A method for controlling the trajectory of a horizontal well containing interlayers in the target layer.
By using a horizontal well trajectory to alternately drill through multiple reservoirs in the target layer containing interlayers, the problems of high development costs and low recovery rates have been solved, and efficient multi-reservoir exploitation and improved drilling rate have been achieved.
Patent Information
- Application Number
- CN202510578729.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-07
- Publication Date
- 2026-11-10
AI Technical Summary
Existing technologies suffer from high development costs and low recovery rates when developing reservoirs containing interlayers, especially when designing horizontal well trajectories for each oil-bearing reservoir, which significantly increases costs.
By drilling through multiple reservoirs with a single horizontal well trajectory, setting target points alternately in the upper and lower reservoirs, and controlling the well trajectory to maintain different angles before and after encountering interlayers, multiple reservoirs can be simultaneously exploited with a single horizontal well trajectory, reducing engineering risks and increasing the drilling success rate.
This approach achieves enhanced recovery rates in reservoirs containing interlayers while reducing extraction costs and increasing the drilling rate of oil-bearing sandstone.
Smart Images

Figure CN123064432A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of oilfield exploration and development, specifically to a method for controlling the trajectory of a horizontal well in a target formation containing interlayers. Background Technology
[0002] With the advancement of technology, people are gradually challenging increasingly complex reservoir types, requiring horizontal well trajectories to be precisely positioned within the desired underground formations and accurately guided to avoid specific formations or traverse formations of interest, thereby improving recovery rates and reducing extraction costs. This has led to well drilling operations becoming increasingly complex in both vertical and horizontal directions.
[0003] For reservoirs containing interlayers, there are generally two existing development methods. The first method designs horizontal well trajectories for development within the single layer with the best reserves, aiming to minimize development costs. Other, less desirable single layers are developed using methods such as vertical perforation and fracturing. This approach, however, increases the difficulty of development within these less desirable single layers and results in lower recovery rates. The second method designs a separate horizontal well trajectory for each oil-bearing reservoir to achieve better recovery rates, but this significantly increases development costs. Summary of the Invention
[0004] To overcome the shortcomings of existing reservoir development methods that result in high development costs and low recovery rates when the target layer contains interlayers, this invention provides a horizontal well trajectory control method for horizontal wells with interlayers. This method allows multiple reservoirs to be developed simultaneously with a single horizontal well trajectory by drilling through them, thereby improving the recovery rate while reducing development costs.
[0005] The technical solution of the present invention is: a method for controlling the trajectory of a horizontal well containing interlayers in the target layer, comprising the following steps:
[0006] Step 1: Collect basic data, which includes: target layer structure map and reference well logging data;
[0007] Step 2: Based on the structural map of the target layer and the logging data of the reference well, establish the target well profile map, and determine whether the target layer contains interlayers based on the target well profile map; if the target layer contains interlayers, divide the target layer into upper reservoir, intermediate interlayer and lower reservoir.
[0008] Step 3: Set at least one target point on the lower reservoir and the upper reservoir respectively. The target points in the lower reservoir and the upper reservoir are set alternately in the horizontal direction, and the first target point in the lower reservoir is the first target point.
[0009] Step 4: After controlling the horizontal well trajectory to reach the first target point, drill through the target points on the upper and lower reservoirs in sequence to reach the preset completion position.
[0010] Furthermore, in step 2, when the number of interlayers is greater than 1, the intermediate interlayer includes an upper interlayer, an intermediate reservoir, and a lower interlayer; the target layer is divided into an upper reservoir, an upper interlayer, an intermediate reservoir, a lower interlayer, and a lower reservoir.
[0011] Furthermore, in step 4, when the horizontal well trajectory lands, the angle between the horizontal well trajectory at the landing point and the target layer is angle a, and the angle between the horizontal well trajectory and the target layer after the first encounter with the interlayer is angle b, and a>b.
[0012] Furthermore, in step 4, during the process of the horizontal well trajectory moving from the lower reservoir target point to the upper reservoir target point, the angle between the horizontal well trajectory and the target layer is c before encountering the interlayer, and the angle between the horizontal well trajectory and the target layer is d after encountering the interlayer, and c <d。
[0013] Furthermore, in step 4, during the process of the horizontal well trajectory moving from the upper reservoir target point to the lower reservoir target point, the angle between the horizontal well trajectory and the target layer is e before encountering the interlayer, and the angle between the horizontal well trajectory and the target layer is f after encountering the interlayer, and e <f。
[0014] Furthermore, in step 3, the horizontal distance between two adjacent target points is greater than 50 meters.
[0015] Furthermore, in step 3, the last target point on the horizontal trajectory is located in the upper reservoir.
[0016] Furthermore, the included angle b is
[0017] b≤arccos(1-2πDK / 360)
[0018] In the formula: arccosine function, π, D, thickness of the lower reservoir, and K, inclination rate.
[0019] Furthermore, the inclination rate K is less than the maximum inclination rate, which is determined based on the inclination tool and geological features.
[0020] Furthermore, the intermediate reservoir includes several secondary interlayers and secondary reservoirs.
[0021] Furthermore, the reference well in step 1 includes a pilot well, a drilled vertical well in the same block, or a drilled deviated well in the same block, and the logging data of the reference well includes the target layer and at least one marker layer.
[0022] The present invention has the following beneficial effects: By adopting the above-mentioned scheme, this invention targets geological conditions where the target layer contains interlayers. It achieves simultaneous exploitation of two reservoirs through a controlled horizontal well trajectory, repeatedly traversing between the two reservoirs, thereby improving recovery rate while reducing exploitation costs. Simultaneously, as the horizontal well trajectory moves from the lower reservoir target point to the upper reservoir target point, it maintains a relatively small angle with the target layer before encountering the interlayer, and a relatively large angle after encountering the interlayer. This allows the horizontal well trajectory to drill a longer distance in the lower reservoir before encountering the interlayer, improving the drilling rate of oil-bearing sandstone. Similarly, as the horizontal well trajectory moves from the upper reservoir target point to the lower reservoir target point, it maintains a relatively small angle with the target layer before encountering the interlayer, and a relatively large angle after encountering the interlayer. This allows the horizontal well trajectory to drill a longer distance in the upper reservoir before encountering the interlayer, further improving the drilling rate of oil-bearing sandstone. Attached Figure Description
[0023] Figure 1 This is a flowchart of the present invention;
[0024] Figure 2 This is a schematic diagram of the well profile of the present invention;
[0025] Figure 3 This is a schematic diagram of the landing process of a horizontal well trajectory;
[0026] Figure 4 This is a schematic diagram of the horizontal well trajectory drilling process from the lower reservoir to the upper reservoir;
[0027] Figure 5 This is a schematic diagram of the horizontal well trajectory as it drills from the upper reservoir to the lower reservoir.
[0028] In the diagram, 100 is the target layer, 110 is the upper reservoir, 120 is the interlayer, 130 is the lower reservoir, 200 is the horizontal well trajectory, 210 is the landing point, 220 is the first target point, 230 is the second target point, 222 is the third target point, 232 is the fourth target point, 240 is the first interlayer marker, 242 is the second interlayer marker, and 244 is the third interlayer marker. Detailed Implementation
[0029] The present invention will now be described in detail with reference to the accompanying drawings and embodiments. The technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0030] In the description of this invention, it is necessary to understand that the orientation or positional relationship indicated by "up", "down", "left", "right", etc. are based on the orientation or positional relationship shown in the accompanying drawings. The purpose is only to facilitate the description of this invention and to simplify the description. It is not intended to indicate or imply that the component referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, it should not be construed as a limitation of this invention.
[0031] Depend on Figure 1 As shown, a method for controlling the trajectory of a horizontal well with interlayers in the target layer includes the following steps:
[0032] Step 1: Collect basic data, including: target layer structural map and reference well logging data. The reference well logging data includes the target layer and one or more marker layers. The reference well can be a pilot well, a drilled vertical well or a drilled deviated well in the same block, or other wells.
[0033] Step 2: Based on the target layer structure map, reference well, and reference well logging data, perform geological interpretation, establish a profile, and determine whether the target layer contains interlayers. If the target layer contains interlayers, divide it into upper reservoir, intermediate layer, and lower reservoir, and then proceed to Step 3. If the target layer does not contain interlayers, the method of this invention is not required, and the currently commonly used conventional horizontal well trajectory control method can be used.
[0034] The method of this invention addresses the case where the target layer contains interlayers. When there is only one interlayer, the intermediate layer is considered the interlayer. When there are two or more interlayers, the intermediate layer includes an upper interlayer, an intermediate reservoir, and a lower interlayer. In this case, the target layer is divided into an upper reservoir, an upper interlayer, an intermediate reservoir, a lower interlayer, and a lower reservoir. That is, all layers except the uppermost and lowermost reservoirs are referred to as intermediate layers. When the number of interlayers is greater than two, the intermediate reservoir may also include secondary interlayers and secondary reservoirs, and so on. When there are multiple interlayers, this method can also be used to determine the target point and horizontal well trajectory.
[0035] Step 3: Set the target point for the horizontal section. The target point location and horizontal well trajectory are shown in [link to documentation]. Figure 2 The well profile diagram is as follows:
[0036] At least one target point is set on both the lower and upper reservoirs. The target points in the lower and upper reservoirs are set alternately in the horizontal direction. In this way, when the horizontal well trajectory reaches any target point in the lower reservoir, the next target point is set in the upper reservoir; similarly, when the horizontal well trajectory reaches any target point in the upper reservoir, the next target point is set in the lower reservoir.
[0037] At the same time, it is required that the first target point in the lower reservoir be the first target point, and the last target point on the horizontal trajectory be located in the upper reservoir, so as to delay the water breakthrough time.
[0038] When setting the target points, the horizontal distance between two adjacent target points is required to be greater than 50 meters, so as to ensure that the overall angle change rate is within the safe range, avoid engineering risks, and ensure the smooth progress of the project.
[0039] Step 4: After controlling the horizontal well trajectory to reach the first target point, drill through the set target points in sequence to reach the preset total depth position. In this process, the following requirements are imposed on the horizontal well trajectory:
[0040] ① The included angle between the horizontal well trajectory at the landing point and the target layer is defined as included angle a, and the included angle between the horizontal well trajectory and the target layer after the horizontal well trajectory first drills through the interlayer is defined as included angle b, and a>b, as shown in Figure 3 . That is, before the horizontal well trajectory drills to the upper reservoir (landing), drilling at a relatively large included angle a with the target layer is selected, which can achieve fast landing over a short distance. At this time, there are still the upper reservoir and the interlayer between the horizontal well trajectory and the first target point, with a relatively long distance, so that relatively large risks can be withstood. In the process from the landing of the horizontal well trajectory to the drilling to the first target point, drilling at a relatively small included angle b with the target layer is selected, which can reach the first target point more smoothly, avoid drilling through the lower reservoir, and reduce the risk of entering the target.
[0041] The included angle b is calculated according to the following formula:
[0042] b≤arccos(1-2πDK / 360)
[0043] In the formula: arccos - inverse cosine function, π - pi; D - thickness of the lower reservoir; K - build-up rate.
[0044] The build-up rate is determined by the directional driller according to the deflecting capacity of the deflecting tool and the geological characteristics of the local area. However, in actual drilling, the set build-up rate needs to be slightly smaller than the maximum allowable build-up rate, that is, a margin shall be reserved to avoid engineering risks and ensure the smooth progress of the project.
[0045] ② In the process where the horizontal well trajectory travels from the target point of the lower reservoir to the target point of the upper reservoir, the included angle between the horizontal well trajectory and the target layer before drilling through the interlayer is defined as included angle c, and the included angle between the horizontal well trajectory and the target layer after drilling through the interlayer is defined as included angle d, and c<d, as shown in Figure 4 . Therefore, before drilling through the interlayer, the horizontal well trajectory can drill in the lower reservoir for a relatively long distance, so as to improve the drilling encounter rate of oil-bearing sandstone. After drilling through the interlayer, the horizontal well trajectory can pass through the interlayer relatively quickly over a short distance. In addition, even if there is a certain error in the dip angle of the target layer, the horizontal well trajectory can still maintain an included angle with the target layer.
[0046] ③ In the process where the horizontal well trajectory travels from the target point of the upper reservoir to the target point of the lower reservoir, the included angle between the horizontal well trajectory and the target layer before drilling through the interlayer is defined as included angle e, and the included angle between the horizontal well trajectory and the target layer after drilling through the interlayer is defined as included angle f, and e<f, as shown in Figure 5Therefore, before encountering the interlayer, the horizontal well trajectory can drill a relatively long distance in the upper reservoir to improve the drilling rate of oil-bearing sandstone. After encountering the interlayer, the horizontal well trajectory can pass through the interlayer relatively quickly and in a short distance. In addition, even if there is a certain error in the dip angle of the target layer, the horizontal well trajectory can maintain an angle with the target layer.
[0047] This invention addresses geological conditions where the target layer contains interlayers. It involves controlled drilling through a horizontal well trajectory to encounter two reservoirs, then repeatedly traversing between the upper and lower reservoirs. This allows for simultaneous exploitation of two reservoirs with a single horizontal well trajectory, improving recovery rates while reducing extraction costs. Furthermore, as the horizontal well trajectory moves from the lower reservoir target point to the upper reservoir target point, it maintains a relatively small angle with the target layer before encountering the interlayer, and a relatively large angle afterward. This allows the horizontal well trajectory to drill a longer distance in the lower reservoir before encountering the interlayer, improving the drilling rate of oil-bearing sandstone. Conversely, as the horizontal well trajectory moves from the upper reservoir target point to the lower reservoir target point, it maintains a relatively small angle with the target layer before encountering the interlayer, and a relatively large angle afterward. This allows the horizontal well trajectory to drill a longer distance in the upper reservoir before encountering the interlayer, further improving the drilling rate of oil-bearing sandstone.
[0048] Example:
[0049] In this embodiment, a method for controlling the trajectory of a horizontal well with interlayers in the target layer includes the following steps:
[0050] Step 1: Data preparation, collecting basic data.
[0051] In this embodiment, the basic data includes: a target layer structure map; and reference well logging data, wherein the reference well logging data includes the target layer and a marker layer.
[0052] Step 2: Determine whether the target layer includes the upper reservoir 110, the interlayer 120, and the lower reservoir 130.
[0053] Based on the reference well, reference well logging data, and target layer structural map, a geological interpretation is made, the dip angle of the target layer is determined to be 88 degrees, the target layer contains an interlayer 120, and a profile map is established; the target layer is subdivided into upper reservoir 110, interlayer 120, and lower reservoir 130, and then proceed to step 3.
[0054] Step 3: Set the target point for the horizontal section and control the horizontal well trajectory 200 to land, enter the target, and drill through the horizontal section.
[0055] Two target points are sequentially set in the lower reservoir and two target points are also set in the upper reservoir. The first target point is set in the lower reservoir 130, and the target points on the lower reservoir 130 and the upper reservoir 110 are alternately set, from front to back as the first target point 220, the second target point 230, the third target point 222, and the fourth target point 232. Among them, the first target point 220 and the third target point 222 are located on the lower reservoir 130, and the second target point 230 and the fourth target point 232 are located on the upper reservoir 110. In this way, when the horizontal well trajectory 200 reaches any target point in the lower reservoir 130, the next target point is set in the upper reservoir 110; when the horizontal well trajectory 200 reaches any target point in the upper reservoir, the next target point is set in the lower reservoir 130.
[0056] Step 4: Control the horizontal well trajectory to reach the first target point, and then drill through the target points set on the upper and lower reservoirs in sequence to reach the preset completion position.
[0057] ① Based on the comparison with the reference well, when the horizontal well trajectory 200 approached the target layer, the horizontal well trajectory 200 was controlled to have a well inclination angle of 76 degrees, and drilling was carried out at a 12-degree angle a with the target layer. When the MD (depth sounding) reached 1375 meters, the logging data showed a significant decrease in GR and a significant increase in resistivity. The logging cuttings indicated oil-bearing sandstone. Geologically, this indicated that the horizontal well trajectory 200 had reached the upper reservoir 110 and had successfully landed. The horizontal well trajectory 200 was then controlled to have a well inclination angle of 83 degrees, and drilling was carried out at a 5-degree angle b with the target layer to the interlayer 120, reaching the first interlayer marker point 240. At this point, the logging data showed that the horizontal well trajectory 200 had entered the lower reservoir 130. The well inclination of the horizontal well trajectory 200 was increased to reach the first target point 220. At this point, the well inclination angle was 88 degrees, parallel to the target layer, and the target was successfully entered, entering the horizontal section.
[0058] ② After passing the first target point 220, the horizontal well trajectory 200 is controlled to drill from the first target point 220 in the lower reservoir 130 to the second target point 230 in the upper reservoir 110. During this process, the well inclination angle is controlled at 91 degrees before encountering the interlayer 120, maintaining a 3-degree angle c with the target layer; when drilling to the second interlayer marker point 242, the well inclination angle is controlled at 92 degrees, maintaining a 4-degree angle d with the target layer, reaching the interlayer 120 at MD1540 meters; the well inclination is gradually reduced to 88 degrees, reaching the second target point 230 at MD1600 meters.
[0059] ③ The horizontal well trajectory 200 was controlled to drill from the second target point 230 in the upper reservoir 110 to the third target point 222 in the lower reservoir 130. During this process, the well inclination angle was controlled at 85 degrees before encountering interlayer 120, maintaining a 3-degree angle e with the target layer; when drilling reached the third interlayer marker point 244, the well inclination angle was controlled at 84 degrees, maintaining a 4-degree angle f with the target layer. Interlayer 120 was reached at MD1655 meters, and the well inclination was gradually increased to 88 degrees, reaching the third target point 222 at MD1740 meters.
[0060] ④ After the horizontal well trajectory 200 passes the third target point 222, the well inclination is gradually increased to 92 degrees, reaching interlayer 120 at MD1825 meters, and then the well inclination is gradually decreased to 88 degrees, reaching the fourth target point 232 at MD1880 meters.
[0061] ⑤ Maintain an 88-degree parallel dip angle to the upper reservoir 110 formation and drill to 1950 meters in the upper reservoir 110 to reach the preset completion position.
[0062] In this embodiment, before encountering the interlayer 120, the horizontal well trajectory 200 can drill a relatively long distance in the upper reservoir to improve the drilling rate of oil-bearing sandstone. After encountering the interlayer 120, the horizontal well trajectory 200 can pass through the interlayer 120 relatively quickly and in a short distance. In addition, even if there is a certain error in the dip angle of the target layer, the horizontal well trajectory can maintain an angle with the target layer.
[0063] In this embodiment, the horizontal distance between any two adjacent target points is greater than 50 meters. For example, the MD of the first target point 220 is 1375 meters, the MD of the second target point 230 is 1600 meters, and the distance between them is 225 meters, with a horizontal distance of 223.7 meters, which is greater than 50 meters. This ensures that the total angle change rate is within a safe range, avoids engineering risks, and ensures the smooth progress of the project.
[0064] In this embodiment, for geological conditions where the target layer contains interlayer 120, two reservoirs, namely the upper reservoir 110 and the lower reservoir 130, are encountered through controlled drilling using a horizontal well trajectory 200. Then, the well is repeatedly drilled through the two reservoirs in sequence, so that a single horizontal well trajectory 200 can simultaneously mine the two reservoirs, thereby improving the recovery rate and reducing the mining cost.
[0065] The various embodiments of the present invention have been described above. These descriptions are exemplary and not exhaustive, nor are they limited to the disclosed embodiments. Many modifications and variations will be apparent to those skilled in the art without departing from the scope and spirit of the described embodiments. The terminology used herein is chosen to best explain the principles, practical application, or technical improvements to the embodiments in the market, or to enable others skilled in the art to understand the embodiments disclosed herein.
Claims
1. A method for controlling the trajectory of a horizontal well containing interlayers in a target layer, characterized in that... Includes the following steps: Step 1: Collect basic data, which includes: target layer structure map and reference well logging data; Step 2: Based on the structural map of the target layer and the logging data of the reference well, establish the target well profile map, and determine whether the target layer contains interlayers based on the target well profile map; if the target layer contains interlayers, divide the target layer into upper reservoir, intermediate interlayer and lower reservoir. Step 3: Set at least one target point on the lower reservoir and the upper reservoir respectively. The target points in the lower reservoir and the upper reservoir are set alternately in the horizontal direction, and the first target point in the lower reservoir is the first target point. Step 4: After controlling the horizontal well trajectory to reach the first target point, drill through the target points on the upper and lower reservoirs in sequence to reach the preset completion position.
2. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1, characterized in that: In step 2, when the number of interlayers is greater than 1, the intermediate interlayer includes an upper interlayer, an intermediate reservoir, and a lower interlayer; the target layer is divided into an upper reservoir, an upper interlayer, an intermediate reservoir, a lower interlayer, and a lower reservoir.
3. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1 or 2, characterized in that: In step 4, when the horizontal well trajectory lands, the angle between the horizontal well trajectory at the landing point and the target layer is angle a, and the angle between the horizontal well trajectory and the target layer after the first encounter with the interlayer is angle b, and a>b.
4. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1 or 2, characterized in that: In step 4, as the horizontal well trajectory moves from the lower reservoir target point to the upper reservoir target point, the angle between the horizontal well trajectory and the target layer is c before encountering the interlayer, and the angle between the horizontal well trajectory and the target layer is d after encountering the interlayer, and c <d。 5. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1 or 2, characterized in that: In step 4, as the horizontal well trajectory moves from the upper reservoir target point to the lower reservoir target point, the angle between the horizontal well trajectory and the target layer is 'e' before encountering the interlayer, and the angle between the horizontal well trajectory and the target layer is 'f' after encountering the interlayer, and 'e'... <f。 6. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1 or 2, characterized in that: In step 3, the horizontal distance between two adjacent target points is greater than 50 meters.
7. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1 or 2, characterized in that: In step 3, the last target point on the horizontal trajectory is located in the upper reservoir.
8. The horizontal well trajectory control method for a target layer containing interlayers according to claim 3, characterized in that: The included angle b is b≤arccos(1-2πDK / 360) In the formula: arccosine function, π, D, thickness of the lower reservoir, and K, inclination rate.
9. The horizontal well trajectory control method for a target layer containing interlayers according to claim 8, characterized in that: The inclination rate K is less than the maximum inclination rate, which is determined based on the inclination tool and geological features.
10. The horizontal well trajectory control method for a target layer containing interlayers according to claim 2, characterized in that: The intermediate reservoir includes several secondary interlayers and secondary reservoirs.
11. The horizontal well trajectory control method for a target layer containing interlayers according to claim 1, characterized in that: The reference well in step 1 includes a pilot well, a drilled vertical well in the same block, or a drilled deviated well in the same block. The logging data of the reference well includes the target layer and at least one marker layer.