A novel trailing suction hopper dredger with automatically adjustable energy dissipation device height and its loading operation method.
By using an adjustable height energy dissipation device and an automatic adjustment method, the problem of low loading efficiency of trailing suction hopper dredgers under different working conditions has been solved, achieving efficient silt loading and environmental protection.
Patent Information
- Application Number
- CN202510874828.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-10-10
AI Technical Summary
The energy dissipation devices of existing trailing suction hopper dredgers are designed in a fixed manner, which cannot adapt to complex working conditions with different soil types and slurry concentrations, resulting in low loading efficiency and adverse impacts on the construction water environment.
An adjustable-height energy dissipation device is provided. Through an automatic adjustment optimization method, combined with CFD software and neural network models, the height of the energy dissipation device is adjusted in real time to reduce sediment disturbance and overflow loss in the tank and improve loading efficiency.
It achieves efficient loading under different soil types and mud concentrations, reduces overflow losses and environmental impact, and improves construction efficiency.
Smart Images

Figure CN120889314B_ABST
Abstract
Description
[0001] This application is a divisional application of Chinese patent application "An Optimization Method for Automatic Height Adjustment of Energy Dissipation Device of a Trailing Suction Hoist Dredger", application number 202411411313.6 Technical Field
[0002] This invention belongs to the field of dredging engineering technology, and specifically relates to an automatic adjustment and loading method for the energy dissipation system of a trailing suction hopper dredger. Technical Background
[0003] Trailing suction hopper dredgers are the mainstay vessels in the dredging industry, playing a vital role in waterway dredging, land reclamation, and port maintenance. The mud hopper system is a crucial component of the trailing suction hopper dredger, responsible for loading dredged material into the hopper and flushing it to the shore. The loading process can be divided into two parts based on the characteristics of different stages: loading and overflow. Depending on the target soil properties, slurry (a mixture of water and sediment) continuously flows into the mud hopper through the inlet pipe. Some of the sediment settles at the bottom of the hopper under gravity, while the remaining sediment mixes with water and remains suspended. When the level of this water-sand mixture exceeds the height of the overflow pipe, varying degrees of overflow loss occur.
[0004] The efficiency of overflow loading for trailing suction hopper dredgers is directly related to the design and layout of their energy dissipation devices. Currently, most trailing suction hopper dredgers in China have fixed energy dissipation devices, which cannot be adjusted to reduce disturbance to the sediment inside the hopper caused by the incoming water flow under various complex working conditions such as different soil types and slurry concentrations. When the sediment particles are coarse, they settle quickly, and if the energy dissipation device is installed too low, it can easily clog the outlet. When the sediment particles are fine, if the energy dissipation device is installed too high, the fine sediment particles will be disturbed by the incoming water flow, causing most of them to remain suspended, increasing overflow losses, reducing loading efficiency, and adversely affecting the surrounding construction water environment. Summary of the Invention
[0005] To address the shortcomings of existing technologies, this invention provides an adjustable-height energy dissipation device for trailing suction hopper dredgers, an automatic height adjustment optimization method, and an onboard system. This enables automatic and flexible adjustment of the energy dissipation device height during the dredging process. By minimizing disturbance of sediment within the hopper and reducing overflow losses, it improves the flatness of sediment loading and hopper loading efficiency. This meets the needs of various working conditions, including different soil types, hopper concentrations, hopper flow rates, and hopper structural dimensions of the trailing suction hopper.
[0006] Technical solution
[0007] One objective of this invention is to provide a method for automatically adjusting and optimizing the height of the energy dissipation device of a trailing suction hopper dredger, comprising:
[0008] An adjustable-height energy dissipation device is constructed inside the hull of the process-driven suction dredger.
[0009] Step 2 determines the optimal energy dissipation height;
[0010] Step 1: Determine the core parameters using existing data related to trailing suction hopper dredger construction, geological survey reports of the area to be constructed, and soil condition data. Core parameters include: geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment movement. Details are as follows:
[0011] (1) The geometric model mainly includes: the structural dimensions of the mud tank, the dimensions of the transverse and longitudinal triangular tanks, the dimensions of the overflow equipment, the dimensions and height of the energy dissipation equipment, and the relative positions of the transverse and longitudinal triangular tanks and the energy dissipation overflow equipment to the mud tank;
[0012] (2) Boundary conditions include: the inlet boundary is the loading flow rate and loading mud concentration, the overflow boundary is the free outflow boundary, the upper boundary of the mud tank is the atmospheric pressure boundary, and the tank wall boundary is the wall boundary with a certain roughness material.
[0013] (3) Mesh conditions include: mesh range in the x, y, and z directions and cell mesh size.
[0014] (4) Initial conditions include: initial water level H0, and loading simulation duration T;
[0015] (5) Fluid motion parameters include: fluid temperature T, fluid viscosity μ, and fluid motion equation.
[0016] (6) The fluid motion equations are selected from the RNG k-ε equations based on the characteristics of the loading compartment, as follows:
[0017]
[0018] In the formula: k—turbulent kinetic energy;
[0019] u i — Velocity component;
[0020] x i y i —Coordinate components;
[0021] μ—molecular viscosity coefficient;
[0022] μ t — Turbulent viscosity coefficient;
[0023] G k —Turbulent kinetic energy generation term;
[0024] ε—Turbulent kinetic energy dissipation rate;
[0025] α k α ε —The Prandtl numbers for turbulence at k and ε;
[0026] Where C 1ε =1.42, η0=4.377, β=0.012;
[0027] in C 2ε =1.68.
[0028] The main parameters of sediment movement include sediment particle size, sediment density, sediment porosity, critical Shields number, underwater angle of repose, bedload coefficient, and scour coefficient, involving four forms of sediment movement: suspension, deposition, scour, and bedload. The following empirical formulas for sediment are used to automatically calculate the movement of each sediment particle during the simulation process.
[0029] The empirical formulas of Mastbergen and Von den Berg were used to calculate the sediment initiation and scouring process.
[0030]
[0031] In the formula, α refers to the entrainment coefficient, and n s The direction of the outward normal to the bed surface is θ, where θ refers to the Shield number of the sediment particles. cr The critical Shield number for sediment particles, g is the acceleration due to gravity, μ is the dynamic viscosity of the fluid, and d is the velocity of the sediment. s Refers to the particle size of sediment, ρ s It is the density of sediment, ρ f It is the fluid density.
[0032] The Shield number θ of sediment particles is expressed as:
[0033]
[0034] In the formula, τ is the shear stress on the riverbed surface.
[0035] In the non-horizontal bed region, considering the influence of the sediment repose angle, the critical Shields number correction value θ cr,i 'for
[0036]
[0037] In the formula, κ is the angle between the vertical line of the sedimentary surface and the gravitational acceleration g; φ is the angle of repose of the sediment; and ψ is the angle between the upslope direction and the flow direction of the fluid.
[0038] use Equati's empirical formulas are used to calculate and simulate the bedload transport process.
[0039]
[0040] In the formula, the thickness δ of the bedload sediment is calculated as follows:
[0041]
[0042] Therefore, the formula for calculating the bedload transport velocity is:
[0043]
[0044] Step 2: Conduct loading process simulation and prediction, which includes two steps: establishing a loading numerical model and loading simulation and prediction.
[0045] Establishing a loading numerical model: This refers to using CFD software (existing technology) to establish a numerical model that can simulate the loading process based on the input core parameters, so as to realize the loading simulation function.
[0046] Loading simulation prediction: Using the above-mentioned loading numerical model, numerical simulations were conducted under different energy dissipation device height positions to simulate the entire loading process. This resulted in simulation predictions of changes in loading volume, earthwork volume, total overflow loss, and sediment height within the tank over loading time. Multiple sets of numerical simulation calculation results corresponding to different energy dissipation device height positions were obtained. The energy dissipation device height position needs to be manually set.
[0047] The numerical simulation results also include: q t (3D mesh point cloud of flow rate at time t); ρ t (3D mesh point cloud of density at time t); v x (3D mesh point cloud of the x-direction velocity component at time t); v y (3D mesh point cloud of the y-direction velocity component at time t). The numerical calculation results are provided to step 3.
[0048] Step 3: Based on the numerical simulation results, the evaluation criteria are set according to four indicators: loading capacity, earthwork volume, overflow loss, and sediment flatness, to obtain the recommended height for the energy dissipation device.
[0049] In multiple sets of numerical simulation results, different energy dissipation device heights correspond to different loading capacity, earthwork volume, overflow loss, and sediment flatness. An evaluation criterion order was established, and the recommended optimal design value for the energy dissipation device height was determined based on this order (first gradient, second gradient). Typically, loading capacity, earthwork volume, and overflow loss, representing the tank loading efficiency, are used as the first gradient criterion, while sediment flatness is used as the second gradient criterion. Specifically, larger loading capacity and earthwork volume, smaller overflow loss, and higher sediment flatness indicate a better impact of the energy dissipation device height on the loading effect under that working condition.
[0050] Preferably, if the optimization objectives are set as maximizing the smoothness α of the sediment and maximizing the earthwork volume D, then the objective function of the optimization model is:
[0051]
[0052] max D = max∑ΔQ i ·Δt·ρ (16)
[0053] Set constraints (xt):
[0054] X = {x1, x2, x3, ..., x} i} (17)
[0055] Where Δt is the length of the time period for calculating the volume of deposited soil; ΔQ i ρ is the outflow rate during the time interval Δt; ρ is the outflow concentration during the time interval Δt; x i It belongs to [0,H], where H represents the mud chamber height, x (it) As a parameter for calculating smoothness, it represents the height of sediment measured at sampling location i at time t. This represents the average height of sediment deposited along the longitudinal centerline of the mud chamber.
[0056] t <T (18)
[0057] In the formula, T represents the initially set maximum time.
[0058] Set the height of multiple energy dissipation devices, and calculate q using the numerical calculation model in step 2 for each device. t ρ t v x and v y Then, the flatness of the sediment and the volume of earthwork are calculated. Based on the above optimization objectives (optimal flatness and maximum volume of earthwork), the best set is selected, and the corresponding energy dissipation device height is the optimal energy dissipation device height.
[0059] Taking into account both time and computing power, and based on relevant numerical calculation and prediction experience, it is recommended that the number of energy dissipation device height groups be 12 to 20, with an interval of 0.25 to 0.5m between each group, and a height variation range of 5 to 6m.
[0060] Process 3: Loading operations at the optimal energy dissipation height
[0061] Step 4: Based on the optimal energy dissipation device height obtained in Step 3, adjust the hydraulic struts of the adjustable height energy dissipation device to raise or lower the energy dissipation device height to the optimal height.
[0062] Furthermore, in step 3, to avoid complex numerical calculations, a neural network is introduced to predict the height of sediment deposition and the volume of earthwork. (See below:)
[0063] A sediment height prediction model was established to predict sediment height, as follows:
[0064] The calculation of X is based on the following prediction model established by X(t) value and the initial and boundary conditions of numerical simulation:
[0065] Input value: q t ρ is the 3D grid point cloud of the flow rate at time t; t A 3D mesh point cloud with density at time t; v x A three-dimensional mesh point cloud of the velocity component in the x-direction at time t; v y The three-dimensional grid point cloud represents the y-direction velocity component at time t.
[0066] Output value: X(t+Δt) represents the sediment height matrix of the smoothness section calculated at the next time step Δt, serving as the label for the sediment height prediction model. The three-dimensional location of the energy dissipation device is set to 0; this setting characterizes the spatial features of the energy dissipation device.
[0067] Extract q from numerical simulation calculations at time intervals of Δt. t ρ t v x v y q for each time t ρ t v x v y Three-dimensional mesh data is subjected to convolutional kernel feature extraction to generate a feature matrix. The values used to calculate the sediment height inside the chamber at time t+Δt are combined into a label matrix X, which is then used to train the network. Through the above operations, a sediment height prediction model for calculation points on the flatness calculation plane is obtained by training with numerical simulation data.
[0068] During the training phase, the input quantities and labels are calculated by the loading process simulation prediction model in step 2; after training is completed, the input quantities and labels are calculated based on the measured q. t ρ t v x v y Predicting the height of sediment at each point reflects the smoothness of the sediment.
[0069] An earthwork volume prediction model is established to predict the earthwork volume inside the chamber, as follows:
[0070] Similarly, dt represents the 3D grid point cloud of the earthwork volume at time t, and d(t+Δt) represents the earthwork volume calculated at the next time Δt as a label term for the earthwork volume prediction model. Establish q at time t. t ρ t v x v yA network of data and three-dimensional data of the earthwork volume inside the mud chamber at time t+Δt is used to train an earthwork volume prediction model.
[0071] Based on the order of the two evaluation criteria, earthwork volume and flatness, set according to the prediction model, the recommended optimal height is obtained.
[0072] The second objective of this invention is to provide a height optimization system for an onboard energy dissipation device of a trailing suction hopper dredger, characterized in that it includes a core parameter input module, a loading process simulation and prediction module, a design optimization output module, and an automatic height adjustment module. These software modules are embedded in and called by the onboard loading control system.
[0073] Among them, the core parameter input module:
[0074] The core parameters include geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. The geometric model includes: the structural dimensions of the mud hopper, the dimensions of the transverse and longitudinal triangular hoppers, the dimensions of the overflow equipment, the dimensions and height of the energy dissipation equipment, and the relative positions of the transverse and longitudinal triangular hoppers and the energy dissipation overflow equipment to the mud hopper. The boundary conditions include: the inlet boundary being the loading flow rate and the loading mud concentration; the overflow boundary being the free outflow boundary; the upper boundary of the mud hopper being the atmospheric pressure boundary; and the hopper wall boundary being the wall boundary with a certain roughness material. The mesh conditions include: the mesh range in the x, y, and z directions and the unit mesh size. The initial conditions include the initial water level H0 and the hopper loading simulation duration t. The fluid motion parameters include fluid temperature T, fluid viscosity μ, and fluid motion equations. The sediment motion parameters mainly include sediment particle size, sediment density, sediment porosity, critical Shields number, underwater angle of repose, bedload coefficient, and scour coefficient, involving four motion forms: sediment suspension, sediment deposition, sediment scour, and sediment bedload.
[0075] Among them, the loading process simulation and prediction module:
[0076] Using the parameters input into the core parameter input module, numerical calculations are performed to simulate the loading process under different operating conditions. The loading process simulation and prediction module implements the simulation and prediction of the loading process, which includes two parts: establishing a loading numerical model and loading simulation and prediction.
[0077] Establish a numerical model for loading: Based on the input core parameters, use CFD software (existing technology) to establish a numerical model that can simulate the loading process, so as to realize the loading simulation function.
[0078] Loading simulation prediction: Using the above-mentioned loading numerical model, numerical simulations were conducted under different energy dissipation device height positions to simulate the entire loading process. This resulted in simulation predictions of changes in loading volume, earthwork volume, total overflow loss, and sediment height within the tank over loading time. Multiple sets of numerical simulation calculation results corresponding to different energy dissipation device height positions were obtained. The energy dissipation device height position needs to be manually set.
[0079] The numerical simulation results also include: q t (3D mesh point cloud of flow rate at time t); ρ t (3D mesh point cloud of density at time t); v x (3D mesh point cloud of the x-direction velocity component at time t); v y (3D mesh point cloud of the y-direction velocity component at time t). The numerical calculation results are provided to the design optimization output module.
[0080] This module can display various data during the calculation process in real time and present the simulation results in a visual manner within the 3D model. Users can gain a more intuitive and in-depth understanding of the loading process by viewing the specific flow rate, concentration, and earthwork volume outputs under various working conditions. This helps users analyze various phenomena during the loading process, such as flow rate distribution and sediment concentration changes, thereby optimizing the loading plan.
[0081] Among them, the design optimization output module:
[0082] Based on the numerical simulation results output by the loading process simulation and prediction module, the system sets the evaluation criteria order using four indicators: loading volume, earthwork volume, overflow loss, and sediment flatness, to obtain the optimized recommended height of the energy dissipation device. Users can click to select the order of evaluation criteria (loading efficiency, flatness) according to their actual needs. The system will automatically output the optimized recommended value of the energy dissipation device height based on the evaluation criteria selected by the user.
[0083] Specifically, in multiple sets of numerical simulation results, different energy dissipation device heights correspond to different mud chamber loading capacity, earthwork volume, overflow loss, and sediment smoothness. An evaluation criterion order is set, and recommended optimal design values for the energy dissipation device height are generated based on this order (first gradient, second gradient). Typically, loading efficiency, represented by loading capacity, earthwork volume, and overflow loss, is used as the first gradient criterion, and sediment smoothness as the second gradient criterion. Higher loading capacity and earthwork volume, lower overflow loss, and higher mud chamber smoothness indicate a better impact of the energy dissipation device height on the loading effect under that working condition.
[0084] Among them, the automatic height adjustment module:
[0085] Based on the recommended optimized height of the energy dissipation device output by the design optimization output module, a control signal is sent via the shipboard loading control system to automatically control the hydraulic struts on the adjustable-height energy dissipation device. By precisely controlling the extension and retraction of the hydraulic struts, the height of the energy dissipation device can be automatically and accurately adjusted. Alternatively, users can manually determine the soil conditions of the construction area based on existing geological survey data and, based on engineering experience, input the appropriate energy dissipation device height through the loading control system. Upon receiving the instruction, the system sends a control signal to the hydraulic struts, enabling manual adjustment of the energy dissipation device's height. This adjustment method is more flexible and can adapt to different construction environments and needs.
[0086] The beneficial effect of this invention is that it provides an automatic height adjustment and optimization method and system for the energy dissipation device of a trailing suction hopper dredger. During construction, the height of the energy dissipation device can be automatically and precisely adjusted in real time according to different soil types and slurry concentration requirements. The energy dissipation device is neither too low, causing rapidly settling coarse particles of slurry to clog the outlet, nor too high, causing the incoming water flow to disturb the slurry and increase the overflow loss of suspended slurry. By precisely controlling the height of the energy dissipation device, the construction efficiency of the trailing suction hopper dredger is improved, while the adverse impact of overflow into the construction water environment is reduced, demonstrating its engineering application value. Attached Figure Description
[0087] Figure 1 This is a front view of the adjustable height energy dissipation device of the trailing suction hopper dredger in an embodiment.
[0088] Figure 2 This is a side view of the adjustable height energy dissipation device of the trailing suction hopper dredger in an embodiment.
[0089] Figure 3 This is a schematic diagram of the retractable pipe structure in an embodiment.
[0090] Figure 4 This is a schematic diagram of the hydraulic support rod structure for lifting, as shown in the embodiment.
[0091] Figure 5 This is a 3D model of the mud hopper of a trailing suction hopper dredger, as shown in the example.
[0092] Figure 6 The mesh division of the 3D model of the mud hopper of the trailing suction hopper dredger is shown in the example.
[0093] Figure 7 A three-dimensional numerical simulation diagram of the mud hopper of a trailing suction hopper dredger, as shown in the example.
[0094] Figure 8 Here is a flowchart of the sediment height prediction model for an example;
[0095] Figure 9 Here is a flowchart of the earthwork volume prediction model for an example;
[0096] Figure 10 Here is a flowchart illustrating the optimized height prediction process for energy dissipation equipment, as shown in the example.
[0097] Figure 11 A simple artificial neural network prediction model for optimizing the height of energy dissipation equipment;
[0098] Figure 12 The system software module for the energy dissipation device on the trailing suction hopper dredger has been optimized.
[0099] Figure 13 This refers to the highly automated adjustment process of the energy dissipation device of the trailing suction hopper dredger during construction.
[0100] Figure Labels
[0101] 1-Retractable main pipe, 2-Horizontal pipe, 3-Connecting steel plate, 4-Hydraulic support rod, 5-Internal crossbeam of mud tank, 6-Side wall of mud tank;
[0102] 11-Inner pipe, 12-Outer pipe, 13-Fill material, 14-Limit block, 15-Main pipe connection flange;
[0103] 21 - Outlet port, 22 - Horizontal pipe connection flange;
[0104] 41-Rear cylinder head, 42-Cylinder barrel, 43-Piston, 44-Piston rod, 45-Guide sleeve, 46-Sealing ring, 47-Front cylinder head. Detailed Implementation
[0105] The adjustable height energy dissipation device, automatic height adjustment optimization method and system of the trailing suction hopper dredger of the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0106] Preparation process
[0107] Structural modifications to trailing suction hopper dredgers include the adjustment of height energy dissipation devices. Figures 1 to 4 As shown.
[0108] The height adjustment of the energy dissipation device is embedded in and controlled by the shipboard loading control system to adjust in a timely manner for optimal loading operations.
[0109] The adjustable height energy dissipation device of the trailing suction hopper dredger consists of a telescopic main pipe 1, a transverse pipe 2, a connecting steel plate 3, hydraulic struts 4, and a crossbeam 5 inside the mud hopper. The crossbeam 5 inside the mud hopper is fixed to the side wall 6 of the mud hopper by welding. Four lifting hydraulic struts 4 are fixed to the crossbeam 5 inside the mud hopper by bolts. The connecting steel plate 3 is placed above the hydraulic struts 4 and fixed to the upper end of the hydraulic struts 4 by bolts. The connecting steel plate 3 is connected to the outer pipe 12 of the telescopic main pipe 1 by welding.
[0110] The telescopic main pipe 1 is a sleeve-type structure. The inner pipe 11 and the outer pipe 12 are sealed by filler material 13 without affecting relative sliding. The limiting block 14 restricts the extension and retraction of the telescopic main pipe 1. Under the action of the hydraulic support rod 4, the telescopic main pipe 1 can freely extend and retract within a certain limit. The outer pipe 12 is connected to the transverse pipe 2 through the main pipe connecting flange 15.
[0111] The transverse pipe 2 is divided into three parts: left, middle and right, which are connected in sequence by flanges. The transverse pipe 2 has a total of 8 outlets 21, which are used for energy dissipation loading of mud.
[0112] The hydraulic strut 4 consists of a rear cylinder head 41, a cylinder 42, a piston 43, a piston rod 44, a guide sleeve 45, a sealing ring 46, and a front cylinder head 47. The rear cylinder head 41 is bolted to the crossbeam 5 inside the mud tank and simultaneously seals the rear of the cylinder 42. The piston 43 is subjected to force inside the cylinder, which is transmitted to the connecting steel plate 3 above through the piston rod 44. The guide sleeve 45 supports and ensures the coaxiality of the piston rod 44 and the cylinder 42. The sealing ring 46 seals the front cylinder head 46 and the piston rod 44 to prevent water, mud, and other contaminants from affecting the normal operation of the components inside the cylinder 42 during the loading process.
[0113] When adjusting the height of the energy dissipation device, the shipboard loading control system controls the lifting and lowering of the four hydraulic struts 4 in the embodiment, which in turn drives the outer pipe 12 and the transverse pipe 2 of the telescopic main pipe 1 to rise or fall through the connecting steel plate 3. The mud is then discharged into the mud tank along the inner pipe 11, the outer pipe 12, the transverse pipe 2, and the outlet 21 to carry out the loading operation.
[0114] Example 1
[0115] Optimization Method for Automatic Height Adjustment of Energy Dissipation Device in Trailing Suction Hoist Dredgers
[0116] Process one involves modifying the facilities of the trailing suction hopper dredger, referring to the preparatory work. Details are omitted.
[0117] Process two involves determining the optimal adjustment height value, including the following steps:
[0118] Step 1: Determine the core parameters, including key parameters in six parts: geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. These parameters are used to automatically build a 3D model of the mud tank system and set the scenario constraints for the loading simulation.
[0119] (1) Geometric model parameters, including setting the structural dimensions of the mud hopper, the dimensions of the transverse and longitudinal triangular hoppers, the dimensions of the overflow equipment, the dimensions of the energy dissipation equipment, and the positions of the transverse and longitudinal triangular hoppers and the energy dissipation overflow equipment relative to the mud hopper, are used to establish a three-dimensional structural model of the mud hopper system. The model is established as follows: Figure 5 As shown.
[0120] (2) Boundary conditions include setting the inlet boundary as the loading flow rate and loading mud concentration, selecting the overflow boundary as the free outflow boundary, the upper boundary of the mud tank as the atmospheric pressure boundary, and the tank wall boundary as the wall boundary with a certain roughness material.
[0121] (3) Figure 6 As shown, the 3D model is meshed. Mesh conditions include setting the total mesh range in three directions to include the mud hull system structure model, and setting the element mesh size to appropriate length, width, and height dimensions for identifying the mud hull structure in the simulation calculation;
[0122] (4) Initial conditions include setting the initial water level and the duration of the loading simulation;
[0123] (5) Fluid motion parameters include setting fluid temperature and fluid viscosity, and selecting the RNG k-ε equation as the fluid motion equation;
[0124] (6) Sediment transport parameters include setting sediment particle size, sediment density, sediment porosity, critical Shields number, underwater angle of repose, bedload coefficient, and scour coefficient. The sediment initiation and scour processes are calculated using empirical formulas from Mastbergen and Von den Berg. Equati's empirical formulas are used to calculate and simulate the bedload transport process.
[0125] Step 2: Establish a numerical model for loading and perform loading simulation predictions;
[0126] Establishing a numerical model for loading: This refers to using CFD software to establish a numerical model that can simulate the loading process based on the input core parameters, so as to realize the loading simulation function.
[0127] Loading simulation prediction: Using the above loading numerical model, set different working conditions for the height position of the energy dissipation device, and conduct numerical simulation to simulate the entire loading process. Realize the simulation prediction of the changes in loading volume, earthwork volume, total overflow loss and sediment height in the tank with loading time, and obtain multiple sets of numerical simulation calculation results corresponding to different height positions of the energy dissipation device; the height position of the energy dissipation device needs to be set manually.
[0128] The numerical simulation results also include: q t (3D mesh point cloud of flow rate at time t); ρ t (3D mesh point cloud of density at time t); v x (3D mesh point cloud of the x-direction velocity component at time t); v y (3D mesh point cloud of the y-direction velocity component at time t); the results of the numerical calculation are provided to step 3.
[0129] This embodiment utilizes CFD software, based on the input core parameters, and employs structured multi-block mesh technology and the finite volume method to automatically establish a numerical model of the loading and unloading process, achieving simulation of the loading and unloading process over time. The simulation results are as follows: Figure 7 As shown. By setting different energy dissipation device heights, the loading control system sets different sediment movement parameters based on the geological survey report of the construction area and referring to existing construction experience data for different soil types, and performs loading simulation calculations under multiple working conditions.
[0130] Step 3: Optimize the output of the energy dissipation device.
[0131] If the optimization objectives are set as maximizing the smoothness α of the sediment and maximizing the earthwork volume D, then the objective function of the optimization model is:
[0132]
[0133] max D = max∑ΔQ i ·Δt·ρ (16)
[0134] Set constraints (xt):
[0135] X = {x1, x2, x3, ..., x} i} (17)
[0136] Where Δt is the length of the time period for calculating the volume of deposited soil; ΔQ i ρ is the outflow rate during the time interval Δt; ρ is the outflow concentration during the time interval Δt.
[0137] x i It belongs to [0,H], where H represents the mud chamber height, x (it) As a parameter for calculating smoothness, it represents the height of sediment measured at sampling location i at time t. This represents the average height of sediment deposited along the longitudinal centerline of the mud chamber.
[0138] t <T (18)
[0139] In the formula, T represents the initially set maximum time.
[0140] Set the height of multiple energy dissipation devices, and calculate q using the numerical calculation model in step 2 for each device. t ρ t v x and v y Then, the flatness of the sediment and the volume of earthwork are calculated. Based on the above optimization objectives (optimal flatness and maximum volume of earthwork), the best set is selected, and the corresponding energy dissipation device height is the optimal energy dissipation device height.
[0141] Optionally, the recommended design value for the energy dissipation device height can be determined based on the evaluation criteria (first-gradient, second-gradient) of four indicators: loading capacity, earthwork volume, overflow loss, and sediment flatness. Typically, loading efficiency, represented by loading capacity, earthwork volume, and overflow loss, is used as the first-gradient criterion, and sediment flatness as the second-gradient criterion. A higher loading capacity and earthwork volume, lower overflow loss, and higher sediment flatness indicate a better impact of the energy dissipation device height on the loading effect under that working condition.
[0142] Furthermore, in construction situations where the flatness of the loading compartment is highly critical, the order of evaluation criteria can be adjusted, with the flatness of the deposited sediment being used as the first priority.
[0143] In step 3, to avoid complex numerical calculations, a neural network is introduced to predict the height of sediment deposition and the volume of earthwork. (See below:)
[0144] Combination Figure 8 As shown, four variables are input into the input layer: qt (flow rate), ρt (density), vxt (x-direction velocity), and vyt (y-direction velocity). These input features are preprocessed by feature selection and standardization and then input into the target Transformer neural network model to obtain the predicted sediment height.
[0145] The target Transformer neural network model includes an Embedding Layer, Multi-head Attention, and Softmax (probability distribution output). The Embedding Layer vectorizes the input features, converting them into a vector representation suitable for network processing. This process maps high-dimensional input features to a low-dimensional vector space for subsequent processing. Multi-head Attention captures different feature information through multiple attention heads and integrates this information to weight the input features. Softmax calculates the probability distribution of each output based on the result of the multi-head attention mechanism.
[0146]
[0147] The output values are mapped to the range [0,1], and the sum of the probabilities of all outputs is 1, which helps the model learn the non-linear relationship between the input features and the output results. Finally, the predicted sediment deposition height sequence (x1,x2,...,x) is output through the output layer. n ).
[0148] The Transformer neural network model (sediment height prediction model) uses four input variables as training data and sediment height sequences as labels for training. After each iteration, the loss function is calculated using validation data and the labels, with mean squared error (MSE) as the loss function.
[0149]
[0150] In the formula, x i , These represent the sediment height obtained through iterative calculation and the actual sediment height used as a label value, respectively.
[0151] The model adjusts the network weights using the backpropagation algorithm to minimize the loss function. In each training iteration, the gradient of the loss function is calculated, and the network weights are updated until the model reaches the preset convergence condition, thus obtaining the target neural network model.
[0152] Combination Figure 9 As shown, four variables are input to the input layer: qt (flow rate), ρt (density), vxt (x-direction velocity), and vyt (y-direction velocity). The input features are preprocessed (standardized) before being fed into the network. The BatchNorm layer calculates the mean and variance of all values in the mini-batch, using these values to normalize each batch of data, ensuring a relatively stable distribution of the input to each layer. This accelerates training and improves model stability. The PointNet layer, a deep learning framework specifically designed for point cloud data, is used in this model to extract high-dimensional feature representations of the input features. The fully connected layer further processes the features extracted from the PointNet layer, mapping the high-dimensional features to the target output space, thereby enabling the prediction of earthwork volume.
[0153] Optionally, the present invention also provides another simpler and faster method for recommending optimal parameters for energy dissipation equipment height, combined with... Figure 10 The diagram illustrates the optimal height prediction process for energy dissipation equipment. This process comprises 10 parts: data input, data preprocessing, training and test set partitioning, neural network model building, forward propagation, loss function calculation, back propagation, parameter updating, model evaluation, and optimal value recommendation.
[0154] (1) Data input: As the starting point of the entire prediction model, the data such as qt (flow rate), ρt (density), vxt (x-direction velocity), vyt (y-direction velocity), and h (height of energy dissipation device) of the mud entering the mud chamber at time t are input in tabular form.
[0155] (2) Data Preprocessing: In this stage, the data described in (1) will be standardized. The earthwork volume D and the sediment smoothness α will be calculated, and a new parameter λ (0 < λ < 1) will be set. For each set of data, λD - (1 - λ)α will be calculated.
[0156]
[0157] D=∑ΔQ i ·Δt·ρ (4)
[0158] In the formula: Δt is the length of the time period for calculating the volume of deposited soil; ΔQ i ρ is the outflow rate during the time interval Δt; ρ is the outflow concentration during the time interval Δt.
[0159] (3) Training and test set partitioning: Data such as qt (flow rate), ρt (density), vxt (x-direction velocity), vyt (y-direction velocity), and h (energy dissipation device height) will be divided into training and test sets. The training set is used to train the model, and the test set is used to evaluate the model's performance. The partition ratio is set to 8:2 or 7:3.
[0160] (4) Neural network model construction: combined with Figure 11 The diagram shows a simple artificial neural network (MLP) model. The neural network consists of multiple layers of neurons (nodes), with each layer containing several neurons. The layer structure includes an input layer (receiving processed input data), hidden layers (performing complex calculations and extracting high-order features from the input data), and an output layer (producing the final prediction result, i.e., the objective function λD-(1-λ)α).
[0161] (5) Forward propagation: Data travels from the input layer through neurons in each layer, where activation functions are calculated and output, until the output layer. The calculation formula for each layer is as follows:
[0162] z (l) =W (l) a (l-1) +b (l) (5)
[0163] a (l) =σ(z) (l) (6) In the formula: l is the number of activation layers; W (l) b is the weight matrix; (l) a is the bias vector; (l) With a (l-1) These are the activation values for the current layer and the previous layer, respectively. In the input layer a, the corresponding input data such as qt (flow rate), ρt (density), vxt (x-direction velocity), vyt (y-direction velocity), and h (energy dissipation device height) can be used for calculation; σ is the activation function.
[0164] Furthermore, the activation function chosen is the ReLU function:
[0165] σ(z (l) ) = ReLU(z (l) ) = max(0, z (l) (7)
[0166] (6) Loss function calculation: The common mean squared error (MSE) is selected as the loss function:
[0167]
[0168] In the formula: y i For the true value, Let be the predicted value, where y = λD - (1 - λ)α, and n is the number of samples.
[0169] (7) Backpropagation: By calculating the gradient of the loss function with respect to each parameter, the parameters are updated to minimize the loss function. The gradient calculation formula is as follows:
[0170]
[0171] Where: δ (l) This is the error term, which is the difference between the network's predicted value and the actual label value.
[0172] (8) Parameter Update: Update the weight matrix and bias vector using the gradient descent optimization algorithm. The gradient descent update formula is as follows:
[0173]
[0174] In the formula: α is the learning rate.
[0175] (9) Model evaluation: The model performance is evaluated using the test set with metrics such as accuracy, precision, and recall.
[0176] (10) Optimal value recommendation: After the model training is completed, predictions can be made for the obtained input parameters qt (flow rate), ρt (density), vxt (x-direction velocity), vyt (y-direction velocity), and h (energy dissipation device height). In order to find the maximum value of the model, the model parameters are fixed, and for each parameter of each layer, the derivative is calculated using the chain rule to make them equal to zero, so as to obtain the extreme value candidates within a certain range, and the maximum value is selected. Backpropagation is then used to obtain the optimal energy dissipation device height h.
[0177] Process 3: Loading operations at the optimal energy dissipation height
[0178] Step 4: Based on the optimal energy dissipation device height obtained in Step 3, adjust the hydraulic struts of the adjustable height energy dissipation device to raise or lower the energy dissipation device height to the optimal height.
[0179] Example 2
[0180] A highly optimized energy dissipation system for trailing suction hopper dredgers
[0181] It includes four developed software modules: a core parameter input module, a loading process simulation and prediction module, a design optimization output module, and an automatic height adjustment module. These software modules are embedded in and called by the shipboard loading control system; such as Figure 12 ;
[0182] Among them, the core parameter input module:
[0183] The core parameters include geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. The geometric model includes: the structural dimensions of the mud hopper, the dimensions of the transverse and longitudinal triangular hoppers, the dimensions of the overflow equipment, the dimensions and height of the energy dissipation equipment, and the relative positions of the transverse and longitudinal triangular hoppers and the energy dissipation overflow equipment to the mud hopper. The boundary conditions include the inlet boundary being the loading flow rate and mud concentration, the overflow boundary being the free outflow boundary, the upper boundary of the mud hopper being the atmospheric pressure boundary, and the hopper wall boundary being the wall boundary with a certain roughness material. The mesh conditions include: the mesh range in the x, y, and z directions and the unit mesh size. The initial conditions include the initial water level H0 and the loading simulation duration T. The fluid motion parameters include the fluid temperature T, the fluid viscosity μ, and the fluid motion equation. The sediment motion parameters mainly include sediment particle size, sediment density, sediment porosity, critical Shields number, underwater angle of repose, bedload coefficient, and scour coefficient, involving four motion forms: sediment suspension, sediment deposition, sediment scour, and sediment bedload.
[0184] Among them, the loading process simulation and prediction module:
[0185] Using the parameters input into the core parameter input module, numerical calculations are performed to simulate the loading process under different operating conditions. The loading process simulation and prediction module implements the simulation and prediction of the loading process, which includes two parts: establishing a loading numerical model and loading simulation and prediction.
[0186] Establishing a loading numerical model: This refers to using CFD software (existing technology) to establish a numerical model that can simulate the loading process based on the input core parameters, so as to realize the loading simulation function.
[0187] Loading simulation prediction: Using the above-mentioned loading numerical model, numerical simulations were conducted under different energy dissipation device height positions to simulate the entire loading process. This resulted in simulation predictions of changes in loading volume, earthwork volume, total overflow loss, and sediment height within the tank over loading time. Multiple sets of numerical simulation calculation results corresponding to different energy dissipation device height positions were obtained. The energy dissipation device height position needs to be manually set.
[0188] The numerical simulation results also include: qt (3D mesh point cloud of flow rate at time t); ρ t (3D mesh point cloud of density at time t); v x (3D mesh point cloud of the x-direction velocity component at time t); v y (3D mesh point cloud of the y-direction velocity component at time t). The numerical calculation results are provided to the design optimization output module.
[0189] This module can display various data during the calculation process in real time and present the simulation results in a visual manner within the 3D model. Users can gain a more intuitive and in-depth understanding of the loading process by viewing the specific flow rate, concentration, and earthwork volume outputs under various working conditions. This helps users analyze various phenomena during the loading process, such as flow rate distribution and sediment concentration changes, thereby optimizing the loading plan.
[0190] Among them, the design optimization output module:
[0191] Based on the numerical simulation results output by the loading process simulation and prediction module, the system sets the evaluation criteria order using four indicators: loading volume, earthwork volume, overflow loss, and sediment flatness, to obtain the optimized recommended height of the energy dissipation device. Users can click to select the order of evaluation criteria (loading efficiency, flatness) according to their actual needs. The system will automatically output the optimized recommended value of the energy dissipation device height based on the evaluation criteria selected by the user.
[0192] Specifically, in multiple sets of numerical simulation results, different energy dissipation device heights correspond to different loading capacity, earthwork volume, overflow loss, and sediment flatness. An evaluation criterion order was established, and the recommended optimal design value for the energy dissipation device height was determined based on this order (first gradient, second gradient). Typically, loading capacity, earthwork volume, and overflow loss, representing the tank loading efficiency, are used as the first gradient criterion, while sediment flatness is used as the second gradient criterion. Higher loading capacity and earthwork volume, lower overflow loss, and higher sediment flatness indicate a better impact of the energy dissipation device height on the loading effect under that working condition.
[0193] Among them, the automatic height adjustment module:
[0194] Based on the recommended optimized height of the energy dissipation device output by the design optimization output module, a control signal is sent via the shipboard loading control system to automatically control the hydraulic struts on the adjustable-height energy dissipation device. By precisely controlling the extension and retraction of the hydraulic struts, the height of the energy dissipation device can be automatically and accurately adjusted. Alternatively, users can manually determine the soil conditions of the construction area based on existing geological survey data and, based on engineering experience, input the appropriate energy dissipation device height through the loading control system. Upon receiving the instruction, the system sends a control signal to the hydraulic struts, enabling manual adjustment of the energy dissipation device's height. This adjustment method is more flexible and can adapt to different construction environments and needs.
[0195] The specific details of each module are as follows:
[0196] The loading process simulation and prediction module uses the parameters input from the core parameter input module to perform numerical simulation calculations of the loading process. It treats sediment as solid particles, employing both fluid and sediment particle models to simulate four states: sediment suspension, deposition, resuspension, and shoveling. A partitioned structured mesh is used, with the energy dissipation device outlet area divided into separate zones and densified by a factor of two. The inlet boundary is defined by the loading flow rate and slurry concentration; the overflow boundary is a free outflow boundary; the upper boundary of the slurry tank is an atmospheric pressure boundary; and the tank wall boundary is a wall boundary made of a material with a certain degree of roughness. The finite volume method is used to perform numerical simulation calculations of the loading process.
[0197] During the simulation, this module can display various data in real time, such as flow rate, concentration, and earthwork volume, and present the simulation results in a visual manner within the 3D model. Users can gain a deeper and more comprehensive understanding of the loading process through these intuitive data and images. Furthermore, users can analyze various phenomena during the loading process, such as flow rate distribution and sediment concentration changes, by viewing the output results under different operating conditions, thereby further optimizing the loading plan.
[0198] Furthermore, the loading volume, earthwork volume, overflow loss, and sediment flatness at different times during the loading process are calculated using the following formula:
[0199] Loading capacity: This refers to the total mass of mud mixture loaded into the mud tank that did not overflow.
[0200] M = M f +M ss +M sd
[0201] In the formula: M represents the loading capacity, M f M represents the mass of the fluid inside the chamber. ss Indicates the mass of suspended sediment particles inside the chamber, M sd This indicates the mass of sediment particles deposited inside the chamber.
[0202] Earthwork volume: This refers to the volume of undisturbed soil that was loaded into the mud bin and did not overflow.
[0203]
[0204] In the formula, ρ s ρ represents the density of sediment particles, e represents the porosity of the undisturbed soil, and ρ represents the density of sediment particles. f ρ represents fluid density. s1 This indicates the density of the original soil.
[0205] Overflow loss: refers to the total mass of mud mixture loaded into the mud tank but overflowing out.
[0206] M l =M o -M
[0207] In the formula, M o The total mass of the mud mixture flowing out of the outlet of the energy dissipation device.
[0208] Flatness inside the mud chamber: expressed as the standard deviation of the height of sediment deposited in the longitudinal centerline section of the mud chamber.
[0209]
[0210] In the formula, α represents the flatness of the cabin interior, and x i This indicates the height of the deposited sediment at position i on the longitudinal centerline section of the mud chamber. This represents the average height of sediment deposited along the longitudinal centerline of the mud chamber, where n represents the number of sediment deposit heights calculated along the longitudinal centerline of the mud chamber.
[0211] The automatic height adjustment module is a concrete manifestation of automation in the shipboard loading control system, eliminating the need for manual adjustment of the energy dissipation device height. This module automatically controls the hydraulic strut 4 installed on the adjustable-height energy dissipation device based on the optimized height recommendation value obtained from the design optimization output module. By precisely controlling the extension and retraction of the hydraulic strut 4, real-time, automated, and accurate adjustment of the energy dissipation device height is achieved. This automatic adjustment method not only improves the accuracy and efficiency of adjustment but also reduces the difficulty and error of manual operation.
[0212] Furthermore, users can also input the appropriate height of the energy dissipation device through the shipboard loading control system based on their own judgment and experience. Upon receiving the instruction, the system will send corresponding control signals to the hydraulic strut 4 to achieve manual adjustment of the energy dissipation device's height. This flexible adjustment method can adapt to different construction environments and needs, improving the system's adaptability and practicality.
[0213] Example 3
[0214] A novel trailing suction hopper dredger with automatically adjustable energy dissipation device height and its loading operation method: By modifying the original trailing suction hopper dredger or building a new one, the hardware is equipped with an adjustable-height energy dissipation device, and the preparatory work is completed. The previous details will not be repeated.
[0215] The height-adjustable energy dissipation device is managed by the shipboard loading control system, as described in Example 2.
[0216] A highly automated method for loading and unloading dredgers with adjustable energy dissipation devices.
[0217] Specific process, such as Figure 13 This includes the following steps:
[0218] Step 1: The trailing suction hopper dredger enters the construction area; before construction begins, the core parameters are manually input, which mainly include six parts: geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. The specific content of the parameters is as described in Example 1.
[0219] Step 2: The shipboard loading control system automatically establishes a numerical model of the loading process based on the input core parameters, realizing the simulation function of loading changes over time.
[0220] Step 3: Set different energy dissipation equipment heights in the shipboard loading control system and perform loading simulation calculations under multiple working conditions.
[0221] Step 4: Recommend energy dissipation device height parameters through the design optimization parameter output module of the shipboard loading control system. Based on user requirements, select the evaluation criteria order (first gradient, second gradient) and the number of recommended values, and automatically generate recommended values for the optimized design of the energy dissipation device height. The core parameter recommendation criteria for the energy dissipation device height location, under the default state, use loading efficiency (represented by loading capacity, earthwork volume, and overflow loss) as the first gradient criterion, and sediment flatness as the second gradient criterion.
[0222] Furthermore, in construction situations where the flatness of the loading compartment is highly critical, the order of evaluation criteria can be adjusted, with the flatness of the deposited sediment being used as the first priority.
[0223] Step 5: When the location and excavation depth of the ship construction area change significantly, refer to the geological survey report and the corresponding changes in the excavated soil. Based on the updated input values such as qt, ρt, vxt, and vyt, repeat step 4 to recommend a new optimized value for the height of the energy dissipation equipment.
[0224] Specifically, as excavation progresses, the excavation location and depth change, and the soil conditions alter. To improve overall loading efficiency, the loading control system adjusts sediment transport parameters based on geological survey data, and re-performs numerical calculations and neural network training processes such as multi-condition loading simulation prediction, automatic optimization and recommendation of height parameters. The loading control system automatically re-controls the height of the hydraulic struts, thereby adjusting the height of the energy dissipation device to consistently ensure high loading efficiency. When the amount of fine particles in the excavated soil increases, the system automatically and precisely lowers the height of the energy dissipation device to reduce disturbance to fine sediment particles by the incoming water flow, allowing them to settle quickly and reducing overflow losses. When the amount of coarse particles in the loading slurry increases, the particles settle faster, and the system automatically and precisely increases the height of the energy dissipation device to prevent soil particles from clogging the outlet 21.
[0225] Step 6: When the trailing suction hopper dredger is operating at different construction locations and dredging depths, the corresponding recommended height of the energy dissipation equipment is called in combination with the dredger's position and the depth of the drag arm, and a command is sent to the hydraulic support rod 4 installed on the adjustable height energy dissipation device to realize the real-time height adjustment of the energy dissipation device.
Claims
1. A novel cutter suction dredger with highly automatic adjustable energy dissipation device, characterized in that, The new trailing suction hopper dredger, through the modification of the original trailing suction hopper dredger or the construction of a new ship, is equipped with an adjustable height energy dissipation device in terms of hardware, and the shipboard loading control system is used to manage the adjustable height energy dissipation device in terms of software, thereby realizing loading construction operations. The adjustable height energy dissipation device is designed to include a telescopic main pipe (1), a transverse pipe (2), a connecting steel plate (3), a hydraulic support rod (4), and a crossbeam inside the mud chamber (5). The retractable main pipe (1) is a sleeve-type structure. The retractable main pipe (1) includes an inner pipe (11), an outer pipe (12), filler (13), a limiting block (14), and a main pipe connecting flange (15). The inner pipe (11) and the outer pipe (12) are sealed by the filler (13), and the limiting block (14) limits the retraction range of the retractable main pipe (1). The inner pipe (11) is connected to the mud conveying pipeline of the trailing suction dredger, and the outer pipe (12) is connected to the transverse pipe (2) through the main pipe connecting flange (15). The transverse pipe (2) is divided into three parts: left, middle and right, which are connected in sequence through the transverse pipe connecting flange (22), and a total of 8 outlets (21) are provided. The crossbeam (5) inside the mud chamber is fixed to the side wall (6) of the mud chamber by welding technology. Four hydraulic support rods (4) for lifting are fixed to the crossbeam (5) inside the mud chamber by bolts. A connecting steel plate (3) is placed above the hydraulic support rod (4) and fixed to the upper end of the hydraulic support rod (4) by bolts. The connecting steel plate (3) is connected to the outer tube (12) of the telescopic main tube (1) by welding technology. Four hydraulic struts (4) are evenly arranged on the crossbeam (5) inside the mud chamber to ensure that the crossbeam (5) inside the mud chamber and the connecting steel plate (3) are subjected to uniform force while providing sufficient force. The hydraulic strut (4) consists of a rear cylinder head (41), a cylinder (42), a piston (43), a piston rod (44), a guide sleeve (45), a sealing ring (46), and a front cylinder head (47). The rear cylinder head (41) is bolted to the crossbeam (5) inside the mud tank, and at the same time seals the rear of the cylinder (42). The piston (43) is subjected to force inside the cylinder, which is transmitted to the connecting steel plate (3) above through the piston rod (44). The guide sleeve (45) supports and ensures the coaxiality of the piston rod (44) and the cylinder (42). The sealing ring (46) seals the front cylinder head (47) and the piston rod (44) to prevent water and mud from affecting the normal operation of the components inside the cylinder (42) during the loading process. The shipboard loading control system is embedded with a core parameter input module, a loading process simulation and prediction module, a design optimization output module, and an automatic altitude adjustment module. Among them, the core parameter input module: The core parameters include the geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. The geometric model includes: the structural dimensions of the mud hopper, the dimensions of the transverse and longitudinal triangular hoppers, the dimensions of the overflow equipment, the dimensions and height of the energy dissipation equipment, and the relative positions of the transverse and longitudinal triangular hoppers, energy dissipation equipment, and overflow equipment to the mud hopper. The boundary conditions include: the inlet boundary is the loading flow rate and mud concentration; the overflow boundary is a free outflow boundary; the upper boundary of the mud hopper is an atmospheric pressure boundary; and the hopper wall boundary is a wall boundary with a rough material. The mesh conditions include: the mesh range in the x, y, and z directions and the element mesh size. The initial conditions include the initial water level H0 and the loading simulation duration t. The fluid motion parameters include the fluid temperature T and the fluid viscosity. The fluid motion equations; the parameters of the sediment motion include sediment particle size, sediment density, sediment porosity, critical Shields number, underwater angle of repose, shoal motion coefficient and scour coefficient, involving four motion forms of sediment: sediment suspension, sediment deposition, sediment scour and sediment shoal.
2. A novel trailing suction hopper dredger with automatically adjustable energy dissipation device height as described in claim 1. Its features are, Among them, the loading process simulation and prediction module: Using the parameters already input by the core parameter input module, numerical calculations are performed to simulate the loading process under different working conditions; the loading process simulation and prediction module realizes the simulation and prediction of the loading process, including two parts: establishing a loading numerical model and loading simulation and prediction. Establish a numerical model for loading: Based on the input core parameters, use CFD software to establish a numerical model that can simulate the loading process, so as to realize the loading simulation function. Loading simulation prediction: Using the above loading numerical model, set different working conditions for the height position of the energy dissipation device, and conduct numerical simulation to simulate the entire loading process. Realize the simulation prediction of the changes in loading volume, earthwork volume, total overflow loss and sediment height in the tank with loading time, and obtain multiple sets of numerical simulation calculation results corresponding to different height positions of the energy dissipation device; the height position of the energy dissipation device needs to be set manually. The numerical simulation calculation results also include: a three-dimensional grid point cloud of the flow at time t, denoted as q t ; a three-dimensional grid point cloud of the density at time t, denoted as ρ t ; a three-dimensional grid point cloud of the x-direction component velocity at time t, denoted as v x ; a three-dimensional grid point cloud of the y-direction component velocity at time t, denoted as v y ; and the numerical calculation result is provided to a design optimization output module; Among them, the design optimization output module: Based on the numerical simulation results output by the loading process simulation and prediction module, the evaluation criteria are set according to four indicators: loading volume, earthwork volume, overflow loss, and sediment flatness, to obtain the optimized recommended height of the energy dissipation device. Users can click to select the order of evaluation criteria according to actual needs. The system automatically outputs the optimized recommended value of the energy dissipation device height according to the evaluation criteria selected by the user. Among them, the automatic height adjustment module: Based on the recommended optimized height of the energy dissipation equipment output by the design optimization output module, a control signal is sent via the shipboard loading control system to automatically control the hydraulic struts on the adjustable-height energy dissipation equipment; by precisely controlling the extension and retraction of the hydraulic struts, the height of the energy dissipation equipment can be automatically and accurately adjusted.
3. A method for loading hoppers into a novel trailing suction hopper dredger with automatically adjustable energy dissipation device as described in any one of claims 1-2, characterized in that... Includes the following steps: Step 1: The trailing suction hopper dredger enters the construction area; before construction begins, the core parameters are manually input, including six parts: geometric model, boundary conditions, mesh conditions, initial conditions, fluid motion, and sediment motion. Step 2: The shipboard loading control system automatically establishes a numerical model of the loading process based on the input core parameters, realizing the simulation function of loading changes over time. Step 3: Set different energy dissipation equipment heights in the shipboard loading control system and perform loading simulation calculations under multiple working conditions; Step 4: Recommend the height parameters of the energy dissipation equipment through the design optimization output module of the shipboard loading control system; Step 5: When the location and excavation depth of the ship construction area change significantly, refer to the geological survey report and the corresponding changes in the excavated soil. Based on the updated input values of flow rate, density, x-direction velocity and y-direction velocity, repeat Step 4 to recommend a new optimized value for the height of the energy dissipation equipment. Step 6: When the trailing suction hopper dredger is working at different construction locations and excavation depths, the corresponding energy dissipation equipment height optimization value is called in combination with the ship's position and the depth of the drag arm, and the command is sent to the hydraulic support rod (4) set on the adjustable height energy dissipation device to realize the real-time height adjustment of the energy dissipation device.
4. The loading and unloading operation method as described in claim 3, characterized in that, Step 4, Based on user needs, the order of evaluation criteria and the number of recommended values are selected and set, and recommended values for the optimal design of energy dissipation equipment are automatically generated; the order of evaluation criteria includes a first gradient and a second gradient. The recommended core parameters for the height and position of energy dissipation equipment are based on the following criteria: under the default conditions, the first-level criterion for judging the loading efficiency is represented by the loading capacity, earthwork volume, and overflow loss, and the second-level criterion is the flatness of the sediment. In construction situations where the flatness of the loading compartment is highly critical, the order of evaluation criteria is adjusted, with the flatness of the sediment as the first priority.
5. The loading and unloading operation method as described in claim 3, characterized in that, Step 5, As excavation progresses, the location and depth of the excavation change, and the soil conditions change. In order to improve the overall loading efficiency, the shipboard loading control system changes the sediment movement parameters based on the geological survey data, and re-performs loading simulation prediction under multiple working conditions, automatic optimization of height parameters, and recommended numerical calculation and neural network training process. The shipboard loading control system automatically re-controls the height of the hydraulic struts, thereby adjusting the height of the energy dissipation device to always ensure high loading efficiency. When the amount of fine particles in the excavated soil increases, the height of the energy dissipation device is automatically and precisely reduced to reduce the disturbance of the incoming water flow to the fine particles of mud and sand, so that the fine particles settle quickly and reduce the overflow loss of the loading tank; when the amount of coarse particles in the loaded mud increases, the particles settle faster, and the height of the energy dissipation device is automatically and precisely increased to prevent soil particles from clogging the outlet of the energy dissipation device (21).