By optimizing the control sequence and duration of the waste liquid pump and waste liquid valve, the problem of long waste liquid discharge time in blood analyzers was solved, thus improving the instrument's operating efficiency.
Patent Information
- Application Number
- CN202611341455.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-31
- Publication Date
- 2026-11-10
AI Technical Summary
Existing blood analyzers have a long time required for the waste liquid to be discharged from the sample preparation module, resulting in low operating efficiency.
By controlling the opening sequence and duration of the waste liquid pump and waste liquid valve, the waste liquid discharge process is optimized, including the waste liquid pump opening first, the waste liquid valve opening later or simultaneously, and the waste liquid pump closing first and the waste liquid valve closing later after waste liquid discharge. This optimizes the pipeline pressure changes between the waste liquid valve and the waste liquid pump, thereby improving the waste liquid discharge efficiency.
This reduces the total time required for waste liquid discharge and improves the operating efficiency of the blood analyzer.
Smart Images

Figure CN123066342A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of sample testing technology, and in particular to blood analyzers. Background Technology
[0002] In existing technologies, a sample preparation module is typically used to prepare the sample solution. After testing the output sample solution, the remaining liquid in the sample preparation module is drained to clean the module.
[0003] The drawback of the existing technology is that the sample preparation module takes a long time to discharge waste liquid, and / or the other steps performed in conjunction with the sample preparation module to discharge waste liquid take a long time, which makes the operating efficiency of the existing blood analyzer low. Summary of the Invention
[0004] The main technical problem addressed in this application is how to improve the operating efficiency of blood analyzers.
[0005] To solve the above-mentioned technical problems, the first technical solution adopted in this application is: a blood analyzer, comprising: a sample preparation module for preparing sample solution, the sample preparation module having a waste liquid outlet; a waste liquid valve, one end of the waste liquid valve being connected to the waste liquid outlet; and a waste liquid pump, the other end of the waste liquid valve being connected to the waste liquid pump, the waste liquid pump being used to discharge the waste liquid in the sample preparation module sequentially through the waste liquid outlet, the waste liquid valve, and the waste liquid pump; wherein, during the discharge of waste liquid, the waste liquid pump is turned on first, and the waste liquid valve is turned on later, or the waste liquid pump and the waste liquid valve are turned on simultaneously; and / or, after the waste liquid is discharged, the waste liquid pump is turned off first, and the waste liquid valve is turned off later.
[0006] The blood analyzer also includes: a detection module; a cleaning fluid valve; a cleaning module for storing cleaning fluid, which is connected to the sample preparation module via the cleaning fluid valve; and a sample dispensing valve connected to both the sample preparation module and the detection module. The sample dispensing valve opens to deliver sample fluid to the detection module, then closes. After the sample dispensing valve closes and the waste fluid pump starts, the waste fluid valve opens. And / or, after waste fluid is discharged, the waste fluid pump closes first, the waste fluid valve closes subsequently, and within 0.5 seconds of the waste fluid valve closing, the cleaning fluid valve opens to deliver cleaning fluid to the sample preparation module.
[0007] Specifically, for the same sample preparation module, the total operating time of the waste liquid pump is different at different time periods; and / or, for the same sample preparation module, the total operating time of the waste liquid valve is different at different time periods; and / or, during the same waste liquid discharge process of the same sample preparation module, the total operating time of the waste liquid pump is different from the total operating time of the waste liquid valve.
[0008] The blood analyzer includes: multiple sample preparation modules; multiple waste liquid valves, with each sample preparation module connected to a corresponding waste liquid valve; each sample preparation module is connected to a waste liquid pump via a corresponding waste liquid valve, the waste liquid pump being used to discharge waste liquid from the sample preparation module sequentially through the sample preparation module, waste liquid valve, and waste liquid pump; for the same sample, different sample solutions are prepared in multiple sample preparation modules for different tests; the total operating time of the waste liquid pumps differs during the waste liquid discharge process of different sample preparation modules; and... / Or, the total opening time of the waste liquid valves in different sample preparation modules is different during the waste liquid discharge operation; and / or, the total opening time of the waste liquid pumps is different during the first cleaning operation of different sample preparation modules; and / or, the total opening time of the waste liquid valves is different during the first cleaning operation of different sample preparation modules; and / or, the total opening time of the waste liquid pumps is different during the second cleaning operation of different sample preparation modules; and / or, the total opening time of the waste liquid valves is different during the second cleaning operation of different sample preparation modules.
[0009] Wherein, the diameter of the waste liquid outlet is greater than 0.5 mm and less than 3 mm; and / or, the length of the waste liquid outlet is not greater than 50 mm; and / or, the volume of the pressure-bearing cavity is less than 5 ml; wherein, the pressure-bearing cavity is the accommodating cavity between the waste liquid outlet and the waste liquid valve; and / or, the height of the waste liquid valve is not greater than the height of the waste liquid outlet.
[0010] The blood analyzer also includes a sample distribution module, which is used to distribute samples to each sample preparation module to prepare sample solutions. In the process of distributing the same sample to each sample preparation module, the volume of the pressure chamber corresponding to the first sample preparation module to which the sample is distributed is not less than the volume of the pressure chamber corresponding to the last sample preparation module to which the sample is distributed. The pressure chamber is the cavity between the waste liquid outlet and the waste liquid valve.
[0011] Specifically, during the process of the waste liquid pump closing first and the waste liquid valve closing later, the time interval between the closing time of the waste liquid pump and the closing time of the waste liquid valve is greater than 0.05 seconds and less than 0.5 seconds; and / or, the diameter of the pipeline between the waste liquid pump and the waste liquid valve is not less than 0.5 mm and not more than 5 mm; and / or, the length of the pipeline between the waste liquid pump and the waste liquid valve is less than 20 cm.
[0012] The sample preparation module includes a reaction chamber, which is used to prepare sample solutions. The capacity of the reaction chamber is no more than 7 ml.
[0013] Specifically, after the sample preparation module delivers at least a portion of the sample solution to the detection module and discharges the remaining sample solution, the cleaning module delivers cleaning solution to the sample preparation module at least twice for cleaning; during the process of the cleaning module delivering cleaning solution to the sample preparation module at least twice, the ratio between the volume of the second cleaning solution and the volume of the first cleaning solution is 1.2-1.5; and / or, during the process of the cleaning module delivering the first cleaning solution to the sample preparation module, the waste liquid valve is opened before the cleaning solution valve is closed.
[0014] The flow rate of the waste liquid pump is 0.1-3 liters; and / or, the suction head of the waste liquid pump is 3-10 meters of water column, or the suction head of the waste liquid pump is 5-30 meters of water column.
[0015] The beneficial effects of this application are as follows: Unlike existing technologies, the blood analyzer in this application includes: a sample preparation module for preparing sample solution, the sample preparation module having a waste liquid outlet; a waste liquid valve, one end of which is connected to the waste liquid outlet; and a waste liquid pump, the other end of which is connected to the waste liquid valve, the waste liquid pump being used to discharge waste liquid from the sample preparation module sequentially through the waste liquid outlet, the waste liquid valve, and the waste liquid pump; wherein, during the discharge of waste liquid, the waste liquid pump is turned on first, followed by the waste liquid valve, or the waste liquid pump and the waste liquid valve are turned on simultaneously; and / or, after the waste liquid is discharged, the waste liquid pump is turned off first, followed by the waste liquid valve. Based on the above methods, by controlling the waste liquid pump to open first and the waste liquid valve to open later during the waste liquid discharge process, or by controlling the waste liquid pump and waste liquid valve to open simultaneously during the waste liquid discharge process, it is possible to reduce the possibility of a high initial value of hydraulic or pneumatic pressure in the pipeline between the waste liquid valve and the waste liquid pump after the waste liquid valve opens, thus reducing the initial value of the waste liquid discharge rate. This reduces the time required for waste liquid discharge. And / or, by controlling the waste liquid pump to close first and the waste liquid valve to close later after waste liquid discharge, it is possible to improve the sample... The last portion of waste liquid in the preparation module is discharged through the residual negative pressure in the pipeline between the waste liquid valve and the waste liquid pump. This discharge of the last portion of waste liquid is completed during the process of the pipeline between the waste liquid valve and the waste liquid pump returning from negative pressure to normal pressure, without having to stop the waste liquid pump after the waste liquid is discharged and wait for a corresponding period of time. This reduces the time required for the step of creating negative pressure and then restoring normal pressure in the pipeline between the waste liquid valve and the waste liquid pump to facilitate the discharge of waste liquid, thereby improving the operating efficiency of the blood analyzer. Attached Figure Description
[0016] To more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0017] Figure 1 This is one of the structural schematic diagrams of an embodiment of the blood analyzer of this application; Figure 2 This is a second schematic diagram of the structure of an embodiment of the blood analyzer of this application; Figure 3 This is the third schematic diagram of the structure of an embodiment of the blood analyzer of this application; Figure 4 This is the fourth schematic diagram of the structure of an embodiment of the blood analyzer of this application; Figure 5 This is the fifth schematic diagram of an embodiment of the blood analyzer of this application.
[0018] Figure reference numerals: 11. Sample preparation module; 12. Waste liquid valve; 13. Waste liquid pump; 14. Waste liquid tank; 15. Detection module; 16. Cleaning liquid valve; 17. Cleaning module; 18. Sample dispensing valve; 19. Sample dispensing module. Detailed Implementation
[0019] The present application will now be described in further detail with reference to the accompanying drawings and embodiments. It should be particularly noted that the following embodiments are for illustrative purposes only and do not limit the scope of the application. Similarly, the following embodiments are only some, not all, embodiments of the present application, and all other embodiments obtained by those skilled in the art without inventive effort are within the scope of protection of the present application.
[0020] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a mutually exclusive, independent, or alternative embodiment. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.
[0021] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "setting," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or a connection through an intermediate medium. Those skilled in the art will understand the specific meanings of the above terms within the context of this application.
[0022] In existing technologies, a sample preparation module is typically used to prepare the sample solution. After testing the output sample solution, the remaining liquid in the sample preparation module is drained to clean the module.
[0023] The drawback of the existing technology is that the sample preparation module takes a long time to discharge waste liquid, and / or the other steps performed in conjunction with the sample preparation module to discharge waste liquid take a long time, which makes the operating efficiency of the existing blood analyzer low.
[0024] For example, if the sample preparation module prepares the sample solution and then delivers it to the corresponding detection module for sample testing, and the sample preparation module is then cleaned, and the waste liquid formed by the remaining sample solution is discharged before cleaning, or the waste liquid formed after cleaning is discharged during the cleaning process, if the waste liquid valve is opened before the waste liquid pump is turned on, the air pressure in the pipeline between the waste liquid valve and the waste liquid pump will be relatively high after the waste liquid valve is opened and before the waste liquid pump is turned on. Therefore, even if the waste liquid valve is fully opened, the waste liquid in the sample preparation module is difficult to be discharged through the pipeline between the waste liquid valve and the waste liquid pump, resulting in low efficiency in waste liquid discharge, that is, a long time required to discharge waste liquid, and low operating efficiency of the blood analyzer.
[0025] To address the aforementioned problems, this application discloses a blood analyzer, comprising: a sample preparation module for preparing sample solution, the sample preparation module having a waste liquid outlet; a waste liquid valve, one end of the waste liquid valve being connected to the waste liquid outlet; and a waste liquid pump, the other end of the waste liquid valve being connected to the waste liquid pump, the waste liquid pump being used to discharge waste liquid from the sample preparation module sequentially through the waste liquid outlet, the waste liquid valve, and the waste liquid pump; wherein, during the discharge of waste liquid, the waste liquid pump is turned on first, followed by the waste liquid valve, or the waste liquid pump and the waste liquid valve are turned on simultaneously; and / or, after the waste liquid is discharged, the waste liquid pump is turned off first, followed by the waste liquid valve. Based on the above method, the operating efficiency of the blood analyzer can be improved.
[0026] This application discloses a blood analyzer, see [link to relevant documentation] Figure 1 , Figure 1 This is a schematic diagram of one embodiment of the blood analyzer of this application, as shown below. Figure 1 As shown, the blood analyzer includes a sample preparation module 11, a waste liquid valve 12, and a waste liquid pump 13.
[0027] The sample preparation module 11 is used to prepare sample solution and has a waste liquid outlet.
[0028] One end of the waste liquid valve 12 is connected to the waste liquid port.
[0029] The other end of the waste liquid valve 12 is connected to the waste liquid pump 13, which is used to discharge the waste liquid in the sample preparation module 11 through the waste liquid port, the waste liquid valve 12 and the waste liquid pump 13 in sequence.
[0030] In the process of discharging waste liquid, waste liquid pump 13 is turned on first, followed by waste liquid valve 12, or waste liquid pump 13 and waste liquid valve 12 are turned on simultaneously.
[0031] And / or, after the waste liquid is discharged, the waste liquid pump 13 is turned off first, and the waste liquid valve 12 is turned off later.
[0032] Specifically, in one example, see Figure 2 , Figure 2 This is a second schematic diagram of the structure of an embodiment of the blood analyzer of this application, as shown below. Figure 2 As shown, the blood analyzer may also include a waste liquid pool 14. The waste liquid pump 13 can extract the waste liquid formed by the residual sample liquid in the sample preparation module 11, or the waste liquid formed after washing, and discharge it into the waste liquid pool 14 to complete the treatment of the discharged waste liquid.
[0033] In one example, the sample preparation module 11 can receive the corresponding blood and corresponding reagents to prepare a sample solution, which is then delivered to the corresponding detection module for sample detection to obtain the sample detection result. After that, the remaining sample solution in the sample preparation module 11 needs to be discharged. The waste liquid formed by the remaining sample solution can be discharged first, and then the sample preparation module 11 can be cleaned at least once to form new waste liquid, and then the new waste liquid can be discharged until the sample preparation module 11 is cleaned.
[0034] During the corresponding waste liquid discharge process, the waste liquid pump 13 can be controlled to open first, followed by the waste liquid valve 12. In this way, when waste liquid needs to be discharged, the waste liquid pump 13 can be turned on in advance before the waste liquid valve 12 is turned on. This ensures that the initial pressure of the pipeline between the waste liquid valve 12 and the waste liquid pump 13 is a high negative pressure after the waste liquid valve 12 is turned on, thereby increasing the rate at which waste liquid is discharged through the pipeline between the waste liquid valve 12 and the waste liquid pump 13 after the waste liquid valve 12 is turned on.
[0035] Alternatively, during the corresponding waste liquid discharge process, the waste liquid pump 13 and the waste liquid valve 12 are opened simultaneously. In this way, when waste liquid needs to be discharged, after the waste liquid valve 12 is opened, a negative pressure can be formed in the pipeline between the waste liquid valve 12 and the waste liquid pump 13 as quickly as possible, so as to increase the rate at which the waste liquid is discharged through the pipeline between the waste liquid valve 12 and the waste liquid pump 13.
[0036] It should be noted that the aforementioned opening of the corresponding valve or pump can refer to sending an opening signal to the corresponding valve or pump to drive it to open. Upon receiving the opening signal, the corresponding valve or pump gradually opens from small to large (e.g., the valve gradually increases or the power provided by the pump gradually increases) until it reaches a preset fully open state. Similarly, the aforementioned closing of the corresponding valve or pump can refer to sending a closing signal to the corresponding valve or pump to drive it to close. Upon receiving the closing signal, the corresponding valve or pump gradually closes from large to small (e.g., the valve gradually decreases or the power provided by the pump gradually decreases) until it reaches a preset fully closed state.
[0037] Unlike existing technologies, the blood analyzer in this application includes: a sample preparation module for preparing sample solution, the sample preparation module having a waste liquid outlet; a waste liquid valve, one end of which is connected to the waste liquid outlet; and a waste liquid pump, the other end of which is connected to the waste liquid valve, the waste liquid pump being used to discharge waste liquid from the sample preparation module sequentially through the waste liquid outlet, the waste liquid valve, and the waste liquid pump; wherein, during the discharge of waste liquid, the waste liquid pump is turned on first, followed by the waste liquid valve, or the waste liquid pump and the waste liquid valve are turned on simultaneously; and / or, after the waste liquid is discharged, the waste liquid pump is turned off first, followed by the waste liquid valve. Based on the above methods, by controlling the waste liquid pump to open first and the waste liquid valve to open later during the waste liquid discharge process, or by controlling the waste liquid pump and waste liquid valve to open simultaneously during the waste liquid discharge process, it is possible to reduce the possibility of a high initial value of hydraulic or pneumatic pressure in the pipeline between the waste liquid valve and the waste liquid pump after the waste liquid valve opens, thus reducing the initial value of the waste liquid discharge rate. This reduces the time required for waste liquid discharge. And / or, by controlling the waste liquid pump to close first and the waste liquid valve to close later after waste liquid discharge, it is possible to improve the sample... The last portion of waste liquid in the preparation module is discharged through the residual negative pressure in the pipeline between the waste liquid valve and the waste liquid pump. This discharge of the last portion of waste liquid is completed during the process of the pipeline between the waste liquid valve and the waste liquid pump returning from negative pressure to normal pressure, without having to stop the waste liquid pump after the waste liquid is discharged and wait for a corresponding period of time. This reduces the time required for the step of creating negative pressure and then restoring normal pressure in the pipeline between the waste liquid valve and the waste liquid pump to facilitate the discharge of waste liquid, thereby improving the operating efficiency of the blood analyzer.
[0038] In some embodiments, see Figure 3 , Figure 3 This is a third schematic diagram of the structure of an embodiment of the blood analyzer of this application, as shown below. Figure 3 As shown, the blood analyzer also includes a detection module 15, a cleaning fluid valve 16, a cleaning module 17, and a sample dispensing valve 18.
[0039] The cleaning module 17 is used to store the cleaning solution, and the cleaning module 17 is connected to the sample preparation module 11 through the cleaning solution valve 16.
[0040] The sample dispensing valve 18 is connected to the sample preparation module 11 and the detection module 15 respectively.
[0041] After the sample outlet valve 18 is opened to deliver the sample liquid to the detection module 15, the sample outlet valve 18 is closed.
[0042] After the sample outlet valve 18 is closed and the waste liquid pump 13 is turned on, the waste liquid valve 12 is turned on.
[0043] And / or, after the waste liquid is discharged, the waste liquid pump 13 is turned off first, the waste liquid valve 12 is turned off then, and within 0.5 seconds after the waste liquid valve 12 is turned off, the cleaning liquid valve 16 is turned on to deliver the cleaning liquid to the sample preparation module 11.
[0044] Specifically, the detection module 15 can be a flow chamber or other types of devices for sample detection, which are not limited here.
[0045] After the sample preparation module 11 has prepared the sample solution, the sample outlet valve 18 can be opened so that the output sample solution is injected into the detection module 15 through the sample outlet valve 18 for sample detection. After the detection module 15 has received enough sample solution, the sample outlet valve 18 can be closed.
[0046] First, after the sample outlet valve 18 is closed and the waste liquid pump 13 is turned on, the waste liquid pump 13 can quickly create a negative pressure in the pipeline between the waste liquid valve 12 and the waste liquid pump 13, and then control the waste liquid valve 12 to open. After the waste liquid valve 12 is turned on, the rate of waste liquid discharge is increased by the negative pressure, thereby improving the operating efficiency of the blood analyzer.
[0047] In one example, the waste pump 13 may be turned on 0.5 seconds after the sample valve 18 is closed, and the waste pump 13 may be turned on 0.5 seconds before the waste valve 12 is turned on, and 10 milliseconds before the time when the closing signal is sent to the sample valve 18 and the time when the opening signal is sent to the waste valve 12.
[0048] Second, after completing the waste liquid discharge process, the waste liquid pump 13 can be turned off first, followed by the waste liquid valve 12 to stop waste liquid discharge. Within 0.5 seconds after closing the waste liquid valve 12, the cleaning liquid valve 16 is opened to allow the cleaning liquid to be delivered to the sample preparation module 11 via the cleaning module 17 through the cleaning liquid valve 16 for cleaning. The cleaning liquid can be a diluent, which can be used both for sample preparation in the sample preparation module 11 and for cleaning the sample preparation module 11. Alternatively, the cleaning liquid can be other types of liquids used solely for cleaning the sample preparation module 11; the specific type depends on actual needs and is not limited here.
[0049] In one example, after the waste liquid is discharged, the corresponding cleaning solution can be injected into the sample preparation module 11 for cleaning. Furthermore, by controlling the opening of the cleaning solution valve 16 within 0.5 seconds after the waste liquid valve 12 is closed to carry out the cleaning operation, the efficiency of the cleaning operation can be improved, thereby increasing the operating efficiency of the blood analyzer.
[0050] Furthermore, if a cleaning operation is required for the sample preparation module 11, the remaining waste liquid in the sample preparation module 11 can be drained first, followed by a first cleaning operation to drain the waste liquid generated during the first cleaning operation, and then a second cleaning operation to drain the waste liquid generated during the second cleaning operation. This completes the cleaning process. Therefore, for sample testing of a single sample solution, at least three processes for draining waste liquid from the sample preparation module 11 used to prepare that sample solution are configured.
[0051] In some embodiments, for the same sample preparation module 11, the total operating time of the waste liquid pump 13 is different for different discharge volumes of waste liquid.
[0052] And / or, for the same sample preparation module 11, the total opening time of the waste liquid valve 12 is different under different discharge volumes of waste liquid.
[0053] And / or, during the same waste liquid discharge process in the same sample preparation module 11, the total opening time of the waste liquid pump 13 is different from the total opening time of the waste liquid valve 12.
[0054] Specifically, within the same sample preparation module 11, the total operating time of the waste liquid pump 13 varies depending on the amount of waste liquid discharged. In one example, the total operating time of the waste liquid pump 13 is positively correlated with the amount of waste liquid discharged. In other examples, since residual liquid may adhere to the inner wall of the sample preparation module 11 during waste liquid discharge, and the rate at which this residual liquid flows to the waste liquid outlet is relatively slow, the total operating time of the waste liquid pump can also be determined based on the amount of liquid on the inner wall of the sample preparation module 11. For example, the total operating time of the waste liquid pump 13 can also be positively correlated with the maximum amount of liquid on the inner wall of the sample preparation module 11 during waste liquid discharge, where the maximum amount of liquid on the inner wall of the sample preparation module 11 during waste liquid discharge can refer to the residual liquid adhering to the inner wall of the sample preparation module 11 during the aforementioned waste liquid discharge process.
[0055] In one example, it is assumed that the total operating time of waste liquid pump 13 can satisfy the following formula: Z = AX + BY In the formula, Z can be the total operating time of the waste liquid pump 13, X can be the discharge volume of waste liquid, Y can be the maximum liquid volume of the liquid located on the inner wall of the sample preparation module 11 during the waste liquid discharge process, A is the first coefficient, B is the second coefficient, and both A and B are greater than or equal to 0.
[0056] If A is greater than 0 and B is equal to 0, then the total operating time of waste liquid pump 13 is positively correlated with the amount of waste liquid discharged, and specifically, the total operating time of waste liquid pump 13 is directly proportional to the amount of waste liquid discharged.
[0057] If A equals 0 and B is greater than 0, then the total operating time of the waste liquid pump 13 is positively correlated with the maximum liquid volume on the inner wall of the sample preparation module 11 during the waste liquid discharge process. Specifically, the total operating time of the waste liquid pump 13 is directly proportional to the maximum liquid volume on the inner wall of the sample preparation module 11 during the waste liquid discharge process.
[0058] If both A and B are greater than 0, then the total operating time of waste liquid pump 13 is positively correlated with the amount of waste liquid discharged, and the total operating time of waste liquid pump 13 is positively correlated with the maximum liquid volume on the inner wall of sample preparation module 11 during the waste liquid discharge process.
[0059] Within the same sample preparation module 11, the total opening time of the waste liquid valve 12 varies depending on the amount of waste liquid discharged. In one example, the total opening time of the waste liquid valve 12 is positively correlated with the amount of waste liquid discharged.
[0060] During the same waste liquid discharge process of the same sample preparation module 11, the total operating time of waste liquid pump 13 is different from the total operating time of waste liquid valve 12. In one example, since the time when waste liquid pump 13 is turned on can be earlier than the time when waste liquid valve 12 is turned on, and the time when waste liquid pump 13 is turned off can be equal to the time when waste liquid valve 12 is turned off, the total operating time of waste liquid pump 13 can be less than the total operating time of waste liquid valve 12.
[0061] Based on the above method, the rationality of the total opening time of waste liquid pump 13 and waste liquid valve 12 during each waste liquid discharge process can be improved, thereby improving the operating efficiency of the blood analyzer.
[0062] In some embodiments, see Figure 4 , Figure 4 This is the fourth schematic diagram of an embodiment of the blood analyzer of this application, as shown below. Figure 4 As shown, the blood analyzer includes multiple sample preparation modules 11 and multiple waste liquid valves 12.
[0063] Multiple sample preparation modules 11 are connected to multiple waste liquid valves 12 in a one-to-one correspondence.
[0064] Each sample preparation module 11 is connected to a waste liquid pump 13 via a corresponding waste liquid valve 12. The waste liquid pump 13 is used to discharge the waste liquid in the sample preparation module 11 through the sample preparation module 11, the waste liquid valve 12 and the waste liquid pump 13 in sequence.
[0065] For the same sample, different sample solutions are prepared in multiple sample preparation modules 11 for different tests.
[0066] The total operating time of the waste liquid pump 13 varies depending on the sample preparation module 11 during the waste liquid discharge operation.
[0067] And / or, the total opening time of the waste liquid valve 12 is different for different sample preparation modules 11 during the waste liquid discharge operation of the remaining sample liquid.
[0068] And / or, the total operating time of the waste liquid pump 13 is different during the first cleaning operation of different sample preparation modules 11.
[0069] And / or, the total opening time of the waste liquid valve 12 is different during the first cleaning operation of different sample preparation modules 11.
[0070] And / or, the total operating time of the waste liquid pump 13 is different during the second cleaning operation of different sample preparation modules 11.
[0071] And / or, the total opening time of the waste liquid valve 12 is different during the second cleaning operation of different sample preparation modules 11.
[0072] Specifically, in one example, different sample preparation modules 11 can prepare sample solutions for corresponding item testing. The amount of sample solution required for different item testing and the amount of waste liquid formed in the end may vary depending on the testing status or testing requirements of the corresponding item.
[0073] When the amount of waste liquid discharged from different sample preparation modules 11 is different, the total opening time of waste liquid pump 13 is different, and / or the total opening time of waste liquid valve 12 is different.
[0074] In addition, in one example, if it is necessary to clean the sample preparation module 11, the remaining waste liquid in the sample preparation module 11 can be discharged first, and then the sample preparation module 11 can be cleaned for the first time to discharge the waste liquid formed by the first cleaning operation, and then the sample preparation module 11 can be cleaned for the second time to discharge the waste liquid formed by the second cleaning operation. Thus, the cleaning operation is completed.
[0075] Assume that the first liquid volume is the volume of cleaning fluid injected into the sample preparation module 11 during the first cleaning operation, the second liquid volume is the volume of cleaning fluid injected into the sample preparation module 11 during the second cleaning operation, and the preparation liquid volume is the volume of sample liquid prepared by the sample preparation module 11 in a single operation.
[0076] The second volume is 1.2 to 1.5 times the first volume.
[0077] And / or, the second liquid volume is 1.5 times the preparation liquid volume.
[0078] And / or, the first liquid volume is 1-1.2 times the preparation liquid volume.
[0079] By injecting a first volume of cleaning solution, greater than or equal to the volume of the preparation solution, into the sample preparation module 11 during the first cleaning operation, it is possible to clean all the inner walls of the sample preparation module 11 contaminated by the sample solution based on the cleaning solution.
[0080] In the rapid process of dispensing blood samples, adding hemolysin, adding dye, adding diluent, mixing samples, incubating samples, and emptying samples before the first cleaning operation, nonlinear processes such as turbulence and eddies inevitably occur in the sample preparation module 11. This results in the actual liquid level on the inner wall of the sample preparation module 11 often being higher than the liquid level below the static liquid level of the same volume. Furthermore, for a considerable period after the liquid in the sample preparation module 11 is emptied, a large amount of residual liquid often remains on the inner wall. If the inner wall, which is higher than the liquid level below the static liquid level of the same volume, is not properly cleaned, it is easy for the inner wall of the sample preparation module 11 to be uncleaned, which can lead to cross-contamination between different samples in the future.
[0081] Because the cleaning fluid is injected into the sample preparation module 11 at a relatively fast speed during the first cleaning operation, based on our experience, turbulence, eddies, and other nonlinear processes inevitably occur in the sample preparation module 11. This causes the actual liquid level on the inner wall of the sample preparation module 11 to be higher than the liquid level below the static liquid level of the same volume. Therefore, when performing the second cleaning operation, the volume of liquid used in the second cleaning operation should be higher than the volume of preparation fluid to reduce the possibility that the inner wall of the sample preparation module 11 may not be cleaned properly.
[0082] In the second cleaning operation, a second volume of cleaning fluid, which is greater than the volume of the preparation liquid and greater than the volume of the first liquid, is injected into the sample preparation module 11. This ensures that the liquid level of the cleaning fluid injected into the sample preparation module 11 in this cleaning operation is higher than the highest liquid level reached by the sample liquid in the preparation liquid operation or the cleaning fluid in the first cleaning operation. This achieves the cleaning operation of all the inner walls of the sample preparation module 11 contaminated by the sample liquid based on the cleaning fluid.
[0083] Furthermore, since the preparation liquid volume of different sample preparation modules 11 is different, resulting in different maximum liquid level heights of the sample liquid prepared by different sample preparation modules 11, and consequently different amounts of waste liquid generated in each cleaning operation, the amount of cleaning liquid injected and / or the amount of waste liquid generated in the cleaning operation will also differ accordingly. Therefore, it is necessary to consider the difference in the amount of waste liquid discharged by the waste liquid valve 12 and the waste liquid pump 13.
[0084] Therefore, during the first cleaning operation of different sample preparation modules 11, the total opening time of the waste liquid pump 13 is different, and / or the total opening time of the waste liquid valve 12 is different.
[0085] Furthermore, during the second cleaning operation of different sample preparation modules 11, the total opening time of the waste liquid pump 13 is different, and / or the total opening time of the waste liquid valve 12 is different.
[0086] In one example, the flow rate of waste liquid pump 13 is 0.1-3 liters.
[0087] And / or, the suction lift of waste liquid pump 13 is 3-10 meters of water column, or the suction lift of waste liquid pump 13 is 5-30 meters of water column.
[0088] In other examples, the parameters of waste pump 13 can be combined in other ways, which are not limited here.
[0089] Based on the above method, the waste liquid valve 12 and waste liquid pump 13 can be controlled differently according to the amount of waste liquid to be discharged corresponding to different sample preparation modules 11, thereby improving the coordination and rationality of cleaning and waste liquid discharge operations, reducing the possibility of poor cleaning effect and needing to be cleaned again, and improving the operating efficiency of the blood analyzer.
[0090] In some embodiments, the diameter of the waste outlet is greater than 0.5 mm and less than 3 mm.
[0091] And / or, the length of the waste liquid outlet is no more than 50 mm.
[0092] And / or, the volume of the pressure chamber is less than 5 ml. The pressure chamber is the accommodating cavity between the waste liquid outlet and the waste liquid valve 12.
[0093] And / or, the height of the waste liquid valve 12 is not greater than the height of the waste liquid port.
[0094] Specifically, the sample preparation module 11 may include a waste liquid outlet, and the sample preparation module 11 may be connected to the waste liquid valve 12 through the waste liquid outlet.
[0095] By making the diameter of the waste liquid outlet greater than 0.5 mm and less than 3 mm, and / or the length of the waste liquid outlet not greater than 50 mm, and / or the volume of the pressure chamber less than 5 ml, the volume of the pressure chamber is small enough to allow the pressure inside the pressure chamber to be increased from atmospheric pressure to positive pressure when a portion of the liquid (such as the sample, or the reagent used to mix with the sample to form the sample solution, or the sample solution) in the sample preparation module 11 falls into the pressure chamber, thereby reducing the amount of liquid that continues to fall and thus reducing the waste of sample, reagent, or sample solution.
[0096] By ensuring that the height of the waste liquid valve 12 is no greater than the height of the waste liquid outlet, the efficiency of transporting waste liquid from the waste liquid outlet to the waste liquid valve 12 can be improved. Through gravity, the flow rate of the waste liquid is increased, thereby improving the operating efficiency of the blood analyzer.
[0097] In some embodiments, see Figure 5 , Figure 5 This is the fifth schematic diagram of an embodiment of the blood analyzer of this application, as shown below. Figure 5 As shown, the blood analyzer also includes a sample separation module 19.
[0098] The sample distribution module 19 is used to distribute samples to each sample preparation module 11 to prepare sample solutions.
[0099] In the process of allocating the same sample to each sample preparation module 11, the volume of the pressure chamber corresponding to the first sample preparation module 11 to be allocated a sample is not less than the volume of the pressure chamber corresponding to the last sample preparation module 11 to be allocated a sample.
[0100] The pressure chamber is the accommodating chamber between the waste liquid outlet and the waste liquid valve 12.
[0101] Specifically, the sample can be a blood sample or other type of sample used to prepare the sample solution, without limitation here.
[0102] In one example, by ensuring that the volume of the pressure chamber corresponding to the first sample preparation module 11 to be allocated a sample is less than or equal to the volume of the pressure chamber corresponding to the last sample preparation module 11 to be allocated a sample, the possibility of sample falling into the pressure chamber due to the excessive volume of the pressure chamber of the first sample preparation module 11 being allocated a sample, resulting in sample waste, and consequently insufficient sample allocated to the last sample preparation module 11 to be allocated a sample, is reduced. This improves the reliability of sample allocation and, in turn, enhances the reliability of the blood analyzer.
[0103] In some embodiments, during the process of the waste liquid pump 13 closing first and the waste liquid valve 12 closing later, the time interval between the closing time of the waste liquid pump 13 and the closing time of the waste liquid valve 12 is greater than 0.05 seconds and less than 0.5 seconds.
[0104] And / or, the diameter of the pipeline between the waste liquid pump 13 and the waste liquid valve 12 is not less than 0.5 mm and not more than 5 mm.
[0105] And / or, the length of the pipe between the waste liquid pump 13 and the waste liquid valve 12 is less than 20 cm.
[0106] Specifically, after the waste liquid discharge operation is completed, the waste liquid pump 13 can be controlled to close first, followed by the waste liquid valve 12. The time interval between the closing of the waste liquid pump 13 and the closing of the waste liquid valve 12 is greater than 0.05 seconds and less than 0.5 seconds. This allows the pipeline between the waste liquid valve 12 and the waste liquid pump 13 to increase the pressure as much as possible during the period when the waste liquid pump 13 is closed and the waste liquid valve 12 is open. The pressure is reduced from a higher negative pressure to a lower negative pressure, or restored to normal pressure. This ensures that the air pressure in the pressure chamber reaches or approaches normal pressure. When the sample preparation module 11 receives the next sample, the higher air pressure in the pressure chamber can support the newly added sample or prepared sample liquid, reducing the amount of sample or sample liquid wasted due to flowing into the pressure chamber. This improves the utilization rate of the sample liquid and thus enhances the reliability of the blood analyzer.
[0107] In some embodiments, the sample preparation module 11 includes a reaction chamber for preparing sample solution, and the capacity of the reaction chamber is no more than 7 ml.
[0108] Specifically, by making the capacity of the reaction chamber less than or equal to 7 ml, the amount of sample and reagents required to form the sample solution can be reduced, thereby maximizing the amount of waste liquid that can be produced in the reaction chamber. This reduces the time required for waste liquid discharge, improves the efficiency and reliability of waste liquid discharge, and also reduces the difficulty of waste liquid discharge, thus improving the reliability of the blood analyzer.
[0109] In some embodiments, based on the aforementioned embodiment of the detection module 15, after the sample preparation module 11 delivers at least a portion of the sample solution to the detection module 15 and discharges the remaining sample solution, the cleaning module 17 delivers cleaning solution to the sample preparation module 11 at least twice for cleaning.
[0110] During the process of the cleaning module 17 delivering cleaning solution to the sample preparation module 11 at least twice, the ratio between the volume of the second cleaning solution and the volume of the first cleaning solution is 1.2-1.5.
[0111] And / or, during the process of the cleaning module 17 delivering the first cleaning solution to the sample preparation module 11, the waste liquid valve 12 is opened before the cleaning solution valve 16 is closed.
[0112] Specifically, in one example, if it is necessary to clean the sample preparation module 11, the remaining waste liquid (such as the remaining sample liquid) in the sample preparation module 11 can be discharged first, and then a first cleaning solution can be supplied to the sample preparation module 11 to perform a first cleaning operation, and the waste liquid formed in the first cleaning operation can be discharged. Then, a second cleaning solution can be supplied to the sample preparation module 11 to perform a second cleaning operation, and the waste liquid formed in the second cleaning operation can be discharged. Thus, the cleaning operation is completed.
[0113] By setting the ratio of the second cleaning solution to the first cleaning solution to 1.2-1.5, the second cleaning operation can effectively clean the highest liquid level reached by the waste liquid generated in the first cleaning operation. This improves the reliability of the second cleaning operation, reduces the possibility that the second cleaning operation may not fully cover the areas contaminated by the first cleaning operation, and enhances the reliability of the cleaning operation, thereby improving the reliability of the blood analyzer.
[0114] By opening the waste liquid valve 12 before the cleaning liquid valve 16 is closed during the first cleaning process of the cleaning module 17 delivering the first cleaning solution to the sample preparation module 11, the efficiency of waste liquid discharge formed by the first cleaning solution can be improved. In addition, the second cleaning operation can clean the areas that were not completely cleaned in the first cleaning operation or the areas that were secondary contaminated. This improves both the reliability and efficiency of the cleaning operation, thereby improving the reliability and operating efficiency of the blood analyzer.
[0115] In the description of this application, the references to terms such as "one embodiment," "some embodiments," "example," "specific example," or "some examples," etc., refer to specific features, structures, materials, or characteristics described in connection with that embodiment or example, which are included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.
[0116] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified.
[0117] Any process or method described in the flowchart or otherwise herein can be understood as representing a module, segment, or portion of code comprising one or more executable instructions for implementing a particular logical function or process, and the scope of the preferred embodiments of this application includes additional implementations in which functions may be performed not in the order shown or discussed, including substantially simultaneously or in reverse order depending on the function involved, as will be understood by those skilled in the art to which embodiments of this application pertain.
[0118] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as a ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by, or in conjunction with, an instruction execution system, apparatus, or device (which may be a personal computer, server, network device, or other system that can fetch and execute instructions from, an instruction execution system, apparatus, or device). For the purposes of this specification, "computer-readable medium" can be any means that can contain, store, communicate, propagate, or transmit programs for use by, or in conjunction with, an instruction execution system, apparatus, or device. More specific examples (a non-exhaustive list) of computer-readable media include: an electrical connection having one or more wires (electronic device), a portable computer disk drive (magnetic device), random access memory (RAM), read-only memory (ROM), erasable and editable read-only memory (EPROM or flash memory), fiber optic devices, and portable optical disc read-only memory (CDROM). Alternatively, the computer-readable medium may be paper or other suitable media on which the program can be printed, since the program can be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, interpreting, or otherwise processing as necessary, and then stored in a computer memory.
[0119] The above description is merely an embodiment of this application and does not limit the patent scope of this application. Any equivalent structural or procedural transformations made using the content of this application's specification and drawings, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of this application.
Claims
1. A blood analyzer, characterized in that, include: A sample preparation module for preparing sample solutions, the sample preparation module having a waste outlet; Waste liquid valve, one end of which is connected to the waste liquid port; Waste liquid pump, the other end of the waste liquid valve is connected to the waste liquid pump, the waste liquid pump is used to discharge the waste liquid in the sample preparation module through the waste liquid port, the waste liquid valve and the waste liquid pump in sequence; In the process of discharging the waste liquid, the waste liquid pump is turned on first, and the waste liquid valve is turned on later, or the waste liquid pump and the waste liquid valve are turned on simultaneously. And / or, after the waste liquid is discharged, the waste liquid pump is shut off first, and the waste liquid valve is then shut off.
2. The blood analyzer according to claim 1, characterized in that, The blood analyzer also includes: Detection module; Cleaning fluid valve; A cleaning module for storing cleaning solution, the cleaning module being connected to the sample preparation module via the cleaning solution valve; A sample dispensing valve, which is connected to both the sample preparation module and the detection module; Wherein, after the sample outlet valve is opened to deliver the sample liquid to the detection module, the sample outlet valve is closed; After the sample outlet valve is closed and the waste liquid pump is turned on, the waste liquid valve is opened; And / or, after the waste liquid is discharged, the waste liquid pump is shut off first, the waste liquid valve is then shut off, and within 0.5 seconds after the waste liquid valve is shut off, the cleaning liquid valve is opened to deliver the cleaning liquid to the sample preparation module.
3. The blood analyzer according to claim 1, characterized in that, For the same sample preparation module, the total operating time of the waste liquid pump is different for different discharge volumes of waste liquid; And / or, for the same sample preparation module, the total opening time of the waste liquid valve is different for different discharge volumes of waste liquid; And / or, during the same discharge of the waste liquid in the same sample preparation module, the total operating time of the waste liquid pump is different from the total operating time of the waste liquid valve.
4. The blood analyzer according to claim 1, characterized in that, The blood analyzer includes: Multiple sample preparation modules; Each of the multiple waste liquid valves and the multiple sample preparation modules are connected to the multiple waste liquid valves in a one-to-one correspondence. Each of the sample preparation modules is connected to the waste liquid pump through a corresponding waste liquid valve. The waste liquid pump is used to discharge the waste liquid in the sample preparation module through the sample preparation module, the waste liquid valve, and the waste liquid pump in sequence. For the same sample, different sample solutions are prepared in multiple sample preparation modules for different tests. The total operating time of the waste liquid pump varies among different sample preparation modules during the waste liquid discharge process. And / or, the total opening time of the waste liquid valve is different for different sample preparation modules during the waste liquid discharge operation of the remaining sample liquid; And / or, the total operating time of the waste liquid pump is different during the first cleaning operation of different sample preparation modules; And / or, the total opening time of the waste liquid valve is different during the first cleaning operation of different sample preparation modules; And / or, the total operating time of the waste liquid pump is different during the second cleaning operation of different sample preparation modules; And / or, the total opening time of the waste liquid valve is different during the second cleaning operation of different sample preparation modules.
5. The blood analyzer according to claim 1, characterized in that, The diameter of the waste liquid outlet is greater than 0.5 mm and less than 3 mm; And / or, the length of the waste liquid outlet is no more than 50 mm; And / or, the volume of the pressure-bearing cavity is less than 5 ml; wherein, the pressure-bearing cavity is the accommodating cavity between the waste liquid outlet and the waste liquid valve; And / or, the height of the waste liquid valve is not greater than the height of the waste liquid outlet.
6. The blood analyzer according to claim 1, characterized in that, The blood analyzer also includes: The sample distribution module is used to allocate samples to each of the sample preparation modules to prepare the sample solution; In the process of allocating the same sample to each of the sample preparation modules, the volume of the pressure chamber corresponding to the first sample preparation module to be allocated the sample is not less than the volume of the pressure chamber corresponding to the last sample preparation module to be allocated the sample. The pressure-bearing cavity is the accommodating cavity between the waste liquid outlet and the waste liquid valve.
7. The blood analyzer according to claim 1, characterized in that, During the process of the waste liquid pump shutting off first and the waste liquid valve shutting off later, the time interval between the time when the waste liquid pump shuts off and the time when the waste liquid valve shuts off is greater than 0.05 seconds and less than 0.5 seconds. And / or, the diameter of the pipeline between the waste liquid pump and the waste liquid valve is not less than 0.5 mm and not more than 5 mm; And / or, the length of the pipeline between the waste liquid pump and the waste liquid valve is less than 20 cm.
8. The blood analyzer according to claim 1, characterized in that, The sample preparation module includes a reaction chamber for preparing the sample solution, and the capacity of the reaction chamber is no more than 7 ml.
9. The blood analyzer according to claim 2, characterized in that, After the sample preparation module delivers at least a portion of the sample solution to the detection module and discharges the remaining sample solution, the cleaning module delivers the cleaning solution to the sample preparation module at least twice for cleaning. During the process of the cleaning module delivering the cleaning solution to the sample preparation module at least twice, the ratio between the volume of the second cleaning solution and the volume of the first cleaning solution is 1.2-1.
5. And / or, during the process of the cleaning module delivering the cleaning solution to the sample preparation module for the first time, the waste liquid valve is opened before the cleaning solution valve is closed.
10. The blood analyzer according to claim 4, characterized in that, The flow rate of the waste liquid pump is 0.1-3 liters; And / or, the suction lift of the waste liquid pump is 3-10 meters of water column, or the suction lift of the waste liquid pump is 5-30 meters of water column.