Industrial plant zenith lighting pre-assembly collaborative construction method and system and medium

By pre-assembling and collaboratively hoisting the zenith lighting system on the ground during the construction of steel structures in large industrial plants, the problems of high risk, low efficiency, and difficulty in quality control in traditional high-altitude operations have been solved. This has enabled a safe and efficient construction process and standardized interfaces, facilitating later maintenance.

CN122190504APending Publication Date: 2026-06-12SHANGHAI BAODING ENVIRONMENT PROTECTION ENG TECH & SERVICES +1

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
SHANGHAI BAODING ENVIRONMENT PROTECTION ENG TECH & SERVICES
Filing Date
2026-04-21
Publication Date
2026-06-12

AI Technical Summary

Technical Problem

In the construction of steel structures for large industrial plants, traditional methods for installing zenith lighting systems have problems such as high risks of working at heights, low construction efficiency, difficulty in controlling quality, and serious interference with the main structure. Existing improvement solutions have failed to fundamentally change the logic of high-altitude construction.

Method used

The pre-assembly collaborative construction method for industrial plant ceiling lighting is adopted. Before the steel structure components are hoisted, pipelines are pre-laid, lines are pre-threaded, and connection bases are pre-installed on the ground to form standardized interface modules. After the steel structure components are hoisted into place, they are finally connected, realizing a parallel collaborative process and reducing the amount of high-altitude work.

Benefits of technology

It significantly reduces the time spent working at height and the risk of safety accidents, improves construction efficiency, ensures construction quality, reduces costs, simplifies high-altitude operations, and provides standardized interfaces for convenient later maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122190504A_ABST
    Figure CN122190504A_ABST
Patent Text Reader

Abstract

The application provides an industrial plant zenith lighting pre-assembly collaborative construction method, system and medium. The method comprises the following steps: confirming lighting pipe path on each steel structure component, junction box position, lamp installation point and pre-assembly unit division; performing pipeline pre-laying, line pre-threading, connection base pre-installation and positioning marking in the ground operation area to complete lighting pre-assembly on the steel structure component; hoisting the steel structure component with completed lighting pre-assembly as a whole hoisting unit, hoisting it into place and fixing it; after hoisting each steel structure component into place and fixing it, performing terminal connection of the lighting system. The application innovates the traditional "structure completion -> high-altitude lighting construction" into a parallel collaborative process of "structure ground pre-assembly -> collaborative hoisting -> ground terminal connection", and transfers more than 80% of the work load of pipe laying and threading, which is high-altitude operation, to the ground to be completed safely and efficiently, so that the high-altitude operation time ratio of the lighting construction of the plant is reduced from about 70% in the traditional method to less than 15%, and the main high-altitude operation is only the final hanging and plugging of the lamps.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of electromechanical installation technology in industrial plant buildings, and more specifically, to a collaborative construction method, system, and medium for pre-assembly of ceiling lighting in industrial plants. Background Technology

[0002] In the construction of large industrial plants, especially steel-structured plants, the ceiling lighting system typically needs to be installed on steel beams or the lower chord of roof trusses at a high location. Currently, the industry generally adopts a sequential construction model, which involves first completing the hoisting and high-altitude welding of the main steel structure of the plant, such as steel columns, steel beams, and purlins. After the main structure forms a stable working platform, construction workers then climb to the height to install the lighting system. This subsequent installation process specifically includes a series of electrical operations at height, such as electrical conduit installation, wiring, fixing of lamp holders and lamps, wiring connection, and debugging.

[0003] However, the traditional "structure first, lighting later" installation method has the following significant drawbacks: First, working at heights carries high risks. Because many electrical procedures, such as piping, wiring, and connection work, must be performed at height, workers are exposed to the risk of falls for extended periods. Although safety platforms and safety harnesses are implemented on construction sites, these measures only reduce the severity of injury in the event of an accident and cannot fundamentally eliminate the danger of workers operating near edges at heights. Furthermore, the safety facilities and management costs invested in ensuring the safety of working at heights significantly increase the overall project cost.

[0004] Secondly, construction efficiency is low and labor costs are high. High-altitude operations are severely affected by weather changes such as strong winds, rain, snow, and other cross-disciplinary construction activities such as equipment hoisting and pipeline installation, making them impossible to carry out continuously and efficiently like ground-based operations. Furthermore, high-altitude operations demand higher levels of skill, physical fitness, and psychological resilience from construction workers, resulting in significantly higher labor costs than ground-based operations. These two factors combined lead to overall low construction efficiency and difficulty in ensuring the project schedule is met.

[0005] Third, construction quality is difficult to control effectively. Laying and connecting pipelines at high altitudes restricts the operator's posture and makes it difficult to establish accurate work benchmarks, easily leading to common quality problems such as uneven pipeline laying, loose pipe joints, and insecure fixing. These quality issues are difficult to detect and rectify in a timely manner under high-altitude conditions, potentially posing safety hazards to the normal operation of the lighting system later.

[0006] Fourth, there is significant overlap and interference with the main structure and other professional construction work. Traditional methods schedule most of the lighting system work after the main steel structure is completed, inevitably leading to time and space conflicts between lighting construction and subsequent equipment installation, interior decoration, and other processes. To avoid safety risks and efficiency losses caused by overlapping work, additional coordination and waiting time is often required, thus extending the overall project construction period.

[0007] To address the aforementioned issues, some improvements have been attempted in existing technologies. For example, luminaires are pre-installed on light poles or brackets on the ground to form semi-finished products, or a dedicated aerial work platform is used for auxiliary installation. However, these solutions do not fundamentally change the sequential construction logic of "installing the lighting system after the main structure is completed." The core installation work of the lighting system still needs to be carried out at high altitude after the structure is hoisted. Summary of the Invention

[0008] In view of this, the present invention proposes a pre-assembled collaborative construction method, system and medium for ceiling lighting in industrial plants, aiming to solve existing problems.

[0009] On one hand, this invention proposes a collaborative construction method for pre-assembly of ceiling lighting in industrial plants. This method includes the following steps: a pre-assembly preparation step, confirming the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component; a ground pre-assembly step, where, before hoisting the steel structure components, pre-laying of pipelines, pre-threading of lines, pre-installation of connecting bases, and positioning markings are carried out in the ground work area to complete the lighting pre-assembly on the steel structure components; wherein, the connecting bases are used to connect the lighting fixtures; a collaborative hoisting step, where the pre-assembled steel structure components are hoisted into place and fixed as a whole hoisting unit; and an on-site installation and final connection step, where, after each steel structure component is hoisted into place and fixed, the lighting system is finally connected.

[0010] Furthermore, in the above-mentioned pre-assembly collaborative construction method for ceiling lighting of industrial plants, the pre-assembly preparation step includes the following sub-steps: steel modeling sub-step, modeling the main steel beams, purlins, stiffening plates, and hoisting lugs in Tekla Structures, and dividing each purlin into pre-assembly units to obtain the steel structure reference model; The lighting modeling sub-step involves creating JDG conduit parametric families, lighting cable parametric families, and connection base parametric families in Revit, and modeling the lighting system based on the steel structure baseline model. The lighting system model includes conduit models, luminaire models, and connection base models. The model integration sub-step imports the steel structure baseline model and lighting system model into Navisworks for integrated integration, performing full-dimensional hard and soft collision detection to eliminate interference between conduits, connection bases, steel structure components, and hoisting parts, thus forming a unified zenith lighting model. The pre-simulation sub-step performs 4D construction simulation on the unified zenith lighting model to verify the feasibility of the entire process of ground pre-assembly, collaborative hoisting, and on-site termination. The output sub-step outputs unified pre-assembly construction drawings, a processing list, unit identification diagrams, and visual handover documents, determining the lighting conduit paths, junction box locations, luminaire installation points, and pre-assembly unit divisions on each steel structure component.

[0011] Furthermore, in the above-mentioned collaborative construction method for pre-assembly of ceiling lighting in industrial plants, the ground pre-assembly step includes the following sub-steps: a pipeline pre-laying sub-step, where, based on the lighting piping path determined in the pre-assembly preparation step, cable protection pipes are fixed to the steel structure components, with threaded joints or clamps connecting the pipes; a line pre-threading sub-step, where lighting cables or traction steel wires are pre-threaded into the protection pipes, with a preset length reserved at both ends, and cable markings are made; a connection base pre-installation sub-step, where, based on the lamp installation points determined in the pre-assembly preparation step, connection bases are initially installed at the lamp installation points; and a positioning and marking sub-step, where the hoisted orientation, number, and interface correspondence with adjacent lighting units are marked on the steel structure components.

[0012] Furthermore, in the aforementioned pre-assembly collaborative construction method for ceiling lighting in industrial plants, the on-site installation and final connection steps include the following sub-steps: a modular luminaire installation sub-step, in which matching modular luminaires are fixed to the base body of the connecting base through a locking mechanism on the connecting base, and the plug-in connection with the terminals on the connecting base is completed; a unit-to-unit wiring connection sub-step, in which the cables reserved by adjacent pre-assembly units are connected through a waterproof and dustproof junction box at the nodes of the pre-assembly units to achieve circuit continuity; and a system testing and debugging sub-step, in which insulation resistance testing, circuit power-on testing, luminaire lighting debugging, and illuminance testing are performed.

[0013] Another invention proposes a collaborative construction system for pre-assembly of ceiling lighting in industrial plants, comprising: a pre-assembly preparation module for confirming the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component; a ground pre-assembly module for pre-laying pipelines, pre-threading lines, pre-installing connecting bases, and marking positions in the ground work area before hoisting the steel structure components, so as to complete the lighting pre-assembly on the steel structure components; wherein, the connecting base is used to insert lighting fixtures; a collaborative hoisting module for hoisting and fixing the pre-assembled lighting steel structure components as a whole hoisting unit; and an on-site installation and termination module for terminating the lighting system after each steel structure component has been hoisted and fixed.

[0014] Furthermore, the aforementioned collaborative construction system for pre-assembled ceiling lighting in industrial plants includes a pre-assembly preparation module comprising: a steel modeling submodule, used to model the main steel beams, purlins, stiffening plates, and hoisting lugs in Tekla Structures, and to divide individual purlins into pre-assembly units to obtain a steel structure baseline model; a lighting modeling submodule, used to create JDG pipe parametric families, lighting cable parametric families, and connection base parametric families in Revit, and to model the lighting system model based on the steel structure baseline model; wherein the lighting system model includes a piping model, a luminaire model, and a connection base model; and a model integration submodule, used to import the steel structure baseline model and the lighting system model into Navisworks. The system integrates and conducts full-dimensional hard and soft collision detection to eliminate interference between pipelines, connecting bases, steel structure components, and hoisting parts, forming an integrated zenith lighting model. The pre-simulation submodule is used to perform 4D construction simulation on the integrated zenith lighting model to verify the feasibility of the entire process of ground pre-assembly, collaborative hoisting, and on-site termination. The output submodule is used to output integrated pre-assembly construction drawings, processing lists, unit identification diagrams, and visual handover documents, determining the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component.

[0015] Furthermore, in the aforementioned collaborative construction system for pre-assembly of ceiling lighting in industrial plants, the ground pre-assembly module includes: a pipeline pre-laying sub-module, used to fix cable protection pipes to steel structure components based on the lighting piping path determined in the pre-assembly preparation steps, with threaded joints or special clamps connecting the pipes; a line pre-threading sub-module, used to pre-thread lighting cables or traction steel wires into the protection pipes, leaving a preset length at both ends and marking the cables; a connection base pre-installation sub-module, used to initially install connection bases at the lighting fixture installation points determined in the pre-assembly preparation steps; and a positioning and marking sub-module, used to mark the hoisted orientation, number, and interface correspondence with adjacent lighting units on the steel structure components.

[0016] Furthermore, in the aforementioned pre-assembled collaborative construction system for ceiling lighting in industrial plants, the on-site installation and termination module includes: a modular luminaire installation sub-module, used to fix the matching modular luminaires to the base body of the connecting base through a locking mechanism on the connecting base, and to complete the plug-in connection with the wiring terminals on the connecting base; an inter-unit wiring connection sub-module, used to connect the cables reserved in adjacent pre-assembled units at the nodes of the pre-assembled units through a waterproof and dustproof junction box to achieve circuit continuity; and a system testing and debugging sub-module, used to perform insulation resistance testing, circuit power-on testing, luminaire lighting debugging, and illuminance testing.

[0017] In another aspect, the present invention also provides a computer-readable storage medium storing a computer program for performing the methods described in any of the above aspects.

[0018] In another aspect, the present invention also proposes an electronic device comprising: a processor; a memory for storing executable instructions of the processor; the processor being configured to read the executable instructions from the memory and execute the instructions to implement the method described in any of the preceding aspects.

[0019] The present invention provides a pre-assembly collaborative construction method, system, and medium for industrial plant ceiling lighting, which revolutionizes the traditional sequential process of "structural completion → high-altitude lighting construction" (i.e., "high-altitude lighting construction after structural completion") into a parallel collaborative process of "structural ground pre-assembly → collaborative hoisting → ground final connection" (i.e., "structural ground pre-assembly, collaborative hoisting, and ground final connection"). This transfers more than 80% of the workload for high-altitude operations, such as piping and wiring, to safe and efficient ground completion. As a result, the proportion of high-altitude operation time for lighting construction in the plant is reduced from about 70% in the traditional method to less than 15%, with the main high-altitude operation being only the final hanging and plugging of the lamps. At the same time, by setting up a pre-assembly connection base with integrated load-bearing fixing, electrical connection, and anti-misinsertion guidance functions, a standardized interface module is formed, realizing plug-and-play of lamps and simplifying high-altitude operations to hanging and plugging operations. This construction method fundamentally reduces the exposure time and labor intensity of construction workers at dangerous heights, lowers the risk of safety accidents such as falls and electric shocks, and significantly improves work efficiency through ground-based assembly line operations, saving on high-altitude operation measures and labor costs. The overall construction cost can be reduced by 30% to 40%. In addition, the good ground pre-assembly environment is conducive to ensuring the construction quality such as horizontal and vertical piping and tight joints. The standardized joints also provide great convenience for the later replacement and maintenance of lighting fixtures. Attached Figure Description

[0020] Various other advantages and benefits will become apparent to those skilled in the art upon reading the following detailed description of preferred embodiments. The accompanying drawings are for illustrative purposes only and are not intended to limit the invention. Furthermore, the same reference numerals denote the same parts throughout the drawings. In the drawings: Figure 1 A flowchart illustrating the pre-assembly and collaborative construction method for ceiling lighting in industrial plants provided in this embodiment of the invention; Figure 2 This is a structural schematic diagram of the pre-assembly collaborative construction method for ceiling lighting in industrial plants provided in an embodiment of the present invention; Figure 3 This is a structural schematic diagram of the pre-assembly collaborative construction method for ceiling lighting in industrial plants provided in an embodiment of the present invention; Figure 4 A flowchart illustrating the pre-assembly preparation steps provided in an embodiment of the present invention; Figure 5 A flowchart illustrating the ground pre-assembly steps provided in an embodiment of the present invention; Figure 6 A flowchart illustrating the on-site installation and termination steps provided in this embodiment of the invention; Figure 7 A structural block diagram of the pre-assembled collaborative construction system for ceiling lighting in industrial plants provided in this embodiment of the invention; Figure 8 This is a structural block diagram of the pre-assembly preparation module provided in an embodiment of the present invention; Figure 9 This is a structural block diagram of the ground pre-assembled module provided in an embodiment of the present invention; Figure 10 This is a structural block diagram of the field installation termination module provided in an embodiment of the present invention; Figure 11 A structural block diagram of an electronic device provided in an embodiment of the present invention; Explanation of reference numerals in the attached figures: 1-Pre-assembly unit, 2-Connecting base, 3-JDG pipe, 4-Gate box. Detailed Implementation

[0021] Hereinafter, exemplary embodiments according to the present invention will be described in detail with reference to the accompanying drawings. Obviously, the described embodiments are merely some embodiments of the present invention, and not all embodiments of the present invention. It should be understood that the present invention is not limited to the exemplary embodiments described herein.

[0022] It should be noted that, unless otherwise specifically stated, the relative arrangement, numerical expressions, and values ​​of the components and steps described in these embodiments do not limit the scope of the invention.

[0023] Those skilled in the art will understand that the terms "first," "second," etc., in the embodiments of the present invention are only used to distinguish different steps, devices, or modules, and do not represent any specific technical meaning, nor do they indicate a necessary logical order between them.

[0024] It should also be understood that in the embodiments of the present invention, "multiple" can refer to two or more, and "at least one" can refer to one, two or more.

[0025] It should also be understood that any component, data or structure mentioned in the embodiments of the present invention can generally be understood as one or more unless explicitly defined or given contrary instructions in the context.

[0026] Furthermore, the term "and / or" in this invention is merely a description of the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent: A existing alone, A and B existing simultaneously, or B existing alone. Additionally, the character " / " in this invention generally indicates that the preceding and following related objects have an "or" relationship.

[0027] It should also be understood that the description of the various embodiments in this invention emphasizes the differences between the various embodiments, and the similarities or similarities can be referred to each other. For the sake of brevity, they will not be described in detail.

[0028] At the same time, it should be understood that, for ease of description, the dimensions of the various parts shown in the accompanying drawings are not drawn according to actual scale.

[0029] The following description of at least one exemplary embodiment is merely illustrative and is in no way intended to limit the invention or its application or use.

[0030] Techniques, methods, and equipment known to those skilled in the art may not be discussed in detail, but where appropriate, they should be considered part of the specification.

[0031] It should be noted that similar labels and letters in the following figures indicate similar items; therefore, once an item is defined in one figure, it does not need to be discussed further in subsequent figures.

[0032] The embodiments of this invention can be applied to electronic devices such as terminal devices, computer systems, and servers, and can operate together with a wide range of other general-purpose or special-purpose computing system environments or configurations. Well-known examples of terminal devices, computing systems, environments, and / or configurations suitable for use with electronic devices such as terminal devices, computer systems, and servers include, but are not limited to: personal computer systems, server computer systems, thin clients, thick clients, handheld or laptop devices, microprocessor-based systems, set-top boxes, programmable consumer electronics, network PCs, minicomputer systems, mainframe computer systems, and distributed cloud computing environments including any of the above systems, etc.

[0033] Electronic devices such as terminal devices, computer systems, and servers can be described in the general context of computer system executable instructions (such as program modules) executed by a computer system. Typically, program modules can include routines, programs, object programs, components, logic, data structures, etc., which perform specific tasks or implement specific abstract data types. Computer systems / servers can be implemented in distributed cloud computing environments, where tasks are executed by remote processing devices linked through communication networks. In distributed cloud computing environments, program modules can reside on local or remote computing system storage media, including storage devices.

[0034] Method Implementation Examples: See Figure 1 This is a flowchart illustrating the pre-assembly and collaborative construction method for ceiling lighting in industrial plants provided in this embodiment of the invention. As shown in the figure, the construction method includes the following steps: Pre-assembly preparation step S1: Confirm the lighting piping path, junction box location, lamp installation point, and pre-assembly unit division on each steel structure component.

[0035] Specifically, BIM can be used first for the coordinated and detailed design of lighting and steel structure construction, resulting in detailed lighting and steel structure construction drawings. In particular, a joint design team should be formed, encompassing steel structure detailing, lighting and electrical systems, construction technology, prefabrication, and hoisting operations. This collaborative detailing design should be conducted using the integrated BIM platform of Tekla Structures + Revit + Navisworks: using the factory's grid lines, elevations, and coordinate systems as a unified benchmark, and achieving seamless interoperability of professional models through the IFC international standard format. Based on the detailed lighting and steel structure construction drawings, the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component should be determined. The steel structure components include main steel beams, secondary beams, and purlins.

[0036] In ground pre-assembly step S2, before the steel structure components are hoisted, pipelines are pre-laid, lines are pre-threaded, connecting bases are pre-installed, and positioning marks are made in the ground work area to complete the lighting pre-assembly on the steel structure components; among them, the connecting base is used to plug in the lighting fixtures.

[0037] Specifically, before the steel structure components are hoisted, the following work is completed in the ground work area: pre-laying of pipelines, i.e., JDG pipe 3, pre-threading of lines, pre-installation of connecting base 2, and positioning marking, such as... Figure 2 As shown, the standardized interface module design is achieved through the connecting base 2, which integrates load-bearing fixation, electrical connection, and anti-misinsertion guidance functions, realizing the "plug and play" of the lamps. This simplifies high-altitude operations to a simple lamp hanging and plugging / unplugging operation, greatly shortening the high-altitude operation time.

[0038] In the collaborative hoisting step S3, the steel structure component that has completed the pre-assembly of lighting is hoisted into place and fixed as a whole hoisting unit.

[0039] Specifically, pre-assembled steel structure components for lighting are hoisted as a whole unit, and hoisted, positioned, aligned, and fixed according to steel structure hoisting procedures. Tracked hoisting can be used. During hoisting, temporary protective measures are taken for the pre-installed lighting conduits and interfaces, and flexible sheaths can be used to protect exposed base interfaces. After the purlins are in place, they are bolted or welded for fixation.

[0040] Step S4 involves terminating the lighting system after all steel structure components have been hoisted into place and secured.

[0041] Specifically, after all purlins are installed, construction workers use a mobile lifting platform to align the lighting fixtures with the connecting base 2 and plug them into the connecting base 2, achieving mechanical shortening and automatic connection of electrical plugs. At the intersection of the main and secondary roof beams, an IP65-rated junction box 4 is installed. Cables from adjacent purlin units (i.e., pre-assembled units 1) are led into the box and connected in parallel via terminal blocks. Figure 3 As shown. After everything is completed, perform system debugging.

[0042] See Figure 4 This is a flowchart of the pre-assembly preparation step provided in an embodiment of the present invention. As shown in the figure, the pre-assembly preparation step S1 includes the following sub-steps: In the steel modeling sub-step S11, the main steel beams, purlins, stiffening plates, and hoisting lugs are modeled in Tekla Structures, and each purlin is divided into pre-assembly units to obtain the steel structure baseline model.

[0043] Specifically, each purlin is divided into pre-assembly unit 1, and the main steel beam, purlin, stiffening plate, and hoisting lug are modeled with high precision at LOD400 in Tekla Structures to obtain the steel structure reference model.

[0044] In the lighting modeling sub-step S12, a JDG pipe parametric family, a lighting cable parametric family, and a connection base parametric family are created in Revit. Based on the steel structure baseline model, the lighting system model is modeled. The lighting system model includes a piping model, a luminaire model, and a connection base model.

[0045] Specifically, in Revit, parametric families such as JDG pipes, lighting cables, and pre-assembled connection bases 2 are created. Based on the steel structure reference model, the piping path planning, the three-dimensional coordinate calibration of the luminaire installation points, and the base interface layout design are completed to obtain the lighting system model.

[0046] In the model integration sub-step S13, the steel structure reference model and the lighting system model are imported into Navisworks for integrated integration. Hard and soft collision detection is carried out in all dimensions to eliminate interference between pipelines, connecting bases and steel structure components and hoisting parts in a closed loop, thus forming an integrated zenith lighting model.

[0047] Specifically, the two models are imported into Navisworks for integrated processing, enabling full-dimensional detection of hard and soft collisions, and closed-loop elimination of interference issues between pipelines, bases, steel structure components, and hoisting parts.

[0048] In the pre-simulation sub-step S14, a 4D construction simulation is performed on the integrated zenith lighting model to verify the feasibility of the entire process of ground pre-assembly, collaborative hoisting, and on-site final connection.

[0049] Specifically, the pre-assembly unit 1 was further solidified, the base parameters were calibrated, the pipeline fixing scheme was optimized, and the identification system was designed. The feasibility of the entire process of ground pre-assembly, collaborative hoisting, and on-site final connection was verified through 4D construction simulation.

[0050] Output sub-step S15, output integrated pre-assembly construction drawings, processing list, unit identification diagram and visual handover documents, and determine the lighting piping path, junction box location, lamp installation point and pre-assembly unit division on each steel structure component.

[0051] Specifically, the final output includes integrated pre-assembled construction drawings, a processing list, unit identification diagrams, and visual handover documents. Based on the above BIM collaborative deepening results, the path of the 20mm diameter JDG conduit, the locations of two junction boxes, and the coordinates of four lighting fixture installation points are clearly defined for each unit. The connecting base 2 includes: a base body, terminals mounted on the connecting base 2, and a locking mechanism mounted on the connecting base 2. The locking mechanism is used to lock the lighting fixtures and can be a three-claw rotating snap-fit ​​structure, or other structures such as rotating snap-fits or bolts. In this embodiment, the pre-assembled connecting base 2 can be fixed to the purlin web plate with two M10 high-strength bolts. The upper part is equipped with a six-pin waterproof plug socket with a foolproof key. The mechanical part is a three-claw rotating snap-fit ​​locking mechanism, which enables "plug-and-play" operation of the lighting fixtures, simplifying high-altitude work to simple lamp hanging and plugging / unplugging operations, greatly reducing high-altitude work time.

[0052] See Figure 5 This is a flowchart of the ground pre-assembly step provided in an embodiment of the present invention. As shown in the figure, the ground pre-assembly step S2 may include the following sub-steps: In the pipeline pre-laying sub-step S21, based on the lighting piping path determined in the pre-assembly preparation step, the cable protection pipe is fixed to the steel structure component, and the pipes are connected by threaded joints or clamps.

[0053] Specifically, in the steel structure processing plant or on-site ground prefabrication yard, the purlins are placed horizontally; first, based on the lighting piping path determined in the pre-assembly preparation steps, the JDG pipe 3, i.e. the cable protection pipe, is fixed to the lower flange of the purlin using pipe clamps as shown in the figure, and the pipes are connected by threaded joints or special clamps.

[0054] In step S22, the lighting cable or traction wire is pre-threaded into the protective tube, with a preset length reserved at both ends, and the cable is marked.

[0055] Specifically, the lighting cable or traction wire is pre-threaded into the protective conduit, for example, an RVV-3x2.5 lighting cable can be threaded in. A preset length is reserved at both ends of the lighting cable, and the cable is clearly marked. The preset length can be determined according to actual conditions; this embodiment does not impose any limitations on it.

[0056] In the pre-installation sub-step S23 of the connecting base, the connecting base is initially installed at the lamp installation point based on the lamp installation point determined in the pre-assembly preparation step.

[0057] Specifically, at the designed lighting fixture mounting points, pre-assembled connection bases 2 are installed and can be fixed to the purlins with bolts. For example, pre-assembled connection bases 2 are installed at four mounting points, and the corresponding wire cores of the cable are connected to the terminals inside the base.

[0058] In the positioning and marking sub-step S24, the orientation, number, and interface correspondence with adjacent lighting units are marked on the steel structure components after hoisting.

[0059] Specifically, mark the orientation, number, and interface correspondence with adjacent lighting units in a prominent position on the component after hoisting. For example, use eye-catching paint to mark "Lighting Unit - Number" and directional arrows at both ends of the purlin to indicate the installation direction.

[0060] See Figure 6 This is a flowchart of the on-site installation and termination steps provided in an embodiment of the present invention. As shown in the figure, the on-site installation and termination step S4 includes the following sub-steps: In the modular lighting installation sub-step S41, the matching modular lighting fixture is fixed to the base body of the connecting base through the locking mechanism on the connecting base, and the plug-in connection with the wiring terminals on the connecting base is completed.

[0061] Specifically, after all the purlins are installed, the construction workers use a mobile lifting platform to align the LED industrial and mining lamps with the base and rotate them about 60 degrees to complete the mechanical locking. At the same time, the electrical plugs are automatically connected.

[0062] In the inter-unit wiring connection sub-step S42, at the pre-assembled unit node, the cables reserved by the adjacent pre-assembled units are connected through a waterproof and dustproof junction box to achieve circuit continuity.

[0063] Specifically, at the intersection of the main beam and the secondary beam of the roof, a junction box 4 with an IP65 protection rating is installed to bring the cables of the adjacent purlin units into the box and complete the parallel connection through the terminal block.

[0064] System testing and debugging sub-step S43 involves performing insulation resistance testing, circuit power-on testing, lamp lighting debugging, and illuminance testing.

[0065] Specifically, insulation resistance testing, circuit power-on testing, lamp lighting debugging, and illuminance testing are conducted.

[0066] In summary, the pre-assembly collaborative construction method for industrial plant ceiling lighting provided in this embodiment revolutionizes the traditional sequential process of "structural completion → high-altitude lighting construction" (i.e., "high-altitude lighting construction after structural completion") into a parallel collaborative process of "structural ground pre-assembly → collaborative hoisting → ground final connection" (i.e., "structural ground pre-assembly, collaborative hoisting, and ground final connection"). This transfers more than 80% of the workload for high-altitude operations, such as piping and wiring, to safe and efficient ground-based completion. Consequently, the proportion of high-altitude operation time for lighting construction in this plant is reduced from approximately 70% in the traditional method to less than 15%, with the main high-altitude operation being only the final connection and plugging of the lamps. At the same time, by setting up a pre-assembly connection base 2 that integrates load-bearing fixation, electrical connection, and anti-misinsertion guidance functions, a standardized interface module is formed, enabling plug-and-play functionality for the lamps and simplifying high-altitude operations to connection and plugging operations. This construction method fundamentally reduces the exposure time and labor intensity of construction workers at dangerous heights, lowers the risk of safety accidents such as falls and electric shocks, and significantly improves work efficiency through ground-based assembly line operations, saving on high-altitude operation measures and labor costs. The overall construction cost can be reduced by 30% to 40%. In addition, the good ground pre-assembly environment is conducive to ensuring the construction quality such as horizontal and vertical piping and tight joints. The standardized joints also provide great convenience for the later replacement and maintenance of lighting fixtures.

[0067] System Implementation Example: See Figure 7 This is a structural block diagram of the pre-assembly collaborative construction system for ceiling lighting in an industrial plant provided by an embodiment of the present invention. As shown in the figure, the collaborative construction system includes: a pre-assembly preparation module 100, a ground pre-assembly module 200, a collaborative hoisting module 300, and an on-site installation and termination module 400; wherein, the pre-assembly preparation module 100 is used to confirm the lighting piping path, junction box location, lamp installation point, and pre-assembly unit division on each steel structure component; the ground pre-assembly module 200 is used to pre-lay pipelines, pre-thread lines, pre-install connecting bases, and mark positions in the ground work area before hoisting the steel structure components, so as to complete the lighting pre-assembly on the steel structure components; wherein, the connecting base is used to insert lighting lamps; the collaborative hoisting module 300 is used to hoist the pre-assembled lighting steel structure components as a whole hoisting unit, and fix them in place; the on-site installation and termination module 400 is used to terminate the lighting system after each steel structure component is hoisted in place and fixed.

[0068] See Figure 8This is a structural block diagram of the pre-assembly preparation module provided in this embodiment of the invention. As shown in the figure, the pre-assembly preparation module 100 includes: a steel modeling submodule 110, used to model the main steel beams, purlins, stiffening plates, and lifting lugs in Tekla Structures, and to divide a single purlin into pre-assembly units to obtain a steel structure reference model; a lighting modeling submodule 120, used to create JDG pipe parametric families, lighting cable parametric families, and connection base parametric families in Revit, and to model the lighting system model based on the steel structure reference model; wherein, the lighting system model includes a piping model, a luminaire model, and a connection base model; and a model integration submodule 130, used to import the steel structure reference model and the lighting system model into Navisworks. The system integrates and conducts full-dimensional hard and soft collision detection to eliminate interference between pipelines, connecting bases, steel structure components, and hoisting parts, forming an integrated zenith lighting model. The pre-simulation submodule 140 is used to perform 4D construction simulation on the integrated zenith lighting model to verify the feasibility of the entire process of ground pre-assembly, collaborative hoisting, and on-site termination. The output submodule 150 is used to output integrated pre-assembly construction drawings, processing lists, unit identification diagrams, and visual handover documents, determining the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component.

[0069] See Figure 9 This is a structural block diagram of the ground pre-assembly module provided in the embodiment of the present invention. As shown in the figure, the ground pre-assembly module 300 includes: a pipeline pre-laying submodule 310, used to fix the cable protection pipe to the steel structure component based on the lighting piping path determined in the pre-assembly preparation step, with the pipes connected by threaded joints or special clamps; a line pre-threading module 320, used to pre-thread the lighting cable or traction steel wire into the protection pipe, leaving a preset length at both ends, and marking the cable; a connecting base pre-installation submodule 330, used to initially install the connecting base at the lighting fixture installation point determined in the pre-assembly preparation step; and a positioning marking submodule 340, used to mark the orientation, number, and interface correspondence with adjacent lighting units on the steel structure component after hoisting.

[0070] See Figure 10This is a structural block diagram of the field installation termination module provided in this embodiment of the invention. As shown in the figure, the field installation termination module 400 includes: a modular lighting fixture installation submodule 410, an inter-unit wiring connection submodule 420, and a system testing and debugging submodule 430; wherein, the modular lighting fixture installation submodule 410 is used to fix the matching modular lighting fixtures to the base body of the connecting base through the locking mechanism on the connecting base, and to complete the plug-in connection with the wiring terminals on the connecting base; the inter-unit wiring connection submodule 420 is used to connect the cables reserved by adjacent pre-assembled units at the pre-assembled unit nodes through a waterproof and dustproof junction box to achieve circuit continuity; the system testing and debugging submodule 430 is used to perform insulation resistance testing, circuit power-on testing, lighting fixture commissioning, and illuminance testing.

[0071] Preferably, the connecting base includes: a base body, a terminal block disposed on the connecting base, and a locking mechanism disposed on the connecting base; wherein the locking mechanism is used to lock the lighting fixture.

[0072] Preferably, the locking mechanism is a three-jaw rotary snap-lock structure.

[0073] Exemplary electronic devices See Figure 9 This is a structural block diagram of the electronic device provided in an embodiment of the present invention. For example... Figure 11 As shown, the electronic device 500 includes one or more processors 501 and memory 502.

[0074] The processor 501 may be a central processing unit (CPU) or other form of processing unit with data processing and / or instruction execution capabilities, and may control other components in the electronic device to perform desired functions.

[0075] Memory 502 may include one or more computer program products, which may include various forms of computer-readable storage media, such as volatile memory and / or non-volatile memory. The volatile memory may include, for example, random access memory (RAM) and / or cache memory. The non-volatile memory may include, for example, read-only memory (ROM), hard disk, flash memory, etc. One or more computer program instructions may be stored on the computer-readable storage medium, and processor 501 may execute the program instructions to implement the methods of the software programs of the various embodiments of the present invention described above, and / or other desired functions. In one example, the electronic device may also include an input device 503 and an output device 504, these components being interconnected via a bus system and / or other forms of connection mechanisms (not shown).

[0076] In addition, the input device 503 may also include, for example, a keyboard, a mouse, etc.

[0077] The output device 504 can output various information to the outside. The output device 504 may include, for example, a display, a speaker, a printer, and a communication network and its connected remote output devices, etc.

[0078] Of course, for the sake of simplicity, Figure 11 Only some of the components of this electronic device relevant to the present invention are shown, omitting components such as buses, input / output interfaces, etc. In addition, the electronic device may include any other suitable components depending on the specific application.

[0079] Exemplary computer program products and computer-readable storage media In addition to the methods and apparatus described above, embodiments of the present invention may also be computer program products, which include computer program instructions that, when executed by a processor, cause the processor to perform the steps in the methods according to various embodiments of the present invention described in the "Exemplary Methods" section above.

[0080] The computer program product can be written in any combination of one or more programming languages ​​to perform the operations of the embodiments of the present invention. The programming languages ​​include object-oriented programming languages ​​such as Java and C++, as well as conventional procedural programming languages ​​such as C or similar languages. The program code can be executed entirely on the user's computing device, partially on the user's computing device, as a standalone software package, partially on the user's computing device and partially on a remote computing device, or entirely on a remote computing device or server.

[0081] Furthermore, embodiments of the present invention may also be computer-readable storage media storing computer program instructions thereon, which, when executed by a processor, cause the processor to perform the steps of the methods according to various embodiments of the present invention described in the "Exemplary Methods" section above.

[0082] The computer-readable storage medium may be any combination of one or more readable media. A readable medium may be a readable signal medium or a readable storage medium. A readable storage medium may be, for example, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or any combination thereof. More specific examples (a non-exhaustive list) of readable storage media include: an electrical connection having one or more wires, a portable disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof.

[0083] The basic principles of the present invention have been described above with reference to specific embodiments. However, it should be noted that the advantages, benefits, and effects mentioned in the present invention are merely examples and not limitations, and should not be considered as essential features of each embodiment of the present invention. Furthermore, the specific details disclosed above are for illustrative and facilitative purposes only, and are not limitations. These details do not limit the present invention to the necessity of employing the aforementioned specific details.

[0084] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on its differences from other embodiments. Similar or identical parts between embodiments can be referred to interchangeably. For system embodiments, since they largely correspond to method embodiments, the description is relatively simple; relevant parts can be referred to the descriptions in the method embodiments.

[0085] The block diagrams of devices, systems, devices, and systems involved in this invention are merely illustrative examples and are not intended to require or imply that they must be connected, arranged, or configured in the manner shown in the block diagrams. As those skilled in the art will recognize, these devices, systems, devices, and systems can be connected, arranged, and configured in any manner. Words such as “comprising,” “including,” “having,” etc., are open-ended terms meaning “including but not limited to,” and are used interchangeably with them. The terms “or” and “and” as used herein refer to the terms “and / or,” and are used interchangeably with them unless the context clearly indicates otherwise. The term “such as” as used herein refers to the phrase “such as but not limited to,” and is used interchangeably with it.

[0086] The methods and systems of the present invention may be implemented in many ways. For example, they may be implemented by software, hardware, firmware, or any combination of software, hardware, and firmware. The above-described order of steps for the methods is for illustrative purposes only, and the steps of the methods of the present invention are not limited to the order specifically described above unless otherwise specifically stated. Furthermore, in some embodiments, the present invention may also be implemented as a program recorded on a recording medium, the program comprising machine-readable instructions for implementing the methods according to the present invention. Thus, the present invention also covers recording media storing programs for performing the methods according to the present invention.

[0087] It should also be noted that in the systems, apparatus, and methods of the present invention, the components or steps can be disassembled and / or recombined. These disassemblies and / or recombinations should be considered equivalents of the present invention. The above description of the disclosed aspects is provided to enable any person skilled in the art to make or use the invention. Various modifications to these aspects will be readily apparent to those skilled in the art, and the general principles defined herein can be applied to other aspects without departing from the scope of the invention. Therefore, the invention is not intended to be limited to the aspects shown herein, but rather to be carried out within the widest scope consistent with the principles and novel features disclosed herein.

[0088] The above description has been given for purposes of illustration and description. Furthermore, this description is not intended to limit the embodiments of the invention to the forms disclosed herein. Although numerous exemplary aspects and embodiments have been discussed above, those skilled in the art will recognize certain variations, modifications, alterations, additions, and sub-combinations therein.

Claims

1. A collaborative construction method for pre-assembly of ceiling lighting in industrial plants, characterized in that, include: Pre-assembly preparation steps include confirming the lighting piping path, junction box location, lamp installation point, and pre-assembly unit division on each steel structure component; The ground pre-assembly step involves pre-laying pipelines, pre-threading lines, pre-installing connecting bases, and positioning markings in the ground work area before hoisting the steel structure components, so as to complete the pre-assembly of lighting on the steel structure components; among them, the connecting bases are used to plug in the lighting fixtures; The coordinated hoisting process involves hoisting and securing the pre-assembled steel structure components, which are treated as a single hoisting unit, into place. The on-site installation and termination process involves terminating the lighting system after all steel structure components have been hoisted into place and secured.

2. The pre-assembly and collaborative construction method for ceiling lighting in industrial plants according to claim 1, characterized in that, The pre-assembly preparation step includes the following sub-steps: The steel modeling sub-step involves modeling the main steel beams, purlins, stiffening plates, and hoisting lugs in Tekla Structures, and dividing each purlin into pre-assembly units to obtain the steel structure baseline model. The lighting modeling sub-step involves creating a JDG conduit parametric family, a lighting cable parametric family, and a connection base parametric family in Revit, and then modeling the lighting system model based on the steel structure baseline model. The lighting system model includes the piping model, the luminaire model, and the connection base model. The model integration sub-step involves importing the steel structure baseline model and the lighting system model into Navisworks for integrated integration, and conducting full-dimensional hard and soft collision detection to eliminate interference between pipelines, connecting bases and steel structure components and hoisting parts in a closed loop, thus integrating them into a unified zenith lighting model. The pre-simulation sub-step involves performing a 4D construction simulation on the integrated zenith lighting model to verify the feasibility of the entire process, including ground pre-assembly, collaborative hoisting, and on-site final connection. Output sub-steps include integrated pre-assembly construction drawings, processing lists, unit identification diagrams, and visual handover documents, which determine the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component.

3. The pre-assembly and collaborative construction method for ceiling lighting in industrial plants according to claim 1 or 2, characterized in that, The ground pre-assembly step includes the following sub-steps: In the pipeline pre-laying sub-step, based on the lighting piping route determined in the pre-assembly preparation step, the cable protection pipe is fixed to the steel structure component, and the pipes are connected by threaded joints or clamps. The pre-threading step involves threading the lighting cable or traction wire into the protective conduit, leaving a predetermined length at both ends, and clearly marking the cable. The pre-installation sub-step of connecting the base involves initially installing the connecting base at the lamp mounting point based on the lamp mounting point determined in the pre-assembly preparation step. The positioning and marking sub-step involves marking the hoisted location, number, and interface correspondence with adjacent lighting units on the steel structure components.

4. The pre-assembly and collaborative construction method for ceiling lighting in industrial plants according to claim 1 or 2, characterized in that, The on-site installation and termination steps include the following sub-steps: The modular lighting fixture installation sub-step involves fixing the matching modular lighting fixture to the base body of the connecting base using the locking mechanism on the connecting base, and completing the plug-in connection with the wiring terminals on the connecting base. In the inter-unit wiring connection sub-step, at the pre-assembled unit node, the cables reserved in adjacent pre-assembled units are connected through a waterproof and dustproof junction box to achieve circuit continuity. The system testing and debugging sub-steps include insulation resistance testing, circuit power-on testing, lamp lighting debugging, and illuminance testing.

5. A pre-assembled collaborative construction system for ceiling lighting in industrial plants, characterized in that, include: The pre-assembly preparation module is used to confirm the lighting piping path, junction box location, lamp installation point, and pre-assembly unit division on each steel structure component; The ground pre-assembly module is used to pre-lay pipelines, pre-thread lines, pre-install connecting bases, and mark positions in the ground work area before hoisting steel structure components, so as to complete the pre-assembly of lighting on the steel structure components; among them, the connecting base is used to plug in lighting fixtures; The collaborative hoisting module is used to hoist and fix pre-assembled steel structure components with lighting as a whole hoisting unit. The termination module is installed on site to terminate the lighting system after all steel structure components have been hoisted into place and fixed.

6. The pre-assembled collaborative construction system for industrial plant ceiling lighting according to claim 5, characterized in that, The pre-assembly preparation module includes: The steel modeling submodule is used to model the main steel beams, purlins, stiffening plates, and hoisting lugs in Tekla Structures, and to divide a single purlin into pre-assembled units to obtain the steel structure baseline model; The lighting modeling submodule is used to create JDG pipe parametric families, lighting cable parametric families, and connection base parametric families in Revit, and to model the lighting system model based on the steel structure baseline model; the lighting system model includes the piping model, luminaire model, and connection base model; The model integration submodule is used to import the steel structure baseline model and the lighting system model into Navisworks for integrated integration, and to carry out full-dimensional hard and soft collision detection, close-loop elimination of interference between pipelines, connecting bases and steel structure components, and hoisting components, and integrate them into an integrated zenith lighting model; The pre-simulation submodule is used to perform 4D construction simulation on the integrated zenith lighting model to verify the feasibility of the entire process of ground pre-assembly, collaborative hoisting and on-site final connection. The output submodule is used to output integrated pre-assembly construction drawings, processing lists, unit identification diagrams, and visual handover documents, and to determine the lighting piping paths, junction box locations, lamp installation points, and pre-assembly unit divisions on each steel structure component.

7. The pre-assembled collaborative construction system for industrial plant ceiling lighting according to claim 4 or 5, characterized in that, The ground pre-assembled module includes: The pipeline pre-laying submodule is used to fix the cable protection pipe to the steel structure component based on the lighting piping route determined in the pre-assembly preparation step, with the pipes connected by threaded joints or special clamps. The pre-threading module is used to pre-thread lighting cables or traction steel wires into the protective tube, with a preset length reserved at both ends, and the cables are clearly marked. The connecting base pre-installation sub-module is used to initially install the connecting base at the lamp installation point based on the lamp installation point determined in the pre-assembly preparation step; The positioning and marking submodule is used to mark the orientation, number, and interface correspondence with adjacent lighting units on steel structure components after hoisting.

8. The pre-assembled collaborative construction system for industrial plant ceiling lighting according to claim 4 or 5, characterized in that, The on-site installation termination module includes: The modular lighting fixture installation submodule is used to fix the matching modular lighting fixture to the base body of the connecting base through the locking mechanism on the connecting base, and to complete the plug-in connection with the wiring terminals on the connecting base; The inter-unit wiring connection submodule is used to connect the cables reserved in adjacent pre-assembled units at the nodes of the pre-assembled units through a waterproof and dustproof junction box to achieve circuit continuity. The system testing and debugging submodule is used for insulation resistance testing, circuit power-on testing, lamp lighting debugging, and illuminance testing.

9. A computer-readable storage medium, characterized in that, The storage medium stores a computer program for performing the method described in any one of claims 1 to 4.

10. An electronic device, characterized in that, The electronic device includes: processor; Memory used to store the processor's executable instructions; The processor is configured to read the executable instructions from the memory and execute the instructions to implement the method described in any one of claims 1 to 4.