Power parameter determination method and device and electronic equipment
By acquiring the actual and reference power information of the power supply components and using proportional or priority-based division methods, the actual power and losses of the virtualized subsystem are accurately calculated, solving the accuracy problem of power calculation in the virtualized system and improving the accuracy of energy flow visualization and system scheduling.
Patent Information
- Application Number
- CN202511501539.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-20
- Publication Date
- 2026-03-17
AI Technical Summary
In virtualization avatar technology, existing technologies struggle to accurately calculate the actual power and loss data of each virtualization subsystem, affecting the accuracy of energy flow visualization and system optimization scheduling.
By acquiring the actual power information and reference power information of the power supply components, and using a proportional or priority allocation method, the actual operating power and power loss of the virtualization subsystem are determined. Using the actual power information and reference power information of the power supply components as the allocation basis, and combined with power balance constraints, the actual power and power loss of each virtualization subsystem are accurately calculated.
It enables accurate calculation of the actual power and loss of the virtualized subsystem, providing precise data support for energy flow visualization and system optimization scheduling, and improving the system's energy utilization efficiency and stability.
Smart Images

Figure CN121684358A_ABST
Abstract
Description
Technical Field
[0001] This application belongs to the field of power supply technology, and in particular relates to a method, apparatus and electronic equipment for determining power parameters. Background Technology
[0002] Virtualization technology is being gradually applied to power supply systems such as photovoltaic-storage and integrated photovoltaic-storage-charging systems. This technology divides a physical system into multiple independent virtual subsystems, each of which can operate independently according to different operating strategies (such as maximum self-consumption, time-of-use pricing, or virtual power plant dispatch). This effectively avoids the risks of overcharging and over-discharging, suppresses the volatility of photovoltaic power generation, and improves the overall energy utilization efficiency of the system.
[0003] In virtualized systems, the actual power and loss data of each virtual subsystem are crucial for energy flow visualization, condition monitoring, and optimal system scheduling. However, these data are difficult to obtain through direct sampling, and traditional calculation methods have limited accuracy. Summary of the Invention
[0004] This application aims to address at least one of the technical problems existing in the prior art. To this end, this application proposes a power parameter determination method, apparatus, and electronic device, which can accurately calculate the actual power and losses of each virtualized subsystem, providing data support for energy flow visualization, status monitoring, and system optimization scheduling.
[0005] In a first aspect, this application provides a method for determining power parameters, the method being used in a power supply system, the power supply system including multiple power supply components, the power supply components being divided into multiple virtualized subsystems, the method comprising: Obtain the actual power information and reference power information of the power supply component; Based on the actual power information and the reference power information, the actual power parameters of the virtualization subsystem are determined according to a proportional division method or a priority division method. The actual power parameters include at least one of the actual operating power and the actual power loss.
[0006] According to the power parameter determination method of this application, by obtaining the actual power information and reference power information of the power supply components, and using the actual power information and reference power information of the power supply components as the allocation basis, the actual operating power and / or actual power loss of each virtualization subsystem are determined according to the proportional division method or the priority division method. The actual power and loss of each virtualization subsystem can be accurately calculated, providing data support for energy flow visualization, status monitoring and system optimization scheduling.
[0007] According to one embodiment of this application, the reference power information includes the reference total operating power of the power supply component and the reference operating power of the virtualization subsystem, and the actual power information includes the actual total operating power of the power supply component; The actual operating power of the virtualization subsystem is determined according to a proportional division method, including: Based on the reference total operating power and the actual total operating power, a first power allocation ratio is determined; Based on the first power allocation ratio and the reference operating power of the virtualization subsystem, the actual operating power of the virtualization subsystem is determined.
[0008] According to one embodiment of this application, determining the first power allocation ratio based on the reference total operating power and the actual total operating power includes: If the total reference operating power is less than the first power threshold, the first power allocation ratio is determined to be 1.
[0009] According to one embodiment of this application, the actual power information further includes the total actual power loss of the power supply component, after determining the actual operating power of the virtualization subsystem; The actual power loss of the virtualization subsystem is determined according to the proportional division method, including: The ratio of the absolute value of the actual operating power of the virtualization subsystem to the sum of the absolute values of the actual operating power of the multiple virtualization subsystems is used as the first loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the first power loss allocation ratio of the virtualization subsystem.
[0010] According to one embodiment of this application, the reference power information includes the reference operating power of each of the virtualization subsystems, and the actual power information includes the total actual power loss of the power supply components; The actual power loss of the virtualization subsystem is determined according to the proportional division method, including: The ratio of the absolute value of the reference operating power of the virtualization subsystem to the sum of the absolute values of the reference operating power of the plurality of virtualization subsystems is used as the second loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the second power loss allocation ratio of the virtualization subsystem.
[0011] According to one embodiment of this application, the method further includes: Based on the actual operating power of each power supply component in the power supply system, determine the total actual power loss of the power supply system; The power weighted sum of the power supply system is determined based on the absolute value of the actual operating power and the power weight of each of the power supply components. The third loss allocation ratio of the power supply component is determined based on the absolute value of the actual operating power, the power weight, and the power weighted sum. The actual power loss of the power supply component is determined based on the total actual power loss and the third power loss allocation ratio.
[0012] According to one embodiment of this application, the actual power information includes the actual total operating power of the power supply components. Determining the actual operating power of the virtualization subsystem according to a priority-based classification method includes: Obtain the priority of each of the aforementioned virtualization subsystems; According to the priority of each virtualization subsystem, the actual total operating power is allocated to at least one of the virtualization subsystems until the power to be allocated is 0; Determine the actual operating power of the virtualization subsystem.
[0013] According to one embodiment of this application, the step of allocating the total actual operating power to at least one of the virtualization subsystems according to the priority of each of the virtualization subsystems until the power to be allocated is 0 includes: According to the priority of each virtualization subsystem from high to low, corresponding reference operating power is allocated to the virtualization subsystem until the power to be allocated is 0.
[0014] According to one embodiment of this application, the actual power information includes the total actual power loss of the power supply component; The actual power consumption of the virtualization subsystem is determined according to a priority-based allocation method, including: Obtain the priority of each of the aforementioned virtualization subsystems; According to the priority of each virtualization subsystem, the total actual power loss is allocated to at least one of the virtualization subsystems until the power loss to be allocated is 0. Determine the actual power loss of the virtualization subsystem.
[0015] According to one embodiment of this application, the step of allocating the total actual power loss to at least one of the virtualization subsystems according to the priority of each of the virtualization subsystems until the power loss to be allocated is 0 includes: The total actual power loss is allocated to the virtualization subsystem with the highest priority. Among them, the actual power loss of the virtualization subsystem with the highest priority is equal to the total actual power loss.
[0016] According to one embodiment of this application, the reference power information includes the reference operating power of each of the virtualization subsystems, and the actual power information includes the actual total operating power of the power supply components; In the case of a virtualization subsystem with a reference operating power sign opposite to that of the virtualization subsystem, the actual operating power of the virtualization subsystem is determined according to a priority allocation method, including: Obtain the power deviation value between the actual total operating power and the sum of the reference operating powers of the multiple virtualization subsystems; The plurality of virtualization subsystems are divided into at least one first virtualization subsystem and at least one second virtualization subsystem according to the sign of the reference operating power, wherein the reference operating power signs of the first virtualization subsystem and the second virtualization subsystem are opposite. Based on the priority of the virtualization subsystem, the power deviation allocation ratio of the first virtualization subsystem is determined; Based on the power deviation value, the power deviation allocation ratio, and the reference operating power of the first virtualization subsystem, the actual operating power of the first virtualization subsystem is determined.
[0017] According to one embodiment of this application, the actual operating power of the second virtualization subsystem is equal to the reference operating power.
[0018] Secondly, this application provides a power parameter determination device for a power supply system, the power supply system including multiple power supply components, the power supply components being divided into multiple virtualized subsystems, the device comprising: The acquisition module is used to acquire the actual power information and reference power information of the power supply component; The processing module is used to determine the actual power parameters of the virtualization subsystem based on the actual power information and the reference power information, according to a proportional division method or a priority division method. The actual power parameters include at least one of the actual operating power and the actual power loss.
[0019] The power parameter determination device according to this application obtains the actual power information and reference power information of the power supply components, and uses the actual power information and reference power information of the power supply components as the allocation basis to determine the actual operating power and / or actual power loss of each virtualization subsystem according to the proportional division method or the priority division method. It can accurately calculate the actual power and loss of each virtualization subsystem, and provide data support for energy flow visualization, status monitoring and system optimization scheduling.
[0020] Thirdly, this application provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the power parameter determination method as described in the first aspect above.
[0021] Fourthly, this application provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the power parameter determination method as described in the first aspect above.
[0022] Fifthly, this application provides a chip including a processor and a communication interface, the communication interface being coupled to the processor, the processor being used to run programs or instructions to implement the power parameter determination method as described in the first aspect.
[0023] In a sixth aspect, this application provides a computer program product, including a computer program that, when executed by a processor, implements the power parameter determination method as described in the first aspect above.
[0024] Additional aspects and advantages of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description
[0025] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the description of the embodiments taken in conjunction with the following drawings, in which: Figure 1 This is a flowchart illustrating the power parameter determination method provided in an embodiment of this application; Figure 2 This is a schematic diagram of the process of virtualizing the power supply system provided in the embodiments of this application; Figure 3 This is one of the power flow diagrams of the virtualized photovoltaic-storage inverter provided in the embodiments of this application; Figure 4 This is the second power flow diagram of the virtualized photovoltaic-storage inverter provided in the embodiments of this application; Figure 5 This is a schematic diagram of the power supply system example provided in the embodiments of this application; Figure 6 This is a schematic diagram of the power parameter determination device provided in the embodiments of this application; Figure 7 This is a schematic diagram of the structure of the electronic device provided in the embodiments of this application. Detailed Implementation
[0026] The technical solutions of the embodiments of this application will be clearly described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application are within the scope of protection of this application.
[0027] The terms "first," "second," etc., used in the specification and claims of this application are used to distinguish similar objects and not to describe a specific order or sequence. It should be understood that such use of data can be interchanged where appropriate so that embodiments of this application can be implemented in orders other than those illustrated or described herein, and the objects distinguished by "first," "second," etc., are generally of the same class and the number of objects is not limited; for example, a first object can be one or more. Furthermore, in the specification and claims, "and / or" indicates at least one of the connected objects, and the character " / " generally indicates that the preceding and following objects are in an "or" relationship.
[0028] The following description, in conjunction with the accompanying drawings, details the power parameter determination method, power parameter determination device, electronic device, and readable storage medium provided in the embodiments of this application through specific implementations and application scenarios.
[0029] The power parameter determination method provided in this application embodiment can be executed by an electronic device or a functional module or functional entity in an electronic device that can implement the power parameter determination method. The following uses an electronic device as the execution subject to illustrate the power parameter determination method provided in this application embodiment.
[0030] The power parameter determination method provided in this application is used in a power supply system, which includes multiple power supply components, and the power supply components are divided into multiple virtualized subsystems.
[0031] In this embodiment, the power supply components of the photovoltaic-storage and photovoltaic-storage-charging power supply systems are divided into virtualized subsystems using virtualization avatar technology. Each subsystem can operate independently according to different operating strategies, effectively avoiding the risks of overcharging and over-discharging, suppressing the volatility of photovoltaic power generation, and improving the overall energy utilization efficiency of the system.
[0032] For example, such as Figure 2 As shown, the original photovoltaic-storage system includes power supply components such as strings, photovoltaic-storage inverters, and batteries. Through virtualization sharding technology, the original photovoltaic-storage system is divided into multiple virtual photovoltaic-storage systems, including photovoltaic-storage system 1 and photovoltaic-storage system 2. The operating modes of the two systems can be set independently (such as maximum self-consumption, virtual power plant dispatch, etc.). The strings are virtualized into string 1 and string 2, the photovoltaic-storage inverters are virtualized into photovoltaic-storage inverter 1 and photovoltaic-storage inverter 2, and the batteries are virtualized into battery 1 and battery 2.
[0033] It should be noted that, at the physical level, the power supply system (or power supply component) is still a complete device, and the power information that the data acquisition device can collect is the power of the power supply system (or power supply component).
[0034] For example, such as Figure 3 As shown, the power supply component is a photovoltaic-storage inverter, which is virtualized into n virtualized subsystems, namely photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, ..., photovoltaic-storage inverter n.
[0035] In this embodiment, the power information that the data acquisition device can collect is the actual operating power of the photovoltaic-storage inverter. For photovoltaic-energy storage inverter 1, photovoltaic-energy storage inverter 2, ... photovoltaic-energy storage inverter n, which are obtained by virtual partitioning, the actual operating power of each virtual photovoltaic-energy storage inverter cannot be obtained by sampling. , … .
[0036] This application provides a method for determining power parameters, which can accurately calculate the actual power and loss of each virtualized subsystem, providing data support for energy flow visualization, status monitoring, and system optimization scheduling.
[0037] like Figure 1 As shown, the method for determining the power parameters includes steps 110 and 120.
[0038] Step 110: Obtain the actual power information and reference power information of the power supply components.
[0039] It is understandable that actual power information refers to the actual power information of the power supply component during real-time operation. The actual power information of the power supply component includes the actual operating power and power loss of the power supply component.
[0040] It is understandable that operating power can be the actual output power of the power supply component during operation; power loss refers to the power lost by the power supply component during operation due to factors such as heat generation and friction, and this part of the power cannot be used for output.
[0041] In this embodiment, the actual power information of the power supply component can be obtained by sampling through a data acquisition device.
[0042] Reference power information refers to the expected power that the power supply system requires power supply components to achieve under the current control strategy or operating mode, i.e., the power target value. The reference power information of power supply components includes the reference operating power that the power supply components should achieve.
[0043] In this embodiment, the reference power information can be dynamically set by external commands (such as grid dispatch, energy management, etc.) or internal control algorithms (such as maximum power point tracking MPPT) to guide the real-time power adjustment of power supply components.
[0044] It should be noted that due to factors such as changes in environmental and input conditions, equipment performance limitations, and power grid or load disturbances, the actual operating power of the power supply components may differ from the reference operating power and are not completely equal.
[0045] Step 120: Based on the actual power information and reference power information, determine the actual power parameters of the virtualization subsystem according to the proportional division method or the priority division method.
[0046] The actual power parameters of the virtualization subsystem include at least one of the actual operating power and the actual power loss.
[0047] In this embodiment, the power supply component is divided into multiple virtualization subsystems. Based on the actual power information and reference power information of the power supply component, the actual operating power and actual power loss of each virtualization subsystem can be determined according to the proportional division method or the priority division method.
[0048] Taking a photovoltaic-storage inverter as an example, which is the power supply component.
[0049] like Figure 3 As shown, the photovoltaic-storage inverter is virtualized into n virtualized subsystems, namely photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, ..., photovoltaic-storage inverter n. The reference operating power of the virtualized subsystem is... The actual operating power of the virtualization subsystem is , This is the sequence number of the virtualization subsystem. =1, 2, ..., n.
[0050] The sum of the actual operating power of photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, ... photovoltaic-storage inverter n is equal to the actual operating power of the power supply component photovoltaic-storage inverter, calculated as follows:
[0051] in, The actual operating power of the photovoltaic-storage inverter can be obtained through voltage and current sampling.
[0052] The sum of the reference operating power of photovoltaic-energy storage inverter 1, photovoltaic-energy storage inverter 2, ... photovoltaic-energy storage inverter n is equal to the reference operating power of the power supply component photovoltaic-energy storage inverter, and the calculation formula is as follows:
[0053] in, The reference operating power for the photovoltaic-storage inverter is set by external commands or internal control algorithms.
[0054] In practice, due to factors such as inverter derating, the actual operating power of the power supply components is not exactly equal to the reference operating power. , that is:
[0055] It is understandable that the actual operating power of each virtualization subsystem may not be able to track the instructions, meaning there is a difference between the actual operating power of the virtualization subsystem and the reference operating power.
[0056] It should be noted that, through virtualization sharding technology, the power supply component is divided into multiple virtualization subsystems. Each virtualization subsystem operates independently according to different operating strategies. The reference operating power of the virtualization subsystem can be obtained according to the scheduling instructions of the upper-level system or the preset operating strategy. The obtained reference power information of the power supply component includes the total reference operating power of the power supply component and the reference operating power of each virtualization subsystem.
[0057] In this embodiment, the actual operating power of the power supply component is allocated to each virtualization subsystem according to a proportional allocation method or a priority allocation method, so that the sum of the actual operating power of each virtualization subsystem is equal to the actual operating power of the power supply component. Similarly, the actual operating power of the power supply component can also be allocated to each virtualization subsystem, so that the sum of the actual power loss of each virtualization subsystem is equal to the actual power loss of the power supply component.
[0058] It should be noted that the power difference between the actual power and the reference power of the power supply component is essentially due to the dynamic uncertainty in the energy conversion process. Based on this characteristic, by using the actual power information and reference power information of the power supply component as the allocation basis, and combining the power balance constraint (the sum of the actual operating power of each virtualization subsystem equals the actual operating power of the power supply component) and the loss balance constraint (the sum of the actual loss power of each virtualization subsystem equals the actual loss power of the power supply component), the actual operating power and actual loss power of each virtualization subsystem can be accurately calculated, effectively addressing the impact of dynamic uncertainty.
[0059] In this embodiment, the proportional allocation method and the priority allocation method are two implementation methods for allocating power to power supply components. Both are used to determine the actual power parameters of the virtualization subsystem. The allocation is based on the actual power information and reference power information of the power supply components, and the allocation target is that the sum of the actual operating power of each virtualization subsystem is equal to the actual operating power of the power supply components, and / or the sum of the actual loss power of each virtualization subsystem is equal to the actual loss power of the power supply components. This allows for accurate calculation of the actual operating power and / or actual loss power of each virtualization subsystem, providing data support for energy flow visualization, status monitoring, and system optimization scheduling.
[0060] Among them, the proportional allocation method refers to dividing the overall power into a portion of the power of multiple virtualization subsystems according to a ratio, and then allocating it to each virtualization subsystem. The priority allocation method refers to setting a corresponding priority for each virtualization subsystem and allocating the overall power to the virtualization subsystem with the target priority.
[0061] According to the power parameter determination method provided in the embodiments of this application, by obtaining the actual power information and reference power information of the power supply components, and using the actual power information and reference power information of the power supply components as the allocation basis, the actual operating power and / or actual power loss of each virtualization subsystem are determined according to the proportional division method or the priority division method. The actual power and loss of each virtualization subsystem can be accurately calculated, providing data support for energy flow visualization, status monitoring and system optimization scheduling.
[0062] It is understandable that the reference power information of the power supply component is obtained, which includes the reference total operating power of the power supply component and the reference operating power of the virtualization subsystem. The sum of the reference operating power of each virtualization subsystem is equal to the reference total operating power of the power supply component. The actual power information of the power supply component is obtained, which may include the actual total operating power and the actual total power loss of the power supply component. The sum of the actual operating power of each virtualization subsystem is equal to the actual total operating power of the power supply component, and the sum of the actual power loss of each virtualization subsystem is equal to the actual total power loss of the power supply component.
[0063] The embodiments of this application will be described in detail below from two different implementation perspectives: proportional division and priority division.
[0064] I. Proportional division method.
[0065] In some embodiments, determining the actual operating power of the virtualization subsystem according to a proportional division method includes: The first power allocation ratio is determined based on the reference total operating power and the actual total operating power; The actual operating power of the virtualization subsystem is determined based on the first power allocation ratio and the reference operating power of the virtualization subsystem.
[0066] In this embodiment, the ratio of the actual total operating power of the power supply component to the reference total operating power can be used as the first power allocation ratio. The actual total operating power is allocated to each virtualization subsystem according to the first power allocation ratio. The product of the first power allocation ratio and the reference operating power of the virtualization subsystem is calculated to obtain the actual operating power of the virtualization subsystem.
[0067] For example, the photovoltaic-storage inverter can be virtualized into n virtualized subsystems, namely photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, ..., photovoltaic-storage inverter n, and the reference operating power of the virtualized subsystem is: The actual operating power of the virtualization subsystem is , This is the sequence number of the virtualization subsystem. =1, 2, ..., n.
[0068] The actual total operating power of the photovoltaic-storage inverter is The reference total operating power of the photovoltaic-storage inverter is The formula for calculating the first power allocation ratio is as follows:
[0069] in, This is the first power allocation ratio.
[0070] For photovoltaic-energy storage inverters The first power allocation ratio and the photovoltaic-storage inverter Multiply by the reference operating power to obtain the photovoltaic-storage inverter. The actual operating power is calculated using the following formula:
[0071] in, For photovoltaic-storage inverters Actual operating power For the first power allocation ratio, For photovoltaic-storage inverters Reference operating power.
[0072] It should be noted that, for power supply components, the ratio of actual total operating power to reference total operating power, i.e., the first power allocation ratio, can characterize the dynamic uncertainty in the energy conversion process. The first power allocation ratio reflects the overall matching accuracy and dynamic following capability of the power supply components during operation. This characteristic also applies to the virtualization subsystem. The dynamic matching characteristics of the virtualization subsystem and the power supply components are consistent. The actual operating power of the virtualization subsystem can be accurately calculated based on the first power allocation ratio and the reference operating power of the virtualization subsystem.
[0073] In some embodiments, determining a first power allocation ratio based on a reference total operating power and an actual total operating power may include: If the total reference operating power is less than the first power threshold, the first power allocation ratio is determined to be 1.
[0074] The first power threshold is a preset operating power threshold. When the reference total operating power of the power supply component is less than the first power threshold, it indicates that the power supply system requires the power supply component to achieve a lower expected power value (such as low load demand, insufficient input energy, etc.).
[0075] It should be noted that the first power allocation ratio is calculated based on the reference total operating power and the actual total operating power of the power supply components. The reference total operating power is used as the denominator of the first power allocation ratio. When the reference total operating power is small, the error in calculating the first power allocation ratio is large. In order to reduce the calculation error, when the reference total operating power is less than the first power threshold, the first power allocation ratio is set to 1.
[0076] In this embodiment, when the reference total operating power is less than the first power threshold, the first power allocation ratio is determined to be 1, and the actual operating power of the virtualization subsystem is equal to the reference operating power, which can effectively reduce calculation errors.
[0077] In some embodiments, after determining the actual operating power of the virtualization subsystem, the actual power loss of the virtualization subsystem is determined according to a proportional division method, including: The ratio of the absolute value of the actual operating power of the virtualization subsystem to the sum of the absolute values of the actual operating power of multiple virtualization subsystems is used as the first loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the first power loss allocation ratio of the virtualization subsystem.
[0078] In this embodiment, the actual operating power of each virtualization subsystem can be calculated based on the first power allocation ratio and the reference operating power of each virtualization subsystem. For a certain virtualization subsystem, the ratio of the absolute value of the actual operating power of the virtualization subsystem to the sum of the absolute values of the actual operating power of multiple virtualization subsystems is calculated. This ratio is used as the first loss allocation ratio of the virtualization subsystem. The actual total loss power of the power supply component is multiplied by the first loss allocation ratio of the virtualization subsystem to obtain the actual loss power of the virtualization subsystem.
[0079] For example, the power supply component is divided into n virtualized subsystems. Based on the first power allocation ratio and the reference operating power of each virtualized subsystem, the actual operating power of the n virtualized subsystems is calculated as follows: , … .
[0080] For virtualization subsystems ( =1, 2, ..., n), the formula for calculating the first loss allocation ratio is as follows:
[0081] in, For virtualization subsystem The first loss allocation ratio, For virtualization subsystem The actual operating power.
[0082] The actual total power loss of the power supply components and the virtualization subsystem First loss allocation ratio To multiply, we obtain the virtualization subsystem. The actual power loss is calculated using the following formula:
[0083] in, For virtualization subsystem The actual power loss This represents the total actual power loss of the power supply components. For virtualization subsystem The first loss allocation ratio.
[0084] In practice, the loss allocation ratio can be determined based on the reference operating power, and the actual power loss of the virtualization subsystem can be calculated.
[0085] In some embodiments, determining the actual power loss of the virtualization subsystem according to a proportional division method includes: The ratio of the absolute value of the reference operating power of the virtualization subsystem to the sum of the absolute values of the reference operating power of multiple virtualization subsystems is used as the second loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the second power loss allocation ratio of the virtualization subsystem.
[0086] In this embodiment, for a certain virtualization subsystem, the ratio of the absolute value of the reference operating power of the virtualization subsystem to the sum of the absolute values of the reference operating power of multiple virtualization subsystems is calculated. This ratio is used as the second loss allocation ratio of the virtualization subsystem. The actual total power loss of the power supply components is multiplied by the second loss allocation ratio of the virtualization subsystem to obtain the actual power loss of the virtualization subsystem.
[0087] For example, the power supply component is divided into n virtualized subsystems. The reference power information of the power supply component is obtained, which includes the reference operating power of each of the n virtualized subsystems, respectively. , … .
[0088] For virtualization subsystems ( =1, 2, ..., n), the formula for calculating the second loss allocation ratio is as follows:
[0089] in, For virtualization subsystem The second loss allocation ratio, For virtualization subsystem Reference operating power.
[0090] The actual total power loss of the power supply components and the virtualization subsystem Second loss allocation ratio To multiply, we obtain the virtualization subsystem. The actual power loss is calculated using the following formula:
[0091] in, For virtualization subsystem The actual power loss This represents the total actual power loss of the power supply components. For virtualization subsystem The second loss allocation ratio.
[0092] It should be noted that the power loss is a positive value. When calculating the power loss allocation ratio, it is calculated based on the absolute value of the actual operating power or reference operating power of the virtualization subsystem to ensure that the power loss allocated to each virtualization subsystem is positive.
[0093] In practice, the actual operating power and actual power loss of the virtualization subsystem can be calculated according to the proportional division method. For the actual operating power of the virtualization subsystem, each virtualization subsystem uses the same first power allocation ratio when calculating. For the actual power loss of the virtualization subsystem, each virtualization subsystem has its own corresponding power loss allocation ratio (first power loss allocation ratio or second power loss allocation ratio) when calculating.
[0094] II. Priority Division Method.
[0095] Understandably, the power supply components are divided into multiple virtualized subsystems, and the priority of each virtualized subsystem can be set according to the actual application scenario, control strategy, or operating mode.
[0096] In some embodiments, determining the actual operating power of the virtualization subsystem according to a priority-based approach includes: Obtain the priority of each virtualization subsystem; Based on the priority of each virtualization subsystem, the actual total operating power is allocated to at least one virtualization subsystem until the power to be allocated is 0. Determine the actual operating power of the virtualization subsystem.
[0097] In this embodiment, the priority of each virtualization subsystem is first determined. Based on the priority of each virtualization subsystem, the operating power is preferentially allocated to some virtualization subsystems in the power supply component until the actual total operating power of the power supply component is allocated, that is, the power to be allocated is 0, and the actual operating power of the virtualization subsystem can be obtained.
[0098] It is understandable that the power to be allocated is the actual total operating power of the power supply components minus the power already allocated to the virtualization subsystem.
[0099] In actual implementation, the total operating power of the power supply components is allocated to the virtualization subsystems according to the priority allocation method. There may be cases where some virtualization subsystems are not allocated power, and the actual operating power of the virtualization subsystems that are not allocated power is 0.
[0100] In some embodiments, allocating the total actual operating power to at least one virtualization subsystem according to the priority of each virtualization subsystem, until the power to be allocated is 0, includes: According to the priority of each virtualization subsystem from high to low, the corresponding reference operating power is allocated to the virtualization subsystem until the power to be allocated is 0.
[0101] In this embodiment, the actual total operating power is preferentially allocated to the highest priority virtualization subsystem. According to the reference operating power of the highest priority virtualization subsystem, the operating power is fully allocated to the highest priority virtualization subsystem. If there is still power remaining after allocation (not 0), it is allocated to the next highest priority virtualization subsystem, and the allocation is still full. This process continues until the power to be allocated is 0.
[0102] In some embodiments, determining the actual power consumption of the virtualization subsystem according to a priority-based approach includes: Obtain the priority of each virtualization subsystem; According to the priority of each virtualization subsystem, the total actual power loss is allocated to at least one virtualization subsystem until the power loss to be allocated is 0. Determine the actual power loss of the virtualization subsystem.
[0103] In this embodiment, the priority of each virtualization subsystem is first determined. Based on the priority of each virtualization subsystem, the power loss is preferentially allocated to some virtualization subsystems in the power supply component until the total actual power loss of the power supply component is allocated, that is, the power loss to be allocated is 0, and the actual power loss of the virtualization subsystem can be obtained.
[0104] It is understandable that the loss to be allocated is the total actual power loss of the power supply components minus the power loss already allocated to the virtualization subsystem.
[0105] In actual implementation, the total actual power loss of the power supply components is allocated to the virtualization subsystems according to the priority allocation method. It is possible that some virtualization subsystems will not be allocated any power loss, and the actual power loss of the virtualization subsystems that are not allocated any power loss is 0.
[0106] In some embodiments, allocating the total actual power loss to at least one virtualization subsystem according to the priority of each virtualization subsystem, until the power loss to be allocated is 0, includes: Allocate the total actual power loss to the highest priority virtualization subsystem; Among them, the actual power loss of the highest priority virtualization subsystem is equal to the total actual power loss.
[0107] In this embodiment, the virtualization subsystems are sorted from highest to lowest priority, and the total actual power loss is allocated to the virtualization subsystem with the highest priority, while the virtualization subsystems with other priorities are allocated 0 power loss.
[0108] In actual implementation, after setting the priority of each virtualization subsystem, the virtualization subsystems are sorted from high to low priority. For the allocation of the actual total operating power, the operating power is allocated in full according to the priority from high to low until the power to be allocated is 0. For the allocation of the actual total power loss, the actual total power loss is directly allocated to the virtualization subsystem with the highest priority.
[0109] Understandably, the power allocation of power supply components can be divided into allocating the actual operating power of the power supply components and allocating the actual power loss of the power supply components according to the priority allocation method. The priority of the operating power allocation of each virtualization subsystem and the priority of the power loss allocation can be the same or different.
[0110] Taking a photovoltaic-storage inverter as an example, a specific implementation is described below.
[0111] like Figure 4 As shown, the photovoltaic-storage inverter is virtually divided into three virtualized subsystems: photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, and photovoltaic-storage inverter 3. The priority of operating power allocation and loss power allocation is set to be the same, and the order from high to low is: photovoltaic-storage inverter 1 > photovoltaic-storage inverter 2 > photovoltaic-storage inverter 3.
[0112] Reference operating power of photovoltaic-storage inverter 1 Reference operating power of photovoltaic-storage inverter 2 Reference operating power of photovoltaic-storage inverter 3 The actual total operating power of the photovoltaic-storage inverter The actual total power loss of the photovoltaic-storage inverter .
[0113] Regarding the allocation of the actual total operating power, based on the power allocation priority setting, the actual total operating power is first allocated to photovoltaic-storage inverter 1. The power to be allocated at this time is Then allocate the power to be allocated Allocated to photovoltaic-storage inverter 2, At this point, the power to be allocated is 0. For photovoltaic-storage inverter 3, .
[0114] Regarding the allocation of the total actual power loss, based on priority settings, all the total actual power loss is allocated to photovoltaic-storage inverter 1. The actual power loss of photovoltaic-storage inverter 1... Actual power loss of photovoltaic-storage inverter 2 Actual power loss of photovoltaic-storage inverter 3 .
[0115] It should be noted that the priority of operating power allocation and the priority of loss power allocation can be different. For example, for the allocation of the actual total loss power, the priority can be set from high to low as: photovoltaic-storage inverter 3 > photovoltaic-storage inverter 2 > photovoltaic-storage inverter 1, so that the total actual loss power is allocated to photovoltaic-storage inverter 3, and the actual loss power of photovoltaic-storage inverter 3 is... Actual power loss of photovoltaic-storage inverter 2 Actual power loss of photovoltaic-storage inverter 1 .
[0116] In practice, power deviations can be allocated based on the priority of the virtualization subsystem, and the actual operating power of the virtualization subsystem can be calculated.
[0117] In some embodiments, when there are virtualization subsystems with opposite reference operating power signs in the power supply components, the actual operating power of the virtualization subsystem is determined according to a priority allocation method, including: Obtain the power deviation value between the actual total operating power and the sum of the reference operating powers of multiple virtualization subsystems; Based on the sign of the reference operating power, multiple virtualization subsystems are divided into at least one first virtualization subsystem and at least one second virtualization subsystem, with the reference operating power signs of the first and second virtualization subsystems being opposite. Based on the priority of the virtualization subsystem, determine the power deviation allocation ratio of the first virtualization subsystem; The actual operating power of the first virtualization subsystem is determined based on the power deviation value, the power deviation allocation ratio, and the reference operating power of the first virtualization subsystem.
[0118] It should be noted that there are virtualized subsystems with opposite reference operating power signs in the power supply components. That is, at least one virtualized subsystem has a positive reference operating power sign and at least one virtualized subsystem has a negative reference operating power sign. The power supply components may have bidirectional energy flow (such as the inverter of the energy storage system).
[0119] In this embodiment, the power deviation value is first obtained as the sum of the actual total operating power of the power supply component and the reference operating power of multiple virtualization subsystems. The power deviation value represents the total power deviation between the actual operation of the power supply component and the reference target. The power deviation value is signed (positive or negative).
[0120] Meanwhile, based on the sign of the reference operating power of each virtualization subsystem, the multiple virtualization subsystems are divided into at least one first virtualization subsystem and at least one second virtualization subsystem. The first virtualization subsystem is the virtualization subsystem whose reference operating power sign is the same as (or opposite to) the power deviation value, and the second virtualization subsystem is the virtualization subsystem whose reference operating power sign is opposite to (or the same as) the power deviation value.
[0121] Based on the priority of the virtualization subsystems, the power deviation allocation ratio of the first virtualization subsystem is determined, and the power deviation value is allocated to each first virtualization subsystem according to the power deviation allocation ratio. The actual operating power of the first virtualization subsystem is equal to the difference between its own reference operating power and the allocated power deviation.
[0122] In practice, based on priority, the power deviation allocation ratio of the first virtualization subsystem with the highest (or lowest) priority can be set to 1, that is, all power deviation is allocated to the first virtualization subsystem with the highest (or lowest) priority. Alternatively, the power deviation allocation ratio of each first virtualization subsystem can be set according to the positive correlation between priority and power deviation allocation ratio.
[0123] In some embodiments, no power deviation value is assigned to the second virtualization subsystem, that is, the power deviation of the second virtualization subsystem can be calculated as 0, and the actual operating power of the second virtualization subsystem is equal to the reference operating power.
[0124] The following is a specific example.
[0125] The photovoltaic-storage inverter is virtually divided into three virtualized subsystems: photovoltaic-storage inverter 1, photovoltaic-storage inverter 2, and photovoltaic-storage inverter 3, with priority ordered from high to low as follows: photovoltaic-storage inverter 1 > photovoltaic-storage inverter 2 > photovoltaic-storage inverter 3.
[0126] Reference operating power of photovoltaic-storage inverter 1 Reference operating power of photovoltaic-storage inverter 2 Reference operating power of photovoltaic-storage inverter 3 There exists a virtualization subsystem with the opposite sign of the reference operating power.
[0127] Actual total operating power of photovoltaic-storage inverter .
[0128] The sum of reference operating power of multiple virtualization subsystems .
[0129] Power deviation value , the symbol is positive.
[0130] When the virtualization subsystem with the same sign as the power deviation value is selected as the first virtualization subsystem, the first virtualization subsystem of the power supply component includes photovoltaic-storage inverter 1 and photovoltaic-storage inverter 3. The power deviation allocation ratio of photovoltaic-storage inverter 3 is 1, and the power deviation allocated to photovoltaic-storage inverter 3 is... , combined The actual operating power of the photovoltaic-storage inverter 3 can be obtained. Meanwhile, the power deviation allocated to photovoltaic-energy storage inverter 1 and photovoltaic-energy storage inverter 2 is 0.
[0131] In this embodiment, the actual operating power of the photovoltaic-storage inverter 1 The actual operating power of the photovoltaic-storage inverter 2 The actual operating power of the photovoltaic-storage inverter 3 .
[0132] When the virtualization subsystem with the opposite sign to the power deviation value is selected as the first virtualization subsystem, the first virtualization subsystem of the power supply component includes the photovoltaic-storage inverter 2. Since there are no other first virtualization subsystems, the power deviation allocated to the photovoltaic-storage inverter 2 is... That is, the power deviation allocation ratio of the photovoltaic-storage inverter 2 is 1.
[0133] In this embodiment, the actual operating power of the photovoltaic-storage inverter 1 The actual operating power of the photovoltaic-storage inverter 2 The actual operating power of the photovoltaic-storage inverter 3 .
[0134] It should be noted that for a power supply system, the actual losses of each power supply component may not be obtainable through sensor sampling. In this case, the power or loss of the power supply system can be allocated to determine the actual power loss of each power supply component, that is, the total actual power loss of the power supply components.
[0135] In some embodiments, the power parameter determination method further includes: Based on the actual operating power of each power supply component in the power supply system, determine the total actual power loss of the power supply system. The power weighted sum of the power supply system is determined based on the absolute value of the actual operating power and the power weight of each power supply component. The third loss allocation ratio of the power supply components is determined based on the absolute value of the actual operating power, power weight, and power weighted sum of the power supply components. The actual power loss of the power supply components is determined based on the total actual power loss and the third loss allocation ratio.
[0136] In this embodiment, according to the law of conservation of energy, when the power supply system is in steady state, the total input power should be equal to the sum of the total output power and the total power loss. The actual operating power of some power supply components is included in the total input power, and the actual operating power of some power supply components is included in the total output power. Based on the actual operating power of each power supply component in the power supply system, the actual total power loss of the power supply system can be calculated.
[0137] The power weight of the power supply component is used to characterize the relative magnitude of the power loss of each power supply component. The power weight can be set to a fixed value or adjusted according to the operating conditions of the power supply component.
[0138] For example, if the power supply component is a photovoltaic panel, under normal operating conditions, the power weight of the photovoltaic panel is a1. When the voltage of the photovoltaic panel is low, the loss of the boost circuit increases significantly. The power weight of the photovoltaic panel can be increased to a2, where a2 > a1.
[0139] In this embodiment, the power weighted sum of the power supply system is calculated by weighting and summing the absolute values of the actual operating power of each power supply component and its corresponding power weight.
[0140] It should be noted that the power weighted sum of the power supply system is calculated based on the absolute value of the actual operating power of each power supply component, without considering whether the power flow is input or output. Regarding the actual power carried by each power supply component, and considering the power weight, the power and losses of power supply components with higher power weights have a greater impact on the power supply system.
[0141] In this embodiment, based on the absolute value of the actual operating power of the power supply component, the power weight, and the power weighted sum, the ratio of the actual power loss of the power supply component to the total actual power loss of the power supply system, i.e., the third loss allocation ratio, can be determined. Then, by multiplying the total actual power loss of the power supply system by the third loss allocation ratio of the power supply component, the actual power loss of the power supply component can be obtained.
[0142] The following is a specific example.
[0143] like Figure 5 As shown, the photovoltaic-storage system includes a photovoltaic power generation module, an energy storage battery module, and an inverter grid-connected module, with each module corresponding to a power supply component of the power supply system.
[0144] A photovoltaic (PV) power generation module includes a photovoltaic panel and a boost circuit, which can collect the voltage and current on the PV panel side to obtain the actual operating power of the PV power generation module. (positive).
[0145] Energy storage battery modules include battery cells and DC / DC conversion circuits, which can collect cell voltage and current to obtain the actual operating power of the energy storage battery module. (Charging the battery cell is positive, discharging the battery cell is negative).
[0146] The inverter grid-connected module includes an inverter and a power grid. It can collect voltage and current data from the grid side to obtain the actual operating power of the inverter grid-connected module on the grid side. (Output to the power grid is positive, and power drawn from the power grid is negative).
[0147] In actual implementation, the actual power loss of photovoltaic power generation modules Actual power loss of energy storage battery modules and the actual power loss of the inverter grid-connected module Typically, this requires a sensor with a set sampling power.
[0148] In this embodiment, no additional sensors are required to calculate the result. , as well as .
[0149] The first step is to calculate the total actual power loss based on the input and output of the photovoltaic system. The calculation formula is as follows:
[0150] in, This represents the total actual power loss of the photovoltaic-storage system.
[0151] The second step is to calculate the weighted sum of power based on the absolute value of the actual operating power and the power weight. The calculation formula is as follows:
[0152] in, For power weighted sum, The power weights corresponding to the photovoltaic power generation modules. The power weight corresponding to the energy storage battery module. The power weight corresponding to the inverter grid-connected module. , , All are positive numbers.
[0153] The third step is to calculate the third loss allocation ratio based on the absolute value of the actual operating power of the power supply components, the power weight, and the power weighted sum.
[0154] The formula for calculating the third loss allocation ratio for photovoltaic power generation modules is as follows:
[0155] The formula for calculating the third loss allocation ratio corresponding to the energy storage battery module is as follows:
[0156] The formula for calculating the third loss allocation ratio corresponding to the inverter grid-connected module is as follows:
[0157] It is understandable that each power supply component has its own corresponding third loss allocation ratio.
[0158] The fourth step is to determine the actual power loss of the power supply components based on the total actual power loss and the third power loss allocation ratio. The calculation formula is as follows:
[0159]
[0160]
[0161] in, This represents the actual power loss of the photovoltaic power generation module. This represents the actual power loss of the energy storage battery module. This represents the actual power loss of the inverter grid-connected module.
[0162] It is understandable that, given the actual operating power, actual power loss, and reference operating power of each power supply component, the actual power parameters of each virtualization subsystem can be calculated using a proportional or priority-based allocation method.
[0163] The power parameter determination method provided in this application can be executed by a power parameter determination device. This application uses the example of a power parameter determination device executing the power parameter determination method to illustrate the power parameter determination device provided in this application.
[0164] This application also provides a power parameter determination device for a power supply system, which includes multiple power supply components and is divided into multiple virtualized subsystems.
[0165] like Figure 6 As shown, the power parameter determining device includes: The acquisition module 610 is used to acquire the actual power information and reference power information of the power supply components; The processing module 620 is used to determine the actual power parameters of the virtualization subsystem based on the actual power information and the reference power information, according to the proportional division method or the priority division method. The actual power parameters include at least one of the actual operating power and the actual power loss.
[0166] According to the power parameter determination device provided in the embodiments of this application, by acquiring the actual power information and reference power information of the power supply component, and using the actual power information and reference power information of the power supply component as the allocation basis, the actual operating power and / or actual power loss of each virtualization subsystem are determined according to the proportional division method or the priority division method. The actual power and loss of each virtualization subsystem can be accurately calculated, providing data support for energy flow visualization, status monitoring and system optimization scheduling.
[0167] In some embodiments, the reference power information includes the reference total operating power of the power supply components and the reference operating power of the virtualization subsystem, and the actual power information includes the actual total operating power of the power supply components; Processing module 620 is used to determine the actual operating power of the virtualization subsystem according to a proportional division method, including: The first power allocation ratio is determined based on the reference total operating power and the actual total operating power; The actual operating power of the virtualization subsystem is determined based on the first power allocation ratio and the reference operating power of the virtualization subsystem.
[0168] In some embodiments, the processing module 620 is configured to determine a first power allocation ratio based on a reference total operating power and an actual total operating power, including: If the total reference operating power is less than the first power threshold, the first power allocation ratio is determined to be 1.
[0169] In some embodiments, the actual power information also includes the total actual power loss of the power supply components. After determining the actual operating power of the virtualization subsystem, the processing module 620 is used to determine the actual power loss of the virtualization subsystem according to a proportional division method, including: The ratio of the absolute value of the actual operating power of the virtualization subsystem to the sum of the absolute values of the actual operating power of multiple virtualization subsystems is used as the first loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the first power loss allocation ratio of the virtualization subsystem.
[0170] In some embodiments, the reference power information includes the reference operating power of each virtualization subsystem, and the actual power information includes the actual total power loss of the power supply components. Processing module 620 is used to determine the actual power loss of the virtualization subsystem according to a proportional division method, including: The ratio of the absolute value of the reference operating power of the virtualization subsystem to the sum of the absolute values of the reference operating power of multiple virtualization subsystems is used as the second loss allocation ratio of the virtualization subsystem. The actual power loss of the virtualization subsystem is determined based on the total actual power loss and the second power loss allocation ratio of the virtualization subsystem.
[0171] In some embodiments, the processing module 620 is further configured to determine the total actual power loss of the power supply system based on the actual operating power of each power supply component in the power supply system. The power weighted sum of the power supply system is determined based on the absolute value of the actual operating power and the power weight of each power supply component. The third loss allocation ratio of the power supply components is determined based on the absolute value of the actual operating power, power weight, and power weighted sum of the power supply components. The actual power loss of the power supply components is determined based on the total actual power loss and the third loss allocation ratio.
[0172] In some embodiments, the actual power information includes the actual total operating power of the power supply components. The processing module 620 is used to determine the actual operating power of the virtualization subsystem according to a priority-based classification method, including: Obtain the priority of each virtualization subsystem; Based on the priority of each virtualization subsystem, the actual total operating power is allocated to at least one virtualization subsystem until the power to be allocated is 0. Determine the actual operating power of the virtualization subsystem.
[0173] In some embodiments, the processing module 620 is configured to allocate the total actual operating power to at least one virtualization subsystem according to the priority of each virtualization subsystem, until the power to be allocated is 0, including: According to the priority of each virtualization subsystem from high to low, the corresponding reference operating power is allocated to the virtualization subsystem until the power to be allocated is 0.
[0174] In some embodiments, actual power information includes the total actual power loss of the power supply components; Processing module 620 is used to determine the actual power loss of the virtualization subsystem according to a priority-based allocation method, including: Obtain the priority of each virtualization subsystem; According to the priority of each virtualization subsystem, the total actual power loss is allocated to at least one virtualization subsystem until the power loss to be allocated is 0. Determine the actual power loss of the virtualization subsystem.
[0175] In some embodiments, the processing module 620 is configured to allocate the total actual power loss to at least one virtualization subsystem according to the priority of each virtualization subsystem, until the power loss to be allocated is 0, including: Allocate the total actual power loss to the highest priority virtualization subsystem; Among them, the actual power loss of the highest priority virtualization subsystem is equal to the total actual power loss.
[0176] In some embodiments, the reference power information includes the reference operating power of each virtualization subsystem, and the actual power information includes the actual total operating power of the power supply components. In the case of virtualization subsystems with opposite reference operating power signs, processing module 620 is used to determine the actual operating power of the virtualization subsystem according to a priority division method, including: Obtain the power deviation value between the actual total operating power and the sum of the reference operating powers of multiple virtualization subsystems; Based on the sign of the reference operating power, multiple virtualization subsystems are divided into at least one first virtualization subsystem and at least one second virtualization subsystem, with the reference operating power signs of the first and second virtualization subsystems being opposite. Based on the priority of the virtualization subsystem, determine the power deviation allocation ratio of the first virtualization subsystem; The actual operating power of the first virtualization subsystem is determined based on the power deviation value, the power deviation allocation ratio, and the reference operating power of the first virtualization subsystem.
[0177] In some embodiments, the actual operating power of the second virtualization subsystem is equal to the reference operating power.
[0178] The power parameter determination device in the embodiments of this application can be an electronic device or a component in an electronic device, such as an integrated circuit or a chip.
[0179] The power parameter determination device provided in this application embodiment can implement all the processes implemented in the above power parameter determination method embodiment, and will not be described again here to avoid repetition.
[0180] In some embodiments, such as Figure 7 As shown, this application embodiment also provides an electronic device 700, including a processor 701, a memory 702, and a computer program stored in the memory 702 and executable on the processor 701. When the program is executed by the processor 701, it implements the various processes of the above-described power parameter determination method embodiment and can achieve the same technical effect. To avoid repetition, it will not be described again here.
[0181] It should be noted that the electronic devices in the embodiments of this application include the mobile electronic devices and non-mobile electronic devices described above.
[0182] This application also provides a non-transitory computer-readable storage medium storing a computer program. When the computer program is executed by a processor, it implements the various processes of the above-described power parameter determination method embodiment and achieves the same technical effect. To avoid repetition, it will not be described again here.
[0183] The processor is the processor in the electronic device described in the above embodiments. The readable storage medium includes computer-readable storage media, such as computer read-only memory (ROM), random access memory (RAM), magnetic disk, or optical disk.
[0184] This application also provides a computer program product, including a computer program that, when executed by a processor, implements the above-described power parameter determination method.
[0185] The processor is the processor in the electronic device described in the above embodiments. The readable storage medium includes computer-readable storage media, such as computer read-only memory (ROM), random access memory (RAM), magnetic disk, or optical disk.
[0186] This application embodiment also provides a chip, which includes a processor and a communication interface. The communication interface is coupled to the processor. The processor is used to run programs or instructions to implement the various processes of the above-described power parameter determination method embodiment and can achieve the same technical effect. To avoid repetition, it will not be described again here.
[0187] It should be understood that the chip mentioned in the embodiments of this application may also be referred to as a system-on-a-chip, system chip, chip system, or system-on-a-chip, etc.
[0188] It should be noted that, in this document, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes that element. Furthermore, it should be noted that the scope of the methods and apparatuses in the embodiments of this application is not limited to performing functions in the order shown or discussed, but may also include performing functions substantially simultaneously or in the reverse order, depending on the functions involved. For example, the described methods may be performed in a different order than described, and various steps may be added, omitted, or combined. Additionally, features described with reference to certain examples may be combined in other examples.
[0189] Through the above description of the embodiments, those skilled in the art can clearly understand that the methods of the above embodiments can be implemented by means of software plus necessary general-purpose hardware platforms. Of course, they can also be implemented by hardware, but in many cases the former is a better implementation method. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, can be embodied in the form of a computer software product. This computer software product is stored in a storage medium (such as ROM / RAM, magnetic disk, optical disk) and includes several instructions to cause a terminal (which may be a mobile phone, computer, server, or network device, etc.) to execute the methods described in the various embodiments of this application.
[0190] The embodiments of this application have been described above with reference to the accompanying drawings. However, this application is not limited to the specific embodiments described above. The specific embodiments described above are merely illustrative and not restrictive. Those skilled in the art can make many other forms under the guidance of this application without departing from the spirit and scope of the claims, and all of these forms are within the protection scope of this application.
[0191] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "illustrative embodiment," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
[0192] Although embodiments of this application have been shown and described, those skilled in the art will understand that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of this application, the scope of which is defined by the claims and their equivalents.
Claims
1. A method of determining a power parameter, characterized by, The method is used for a power supply system including a plurality of power supply components, the power supply components are divided into a plurality of virtualized subsystems, the method includes: obtaining actual power information and reference power information of the power supply components; based on the actual power information and the reference power information, determining actual power parameters of the virtualized subsystems in a proportional division manner or a priority division manner, the actual power parameters including at least one of actual operating power and actual loss power.
2. The power parameter determination method of claim 1, wherein, The reference power information includes reference total operating power of the power supply components and reference operating power of the virtualized subsystems, and the actual power information includes actual total operating power of the power supply components; determining actual operating power of the virtualized subsystems in the proportional division manner includes: determining a first power allocation ratio based on the reference total operating power and the actual total operating power; determining actual operating power of the virtualized subsystems based on the first power allocation ratio and the reference operating power of the virtualized subsystems.
3. The power parameter determination method of claim 2, wherein, The determination of the first power allocation ratio based on the reference total operating power and the actual total operating power includes: in the case that the reference total operating power is less than a first power threshold, determining the first power allocation ratio as 1.
4. The power parameter determination method of claim 2, wherein, The actual power information further includes actual total loss power of the power supply components, after the determination of the actual operating power of the virtualized subsystems; determining actual loss power of the virtualized subsystems in the proportional division manner includes: taking a ratio of an absolute value of the actual operating power of the virtualized subsystems to a sum of absolute values of actual operating power of the plurality of virtualized subsystems as a first loss allocation ratio of the virtualized subsystems; determining actual loss power of the virtualized subsystems based on the actual total loss power and the first loss allocation ratio of the virtualized subsystems.
5. The method of claim 1, wherein The reference power information includes reference operating power of each of the virtualized subsystems, and the actual power information includes actual total loss power of the power supply components; determining actual loss power of the virtualized subsystems in the proportional division manner includes: taking a ratio of an absolute value of the reference operating power of the virtualized subsystems to a sum of absolute values of reference operating power of the plurality of virtualized subsystems as a second loss allocation ratio of the virtualized subsystems; determining actual loss power of the virtualized subsystems based on the actual total loss power and the second loss allocation ratio of the virtualized subsystems.
6. The method of claim 1, wherein, The method further includes: determining actual total loss power of the power supply system based on actual operating power of each of the power supply components in the power supply system; determining a power weighted sum of the power supply system based on absolute values of actual operating power of each of the power supply components and power weights; determining a third loss allocation ratio of the power supply components based on the absolute values of actual operating power of the power supply components, the power weights and the power weighted sum; determining actual loss power of the power supply components based on the actual total loss power and the third loss allocation ratio.
7. The method of claim 1, wherein, The actual power information includes actual total power of the power supply component, and the actual running power of the virtualization subsystem is determined according to a priority division mode, including: obtaining priorities of the virtualization subsystems; allocating the actual total power to at least one of the virtualization subsystems according to the priorities of the virtualization subsystems until the power to be allocated is 0; determining the actual running power of the virtualization subsystem.
8. The power parameter determination method of claim 7, wherein, The actual total power is allocated to at least one of the virtualization subsystems according to the priorities of the virtualization subsystems until the power to be allocated is 0, including: allocating corresponding reference running power to the virtualization subsystems in order from high to low according to the priorities of the virtualization subsystems until the power to be allocated is 0.
9. The method for determining power parameters according to claim 1, wherein, The actual power information includes actual total loss power of the power supply component; The actual loss power of the virtualization subsystem is determined according to a priority division mode, including: obtaining priorities of the virtualization subsystems; allocating the actual total loss power to at least one of the virtualization subsystems according to the priorities of the virtualization subsystems until the loss to be allocated is 0; determining the actual loss power of the virtualization subsystem.
10. The power parameter determination method of claim 9, wherein, The actual total loss power is allocated to at least one of the virtualization subsystems according to the priorities of the virtualization subsystems until the loss to be allocated is 0, including: allocating the actual total loss power to the virtualization subsystem with the highest priority; wherein the actual loss power of the virtualization subsystem with the highest priority is equal to the actual total loss power.
11. The method for power parameter determination according to claim 1, wherein, The reference power information includes reference running power of each of the virtualization subsystems, and the actual power information includes actual total power of the power supply component; in the case where there is a virtualization subsystem with opposite signs of reference running power, the actual running power of the virtualization subsystem is determined according to a priority division mode, including: obtaining a power deviation value of the sum of the actual total power and the reference running power of the plurality of virtualization subsystems; dividing the plurality of virtualization subsystems into at least one first virtualization subsystem and at least one second virtualization subsystem according to the signs of the reference running power, the reference running power of the first virtualization subsystem and the second virtualization subsystem having opposite signs; determining a power deviation allocation ratio of the first virtualization subsystem based on the priorities of the virtualization subsystems; determining the actual running power of the first virtualization subsystem based on the power deviation value, the power deviation allocation ratio, and the reference running power of the first virtualization subsystem.
12. The power parameter determination method of claim 11, wherein, The actual running power of the second virtualization subsystem is equal to the reference running power.
13. A power parameter determination apparatus, characterized by, The device is used for a power supply system including a plurality of power supply components, the power supply components are divided into a plurality of virtualization subsystems, and the device includes: an obtaining module for obtaining actual power information and reference power information of the power supply components; The processing module is configured to determine actual power parameters of the virtualization subsystem based on the actual power information and the reference power information in a proportional division manner or a priority division manner, wherein the actual power parameters include at least one of actual running power and actual loss power.
14. An electronic device comprising a memory, a processor, and a computer program stored on the memory and executable on the processor, characterized in that, The processor implements the power parameter determination method according to any one of claims 1-12 when executing the program.