Construction method and device for efficient heat preservation and insulation composite wall of building envelope structure

By integrating a multi-functional composite pouring head and a dynamic vibration mechanism, the problems of low construction efficiency and difficulty in thickness control in traditional composite wall construction have been solved, realizing efficient and precise construction of thermal insulation composite walls, and improving construction quality and energy-saving performance.

CN122013913APending Publication Date: 2026-05-12JIANGSU HENGJIAN CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
JIANGSU HENGJIAN CONSTR GRP CO LTD
Filing Date
2026-04-13
Publication Date
2026-05-12

AI Technical Summary

Technical Problem

Traditional composite wall construction suffers from problems such as fragmented construction procedures, low efficiency, difficulty in vibration and thickness control, and lack of integrated pouring and adjustment devices. In particular, it is difficult to protect and accurately layer brittle insulation materials and phase change materials.

Method used

The multifunctional composite pouring head, which integrates a three-channel independent conveying system, switchable molding molds, phase change material anti-breakage protection device, and layered positioning thickness control system, combined with a dynamic vibration mechanism and adjustable guide plate, enables one-time layered pouring and precise thickness control of the outer protective layer, aerogel-vacuum insulation composite insulation layer, and phase change energy storage layer.

Benefits of technology

It has achieved a significant improvement in construction efficiency and quality, ensured the density, uniformity and thickness accuracy of materials, avoided cold joints and debonding defects, and met different energy-saving design standards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122013913A_ABST
    Figure CN122013913A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method and device for an efficient heat preservation and heat insulation composite wall of a building envelope, and belongs to the technical field of building construction.The construction method comprises the following steps that S1, construction preparation is conducted, formworks and steel bars are installed, and it is confirmed that the construction environment temperature is within the range of 5-35 DEG C; s2, a multifunctional composite pouring head is installed, wherein the pouring head is integrated with a three-channel independent conveying system, a switchable forming mold, a phase-change material breakage-proof protection device and a layered positioning thickness control system; and S3, an outer protection layer and an aerogel-vacuum heat insulation composite heat preservation layer are poured, and a phase change energy storage adjusting layer is poured. A three-channel independent conveying system, a switchable forming mold, a phase change material breakage-proof protection device and a layering positioning thickness control system are integrated through a pouring head, one-time layering pouring of an outer protection layer, an aerogel-vacuum heat insulation composite heat preservation layer and a phase change energy storage adjusting layer can be achieved, and repeated equipment replacement is avoided; and the construction continuity and precision are obviously improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of building construction technology, specifically relating to a construction method and apparatus for high-efficiency thermal insulation composite walls for building envelopes. Background Technology

[0002] With the continuous improvement of building energy efficiency standards, especially the promotion of passive ultra-low energy buildings and near-zero energy buildings, the thermal insulation performance of building envelopes has become crucial for reducing building operating energy consumption and improving indoor thermal comfort. Traditional composite wall construction often employs layered casting or external insulation board application to form an outer protective layer, an insulation layer, and an inner structural layer. However, existing technologies have the following shortcomings: 1. The construction process is fragmented and inefficient. The outer protective layer, insulation layer and phase change energy storage layer often need to be poured in multiple stages. After each pour, it is necessary to wait for initial setting or install temporary partition templates. The construction cycle is long and the quality of interlayer bonding is difficult to guarantee, which can easily lead to cold joints or debonding.

[0003] 2. Difficulty in vibration and thickness control For thermal insulation materials containing aerogels, vacuum insulation panels, or other brittle and easily damaged materials, as well as energy storage layers containing microencapsulated phase change materials, traditional vibratory rods or immersion vibrators can easily damage the material structure, leading to a decrease in thermal insulation or energy storage performance. Furthermore, the thickness of each layer relies on manual positioning and adjustment, resulting in poor precision and difficulty in meeting the uniformity requirements of the design.

[0004] 3. Lack of integrated pouring and regulating devices Existing equipment cannot simultaneously complete precise layered casting of multiple materials and thicknesses, lacks a protection mechanism for phase change materials, and cannot dynamically adjust the vibration depth and angle during the casting process to meet the compaction requirements of different layer thicknesses. To address the aforementioned issues, this application proposes a construction method and apparatus for a high-efficiency thermal insulation composite wall for building envelopes. Summary of the Invention

[0005] In response to the problems in related technologies, this invention proposes a construction method and apparatus for high-efficiency thermal insulation composite walls for building envelopes, so as to overcome the aforementioned technical problems existing in the existing related technologies.

[0006] To achieve the above objectives, the present invention adopts the following technical solution: The construction method for high-efficiency thermal insulation composite walls in building envelopes includes the following steps: S1. Construction preparation: Install formwork and reinforcing bars, and confirm that the ambient temperature of the construction environment is within the range of 5℃ to 35℃. S2. Install a multi-functional composite pouring head, which integrates a three-channel independent conveying system, a switchable molding mold, a phase change material anti-breakage protection device, and a layered positioning thickness control system. S3, pouring out the outer protective layer, aerogel-vacuum insulation composite insulation layer, and pouring out the phase change energy storage and regulation layer; S4. Curing and Demolding: Cover and moisturize or keep warm for no less than 7 days, and demold after reaching the design strength.

[0007] Construction device for high-efficiency thermal insulation composite wall of building envelope includes a casting box, the top and bottom of which are open, two partitions are fixedly installed on the inner wall of the casting box, baffles are fixedly installed on both sides of the bottom of the casting box, and a pressure injection box is installed on one side of the casting box. The tamping mechanism includes six fixed frames, which are slidably installed on the inner wall of the casting box and located between two partitions. Multiple vibrating strips are installed on the inner wall of the fixed frames. Two mounting plates are slidably connected to both sides of the casting box, and the same push plate is fixedly installed between the four mounting plates. The layer thickness adjustment mechanism includes four guide plates, which are rotatably installed at the bottom of the casting box and located at the bottom of the two partitions and on both sides of the casting box. The adjustment mechanism includes an adjustment motor, which is fixedly mounted on one of the four mounting plates. Positioning shafts are fixedly mounted on both sides of the fixed frame. Rotating rods are rotatably connected to the two mounting plates located on one side of the four mounting plates. The rotating rods are driven by the three corresponding positioning shafts. The output shaft of the adjustment motor is fixedly connected to the corresponding rotating rod.

[0008] Preferably, the tamping mechanism further includes multiple movable holes, which are respectively opened on both sides of the casting box, and the positioning shaft is located in the corresponding movable hole.

[0009] Preferably, two mounting seats are fixedly installed on the front side of the casting box. A drive motor is fixedly installed on one of the two mounting seats. An active rod is fixedly installed on the output shaft of the drive motor. The active rod is rotatably connected to the two mounting seats and is drivenly connected to the push plate.

[0010] Preferably, a rotating roller is fixedly installed on the drive rod, a drive plate is movably sleeved on the rotating roller, two force plates are fixedly installed on one side of the push plate, an oblique hole is opened on the force plate, a movable shaft is slidably connected to the inner wall of the oblique hole, and the movable shaft is fixedly connected to the drive plate.

[0011] Preferably, the outer side of the roller is provided with a cam groove, and a slider is slidably connected to the inner wall of the cam groove. The slider is fixedly connected to the inner side of the drive plate.

[0012] Preferably, the partition thickness adjustment mechanism further includes four hydraulic cylinders, which are installed at the bottom of the injection box. Each hydraulic cylinder is equipped with a solenoid valve, and a top block is fixedly installed on the piston of the hydraulic cylinder. The top block is connected to the corresponding guide plate in a transmission manner.

[0013] Preferably, one of the two baffles has four sliding holes, and a guide block is movably connected to the inner wall of the sliding hole. The guide block is slidably connected to the corresponding guide plate and rotatably connected to the corresponding top block. A blocking plate is fixedly installed on one side of the top block and fits into the sliding hole.

[0014] Preferably, the adjustment mechanism further includes multiple fixed boxes, which are fixedly installed on two mounting plates on the same side. The rotating rod is rotatably connected to the fixed box on the same mounting plate. Three worm gears are fixedly installed on the rotating rod, and a worm wheel is fixedly installed at one end of the positioning shaft. The worm gears and corresponding worm wheels mesh with each other, and both the worm gears and worm wheels are located inside the fixed boxes.

[0015] Preferably, a sprocket is fixedly sleeved on the rotating rod, and the same chain meshes on the two sprockets.

[0016] In summary, the technical effects and advantages of this invention are as follows: 1. Multifunctional integrated casting system improves construction efficiency and quality. The pouring head integrates a three-channel independent conveying system, a switchable molding mold, a phase change material anti-breakage protection device, and a layered positioning and thickness control system. It can realize one-time layered pouring of the outer protective layer, aerogel-vacuum insulation composite insulation layer, and phase change energy storage regulation layer, avoiding multiple equipment changes and significantly improving construction continuity and accuracy.

[0017] 2. Dynamic vibration mechanism to adapt to different thicknesses and compaction requirements. By adjusting the motor, worm gear, and sprocket chain drive, the angle and position of the fixed frame and the vibrating bar can be flexibly changed to achieve targeted vibration of pouring layers of different thicknesses, ensuring that the material is dense and uniform and avoiding defects such as delamination or voids.

[0018] 3. Adjustable baffle design for precise control of each layer thickness. The bottom guide plate is independently driven by a hydraulic cylinder, and its angle is precisely controlled by a solenoid valve, thereby adjusting the gap between adjacent guide plates and achieving precise adjustment of the thickness of the outer protective layer, insulation layer and phase change layer to meet different energy-saving design standards. Attached Figure Description

[0019] Figure 1 This is a schematic diagram of the overall structure of the present invention; Figure 2 This is a schematic diagram of the structure of the present invention from a bottom view; Figure 3 This is a schematic diagram of the internal structure of the casting box of the present invention; Figure 4 This is a schematic diagram of the interlayer thickness adjustment mechanism of the present invention; Figure 5 This is a schematic diagram of the casting box and guide plate structure of the present invention; Figure 6 This is a schematic diagram of the vibrating mechanism of the present invention; Figure 7 This is a schematic diagram of the transmission connection structure between the active rod and the force-receiving plate of the present invention; Figure 8 This is a schematic diagram of part A of the present invention.

[0020] In the picture: 1. Casting box; 2. Partition plate; 3. Baffle plate; 4. Injection box; 5. Compaction mechanism; 51. Fixing frame; 52. Vibrating bar; 53. Mounting plate; 54. Push plate; 55. Movable hole; 6. Layer thickness adjustment mechanism; 61. Guide plate; 62. Hydraulic cylinder; 63. Top block; 64. Blocking plate; 65. Guide block; 66. Solenoid valve; 67. Sliding hole; 7. Adjustment mechanism; 71. Positioning shaft; 72. Rotating rod; 73. Adjusting motor; 74. Worm gear; 75. Worm wheel; 76. Sprocket; 77. Chain; 78. Fixing box; 8. Mounting base; 9. Drive motor; 10. Force plate; 11. Active rod; 12. Drive plate; 13. Inclined hole; 14. Movable shaft; 15. Rotating roller; 16. Cam groove; 17. Slider. Detailed Implementation

[0021] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.

[0022] Reference Figure 1-8 The construction method for high-efficiency thermal insulation composite walls in building envelopes includes the following steps: S1. Construction preparation: Install formwork and reinforcing bars, and confirm that the ambient temperature of the construction environment is within the range of 5℃ to 35℃. S2. Install a multi-functional composite pouring head, which integrates a three-channel independent conveying system, a switchable molding mold, a phase change material anti-breakage protection device, and a layered positioning thickness control system. S3, pouring out the outer protective layer, aerogel-vacuum insulation composite insulation layer, and pouring the phase change energy storage and regulation layer; S4. Curing and Demolding: Cover and moisturize or keep warm for no less than 7 days, and demold after reaching the design strength.

[0023] Construction device for high-efficiency thermal insulation composite wall of building envelope includes a casting box 1, the top and bottom of the casting box 1 are open, two partitions 2 are fixedly installed on the inner wall of the casting box 1, baffles 3 are fixedly installed on both sides of the bottom of the casting box 1, and a pressure injection box 4 is installed on one side of the casting box 1. The tamping mechanism 5 includes six fixed frames 51, which are slidably installed on the inner wall of the casting box 1 and located between two partitions 2. Multiple vibrating strips 52 are installed on the inner wall of the fixed frames 51. Two mounting plates 53 are slidably connected to both sides of the casting box 1, and the same push plate 54 is fixedly installed between the four mounting plates 53. The layer thickness adjustment mechanism 6 includes four guide plates 61, which are rotatably installed at the bottom of the casting box 1, and the four guide plates 61 are located at the bottom of the two partitions 2 and on both sides of the casting box 1. The adjustment mechanism 7 includes an adjustment motor 73, which is fixedly mounted on one of the four mounting plates 53. Positioning shafts 71 are fixedly mounted on both sides of the fixed frame 51. Rotating rods 72 are rotatably connected to the two mounting plates 53 located on one side of the four mounting plates 53. The rotating rods 72 are connected to the corresponding three positioning shafts 71 in a transmission connection. The output shaft of the adjustment motor 73 is fixedly connected to the corresponding rotating rod 72.

[0024] Reference Figure 1 and Figure 4 The tamping mechanism 5 also includes multiple movable holes 55, which are respectively opened on both sides of the casting box 1. The positioning shaft 71 is located in the corresponding movable hole 55. Two mounting seats 8 are fixedly installed on the front side of the casting box 1. One of the mounting seats 8 is fixedly installed with a drive motor 9. An active rod 11 is fixedly installed on the output shaft of the drive motor 9. The active rod 11 is rotatably connected to the two mounting seats 8 and is drivenly connected to the push plate 54. A rotating roller 15 is fixedly installed on the active rod 11. A drive plate 12 is movably sleeved on the rotating roller 15. Two force plates 10 are fixedly installed on one side of the push plate 54. An inclined hole 13 is opened on the force plate 10. A sliding connection is made on the inner wall of the inclined hole 13. The movable shaft 14 is fixedly connected to the drive plate 12. The outer side of the rotating roller 15 is provided with a cam groove 16. A slider 17 is slidably connected to the inner wall of the cam groove 16. The slider 17 is fixedly connected to the inner side of the drive plate 12. The output shaft of the drive motor 9 drives the active rod 11 to rotate. The active rod 11 drives the rotating roller 15 to rotate. The rotating roller 15 is slidably connected to the slider 17 through the cam groove 16, thereby driving the drive plate 12 to move up and down. The drive plate 12 is slidably connected to the inclined hole 13 through the movable shaft 14, thereby driving the force plate 10 and the push plate 54 to move laterally. In turn, the mounting plate 53 drives the fixed frame 51 and the vibrating strip 52 to quickly vibrate the pouring material in the pouring box 1.

[0025] Reference Figure 4 The layer thickness adjustment mechanism 6 also includes four hydraulic cylinders 62, which are installed at the bottom of the injection box 4. Each hydraulic cylinder 62 is equipped with a solenoid valve 66. A top block 63 is fixedly installed on the piston of each hydraulic cylinder 62. The top block 63 is connected to the corresponding guide plate 61. One of the two baffles 3 has four sliding holes 67. A guide block 65 is movably connected to the inner wall of each sliding hole 67. The guide block 65 is slidably connected to the corresponding guide plate 61, and the guide block 65 rotates with the corresponding top block 63. A blocking plate 64 is fixedly installed on one side of the top block 63. The blocking plate 64 fits into the sliding hole 67. The four hydraulic cylinders 62 are controlled by the solenoid valve 66. The hydraulic cylinders 62 drive the top block 63 to move through the piston. The top block 63 is rotatably connected to the guide block 65, which can drive the guide block 65 to move up and down. The guide block 65 is slidably connected to the guide plate 61, which can drive the guide plate 61 to change angle, thereby adjusting the pouring thickness between the two guide plates 61.

[0026] Reference Figure 2 The adjustment mechanism 7 also includes multiple fixing boxes 78. The rotating rod 72 is fixedly installed on two mounting plates 53 on the same side, and is rotatably connected to a fixed box 78 on the same mounting plate 53. Three worm gears 74 are fixedly installed on the rotating rod 72, and a worm wheel 75 is fixedly installed at one end of the positioning shaft 71. The worm gears 74 and the corresponding worm wheels 75 mesh with each other, and both the worm gears 74 and worm wheels 75 are located inside the fixed box 78. A sprocket 76 is fixedly sleeved on the rotating rod 72, and the same chain 77 meshes on the two sprockets 76. The output shaft of the adjusting motor 73 drives the two rotating rods 72 to rotate simultaneously through the meshing of the two sprockets 76 and the chain 77. The rotating rod 72, through the meshing of the worm gears 74 and the worm wheels 75, drives the positioning shaft 71 to change angle, and then drives the fixed frame 51 to change angle, thereby enabling vibration operation of different thicknesses of the poured material. At the same time, the setting of the fixed box 78 can stabilize the rotation state of the rotating rod 72 and isolate and protect the worm gears 74 and worm wheels 75.

[0027] Working principle: During operation, different building phase change materials are placed between two partitions 2 inside the casting box 1. During casting, the drive motor 9 is switched on, and the output shaft of the drive motor 9 drives the active rod 11 to rotate. The active rod 11 drives the rotating roller 15 to rotate. The rotating roller 15 is slidably connected to the slider 17 through the cam groove 16, thereby driving the drive plate 12 to move up and down. The drive plate 12 is slidably connected to the inclined hole 13 through the movable shaft 14, thereby driving the force plate 10 and the push plate 54 to move laterally. In turn, the mounting plate 53 drives the fixed frame 51 and the vibrating bar 52 to quickly vibrate the casting material in the casting box 1. When it is necessary to adjust the vibration height, the output shaft of the adjusting motor 73 drives the two rotating rods 72 to rotate simultaneously through the meshing of the two sprockets 76 and the chain 77. The rotating rod 72, through the meshing of the worm gear 74 and the worm wheel 75, drives the positioning shaft 71 to change angle, which in turn drives the fixed frame 51 to change angle. This allows for vibration compaction of the pouring material to different thicknesses. At the same time, the fixed box 78 stabilizes the rotation of the rotating rod 72 and isolates and protects the worm gear 74 and the worm wheel 75. When it is necessary to adjust the pouring thickness, the solenoid valve 66 controls the four hydraulic cylinders 62. The hydraulic cylinders 62 drive the top block 63 to move through the piston. The top block 63 is rotatably connected to the guide block 65, which drives the guide block 65 to move up and down. The guide block 65 is slidably connected to the guide plate 61, which drives the guide plate 61 to change angle, thereby adjusting the pouring thickness between the two guide plates 61.

[0028] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. Construction method for high-efficiency thermal insulation composite walls in building envelopes, including the following steps: S1. Construction preparation: Install formwork and reinforcing bars, and confirm that the ambient temperature of the construction environment is within the range of 5℃ to 35℃. S2. Install a multi-functional composite pouring head, which integrates a three-channel independent conveying system, a switchable molding mold, a phase change material anti-breakage protection device, and a layered positioning thickness control system. S3, pouring out the outer protective layer, aerogel-vacuum insulation composite insulation layer, and pouring the phase change energy storage and regulation layer; S4. Curing and Demolding: Cover and moisturize or keep warm for no less than 7 days, and demold after reaching the design strength.

2. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 1, comprising a casting box (1), characterized in that, The top and bottom of the casting box (1) are open. Two partitions (2) are fixedly installed on the inner wall of the casting box (1). Baffles (3) are fixedly installed on both sides of the bottom of the casting box (1). A pressure injection box (4) is installed on one side of the casting box (1). The tamping mechanism (5) includes six fixed frames (51), which are slidably installed on the inner wall of the casting box (1) and located between two partitions (2). Multiple vibrating strips (52) are installed on the inner wall of the fixed frames (51). Two mounting plates (53) are slidably connected to both sides of the casting box (1), and the same push plate (54) is fixedly installed between the four mounting plates (53). The layer thickness adjustment mechanism (6) includes four guide plates (61), which are rotatably installed at the bottom of the casting box (1) and located at the bottom of the two partitions (2) and on both sides of the casting box (1); The adjustment mechanism (7) includes an adjustment motor (73), which is fixedly installed on one of the four mounting plates (53). Positioning shafts (71) are fixedly installed on both sides of the fixed frame (51). Rotating rods (72) are rotatably connected to the two mounting plates (53) located on one side of the four mounting plates (53). The rotating rods (72) are connected to the corresponding three positioning shafts (71) in a transmission connection. The output shaft of the adjustment motor (73) is fixedly connected to the corresponding rotating rods (72).

3. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 2, characterized in that, The tamping mechanism (5) also includes multiple movable holes (55), which are respectively opened on both sides of the casting box (1), and the positioning shaft (71) is located in the corresponding movable hole (55).

4. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 2, characterized in that, Two mounting seats (8) are fixedly installed on the front side of the casting box (1). One of the mounting seats (8) is fixedly installed with a drive motor (9). An active rod (11) is fixedly installed on the output shaft of the drive motor (9). The active rod (11) is rotatably connected to the two mounting seats (8). The active rod (11) is connected to the push plate (54) in a transmission manner.

5. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 4, characterized in that, A rotating roller (15) is fixedly installed on the active rod (11), and a drive plate (12) is movably sleeved on the rotating roller (15). Two force plates (10) are fixedly installed on one side of the push plate (54). An oblique hole (13) is opened on the force plate (10), and a movable shaft (14) is slidably connected to the inner wall of the oblique hole (13). The movable shaft (14) is fixedly connected to the drive plate (12).

6. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 5, characterized in that, The outer side of the roller (15) is provided with a cam groove (16), and a slider (17) is slidably connected to the inner wall of the cam groove (16). The slider (17) is fixedly connected to the inner side of the drive plate (12).

7. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 2, characterized in that, The layer thickness adjustment mechanism (6) also includes four hydraulic cylinders (62). The four hydraulic cylinders (62) are installed at the bottom of the injection box (4), and the hydraulic cylinders (62) are equipped with solenoid valves (66). A top block (63) is fixedly installed on the piston of the hydraulic cylinder (62), and the top block (63) is connected to the corresponding guide plate (61) in a transmission connection.

8. The construction device for the high-efficiency thermal insulation composite wall of the building envelope according to claim 7, characterized in that, Four sliding holes (67) are provided on one of the two baffles (3). A guide block (65) is movably connected to the inner wall of the sliding hole (67). The guide block (65) is slidably connected to the corresponding guide plate (61), and the guide block (65) is rotatably connected to the corresponding top block (63). A blocking plate (64) is fixedly installed on one side of the top block (63). The blocking plate (64) fits and cooperates with the sliding hole (67).

9. The construction device for a high-efficiency thermal insulation composite wall for building envelope according to claim 2, characterized in that, The adjustment mechanism (7) also includes multiple fixed boxes (78), which are fixedly installed on two mounting plates (53) on the same side. The rotating rod (72) is rotatably connected to the fixed box (78) on the same mounting plate (53). Three worm gears (74) are fixedly installed on the rotating rod (72). A worm wheel (75) is fixedly installed at one end of the positioning shaft (71). The worm gears (74) and the corresponding worm wheels (75) mesh with each other, and both the worm gears (74) and the worm wheels (75) are located inside the fixed box (78).

10. The construction device for a high-efficiency thermal insulation composite wall for building envelope as described in claim 9, characterized in that, A sprocket (76) is fixedly sleeved on the rotating rod (72), and the same chain (77) meshes on the two sprockets (76).