Adjustable pipeline supporting device for water conservancy project

The design of bagged concrete slope protection and limit track components solves the problem of low water intake elevation and steep outer slope in water conservancy projects, realizes stable and low-cost pipeline support and water intake device, which is suitable for embankment slopes without bunds, reducing construction difficulty and investment.

CN120759986AActive Publication Date: 2025-10-10FOSHAN SHUNDE WATER RESOURCES & HYDROPOWER SURVEY & DESIGN INST CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202511251871.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-09-03
Publication Date
2025-10-10
Estimated Expiration
2045-09-03

AI Technical Summary

Technical Problem

In water conservancy projects, when the water intake elevation is low and there is no outer bund at the embankment and the outer slope is steep, the existing technology requires the construction of a cofferdam for dry water construction, resulting in large construction investment and difficulty in implementing stable installation of the water intake pipeline.

Method used

The use of bagged concrete slope protection and limited track components, including leveling I-beams, expansion anchors, limited angle steels, track channels, connecting beam channels and positioning plates, forms an adjustable pipeline support device. The setting of multiple sections of track channels, steel pipe piles and positioning plates reduces the number of pier facilities, has a wide range of applications, ensures the stability of the slide rail, and reduces the difficulty of installation and maintenance through the segmented adjustment of the water delivery pipes and water pumps.

Benefits of technology

No need for cofferdam dry water construction, which reduces construction difficulty and investment, increases the water intake elevation, reduces the pump's suction of riverbed silt, simplifies the installation and maintenance process, and expands the scope of application.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120759986A_ABST
    Figure CN120759986A_ABST
Patent Text Reader

Abstract

The invention discloses an adjustable pipeline supporting device for hydraulic engineering, and relates to the technical field of pipeline supporting, the adjustable pipeline supporting device comprises a mold bag concrete protection slope which is formed on the surface of a soil layer in a pouring mode, and further comprises a limiting rail assembly arranged on the mold bag concrete protection slope; the limiting rail assembly comprises leveling I-shaped steel symmetrically and horizontally arranged on the upper surface of the mold bag concrete slope protection, expansion anchor bolts are fixedly installed in the leveling I-shaped steel at equal intervals, limiting angle steel is fixedly installed on the upper surfaces of the expansion anchor bolts through bolts, and rail channel steel is jointly welded between the two pieces of limiting angle steel. Through the arrangement of the multiple sections of rail channel steel, the steel pipe piles, the connecting beam channel steel and the clamping plates, the sliding rail can be fixed at the end point of the sliding rail composed of the rail channel steel, so that the arrangement of buttresses and infrastructures along the bank of the mold bag concrete slope protection is reduced, the requirement for bank slope soil texture is lowered, the application range is wide, and the stability of the sliding rail is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of pipeline support, in particular to an adjustable pipeline support device for water conservancy projects. BACKGROUND

[0002] Water conservancy project is an engineering for controlling and allocating surface water and groundwater in nature to achieve the purpose of eliminating harm and benefiting, also known as water project, and is built to control water flow, prevent flood disasters, and regulate and distribute water to meet the needs of people's life and production for water resources. The water conservancy project has a requirement for water intake guarantee rate in specific implementation, so the river water intake port needs to be set below the low water level in the dry season to ensure stable water intake. When the single-span length of the water intake pipe is large, a concrete support pier (or a pier) is added in the middle to divide the water intake pipe into multiple spans to reduce the single-span length. The above technical means is relatively easy to implement for water intake pipes with high elevation, outer beach, and gentle outer slope at the embankment (the water pipe can enter the water relatively gently, and the intermediate support pier or pier can be constructed on the dry outer beach during the dry season); however, it is difficult to implement for water intake pipes with low elevation, no outer beach, and steep outer slope at the embankment. The position of the support pier or pier may be below the water surface all year round, so a cofferdam needs to be built for dry construction, resulting in large construction investment, and the cost of building a cofferdam is much higher than that of building a pier or support pier. To solve the above problems, the present application provides an adjustable pipeline support device for water conservancy projects. SUMMARY

[0003] Technical problems to be solved Therefore, in view of the deficiencies in the prior art, the present application provides an adjustable pipeline support device for water conservancy projects to solve the problems raised in the background. Technical scheme

[0004] To achieve the above-mentioned purpose, the present application provides the following technical scheme: an adjustable pipeline support device for water conservancy projects, comprising a formwork concrete slope, which is cast on the surface of the soil layer, and a limiting rail assembly arranged on the formwork concrete slope; The limiting rail assembly comprises symmetrical and parallel leveling H-beams arranged on the upper surface of the formwork concrete slope. The leveling H-beams are arranged in two groups, and multiple leveling H-beams in the two groups are arranged at equal distances from each other. Expansion anchors are fixedly installed at equal distances inside the leveling H-beams. Limiting angle steels are fixedly installed on the upper surfaces of the expansion anchors by bolts. A rail channel steel is welded between the two limiting angle steels. A coupling beam channel steel is welded to the outer surfaces of the ends of the rail channel steel. A clamping plate is welded to the outer surface of the coupling beam channel steel. A steel pipe pile is welded to the end of the clamping plate away from the coupling beam channel steel.

[0005] Preferably, the leveling I-beam, expansion anchor bolts, limiting angle steels and track channel steels are all arranged at an angle, and the leveling I-beam, expansion anchor bolts, limiting angle steels and track channel steels are all kept parallel to the inclined plane of the mold bag concrete slope protection. The expansion anchor bolts penetrate and extend into the interior of the mold bag concrete slope protection away from one end of the leveling I-beam. The two limiting angle steels are arranged axially symmetrically with reference to the central axis of the mold bag concrete slope protection, and the two track channel steels are arranged axially symmetrically with reference to the central axis of the mold bag concrete slope protection.

[0006] Preferably, the interior of the positioning plate fits the outer surface of the track channel steel, the connecting beam channel steel and the positioning plate together constitute a box-type positioning device, and the bottom end of the steel pipe pile passes through the mold bag concrete slope protection and extends into the soil layer.

[0007] Preferably, it also includes a conveying assembly arranged on the mold bag concrete slope protection; The conveying assembly includes water delivery pipes equidistantly arranged inside the track channel steel, and water pumps are provided between adjacent water delivery pipes. A butterfly valve is fixedly installed on one end of the water delivery pipe inside the vertically higher end of the track channel steel, and a telescopic pipe is fixedly installed on the end of the butterfly valve away from the water delivery pipe. A connecting pipe is fixedly installed on the end of the telescopic pipe away from the butterfly valve, and a through-embankment reinforced concrete pipe is fixedly installed on the outer surface of the end of the connecting pipe close to the telescopic pipe. A breathing valve is fixedly installed inside the connecting pipe, and an buried reinforced concrete pipe is fixedly installed on the outer surface of the end of the connecting pipe away from the telescopic pipe. A reinforced concrete pier is fixedly installed on the bottom of the end of the connecting pipe away from the telescopic pipe.

[0008] Preferably, the reinforced concrete pipes passing through the embankment and the buried reinforced concrete pipes are both arranged on the upper surface of the bagged concrete slope protection and fixedly installed with the upper surface of the bagged concrete slope protection, and the bottom end of the reinforced concrete pier passes through and extends to the inside of the bagged concrete slope protection.

[0009] Preferably, it further comprises a sliding assembly provided on the outer surface of the water delivery pipe and the water pump; The sliding assembly includes supporting angle steels fixedly welded to the outer surfaces of both ends of the water delivery pipe, supporting channel steels are welded and fixed to the outer surfaces of both ends of the water pump, tie rod angle steels are welded to the outer surfaces of the supporting angle steels and both sides of the supporting channel steels, connecting angle steels are welded to the outer surface of the end of the supporting angle steel away from the water delivery pipe and the outer surface of the end of the supporting channel steel away from the water pump, a slider is fixedly installed on the outer surface of the bottom end of the connecting angle steel by bolts, a stopper is fixedly installed on the outer surface of one side of the slider, two partition plates 1 are provided on the side of the stopper away from the slider, and partition plate 2 is welded and fixed between the two partition plates 1.

[0010] Preferably, the support channel steel is symmetrically arranged on both sides of the water conveying pipe along the central axis of the water conveying pipe, the two connecting angle steels are arranged on and attached to the outer surfaces of the water conveying pipe and the water pump, the sliding block is arranged between the two rail channel steels and is in sliding connection with the inner walls of the rail channel steels, the first partition plate is fixedly installed on the stop block through bolts, and the first partition plate is in sliding connection with the inside of the rail channel steel.

[0011] Preferably, the water conveying pipe further comprises a clamping assembly arranged between adjacent water conveying pipes. The clamping assembly comprises a limiting ring fixedly installed on the outer surface of one of the two adjacent water conveying pipes, a resisting circular rod fixedly connected to the side surface of the limiting ring, a limiting spring sleeved on the outer surface of the resisting circular rod, a positioning ring fixedly connected to the outer surface of the other water conveying pipe, and a clamping block rotatably connected to the outer surface of the positioning ring.

[0012] Preferably, the resisting circular rod, the limiting spring and the clamping block are centrally symmetrically arranged with the center of the limiting ring as the reference, the resisting circular rod is arranged between the limiting ring and the positioning ring, the positioning ring is internally provided with through holes in a size and number matched with the resisting circular rod, the clamping block is clamped to the outer surface of the limiting ring at the end away from the positioning ring, and the clamping block is heavier at the end close to the positioning ring than at the end close to the limiting ring.

[0013] Compared with the prior art, the present application provides an adjustable pipeline support device for water conservancy projects, which has the following advantages: Through the arrangement of the multi-section rail channel steel, the steel pipe pile, the connecting beam channel steel and the clamping plate, the slide rail formed by the rail channel steel can be fixed at the end of the slide rail, thereby reducing the arrangement of the supporting pier and infrastructure along the shore of the mold bag concrete revetment, lowering the requirement for the soil quality of the shore slope, being suitable for a wide range of applications and ensuring the stability of the slide rail. Through the arrangement of the multiple water conveying pipes and the multiple water pumps, the original long pipeline is segmented, the water pump inlet elevation can be adjusted according to actual needs, in addition, the water conveying pipe can be installed and recycled on the mold bag concrete revetment in a sliding manner, reducing the underwater work of the workers during installation and recycling, thereby reducing the installation, maintenance and pipeline maintenance difficulty. Through the arrangement of the limiting ring, the resisting circular rod, the positioning ring and the clamping block, the adjacent water conveying pipes and water pumps can be quickly connected, and they can also be quickly disassembled under the condition of stable connection between them, thereby shortening the maintenance time when the water conveying pipe is maintained. Through the arrangement of the multi-section water conveying pipeline, the multiple water pumps and the connecting pipeline, the water inlet elevation can be increased when water is taken, thereby reducing the occurrence of the water pump suctioning riverbed silt, which is conducive to the long-term use of the water pump. By setting up the bagged concrete slope protection, a slide rail installation base composed of track channel steel can be formed, thereby eliminating the need for cofferdam dry water construction, reducing construction difficulty and construction investment. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic top view of the overall structure of the present invention; Figure 2 It is a side view schematic diagram of the overall structure of the present invention; Figure 3 This is a schematic diagram of the cross-sectional structure of the bagged concrete slope protection of the present invention; Figure 4 This is a schematic diagram of the connection relationship of the steel pipe piles of the present invention; Figure 5 For the present invention Figure 4 A magnified schematic diagram of the structure at point B in the middle; Figure 6 For the present invention Figure 4 A magnified schematic diagram of the structure at point C in the middle; Figure 7 This is a schematic diagram of the connection relationship of the channel steel of the coupling beam of the present invention; Figure 8 This is a schematic diagram of the internal structure of the track channel steel of the present invention; Figure 9 This is a schematic diagram of the connection relationship of the supporting channel steel of the present invention; Figure 10 For the present invention Figure 9 A magnified schematic diagram of the structure at D in the middle; Figure 11 This is a schematic diagram of a planar structure of a partition of the present invention; Figure 12 This is a schematic diagram of the planar structure of the supporting channel steel of the present invention; Figure 13 This is a schematic diagram of the planar structure of the supporting angle steel of the present invention; Figure 14 This is a schematic diagram of the connection relationship of the supporting angle steel of the present invention.

[0015] In the figure: 11, bagged concrete slope protection; 21. Leveling I-beam; 22. Expansion anchor; 23. Limiting angle steel; 24. Track channel steel; 26. Connecting beam channel steel; 27. Positioning plate; 28. Steel pipe pile; 31. Water delivery pipe; 32. Water pump; 33. Butterfly valve; 34. Telescopic pipe; 35. Reinforced concrete pipe for embankment penetration; 36. Breathing valve; 37. Buried reinforced concrete pipe; 38. Reinforced concrete pier; 39. Connecting pipe; 41. Support angle steel; 42. Support channel steel; 43. Tie rod angle steel; 44. Connecting angle steel; 45. Slider; 46. Stopper; 47. Partition 1; 48. Partition 2; 51. Limiting ring; 52. Interference rod; 53. Limiting spring; 54. Positioning ring; 55. Clamping block. DETAILED DESCRIPTION

[0016] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0017] Embodiments of the present invention See also Figures 1 to 5 、 Figure 7 、 Figure 8 、 Figure 11 and Figure 14 An adjustable pipe support device for water conservancy projects includes a mold bag concrete slope protection 11, the mold bag concrete slope protection 11 is cast and formed on the surface of the soil layer, and also includes a limit track assembly set on the mold bag concrete slope protection 11; The limiting track assembly includes a leveling I-beam 21 symmetrically and parallelly arranged on the upper surface of the mold bag concrete slope protection 11. There are two groups of leveling I-beams 21. The multiple leveling I-beams 21 in the two groups of leveling I-beams 21 are equidistantly arranged. Expansion anchors 22 are equidistantly fixed inside the leveling I-beams 21. The upper surfaces of the expansion anchors 22 are fixed with limiting angle steels 23 by bolts. A track channel steel 24 is welded between the two limiting angle steels 23. The outer surfaces of the ends of the track channel steel 24 are welded with connecting beam channel steels 26. The outer surfaces of the connecting beam channel steels 26 are welded with a positioning plate 27. The positioning plate 27 is welded with a steel pipe pile 28 at the end away from the connecting beam channel steel 26.

[0018] The spacing between adjacent leveling I-beams 21 is set to 3 meters.

[0019] Among them, the leveling I-beam 21, the expansion anchor 22, the limiting angle steel 23 and the track channel steel 24 are all arranged at an angle, and the leveling I-beam 21, the expansion anchor 22, the limiting angle steel 23 and the track channel steel 24 are all kept parallel to the inclined plane of the mold bag concrete slope protection 11. The expansion anchor 22 penetrates and extends into the interior of the mold bag concrete slope protection 11 away from one end of the leveling I-beam 21. The two limiting angle steels 23 are arranged axially symmetrically with respect to the central axis of the mold bag concrete slope protection 11, and the two track channel steels 24 are arranged axially symmetrically with respect to the central axis of the mold bag concrete slope protection 11.

[0020] Among them, the mold bag concrete slope protection 11 is built on the water-facing side of the embankment slope. The construction of the mold bag concrete slope protection 11 strengthens the embankment slope while ensuring that the installation surface of the leveling I-beam 21 and other steel materials is in a flat state; The box type clamping device is formed by the clamping plate 27 and the beam channel steel 26, and the steel pipe pile 28 penetrates the bagged concrete slope 11 and extends into the soil layer.

[0021] Further embodiments Please refer to Figures 1 to 3 , Figure 7 and Figure 8 The adjustable pipeline support device for water conservancy projects further comprises a conveying assembly arranged on the bagged concrete slope 11. The conveying assembly comprises conveying water pipes 31 arranged equidistantly inside the track channel steel 24, a water pump 32 arranged between adjacent conveying water pipes 31, a butterfly valve 33 fixedly installed at one end of the conveying water pipe 31 located at the higher vertical height end of the track channel steel 24, an extension pipeline 34 fixedly installed at the end of the butterfly valve 33 away from the conveying water pipe 31, a connecting pipeline 39 fixedly installed at the end of the extension pipeline 34 away from the butterfly valve 33, a diaphragm valve 36 fixedly installed inside the connecting pipeline 39, a buried reinforced concrete pipe 37 fixedly installed at the end of the connecting pipeline 39 away from the extension pipeline 34, and a reinforced concrete pier 38 fixedly installed at the bottom of the connecting pipeline 39 away from the extension pipeline 34.

[0022] The diaphragm valve 36 is fixedly installed inside the connecting pipeline 39.

[0023] The first section of the track channel steel 24 arranged symmetrically in the vertical direction is located at the upper wing edge of the highest position of the bagged concrete slope 11, and needs to be cut according to the size of the conveying water pipe 31.

[0024] Further embodiments Please refer to Figure 7 and Figures 9 to 14 The adjustable pipeline support device for water conservancy projects further comprises a sliding assembly arranged on the outer surface of the conveying water pipe 31 and the water pump 32. The sliding assembly includes a supporting angle steel 41 fixedly welded to the outer surfaces of both ends of the water delivery pipe 31, and a supporting channel steel 42 is welded and fixed to the outer surfaces of both ends of the water pump 32. A pull rod angle steel 43 is welded to the outer surfaces of both sides of the supporting angle steel 41 and the supporting channel steel 42. A connecting angle steel 44 is welded to the outer surface of the end of the supporting angle steel 41 away from the water delivery pipe 31 and the outer surface of the end of the supporting channel steel 42 away from the water pump 32. A slider 45 is fixedly installed on the outer surface of the bottom end of the connecting angle steel 44 by bolts, and a stopper 46 is fixedly installed on the outer surface of one side of the slider 45. Two partition plates 47 are provided on the side of the stopper 46 away from the slider 45, and a partition plate 2 48 is welded and fixed between the two partition plates 1 47.

[0025] Among them, the supporting channel steel 42 is symmetrically arranged on both sides of the water delivery pipe 31 and the water pump 32 along the horizontal central axis of the water delivery pipe 31. The two connecting angle steels 44 are respectively arranged on the outer surfaces of the water delivery pipe 31 and the water pump 32 and are in contact with the outer surfaces of the water delivery pipe 31 and the water pump 32. The slider 45 is arranged between the two track channel steels 24 and is slidingly connected to the inner wall of the track channel steel 24. The partition 47 is fixedly installed by bolts and the block 46, and the partition 47 is slidingly connected to the inside of the track channel steel 24.

[0026] Further embodiments See also Figure 4 and Figure 6 , the adjustable water conservancy engineering pipe support device also includes a clamping assembly provided between adjacent water delivery pipes 31; The clamping assembly includes a limiting ring 51 fixedly installed on the outer surface of one of the two adjacent water delivery pipes 31, a resistance round rod 52 fixedly connected to the side of the limiting ring 51, and a limiting spring 53 is sleeved on the outer surface of the resistance round rod 52, and a positioning ring 54 is fixedly connected to the outer surface of the other water delivery pipe 31, and a clamping block 55 is rotatably connected to the outer surface of the positioning ring 54.

[0027] Among them, the interference rod 52, the limiting spring 53 and the clamping block 55 are all arranged in a central symmetrical manner with the center of the limiting ring 51 as a reference. The interference rod 52 is arranged between the limiting ring 51 and the positioning ring 54. The positioning ring 54 is penetrated by a through hole with a size and number that is compatible with the interference rod 52. The clamping block 55 is clamped on the outer surface of the limiting ring 51 at one end away from the positioning ring 54, and the weight of the clamping block 55 close to the positioning ring 54 is greater than that of the clamping block 55 close to the limiting ring 51.

[0028] The working process and principle of the above embodiment are as follows: Forming of bagged concrete slope protection 11: It should be noted that the adjustable pipeline support device for water conservancy projects is specifically used for constructing a water intake pipe on a dike slope without an outer beach and with a relatively steep outer slope. In order to reduce the impact of the newly built project on the original dike slope, the staff needs to perform slope trimming and reinforcement on the steep and uneven dike slope by using concrete, so as to form a surface flatness of the formwork concrete slope 11. Installation of the device: The staff transports metal pieces such as leveling H-beams 21, limiting angle steels 23, and track channel steels 24 to the concrete dike slope by using the external device, places the leveling H-beams 21 at the specified positions according to the pre-calculated data, and makes the leveling H-beams 21 parallel to the inclined plane of the formwork concrete slope 11. Then, the expansion anchors 22 are installed equidistantly in the leveling H-beams 21 by using a drilling tool. It should be noted that, in order to ensure that the expansion anchors 22 can stably fix the leveling H-beams 21, the bottom end of the expansion anchors 22 needs to be located in the formwork concrete slope 11, and the top end of the expansion anchors 22 needs to be immersed in the leveling H-beams 21. Then, the limiting angle steels 23 are fixedly installed on the upper surface of the installed leveling H-beams 21, and the limiting angle steels 23 are fixedly installed with the leveling H-beams 21 by using bolts. This process needs to ensure that the two limiting angle steels 23 on the two leveling H-beams 21 are arranged in axial symmetry. After installation is completed, two track channel steels 24 are placed between the left and right limiting angle steels 23, and the track channel steels 24 are welded with the leveling H-beams 21 and the limiting angle steels 23. It should be noted that, since the length of the formwork concrete slope 11 needs to be trimmed according to the size of the dike slope, the length of the formwork concrete slope 11 is not uniform. Under the limitation of the existing fixed-size track channel steels 24, the track channel steels 24 need to be arranged in multiple sections according to the above steps, and the adjacent two sections of the track channel steels 24 are welded with each other, and it needs to be ensured that the multiple sections of the track channel steels 24 are kept in parallel with the inclined plane of the formwork concrete slope 11. After the multiple sections of the track channel steels 24 are welded, the outer surface of the track channel steel 24 located at the last section of the track channel steels 24, i.e., located at the bottom end of the inclined plane of the formwork concrete slope 11, is welded with the continuous beam channel steel 26 to fix the position of the last end track channel steel 24. In addition, multiple clamping plates 27 are welded on the outer surfaces of the continuous beam channel steel 26 and the track channel steels 24 after welding is completed. It should be noted that the continuous beam channel steel 26 and the multiple clamping plates 27 jointly constitute a box-type clamping device, the end of the clamping device is welded with a steel pipe pile 28, and the bottom end of the steel pipe pile 28 penetrates through the formwork concrete slope 11 and extends into the soil layer, so as to further fix the position of the last end track channel steel 24, thereby forming a stable track for the movement of the water conveying pipe 31. It should be noted that, in order to ensure that the water conveying pipe 31 can be quickly placed inside the track channel steel 24, the first section of the track channel steel 24 symmetrically arranged in the vertical direction is located on the upper edge of the one end of the highest position of the bagged concrete slope 11, and the size of the water conveying pipe 31 needs to be cut. At the same time, the box type clamping device composed of the continuous beam channel steel 26 and the clamping plate 27 is welded on the steel pipe pile 28, which can transmit the horizontal component force of the whole structure to the steel pipe pile 28, thereby reducing the horizontal stress of the conveying track formed by the track channel steel 24, and avoiding stress concentration; Through the arrangement of the track channel steel 24, the steel pipe pile 28, the continuous beam channel steel 26 and the clamping plate 27, the sliding rail formed by the track channel steel 24 can be fixed at the end of the sliding rail, thereby reducing the setting of the abutment and infrastructure along the shore of the bagged concrete slope 11, reducing the requirement for the soil quality of the shore slope, and having a wide application range and ensuring the stability of the sliding rail; Subsequently, the workers can place the multi-section water conveying pipe 31 and the water pump 32 into the conveying track formed by the track channel steel 24. It should be noted that, in order to adapt to the size of the bagged concrete slope 11, the water conveying pipe 31 and the water pump 32 are arranged in multiple sections, and in order to enable the water conveying pipe 31 and the water pump 32 to slide inside the track channel steel 24, the first end water conveying pipe 31 and the water pump 32 connected thereto are arranged as a group, and the multiple groups of water conveying pipes 31 are sequentially arranged in the above order; Through the arrangement of the multiple water conveying pipes 31 and the multiple water pumps 32, the original long pipeline is segmented, which is convenient for adjusting the water inlet elevation of the water pump 32 according to actual needs. In addition, the water conveying pipe 31 can be installed and recycled on the bagged concrete slope 11 in a sliding manner, reducing the underwater work of the workers during installation and recycling, thereby reducing the difficulty of installation, maintenance and pipeline maintenance; Before placing the water conveying pipe 31 and the water pump 32 inside the track channel steel 24, the workers need to weld support angle steels 41 and support channel steels 42 at both ends of each group of water conveying pipes 31 and water pumps 32, respectively, that is, two groups of support angle steels 41 are located at the ends of the water conveying pipe 31 and the water pump 32 away from each other. Subsequently, the support angle steels 41 and the support channel steels 42 are welded together through the tie rod angle steel 43, and the stability of the support angle steels 41 and the support channel steels 42 supporting the water conveying pipe 31 and the water pump 32 is improved through the tie rod angle steel 43; Subsequently, the ends of the support angle steels 41 and the support channel steels 42 are welded with the connecting angle steel 44, and the slide block 45 is fixed and installed on the bottom surface of the connecting angle steel 44 through bolts, so that the bottom surface of the slide block 45 is in contact with the inner surfaces of the two track channel steels 24, and the multiple water conveying pipes 31 and the water pump 32 can stably slide inside the track channel steel 24; At the same time, when the slider 45 slides inside the track channel steel 24, the stopper 46 provided on the slider 45 also slides with it, and during the sliding process, the baffle 1 47 and the baffle 2 48 assist, so that the slider 45 can slide stably; During the above process, due to the symmetrical arrangement of the support channel steel 42, the support angle steel 41, the connecting angle steel 44 and the slider 45 at both ends of each set of water delivery pipes 31 and water pumps 32, the multiple sections of water delivery pipes 31 and water pumps 32 in the track channel steel 24 can all remain in a horizontal state and can slide within the movable track formed by the multiple sections of track channel steel 24; After the first section of the water delivery pipe 31 and the water pump 32 are installed, the staff needs to assemble multiple sections of the water delivery pipe 31 to form a stable water vapor delivery channel in the track channel steel 24. Therefore, the ports of two adjacent groups of water delivery pipes 31 and water pumps 32 need to be fixed and installed; It should be noted that, referring to Figure 1 The water vapor delivery pipeline composed of the leveling I-steel 21, the water delivery pipe 31 and the water pump 32 can be provided with multiple groups according to the needs of the project; In the prior art, bolts and other fixing methods are often used to install the ports of the two groups of water delivery pipes 31, which takes a lot of time to install and disassemble. Therefore, when the above device installs the two adjacent groups of water delivery pipes 31, the limiting ring 51 fixedly installed on the outer surface of the water delivery pipe 31 will move toward the positioning ring 54 fixedly connected to the outer surface of the port of the adjacent water delivery pipe 31. At this time, the interference rods 52 fixedly connected to the outer surface of the limiting ring 51 in a circular array will move toward the positioning ring 54, so that the interference rods 52 are inserted into the through grooves provided in the positioning ring 54 until the end of the interference rod 52 away from the limiting ring 51 contacts the outer surface of the clamping block 55. During the above process, the limit spring 53 sleeved on the outer surface of the contact rod 52 is squeezed by the limit ring 51 and the positioning ring 54 and is in a compressed state. Moreover, since the weight of the clamping block 55 near the positioning ring 54 is greater than that of the clamping block 55 near the limit ring 51, in the initial state of the clamping block 55, the end thereof near the positioning ring 54 rotates with the rotation connection point between the clamping block 55 and the positioning ring 54 as the fulcrum, thereby presenting a state in which one end is higher than the other end. As the interfering rod 52 and the clamping block 55 come into contact with one end of the positioning ring 54, the clamping block 55 will deflect with its connection point with the positioning ring 54 as a fulcrum, so that its other end approaches the direction of the limiting ring 51. The above process continues as the water delivery pipe 31 is inserted into the water pump 32 until the clamping block 55 is engaged with the limiting ring 51, fixing the position of the limiting ring 51. In this way, the two sets of adjacent water delivery pipes 31 and the ends of the water pump 32 are fixedly installed by the limiting ring 51, the clamping block 55 and the positioning ring 54. It should be noted that the connection between the delivery water pipe 31 and the water pump 32 and the sealing ring provided between the adjacent delivery water pipes 31 are all prior art, so here is not much redundant.

[0029] By limiting the ring 51, the contact round rod 52, the positioning ring 54 and the clamping block 55, the adjacent delivery water pipe 31 and the water pump 32 can be quickly connected, and the two can be quickly disassembled under the condition of stable connection, thereby shortening the maintenance time of the delivery water pipe 31 during maintenance; After the multi-section delivery water pipe 31 and the water pump 32 are installed, the worker installs the butterfly valve 33 in the last delivery water pipe 31, and installs the telescopic pipe 34 away from the inside of the delivery water pipe 31, which is convenient for adjusting the length of the whole pipe. After installation, the other end of the telescopic pipe 34 is fixedly installed with the connecting pipe 39, and the connecting pipe 39 is arranged to fit the surface of the mold bag concrete slope 11. Finally, the end of the connecting pipe 39 away from the telescopic pipe 34 is buried in the grounding pipe after being erected across the river. It should be noted that the height of the pipe bottom of the connecting pipe 39 needs to be higher than the highest water level of the river; At the same time, in the above process, the worker needs to install the breathing valve 36 on the outer surface of the connecting pipe 39, and install the diaphragm reinforced concrete pipe 35 between the telescopic pipe 34 and the breathing valve 36 outside the connecting pipe 39, and fix the diaphragm reinforced concrete pipe 35 with the mold bag concrete slope 11. Then, the reinforced concrete pier 38 is fixedly installed at the end of the connecting pipe 39, and the reinforced concrete pier 38 is fixedly installed with the mold bag concrete slope 11. Then, the buried reinforced concrete pipe 37 is fixedly installed between the reinforced concrete pier 38 and the breathing valve 36 outside the connecting pipe 39, and the buried reinforced concrete pipe 37 is fixedly installed with the mold bag concrete slope 11; In the above device, the worker opens the breathing valve 36 and the butterfly valve 33, and transports the water flow in the river through the multiple water pumps 32, multiple delivery pipes and connecting pipes 39; In order to facilitate the subsequent maintenance of the water pump 32 and the delivery pipe, after the connection between one of the delivery pipes connected with the connecting pipe 39 is removed, the delivery pipe and the water pump 32 can be removed from the inside of the rail channel steel 24 by the external lifting machine. Since the delivery pipe and the water pump 32 are provided in multiple groups, each group of delivery pipe and water pump 32 can be directly disassembled and maintained after being pulled out of the rail channel steel 24. It should be noted that the connection between the adjacent delivery water pipe 31 and the water pump 32 only needs to make the clamping block 55 and the outer surface of the limiting ring 51 separate, so that the two can be separated; Through the setting of the multi-section conveying pipeline, the plurality of water pumps 32 and the connecting pipeline 39, when taking water, the water taking height can be increased, thereby reducing the occurrence of the water pump 32 suction riverbed sand, and being beneficial to the long-term use of the water pump 32; Through the setting of the formwork bag concrete protection slope 11, the slide rail installation base surface composed of the track channel steel 24 can be formed, thereby without cofferdam dry water construction, reducing the construction difficulty and reducing the construction investment.

[0030] It should be noted that, in this document, the terms such as first and second are used merely to distinguish one entity or operation from another, and do not necessarily require or imply that these entities or operations exist in any actual relationship or order. Moreover, the terms "include", "contain" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements not only includes those elements, but also includes other elements not explicitly listed or inherent to such process, method, article or equipment. Without more limitations, the element defined by the statement "including a" does not exclude the existence of other identical elements in the process, method, article or equipment including the element.

[0031] Although the embodiments of the present application have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present application, and the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. An adjustable pipe support device for water conservancy projects, comprising a bagged concrete slope protection (11), the bagged concrete slope protection (11) being cast and formed on the surface of a soil layer, characterized in that: It also includes a limiting track assembly arranged on the mold bag concrete slope protection (11); The limiting track assembly comprises a leveling I-beam (21) symmetrically arranged in parallel on the upper surface of the mold bag concrete slope protection (11), wherein the leveling I-beam (21) is provided in two groups, wherein a plurality of leveling I-beams (21) in the two groups of leveling I-beams (21) are equidistantly arranged, and expansion anchor bolts (22) are fixedly installed equidistantly inside the leveling I-beam (21), and the upper surfaces of the expansion anchor bolts (22) are fixedly installed with limiting angle steels (23) by bolts, and a track channel steel (24) is welded between the two limiting angle steels (23), and the outer surfaces of the ends of the track channel steel (24) are welded with a connecting beam channel steel (26), and the outer surface of the connecting beam channel steel (26) is welded with a clamping plate (27), and the clamping plate (27) is welded with a steel pipe pile (28) at one end away from the connecting beam channel steel (26).

2. The adjustable pipe support device for water conservancy projects according to claim 1, characterized in that: The leveling I-beam (21), the expansion anchor (22), the limiting angle steel (23) and the track channel steel (24) are all arranged in an inclined manner, and the leveling I-beam (21), the expansion anchor (22), the limiting angle steel (23) and the track channel steel (24) are all kept parallel to the inclined plane of the mold bag concrete slope protection (11), the expansion anchor (22) is far away from the end of the leveling I-beam (21) and extends into the interior of the mold bag concrete slope protection (11), the two limiting angle steels (23) are arranged axially symmetrically with reference to the central axis of the mold bag concrete slope protection (11), and the two track channel steels (24) are arranged axially symmetrically with reference to the central axis of the mold bag concrete slope protection (11).

3. The adjustable pipe support device for water conservancy projects according to claim 1, characterized in that: The interior of the positioning plate (27) is fitted with the outer surface of the track channel steel (24), and the connecting beam channel steel (26) and the positioning plate (27) together form a box-type positioning device. The bottom end of the steel pipe pile (28) penetrates the mold bag concrete slope protection (11) and extends into the soil layer.

4. The adjustable pipe support device for water conservancy projects according to claim 1, characterized in that: It also includes a conveying assembly arranged on the mold bag concrete slope protection (11); The conveying assembly includes a water delivery pipe (31) equidistantly arranged inside the track channel steel (24), a water pump (32) is arranged between adjacent water delivery pipes (31), a butterfly valve (33) is fixedly installed at one end of the water delivery pipe (31) located inside the vertically higher end of the track channel steel (24), a telescopic pipe (34) is fixedly installed at one end of the butterfly valve (33) away from the water delivery pipe (31), a connecting pipe (39) is fixedly installed at one end of the telescopic pipe (34) away from the butterfly valve (33), a embankment-penetrating reinforced concrete pipe (35) is fixedly installed on the outer surface of one end of the connecting pipe (39) close to the telescopic pipe (34), a breathing valve (36) is fixedly installed inside the connecting pipe (39), a buried reinforced concrete pipe (37) is fixedly installed on the outer surface of one end of the connecting pipe (39) away from the telescopic pipe (34), and a reinforced concrete pier (38) is fixedly installed at the bottom of one end of the connecting pipe (39) away from the telescopic pipe (34).

5. The adjustable pipe support device for water conservancy projects according to claim 4, characterized in that: The reinforced concrete pipe (35) passing through the embankment and the buried reinforced concrete pipe (37) are both arranged on the upper surface of the bagged concrete slope protection (11) and fixedly installed with the upper surface of the bagged concrete slope protection (11). The bottom end of the reinforced concrete pier (38) passes through and extends into the interior of the bagged concrete slope protection (11).

6. The adjustable pipe support device for water conservancy projects according to claim 4, characterized in that: It also includes a sliding component arranged on the outer surface of the water delivery pipe (31) and the water pump (32); The sliding assembly includes a support angle steel (41) fixedly welded to the outer surface of both ends of the water delivery pipe (31), a support channel steel (42) welded and fixed to the outer surface of both ends of the water pump (32), a pull rod angle steel (43) welded to the outer surface of both sides of the support angle steel (41) and the support channel steel (42), a connecting angle steel (44) welded to the outer surface of the end of the support angle steel (41) away from the water delivery pipe (31) and the outer surface of the end of the support channel steel (42) away from the water pump (32), a slider (45) is fixedly installed on the outer surface of the bottom end of the connecting angle steel (44) by bolts, a stopper (46) is fixedly installed on the outer surface of one side of the slider (45), two partition plates (47) are provided on the side of the stopper (46) away from the slider (45), and a partition plate (48) is welded and fixed between the two partition plates (47).

7. The adjustable pipe support device for water conservancy projects according to claim 6, characterized in that: The supporting channel steel (42) is symmetrically arranged on both sides of the water delivery pipe (31) and the water pump (32) along the central axis of the water delivery pipe (31). The two connecting angle steels (44) are respectively arranged on the outer surfaces of the water delivery pipe (31) and the water pump (32) and are in contact with the outer surfaces of the water delivery pipe (31) and the water pump (32). The slider (45) is arranged between the two track channel steels (24) and is slidably connected to the inner wall of the track channel steel (24). The partition plate (47) is fixedly installed by bolts and the block (46). The partition plate (47) is slidably connected to the inside of the track channel steel (24).

8. The adjustable pipe support device for water conservancy projects according to claim 4, characterized in that: It also includes a clamping assembly arranged between adjacent water delivery pipes (31); The clamping assembly comprises a limiting ring (51) fixedly mounted on the outer surface of one of the two adjacent water delivery pipes (31), a side of the limiting ring (51) being fixedly connected to a resisting round rod (52), an outer surface of the resisting round rod (52) being sleeved with a limiting spring (53), and an outer surface of the other water delivery pipe (31) being fixedly connected to a positioning ring (54), an outer surface of the positioning ring (54) being rotatably connected to a clamping block (55).

9. The adjustable pipe support device for water conservancy projects according to claim 8, characterized in that: The resisting rod (52), the limiting spring (53) and the clamping block (55) are all centrally symmetrically arranged with the center of the limiting ring (51) as a reference. The resisting rod (52) is arranged between the limiting ring (51) and the positioning ring (54). The positioning ring (54) is provided with through holes of a size and a number that are adapted to the resisting rod (52). The end of the clamping block (55) away from the positioning ring (54) is clamped to the outer surface of the limiting ring (51). The weight of the end of the clamping block (55) close to the positioning ring (54) is greater than that of the end of the clamping block (55) close to the limiting ring (51).

Citation Information

Patent Citations

  • Mold bag concrete slope protecting structure and rebar cage with anchoring structure

    CN107724334A

  • Pipe jacking stable construction structure and construction method thereof

    CN113294161A

  • Water conservancy project slope treatment drainage pipeline integrated energy-saving construction technology

    CN119663795A

  • Auxiliary tool for concrete pipe support construction

    CN215522211U

  • Methanation product gas pipeline spanning slope protection device

    CN217177659U