A modular multi-stage telescopic foundation pit pre-support structure
The modular multi-stage telescopic foundation pit pre-support structure solves the problems of limited adjustment range and low reuse rate of fixed-length steel pipe supports in deep foundation pit construction by using multi-stage sleeve hydraulic cylinders and detachable connections. It realizes flexible adjustment and stability of support length, and improves construction efficiency and material utilization.
Patent Information
- Application Number
- CN202611291830.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-25
- Publication Date
- 2026-11-10
AI Technical Summary
Fixed-length steel pipe support structures are difficult to adapt to local bulging deformation of diaphragm walls during deep foundation pit construction, resulting in limited range of interference and adjustment during lowering, and low component reuse rate.
The modular multi-stage telescopic foundation pit pre-support structure adopts a modular multi-stage telescopic hydraulic cylinder and a detachable connection mechanism on the transverse support to achieve flexible adjustment of the support length and overall stability. The modular combination of short and long steel pipes can adapt to different foundation pit sizes.
It effectively avoids interference at the support ends, reduces construction complexity, improves the adaptability and reusability of components, and reduces material consumption.
Smart Images

Figure CN123064170A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of deep foundation pit construction technology, and in particular relates to a modular multi-stage expansion joint pre-support structure for foundation pits. Background Technology
[0002] In deep foundation pit construction, diaphragm walls are typically an important component of the pit support system, bearing the effects of external soil pressure, water pressure, and construction loads during the excavation phase. To control the lateral deformation of the diaphragm walls during excavation, pre-supports are often installed between the diaphragm walls on both sides of the pit before formal excavation, allowing the support system to form axial stress constraints in advance. Currently, commonly used pre-supports for foundation pits mostly employ fixed-length steel pipe support structures. These supports are generally prefabricated in the factory according to the design clearance or processed to fixed specifications and then transported to the construction site, where they are installed at the predetermined elevation through on-site assembly, hoisting, or lowering. Fixed-length steel pipe supports are widely used in deep foundation pit support construction due to their clear stress path and relatively mature component design.
[0003] However, in actual construction, due to factors such as geological conditions, trenching deviations, and verticality deviations in diaphragm wall construction, diaphragm walls are prone to localized bulging deformations towards the inside of the pit, commonly referred to as "diaphragm wall bulges." This phenomenon causes the actual net distance between the two diaphragm walls to be smaller than the design net distance in certain areas. For existing fixed-length pre-support structures, their overall length is difficult to adjust significantly during lowering based on local net distance changes. Once the support end interferes with the bulging part of the diaphragm wall, the pre-support is easily stuck and cannot be lowered further to the design elevation. This usually requires re-lifting and chiseling, repairing, or taking other temporary measures to the bulge, increasing construction steps and potentially affecting the surface quality of the retaining structure. Simultaneously, some telescopic support structures typically have limited adjustment ranges, making it difficult to adapt to large net distance deviations; the versatility of support components for different pit sizes is insufficient, often requiring the separate configuration of fixed-length components for specific projects, resulting in low component turnover rate. Summary of the Invention
[0004] The purpose of this invention is to provide a modular multi-stage telescopic foundation pit pre-support structure to solve the problems of interference when fixed-length pre-supports are lowered due to diaphragm wall bulging, limited adjustment range, and low component reuse rate.
[0005] To achieve the above objectives, the present invention adopts the following technical solution:
[0006] A modular multi-stage telescopic pre-support structure for foundation pits is used to be installed between diaphragm walls on both sides of a foundation pit. It includes multiple transverse supports arranged in layers along the depth of the foundation pit. Each transverse support includes a central steel pipe support section. Both ends of the central steel pipe support section are respectively equipped with a steel pipe support cross section, a multi-stage telescopic hydraulic cylinder, and a hydraulic cylinder. Adjacent transverse supports are connected by vertical steel pipe support pipes. The central steel pipe support section is formed by a combination of short and long horizontal steel pipe support pipes, which are detachably connected via a steel pipe connecting mechanism. The multi-stage telescopic hydraulic cylinder is arranged along the axial direction of the transverse supports, and its telescopic direction is consistent with the axial direction of the transverse supports. The end of the multi-stage telescopic hydraulic cylinder furthest from the steel pipe support cross section is detachably connected to the hydraulic cylinder via a telescopic connecting mechanism, allowing the multi-stage telescopic hydraulic cylinder to shorten the overall length of the pre-support structure in the retracted state and to move closer to the inner side of the diaphragm wall in the extended state.
[0007] Preferably, the steel pipe connection mechanism includes a fixed plate and two bolts. Inserts are installed on both sides of the fixed plate. Through holes are opened on the inserts. Insert holes are opened at the ends of the short steel pipe supporting the horizontal pipe and the long steel pipe supporting the horizontal pipe. The short steel pipe supporting the horizontal pipe and the long steel pipe supporting the horizontal pipe are respectively inserted into the inserts on both sides of the fixed plate and are respectively connected to the corresponding inserts by bolts.
[0008] Preferably, the steel pipe support cross is located at the intersection of the horizontal support and the vertical support. The short steel pipe support horizontal pipe, the long steel pipe support horizontal pipe, and the steel pipe support vertical pipe are all connected to the steel pipe support cross, so that the multiple horizontal supports arranged in layers form an overall support system through the steel pipe support vertical pipe.
[0009] Preferably, the short steel pipe supporting the horizontal pipe, the long steel pipe supporting the horizontal pipe, and the steel pipe supporting the vertical pipe all adopt modular standard segments; the short steel pipe supporting the horizontal pipe, the long steel pipe supporting the horizontal pipe, the steel pipe supporting the vertical pipe, and the steel pipe supporting the ten-section are provided with a unified interface standard and are connected by detachable connectors.
[0010] Preferably, the multi-stage telescopic hydraulic cylinder comprises three interconnected telescopic sleeves, and the telescopic stroke of each telescopic sleeve is independently adjustable.
[0011] Preferably, a fixing plate is installed at the extended end of the multi-stage telescopic hydraulic cylinder, and a plug rod is installed on the side of the fixing plate away from the multi-stage telescopic hydraulic cylinder. The plug rod is inserted into the steel pipe support. A connecting cylinder is installed at the end of the multi-stage telescopic hydraulic cylinder away from the fixing plate, and the connecting cylinder is connected to the telescopic connecting mechanism.
[0012] Preferably, the telescopic connection mechanism includes a fixed seat, a plug, a threaded post, and a nut. The fixed seat is connected to the extension end of the hydraulic cylinder. The plug is installed on the fixed seat and inserted into the connecting cylinder. The threaded post is installed on the upper end of the plug. The nut is threadedly connected to the threaded post so that the plug and the connecting cylinder form a limiting connection.
[0013] Preferably, the pre-support structure has a lowered state and a supported state; in the lowered state, the multi-stage telescopic hydraulic cylinder is in a retracted state, so that the overall length of the pre-support structure is less than the minimum actual clear distance between the two underground continuous walls; in the supported state, the multi-stage telescopic hydraulic cylinder extends step by step along the transverse support axis, so that the hydraulic cylinder abuts against the pressure-bearing component on the inner side of the underground continuous wall, and the axial force applied by the hydraulic cylinder is transmitted through the telescopic connection mechanism, the multi-stage telescopic hydraulic cylinder, the steel pipe support cross tube, the short steel pipe support horizontal tube, and the long steel pipe support horizontal tube.
[0014] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0015] 1. By installing multi-stage telescopic hydraulic cylinders at the ends of each transverse support and arranging them along the support axis, the multi-stage telescopic hydraulic cylinders can be retracted before the pre-support is lowered, making the overall length of the pre-support less than the minimum actual net distance between the two diaphragm walls. This allows the pre-support to avoid lowering the bulging parts when there is local bulging deformation in the diaphragm wall, reducing interference between the support end and the diaphragm wall, and reducing the need for repeated lifting and readjustment.
[0016] 2. By setting the multi-stage telescopic hydraulic cylinder as a multi-stage telescopic structure and setting a locking mechanism between each stage of the sleeve, the multi-stage telescopic hydraulic cylinder can remain in a retracted state during the lowering stage and can be locked after extending to the target position step by step during the installation stage. This can not only meet the length reduction requirements during the lowering process, but also limit unexpected contraction or extension after the support is installed, thereby improving the stability of the support after length adjustment.
[0017] 3. By modularly combining short steel pipes to support horizontal pipes, long steel pipes to support horizontal pipes, steel pipes to support vertical pipes, and steel pipes to support ten-section sections, and by connecting the ends of steel pipes supporting horizontal pipes of different lengths through a steel pipe connecting mechanism, the pre-supported structure can select the appropriate number and specifications of support segments for assembly according to the width and depth of the foundation pit. This improves the adaptability to different foundation pit working conditions and reduces the need to manufacture fixed-length support components for a single project.
[0018] 4. The hydraulic cylinder is detachably connected to the multi-stage telescopic hydraulic cylinder via a telescopic connection mechanism, and the horizontal steel pipe support segments are detachably connected via a steel pipe connection mechanism. This allows the hydraulic cylinder, multi-stage telescopic hydraulic cylinder, and each steel pipe support segment to be disassembled, separated, and recycled after construction. After inspection and maintenance, each component can be used for subsequent foundation pit projects, thereby improving the reuse rate of support components and reducing material consumption. Attached Figure Description
[0019] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0020] Figure 1 This is a schematic diagram of the overall layout of the foundation pit pre-support structure installed between the underground continuous walls in this invention;
[0021] Figure 2 This is a three-dimensional structural diagram of the pre-support structure for the foundation pit in this invention;
[0022] Figure 3 This is a schematic diagram of the single-channel transverse support structure in this invention;
[0023] Figure 4 This is a schematic diagram of the steel pipe connection mechanism in this invention;
[0024] Figure 5 This is a schematic diagram showing the connection state between the hydraulic cylinder and the multi-stage telescopic hydraulic cylinder in this invention;
[0025] Figure 6 This is an exploded structural diagram of the telescopic connection mechanism in this invention;
[0026] Reference numerals: 1. Hydraulic cylinder; 2. Multi-stage telescopic hydraulic cylinder; 21. Fixing plate; 22. Insert rod; 23. Connecting cylinder; 3. Steel pipe support cross section; 4. Short steel pipe support for horizontal pipe; 5. Long steel pipe support for horizontal pipe; 6. Steel pipe support for vertical pipe; 7. Steel pipe connection mechanism; 71. Fixing plate; 72. Insert cylinder; 73. Bolt; 8. Diaphragm wall; 9. Telescopic connection mechanism; 91. Fixing seat; 92. Insert column; 93. Threaded column; 94. Nut. Detailed Implementation
[0027] To make the above-mentioned objects, features, and advantages of the present invention more readily understood, specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the protection scope of the present invention.
[0028] This invention is described in detail with reference to the accompanying drawings. When detailing the embodiments of this invention, for ease of explanation, the cross-sectional views illustrating the device structure may be partially enlarged, not to scale. Furthermore, the accompanying drawings are merely examples and should not be construed as limiting the scope of protection of this invention. In actual fabrication, the three-dimensional spatial dimensions of length, width, and depth should be included.
[0029] Furthermore, it should be noted in the description of this invention that the terms "first," "second," or "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0030] Example: Figures 1 to 6 As shown, a modular multi-stage telescopic foundation pit pre-support structure is used for the pre-support construction between the underground continuous walls 8 on both sides of the foundation pit.
[0031] like Figure 1 and Figure 2 As shown, the pre-support structure for the foundation pit includes multiple transverse supports arranged in layers along the depth of the foundation pit. Each transverse support is arranged transversely between the underground continuous walls 8 on both sides of the foundation pit. Each transverse support includes a middle steel pipe support section, and at both ends of the middle steel pipe support section are respectively provided a steel pipe support cross section 3, a multi-stage sleeve-type telescopic hydraulic cylinder 2, and a hydraulic cylinder 1. Adjacent transverse supports are connected by steel pipe support vertical pipes 6, thereby forming an overall support system arranged along the depth of the foundation pit.
[0032] The intermediate steel pipe support section is formed by combining short steel pipe support horizontal pipes 4 and long steel pipe support horizontal pipes 5, both of which are arranged along the axial direction of the transverse support. The short and long steel pipe support horizontal pipes 4 and 5 can be modular standard segments, preferably 1m, 3m, and 5m in length, allowing for the selection of different quantities and specifications of steel pipe support horizontal pipes for combination based on the width of the foundation pit. Similarly, the steel pipe support vertical pipe 6 can also be modular standard segments, preferably 1m, 3m, and 5m in length, allowing for combination based on the depth of the foundation pit. The steel pipe support horizontal pipes, steel pipe support vertical pipes 6, and steel pipe support cross-sections 3 are equipped with a unified interface standard and are connected by detachable connectors.
[0033] like Figure 3 and Figure 4As shown, the short steel pipe supporting the horizontal pipe 4 and the long steel pipe supporting the horizontal pipe 5 are connected by a steel pipe connecting mechanism 7. The steel pipe connecting mechanism 7 includes a fixing plate 71, inserts 72, and bolts 73. Inserts 72 are installed on both sides of the fixing plate 71, and through holes are opened on the inserts 72. The bolts 73 are connected to the inserts 72 through the through holes. Insert holes are opened at the ends of both the short steel pipe supporting the horizontal pipe 4 and the long steel pipe supporting the horizontal pipe 5. During installation, the short steel pipe supporting the horizontal pipe 4 and the long steel pipe supporting the horizontal pipe 5 are respectively inserted into the inserts 72 on both sides of the fixing plate 71. Then, the short steel pipe supporting the horizontal pipe 4 is connected to one of the inserts 72 by the bolts 73, and the long steel pipe supporting the horizontal pipe 5 is connected to the other insert 72 by the other bolt 73.
[0034] Specifically, the short steel pipe supporting horizontal pipe 4 and the long steel pipe supporting horizontal pipe 5 are connected end to end by the steel pipe connecting mechanism 7, so that steel pipe supporting horizontal pipes of different lengths can be assembled according to the width of the foundation pit; after the construction is completed, the short steel pipe supporting horizontal pipe 4 and the long steel pipe supporting horizontal pipe 5 can be separated from the steel pipe connecting mechanism 7 by removing the bolts 73, which facilitates the disassembly, transportation and recycling of each component.
[0035] like Figures 1 to 3 As shown, the steel pipe support cross-section 3 is located at the intersection of the horizontal and vertical supports. The short horizontal steel pipe support 4, the long horizontal steel pipe support 5, and the vertical steel pipe support 6 are all connected to the steel pipe support cross-section 3, forming a node connection between the horizontal and vertical supports at the intersection. The steel pipe support cross-section 3 connects the layered horizontal supports with the vertical steel pipe support 6 arranged along the depth of the foundation pit, thus forming a unified load-bearing system among the multiple horizontal supports.
[0036] like Figure 5 As shown, the multi-stage telescopic hydraulic cylinder 2 is arranged along the axial direction of the transverse support, and its extension and retraction direction is consistent with the axial direction of the transverse support. The multi-stage telescopic hydraulic cylinder 2 includes three interconnected telescopic sleeves, and the extension and retraction stroke of each telescopic sleeve is independently adjustable. A locking mechanism is provided between each stage of the multi-stage telescopic hydraulic cylinder 2. The locking mechanism is not shown in the attached figure. The locking mechanism can adopt existing mature technologies and products. When any stage of the telescopic sleeve extends or retracts to the target position, the locking mechanism can lock the stage of the telescopic sleeve to limit the unexpected contraction or extension of the stage of the telescopic sleeve.
[0037] A fixing plate 21 is installed at the extended end of the multi-stage telescopic hydraulic cylinder 2. A plug rod 22 is installed on the side of the fixing plate 21 away from the multi-stage telescopic hydraulic cylinder 2. The plug rod 22 is inserted into the steel pipe support cross 3. A connecting cylinder 23 is installed at the end of the multi-stage telescopic hydraulic cylinder 2 away from the fixing plate 21. The connecting cylinder 23 is used to connect with the telescopic connection mechanism 9.
[0038] like Figure 5 and Figure 6 As shown, hydraulic cylinder 1 is located on the side of multi-stage telescopic hydraulic cylinder 2 away from the steel pipe support cross 3. A telescopic connection mechanism 9 is provided between hydraulic cylinder 1 and multi-stage telescopic hydraulic cylinder 2. The telescopic connection mechanism 9 includes a fixed seat 91, a plug 92, a threaded plug 93, and a nut 94. The fixed seat 91 is connected to the extension end of hydraulic cylinder 1. The plug 92 is installed on the fixed seat 91 and is inserted into the connecting cylinder 23. The threaded plug 93 is installed on the upper end of the plug 92. The nut 94 is threadedly connected to the threaded plug 93.
[0039] When installing hydraulic cylinder 1 and multi-stage telescopic hydraulic cylinder 2, insert pin 92 into connecting cylinder 23, so that threaded pin 93 protrudes above connecting cylinder 23, and then screw nut 94 onto threaded pin 93, so that pin 92 and connecting cylinder 23 form a limiting connection, thereby forming a detachable connection between hydraulic cylinder 1 and multi-stage telescopic hydraulic cylinder 2.
[0040] Specifically, the telescopic connection mechanism 9 is located between the hydraulic cylinder 1 and the multi-stage telescopic hydraulic cylinder 2. On the one hand, it is used to transmit the axial force between the hydraulic cylinder 1 and the multi-stage telescopic hydraulic cylinder 2. On the other hand, it forms a detachable connection relationship through the insert 92, connecting cylinder 23, threaded column 93 and nut 94, so that the hydraulic cylinder 1 and the multi-stage telescopic hydraulic cylinder 2 can be disassembled and separated after construction.
[0041] Working principle: In actual use, first determine the design clearance between the underground continuous walls 8 on both sides of the foundation pit according to the design drawings, and measure the actual clearance between the underground continuous walls 8 on the ground to determine whether there is a "big belly" deformation of the underground continuous wall 8 that bulges out into the foundation pit, and determine the location and size of the bulging deformation.
[0042] Subsequently, based on the actual net distance between the underground continuous walls 8 and the depth of the foundation pit, select the appropriate number and specifications of steel pipe support cross section 3, short steel pipe support horizontal pipe 4, long steel pipe support horizontal pipe 5 and steel pipe support vertical pipe 6, and connect the short steel pipe support horizontal pipe 4 and the long steel pipe support horizontal pipe 5 end to end through the steel pipe connection mechanism 7; then connect the hydraulic cylinders 1 at both ends and the multi-stage sleeve telescopic hydraulic cylinders 2 to the steel pipe support sections respectively to complete the overall assembly of the pre-support structure.
[0043] Before lowering the pre-support structure, the multi-stage telescopic hydraulic cylinders 2 at both ends of the pre-support structure are adjusted to the fully retracted state, so that each stage of the telescopic sleeve retracts step by step, and the telescopic sleeves are locked by the locking mechanism so that the overall length of the pre-support structure is less than the minimum actual net distance between the two underground continuous walls 8; then the pre-support structure is lowered to the design elevation by the lifting equipment.
[0044] After the pre-supported structure is lowered to the design elevation, the locking mechanism is released from the multi-stage telescopic hydraulic cylinder 2. The hydraulic control system then controls the multi-stage telescopic hydraulic cylinder 2 to extend outwards stage by stage. During extension, the third-stage sleeve extends first, followed by the second-stage sleeve, and finally the first-stage sleeve, causing the hydraulic cylinder 1 at the end of the pre-supported structure to gradually approach and abut against the pressure-bearing component inside the diaphragm wall 8. The pressure-bearing component can be a steel waler, a pressure plate, or a support.
[0045] After the hydraulic cylinder 1 comes into contact with the pressure-bearing component inside the diaphragm wall 8, the hydraulic cylinder 1 applies the axial force required by the design. This axial force is transmitted to the diaphragm walls 8 on both sides through the hydraulic cylinder 1, the telescopic connection mechanism 9, the multi-stage sleeve telescopic hydraulic cylinder 2, the steel pipe support cross tube 3, the short steel pipe support horizontal tube 4, the long steel pipe support horizontal tube 5, and the corresponding components on the opposite side, thereby completing the support installation and forming a support system.
[0046] After the foundation pit construction is completed, the axial jacking effect of hydraulic cylinder 1 is released. Then, hydraulic cylinder 1, multi-stage telescopic hydraulic cylinder 2, telescopic connection mechanism 9, steel pipe support cross tube 3, short steel pipe support horizontal tube 4, long steel pipe support horizontal tube 5, steel pipe support vertical tube 6, and steel pipe connection mechanism 7 are disassembled in sequence. After inspection and maintenance, each disassembled support component can be used for subsequent foundation pit construction.
[0047] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.
Claims
1. A modular multi-stage telescopic foundation pit pre-support structure, used for installation between underground continuous walls (8) on both sides of a foundation pit, comprising multiple transverse supports layered along the depth direction of the foundation pit, each of the transverse supports comprising a middle steel pipe support section, wherein the two ends of the middle steel pipe support section are respectively provided with a steel pipe support cross section (3), a multi-stage sleeve telescopic hydraulic cylinder (2) and a hydraulic cylinder (1), and adjacent transverse supports are connected by steel pipe support vertical pipes (6), characterized in that: The intermediate steel pipe support section is formed by combining a short steel pipe support horizontal pipe (4) and a long steel pipe support horizontal pipe (5). The short steel pipe support horizontal pipe (4) and the long steel pipe support horizontal pipe (5) are detachably connected by a steel pipe connection mechanism (7). The multi-stage telescopic hydraulic cylinder (2) is arranged along the axial direction of the transverse support, and its telescopic direction is consistent with the axial direction of the transverse support. The end of the multi-stage telescopic hydraulic cylinder (2) away from the steel pipe support cross section (3) is detachably connected to the hydraulic cylinder (1) through the telescopic connection mechanism (9), so that the multi-stage telescopic hydraulic cylinder (2) can shorten the overall length of the pre-support structure in the retracted state, and can bring the hydraulic cylinder (1) closer to the inner side of the underground continuous wall (8) in the extended state.
2. The modular multi-stage telescopic foundation pit pre-support structure according to claim 1, characterized in that, The steel pipe connection mechanism (7) includes a fixed plate (71) and two bolts (73). Inserts (72) are installed on both sides of the fixed plate (71). Through holes are opened on the inserts (72). Insert holes are opened at the ends of the short steel pipe supporting horizontal pipe (4) and the long steel pipe supporting horizontal pipe (5). The short steel pipe supporting horizontal pipe (4) and the long steel pipe supporting horizontal pipe (5) are respectively inserted into the inserts (72) on both sides of the fixed plate (71) and are respectively connected to the corresponding inserts (72) by bolts (73).
3. The modular multi-stage telescopic foundation pit pre-support structure according to claim 1, characterized in that, The steel pipe support 10-section (3) is set at the intersection of the horizontal support and the vertical support. The short steel pipe support horizontal pipe (4), the long steel pipe support horizontal pipe (5) and the steel pipe support vertical pipe (6) are all connected to the steel pipe support 10-section (3), so that the multiple horizontal supports set in layers form an overall support system through the steel pipe support vertical pipe (6).
4. The modular multi-stage telescopic foundation pit pre-support structure according to claim 3, characterized in that, The short steel pipe supporting the horizontal pipe (4), the long steel pipe supporting the horizontal pipe (5), and the steel pipe supporting the vertical pipe (6) all adopt modular standard segments; the short steel pipe supporting the horizontal pipe (4), the long steel pipe supporting the horizontal pipe (5), the steel pipe supporting the vertical pipe (6), and the steel pipe supporting the ten-section pipe (3) are equipped with a unified interface standard and are connected by detachable connectors.
5. The modular multi-stage telescopic foundation pit pre-support structure according to claim 1, characterized in that, The multi-stage telescopic hydraulic cylinder (2) includes three interconnected telescopic sleeves, and the extension stroke of each telescopic sleeve is independently adjustable.
6. The modular multi-stage telescopic foundation pit pre-support structure according to claim 1, characterized in that, The extension end of the multi-stage telescopic hydraulic cylinder (2) is equipped with a fixing plate (21). A plug rod (22) is installed on the side of the fixing plate (21) away from the multi-stage telescopic hydraulic cylinder (2). The plug rod (22) is inserted into the steel pipe support cross joint (3). A connecting cylinder (23) is installed on the end of the multi-stage telescopic hydraulic cylinder (2) away from the fixing plate (21). The connecting cylinder (23) is connected to the telescopic connecting mechanism (9).
7. The modular multi-stage telescopic foundation pit pre-support structure according to claim 6, characterized in that, The telescopic connection mechanism (9) includes a fixed seat (91), a plug (92), a threaded plug (93), and a nut (94). The fixed seat (91) is connected to the extension end of the hydraulic cylinder (1). The plug (92) is installed on the fixed seat (91) and is inserted into the connecting cylinder (23). The threaded plug (93) is installed on the upper end of the plug (92). The nut (94) is threadedly connected to the threaded plug (93) so that the plug (92) and the connecting cylinder (23) form a limiting connection.
8. The modular multi-stage telescopic foundation pit pre-support structure according to claim 7, characterized in that, The pre-supported structure has a lowered state and a supported state; In the lowered state, the multi-stage sleeve telescopic hydraulic cylinder (2) is in the retracted state, so that the overall length of the pre-support structure is less than the minimum actual net distance between the two underground continuous walls (8). In the supported state, the multi-stage telescopic hydraulic cylinder (2) extends step by step along the transverse support axis, so that the hydraulic cylinder (1) abuts against the pressure-bearing component inside the underground continuous wall (8). The axial force applied by the hydraulic cylinder (1) is transmitted through the telescopic connection mechanism (9), the multi-stage telescopic hydraulic cylinder (2), the steel pipe support cross tube (3), the short steel pipe support horizontal tube (4), and the long steel pipe support horizontal tube (5).