multiple groups of main load-bearing frames, secondary load-bearing frames and assembly blocks connecting cross bars, the length of which can meet the length of the buildings on both sides, using a crane to set the first group of assembly blocks between the buildings on both sides, and hoisting the assembly blocks from the middle to both ends, each group of assembly blocks is connected by bolts, and a temporary stabilizing cable is immediately tensioned after each group of assembly blocks is installed. When the assembly blocks are connected to the buildings, multiple groups of support blocks fixed outside the suspension support are inserted into the main load-bearing frames, so that the first pouring hole and the second pouring hole are connected; S5. Pour concrete into the first pouring hole, so that the concrete is poured into the first pouring hole through the first pouring hole and the second pouring hole, and is poured into the reinforcement groove through the conveying hole. When the concrete fills the support block and solidifies, the solidified concrete can connect the support block and the main load-bearing frame, thereby improving the strength of the corridor after installation.
[0016] Compared with the prior art, the present invention has the following beneficial effects: The present invention cooperates with the first reinforcement frame, the first casting trough, the second reinforcement frame and other structures to enable the device to slide the first reinforcement frame and the second reinforcement frame so that the sliding end of the first reinforcement frame is away from the sliding end of the second reinforcement frame, and the first reinforcement frame and the second reinforcement frame are respectively inserted into the reinforcement slots opened by the corresponding connecting cross bars. After the insertion and connection of the first reinforcement frame, the second reinforcement frame and the reinforcement slots are completed, concrete is poured into the reinforcement slots and the first casting trough through the third casting trough, so that after the concrete solidifies, the first reinforcement frame and the connecting cross bar and the second reinforcement frame and the connecting cross bar are firmly connected, thereby achieving the purpose of facilitating the splicing of multiple main load-bearing frames and secondary load-bearing frames to meet the length and width of the corridor.
[0017] The present invention cooperates with structures such as installation grooves, sliding grooves, and prefabricated casting blocks, so that the device can insert the prefabricated casting blocks into the interior of the sliding grooves through the installation grooves, and cast concrete inside the prefabricated casting blocks. After casting, they are slid between the second reinforcement frame and the first reinforcement frame. By setting multiple groups of prefabricated casting blocks, the sliding grooves are filled and the concrete inside the prefabricated casting blocks is solidified. The solidified prefabricated casting blocks squeeze the first reinforcement frame and the second reinforcement frame, thereby achieving the purpose of improving the fixing strength of the two groups of connecting cross bars to the secondary load-bearing frame and the main load-bearing frame through multiple groups of prefabricated casting blocks.
[0018] The present invention cooperates with structures such as the first pouring hole, the support block, and the second pouring hole, so that the device can pour the interior of the first pouring hole through the first pouring hole and the second pouring hole, and pour the interior of the reinforcement groove through the conveying hole. When the concrete fills the support block and solidifies, the solidified concrete can connect the support block and the main load-bearing frame, thereby connecting the splicing block with the suspension support embedded in the building, so as to achieve the purpose of improving the connection strength of the corridor. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is the whole structure schematic diagram of the present application; Figure 2 It is the whole bottom structure schematic diagram of the present application; Figure 3 It is the whole explosion structure schematic diagram of the present application; Figure 4 It is the reinforcing mechanism structure schematic diagram of the present application; Figure 5 It is the reinforcing mechanism connection state structure schematic diagram of the present application; Figure 6 It is the reinforcing frame structure schematic diagram of the present application; Figure 7 It is the reinforcing frame right view structure schematic diagram of the present application; Figure 8 It is the prefabricated pouring block structure schematic diagram of the present application; Figure 9 It is the suspension support structure schematic diagram of the present application; Figure 10 It is the first pouring hole structure schematic diagram of the present application; Figure 11 It is the pouring mechanism structure schematic diagram of the present application; Figure 12 It is the pouring block forming structure schematic diagram of the present application.
[0020] In the figure: 1, suspension support; 2, main bearing frame; 3, auxiliary bearing frame; 4, corridor frame; 5, connecting cross rod; 6, reinforcing mechanism; 601, first reinforcing frame; 602, first pouring groove; 603, second reinforcing frame; 604, second pouring groove; 605, reinforcing slot; 606, third pouring groove; 7, supporting mechanism; 701, mounting groove; 702, sliding groove; 703, prefabricated pouring block; 8, pouring mechanism; 801, first pouring hole; 802, supporting block; 803, second pouring hole; 804, reinforcing rib; 805, conveying hole; 806, reinforcing groove. DETAILED DESCRIPTION
[0021] As Figures 1 to 12As shown, the present invention provides a high-altitude load-sharing steel corridor, including a suspension support 1, the external movably connected to the main load-bearing frame 2, the external movably connected to the suspension support 1 is a secondary load-bearing frame 3, the main load-bearing frame 2 is provided with a plurality of groups, the main load-bearing frames 2 are arranged in an array with respect to the central axis of the suspension support 1, the main load-bearing frame 2 is in a "double-limb H" shape, the secondary load-bearing frames 3 are provided with two groups, the secondary load-bearing frames 3 are symmetrically distributed with respect to the central axis of the suspension support 1, and the top of the secondary load-bearing frame 3 is fixed with a connecting rod. The gallery frame 4, the main load-bearing frame 2 is internally movably connected with a connecting cross bar 5, the inner wall of the main load-bearing frame 2 fits the outer wall of the connecting cross bar 5, the main load-bearing frame 2 and the connecting cross bar 5 are slidingly connected, the auxiliary load-bearing frame 3 and the connecting cross bar 5 are slidingly connected, there are two groups of connecting cross bars 5, the connecting cross bars 5 are symmetrically distributed about the central axis of the main load-bearing frame 2, the outside of the auxiliary load-bearing frame 3 is installed with a reinforcement mechanism 6, one end of the reinforcement mechanism 6 is provided with a supporting mechanism 7, and the top of the main load-bearing frame 2 is provided with a casting mechanism 8.
[0022] The above scheme is adopted: by pre-embedding the suspension support 1 in the shear walls of the buildings on both sides and leaving the support block 802 exposed, multiple groups of main load-bearing frames 2 are placed side by side on the ground, and two groups of auxiliary load-bearing frames 3 are placed at the ends on the left and right sides, so that the slots of the two groups of auxiliary load-bearing frames 3 and the main load-bearing frames 2 correspond. At this time, the connecting cross bar 5 is inserted into the main load-bearing frame 2 and the auxiliary load-bearing frame 3, and its position is centered. By setting multiple groups of main load-bearing frames 2, auxiliary load-bearing frames 3 and connecting cross bars 5, its length can meet the length of the buildings on both sides. Use a crane to set the first group of assembly blocks between the buildings on both sides, and use the assembly blocks to lift them from the middle to both ends. Each group of assembly blocks is connected by bolts, and the temporary stabilizing cable is immediately tensioned after each group of assembly blocks is installed.
[0023] like Figures 1 to 8 As shown, the reinforcement mechanism 6 includes a first reinforcement frame 601, a first pouring trough 602 and a second reinforcement frame 603. The first reinforcement frame 601 is movably connected to the outside of the auxiliary load-bearing frame 3. The top of the first reinforcement frame 601 is provided with a first pouring trough 602. The inside of the auxiliary load-bearing frame 3 is movably connected to the second reinforcement frame 603. The top of the second reinforcement frame 603 is provided with a second pouring trough 604. The outside of the connecting crossbar 5 is provided with a reinforcement slot 605. The top of the connecting crossbar 5 is provided with a third pouring trough 606. 6. The outer wall of the first reinforcement frame 601 fits the inner wall of the auxiliary load-bearing frame 3, the first reinforcement frame 601 and the auxiliary load-bearing frame 3 are slidingly connected, the second reinforcement frame 603 and the auxiliary load-bearing frame 3 are slidingly connected, the outer wall of the first reinforcement frame 601 fits the inner wall of the second reinforcement frame 603, the first reinforcement frame 601 and the second reinforcement frame 603 are slidingly connected, two groups of reinforcement slots 605 and the third casting trough 606 are opened, and the reinforcement slots 605 and the third casting trough 606 are symmetrically distributed about the central axis of the connecting cross bar 5.
[0024] The above-mentioned scheme is adopted: by sliding the first reinforcement frame 601 and the second reinforcement frame 603, the sliding end of the first reinforcement frame 601 is away from the sliding end of the second reinforcement frame 603, and the first reinforcement frame 601 and the second reinforcement frame 603 are respectively inserted into the reinforcement slots 605 opened by the corresponding connecting cross bars 5. After completing the insertion and connection of the first reinforcement frame 601, the second reinforcement frame 603 and the reinforcement slots 605, concrete is poured into the reinforcement slots 605 and the first casting trough 602 through the third casting trough 606, so that after the concrete solidifies, the first reinforcement frame 601 and the connecting cross bar 5 and the second reinforcement frame 603 and the connecting cross bar 5 are connected, thereby fixing the multiple groups of main load-bearing frames 2 between the two groups of secondary load-bearing frames 3, and then completing the assembly of the split main load-bearing frames 2.
[0025] like Figures 1 to 8 As shown, the support mechanism 7 includes an installation groove 701, a sliding groove 702 and a prefabricated casting block 703. The installation groove 701 is opened at the top of the second reinforcement frame 603. The sliding groove 702 is opened inside the second reinforcement frame 603. The prefabricated casting block 703 is movably connected inside the sliding groove 702. The outer wall of the prefabricated casting block 703 fits the inner wall of the sliding groove 702. The prefabricated casting block 703 and the sliding groove 702 are slidably connected. Several groups of prefabricated casting blocks 703 are provided, and the prefabricated casting blocks 703 are distributed in an array.
[0026] The above scheme is adopted: by inserting the prefabricated casting block 703 into the sliding groove 702 through the installation groove 701, and pouring concrete inside the prefabricated casting block 703, after the pouring is completed, it is slid to between the second reinforcement frame 603 and the first reinforcement frame 601, and by setting multiple groups of prefabricated casting blocks 703, after the sliding groove 702 is filled, the concrete inside the prefabricated casting block 703 is solidified, and at this time, the connecting cross bars 5 on both sides are supported by the first reinforcement frame 601 and the second reinforcement frame 603 and the solidified multiple groups of prefabricated casting blocks 703, thereby improving the strength of the main load-bearing frame 2, the auxiliary load-bearing frame 3 and the connecting cross bar 5 after assembly.
[0027] like Figures 1 to 12 As shown, the pouring mechanism 8 includes a first pouring hole 801, a support block 802 and a second pouring hole 803. The first pouring hole 801 is opened at the top of the main load-bearing frame 2. The support block 802 is fixed to the outside of the suspension support 1. The second pouring hole 803 is opened at the top of the support block 802. The inside of the support block 802 is fixed with a reinforcing rib 804. The support blocks 802 are provided in several groups, and the support blocks 802 are distributed at equal intervals about the central axis of the suspension support 1. Four groups of reinforcing ribs 804 are provided, and the reinforcing ribs 804 are symmetrically distributed about the central axis of the second pouring hole 803.
[0028] like Figures 1 to 12As shown, a delivery hole 805 is opened inside the support block 802, and a reinforcement groove 806 is opened inside the support block 802. There are several groups of delivery holes 805, and the delivery holes 805 are evenly spaced and shaped like "[". The output end of the delivery hole 805 is connected to the reinforcement groove 806.
[0029] The above-mentioned solution is adopted: by pouring concrete into the first pouring hole 801, the concrete is poured into the first pouring hole 801 through the first pouring hole 801 and the second pouring hole 803, and is poured into the interior of the reinforcement groove 806 through the conveying hole 805. When the concrete fills the support block 802 and solidifies, the solidified concrete can connect the support block 802 and the main load-bearing frame 2, thereby improving the strength of the corridor after installation.
[0030] The present invention also provides a high-altitude shared-load steel corridor construction process, comprising the following steps: S1. Pre-embed the suspension supports 1 in the shear walls on both sides of the building, and expose the support blocks 802. Place multiple sets of main load-bearing frames 2 side by side on the ground, and place two sets of auxiliary load-bearing frames 3 at the ends on the left and right sides, so that the slots of the two sets of auxiliary load-bearing frames 3 and the main load-bearing frames 2 are aligned. At this time, insert the connecting crossbar 5 into the main load-bearing frames 2 and the auxiliary load-bearing frames 3 and center them. S2. Slide the first reinforcement frame 601 and the second reinforcement frame 603 so that the sliding end of the first reinforcement frame 601 is away from the sliding end of the second reinforcement frame 603, and insert the first reinforcement frame 601 and the second reinforcement frame 603 into the reinforcement slots 605 opened by the corresponding connecting cross bars 5 respectively. After completing the insertion and connection of the first reinforcement frame 601, the second reinforcement frame 603 and the reinforcement slots 605, pour concrete into the reinforcement slots 605 and the first casting groove 602 through the third casting groove 606. After the concrete solidifies, the first reinforcement frame 601 and the connecting cross bars 5 and the second reinforcement frame 603 and the connecting cross bars 5 are connected, thereby fixing the multiple groups of main load-bearing frames 2 between the two groups of secondary load-bearing frames 3, and then completing the assembly of the split main load-bearing frames 2; S3. After completing the insertion of the first reinforcement frame 601 and the second reinforcement frame 603 and fixing them to the connecting cross bar 5, the precast casting block 703 is inserted into the sliding groove 702 through the installation groove 701, and concrete is poured inside the precast casting block 703. After the pouring is completed, it is slid between the second reinforcement frame 603 and the first reinforcement frame 601, and multiple groups of precast casting blocks 703 are set. After the sliding groove 702 is filled, the concrete inside the precast casting block 703 is solidified. At this time, the connecting cross bars 5 on both sides are supported by the first reinforcement frame 601 and the second reinforcement frame 603 and the solidified multiple groups of precast casting blocks 703, thereby improving the strength of the main load-bearing frame 2, the auxiliary load-bearing frame 3 and the connecting cross bar 5 after assembly; S4, and by setting up multiple groups of main load-bearing frames 2, secondary load-bearing frames 3 and assembly blocks of connecting cross bars 5, the length of which can meet the length of the buildings on both sides, using a crane to set the first group of assembly blocks between the buildings on both sides, and hoisting the assembly blocks from the middle to both ends, each group of assembly blocks is connected by bolts, and a temporary stabilizing cable is immediately tensioned after each group of assembly blocks is installed. When the assembly blocks are connected to the buildings, multiple groups of support blocks 802 fixed outside the suspension support 1 are inserted into the main load-bearing frame 2, so that the first pouring hole 801 and the second pouring hole 803 are connected; S5. Pour concrete into the first pouring hole 801, so that the concrete is poured into the first pouring hole 801 through the first pouring hole 801 and the second pouring hole 803, and is poured into the reinforcement groove 806 through the delivery hole 805. When the concrete fills the support block 802 and solidifies, the solidified concrete can connect the support block 802 and the main load-bearing frame 2, thereby improving the strength of the corridor after installation.
[0031] The examples of this specific embodiment are all preferred embodiments of this application and are not intended to limit the scope of protection of this application. Identical components are represented by the same reference numerals. Therefore, any equivalent changes made based on the structure, shape, and principle of this application should be included in the scope of protection of this application.
Claims
1. A high-altitude load-sharing steel corridor, comprising a suspension support (1), characterized in that: The outside of the suspension support (1) is movably connected to the main load-bearing frame (2), the outside of the suspension support (1) is movably connected to the auxiliary load-bearing frame (3), the top of the auxiliary load-bearing frame (3) is fixed with a gallery frame (4), the inside of the main load-bearing frame (2) is movably connected to a connecting crossbar (5), the outside of the auxiliary load-bearing frame (3) is equipped with a reinforcement mechanism (6), one end of the reinforcement mechanism (6) is provided with a support mechanism (7), and the top of the main load-bearing frame (2) is provided with a casting mechanism (8); The reinforcing mechanism (6) comprises a first reinforcing frame (601), a first pouring trough (602) and a second reinforcing frame (603); the first reinforcing frame (601) is movably connected to the outside of the auxiliary load-bearing frame (3); the first pouring trough (602) is provided at the top of the first reinforcing frame (601); the second reinforcing frame (603) is movably connected to the inside of the auxiliary load-bearing frame (3); the second pouring trough (604) is provided at the top of the second reinforcing frame (603); The support mechanism (7) comprises a mounting groove (701), a sliding groove (702) and a prefabricated casting block (703); the mounting groove (701) is provided at the top end of the second reinforcement frame (603); a sliding groove (702) is provided inside the second reinforcement frame (603); and the prefabricated casting block (703) is movably connected inside the sliding groove (702).
2. The high-altitude load-sharing steel corridor according to claim 1 is characterized in that: A reinforcement slot (605) is provided on the outside of the connecting crossbar (5), a third casting trough (606) is provided on the top of the connecting crossbar (5), the outer wall of the first reinforcement frame (601) is in contact with the inner wall of the auxiliary load-bearing frame (3), the first reinforcement frame (601) and the auxiliary load-bearing frame (3) are slidably connected, and the second reinforcement frame (603) and the auxiliary load-bearing frame (3) are slidably connected.
3. The high-altitude load-sharing steel corridor according to claim 2 is characterized in that: The outer wall of the first reinforcement frame (601) fits the inner wall of the second reinforcement frame (603), the first reinforcement frame (601) and the second reinforcement frame (603) are slidably connected, two groups of reinforcement slots (605) and third casting troughs (606) are provided, and the reinforcement slots (605) and third casting troughs (606) are symmetrically distributed about the central axis of the connecting crossbar (5).
4. The high-altitude load-sharing steel corridor according to claim 1 is characterized in that: The outer wall of the prefabricated casting block (703) fits the inner wall of the sliding groove (702), and the prefabricated casting block (703) and the sliding groove (702) are slidably connected. The prefabricated casting block (703) is provided in a plurality of groups, and the prefabricated casting blocks (703) are distributed in an array.
5. The high-altitude load-sharing steel corridor according to claim 1 is characterized in that: The pouring mechanism (8) comprises a first pouring hole (801), a support block (802) and a second pouring hole (803); the first pouring hole (801) is provided at the top end of the main load-bearing frame (2); a support block (802) is fixed to the outside of the suspension support (1); a second pouring hole (803) is provided at the top end of the support block (802); a reinforcing rib (804) is fixed to the inside of the support block (802); a conveying hole (805) is provided in the inside of the support block (802); and a reinforcement groove (806) is provided in the inside of the support block (802).
6. The high-altitude load-sharing steel corridor according to claim 5 is characterized in that: The support blocks (802) are provided in several groups, and the support blocks (802) are distributed at equal intervals about the central axis of the suspension support (1). The reinforcing ribs (804) are provided in four groups, and the reinforcing ribs (804) are distributed symmetrically about the central axis of the second pouring hole (803).
7. The high-altitude load-sharing steel corridor according to claim 5 is characterized in that: The delivery holes (805) are provided in a plurality of groups. The delivery holes (805) are distributed at equal intervals. The delivery holes (805) are in a "[" shape. The output ends of the delivery holes (805) are connected to the reinforcement groove (806).
8. The high-altitude load-sharing steel corridor according to claim 1 is characterized in that: The main load-bearing frames (2) are provided in a plurality of groups, and the main load-bearing frames (2) are distributed in an array about the central axis of the suspension support (1). The main load-bearing frames (2) are in a "double-limb H" shape. The auxiliary load-bearing frames (3) are provided in two groups, and the auxiliary load-bearing frames (3) are distributed symmetrically about the central axis of the suspension support (1).
9. The high-altitude load-sharing steel corridor according to claim 1 is characterized in that: The inner wall of the main load-bearing frame (2) fits the outer wall of the connecting cross bar (5), the main load-bearing frame (2) and the connecting cross bar (5) are slidably connected, the auxiliary load-bearing frame (3) and the connecting cross bar (5) are slidably connected, two groups of the connecting cross bars (5) are provided, and the connecting cross bars (5) are symmetrically distributed about the central axis of the main load-bearing frame (2).
10. A construction process for a high-altitude load-sharing steel corridor, using the high-altitude load-sharing steel corridor according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1. Pre-embed the hanging supports (1) in the shear walls of the buildings on both sides, and expose the support blocks (802). Place multiple sets of main load-bearing frames (2) side by side on the ground, and place two sets of auxiliary load-bearing frames (3) at the ends on the left and right sides, so that the slots of the two sets of auxiliary load-bearing frames (3) and the main load-bearing frames (2) correspond. At this time, insert the connecting crossbar (5) into the main load-bearing frames (2) and the auxiliary load-bearing frames (3), and center them. S2, sliding the first reinforcement frame (601) and the second reinforcement frame (603) so that the sliding end of the first reinforcement frame (601) is away from the sliding end of the second reinforcement frame (603), and the first reinforcement frame (601) and the second reinforcement frame (603) are respectively inserted into the reinforcement slots (605) opened by the corresponding connecting cross bars (5). After completing the insertion and connection of the first reinforcement frame (601), the second reinforcement frame (603) and the reinforcement slots (605), concrete is poured into the reinforcement slots (605) and the first casting trough (602) through the third casting trough (606). After the concrete solidifies, the first reinforcement frame (601) and the connecting cross bars (5) and the second reinforcement frame (603) and the connecting cross bars (5) are connected, thereby fixing the multiple groups of main load-bearing frames (2) between the two groups of secondary load-bearing frames (3), and completing the assembly of the split main load-bearing frames (2); S3, after completing the insertion of the first reinforcement frame (601) and the second reinforcement frame (603) and fixing them to the connecting crossbar (5), insert the prefabricated casting block (703) into the interior of the sliding groove (702) through the installation groove (701), and pour concrete inside the prefabricated casting block (703). After the pouring is completed, slide it between the second reinforcement frame (603) and the first reinforcement frame (601), and set multiple groups of prefabricated casting blocks (703). After the sliding groove (702) is filled, the concrete inside the prefabricated casting block (703) is solidified. At this time, the connecting crossbars (5) on both sides are supported by the first reinforcement frame (601) and the second reinforcement frame (603) and the solidified multiple groups of prefabricated casting blocks (703), thereby improving the strength of the main load-bearing frame (2), the auxiliary load-bearing frame (3) and the connecting crossbar (5) after assembly; S4, and by setting up multiple groups of main load-bearing frames (2), secondary load-bearing frames (3) and assembly blocks of connecting cross bars (5), the length of which can meet the length of the buildings on both sides, using a crane to set the first group of assembly blocks between the buildings on both sides, and hoisting the assembly blocks from the middle to both ends, each group of assembly blocks is connected by bolts, and a temporary stabilizing cable is immediately tensioned after each group of assembly blocks is installed. When the assembly blocks are connected to the buildings, multiple groups of support blocks (802) fixed outside the suspension support (1) are inserted into the main load-bearing frame (2), so that the first pouring hole (801) and the second pouring hole (803) are connected; S5. Pour concrete into the first pouring hole (801), so that the concrete is poured into the first pouring hole (801) through the first pouring hole (801) and the second pouring hole (803), and poured into the reinforcement groove (806) through the conveying hole (805). When the concrete fills the support block (802) and solidifies, the solidified concrete can connect the support block (802) and the main load-bearing frame (2), thereby improving the strength of the corridor after installation.
Citation Information
Patent Citations
Assembled building steel corridor structure
CN222120496U