A hierarchical multi-agent construction progress simulation method and system

CN122452379APending Publication Date: 2026-07-24中亿丰数字科技集团股份有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
中亿丰数字科技集团股份有限公司
Filing Date
2026-06-24
Publication Date
2026-07-24

AI Technical Summary

Technical Problem

In existing construction progress simulation methods, there is insufficient linkage between construction model data and scheduling decision data, unclear division of functions among multiple agents, resulting in low efficiency of collaborative decision-making, difficulty in continuously transmitting construction deviation and conflict states in the task chain, and the progress simulation process focuses on the playback of the initial plan and lacks a closed-loop iteration mechanism.

Method used

A hierarchical multi-agent construction progress simulation method is adopted. By importing construction project data into the construction information model, the construction process tasks are analyzed based on the hierarchical multi-agent structure, standardized construction task units and constraint feature information are generated, collaborative decision-making is carried out, construction status features are output, and the construction progress plan is iteratively adjusted.

Benefits of technology

It enables the invocation and write-back of construction objects, task sequences, resource constraints, and site constraints in the same data link, unifies the task running status, resource allocation status, and environment executable status, reduces scheduling conflicts caused by the homogenization of multi-agent functions and the disconnection of local decisions, and improves the consistency between the progress simulation model and the scheduling data and the accuracy of dynamic iteration.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122452379A_ABST
    Figure CN122452379A_ABST
Patent Text Reader

Abstract

The application discloses a layered multi-agent construction progress simulation method and system, and relates to the technical field of intelligent construction, which comprises the following steps: importing construction project data into a corresponding modeling tool to obtain a construction information model corresponding to the construction project; analyzing construction process tasks based on a layered multi-agent structure to obtain standardized construction task units and constraint characteristic information; executing the layered multi-agent structure in the construction information model to make collaborative decisions on the standardized construction task units, and outputting construction state characteristics; inputting the construction state characteristics and the constraint characteristic information into the layered multi-agent structure for iterative adjustment, and outputting a construction progress plan; and the method realizes unified scheduling of tasks, resources and constraints through the collaborative linkage of the construction information model and the layered multi-agent, and improves the dynamic adjustment precision of the construction progress simulation and the reliability of the plan output.