A method for reinforcing precast floor slabs by slotting and embedding reinforcing bars in holes using pressure grouting.
By slotting and embedding reinforcing bars in the bottom surface of precast floor slabs and then performing pressure grouting, the problem of poor applicability of precast hollow floor slab reinforcement is solved, the load-bearing capacity is improved and the structural reliability is enhanced, while avoiding interference with the building and space occupation, making it suitable for various building scenarios.
Patent Information
- Application Number
- CN202611172780.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-04
- Publication Date
- 2026-11-10
AI Technical Summary
Existing precast hollow core slab reinforcement technologies have poor applicability, limited load-bearing capacity improvement, cannot meet minimum reinforcement ratio requirements, require damage to the floor decoration layer and occupy building space during construction, and lack efficient and feasible reinforcement methods.
After longitudinal grooves are opened and slag is removed from the bottom side of the precast floor slab, reinforcing steel bars are embedded and the longitudinal holes are filled with reinforced solid core structure by pressure grouting. All construction procedures are completed on the bottom surface of the floor slab.
It achieves a significant increase in the load-bearing capacity of precast floor slabs, enhances structural reliability, ensures that construction does not affect the normal use of the building, and does not occupy the building's clearance. It is suitable for the reinforcement of precast floor slabs in various scenarios, with low cost and short cycle.
Smart Images

Figure CN123064322A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building structure reinforcement engineering technology, and in particular to a method for reinforcing precast floor slabs by slotting and embedding reinforcing bars in holes using pressure grouting. Background Technology
[0002] Precast hollow core slabs are commonly used precast assembled floor components in building construction. These components have multiple longitudinally penetrating holes along their length, offering advantages such as light weight, low cost, and convenient production and installation. They have been widely used in the construction of residential, office, and industrial buildings in my country. For strengthening and enhancing the load-bearing capacity of existing floor slabs, several mature technologies have been developed, including carbon fiber reinforcement, steel reinforcement, cast-in-place concrete composite layer reinforcement, and reinforcement with additional supporting steel beams. Among these, cast-in-place composite layer reinforcement typically involves filling the slab surface with concrete through openings, increasing the slab's cross-sectional height, and supplementing with additional reinforcement to achieve structural strengthening.
[0003] However, the existing reinforcement methods mentioned above have many unavoidable drawbacks when applied to precast hollow core slabs: The carbon fiber bonding method is only effective in improving load-bearing capacity by bonding carbon fiber strips to the rib surfaces between the holes. Precast slabs have many holes, few ribs, and narrow widths, limiting the number of strips that can be bonded and resulting in a limited increase in load-bearing capacity. Furthermore, most precast slabs were built in earlier years and were produced in workshops and small factories, resulting in poor concrete pouring quality and various transverse cracks. Carbon fiber fabric cannot compensate for these cracks. Crack injection reinforcement cannot effectively repair existing cracks within the precast slab due to the presence of internal holes, leading to insufficient reliability. Steel bonding reinforcement requires chemical anchors, but the holes in the precast slabs make it difficult for these anchors to penetrate easily, failing to meet the required anchoring length. The small cross-section of the ribs between the holes also makes it impossible to anchor the steel bolts, rendering the method unusable. Even so, precast floor slabs still have a significant drawback: the prestressed steel wires or strands in existing precast slabs generally do not meet the minimum reinforcement ratio requirements of current codes. Without meeting the minimum basic structural requirements of the codes, surface carbon fiber bonding and steel bonding methods cannot solve this problem. Adding a composite layer for reinforcement, whether on the surface or bottom of the slab, requires vertical anchoring short bars within the original slab to increase the adhesion and integrity of the composite layer to the original floor slab and prevent it from becoming a "two-layer" structure. However, due to the presence of holes, the anchoring short bars cannot achieve the required anchorage length. Furthermore, precast floor slabs are typically 600mm to 900mm wide unidirectional load-bearing slabs. When setting up composite layers, the load transfer path is unclear, resulting in extremely poor applicability on precast floor slabs. This method cannot be effectively implemented in most scenarios. In addition, because the composite layers are generally thin, pouring concrete is difficult. Even if this method is used, it is generally only applied to cast-in-place solid floor slabs. The reinforcement method of adding supporting steel beams will reduce the internal clear height of the building, affecting the normal use function of the building, and is difficult to apply in most indoor scenarios.
[0004] Meanwhile, existing grouting reinforcement processes generally employ a construction path of grouting through openings in the slab surface. This requires removing the floor's decorative finish and clearing away furniture and equipment before construction, significantly disrupting normal building use, resulting in long construction periods and high overall costs. Currently, relevant domestic building reinforcement standards lack specific reinforcement methods for precast hollow core slabs. In the context of urban renewal and existing building renovation projects, the problem of insufficient load-bearing capacity in precast core slabs has long lacked efficient and feasible technical solutions, representing a pressing technical challenge in the field of building reinforcement. Summary of the Invention
[0005] This invention addresses the technical problems of existing precast hollow core slab reinforcement technologies, such as poor applicability, limited improvement in load-bearing capacity, inability to solve basic structural defects that do not meet the minimum reinforcement ratio, and the need to damage the floor decoration layer and occupy building space during construction.
[0006] To solve the above-mentioned technical problems, the present invention provides the following technical solution: a method for reinforcing precast floor slabs with slotted bottom reinforcement and pressure grouting, which is used for structural reinforcement of precast hollow floor slabs with longitudinal through holes. All construction procedures are completed on the bottom side of the floor slab, and specifically includes the following steps: (1) Positioning and layout: Mark the position and axial direction of each longitudinal hole on the bottom surface of the precast floor slab, and mark the grooving control line along the axial direction of each hole to be reinforced; (2) Slotting at the bottom of the slab: A longitudinal through slot is opened on the bottom surface of the floor slab along the slotting control line. The longitudinal through slot extends along the axial direction of the hole and the slot depth penetrates the bottom wall of the floor slab and communicates with the internal cavity of the corresponding hole. (3) Slag removal treatment: The walls of the longitudinal through channel and the internal cavities of the corresponding holes are cleaned and slag removed to remove floating dust and concrete debris from the channel and the holes. (4) Reinforcing bar fixing: Reinforcing bars are laid in the longitudinal through groove and fixed along the axial direction of the groove. The thickness of the protective layer between the bottom surface of the reinforcing bars and the bottom surface of the floor slab is controlled to meet the design requirements. (5) Sealing the bottom cavity: The bottom opening of the longitudinal through groove is sealed by the bottom sealing template, so that the bottom sealing template, the inner wall of the hole and the groove wall together form a closed grouting cavity, and the grouting port and the exhaust port are reserved on the bottom sealing template; (6) Pressure grouting: Connect the pressure grouting equipment to the grouting port through the grouting pipe, and press the grouting material into the grouting cavity from the bottom of the floor slab. After the grouting material fills the entire cavity and overflows steadily from the vent, seal the vent and the grouting port in sequence to complete the grouting. (7) Curing and demolding: After the grout has cured to the design strength, remove the bottom sealing template, level and repair the groove on the bottom of the floor slab, and complete the reinforcement construction of the precast floor slab.
[0007] Furthermore, in step (2), the width of the longitudinal through groove is 25~35mm, and a single longitudinal through groove corresponds to a single prefabricated hole. The length of the groove is consistent with the length of the hole in the section to be reinforced.
[0008] Further, in step (4), the reinforcing steel bars are hot-rolled ribbed steel bars, and one or more parallel reinforcing steel bars are arranged in a single longitudinal through groove; the reinforcing steel bars are fixed to the side wall of the groove by binding or spot welding, and the thickness of the protective layer from the bottom surface of the reinforcing steel bars to the bottom surface of the floor slab is not less than 20mm.
[0009] Furthermore, in step (5), the bottom sealing template is made of a hard, flat board, which is bonded and sealed to the periphery of the groove on the bottom surface of the floor slab by an adhesive or mechanical fastener; the grouting port and the venting port are respectively set at the two ends of the axial direction of the bottom sealing template, with the grouting port located at the starting end of the grouting operation and the venting port located at the far end of the hole.
[0010] Further, in step (6), the grouting material is high-strength non-shrink grouting material or fine stone concrete; the grouting pressure is controlled at 0.2~0.5MPa. After the grouting material without air bubbles continuously overflows from the vent, the vent is first sealed, and the grouting pressure is maintained for 30~60s before the grouting port is sealed again.
[0011] Furthermore, in step (6), the grouting operation is carried out by using an air compressor in conjunction with a pressure grouting machine. The grouting hose is connected to the grouting port from the bottom space under the floor slab, and there is no need to open grouting holes on the floor slab surface throughout the process.
[0012] Furthermore, for precast floor slabs containing multiple longitudinal holes, the grooving, reinforcement, sealing and grouting processes are completed sequentially for each hole, or reinforcement operations are carried out simultaneously for multiple holes.
[0013] One or more technical solutions provided in the embodiments of this application have at least the following technical effects or advantages compared with the prior art: 1. By embedding new reinforcing bars into the holes of precast slabs and injecting grout, the original hollow precast floor slabs are transformed into reinforced solid structures. This retains the original reinforcement in the ribs of the precast slabs while adding new reinforcing bars and solid concrete sections, resulting in a significant increase in the load-bearing capacity of the floor slabs and a substantial enhancement in structural reliability. This method solves all the problems that previous existing reinforcement methods could not address.
[0014] 2. All processes are completed on the bottom side of the floor slab, without the need to remove the floor decoration layer, remove floor furniture and equipment, and without affecting the normal use of the upper part of the building, greatly reducing the interference of construction on building operation.
[0015] 3. The reinforcement work is carried out using only the space under the slab. After the reinforcement is completed, there is no additional reinforcement layer occupying the building's clearance, nor is it necessary to add supporting components. The original building's usable space and floor height are completely preserved.
[0016] 4. It can be adapted to various specifications of perforated precast floor slabs. The reinforcement load-bearing capacity can be flexibly set by adjusting the specifications and quantity of steel bars. It is suitable for precast floor slab reinforcement projects in various scenarios such as civil buildings and industrial buildings.
[0017] 5. The process is simple to operate, requires no large construction equipment, has a short construction period, and the overall cost is lower than traditional reinforcement schemes. It fills the technical gap in special reinforcement methods for precast hollow floor slabs and has high engineering application value and economic value.
[0018] Other advantages, objectives and features of the invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination or study, or may be learned from the practice of the invention. Attached Figure Description
[0019] Figure 1 This is a sequence diagram of the overall construction process for the precast floor slab reinforcement of the present invention; Figure 2 This is a sequence diagram of the bottom grooving and slag removal processes of the present invention; Figure 3 This is a sequence diagram of the embedding and sealing cavity forming processes of the present invention; Figure 4 This is a timing diagram for the bottom pressure grouting operation control of the present invention; Figure 5 This is a sequence diagram of the construction organization for the multi-hole water flow system of the present invention; Figure 6 This is a schematic diagram of the cross-sectional structure of the original precast hollow floor slab of the present invention; Figure 7 This is a schematic diagram of the cross-section of the precast floor slab after the bottom groove of the slab has been completed according to the present invention; Figure 8 This is a schematic diagram of the cross-section of the precast floor slab after the reinforcement fixing is completed according to the present invention; Figure 9 This is a schematic diagram of the cross-section of the precast floor slab after the bottom sealing grouting is completed according to the present invention. Detailed Implementation
[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0021] It should be noted that the terms "vertical," "horizontal," "up," "down," "left," "right," and similar expressions used in this article are for illustrative purposes only and do not represent the only possible implementation.
[0022] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains; the terminology used herein in the description of the invention is for the purpose of describing particular embodiments only and is not intended to limit the invention; the term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0023] like Figure 1-5As shown, a method for reinforcing precast floor slabs by slotting and embedding reinforcing bars through pressure grouting is used to reinforce precast floor slabs with multiple longitudinal through holes. All construction procedures are completed on the bottom side of the precast floor slab, without the need to open or break the floor slab surface.
[0024] The precast floor slab to be reinforced is a precast hollow slab with multiple longitudinal holes of circular or elliptical cross-section evenly distributed along its length. The slab body is a precast concrete component, with existing reinforcing steel bars embedded in the ribs. This method involves inserting reinforcing steel bars into longitudinal slots in the bottom of the slab, combined with bottom formwork sealing and pressure grouting, to fill the longitudinal holes into a reinforced solid core structure, thereby achieving overall reinforcement of the floor slab.
[0025] The specific construction steps are as follows: Before construction, based on the original design data of the precast floor slab and in conjunction with on-site detection equipment, confirm the specific location, axial direction, and diameter of each longitudinal hole inside. Mark the corresponding slotting control lines on the bottom surface of the precast floor slab for each hole to be reinforced, clearly defining the start and end points and width boundaries of the slots. For floor slabs without original data, the hole locations can be marked by interval drilling to ensure precise correspondence between the slotting positions and the internal holes.
[0026] Along the marked grooving control lines, longitudinal through grooves are cut on the bottom surface of the precast floor slab using grooving equipment. The longitudinal through groove extends along the entire axial length of the longitudinal hole, with the groove length matching the hole length of the section to be reinforced. The groove width is controlled at 25-35mm, preferably 30mm in this embodiment. The groove depth must completely penetrate the bottom wall thickness of the precast floor slab, ensuring complete communication between the longitudinal through groove and the internal cavity of the corresponding longitudinal hole, forming a connecting channel for reinforcement embedding and grouting. The cutting depth is controlled during grooving to avoid damaging the original reinforcing bars in the ribs of the precast slab.
[0027] After the trenching is completed, high-pressure air blowing combined with brush cleaning is used to thoroughly clean the walls, bottom, and internal cavities of the longitudinal through trenches and the longitudinal holes, removing concrete debris, dust, and loose particles from the trenches and holes. This ensures that the subsequent grouting material adheres firmly to the original concrete interface and prevents residue from affecting the grouting density.
[0028] According to the reinforcement bearing capacity design requirements, reinforcement bars of corresponding specifications are selected. In this embodiment, hot-rolled ribbed steel bars are used. The reinforcement bars are placed into the longitudinal through groove along its axial direction. One or more parallel reinforcement bars can be arranged in a single longitudinal through groove. The reinforcement bars are temporarily fixed to the concrete substrate of the groove sidewall by binding wire or spot welding. The position of the reinforcement bars is adjusted so that the distance from the bottom surface of the reinforcement bar to the bottom surface of the precast floor slab is not less than 20mm, ensuring that the outside of the reinforcement bars has sufficient concrete cover thickness to meet the structural durability requirements.
[0029] A rigid, flat board is used as the bottom sealing template. The board can be PVC board, wood, or steel, and is cut to shape according to the width and length of the groove. Grouting ports and vents are respectively opened at both ends of the bottom sealing template along the axial direction. The grouting ports are located at the starting end of the grouting operation, and the vents are located at the far end of the hole to expel air from the hole during grouting. The bottom sealing template is tightly attached to the bottom surface of the precast floor slab using adhesive or mechanical fasteners such as expansion bolts, sealing the bottom opening of the longitudinal through groove. This allows the bottom sealing template, the groove wall of the longitudinal through groove, and the inner wall of the longitudinal hole to together form a closed grouting cavity. Gaps around the template are sealed with sealant to prevent grout leakage during the grouting process.
[0030] The grouting equipment uses an air compressor in conjunction with a pressure grouting machine. The grouting hose connects to the grouting port on the bottom sealing template from the interior bottom space beneath the precast floor slab. High-strength, non-shrink grout or fine aggregate concrete is used, with the appropriate grade selected according to the design strength requirements. The grouting equipment is started for pressure grouting, with the grouting pressure controlled within the range of 0.2~0.5MPa. Low-pressure, slow grouting gradually fills the internal cavities of the longitudinal holes. When air-free grout continuously overflows from the vent at the far end, it indicates that the hole is completely filled and compacted. At this point, the vent is first sealed, and the grouting pressure is maintained for 30~60 seconds to ensure full grouting. Then, the grouting port is sealed, completing the single-hole grouting operation. No grouting holes need to be opened on the floor slab surface throughout the entire grouting process; the operation is completed entirely on the bottom side of the slab.
[0031] After grouting is completed, natural curing is carried out according to the curing requirements of the grout. After the grout has solidified and reached the design strength, the bottom sealing template of the precast floor slab is removed, and the residual marks at the bottom groove of the slab are leveled and repaired to keep the bottom surface of the reinforced floor slab flat and beautiful, and finally the reinforcement construction of the entire precast floor slab is completed.
[0032] For precast floor slabs containing multiple longitudinal holes, the process of slotting, reinforcing bars, sealing the bottom, and grouting can be completed sequentially for each hole. Alternatively, depending on the number of construction personnel and equipment, multiple holes can be reinforced in parallel, allowing for flexible adjustment of the construction pace.
[0033] During use, the precast floor slab to be reinforced is first surveyed and inspected to determine the distribution of internal holes and the extent of damage. Based on the load-bearing capacity requirements, the specifications of the reinforcing steel, the grade of the grouting material, and the range of the reinforcing holes are determined. Then, construction proceeds sequentially according to the following steps: positioning and layout, grooving the bottom of the slab, cleaning and removing slag and ash, embedding and fixing the reinforcing steel, sealing the formwork and leaving holes, pressure grouting, curing, and demolding, completing the reinforcement work hole by hole. After all holes are reinforced, the appearance of the slab bottom is repaired and inspected before it is put into use. The reinforced precast floor slab transforms the internal hollow holes into a reinforced solid section, significantly improving the overall bending and shear bearing capacity and structural stiffness, meeting current building safety requirements.
[0034] Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Anyone skilled in the art can make various modifications and alterations without departing from the spirit and scope of the present invention. Therefore, the scope of protection of the present invention should be determined by the claims.
Claims
1. A method for reinforcing precast hollow core slabs with slotted bottoms and embedded reinforcing bars via pressure grouting, characterized in that: All construction procedures are completed on the bottom side of the floor slab, specifically including the following steps: (1) Positioning and layout: Mark the position and axial direction of each longitudinal hole on the bottom surface of the precast floor slab, and mark the grooving control line along the axial direction of each hole to be reinforced; (2) Slotting at the bottom of the slab: A longitudinal through slot is opened on the bottom surface of the floor slab along the slotting control line. The longitudinal through slot extends along the axial direction of the hole and the slot depth penetrates the bottom wall of the floor slab and communicates with the internal cavity of the corresponding hole. (3) Reinforcing bar fixing: Reinforcing bars are laid in the longitudinal through groove, and the reinforcing bars are fixed along the axial direction of the groove. The thickness of the protective layer between the bottom surface of the reinforcing bars and the bottom surface of the floor slab is controlled to meet the design requirements. (4) Sealing the bottom cavity: The bottom opening of the longitudinal through groove is sealed by the bottom sealing template, so that the bottom sealing template, the inner wall of the hole and the groove wall together form a closed grouting cavity, and the grouting port and the exhaust port are reserved on the bottom sealing template; (5) Pressure grouting: Connect the pressure grouting equipment to the grouting port through the grouting pipe, and press the grouting material into the grouting cavity from the bottom of the floor slab. After the grouting material fills the entire cavity and overflows steadily from the vent, seal the vent and the grouting port in sequence to complete the grouting. (6) Curing and formwork removal: After the grout has cured to the design strength, remove the bottom sealing formwork to complete the reinforcement construction of the precast floor slab.
2. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (2), the width of the longitudinal through groove is 25~35mm, and a single longitudinal through groove corresponds to a single prefabricated hole. The length of the groove is consistent with the length of the hole in the section to be reinforced.
3. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... After step (2) is completed, the walls of the longitudinal through groove and the internal cavities of the corresponding holes are cleaned and slag removed to remove floating dust and concrete debris from the groove and holes.
4. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (3), the reinforcing steel bars are hot-rolled ribbed steel bars, and one or more parallel reinforcing steel bars are arranged in a single longitudinal through groove. The reinforcing steel bars are fixed to the side wall of the groove by binding or spot welding, and the thickness of the protective layer from the bottom surface of the reinforcing steel bars to the bottom surface of the floor slab is not less than 20mm.
5. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (4), the bottom sealing template is made of hard, flat board material, which is bonded and sealed to the periphery of the groove on the bottom surface of the floor slab by adhesive or mechanical fasteners; the grouting port and the venting port are respectively set at both ends of the axial direction of the bottom sealing template, the grouting port is located at the starting end of the grouting operation, and the venting port is located at the far end of the hole.
6. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (5), the grouting material is high-strength non-shrink grouting material or fine stone concrete; the grouting pressure is controlled at 0.2~0.5MPa. After the grouting material without air bubbles continuously overflows from the vent, the vent is first sealed, and the grouting pressure is maintained for 30~60s before the grouting port is sealed.
7. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (5), the grouting operation is carried out by using an air compressor in conjunction with a pressure grouting machine. The grouting hose is connected to the grouting port from the bottom space under the floor slab. There is no need to open grouting holes on the floor slab surface throughout the process.
8. The method for reinforcing precast floor slabs by slotting and embedding reinforcing bars at the bottom of holes using pressure grouting, as described in claim 1, is characterized in that... In step (6), after removing the bottom sealing template, the groove position on the bottom surface of the floor slab is leveled and repaired to keep the bottom surface of the reinforced floor slab flat.