A double-sided locking curb stone buffer pad and its construction method

By designing a double-sided locking curbstone buffer pad, the problems of easy cracking and poor controllability of construction precision in the traditional rigid cement grouting process are solved. It achieves full sealing, dynamic self-locking and three-dimensional anchoring, adapts to different working conditions, and improves construction efficiency and durability.

CN123064072APending Publication Date: 2026-11-10刘凡亮
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611500577.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-24
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Traditional rigid cement grouting technology is prone to cracking and misalignment under conditions such as temperature expansion and contraction, root heave, and foundation settlement. It also has poor controllability of construction precision and is difficult to meet acceptance standards. Existing buffer pads are mostly single-sided protective structures, and the problems of three-dimensional anchoring and positioning and thickness variation of the pads have not been solved.

Method used

The double-sided locking curbstone buffer pad is designed with an outer sealing area, an oblique locking area and an anchoring tooth structure. It achieves cement-free grouting installation through mortar interlocking and soil embedding. It is compatible with pads of different thicknesses and combines oblique locking and three-dimensional anchoring technology.

Benefits of technology

It achieves full sealing and anti-fouling, oblique dynamic self-locking, elastic deformation adaptation and three-dimensional anchoring, eliminates gap defects, improves construction efficiency, reduces maintenance costs and meets long-term use requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064072A_ABST
    Figure CN123064072A_ABST
Patent Text Reader

Abstract

This invention discloses a double-sided locking curbstone buffer pad and its construction method, belonging to the field of municipal road construction materials technology. The invention features a one-piece molded elastic body with a gradient thickness of 3-12mm. Double-sided grooveless outer sealing zones achieve closed-loop seepage and pollution prevention. A 40°-45° oblique strip locking structure is located in the middle. Ultra-thin specifications utilize anti-slip grooves and shallow tooth anchoring, while thicker specifications employ a closed-loop gradient dovetail groove dynamic self-locking structure. Three-dimensional anchoring tooth structures are located at the bottom and lower sides. This invention specifically solves the industry problems of traditional cement grouting, such as cracking, dirt accumulation, and curbstone arching and misalignment. Through differentiated structural design, three-dimensional anchoring, and elastic dynamic self-locking, it completely replaces the traditional rigid grouting process. The structure has strong weather resistance, is easy to install, requires no long-term maintenance, and is suitable for various refined municipal road construction projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of environmentally friendly and weather-resistant building materials technology for municipal road engineering. Specifically, it relates to a double-sided locking curb stone buffer pad and its construction method. It is applicable to various municipal road projects such as urban main roads, electric vehicle lanes, sidewalks, park landscape roads, and residential roads. It belongs to the field of new prefabricated building materials technology for urban refined management. Background Technology

[0002] Currently, the installation of curb stones in China generally adopts a rigid grouting process using pure cement slurry, which fills and solidifies the gaps between adjacent curb stones by injecting cement mortar. This rigid connection method lacks elasticity, buffering deformation capacity, and self-adaptive locking structure, resulting in significant technical defects in long-term service.

[0003] Under the combined effects of vehicle vibration and impact, environmental temperature changes and expansion, slight foundation settlement, and pressure from plant roots, traditional cement grouting usually develops problems such as cracking, chipping, detachment, hollowing, blackening and dirt accumulation within 2 to 5 years, resulting in curbstone alignment deviation, skewness, and misalignment, leading to an extremely high maintenance and repair rate.

[0004] According to Table 16.11.1 of the "Code for Construction and Quality Acceptance of Urban Road Engineering" (CJJ 1-2008), the core deviation indicators for curbstone installation acceptance are: straightness ≤ 10mm, height difference between adjacent blocks ≤ 3mm, and joint width ± 3mm. The construction precision controllability of the rigid grouting process using pure cement slurry is poor, and it is very easy to exceed the allowable deviation range specified in the code.

[0005] According to Article 8.4.5 of the Technical Specification for Urban Road Maintenance (CJJ 36-2016), the joint width for the maintenance of granite and marble curbs shall not be less than 3mm and the maximum joint width shall not exceed 10mm. The explanatory notes indicate that this regulation takes into account the situation of curb arching and edge chipping caused by temperature changes, and the joint width should be kept at around 5mm during construction.

[0006] In the prior art, there are solutions for attaching rubber or polyurethane buffer protective components to the surface of curb stones. These solutions cover the outer wall and top surface of the curb stone with a buffer protective layer to reduce vehicle impact damage. In addition, utility model patent CN213173198U discloses a crash shoulder for municipal engineering, which has a base at the bottom of the shoulder body. The inside of the base has a water channel running through it, and the top side of the base has through holes and curved grooves, which buffer the vehicle through a buffer pad.

[0007] While existing literature contains information on curbstone paving equipment and construction devices, none of it addresses the technical approach of using double-sided locking buffer pads between adjacent curbstone ends to replace cement grouting. The buffer components in these existing technologies only serve as single-sided protective structures, failing to disclose features such as double-sided outer sealing zones, a central oblique self-locking structure, and three-dimensional anchoring teeth on the bottom surface; they do not address the three-dimensional anchoring and positioning of the pads themselves in the foundation trench; they do not propose differentiated locking structure designs for pads of different thicknesses; and they do not achieve crack-free installation that eliminates the need for concrete grouting. Summary of the Invention

[0008] Technical issues

[0009] The technical problem this invention aims to solve is that traditional rigid cement grouting technology lacks elastic deformation capability, making it prone to cracking, arching, and misalignment under conditions of temperature expansion and contraction, root heave, and foundation settlement. Furthermore, its construction precision is poorly controllable, making it difficult to meet the acceptance standards of CJJ 1-2008 and CJJ 36-2016 in the long term. Existing elastic gasket solutions are mostly single-sided protective structures or external connection structures, failing to solve the core technical challenges of three-dimensional anchoring of the gasket itself, double-sided dynamic self-locking, and adaptation to different thickness specifications.

[0010] Technical solution

[0011] To achieve the above objectives, the present invention adopts the following technical solution:

[0012] A double-sided locking curb stone buffer pad includes an integrally molded elastic body with a thickness of 3-12mm; both sides of the elastic body are provided with outer sealing areas with a width of 15-20mm along their edges, the outer sealing areas being sealing surfaces for contacting the end face of the curb stone, and the surfaces of the outer sealing areas are free of grooves, holes, and depressions; the two sides of the elastic body are respectively provided with central locking areas, the central locking areas being provided with oblique strip-shaped locking parts, the strip-shaped locking parts forming an angle of 40°-45° with the length direction of the elastic body; the strip-shaped locking parts are oblique anti-slip grooves or oblique dovetail grooves; the entire bottom surface of the elastic body and the lower 100mm height range on both sides are provided with anchoring tooth structures.

[0013] The ultra-thin 3-4mm gaskets employ a slanted anti-slip groove deep line + shallow tooth anchoring structure, while the 5-12mm medium-thick gaskets utilize a gradient groove deep slanted dovetail groove self-locking structure with rounded corners at the groove opening and bottom to eliminate stress concentration. The lower part of the gasket has three anchoring teeth, while the upper side is smooth to prevent stress compression damage to the curbstone. The gasket's road-facing side features a dual-shape corner structure, suitable for standardized construction on landscape roads and municipal main roads.

[0014] The present invention further provides a special construction process adapted to the gasket, which achieves cement-free grouting installation through mortar interlocking, soil embedding, and elastic compression self-locking.

[0015] The construction method for this double-sided locking curb cushion pad includes the following steps:

[0016] (1) Complete the cement mortar leveling work for the roadbed and reserve backfill soil trenches on both sides;

[0017] (2) Place the flat bottom structure of the buffer pad on the mortar layer to level it, so that the bottom anchor teeth are pressed into the uncured mortar and the two side anchor teeth are embedded in the backfill soil trench wall to complete the three-dimensional anchoring position.

[0018] (3) Hoist the two adjacent curb stones to both sides of the pad, so that the two sides of the pad are in contact with the end faces of the two curb stones respectively;

[0019] (4) Apply a horizontal thrust to the curbstone to cause the gasket to generate elastic compression, forming a locking structure with the curbstone end face through the strip locking part; wherein, for gaskets with a thickness of 5-12mm, the compression is 3-5mm; for gaskets with a thickness of 3-4mm, the compression is 30% to 50% of the gasket thickness;

[0020] (5) When the external force is removed, the gasket rebounds elastically, the central locking zone self-locks, and the anchoring teeth form a stable three-dimensional anchoring system with the mortar and soil.

[0021] Beneficial effects (including one-to-one correspondence of technical features)

[0022] 1. Fully sealed to prevent contamination and eliminate defects caused by gaps.

[0023] Corresponding features: Double-sided 15-20mm non-perforated and non-grooved outer ring sealing area. Forms a closed-loop sealing barrier, completely preventing mud, water, and weeds from entering the gaps, eradicating the stubborn problems of blackening, hollowing, peeling, and water seepage in traditional grouting.

[0024] 2. Oblique dynamic self-locking, becoming more stable with increasing vibration.

[0025] Corresponding features: 40°-45° angled strip locking section, closed dovetail groove (wider at the top and narrower at the bottom). It conforms to the mechanical self-locking principle, automatically tightening under vibration and compression, effectively suppressing curbstone displacement, misalignment, and loosening.

[0026] 3. Elastic deformation adaptation solves arching deformation.

[0027] Corresponding characteristics: Highly elastic TPV substrate, overall deformation ≥2mm. Adapts to seasonal temperature changes, ground settlement, and root compression from vegetation, completely solving the problem of curbstone arching and cracking.

[0028] 4. Three-dimensional anchoring prevents detachment and ensures long-term stability.

[0029] Corresponding features: Bottom surface + 100mm lower side anchoring tooth structure. Interlocking mortar and backfill soil form a three-dimensional anchoring system that resists vertical buoyancy and lateral compression, preventing the gasket from slipping and falling off.

[0030] 5. Adaptable to different specifications, highly versatile

[0031] Corresponding features: thin anti-slip groove line + shallow toothed anchoring, thick gradient dovetail groove structure. Suitable for 3-12mm full joint width conditions, accommodating both light-load landscaping and heavy-load municipal roads.

[0032] 6. Completely replaces cement grout, reducing costs and increasing efficiency.

[0033] Eliminating the traditional grouting process, this system allows for one-time installation with no need for lifetime maintenance, improving construction efficiency and significantly reducing maintenance costs.

[0034] The core difference of the inventiveness of this invention

[0035] 1. Abandoning the existing external clamping and external protection structures, we have pioneered a double-sided internal sealing and self-locking structure for the curbstone end face;

[0036] 2. It features a pioneering dual-structure locking design with 3-4mm anti-slip shallow teeth and 5-12mm gradient dovetail grooves, a configuration not found in existing technologies.

[0037] 3. The first three-dimensional soil body + mortar anchoring structure of the gasket body is used to solve the problem of gasket displacement.

[0038] 4. Achieving a truly elastic assembly process with zero cement slurry and zero concrete pouring, breaking through the technical limitations of existing rigid auxiliary fixing. Attached Figure Description

[0039] Figure 1 This is a schematic diagram of the three-dimensional structure of the dovetail groove type buffer pad of the present invention;

[0040] Figure 2 This is a front view schematic diagram of the dovetail groove type buffer pad of the present invention;

[0041] Figure 3 This is a partially enlarged structural diagram of the oblique dovetail groove of the present invention;

[0042] Figure 4 This is a front view schematic diagram of the straight-angled buffer pad of the present invention;

[0043] Figure 5 This is a front view schematic diagram of the anti-slip groove linear buffer pad of the present invention;

[0044] Figure 6 This is a schematic diagram of the gasket anchor fixing position installation of the present invention (corresponding to construction step 2).

[0045] Figure 7This is a schematic diagram of the two curb stones being fitted and assembled with the gasket of the present invention (corresponding to construction step 3).

[0046] Figure 8 This is a schematic cross-sectional view of the gasket compression and locking of the present invention (corresponding to construction steps 4-5).

[0047] Figure Labels

[0048] 1-Elastic body; 2-Oblique dovetail groove; 3-Triangular convex tooth; 4-Concave arc-shaped decorative surface; 5-Rounded corner; 6-Outer ring sealing area; 7-Central locking area; 8-Straight-cut corner; 9-Oblique anti-skid trench depth line; 10-Roadbed; 11-Backfill soil base trench; 12-Road curb stone. Detailed Implementation

[0049] The gasket of this invention is compatible with standard national standard curbstone specifications, with thicknesses ranging from 3mm to 12mm and a tolerance of ±0.2mm. It is integrally molded. To clearly demonstrate the differentiated structural parameters of this invention, a comparison table of core structural parameters is provided below:

[0050] Table 1 Comparison of Gasket Core Structural Parameters

[0051] Gasket thickness specifications Locking structure type Anchor tooth structure parameters Core structural dimensions Installation compression volume Decorative groove depth 3mm (Ultra-thin Landscape Model) Sloping anti-slip trench depth line Shallow tooth anchoring, tooth height 0.5-1.0mm, corner radius 0.3-0.5mm The trench is 0.5mm deep, 1-1.5mm wide, spaced 1-1.5mm apart, and has an inclination angle of 40°-45°. 30% to 50% of the thickness ≤1mm 4mm (for rural trails) Sloping anti-slip trench depth line Shallow tooth anchoring, tooth height 0.5-1.0mm, corner radius 0.3-0.5mm The trench is 0.8 mm deep, 1.5 mm wide, 1.5 mm spaced, and has an inclination angle of 40°-45°. 30% to 50% of the thickness ≤1mm 5-6mm (Lightweight municipal model) Slanted closed dovetail groove Standard equilateral triangular convex teeth, side length 10mm, tooth height 8.7mm, spacing 10mm. The groove depth is 1.0-1.2mm, the top width is 6mm, the bottom width is 3mm, and the inclination angle is 40°-45°. 3-5mm 1-2mm 7-9mm (Standard heavy-duty model) Slanted closed dovetail groove Standard equilateral triangular convex teeth, side length 10mm, tooth height 8.7mm, spacing 10mm. The groove depth is 1.5-1.8mm, the top width is 6mm, the bottom width is 3mm, and the inclination angle is 40°-45°. 3-5mm 1-2mm 10-12mm (Premium Heavy-Duty Model) Slanted closed dovetail groove Standard equilateral triangular convex teeth, side length 10mm, tooth height 8.7mm, spacing 10mm. The groove depth is 1.8-2.0mm, the top width is 6mm, the bottom width is 3mm, and the inclination angle is 40°-45°. 3-5mm 1-2mm

[0052] The remaining general structural parameters are as follows: the width of the outer ring sealing area is 15-20mm; the width of the solid transition zone between the locking area and the sealing area is ≥3mm; the center-to-center distance of the dovetail groove is 30mm, the width of the adjacent rib is ≥4mm, and the distance from the end to the edge is 20mm; the side corners facing the road can be rounded (R15-50mm) or cut (cut edge 20-30mm), and the remaining corners are chamfered with R3-R5mm.

[0053] 1. Parameters of the outer ring sealing area

[0054] The double-sided design features a 15-20mm solid sealing area without grooves or recesses, ensuring a tight seal with the curbstone end face, forming a continuous waterproof and seepage-proof closed loop, and preventing dirt accumulation and water seepage in the gaps.

[0055] 2. Parameter basis for solid transition zone

[0056] The distance between the central locking zone and the outer sealing zone should be ≥3mm. If the width is less than 3mm, stress concentration under alternating compression conditions can easily lead to fatigue cracks; a distance of ≥3mm can effectively disperse stress, while isolating the locking pattern, ensuring the sealing zone is absolutely flat, and balancing sealing performance and structural strength.

[0057] 3. Parameters of the middle locking zone

[0058] The dovetail groove has a center distance of 30mm, a solid rib width of ≥4mm, and an end distance of 20mm from the edge: the center distance of 30mm ensures that the locking points are evenly distributed; the rib width of ≥4mm avoids structural weakness, breakage and deformation after slotting; the end of 20mm avoids the sealing area and does not damage the overall sealing structure; the closed design at both ends prevents stress gap cracking.

[0059] 3-4mm ultra-thin gaskets use 30%-50% compression: the thin substrate has a small elastic stroke, and this ratio is a safe elastic deformation range, which can ensure a tight seal and avoid permanent plastic deformation caused by excessive compression.

[0060] 4. Three-dimensional anchoring structure

[0061] The 5-12mm thick gaskets use standard 10mm equilateral triangular teeth for high interlocking strength; the 3-4mm ultra-thin gaskets use 0.5-1.0mm shallow tooth structure, which is suitable for thin substrates, does not penetrate or tear, and balances anchoring and structural integrity.

[0062] 5. Material properties and data traceability

[0063] The main body uses Sarlink TPV5755B modified elastomer. The data comes from the official product data sheet of Teknor Apex: 17% compression set at 23℃×22h, 27% compression set at 70℃×22h, and 42% compression set at 125℃×70h (ASTM D395 / ISO 815), meeting the design requirement of ≤30%; the Shore A hardness of the material is 55 for extrusion and 58 for injection molding (ASTM D2240), and the finished product can reach 60-80A through formula adjustment; the ozone resistance performance meets the GB / T 7762-2014 standard, with no cracking or damage at 50pphm, 40℃, and 72h.

[0064] 6. Correspondence between construction steps and attached drawings

[0065] Step (2) Anchoring Position → Corresponding Figure 6 Step (3) End face fitting → Corresponding Figure 7 Step (4) Compression locking, (5) Springback self-locking → Corresponding Figure 8 .

[0066] Summary table of parameters for each embodiment

[0067] Example Model Thickness Specifications Core structural configuration Material Key performance parameters Applicable Scenarios Example 1 (Ultra-thin Landscape Model) 3mm Sloping anti-slip groove deep line + shallow tooth anchoring, arc angle R30mm, groove depth ≤1mm Reclaimed rubber (light gray) Elastic deformation ≥2mm, no ozone cracking Landscape roads in high-end residential communities Example 2 (Township Trail Design) 4mm Sloping anti-slip groove deep line + shallow tooth anchoring, arc angle R30mm, groove depth ≤1mm Reclaimed rubber (medium gray) Elastic deformation ≥2mm, no ozone cracking Township municipal roads and urban park trails Example 3 (Municipal Heavy-Duty Model) 8mm Gradient dovetail groove + standard anchoring teeth, 25mm straight cut angle, 1.5mm groove depth. TPV modified substrate (dark gray) Compression set: 29%; Hardness: 72A; Deformation: ≥2.5mm Urban main roads and municipal landscape improvement projects Example 4 (Premium Heavy-Duty Model) 12mm Deepened dovetail groove + standard anchoring teeth, radius R40mm, groove depth 2.0mm TPV / EPDM blend modified substrate Compression set: 27%; Deformation: ≥2.5mm City gateway avenue, model project, heavy-duty road section

[0068] The above embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit the scope of protection thereof. Equivalent substitutions and modifications made by those skilled in the art all fall within the scope of protection of the present invention.

Claims

1. A double-sided locking type curb stone buffer pad, characterized in that, It includes an integrally formed elastic body (1); the thickness of the elastic body (1) is 3-12 mm; The elastic body (1) has an outer ring sealing area (6) with a width of 15-20mm on both sides along the edge. The outer ring sealing area (6) is a sealing surface that fits against the end face of the curbstone, and the surface of the outer ring sealing area (6) has no groove, no hole, and no recessed structure. The elastic body (1) has a central locking area (7) on each of its two sides. The central locking area (7) is provided with an oblique strip locking part. The strip locking part is arranged at an angle of 40°-45° with the length direction of the elastic body (1). The strip locking part is an oblique anti-slip groove (9) or an oblique dovetail groove (2) that is wider at the top and narrower at the bottom. The elastic body (1) has anchoring tooth structures on its bottom surface and on both sides within a 100mm area from the bottom surface upwards.

2. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, The elastic body (1) with a thickness of 5-12mm adopts a standard anchoring tooth structure. The anchoring tooth structure is an equilateral triangular convex tooth (3). The triangular convex tooth (3) has a side length of 10mm, an included angle of 60°, a tooth height of 8.7mm, a net distance between adjacent teeth of 10mm, and a rounded corner blunting structure with a radius of 0.5-1.0mm at the tooth tip. The ultra-thin elastic body (1) with a thickness of 3-4mm adopts a shallow tooth anchoring structure. The tooth height of the triangular convex tooth (3) is 0.5-1.0mm and the tooth tip radius is 0.3-0.5mm.

3. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, A solid smooth transition zone with a width of ≥3mm is provided between the central locking area (7) and the outer ring sealing area (6). The solid smooth transition zone has no texture and no recessed structure.

4. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, When the thickness of the elastic body (1) is 3mm, the strip locking part is an oblique anti-slip groove (9) with a groove depth of 0.5mm and a width of 1-1.5mm, and the spacing between adjacent oblique anti-slip grooves (9) is 1-1.5mm. When the thickness of the elastic body (1) is 4mm, the strip locking part is an oblique anti-slip groove (9) with a groove depth of 0.8mm and a width of 1.5mm, and the distance between adjacent oblique anti-slip grooves (9) is 1.5mm.

5. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, When the thickness of the elastic body (1) is 5-12mm, the strip-shaped locking part is an oblique dovetail groove (2) that is wider at the top and narrower at the bottom. The oblique dovetail groove (2) has an upper width of 6mm, a lower width of 3mm, and an effective length of 50mm. The groove depth is adapted to the thickness gradient of the elastic body, and the remaining thickness of the elastic body (1) at the groove depth position is ≥3mm. The groove depth is the groove depth on one side.

6. The double-sided locking curb stone buffer pad according to claim 5, characterized in that, The opening and bottom of the oblique dovetail groove (2) are both set with rounded transitions and no right-angled sharp corners.

7. The double-sided locking curb stone buffer pad according to claim 5, characterized in that, The depth gradient of the oblique dovetail groove (2) is set as follows: When the thickness of the elastic body (1) is 5-6 mm, the groove depth is 1.0-1.2 mm; When the thickness of the elastic body (1) is 7-9mm, the groove depth is 1.5-1.8mm; When the thickness of the elastic body (1) is 10-12mm, the groove depth is 1.8-2.0mm.

8. The double-sided locking curb stone buffer pad according to claim 5, characterized in that, The oblique dovetail groove (2) has a closed structure at both ends and no open opening; the center-to-center distance between the upper and lower oblique dovetail grooves is 30mm, the net width of the solid reinforcing rib between adjacent dovetail grooves is ≥4mm, and the distance between the two ends of the dovetail groove and the edge of the gasket is 20mm.

9. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, The roadside facade and top surface of the elastic body (1) are provided with concave arc-shaped decorative surfaces (4), while the bottom surface and back soil side are not provided with the concave arc-shaped decorative surfaces (4). The groove depth of the concave arc-shaped decorative surface (4) is 1-2mm, and the groove depth is ≤1mm when the thickness of the elastic body (1) is 3-4mm.

10. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, The elastic body (1) has a rounded corner (5) or a straight corner (8) on the top corner of the side facing the road. The radius R of the arc-shaped corner (5) is 15-50mm, and the length L2 of the cut edge of the straight-cut corner (8) is 20-30mm; The remaining corners of the elastic body (1) are all provided with R3-R5mm rounded chamfers.

11. The double-sided locking curb stone buffer pad according to claim 1, characterized in that, The bottom of the elastic body (1) is a flat structure, without outward wing plates or U-shaped flanges.

12. A construction method for a double-sided locking curb stone buffer pad, characterized in that, The double-sided locking curb cushion pad according to any one of claims 1 to 11 includes the following construction steps: (1) Complete the roadbed cement mortar leveling operation and reserve backfill soil foundation trenches on both sides (11); (2) Place the flat structure at the bottom of the buffer pad on the mortar layer to level it, so that the bottom anchor teeth are pressed into the uncured mortar, and the anchor teeth on both sides are embedded into the backfill soil trench (11) wall to complete the three-dimensional anchoring position. (3) Hoist the two adjacent curb stones (12) to both sides of the pad so that the two sides of the pad are in contact with the end faces of the two curb stones (12); (4) Apply a horizontal thrust to the curbstone to cause the gasket to generate elastic compression, and form a locking structure with the end face of the curbstone (12) through the strip locking part; wherein, for gaskets with a thickness of 5-12mm, the compression is 3-5mm; for gaskets with a thickness of 3-4mm, the compression is 30% to 50% of the gasket thickness; (5) Remove external force, the gasket rebounds elastically, the middle locking zone (7) self-adaptively locks, and the anchoring teeth form a stable three-dimensional anchoring system with the mortar and soil.