Compressed gas energy storage power station salt cavern gas injection and brine discharge schedule control system
The salt cavern gas injection and brine drainage schedule control system enables dynamic, precise, and closed-loop management of salt cavern gas injection and brine drainage construction, solving the problems of insufficient precision and data silos in the existing technology, and improving construction efficiency and safety.
Patent Information
- Application Number
- CN202611170835.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-04
- Publication Date
- 2026-11-10
AI Technical Summary
The existing construction schedule management for salt cavern gas injection and brine drainage projects suffers from problems such as insufficient forecast accuracy, lack of data support for adjustment decisions, data silos from multiple sources, and a lack of closed-loop management, leading to construction delays and safety risks.
Develop a brine injection and desalination schedule control system for compressed air energy storage power stations. Through real-time acquisition of multi-source data, dynamic analysis of a dedicated schedule model, intelligent hierarchical early warning, and visual interaction, the system achieves dynamic, precise, and closed-loop management of the schedule, including modules for data acquisition, progress analysis, early warning and adjustment, visualization, and control execution.
Significantly improve the accuracy and speed of project schedule management, reduce the risk of construction delays, improve construction efficiency and resource utilization efficiency, ensure that adjustment measures are traceable, verifiable and accountable, and guarantee construction safety.
Smart Images

Figure CN123070545A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of compressed air energy storage power station construction management technology, and in particular to an intelligent control system and control method for the construction period of salt cavern storage gas injection and brine discharge, which belongs to the cross-technical field of energy storage engineering, salt cavern underground storage construction and intelligent construction. Background Technology
[0002] Compressed air energy storage (CAES) is one of the core technologies for large-scale, long-term energy storage, boasting significant advantages such as large capacity, long lifespan, low cost, and environmental friendliness. It is crucial equipment for supporting the construction of new power systems and enhancing the absorption capacity of new energy sources. Salt cavern underground storage, with its excellent sealing, large storage capacity, and safe and stable operation, has become the preferred gas storage carrier for CAES power plants. The core construction process of salt cavern gas storage is the gas injection and brine discharge process. Compressed air is continuously injected into the water-soluble, molded salt cavern cavity, and the brine inside is gradually discharged using gas pressure. Simultaneously, the surrounding salt rock undergoes creep deformation under the gas pressure, gradually expanding the cavity volume until it reaches the designed volume and stable shape. This process is characterized by a long construction period, numerous influencing factors, strong geological uncertainties, and irreversible processes. The accuracy of schedule management directly determines the project's commissioning time and overall economic benefits. Currently, the schedule management of salt cavern gas injection and brine discharge construction mainly relies on traditional project management models, which have the following significant defects and shortcomings: Insufficient accuracy in project schedule forecasting and poor adaptability of static plans mean that when unexpected situations such as changes in geological conditions or equipment failures occur, schedule deviations cannot be identified in a timely manner, and small delays often evolve into systemic delays, missing the best opportunity to correct course. Adjustment decisions rely on experience and lack data support; because it is impossible to accurately quantify the impact of different factors on the project schedule, it is also difficult to predict the actual effect of adjustment measures, resulting in insufficient effectiveness of the corrective plan, or even over-adjustment leading to safety risks or cost overruns. The silos of multi-source data make systematic analysis difficult. The construction of salt cavern gas injection and brine drainage involves multi-dimensional data such as progress, geology, equipment, and environment, which belong to different systems such as construction management, geological monitoring, equipment operation and maintenance, and meteorology. The data standards are not unified and the interfaces are not interoperable, making it impossible to achieve integrated analysis. When the construction period is delayed, it is difficult to quickly locate the root cause, and the investigation process consumes a lot of manpower and time. The lack of a closed-loop management system leads to uncontrollable execution results. In the existing model, adjustment instructions are mainly issued manually through meetings, work orders, etc., and the execution process lacks real-time tracking, with the execution results relying on manual verification afterward.
[0003] Therefore, developing a dedicated intelligent control system and corresponding control methods for the construction of compressed air energy storage power stations with salt cavern gas injection and brine discharge, and achieving dynamic, precise, and closed-loop management of the construction period, is a technical problem that urgently needs to be solved in the industry. Summary of the Invention
[0004] To address the aforementioned shortcomings of existing salt cavern gas injection and brine drainage construction period management technologies, the present invention aims to provide a control system and method for salt cavern gas injection and brine drainage construction period management in compressed air energy storage power stations. This system comprehensively improves the accuracy, response speed, and scientific nature of construction period management through real-time acquisition of multi-source data, dynamic analysis using a dedicated construction period model, intelligent hierarchical early warning, quantitative adjustment scheme generation, visual interaction, and closed-loop execution control. This effectively reduces the risk of construction delays, improves construction efficiency and resource utilization efficiency, and achieves intelligent and refined management of the salt cavern gas injection and brine drainage construction period.
[0005] To achieve the above objectives, the present invention provides a control system for the construction period of a compressed air energy storage power station with salt cavern gas injection and brine discharge, including a data acquisition module, a progress analysis module, an early warning and adjustment module, a visualization display module, and a control execution module. The data acquisition module includes a construction progress data acquisition unit, a geological parameter acquisition unit, an equipment operation status acquisition unit, an environmental monitoring data acquisition unit, and a data preprocessing and transmission unit, which is used to collect construction progress data, geological parameters, equipment operation status data, and environmental monitoring data in real time during the salt cavern gas injection and brine discharge construction process, and transmit the raw data after preprocessing. The progress analysis module includes a schedule model library unit, a dynamic progress calculation unit, a deviation source analysis unit, and a remaining schedule prediction unit. It has a built-in salt cavern gas injection and brine discharge schedule model library. Based on the collected real-time data and the preset schedule benchmark model, it dynamically calculates the deviation between the actual progress and the planned progress, traces the cause of the deviation, and predicts the remaining schedule. The early warning and adjustment module includes a graded early warning unit, an adjustment scheme generation unit, and a scheme simulation verification unit. It can trigger graded early warnings based on the level of progress deviation, automatically generate multiple schedule adjustment schemes based on the causes of deviations, and perform simulation verification and effect prediction on the schemes. The visualization module includes an overview dashboard, a progress details unit, a monitoring data unit, a 3D visualization unit, and a multi-terminal adaptation unit. It displays the total project schedule, process details, monitoring data trends, early warning information, and adjustment plans through a graphical interface, and supports access from multiple terminals. The control execution module includes a manual confirmation execution unit, an automatic control execution unit, a system docking unit, and an execution effect evaluation unit. It supports manual confirmation or automatic issuance of schedule adjustment instructions to on-site construction equipment and management system, tracks the execution process, and verifies the adjustment effect to form a closed-loop control system.
[0006] Furthermore, the construction progress data acquisition unit of the data acquisition module is used to collect data on gas injection pressure and flow rate, brine discharge flow rate and cumulative amount, process node status, and salt cavern morphology; the geological parameter acquisition unit is used to collect data on salt rock surrounding stress and strain, brine concentration and temperature, and formation pore pressure and permeability; the equipment operation status acquisition unit is used to collect operating parameters, fault codes, and load status of the gas injection compressor, brine discharge pump, valve pipelines, and auxiliary equipment; the environmental monitoring data acquisition unit is used to collect wellhead environmental parameters and regional meteorological data; and the data preprocessing and transmission unit is used to clean, denoise, and normalize the raw data, and upload it to the server through an encrypted network.
[0007] Furthermore, the schedule analysis module's schedule model library unit stores multiple benchmark schedule models categorized by salt rock geological type, cavity size, and design parameters. These models are generated through machine learning training based on historical engineering data. The dynamic schedule calculation unit uses a combination of earned value method and critical path method to calculate cumulative completion rate, process schedule deviation, and total schedule deviation, and dynamically corrects the schedule benchmark based on real-time geological parameters. The deviation source analysis unit quantifies and identifies the contribution of geological factors, equipment factors, resource factors, and environmental factors to schedule deviation through multi-parameter correlation analysis. The remaining schedule prediction unit uses a long short-term memory network model to output remaining schedule prediction results under multiple scenarios based on the current schedule, corrected geological parameters, and equipment status.
[0008] Furthermore, the early warning and adjustment module's hierarchical early warning unit presets four levels of deviation thresholds, with different levels of early warning matching different push targets and handling procedures; the adjustment scheme generation unit generates three types of adjustment strategies—process optimization, resource enhancement, and process adjustment—based on the causes and levels of deviation, and outputs multiple alternative schemes and corresponding time gain, cost increment, and risk level indicators; the scheme simulation verification unit uses a progress simulation model to deduce the progress trend after the scheme is implemented, verifies the time correction effect, and outputs a simulation prediction curve.
[0009] Furthermore, the overview dashboard unit of the visualization module displays the overall project schedule, the completion status of key nodes, current early warning statistics, and the predicted remaining project time; the progress details unit provides dynamic Gantt charts and progress trend curves, supporting comparison between drilling operations and actual plans; the monitoring data unit categorizes and displays real-time values and historical trends of geological, equipment, and environmental parameters, supporting multi-parameter comparison on the same screen; the 3D visualization unit, combined with a 3D model of the salt cavern, intuitively displays the cavern expansion progress and spatial morphology; and the multi-terminal adaptation unit supports differentiated display and interaction across Web dashboards, PC management terminals, and mobile apps.
[0010] Furthermore, the manual confirmation execution unit of the control execution module supports administrators in reviewing adjustment plans, issuing execution work orders, tracking execution status, and accepting execution results; the automatic control execution unit automatically issues parameter adjustment instructions to the field control system after passing safety verification for preset minor deviation scenarios; the system interface unit supports data exchange and instruction linkage with field PLCs, SCADA systems, equipment management systems, and enterprise ERP systems; and the execution effect evaluation unit continuously collects adjusted progress data, evaluates the correction effect, and feeds the effect data back to the schedule model library for model iteration.
[0011] Furthermore, the morphological data of the salt cavern cavity in the construction progress data acquisition unit is collected periodically by the downhole sonar cavity measurement system. The data is automatically synchronized to the system and used to update the cavity volume and the total amount of brine discharged.
[0012] Furthermore, the benchmark models in the construction period model library are divided into layered salt rock models and salt dome models according to the salt cave type. Each type of model includes the construction period benchmark and weight allocation for four process stages: pretreatment, gas injection and brine discharge, pressure stabilization and molding, and acceptance.
[0013] Furthermore, the process adjustment strategy includes step optimization of gas injection pressure, dynamic adjustment of brine discharge flow rate, and adjustment of pressure stabilization cycle. All adjustment parameters are preset with safety thresholds, and schemes that exceed the thresholds are automatically marked as high-risk and prompted for manual review.
[0014] Furthermore, the triggering conditions for the automatic control execution unit are: the deviation rate of non-critical processes is less than 5%, the equipment is operating normally, the adjustment parameters are within the safety threshold range, and if the progress does not recover to the planned range within 15 minutes after the adjustment is executed, it will automatically upgrade to manual intervention mode.
[0015] A method for controlling the construction period of salt cavern gas injection and brine discharge in a compressed air energy storage power station is implemented based on a control system for the construction period of salt cavern gas injection and brine discharge in a compressed air energy storage power station. The control method specifically includes the following steps: Step 1: System initialization and baseline schedule model construction, input basic project parameters, match the baseline model to generate an initial schedule plan, and configure control rules; Step 2: Real-time acquisition and preprocessing of multi-source construction data, simultaneously acquiring four types of data: progress, geology, equipment, and environment, which are then reliably transmitted after edge cleaning and normalization; Step 3: Dynamic progress calculation and deviation identification, combining real-time data to calculate progress indicators, dynamically adjust the schedule baseline, and determine the deviation level and scope of impact; Step 4: Tracing the causes of deviations and predicting the remaining construction period, quantifying the contribution of each factor to locate the main cause, correcting model parameters and outputting multi-scenario construction period prediction results; Step 5: Generate graded early warning and correction schemes. Trigger corresponding early warnings according to the deviation level, match the strategy library to generate multiple alternative correction schemes and output evaluation indicators; Step Six: Simulation Verification and Execution Command Issuance. The scheme's corrective effect is verified through simulation. After confirmation, an execution work order or automatic control command is issued. Step 7: Execution effect evaluation and model iteration optimization. Track the execution process, quantitatively evaluate the effect of corrective measures, and use feedback data to iteratively optimize the project schedule model to form a closed-loop management system.
[0016] The present invention has the following beneficial effects: 1. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system proposed in this invention has a built-in dedicated schedule model for salt cavern gas injection and brine discharge, and can be dynamically corrected by combining real-time geological data. It replaces the traditional static plan, greatly improves the accuracy of schedule control, and the system collects and analyzes progress data in real time 24 hours a day. When deviation occurs, it triggers an early warning. Compared with the traditional manual weekly inventory, the deviation detection time is greatly advanced. Managers can intervene in time at the beginning of the deviation, avoid small delays from becoming large delays, and effectively reduce the risk of schedule delays.
[0017] 2. The compressed air storage power station salt cavern gas injection and brine discharge schedule control system proposed in this invention provides managers with quantitative decision-making basis through data-driven deviation tracing and multi-scheme generation simulation, replacing traditional experience-based decision-making. The system integrates multi-source data from progress, geology, equipment, and environment to achieve integrated acquisition, storage, and analysis, constructing a complete control closed loop. The system realizes closed-loop control of the entire process from data acquisition, analysis and decision-making, instruction issuance to execution feedback and model optimization, ensuring that every adjustment measure is traceable, verifiable, and accountable. At the same time, the execution effect feeds back into model optimization. As project data accumulates, the system's control accuracy continuously improves, forming a virtuous cycle.
[0018] 3. The compressed gas energy storage power station salt cavern gas injection and brine discharge schedule control system proposed in this invention features an intuitive visual interface and multi-terminal support, allowing managers at all levels to quickly grasp the project status and significantly reducing information synchronization costs. It significantly improves cross-position and cross-departmental collaboration efficiency, greatly shortens the decision-making cycle, and all process adjustment schemes have built-in safety threshold verification. The automatic control mode has multiple safety protections, ensuring both efficient schedule management and strict safety during salt cavern construction, preventing safety accidents caused by rushing the schedule. Attached Figure Description
[0019] Figure 1 This is a system architecture diagram of the compressed air energy storage power station salt cavern gas injection and brine discharge period control system proposed in this invention; Figure 2 This is a flowchart illustrating the working steps of the compressed air energy storage power station salt cavern gas injection and brine discharge period control system proposed in this invention. Detailed Implementation
[0020] The technical solutions of the specific embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described specific embodiments are only a part of the specific embodiments of the present invention, and not all of them. Based on the specific embodiments of the present invention, all other specific embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention. Example
[0021] Reference Figure 1-2 The present invention provides a specific implementation method: A compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system. The system adopts a layered architecture design, which is divided into an application interaction layer, a platform service layer, an edge computing layer and a field perception layer from top to bottom. The core consists of five major functional modules: data acquisition module, progress analysis module, early warning and adjustment module, visualization display module and control execution module. The data acquisition module corresponds to the field perception layer and the edge computing layer, and is the data foundation of the entire system. It is responsible for comprehensively collecting all dimensions of data related to the salt cavern aeration and brine drainage construction, and for completing preprocessing and reliable transmission. This module is further divided into five functional units: Construction progress data acquisition unit: This unit comprises four sub-units. The gas injection parameter acquisition sub-unit collects real-time data on gas injection pressure, instantaneous flow rate, and cumulative gas injection volume using a high-precision pressure transmitter and vortex flow meter at the compressor outlet, with a acquisition frequency of no less than once per second. The brine discharge parameter acquisition sub-unit collects data on instantaneous brine discharge flow rate, cumulative brine discharge volume, and wellhead brine level using an electromagnetic flow meter and radar level gauge on the brine discharge main pipeline, with a acquisition frequency of once every 5 seconds. The process node acquisition sub-unit automatically identifies the start and end times and node completion status of each process through on-site equipment start / stop signals, reports from construction personnel's mobile terminals, and access control system linkage. The cavity morphology monitoring sub-unit connects to the downhole sonar cavity measurement system to periodically collect three-dimensional morphological data of the salt cavern cavity, automatically calculates the actual cavity volume, and is used to calibrate the total brine discharge volume and expansion progress. Geological Parameter Acquisition Unit: This unit monitors key geological factors affecting the project schedule in real time. The salt rock creep monitoring subunit uses fiber optic strain sensors and stress sensors embedded at different depths in the surrounding rock of the cavity to collect stress and strain data in real time, monitoring the salt rock creep rate at a frequency of once per minute. The brine parameter monitoring subunit uses online concentration meters and platinum resistance temperature sensors installed in the brine discharge pipeline to collect brine concentration, temperature, and density parameters for analyzing salt dissolution rate and brine discharge efficiency. The formation parameter subunit uses downhole permanent monitoring instruments to collect formation pore pressure and permeability data to assess gas leakage risk and changes in brine discharge resistance. Equipment Operation Status Acquisition Unit: Comprehensive coverage of the operational status of core construction equipment. The gas injection equipment monitoring subunit interfaces with the compressor PLC control system to collect parameters such as compressor operating power, speed, oil temperature, vibration level, outlet pressure, and fault codes, enabling real-time assessment of equipment health and output capacity. The brine discharge equipment monitoring subunit interfaces with the brine discharge pump control cabinet to collect pump unit operating current, head, efficiency, start / stop status, and inverter frequency. The valve and pipeline monitoring subunit collects the opening status of each process valve, pressure at each pipeline node, and leakage monitoring data. The auxiliary equipment monitoring subunit collects the operational status of the cooling system, power supply system, and instrument ventilation system to ensure stable operation of the main equipment. Environmental monitoring data acquisition unit: Collects environmental and meteorological data that affect construction efficiency. The wellhead environmental monitoring subunit collects temperature, humidity, and wind speed parameters in the wellhead area through the wellhead meteorological station; the meteorological data subunit connects to a third-party meteorological service platform via API to obtain information such as rainfall and extreme weather warnings in the construction area, used to predict the impact of environmental factors on the construction period. Data preprocessing and transmission unit: Deployed at the field edge gateway, it cleans, denoises, removes outliers, aligns and normalizes the raw data collected by various sensors, and filters invalid data to reduce transmission and storage pressure; the data is transmitted to the cloud server in encrypted form via 5G wireless or industrial wired network, supporting breakpoint resume and data caching to ensure that data is not lost when the network is interrupted; Progress Analysis Module: The progress analysis module is deployed in the platform service layer and is the core computing unit of the system. It has a built-in special schedule model for salt cavern aeration and brine discharge, and realizes the functions of progress calculation, deviation analysis, cause tracing and schedule prediction. The project duration model library unit stores multiple trained benchmark project duration models for salt cavern gas injection and brine drainage. These models are categorized by salt rock geological type into layered salt rock models and salt dome models. Each model is further subdivided according to cavity volume level and design gas injection pressure. Based on historical construction data from dozens of domestic salt cavern storage projects, the models are generated using a BP neural network algorithm. After inputting geological exploration parameters, design parameters, and resource allocation parameters, the model automatically outputs a benchmark project duration plan including four stages: pretreatment, main gas injection and brine drainage, pressure stabilization and molding, and acceptance. The plan specifies the start and end times, critical path, resource allocation baseline, and milestone nodes for each process. The model supports custom modifications, allowing adjustment of process weights and project duration baselines according to project characteristics. Dynamic progress calculation unit: Receives construction data uploaded by the data acquisition module in real time and performs progress accounting using a combination of earned value method and critical path method. Core calculation indicators include: cumulative completion rate, with the ratio of actual cumulative brine discharge to the designed total brine discharge as the core indicator, calibrated in conjunction with the measured volume of the cavity; Schedule Deviation (SV) = Budgeted cost of completed work - Budgeted cost of planned work; Project duration deviation (TV) = Actual time taken on the critical path - Planned time taken on the critical path; During the calculation process, the system will dynamically adjust the schedule benchmark for subsequent processes based on real-time collected geological parameters such as salt rock creep rate and brine concentration, replacing the traditional static plan and realizing dynamic adaptation of the schedule benchmark to geological conditions. Deviation Source Analysis Unit: When a schedule deviation is detected to exceed a preset threshold, deviation source analysis is automatically initiated. The system uses Pearson correlation analysis and grey relational analysis algorithms to calculate the correlation between four types of parameters: geology, equipment, resources, and environment. This quantifies the contribution of each factor to the deviation and accurately identifies the main cause. For example, when the salt rock creep rate is lower than the exploration value, the system automatically identifies geological factors as the main cause and quantifies its proportion of impact on the schedule delay; when equipment failure leads to downtime, the system automatically identifies equipment factors and calculates the corresponding schedule loss for the downtime. Remaining Construction Period Prediction Unit: Based on the current actual progress, corrected geological parameters, equipment health status, and resource allocation, a Long Short-Term Memory (LSTM) time series prediction model is used to predict the remaining construction period. The model outputs prediction results under three scenarios: optimistic, neutral, and pessimistic, corresponding to the optimal, normal, and unfavorable working conditions, respectively, providing managers with multi-dimensional decision-making references. The prediction model automatically iterates every 24 hours, incorporating the latest construction data to continuously improve prediction accuracy. Early warning and adjustment module: The early warning and adjustment module is the core of the system's decision-making. Based on the progress analysis results, it realizes hierarchical early warning and intelligent solution generation, assisting managers to quickly and scientifically carry out schedule correction. Tiered early warning unit: Preset four levels of progress deviation thresholds, corresponding to a four-level early warning mechanism; Blue alert (minor deviation): The overall schedule deviation rate is less than 5%, or the delay of non-critical processes does not affect the overall schedule. The alert will be sent to the on-site construction manager. Yellow alert (general deviation): Total schedule deviation rate of 5%-10%, or slight delay in key processes, will be sent to the construction supervisor and progress engineer. Orange alert (significant deviation): Total schedule deviation rate is 10%-20%, key processes are significantly delayed, and this alert is sent to the project manager and technical lead. Red Alert (Serious Deviation): Total schedule deviation rate >20%, indicating a significant risk of delay, and should be sent to the project commander and management. The warning information includes the deviation value, the scope of impact, the cause analysis, and the estimated delay time, and supports multiple notification methods such as SMS, system pop-ups, mobile push, and email; Adjustment plan generation unit: Based on the warning level and the cause of the deviation, it automatically matches adjustment measures from the strategy library and generates multiple alternative plans. Adjustment strategies are divided into three main categories: Process optimization: This type of solution reduces the time required by adjusting the process logic. It includes using the total float of non-critical processes, delaying the start time of non-critical processes, adjusting some sequential processes to parallel processes, and optimizing process connection time. This type of solution does not require additional cost and is suitable for minor deviations. Resource Enhancement: Improve construction efficiency by increasing resource input, including activating backup brine pumps, increasing the number of operating compressors, adjusting personnel shifts, and supplementing maintenance personnel. This type of solution can quickly increase the construction speed and is suitable for moderate deviations. The system will calculate the cost increment simultaneously. Process adjustment category: Improves brine discharge and cavity expansion efficiency by optimizing process parameters, including stepwise increase of gas injection pressure within safe limits, optimization of brine discharge flow control strategy, and adjustment of pressure stabilization cycle. The system has built-in safety thresholds for process parameters, and all generated process adjustment schemes must pass safety verification. Schemes exceeding the thresholds are automatically marked as high-risk and require manual review. The scheme simulation and verification unit has a built-in progress simulation engine that performs digital simulation and deduction of the generated alternative adjustment schemes. Based on the revised schedule model, the system simulates the progress trend of each process after the scheme is implemented, outputs the schedule prediction curve and the final completion time, and verifies whether the scheme can bring the schedule back on track. For multi-stage adjustment schemes, the simulation engine can simulate the effects of step-by-step implementation to assist managers in formulating phased correction plans. Visualization module: The visualization module corresponds to the application interaction layer, providing intuitive and efficient interactive interfaces for users at different levels, and realizing the visualization and interactive operation of project schedule information; Overview Dashboard Unit: Designed for project management and command center, this unit provides a macro-level view of the overall project status. Core content includes: a pie chart of total project schedule, statistics on key milestone completion, the number and level of current warnings at all levels, multi-scenario forecasts of remaining project time, and the operational rate of core equipment. The interface is simple and intuitive, supporting one-click drill-down for detailed information. The progress details unit provides a detailed progress display for progress engineers and construction managers. It includes a dynamic Gantt chart that updates the actual progress bar and planned progress bar for each process in real time, supporting zoom, drill-down, and filtering operations; a cumulative completion rate trend chart that compares the actual completion rate curve with the planned curve from the start of construction, visually presenting the trend of deviation changes; and a critical path analysis chart that marks the current critical path and the total float and free float of each process. Monitoring Data Unit: Designed for technical personnel, this unit displays real-time values and historical trend curves of geological parameters, equipment status, and environmental data, categorized and displayed simultaneously. It supports overlaying and comparing multiple parameters on the same screen. Users can customize time intervals to view historical data, and the unit also supports data export for specialized analysis. 3D visualization unit: Based on the initial 3D model of the salt cavern cavity, the cavity shape is dynamically updated by combining real-time cavity measurement data. The current volume, diameter, height and other parameters of the cavity are displayed intuitively. The cavity expansion progress is displayed by color gradient, realizing spatial dimension progress visualization and assisting technicians in judging the uniformity of cavity forming and construction quality. Multi-terminal adaptation unit: The system adopts a responsive design to adapt to various terminal scenarios. The web large screen terminal is optimized for display in the command center, highlighting core indicators and overall situation. The PC management terminal provides complete management, configuration, and analysis functions. The mobile APP supports progress viewing, early warning reception, and work order processing, meeting the needs of management personnel for on-site and mobile office work. Control execution module: The control and execution module connects decision-making with on-site execution, achieving a closed loop in schedule management and ensuring that adjustment measures are implemented effectively. Manual Confirmation Execution Unit: For medium-to-high level early warnings and complex adjustment plans, a manual confirmation mode is adopted. Managers review alternative plans in a visual interface. After selecting the final plan, the system automatically generates a standardized execution work order, clearly defining the execution content, responsible person, completion deadline, and acceptance criteria. The work order is pushed to the corresponding executor through the system. After receiving the work order, the executor reports the execution progress, submits an acceptance application upon completion, and the administrator verifies and approves the work order to close the loop. Automatic control execution unit: Supports fully automatic closed-loop control for preset minor deviation scenarios. Triggering conditions include: non-critical process deviation rate below 5%, normal equipment operating status, and adjustment parameters within safe threshold range. When the conditions are met, the system automatically generates parameter adjustment instructions, which are then double-verified by the safety verification module and sent to the field PLC control system. System Interface Unit: Provides standardized interfaces to support integration with field PLC control systems, SCADA systems, equipment management systems, enterprise ERP systems, and project management systems, enabling bidirectional data exchange and command linkage. The interfaces support multiple industrial and internet protocols such as OPCUA, Modbus, and HTTP / HTTPS, adapting to equipment and systems from different manufacturers. Execution Effectiveness Evaluation Unit: After the adjustment command is executed, the system continuously collects subsequent construction progress data, compares the progress rate before and after the adjustment, and quantitatively evaluates the actual corrective effect of the adjustment measures. The evaluation results are automatically recorded in the database, serving as an archive of the effectiveness of this adjustment and also feeding back into the schedule model library for iterative optimization of model parameters, achieving continuous evolution of execution, feedback, and optimization.
[0022] The following points should be noted in this article: 1. The accompanying drawings of the embodiments disclosed herein only relate to the structures involved in the embodiments disclosed herein; other structures can be referred to in general design.
[0023] 2. Where there is no conflict, the embodiments of this disclosure and the features in the embodiments can be combined with each other to obtain new embodiments.
[0024] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing specific embodiments, those skilled in the art can still modify the technical solutions described in the foregoing specific embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A compressed air storage power station brine cavern gas injection and desalination schedule control system, comprising a data acquisition module, a progress analysis module, an early warning and adjustment module, a visualization module, and a control execution module, characterized in that: The data acquisition module includes a construction progress data acquisition unit, a geological parameter acquisition unit, an equipment operation status acquisition unit, an environmental monitoring data acquisition unit, and a data preprocessing and transmission unit. It is used to collect construction progress data, geological parameters, equipment operation status data, and environmental monitoring data in real time during the salt cavern aeration and brine discharge construction process, and to transmit the raw data after preprocessing. The progress analysis module includes a schedule model library unit, a dynamic progress calculation unit, a deviation source analysis unit, and a remaining schedule prediction unit. It has a built-in salt cavern gas injection and brine discharge schedule model library. Based on the collected real-time data and the preset schedule benchmark model, it dynamically calculates the deviation between the actual progress and the planned progress, traces the cause of the deviation, and predicts the remaining schedule. The early warning and adjustment module includes a graded early warning unit, an adjustment scheme generation unit, and a scheme simulation verification unit. It can trigger graded early warnings based on the level of progress deviation, automatically generate multiple schedule adjustment schemes based on the causes of deviations, and perform simulation verification and effect prediction on the schemes. The visualization module includes an overview dashboard, a progress details unit, a monitoring data unit, a 3D visualization unit, and a multi-terminal adaptation unit. It displays the total project schedule, process details, monitoring data trends, early warning information, and adjustment plans through a graphical interface, and supports access from multiple terminals. The control execution module includes a manual confirmation execution unit, an automatic control execution unit, a system docking unit, and an execution effect evaluation unit. It supports manual confirmation or automatic issuance of schedule adjustment instructions to on-site construction equipment and management system, tracks the execution process, and verifies the adjustment effect to form a closed-loop control system.
2. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 1, characterized in that: The data acquisition module includes a construction progress data acquisition unit for collecting data on gas injection pressure and flow rate, brine discharge flow rate and cumulative amount, process node status, and salt cavern morphology; a geological parameter acquisition unit for collecting data on salt rock surrounding stress and strain, brine concentration and temperature, and formation pore pressure and permeability; an equipment operation status acquisition unit for collecting operating parameters, fault codes, and load status of the gas injection compressor, brine discharge pump, valves, pipelines, and auxiliary equipment; an environmental monitoring data acquisition unit for collecting wellhead environmental parameters and regional meteorological data; and a data preprocessing and transmission unit for cleaning, denoising, and normalizing the raw data, and uploading it to the server via an encrypted network.
3. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 1, characterized in that: The schedule analysis module's schedule model library unit stores multiple benchmark schedule models categorized by salt rock geological type, cavity size, and design parameters. These models are generated through machine learning training based on historical engineering data. The dynamic schedule calculation unit uses a combination of earned value method and critical path method to calculate cumulative completion rate, process schedule deviation, and total schedule deviation, and dynamically corrects the schedule benchmark based on real-time geological parameters. The deviation source analysis unit uses multi-parameter correlation analysis to quantify the contribution of geological factors, equipment factors, resource factors, and environmental factors to schedule deviation. The remaining schedule prediction unit uses a long short-term memory network model to output remaining schedule prediction results under multiple scenarios based on the current schedule, corrected geological parameters, and equipment status.
4. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 1, characterized in that: The tiered early warning unit of the early warning and adjustment module is preset with four levels of deviation thresholds, and different levels of early warning are matched with different push targets and handling procedures. The adjustment scheme generation unit generates three types of adjustment strategies—process optimization, resource enhancement, and process adjustment—based on the causes and levels of deviations, and outputs multiple alternative schemes along with corresponding time gains, cost increments, and risk level indicators. The scheme simulation verification unit uses a progress simulation model to deduce the progress trend after the scheme is implemented, verifies the time correction effect, and outputs simulation prediction curves.
5. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 1, characterized in that: The overview dashboard unit of the visualization module displays the overall project schedule, the completion status of key nodes, current early warning statistics, and the predicted remaining project time; the progress details unit provides a dynamic Gantt chart and progress trend curve, supporting process drill-down and comparison between the planned and actual progress. The monitoring data unit categorizes and displays real-time values and historical trends of geological, equipment, and environmental parameters, supporting multi-parameter comparison on the same screen; the 3D visualization unit combines a 3D model of the salt cavern to intuitively display the cavern expansion progress and spatial morphology. The multi-terminal adaptation unit supports differentiated display and interaction across web dashboards, PC management terminals, and mobile apps.
6. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 1, characterized in that: The manual confirmation execution unit of the control execution module supports administrators in reviewing adjustment plans, issuing execution work orders, tracking execution status, and accepting execution results; the automatic control execution unit automatically issues parameter adjustment instructions to the field control system after passing safety verification for preset minor deviation scenarios; the system interface unit supports data exchange and instruction linkage with field PLCs, SCADA systems, equipment management systems, and enterprise ERP systems; and the execution effect evaluation unit continuously collects adjusted progress data, evaluates the correction effect, and feeds the effect data back to the schedule model library for model iteration.
7. The compressed air energy storage power station salt cavern gas injection and brine discharge period control system according to claim 2, characterized in that: The morphological data of the salt cavern cavity in the construction progress data acquisition unit is collected periodically by the downhole sonar cavity measurement system. The data is automatically synchronized to the system and used to update the cavity volume and total amount of brine discharged.
8. The compressed air energy storage power station salt cavern gas injection and brine discharge period control system according to claim 3, characterized in that: The baseline models in the construction period model library are divided into layered salt rock models and salt dome models according to the salt cave type. Each type of model includes the construction period baseline and weight allocation for four process stages: pretreatment, gas injection and brine discharge, pressure stabilization and molding, and acceptance.
9. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 4, characterized in that: The process adjustment strategy includes step optimization of gas injection pressure, dynamic adjustment of brine discharge flow rate, and adjustment of pressure stabilization cycle. All adjustment parameters are preset with safety thresholds. Schemes that exceed the thresholds are automatically marked as high-risk and prompt for manual review.
10. The compressed air energy storage power station salt cavern gas injection and brine discharge schedule control system according to claim 6, characterized in that: The triggering conditions for the automatic control execution unit are: the deviation rate of non-critical processes is less than 5%, the equipment is operating normally, the adjustment parameters are within the safety threshold range, and if the progress does not recover to the planned range within 15 minutes after the adjustment is executed, it will automatically upgrade to manual intervention mode.
11. A method for controlling the construction period of compressed air energy storage power station salt cavern gas injection and brine discharge, implemented based on the compressed air energy storage power station salt cavern gas injection and brine discharge construction period control system according to any one of claims 1-10, characterized in that: The control method specifically includes the following steps: Step 1: System initialization and baseline duration model construction, input basic project parameters, match the baseline model to generate an initial duration plan, and configure control rules; Step 2: Real-time acquisition and preprocessing of multi-source construction data, simultaneously acquiring four types of data: progress, geology, equipment, and environment, which are then reliably transmitted after edge cleaning and normalization; Step 3: Dynamic progress calculation and deviation identification, combining real-time data to calculate progress indicators, dynamically adjust the schedule baseline, and determine the deviation level and scope of impact; Step 4: Tracing the causes of deviations and predicting the remaining construction period, quantifying the contribution of each factor to locate the main cause, correcting model parameters and outputting multi-scenario construction period prediction results; Step 5: Generate graded early warning and correction schemes. Trigger corresponding early warnings according to the deviation level, match the strategy library to generate multiple alternative correction schemes and output evaluation indicators; Step Six: Simulation Verification and Execution Command Issuance. The scheme's corrective effect is verified through simulation. After confirmation, an execution work order or automatic control command is issued. Step 7: Execution effect evaluation and model iteration optimization. Track the execution process, quantitatively evaluate the effect of corrective measures, and use feedback data to iteratively optimize the project schedule model to form a closed-loop management system.