An intelligent energy consumption management system and control method for equipment

By linking APS, MES and PLC systems and combining them with the status monitoring module, precise preheating and gradient shutdown of tire production equipment were achieved, solving the problems of labor costs and energy waste in equipment energy management, and improving production efficiency and economic benefits.

CN123067288APending Publication Date: 2026-11-10PRINX CHENGSHAN (SHANDONG) TIRE COMPANY LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611356174.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-03
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

The existing energy management model for tire production equipment suffers from high labor costs, serious energy waste, and prolonged equipment standby due to operational errors. In particular, the equipment cannot be precisely controlled during preheating and shutdown, leading to increased production efficiency and economic costs.

Method used

By linking APS, MES and PLC systems, the preheating start time and graded delayed shutdown strategy are automatically calculated based on production scheduling data, so as to achieve precise preheating and gradient shutdown of equipment. Combined with the status monitoring module, the status of equipment and personnel is monitored in real time to optimize equipment energy consumption management.

Benefits of technology

It enables precise preheating and gradient shutdown of equipment, reduces standby energy consumption by 15%-25%, reduces startup and production waiting time, improves equipment utilization and economic benefits, and reduces the burden on production personnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123067288A_ABST
    Figure CN123067288A_ABST
Patent Text Reader

Abstract

This invention provides an intelligent energy consumption management and control method for equipment, comprising: transmitting production scheduling data from the APS to the MES; the MES determining whether there are any production tasks pending on the current equipment based on the production scheduling data, and if so, determining the planned production time and issuing a pre-start command to the PLC; the PLC receiving the command, determining the preheating start time, and starting the preheating process; the PLC starting production after personnel arrive; after production is completed and the equipment stops, the MES reading the estimated downtime of the equipment and the subsequent production schedule and transmitting it to the PLC; the PLC shutting down energy-consuming equipment groups and temperature-controlled heating devices according to a tiered delayed shutdown strategy. Through the linkage of the APS, MES, and PLC systems, the preheating start time is automatically calculated based on the production schedule, achieving precise equipment preheating. This avoids the waste of manpower costs caused by personnel arriving early, reduces resistance, prevents energy loss due to excessive preheating time, and also prevents forgetting to shut down high-power equipment after production, reducing non-production energy consumption.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of equipment energy consumption management technology, and in particular to an intelligent equipment energy consumption management system and control method. Background Technology

[0002] With the rapid development of tire companies, the need for new technologies and demands such as automation, intelligence, and digitalization in production equipment has become more urgent. In the tire production process, extruders and calenders are large-scale, high-energy-consuming equipment. Extruders and calenders are usually equipped with multiple barrel or roller temperature control zones, as well as energy-consuming equipment such as flue gas treatment equipment, water blowers, and circulating cooling systems. The energy consumption of these energy-consuming devices accounts for more than 50% of the total energy consumption of the equipment.

[0003] The aforementioned equipment has a large rated power and a long heating process. To reach the process set temperature (usually above 80℃), a long preheating time is required. Furthermore, the equipment is subject to process constraints, such as the inability to simultaneously and instantaneously cut off power after the production line stops due to thermal inertia, safety ventilation, or cooling requirements. Therefore, the timing of equipment preheating, the transition to heat preservation, and the order in which auxiliary energy-consuming equipment is shut down directly affect start-up waiting time and non-production energy consumption.

[0004] The current industry standard control method is as follows: production personnel need to arrive approximately 1.5 hours in advance, manually start the machine for preheating, and manually shut it down after production is complete. This method has two drawbacks:

[0005] Firstly, production staff sometimes arrive late, resulting in insufficient equipment preheating time, which leads to uncontrollable output quality or requires delayed production. On the other hand, arriving too early results in excessive heating time, wasting equipment energy. Furthermore, production staff are required to arrive 1.5 hours in advance. Even if qualified products are not produced during this period, the company still needs to count this time as working hours or pay overtime, resulting in high labor costs and reduced employee job satisfaction. This can easily trigger resistance from frontline production staff, increase management difficulty, and raise the risk of staff turnover.

[0006] Secondly, when the equipment is shut down or in standby mode, although the main unit has stopped, the temperature control heating, flue gas treatment, water blowing fan and circulating cooling system are operated independently by different controllers. Sometimes the operators forget to turn them off one by one, which will cause high-power equipment such as temperature control heating device, flue gas treatment equipment, water blowing fan and circulating cooling system to continue to run. The equipment continues to work after production stops, resulting in excessive energy consumption. Summary of the Invention

[0007] The purpose of this invention is to overcome the shortcomings of the above-mentioned technologies and provide an intelligent energy consumption management system and control method for equipment.

[0008] Therefore, the present invention provides a method for intelligent management and control of equipment energy consumption, comprising the following steps:

[0009] S1 and APS systems generate production scheduling data and automatically transmit the production scheduling data to the MES system;

[0010] Based on production scheduling data, the S2 and MES systems determine whether there are any production tasks waiting to be completed on the current equipment. If there are any production tasks waiting to be completed and the equipment is in a shutdown state, the system determines the production plan time and sends a pre-start command to the PLC control system. If there are no production tasks waiting to be completed, the equipment remains in a standby monitoring state.

[0011] After receiving the pre-start command, the S3 and PLC control systems determine the preheating start time and start the preheating process after the time is reached. The status monitoring module collects the equipment temperature in real time. When the temperature reaches the process set value and stabilizes, it switches to low-power constant temperature standby mode.

[0012] S4. After the status monitoring module detects the signal that the production personnel have arrived, the PLC control system starts the main control equipment and the group of power-consuming equipment, and enters the normal production process.

[0013] S5. After production is completed and the equipment is shut down, the MES system reads the estimated downtime of the equipment and the subsequent production schedule and transmits the data to the PLC control system. The PLC control system matches the corresponding graded delayed shutdown strategy according to the shutdown threshold, and shuts down the energy-consuming equipment group and temperature control heating device according to the time gradient, only retaining power supply to the basic monitoring and communication modules.

[0014] Preferably, in step S1, the production scheduling data includes the production specifications, quantity, input and output of rubber materials, rubber material storage time, and processing time period of the equipment and machine daily and per shift production plan.

[0015] Preferably, in step S3, determining the preheating start time includes the following steps:

[0016] S31. The preheating time is preset on the human-machine interface of the equipment.

[0017] S32. Based on the production plan time issued by the MES system and the current equipment time read by the PLC system, subtract the preset preheating time from the production plan time to obtain the equipment preheating start time.

[0018] Preferably, in step S5, the MES system needs to predict the remaining time based on production scheduling data and real-time production progress: when it detects that there is only 1 production specification information remaining for the shift, the estimated remaining production time is calculated based on the remaining production quantity and the standard production cycle of the equipment. Combined with the current system time, the estimated downtime is obtained. Then, combined with the production plan time of subsequent production scheduling data, the estimated total downtime is calculated, and this time data is synchronized to the PLC system as the basis for judging the graded delayed downtime strategy.

[0019] Preferably, in step S5, the tiered delayed shutdown strategy is executed step by step according to the time gradient, including:

[0020] If the downtime exceeds the first threshold, the energy-consuming equipment group will be shut down, but the temperature-controlled heating device will continue to operate.

[0021] If the downtime exceeds the second threshold, reduce the power of the temperature control heating device to maintain the heat preservation state;

[0022] If the downtime exceeds the third threshold, the main power supply of the temperature control heating device will be shut off, and only the power supply to the basic monitoring and communication modules will be maintained.

[0023] Preferably, the first threshold is 25-40 minutes, the second threshold is 1-1.5 hours, and the third threshold is 2-2.5 hours.

[0024] Preferably, in step S4, after the production personnel arrival signal is collected by the workstation card swiping system or the facial recognition system, it is fed back to the MES system through the status monitoring module; the MES system then transmits the arrival signal to the PLC control system.

[0025] Preferably, in step S2, if the equipment is detected to be in a maintenance-tagged and locked state, the pre-start command is blocked and the equipment enters a shutdown state.

[0026] The present invention also provides an intelligent energy consumption management system for equipment, comprising:

[0027] The APS system automatically transmits production scheduling data to the MES system;

[0028] The MES system is used to pre-store production scheduling data, record the actual production progress and downtime of equipment, and communicate bidirectionally with the PLC system.

[0029] The PLC control system receives pre-start instructions from the MES system and controls the start and stop of the main equipment, temperature control heating device, and energy-consuming equipment group.

[0030] The status monitoring module is used to monitor equipment temperature, whether production personnel are in place, equipment operating status, and equipment safety interlock signals in real time.

[0031] The PLC control system has a built-in execution control module, which executes the following control logic:

[0032] Before the production personnel arrive, the temperature control heating device is controlled to turn on the power supply system in advance and preheat according to the pre-start command issued by the MES system until the equipment temperature reaches the process set value.

[0033] Upon receiving a shutdown command, the system receives the estimated shutdown duration data from the MES system, matches the corresponding tiered delayed shutdown strategy based on the shutdown threshold, and gradually shuts down the energy-consuming equipment group and temperature-controlled heating device.

[0034] Preferably, the energy-consuming equipment group includes flue gas treatment equipment, a water blower, and a circulating cooling system.

[0035] This invention provides an intelligent energy consumption management system and control method for equipment, which has the following beneficial effects.

[0036] (1) By linking APS, MES and PLC systems, the preheating start time is automatically calculated according to the production schedule, so as to achieve precise equipment preheating and realize "the temperature arrives when people arrive". This avoids the waste of human resources caused by production personnel arriving early, reduces the resistance of production personnel, and prevents the power loss caused by excessive preheating time, thus ensuring the quality of product production process.

[0037] (2) Set up a graded delayed shutdown strategy, and shut down the energy-consuming equipment group and temperature control heating device according to the expected shutdown duration, while only keeping the basic monitoring and communication modules powered, to solve the standby energy consumption problem caused by forgetting to shut down the high-power auxiliary energy-consuming equipment after production, and effectively reduce the power consumption of the equipment in non-production state;

[0038] (3) The total estimated downtime calculated by the MES system is used as the basis for judging the graded delayed downtime strategy. On the one hand, there is no need for manual filling and estimation of downtime, eliminating errors and omissions caused by manual operation; on the other hand, it can distinguish between different working conditions such as short-term specification change, short-intermittent downtime and long-term shutdown, so that the graded downtime strategy fits the actual production interval on site, takes into account both energy saving effect and production continuity, and can avoid the problem of premature shutdown of temperature control heating device in short-term resumption of production, which causes secondary preheating energy consumption and delays in production rhythm.

[0039] (4) This invention can achieve refined energy consumption control of large, high-energy-consuming equipment such as extruders and calenders. Actual measurements show that it can reduce standby energy consumption by 15%-25%, while reducing start-up and production waiting time, improving equipment utilization, and bringing significant economic benefits to enterprises.

[0040] (5) If the equipment needs temporary maintenance after shutdown, the equipment must be stopped and the "stop, hang tag and lock" safety procedure must be followed. The emergency stop button is pressed and the emergency stop casing is locked and the maintenance stop button is hung. Even if the equipment is started according to the MES, the equipment cannot be started normally after the emergency stop button is pressed, ensuring the safety of maintenance personnel. Attached Figure Description

[0041] Figure 1 This is a flowchart of an intelligent energy consumption management and control method for equipment;

[0042] Figure 2 This is a schematic diagram of the intelligent energy consumption management system for equipment. Detailed Implementation

[0043] The present invention will be further described below with reference to the accompanying drawings and specific embodiments to aid in understanding its content. Unless otherwise specified, the methods used in this invention are conventional methods; the raw materials and apparatus used, unless otherwise specified, are conventional commercially available products.

[0044] like Figures 1-2 As shown, the present invention provides a method for intelligent management and control of equipment energy consumption, comprising the following steps:

[0045] S1. The APS system generates production scheduling data and automatically transmits the scheduling data to the corresponding equipment in the MES system for pre-storage. The scheduling data includes production information such as the production specifications, quantity, input and output of rubber materials, rubber material storage time, and processing time period of the equipment's daily and shift production plans.

[0046] Based on production scheduling data, the S2 and MES systems identify equipment information and time nodes to determine if there are any pending production tasks for the current equipment. If there are pending production tasks and the equipment is in a shutdown state, the system determines the planned production time and sends a pre-start command to the PLC control system, preheating the production equipment 1.5 hours before the production shift. If there are no pending production tasks, the equipment remains in standby monitoring mode, with the main equipment, temperature control heating devices, and energy-consuming equipment groups all disconnected from power. Only the PLC control system, status monitoring module, and communication module are powered. This maintains the communication channel between the MES system and the PLC control system, allowing the PLC control system to quickly respond to the pre-start command when the production schedule is updated and new production tasks are added. Furthermore, the status monitoring module continuously collects equipment safety interlock signals and sensor status, enabling timely fault alarms.

[0047] If temporary maintenance is required after shutdown, the equipment must be stopped and the "stop, tag, and lock" safety procedure must be followed. The emergency stop button must be pressed, the emergency stop casing must be locked, and the maintenance stop button must be hung. Even if the equipment is started according to the MES system, it cannot be started normally after the emergency stop button is pressed, ensuring the safety of maintenance personnel.

[0048] If the equipment is detected to be in a maintenance shutdown and locked state, the pre-start command is blocked, and the PLC control system directly controls the equipment to enter a shutdown state, preventing it from starting and avoiding safety accidents. The equipment maintenance shutdown and locked state is collected through the auxiliary contacts of the equipment's main power disconnect switch, and this switch signal is connected to the status monitoring module.

[0049] It should be noted that the equipment includes extruders, calenders, etc.

[0050] After receiving the pre-start command, the S3 and PLC control systems determine the preheating start time. Once the time is reached, the temperature control heating device is turned on, and the preheating process is started. The temperature sensor of the status monitoring module collects the equipment temperature in real time. When the temperature reaches the process set value and stabilizes, it switches to a low-power constant temperature standby state.

[0051] It should be noted that the temperature controller used by the temperature control heating device of the tire production equipment is set to PID constant temperature control mode by default at the factory. This mode is used to control the equipment temperature to maintain the set temperature and keep it in a constant temperature state.

[0052] Determining the preheating start time includes the following steps:

[0053] S31. The preheating time T is preset on the human-machine interface of the equipment. The preheating time T can be adjusted according to seasonal temperature difference, actual equipment usage requirements, product process, etc.

[0054] S32. Based on the production plan time issued by the MES system and the current equipment time read by the PLC system, subtract the preset preheating time T from the production plan time to obtain the equipment preheating start time.

[0055] Preheating is only started when the current time of the device read by the PLC system reaches the preheating start time, thus avoiding energy waste caused by starting the machine too early and heating up.

[0056] S4. After the status monitoring module detects the signal that the production personnel have arrived, the PLC control system starts the main unit of the control equipment and the group of power-consuming equipment, and enters the normal production process; if the personnel have not arrived, the equipment continues to maintain a constant temperature standby state.

[0057] The personnel arrival signal is collected by the workstation card swiping system or facial recognition system and fed back to the MES system through the status monitoring module. The MES system then transmits the arrival signal to the PLC control system, enabling personnel status to be associated with production tasks, machines, and shifts. This signal serves as one of the conditions for starting the main equipment, preventing the main equipment from starting without anyone present simply because the planned time has arrived. It also provides a data foundation for tracing production start time, personnel arrival time, and waiting time.

[0058] S5. After production is completed and the equipment is shut down, the MES system reads the estimated downtime of the equipment and the subsequent production schedule and transmits the data to the PLC control system. The PLC control system matches the corresponding graded delayed shutdown strategy according to the shutdown threshold, and shuts down the energy-consuming equipment group and temperature control heating device according to the time gradient, only retaining power supply to the basic monitoring and communication modules.

[0059] The MES system monitors the production schedule of the APS system and the actual production progress of the corresponding equipment in the MES system in real time. Based on the production schedule data and real-time production progress, it predicts the remaining time. The specific steps are as follows:

[0060] When only one production specification information remains for the current shift, the estimated remaining production time is calculated based on the remaining production quantity and the equipment's standard production cycle time. Combined with the current system time, the estimated downtime is determined. Then, the estimated total downtime is calculated by combining the production plan time of subsequent production scheduling data. This time data is synchronized to the PLC system as the basis for judging the graded delayed downtime strategy.

[0061] The MES system initiates prediction when only one production specification record remains for the current shift. This allows for the creation of a shutdown plan before production concludes, reserving calculation and communication time for subsequent tiered shutdowns. If prediction is initiated too early (calculating when only 3-5 records remain), numerous production variables, such as minor equipment malfunctions or delays in material supply from upstream processes, can interfere with the calculation of the estimated shutdown time, leading to inaccurate estimates. However, when only one record remains, it signifies that the current batch of production is nearing completion, all interfering factors are largely eliminated, and the remaining output is certain. The calculated remaining production time at this point is closest to reality, ensuring the reliability of the subsequent tiered shutdown strategy.

[0062] The estimated downtime and the production schedule of the next task together determine the total estimated downtime. Therefore, the system can distinguish between short downtime caused by switching specifications, medium downtime caused by waiting between shifts, and long downtime caused by no subsequent tasks, and select different energy consumption strategies accordingly.

[0063] The tiered delayed shutdown strategy is executed step-by-step according to time gradients, including:

[0064] If the downtime exceeds the first threshold, the energy-consuming equipment group will be shut down, but the temperature-controlled heating device will continue to operate.

[0065] If the downtime exceeds the second threshold, reduce the power of the temperature control heating device to maintain the heat preservation state;

[0066] If the downtime exceeds the third threshold, the main power supply of the temperature control heating device will be shut off, and only the power supply to the basic monitoring and communication modules will be maintained.

[0067] The above-mentioned tiered delayed shutdown strategy is executed sequentially according to time, rather than individually. For example, if the shutdown duration exceeds 3 hours (long shutdown), the energy-consuming equipment group is shut down when the shutdown duration exceeds the first threshold. When the shutdown duration exceeds the second threshold, the power of the temperature control heating device is reduced to maintain the heat preservation state. When the shutdown duration exceeds the third threshold, the main power supply of the temperature control heating device is shut down, and only the power supply to the basic monitoring and communication modules is retained.

[0068] Layered shutdown avoids the problem of slow temperature recovery during restarting due to a complete shutdown, and also avoids prolonged idle time caused by continuous heat preservation. All three levels are triggered by the same estimated total downtime.

[0069] Specifically, the first threshold is 25-40 minutes, preferably 30 minutes; the second threshold is 1-1.5 hours, preferably 1 hour; and the third threshold is 2-2.5 hours, preferably 2 hours.

[0070] Taking the extruder as an example, under normal production conditions, switching production specifications takes 10-15 minutes, mainly for changing the extrusion die plate and completing the finishing work of the previous specification material on the production line. Therefore, the first threshold is set to 30 minutes. If this time limit is not exceeded, the water tank water circulation filter, flue gas treatment equipment, and water blower will continue to operate to fully treat the residual waste gas on the production line. If this time limit is exceeded, the water blower, flue gas treatment equipment, and circulating cooling system and other energy-consuming equipment will be shut down. Even if the subsequent equipment (extruder) restarts production, it will not affect normal production.

[0071] The second threshold of 1 hour was determined by weighing the actual production conditions. In addition to short shutdowns of 10-15 minutes for specification changes during extrusion and calendering production, there are also medium-term shutdowns of 30-60 minutes, such as shift breaks, material shortages, delays in previous processes, and troubleshooting minor equipment malfunctions. Under these conditions, the equipment is highly likely to resume production within 1 hour. After the first threshold of 30 minutes, only auxiliary power-consuming equipment such as water blowers, flue gas treatment equipment, and circulating cooling systems are shut down. These auxiliary power-consuming devices have a fast start-up response and can be turned on immediately upon resumption of production without affecting production. If the shutdown time does not exceed 1 hour, the temperature-controlled heating device is allowed to output full power to cope with sudden fluctuations in equipment heat dissipation and ensure rapid resumption of production. When the shutdown time exceeds 1 hour, the probability of resuming production in a short time is considered low, and the temperature-controlled heating device switches to a low-power constant temperature insulation mode. This mode still uses a PID closed-loop to stably lock the temperature at the process set value, and the equipment can be directly put into production, but the maximum output power of the heating unit is limited to reduce standby power consumption while meeting the temperature process requirements. If the downtime exceeds the third threshold by 2 hours, the main power supply to the temperature control heating device should be cut off. If the power supply to the temperature control station is cut off too early, it will take longer to reheat the equipment once production needs to resume, which will seriously delay the production schedule.

[0072] The aforementioned intelligent energy management and control methods create a complete closed loop encompassing production scheduling, preheating, personnel arrival, normal production, and shutdown for energy conservation. The APS system provides future production plan data, the MES system handles production plan judgment and progress aggregation, the PLC control system executes real-time control, and the status monitoring module provides feedback on temperature, equipment status, and personnel status, thus avoiding control gaps caused by relying solely on timers or manual operation. Furthermore, preheating and production start-up are separated into two states: first, the temperature-controlled heating device is activated to reach the process conditions before entering a low-power waiting state; then, the main equipment and auxiliary energy-consuming equipment are started after personnel arrive. This separation ensures that the equipment reaches the predetermined process temperature at planned start-up without automatically starting production without personnel. After production ends, shutdown is gradually implemented according to time gradients, balancing rapid recovery from short shutdowns with deep energy savings during long shutdowns, resulting in excellent energy-saving performance.

[0073] It should be noted that the temperature-controlled heating device includes a heating execution unit and a temperature control unit. The heating execution unit (such as an electric heating element or heating plate) is responsible for converting electrical energy into heat energy, while the temperature control unit (such as a PLC, temperature control module, and thyristor) precisely adjusts the power. Under the unified scheduling of the MES / PLC system, the device can dynamically execute preheating, low-power constant temperature, and graded delayed shutdown strategies according to the production plan, thereby further reducing energy consumption while ensuring stable process temperature.

[0074] The present invention also provides an intelligent energy consumption management system for equipment, comprising:

[0075] The APS system is used to generate production scheduling data and automatically transmits the scheduling data to the MES system in real time.

[0076] The MES system is used to receive and store production scheduling data issued by the APS system, record the actual production progress and downtime of the equipment, and communicate bidirectionally with the PLC system.

[0077] The PLC control system receives pre-start instructions from the MES system and controls the start and stop of the main equipment, temperature control heating device, and energy-consuming equipment group.

[0078] The status monitoring module is used to monitor equipment temperature, personnel presence, equipment operating status, and equipment safety interlock signals in real time. Specifically, equipment temperature is monitored by temperature sensors; personnel presence is monitored by workstation card readers (IC cards) or facial recognition terminals; equipment operating status is monitored by auxiliary feedback contacts of each power contactor; and equipment safety interlock signals are monitored by passive auxiliary contacts of the main power disconnect switch. The raw signals from these sources are sent to the status monitoring module for signal conversion and filtering before being transmitted to the PLC control system and the MES system, respectively, providing status data for intelligent energy consumption management.

[0079] The PLC control system has a built-in execution control module, which executes the following control logic:

[0080] Before production personnel arrive, the temperature control heating device is controlled to turn on the power supply system in advance and preheat according to the pre-start command issued by the MES system until the equipment temperature reaches the process set value.

[0081] Upon receiving a shutdown command, the system receives the estimated shutdown duration data from the MES system, matches the corresponding tiered delayed shutdown strategy based on the shutdown threshold, and gradually shuts down the energy-consuming equipment group and temperature control heating device to reduce energy consumption.

[0082] Specifically, the energy-consuming equipment group includes flue gas treatment equipment, water blower, and circulating cooling system.

[0083] Furthermore, each piece of equipment, energy-consuming equipment group, and temperature control heating device has an independent control system. Its operating status, start / stop signals, and heartbeat signals interact with the PLC control systems of extrusion lines, calendering lines, etc. Data interaction includes Ethernet communication, point-to-point communication, OPC communication, etc.

[0084] Example 1:

[0085] This embodiment applies to extrusion equipment in a tire factory. The equipment is equipped with a temperature control heating device, flue gas treatment equipment, water blower, and circulating cooling system. The temperature of each zone of the barrel is set to 70℃-90℃, with one zone's barrel temperature specifically set to 85℃. The machine's human-machine interface has a preset preheating time of 1.5 hours; the tiered shutdown thresholds are set as follows: the first threshold is 30 minutes, the second threshold is 1 hour, and the third threshold is 2 hours.

[0086] The APS system generates production scheduling data for the extruder, including production specifications, rubber compound type, production quantity, and processing time period. This data is automatically distributed to the corresponding machine module in the MES system via the enterprise intranet. The MES system then updates the production task status of this equipment in real time.

[0087] The MES system detected that the extruder was scheduled to start production at 8:00 AM, 2 hours later. The equipment was currently in a stopped and non-operating state, and there was no maintenance tag or lock signal. The system then sent a pre-start command to the PLC control system.

[0088] The PLC control system uses the planned production time of 8:00 as the endpoint, subtracts the preset 1.5-hour preheating time, and calculates the preheating start time to be 6:30. After 6:30, the PLC control system activates the temperature-controlled heating device, initiating the preheating process. The temperature sensor in the status monitoring module collects the barrel temperature in real time. Once the temperature in the corresponding area of ​​the barrel reaches 85℃ and stabilizes for 5 minutes, it switches to low-power constant-temperature standby. If the temperature does not reach 85℃, the PLC control system controls the temperature-controlled heating device to continue heating.

[0089] At 8:05, production personnel confirm their arrival at their workstations via the workstation card swiping system. The status monitoring module sends the personnel arrival signal back to the MES system, which then transmits the signal to the PLC control system. The PLC starts the extruder main unit, flue gas treatment equipment, water blower, and circulating cooling system, and controls the extruder to start feeding, screw, and other components, allowing the equipment to enter the normal production process.

[0090] The MES system continuously reads the production progress. When it detects that there is only one production specification information remaining for the current shift, for example, if the remaining production specification information is an extrusion material output of 150kg and the standard production cycle of the extruder is 200kg / h, the estimated remaining production time is 45 minutes. Based on the current time of 10:15, the estimated downtime is 11:00. The MES system then queries the subsequent production schedule of the current extruder. The next production task is at 13:30 in the afternoon. The system calculates the estimated total downtime to be 2 hours and 30 minutes and synchronizes this time to the PLC control system.

[0091] After production is completed and the equipment is shut down, the PLC control system determines that the downtime of 2 hours and 30 minutes exceeds the third threshold (2 hours). According to the graded delayed shutdown strategy, the energy-consuming equipment group and temperature control heating device are shut down in a time gradient: after 30 minutes of downtime, the flue gas treatment equipment, water blower, and circulating cooling system are shut down first; after 1 hour of downtime, the temperature control heating device reduces power and enters heat preservation mode; after 2 hours of downtime, the main power supply of the temperature control heating device is cut off, and only the basic monitoring and communication modules are powered, and the equipment enters energy-saving standby mode.

[0092] If the downtime is 45 minutes, which is greater than the first threshold of 30 minutes but less than the second threshold of 1 hour, the PLC executes a tiered strategy: after reaching the first threshold of 30 minutes, the flue gas treatment equipment, water blower, and circulating cooling system are shut down; since the second threshold of 1 hour has not been reached, the temperature-controlled heating device does not reduce power or cut off the main power supply, and continues to maintain the roller insulation state. After 45 minutes, when the next production cycle begins, the PLC can directly start production based on the personnel arrival signal without needing to reheat. This approach achieves energy saving by shutting down high-power auxiliary equipment while maintaining temperature control and insulation, avoiding the time and additional heating energy consumption caused by a complete power outage after a short-interval downtime, thus balancing energy saving and production efficiency.

[0093] The entire process requires no personnel to arrive in advance for preheating or to shut down the energy-consuming equipment and temperature control heating devices after production is completed. According to statistics, the preheating energy consumption of the extruder for a single production run has been reduced from 120kWh to 80kWh, and the energy consumption for a single 8-hour shutdown has been reduced from 60kWh to 15kWh. The average monthly energy consumption of a single machine has been reduced by about 18%, demonstrating significant energy-saving effects.

[0094] Compared with the prior art, the present invention has the following beneficial effects.

[0095] (1) By linking APS, MES and PLC systems, the preheating start time is automatically calculated according to the production schedule, so as to achieve precise equipment preheating and realize "the temperature arrives when people arrive". This avoids the waste of human resources caused by production personnel arriving early, reduces the resistance of production personnel, and prevents the power loss caused by excessive preheating time, thus ensuring the quality of product production process.

[0096] (2) Set up a graded delayed shutdown strategy, and shut down the energy-consuming equipment group and temperature control heating device according to the expected shutdown duration, while only keeping the basic monitoring and communication modules powered, to solve the standby energy consumption problem caused by forgetting to shut down the high-power auxiliary equipment after production, and effectively reduce the power consumption of the equipment in non-production state;

[0097] (3) The total estimated downtime calculated by the MES system is used as the basis for judging the graded delayed downtime strategy. On the one hand, there is no need for manual filling and estimation of downtime, eliminating errors and omissions caused by manual operation; on the other hand, it can distinguish between different working conditions such as short-term specification change, short-intermittent downtime and long-term shutdown, so that the graded downtime strategy fits the actual production interval on site, takes into account both energy saving effect and production continuity, and can avoid the problem of premature shutdown of temperature control heating device in short-term resumption of production, which causes secondary preheating energy consumption and delays in production rhythm.

[0098] (4) It can realize refined energy consumption control of large high-energy-consuming equipment such as extruders and calenders. Actual measurements show that it can reduce the standby energy consumption of equipment by 15%-25%, while reducing the waiting time for start-up and production, improving the effective utilization rate of equipment, and bringing significant economic benefits to enterprises.

[0099] This invention aims to solve the problem of inefficient energy management of large equipment such as extruders and calenders in the tire industry, by achieving preheating control of equipment energy consumption and delayed shutdown of energy-consuming equipment to save electricity. When the equipment is in a ready-to-produce state, the temperature-controlled heating device is started in advance using production scheduling data to preheat, ensuring production can begin as soon as personnel are in place. When the equipment is shut down, based on the actual downtime recorded by the MES system, high-power equipment such as large temperature-controlled heating devices, flue gas treatment equipment, water blowers, and circulating cooling systems are automatically shut down in stages. This invention effectively reduces the ineffective energy consumption of large heating equipment, significantly lowers enterprise production costs, and is particularly suitable for the management of large energy-consuming equipment in the extrusion and calendering processes of the tire manufacturing industry.

[0100] In the description of this invention, it should be understood that the terms "left", "right", "up", "down", "top", "bottom", "front", "back", "inner", "outer", "back", "middle", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.

[0101] However, the above description is merely a specific embodiment of the present invention and should not be construed as limiting the scope of the present invention. Therefore, any substitution of equivalent components or equivalent changes and modifications made in accordance with the scope of protection of the present invention should still fall within the scope of the claims of the present invention.

Claims

1. A method for intelligent management and control of equipment energy consumption, characterized in that, Includes the following steps: S1 and APS systems generate production scheduling data and automatically transmit the production scheduling data to the MES system; Based on production scheduling data, the S2 and MES systems determine whether there are any production tasks waiting to be completed on the current equipment. If there are any production tasks waiting to be completed and the equipment is in a shutdown state, the system determines the production plan time and sends a pre-start command to the PLC control system. If there are no production tasks waiting to be completed, the equipment remains in a standby monitoring state. After receiving the pre-start command, the S3 and PLC control systems determine the preheating start time and start the preheating process after the time is reached. The status monitoring module collects the equipment temperature in real time. When the temperature reaches the process set value and stabilizes, it switches to low-power constant temperature standby mode. S4. After the status monitoring module detects the signal that the production personnel have arrived, the PLC control system starts the main control equipment and the group of power-consuming equipment, and enters the normal production process. S5. After production is completed and the equipment is shut down, the MES system reads the estimated downtime of the equipment and the subsequent production schedule and transmits the data to the PLC control system. The PLC control system matches the corresponding graded delayed shutdown strategy according to the shutdown threshold, and shuts down the energy-consuming equipment group and temperature control heating device according to the time gradient, only retaining power supply to the basic monitoring and communication modules.

2. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, In step S1, the production scheduling data includes the production specifications, quantity, input and output of rubber materials, rubber material storage time, and processing time period of the equipment and machines on a daily and shift basis.

3. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, Step S3, determining the preheating start time, includes the following steps: S31. The preheating time is preset on the human-machine interface of the equipment. S32. Based on the production plan time issued by the MES system and the current equipment time read by the PLC system, subtract the preset preheating time from the production plan time to obtain the equipment preheating start time.

4. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, In step S5, the MES system needs to predict the remaining time based on production scheduling data and real-time production progress: when it detects that there is only 1 production specification information left for the shift, the estimated remaining production time is calculated based on the remaining production quantity and the standard production cycle of the equipment. Combined with the current system time, the estimated downtime is obtained. Then, combined with the production plan time of subsequent production scheduling data, the estimated total downtime is calculated, and this time data is synchronized to the PLC system as the basis for judging the graded delayed downtime strategy.

5. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, In step S5, the tiered delayed shutdown strategy is executed step by step according to the time gradient, including: If the downtime exceeds the first threshold, the energy-consuming equipment group will be shut down, but the temperature-controlled heating device will continue to operate. If the downtime exceeds the second threshold, reduce the power of the temperature control heating device to maintain the heat preservation state; If the downtime exceeds the third threshold, the main power supply of the temperature control heating device will be shut off, and only the power supply to the basic monitoring and communication modules will be maintained.

6. The intelligent energy consumption management and control method for equipment according to claim 5, characterized in that, The first threshold is 25-40 minutes, the second threshold is 1-1.5 hours, and the third threshold is 2-2.5 hours.

7. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, In step S4, the signal of production personnel arriving is collected by the workstation card swiping system or facial recognition system and then fed back to the MES system through the status monitoring module; the MES system then transmits the arrival signal to the PLC control system.

8. The intelligent energy consumption management and control method for equipment according to claim 1, characterized in that, In step S2, if the equipment is detected to be in a maintenance-tagged and locked state, the pre-start command is blocked and the equipment enters a shutdown state.

9. A device energy consumption intelligent management system applying the method of any one of claims 1-8, characterized in that, include: The APS system automatically transmits production scheduling data to the MES system; The MES system is used to pre-store production scheduling data, record the actual production progress and downtime of equipment, and communicate bidirectionally with the PLC system. The PLC control system receives pre-start instructions from the MES system and controls the start and stop of the main equipment, temperature control heating device, and energy-consuming equipment group. The status monitoring module is used to monitor equipment temperature, whether production personnel are in place, equipment operating status, and equipment safety interlock signals in real time. The PLC control system has a built-in execution control module, which executes the following control logic: Before the production personnel arrive, the temperature control heating device is controlled to turn on the power supply system in advance and preheat according to the pre-start command issued by the MES system until the equipment temperature reaches the process set value. Upon receiving a shutdown command, the system receives the estimated shutdown duration data from the MES system, matches the corresponding tiered delayed shutdown strategy based on the shutdown threshold, and gradually shuts down the energy-consuming equipment group and temperature-controlled heating device.

10. The intelligent energy consumption management system for equipment according to claim 9, characterized in that, The energy-consuming equipment group includes flue gas treatment equipment, water blowing fan, and circulating cooling system.