A wind-solar power generation system short-circuit current calculation method considering control switching
By establishing an inverter current output characteristic model and taking into account the dynamic changes in current during the control mode switching process, the problem of dynamic switching of control strategies in the short-circuit current calculation of wind and solar power generation systems was solved, improving the calculation accuracy and the reliability of power system analysis, and ensuring the safety and stability of the power system.
Patent Information
- Application Number
- CN202611569235.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-12
- Publication Date
- 2026-11-10
AI Technical Summary
Existing technologies fail to adequately consider the dynamic switching of control strategies when calculating short-circuit currents in wind and solar power generation systems, resulting in significant deviations between the calculated results and the actual short-circuit currents. This affects the accuracy of relay protection settings and threatens the safe and stable operation of the power system.
By acquiring real-time operating data of the wind and solar power generation system, the conditions for switching control modes are determined, and inverter current output characteristic models under different control modes are established. During the control mode switching process, the dynamic changes in current are taken into account, and the current change characteristics are described by a first-order inertial element. The impact current component generated by the discharge of the inverter's DC-side capacitor is considered, and the short-circuit current is accurately calculated.
It improves the accuracy of short-circuit current calculation, accurately simulates the dynamic process of control switching, provides more reliable data support, provides reliable input for relay protection setting and power system stability assessment, and ensures the safe and stable operation of the power system under the environment of large-scale new energy grid access.
Smart Images

Figure CN123073772A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power systems, and more particularly to a method for calculating short-circuit current in wind and solar power generation systems that takes into account control switching. Background Technology
[0002] Short-circuit current calculation for wind and solar power systems is a core technical aspect of new energy power system analysis. Unlike traditional synchronous generators, wind and solar power systems are connected to the grid via power electronic converters, and their output characteristics are primarily determined by the converter's control strategy. Under steady-state conditions, short-circuit current calculations are typically based on fixed control mode assumptions to assess the system's grid support capability under fault conditions, providing crucial information for configuring protection device parameters. However, the operating characteristics of wind and solar power systems are not static; their control strategies dynamically adjust as the grid's operating state changes.
[0003] Existing technologies for calculating short-circuit currents in wind and solar power systems generally suffer from insufficient consideration of the dynamic characteristics of control strategies. Specifically, when a short-circuit fault occurs in the grid, wind and solar power systems typically need to quickly switch from the maximum power point tracking control mode under normal operating conditions to the low voltage ride-through control mode to meet grid specifications for non-disconnection during fault periods. This control mode switching causes a significant change in the inverter's current output characteristics, thereby affecting the amplitude and phase of the short-circuit current at the fault point. However, existing short-circuit current calculation methods are usually based on a single steady-state control assumption, failing to fully account for the dynamic evolution of the inverter's current output characteristics during the control switching process. This leads to a large deviation between the calculated results and the actual short-circuit current. Especially in the context of large-scale renewable energy grid integration, this calculation error may cause relay protection settings to deviate from actual requirements, and in severe cases, threaten the safe and stable operation of the power system. Summary of the Invention
[0004] The purpose of this invention is to provide a method for calculating the short-circuit current of a wind and solar power generation system that takes into account control switching, which can effectively solve the problem that the existing technology does not fully consider the dynamic switching of control strategies when calculating the short-circuit current of a wind and solar power generation system.
[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:
[0006] A method for calculating short-circuit current in a wind and solar power generation system considering control switching includes the following specific steps: Step 1: Obtain real-time operating data of the wind and solar power generation system: Collect the voltage, current, active power, and reactive power at the grid connection point of the wind and solar power generation system, and simultaneously obtain the current control mode status information of the inverter; Step 2: Determine the control mode switching conditions: Based on the collected grid connection point voltage value, determine whether a voltage drop to a preset low-voltage ride-through trigger threshold has occurred. When the grid connection point voltage drops below the preset threshold, it is determined that the wind and solar power generation system needs to switch from the maximum power point tracking control mode to the low-voltage ride-through control mode; Step 3: Establish inverter current output characteristic models under different control modes: In the maximum power point tracking control mode, establish a mathematical model of the inverter output current according to the maximum power point tracking strategy. The model parameters include the maximum power point current command value corresponding to the current irradiance or wind speed; In the low-voltage ride-through control mode, establish... Step 4: Establish a mathematical model for the inverter's output current according to the grid's reactive power support requirements. The model parameters include the grid's required reactive current coefficient and active current limit. Step 5: Establish a short-circuit current calculation model considering the control switching process. Based on the control mode switching judgment results, during the control mode switching process, a short-circuit current calculation model including the dynamic change process of the current is established based on the difference in the inverter's current output characteristics before and after the switching. The dynamic change process of the current is described by a first-order inertial element, and the time constant is determined according to the response characteristics of the inverter control system. The steady-state short-circuit current after the switching is completed is calculated using the current output characteristics under the low-voltage ride-through control mode. Step 6: Output the short-circuit current calculation results for power system analysis applications. The short-circuit current calculation results are applied to power system fault analysis calculations to provide data support for the setting of relay protection devices and to provide basic input for power system stability assessment.
[0007] Preferably, the sampling period for collecting real-time running data in step 1 is no more than 1 millisecond, in order to meet the time resolution requirements for capturing the dynamic switching process of the control strategy.
[0008] Preferably, the low voltage ride-through trigger threshold in step 2 is set to 0.85 to 0.9 times the rated voltage, and the specific value is determined according to the grid access specifications and the grid connection technical requirements of the wind and solar power generation system.
[0009] Step 2 also includes setting hysteresis control logic for determining control mode switching. The hysteresis width is set to 0.02 times the rated voltage to avoid frequent switching of control modes near the voltage boundary.
[0010] Preferably, in step 3, the inverter current output characteristic model under the maximum power point tracking control mode uses the perturbation observation method or the incremental conductance method to determine the current command value corresponding to the current maximum power point, and considers the dynamic influence of changes in light intensity or wind speed on the position of the maximum power point.
[0011] In step 3, the inverter current output characteristic model under the low voltage ride-through control mode calculates the required reactive current injection based on the reactive support requirements during grid faults and the ratio of reactive current to voltage drop, while limiting active current output to avoid DC-side overvoltage.
[0012] Preferably, the time constant of the first-order inertial element in step 4 is determined based on the bandwidth of the inverter current inner loop controller, and the value ranges from 5 milliseconds to 20 milliseconds. The specific value is obtained through frequency response testing of the inverter control system.
[0013] In step 4, the short-circuit current calculation during the control mode switching process takes into account the instantaneous impact current component generated by the discharge of the DC-side capacitor of the inverter during the switching instant. The decay time constant of this component is the product of the DC-side capacitor and the equivalent impedance of the inverter.
[0014] The steady-state short-circuit current calculation after the switching in step 4 takes into account the limiting characteristics of the inverter output current under the low voltage ride-through control mode. The limiting value is determined according to the maximum fault current injection multiple required by the power grid specifications.
[0015] Preferably, in step 5, the short-circuit current calculation result is compared with the preset relay protection setting threshold. When the calculated short-circuit current value exceeds the operating current range of the relay protection, a corresponding alarm message is given.
[0016] Preferably, it also includes establishing a short-circuit current calculation database for wind and solar power generation systems to store short-circuit current calculation results under different operating conditions and different control mode switching scenarios, and optimizing the parameter settings of the short-circuit current calculation model through statistical analysis of historical data.
[0017] The beneficial effects of this invention are:
[0018] 1. Improved accuracy of short-circuit current calculation: This invention establishes inverter current output characteristic models under different control modes and takes into account the dynamic change of current during the control mode switching process. It effectively solves the calculation deviation problem caused by the single steady-state control assumption in the existing technology, significantly improves the calculation accuracy, and provides more reliable data support for relay protection setting.
[0019] 2. Accurate simulation of the dynamic process of control switching: This invention uses a first-order inertial element to describe the current change characteristics during the control mode switching process, and considers the impact current component generated by the DC side capacitor discharge during the switching instant. It can accurately simulate the complete dynamic process of the wind and solar power generation system switching from the maximum power point tracking control mode to the low voltage ride-through control mode during grid faults, making the short-circuit current calculation results closer to the actual system response.
[0020] 3. Enhance the reliability of power system analysis: The short-circuit current calculation results provided by this invention can be directly applied to relay protection settings and power system stability assessment, which can effectively avoid the problem of protection setting values deviating from actual needs due to calculation errors, and ensure the safe and stable operation of the power system under the environment of large-scale new energy grid access. Attached Figure Description
[0021] Figure 1 This is a schematic diagram of the overall technical solution architecture of the short-circuit current calculation method for wind and solar power generation systems that takes into account control switching proposed in this invention. Detailed Implementation
[0022] The present invention will be further described below with reference to the accompanying drawings and specific embodiments. The illustrative embodiments and descriptions herein are used to explain the present invention, but are not intended to limit the present invention.
[0023] like Figure 1 As shown, the short-circuit current calculation method for wind and solar power generation systems, considering control switching, proposed in this invention comprises four core functional modules: a data acquisition layer, a control mode determination layer, a model calculation layer, and an application output layer. These modules interact via standardized data interfaces, forming a complete closed loop for short-circuit current calculation. The data acquisition layer acquires raw operating data from various sensor nodes of the wind and solar power generation system and performs data preprocessing and time-stamping. The control mode determination layer determines the appropriate control mode for the inverter in the wind and solar power generation system based on a comparison of the acquired voltage signal with a preset threshold. The model calculation layer establishes an accurate inverter current output characteristic model based on the current control mode and its switching process, and calculates the system's short-circuit current value. The application output layer outputs the calculation results in a standard format to the relay protection setting system or the power system stability assessment module.
[0024] In step 1, during the acquisition of real-time operating data of the wind and solar power generation system, the acquisition unit obtains the instantaneous values of the three-phase voltage and three-phase current at the grid connection point in real time through voltage transformers and current transformers. The voltage signal acquisition uses an electromagnetic voltage transformer with an accuracy of no less than 0.2 class. Its secondary side output signal undergoes amplitude adjustment and filtering processing by a signal conditioning circuit before being sent to an analog-to-digital converter for digitization. The current signal acquisition uses a feedthrough current transformer or a Rogowski coil. Its output signal also undergoes impedance matching and noise suppression processing by a signal conditioning circuit. The sampling frequency of the analog-to-digital converter is set to no less than one sampling point per millisecond, i.e., a sampling period of no more than 1 millisecond, to meet the time resolution requirements for capturing the dynamic switching process of the inverter control strategy. At the initial moment of a grid fault, the voltage drop and current change process often complete within milliseconds. If the sampling frequency is too low, it will be impossible to accurately capture the instantaneous characteristics of the control mode switching, resulting in a large deviation between the short-circuit current calculation result and the actual system response.
[0025] The acquired raw data first enters the data preprocessing module for filtering and calibration. Digital filtering employs a second-order Butterworth low-pass filter, with the cutoff frequency set to 5 to 8 times the fundamental frequency of the sampled signal to effectively suppress the impact of high-frequency noise and switching harmonic components on measurement accuracy. Calibration, based on pre-determined sensor gain coefficients and phase offsets, performs online compensation on the acquired signal to eliminate measurement errors inherent in the sensor itself. The pre-processed voltage signal is then further subjected to RMS value calculation using a sliding window root mean square algorithm. The window length is set to one power frequency cycle (20 milliseconds), and the window sliding step size is set to 1 millisecond to obtain a continuous sequence of voltage RMS values. The same method and parameter settings are used to calculate the RMS value of the current signal, ensuring the synchronization of the voltage and current signals in time.
[0026] The calculation of active and reactive power is based on the instantaneous values of the three-phase voltage and current. The time-varying signals in the three-phase stationary coordinate system are converted into DC components in the two-phase rotating coordinate system using the Park transform. The angle reference for the Park transform is determined by the grid voltage phase angle provided by the phase-locked loop (PLL) module. The dynamic response bandwidth of the PLL is set to 30 Hz to 50 Hz to ensure phase tracking accuracy under grid frequency fluctuations. The active power calculation formula in the rotating coordinate system is the sum of the products of the two-phase current components and the voltage components, while the reactive power calculation formula is the difference between the cross products of voltage and current. The calculated active and reactive power are output at an update rate of 1000 points per second as input parameters for control mode judgment and model calculation.
[0027] The current control mode status information of the inverter is obtained by reading the mode flag bit inside the inverter control system. The inverter control system maintains a control mode status variable internally, which reflects the control strategy number currently being executed by the inverter in real time. The encoding rule for the control strategy number is set as follows: 0 represents standby mode, 1 represents maximum power point tracking control mode, 2 represents low voltage ride-through control mode, 3 represents constant power control mode, and 4 represents islanding detection mode. The data acquisition unit communicates with the inverter control system and periodically reads the current value of this status variable. The communication interface uses the Modbus TCP protocol based on Ethernet or the IEC 61850 protocol, with a communication period set to 1 millisecond to ensure consistency between the control mode status information and electrical measurement data on the time scale.
[0028] In step 2, during the determination of control mode switching conditions, the core of the judgment logic is to compare the currently collected effective value of the grid connection point voltage with the preset low-voltage ride-through trigger threshold. The low-voltage ride-through trigger threshold is set based on grid access specifications and grid connection technology requirements for wind and solar power generation systems, with a typical setting between 85% and 90% of the rated voltage. Taking a wind and solar power generation system with a rated voltage of 10 kV as an example, its low-voltage ride-through trigger threshold can be set to a specific value between 8.5 kV and 9 kV. The selection of this specific value needs to comprehensively consider the voltage regulation margin of the grid dispatch, the voltage tolerance capability of the local load, and the low-voltage ride-through performance of the inverter itself. When the effective value of the grid connection point voltage drops below the aforementioned trigger threshold, the judgment logic outputs a control mode switching trigger signal, indicating that the wind and solar power generation system needs to switch from the maximum power point tracking control mode to the low-voltage ride-through control mode.
[0029] To avoid frequent control mode switching near voltage boundaries, a hysteresis control module is incorporated into the decision logic. This module is implemented by comparing two voltage thresholds: a trigger threshold and a recovery threshold. The trigger threshold is the voltage boundary at which a low voltage crosses the start-up threshold, while the recovery threshold is higher than the trigger threshold; the difference between the two is the hysteresis width. The hysteresis width is set to 2% of the rated voltage; for example, in a 10 kV system, the hysteresis width is 0.2 kV. This means that a control mode switch is only determined when the voltage drops from a normal operating state (above the recovery threshold) to below the trigger threshold; and a return to maximum power point tracking (MPPT) control mode is only determined when the voltage rises from a fault state (below the trigger threshold) to above the recovery threshold. Within the hysteresis range between the trigger and recovery thresholds, the control mode remains unchanged, effectively preventing frequent control mode jumps caused by small voltage fluctuations near the thresholds.
[0030] The timing logic for control mode switching is implemented using a state machine. The state machine contains two stable states and one transitional state. The first stable state is the maximum power point tracking (MPPT) control mode state, the second stable state is the low voltage ride-through (LVRT) control mode state, and the transitional state is the state in the process of switching control modes. When the state machine is in the MPPT control mode state, if the effective voltage value is detected to be lower than the trigger threshold and the hysteresis condition is met, the state machine transitions to the transitional state, and simultaneously records the timestamp of the switching trigger moment. The transitional state continues until the pre-switching preparation operations are completed, specifically including freezing the output commands of the MPPT controller and initializing the state variables of the LVRT controller. After completing the preparation operations, the state machine transitions to the LVRT control mode state and sends a control mode switching event notification to the model calculation layer.
[0031] In step 3, during the establishment of inverter current output characteristic models under different control modes, the inverter current output characteristic model under maximum power point tracking (MPPT) control mode uses the maximum power point current command value at the current operating point as its core parameter. The methods for obtaining this current command value include two mainstream algorithms: the perturbation-observation method and the incremental conductance method. The perturbation-observation method works by periodically applying small perturbations to the output voltage of the photovoltaic module or wind turbine generator, observing the direction of output power change after the perturbation. If the power increases after the perturbation, the perturbation continues in the same direction; if the power decreases, the perturbation direction is changed. This process iterates until the operating point with the maximum output power is found. Key parameters of this method include the perturbation step size and the perturbation period. The perturbation step size is typically set to 0.5% to 2% of the rated voltage, and the perturbation period is typically set to tens to hundreds of milliseconds to balance the tracking speed and the steady-state oscillation amplitude. The incremental conductance method works by determining the relative position between the current operating point and the maximum power point based on the ratio of the derivative of the output power of the photovoltaic module or wind turbine generator with respect to voltage and the current conductance, thereby determining the voltage adjustment direction. The mathematical expression for this method is the ratio of dP / dV to P / V. When dP / dV is greater than negative P / V, the voltage should be adjusted in the direction of increasing; when dP / dV is less than negative P / V, the voltage should be adjusted in the direction of decreasing; when dP / dV is equal to negative P / V, the current operating point is the maximum power point.
[0032] When considering the dynamic impact of changes in light intensity or wind speed on the location of the maximum power point (MPP), the MPP controller needs to be adaptable to changes in environmental conditions. When light intensity or wind speed changes significantly, the MPP may shift considerably. If tracking is performed solely using the perturbation observation method or incremental conductance method, the tracking speed may not keep pace with the environmental changes, causing the inverter to operate for extended periods away from the MPP. To address this issue, a feedforward compensation stage based on environmental parameter predictions is introduced into the model. This stage utilizes short-term solar radiation intensity and wind speed predictions provided by weather forecasting systems, combined with a mathematical model of the power-voltage characteristic curve of photovoltaic modules or wind turbine generators, to estimate the possible location range of the MPP within the next few seconds. Based on this, the perturbation step size and search range of the perturbation observation method or incremental conductance method are adjusted to achieve rapid tracking.
[0033] The inverter current output characteristic model under maximum power point tracking control mode can be expressed in the following form:
[0034]
[0035] in, This represents the inverter output current command value in maximum power point tracking control mode, in amperes (A). This represents the maximum power point power value under the current environmental conditions, in watts (W). This represents the DC-side voltage of the inverter, in volts (V). This represents the maximum power point tracking current command correction factor, which is dimensionless and typically takes the value of 1, but can also be determined based on the maximum power point tracking controller gain. The model's input parameters. It is updated in real time by the maximum power point tracking algorithm. The update period is the same as the execution period of the perturbation observation method or the incremental conductance method, which is usually set to 10 milliseconds to 100 milliseconds.
[0036] The inverter current output characteristic model under low voltage ride-through control mode uses the grid-required reactive current coefficient and active current limit as core parameters. During grid faults, wind and solar power systems need to inject reactive current into the grid to support voltage recovery. The amount of reactive current injected is typically proportional to the degree of voltage drop. The mathematical expression for this proportionality is:
[0037]
[0038] in, This represents the reactive current command value output by the inverter under low voltage ride-through control mode, in amperes (A). It represents the low voltage ride-through reactive power support factor, which is dimensionless and typically ranges from 1.0 to 2.0. This indicates the inverter's rated current, expressed in amperes (A). This represents the effective value of the grid connection point voltage, in V. This represents the rated voltage value, in volts (V). When the grid connection point voltage drops completely to zero, the reactive current command value given by this formula is equal to... With inverter rated current The product of these two values represents the maximum permissible reactive current output by the inverter to support grid voltage rebuilding.
[0039] The active current limit is determined jointly based on DC-side voltage safety constraints and inverter thermal capacity constraints. During low-voltage ride-through, the inverter's output power capability is limited due to the voltage drop at the grid connection point. Maintaining a large active current output would lead to an increase in DC-side voltage, endangering the safety of the DC capacitor and power devices. Therefore, a limiting mechanism is set for the active current command value in the model. The formula for calculating the limiting value is as follows:
[0040]
[0041] in, This indicates the upper limit of the active current command value, in amperes (A). This represents the rated maximum output current of the inverter, measured in amperes (A). This value is determined by the current withstand capability and heat dissipation conditions of the inverter's power devices. After calculation, the active current command value needs to be processed by this limiting circuit to ensure it does not exceed the calculated limit.
[0042] The inverter current output characteristic model under low voltage ride-through control mode can be comprehensively expressed in the following form:
[0043]
[0044] in, This represents the inverter output current command value in low voltage ride-through control mode, in amperes (A). Represents the imaginary unit; This indicates the low-voltage ride-through trigger threshold, in V; This represents the inverter output current command value in maximum power point tracking (MPPT) mode, expressed in amperes (A). The model indicates that when the grid connection point voltage is below the low-voltage crossover trigger threshold, the inverter outputs a complex combination of the reactive current command value and the active current limit value; when the grid connection point voltage recovers above the trigger threshold, the inverter resumes execution of MPPT mode.
[0045] In step 4, during the establishment of the short-circuit current calculation model considering the control switching process, the core task of the model is to accurately describe the dynamic changes in the inverter output current during the control mode switching process. The essence of the control mode switching process is the inverter control system switching from executing one control algorithm to executing another. This process involves abrupt changes in the controller's internal state variables and a step change in the current command value. Due to the inherent inertial characteristics of the inverter current control system, the actual change in current cannot be instantaneous but gradually approaches the new command value according to certain dynamic laws. This inertial characteristic is mainly determined by the parameters of the inner current loop controller in the inverter control system, specifically the bandwidth and sampling period of the current controller.
[0046] A first-order inertial element is a classic mathematical model describing this inertial characteristic, and its transfer function is in the form of:
[0047]
[0048] in, The transfer function of a first-order inertial element. Represents the inertial time constant. This represents the Laplace operator, with units of 1 / s. The time-domain response characteristics of a first-order inertial element are: when the initial current value is... The current command value undergoes a step change to At that time, the actual current value follows an exponential law from Gradually change to The time constant of the change process is The specific expression is:
[0049]
[0050] Let the time when the control mode switch occurs be Before switching, the inverter was in maximum power point tracking control mode, and its current output command value was... After switching, the inverter enters the low voltage ride-through control mode, and its current output command value is... At the moment of switching, the current command value received by the current control system changes from... Mutation However, due to the presence of the inertial element, the actual current value gradually changes from the current value to the value according to the dynamic characteristics of the first-order inertial element. Time constant The value of is determined based on the bandwidth of the inverter's inner current loop controller. The inner current loop controller typically employs a proportional-integral (PI) controller or a proportional-resonant (RIR) controller, and its control bandwidth is closely related to the current sampling frequency, controller gain parameters, and the electrical parameters of the inverter's output filter. In engineering practice, the time constant... The typical value range is 5 milliseconds to 20 milliseconds, and the specific value is obtained through frequency response testing of the inverter control system. The frequency response test method is as follows: apply sinusoidal current command signals of different frequencies to the current control system, measure the amplitude gain and phase delay of the system output current relative to the command signal, plot the Bode plot, read the frequency value corresponding to the -3 dB bandwidth, and then calculate the equivalent first-order inertial element time constant.
[0051] During control mode switching, the dynamic calculation of the short-circuit current needs to comprehensively consider the differences in current output characteristics between the two control modes and the transient process of the switching itself. Let the moment of control mode switching be... Before switching, the inverter was in maximum power point tracking control mode, and its current output command value was... After switching, the inverter enters the low voltage ride-through control mode, and its current output command value is... At the moment of switching, the current command value received by the current control system changes from... Mutation However, due to the presence of inertial elements, the actual current value gradually changes from the current value to the specified value according to the dynamic characteristics of a first-order inertial element. The short-circuit current calculation model during the control mode switching process can be expressed as the following piecewise function:
[0052]
[0053] in, This represents the short-circuit current injected into the power grid at the grid connection point of the wind and solar power generation system; This represents the steady-state value of the current command after the control mode switch; Indicates the duration of the transition process when switching control modes; This represents the instantaneous inrush current component generated by the discharge of the DC-side capacitor in the inverter; The inertial time constant is the same as that in the aforementioned transfer function. Consistent.
[0054] The instantaneous inrush current component generated by the discharge of the inverter's DC-side capacitor is a crucial characteristic that cannot be ignored during control mode switching. At the instant of control mode switching, due to a sudden drop in grid voltage, the electrical energy stored in the inverter's DC-side capacitor cannot be transferred to the grid through the inverter. The voltage across the capacitor remains relatively stable, and the capacitor releases energy to the grid through a discharge circuit formed by the power devices inside the inverter. This inrush current component exhibits high-frequency attenuation characteristics, with its attenuation time constant being the product of the DC-side capacitor and the inverter's equivalent impedance. The capacitance of the DC-side capacitor is typically from several thousand microfarads to tens of thousands of microfarads, depending on the inverter's power rating and DC voltage level. The inverter's equivalent impedance includes the on-resistance of the power devices, filter impedance, and connection line impedance, and its value is typically from a few milliohms to tens of milliohms. Taking all factors into account, the attenuation time constant of the capacitor discharge inrush current component is typically from a few milliseconds to tens of milliseconds.
[0055] The mathematical expression for the capacitor discharge impulse current component is:
[0056]
[0057] in, This indicates the initial amplitude of the capacitor discharge inrush current at the moment of switching; The capacitor discharge decay time constant is represented by the following formula:
[0058]
[0059] in, This indicates the capacitance value of the DC-side capacitor. This represents the magnitude of the inverter's equivalent impedance.
[0060] After the switchover, the steady-state short-circuit current is calculated using the current output characteristics under the low-voltage ride-through control mode. At this point, the transition process of the control mode switchover is complete, and the inverter control system operates stably in the low-voltage ride-through control mode. Its output current characteristics are determined by the reactive current command value and the active current limit value. It is important to consider that the inverter output current in the low-voltage ride-through control mode has a limiting characteristic. This limiting value is determined based on the maximum fault current injection multiple required by the grid specifications. The requirements for the fault current injection multiple vary across different countries and regions. Generally, it requires the inverter to provide reactive current support of 1.0 to 1.5 times the rated current during a fault, while maintaining an active current output not lower than a certain percentage of the rated current. Specific parameters are determined by the local grid dispatching department.
[0061] The total short-circuit current of a wind and solar power generation system consists of two parts: the short-circuit current on the inverter side and the short-circuit current on the synchronous generator side (if the system contains synchronous generators). If the wind and solar power generation system includes photovoltaic modules and wind turbine generators, and both are connected to the grid through inverters, then the total short-circuit current of the system is the algebraic sum of the short-circuit currents of each inverter unit. The number of inverter units may range from tens to thousands, depending on the installed capacity of the wind and solar power plant. In the short-circuit current calculation process, the operating status of each inverter unit needs to be aggregated to form an equivalent inverter group model. The aggregation method includes: dividing the inverter units into several regions according to geographical location, with each inverter unit in each region being equivalent to an equivalent inverter with the same control characteristics and electrical parameters; and modeling the connection relationship between each equivalent inverter according to the actual electrical topology.
[0062] In step 5, during the output of the short-circuit current calculation results for power system analysis applications, the calculated short-circuit current results are output to the power system analysis application module in a standard data format. The output data format adopts the event data format defined by the IEEE 1159.1 standard or the data object model defined by the IEC 61850 standard. The output data includes: the occurrence time of the short-circuit fault, the fault duration, the instantaneous or effective value sequence of the current in each phase at the grid connection point of the wind and solar power generation system, the peak and duration values of the short-circuit current, the timestamp and type of the control mode switching event, and the model parameters and algorithm identifiers used in the calculation process. Data transmission supports both real-time streaming and historical data query modes. Real-time streaming is used for online applications of relay protection systems, while historical data query is used for power system planning analysis and accident retrospective analysis.
[0063] Relay protection setting is one of the main application scenarios for short-circuit current calculation results. During relay protection setting, the operating current setting value of the protection device needs to be determined based on the calculated maximum short-circuit current value to ensure reliable operation of the protection device during short-circuit faults and to prevent malfunctions during normal operation. The comparison process of the relay protection setting threshold includes the following steps: First, the calculated short-circuit current values at each moment are compared with the preset protection operating current setting value. If the short-circuit current value is greater than the operating current setting value for several consecutive sampling periods, a fault condition requiring protection operation is determined. Second, the calculated short-circuit current value is compared with the rated breaking capacity of the protection device to ensure that the protection device is not damaged when disconnecting the short-circuit current. Finally, protection action suggestions or alarm information are generated based on the comparison results. When the calculated short-circuit current value exceeds the operating current range of the relay protection device, the system provides corresponding alarm information, prompting maintenance personnel to check the rationality of the protection setting value or investigate abnormal operating conditions in the system.
[0064] Power system stability assessment is another important application of short-circuit current calculation results. In transient stability analysis, it is necessary to evaluate the system's support capacity for the power grid and its own disturbance rejection capability based on the short-circuit current characteristics of the wind and solar power generation system during a fault. The short-circuit current calculation results serve as input parameters in the solution process of the power system dynamic simulation model. The simulation time range typically extends from several power frequency cycles before the fault occurs to dozens of power frequency cycles after the fault is cleared, to comprehensively evaluate the dynamic response characteristics of the system throughout the fault process. The simulation output results include: voltage trajectories of each node in the wind and solar power generation system, current trajectories of each inverter unit, system frequency response trajectory, and power angle stability indices. By analyzing these output results, it can be determined whether the wind and solar power generation system meets the power system stability requirements after being connected to the grid. If not, system parameters or control strategies need to be adjusted.
[0065] The establishment of a short-circuit current calculation database for wind and solar power systems provides a data foundation for the continuous optimization of short-circuit current calculation models. The database stores: real-time operating data records under different operating conditions; control commands and current response records under different control mode switching scenarios; short-circuit current calculation results for different short-circuit fault types and locations; and statistical analysis of the deviations between these calculation results and actual measured values. The database storage structure combines relational and time-series databases. The relational database stores static configuration parameters and event records, while the time-series database stores high-frequency sampling data and calculation result sequences. The database query interface supports combined queries based on various conditions such as time range, operating condition type, and fault type, facilitating statistical analysis and feature extraction of historical data.
[0066] Statistical analysis of historical data can optimize the parameter settings of the short-circuit current calculation model. Parameter optimization methods include: using actual fault recording data to identify parameters such as the time constant and gain coefficient in the model online, and adjusting the initial settings of the model parameters based on the identification results; using cluster analysis to classify the short-circuit current characteristics under different operating conditions, and establishing a dedicated set of calculation model parameters for each type of operating condition; and using machine learning methods to establish a nonlinear mapping relationship from operating condition characteristics to model parameters, achieving intelligent adaptive adjustment of model parameters.
[0067] Example 1
[0068] The following detailed explanation of the operational process and expected results of the method of this invention in practical engineering is illustrated with a specific application example. Assume a grid-connected wind-solar hybrid power generation system consists of a 100 MW photovoltaic array and a 50 MW wind turbine generator set, with a total installed capacity of 150 MW. The photovoltaic array is divided into 10 photovoltaic sub-arrays, each with an installed capacity of 10 MW, and is equipped with one 10 MW rated power three-level voltage source inverter. There are 25 wind turbine generator sets, each with a rated power of 2 MW, and each equipped with one 2 MW rated power full-power inverter. All inverters have low-voltage ride-through capability, with the low-voltage ride-through trigger threshold uniformly set to 0.85 times the rated voltage and the hysteresis width set to 0.02 times the rated voltage.
[0069] Under normal operating conditions, the photovoltaic array has a solar irradiance of 800 watts per square meter, an ambient temperature of 25 degrees Celsius, and an average wind speed of 10 meters per second for the wind turbines. Each inverter operates in maximum power point tracking (MPPT) mode. The MPPT current command value for the photovoltaic inverters is calculated based on the current solar irradiance and temperature conditions, while the MPPT current command value for the wind turbine inverters is calculated based on the current wind speed and rotor speed. The total output power of the wind and solar power system is approximately 120 megawatts, with a power factor maintained at around 0.98, exhibiting lagging operation.
[0070] Assume a three-phase short-circuit ground fault occurs on a 110 kV transmission line 5 km from the grid connection point of the wind-solar power generation system, with the fault occurring at time t = 0 seconds. After the fault, the grid connection voltage drops from 102.6 kV to approximately 40 kV within 1 millisecond, a voltage drop of 61%, far below the low-voltage ride-through trigger threshold of 93.5 kV. Upon detecting the voltage drop, the data acquisition unit immediately sends a voltage drop alarm signal to the control mode determination module. The control mode determination module, based on hysteresis control logic, determines that since the current voltage value is below the low-voltage ride-through trigger threshold and not within the hysteresis range, a control mode switch needs to be triggered. The control mode switch command is sent to the control systems of all inverters approximately 2 milliseconds after the fault occurs.
[0071] Upon receiving the control mode switching command, each inverter executes the switching operation according to the predetermined switching sequence. The specific steps of the switching operation include: freezing the output register of the maximum power point tracking controller and saving the current command value as the reference value before switching; initializing the proportional-integral (PI) term of the low-voltage ride-through controller, setting the integral term to 50% of its steady-state value to avoid integral saturation; enabling the reactive current support function, and calculating the reactive current command value under the current operating condition according to a reactive current coefficient of 1.2. The completion time of the switching operation is approximately 5 to 10 milliseconds, depending on the processing capability and communication latency of the inverter control system.
[0072] During the control mode switching process, the dynamic calculation model of the short-circuit current is calculated according to the aforementioned piecewise function form. Let the fault occurrence time be t = 0 seconds, the control mode switching trigger time be t = 2 milliseconds, and the switching operation completion time be t = 10 milliseconds. During the period from t = 0 to 2 milliseconds, the inverter remains in maximum power point tracking (MPPT) control mode, and its output current is determined according to the MPPT strategy, with a current value approximately 0.8 times the rated current. During the period from t = 2 to 10 milliseconds, the inverter is in the control mode transition phase. The current command value changes abruptly from the MPPT mode current value to the low voltage ride-through mode current value. The actual current value gradually approaches the target value from the current value according to the dynamic characteristics of the first-order inertial element, with the time constant of the first-order inertial element set to 10 milliseconds. After t = 10 milliseconds, the inverter enters the steady-state low voltage ride-through control mode, where its output reactive current reaches 1.2 times the rated current as required by the grid, and the active current is limited to 0.4 times the rated current, with the total output current approximately 1.26 times the rated current.
[0073] Meanwhile, the instantaneous inrush current component generated by the discharge of the inverter's DC-side capacitor appears immediately after the fault occurs, with an initial amplitude of approximately 0.5 to 1.0 times the rated current and a decay time constant of approximately 8 milliseconds. This inrush current component is superimposed on the current during the control mode transition phase, forming the short-circuit current peak during the control mode switching process. The calculated total short-circuit current peak of the wind-solar power generation system is approximately 2.0 times the rated current, occurring within a time window of approximately 3 to 5 milliseconds after the fault occurs. The steady-state short-circuit current value is approximately 1.26 times the rated current, persisting until the fault is cleared.
[0074] After the calculation results are output to the relay protection setting system, the system automatically compares the calculated peak and duration values of the short-circuit current with the preset protection operating current settings. The total installed capacity of this wind and solar power system is 150 MW, with a power factor of approximately 0.98. The rated line voltage at the grid connection point is 110 kV, and its rated current is approximately 803 amps; when normally outputting 120 MW, the operating current is approximately 642 amps. The operating current setting of the 110 kV line protection device configured for this wind and solar power system is 400 amps, corresponding to approximately 0.5 times the rated current of 803 amps; the operating current setting of the instantaneous overcurrent protection is 1600 amps, corresponding to 2.0 times the rated current. Since the calculated peak short-circuit current is approximately 1606 amperes, which is close to the instantaneous overcurrent protection's operating current setting value of 1600 amperes, the protection setting system issues an alarm message, indicating to maintenance personnel that the sensitivity of the instantaneous overcurrent protection may be insufficient. It is recommended to appropriately increase the operating current setting value of the instantaneous overcurrent protection or add time-limited instantaneous overcurrent protection to ensure the selectivity of the protection.
[0075] The calculation results are simultaneously output to the power system stability assessment module for system transient stability simulation. Simulation results show that after the fault is cleared, the grid connection point voltage recovers to over 90% of the rated voltage within 0.5 seconds, the active power of the wind and solar power system recovers to 95% of the pre-fault level within 2 seconds, and the system frequency remains stable. The simulation results verify that the low-voltage ride-through performance of the wind and solar power system meets the grid connection specifications.
[0076] Example 2
[0077] To meet the engineering requirements for short-circuit current calculation in large-scale wind and solar power generation systems, this embodiment provides a short-circuit current calculation method based on a multi-region aggregation model. Building upon the basic method described in Embodiment 1, this method further addresses the characteristics of numerous inverters and their geographically dispersed locations in wind and solar power generation systems by introducing a multi-region aggregation processing mechanism to improve computational efficiency while maintaining sufficient computational accuracy.
[0078] The core idea of the multi-region aggregation model is to aggregate multiple inverter units that are geographically adjacent and have similar control characteristics into an equivalent inverter model. The aggregation process first divides the wind and solar power system into several geographical regions based on the electrical wiring diagram and geographical distribution map. Each region contains an equal or similar number of inverter units. The principles for region division include: using the collection line as the boundary, inverter units within the region share the same collection bus; using major equipment as a reference, the communication delay between inverter units within the region is within an acceptable range; and based on the control strategy, inverter units within the same region use the same control parameter configuration.
[0079] Taking a large-scale photovoltaic power plant as an example, its installed capacity is 500 MW, comprising 50 inverter units with a rated power of 10 MW each. Based on the distribution of the collection lines, the photovoltaic power plant can be divided into 5 power generation units, each containing 10 inverter units and a 35 kV collection bus. The 35 kV collection bus of the 5 power generation units is connected to a 110 kV step-up transformer via collection lines. After applying a multi-region aggregation model, the 50 inverter units are aggregated into 5 equivalent inverter models, each with a rated capacity of 100 MW. The parameter setting method for the equivalent inverter models is as follows: the average value of the parameters of each inverter unit within the region is taken as the parameters of the equivalent model. Simultaneously, considering the impact of parameter dispersion on the calculation results, Monte Carlo analysis of parameter uncertainty is introduced.
[0080] The short-circuit current calculation process for the multi-region aggregation model is the same as the basic process described in Example 1, except that the number of calculation objects is reduced from 50 to 5, improving the calculation efficiency by approximately 10 times. After the calculation is completed, the calculation errors generated by the aggregation model need to be corrected. The error correction methods include: calculating the statistical distribution of aggregation errors based on the parameter deviations between each inverter unit in the region and the equivalent inverter model; and applying a weighted correction to the output short-circuit current of the equivalent model based on the statistical distribution of aggregation errors. The correction coefficient ranges from 0.95 to 1.05, and the specific value is determined based on the mean and variance of the error distribution.
[0081] The handling of control mode switching in a multi-region aggregation model needs to consider the inconsistency of control mode states among inverter units within a region. Due to differences in local measurement data and communication delays among inverter units, different inverter units within a region may be in different control mode states. To address this inconsistency, the aggregation model employs a majority voting mechanism: the number of inverter units in each control mode state within a region is counted, and the control mode with the most occurrences is taken as the current control mode state of the equivalent inverter model; when the number of inverter units in different control mode states is equal, the lower-level control mode is taken as the current control mode state of the equivalent inverter model. The control mode levels, from highest to lowest, are standby mode, maximum power point tracking control mode, low voltage ride-through control mode, and constant power control mode.
[0082] The multi-region aggregation model short-circuit current calculation method provided in this embodiment significantly improves computational efficiency while ensuring calculation accuracy, and is suitable for online short-circuit current calculation applications in large-scale wind and solar power generation systems. Combined with the basic method described in Embodiment 1, this method can cover various application scenarios from small-scale distributed wind and solar power generation systems to large-scale centralized wind and solar power farms, demonstrating broad applicability and good engineering practical value.
[0083] Example 3
[0084] To meet the need for sharing and reusing short-circuit current calculation results across different power system analysis applications, this embodiment provides a method for outputting short-circuit current calculation results based on a standardized data interface. This method defines a standardized data model and interface protocol, ensuring that the short-circuit current calculation results can be correctly received and parsed by various application modules such as relay protection setting systems, power system stability assessment modules, and power grid dispatch automation systems.
[0085] The core data structure of the standardized data model includes the following components: The first part is fault event information, including fault occurrence timestamp, fault type identifier, fault location coordinates, fault duration, and fault clearing method; the second part is system operating condition information, including the total active power, total reactive power, power factor, control mode status of each inverter unit, and main meteorological parameters of the wind and solar power generation system before the fault; the third part is short-circuit current calculation results, including the instantaneous value sequence of each phase current at the grid connection point, the effective value sequence of three-phase current, zero-sequence current and negative-sequence current components, the model parameters and algorithm identifiers used in the calculation, and the confidence interval of the calculation results; the fourth part is metadata information, including data generation timestamp, data version number, calculation module identifier, and data integrity check code.
[0086] The data interface protocol supports both synchronous and asynchronous call modes. Synchronous call mode is suitable for applications with high real-time requirements, such as online verification of relay protection. After the caller sends a calculation request, it blocks and waits; the result is returned immediately upon completion, with a response latency of less than 100 milliseconds. Asynchronous call mode is suitable for batch calculations and historical data queries. After the caller sends a calculation request, it immediately returns a task identifier and then receives the calculation result through a callback function or message queue. The response latency can be relaxed to several seconds to several minutes. The data interface adopts a RESTful API design based on the HTTP protocol. Data serialization formats support JSON and XML, with the specific format specified by the Content-Type field in the request message header.
[0087] To ensure the reliability and integrity of data transmission, the standardized data interface also defines data compression, breakpoint resumption, and consistency verification mechanisms. Data compression uses the gzip algorithm, typically achieving a compression ratio of 3 to 5 times, effectively reducing network transmission overhead. The breakpoint resumption mechanism allows data transmission to resume from the point of interruption after a network outage, avoiding duplicate data transmission due to network failures. Consistency verification uses MD5 or SHA-256 algorithms to calculate the data digest. Upon receiving the data, the receiver calculates its local digest and compares it with the digest provided by the sender, ensuring that no errors or tampering occurred during data transmission.
[0088] The standardized data interface method provided in this embodiment, combined with the short-circuit current calculation methods described in Embodiments 1 and 2, constitutes a complete solution for short-circuit current calculation and result application in wind and solar power generation systems. This solution can meet the technical requirements of multi-system collaboration, data sharing, and business integration in the context of power system digital transformation, and has good interoperability and scalability.
[0089] The technical solutions of the present invention are not limited to the specific embodiments described above. Any technical modifications made in accordance with the technical solutions of the present invention fall within the protection scope of the present invention.
Claims
1. A method for calculating the short-circuit current of a wind and solar power generation system considering control switching, characterized in that, Includes the following steps: Step 1: Collect real-time operating data of the wind and solar power generation system grid connection point, including voltage and current values, and at the same time obtain the current control mode status information of the inverter; Step 2: Based on the collected grid connection point voltage value, determine whether a voltage drop to the preset low voltage ride-through trigger threshold has occurred. When the voltage drops below the low voltage ride-through trigger threshold, determine that the wind and solar power generation system needs to switch from the maximum power point tracking control mode to the low voltage ride-through control mode. Step 3: Establish inverter current output characteristic models under different control modes: in, This represents the inverter output current command value in maximum power point tracking control mode. This represents the maximum power point power value under the current environmental conditions. This indicates the DC-side voltage of the inverter. This represents the maximum power point tracking current command correction factor, which is dimensionless and determined based on the maximum power point tracking controller gain. Under low voltage ride-through control mode, the inverter current output characteristic model is as follows: in, This is the reactive current command value output by the inverter under low voltage ride-through control mode, in amperes (A). The low-voltage ride-through reactive power support factor is dimensionless and ranges from 1.0 to 2.
0. This is the rated current of the inverter, in amperes (A). This is the effective value of the grid connection point voltage, in V; This is the rated voltage value, in volts (V). This represents the upper limit of the active current command value, in amperes (A). This is the rated maximum value of the inverter output current, expressed in amperes (A). The imaginary unit; This is the inverter output current command value under low voltage ride-through control mode, in A. This is the low-voltage ride-through trigger threshold, in V; Step 4: Based on the control mode switching judgment result, establish a short-circuit current calculation model that takes into account the control switching process: When hour: when hour: when hour: in, The short-circuit current injected into the power grid at the grid connection point of the wind and solar power generation system, expressed in amperes (A). This refers to the moment when the control mode switch occurs; The current command value in the maximum power point tracking control mode before switching; This is the steady-state current command value in the low-voltage ride-through control mode after switching; The time constant of the first-order inertial element is expressed in seconds and is determined based on the bandwidth of the inverter's inner current loop controller, with a value ranging from 5 milliseconds to 20 milliseconds. This refers to the duration of the control mode switching transition process; To switch the instantaneous inrush current component generated by the discharge of the DC-side capacitor in the instantaneous inverter, and in, To switch the initial amplitude of the instantaneous capacitor discharge surge current; This is the capacitor discharge decay time constant; This is the capacitance value of the DC-side capacitor; This is the magnitude of the inverter's equivalent impedance; Step 5: Output the short-circuit current calculation results obtained in Step 4 for power system analysis applications.
2. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, In step 1, the sampling period for collecting real-time running data is no more than 1 millisecond, which is used to meet the time resolution requirements for capturing the dynamic switching process of the control strategy.
3. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, In step 2, the trigger threshold for low voltage ride-through is set to 0.85 to 0.9 times the rated voltage, with the specific value determined according to the grid access specifications and the grid connection technical requirements of the wind and solar power generation system.
4. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, Step 2 also includes setting hysteresis control logic for determining control mode switching. The hysteresis width is set to 0.02 times the rated voltage to avoid frequent switching of control modes near the voltage boundary.
5. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, In step 3, the inverter current output characteristic model under the maximum power point tracking control mode uses the perturbation observation method or the incremental conductance method to determine the current command value corresponding to the current maximum power point, and considers the dynamic influence of changes in light intensity or wind speed on the position of the maximum power point; the inverter current output characteristic model under the low voltage ride-through control mode calculates the required reactive current injection according to the reactive current to voltage drop ratio based on the reactive current support requirements during grid faults, while limiting the active current output to avoid DC side overvoltage.
6. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, In step 4, the time constant of the first-order inertial element is determined based on the bandwidth of the inverter current inner loop controller, and the value ranges from 5 milliseconds to 20 milliseconds. The specific value is obtained through frequency response testing of the inverter control system. The short-circuit current calculation during the control mode switching process considers the instantaneous impact current component generated by the discharge of the inverter DC-side capacitor during the switching instant. This component decays exponentially, and the decay time constant is the product of the DC-side capacitor and the inverter equivalent impedance. The steady-state short-circuit current calculation after the switching is completed takes into account the limiting characteristics of the inverter output current under the low voltage ride-through control mode. The limiting value is determined according to the maximum fault current injection multiple required by the power grid specifications.
7. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, Step 5 also includes comparing the short-circuit current calculation result with the preset relay protection setting threshold. When the calculated short-circuit current value exceeds the operating current range of the relay protection device, a corresponding alarm message is given.
8. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, It also includes establishing a short-circuit current calculation database for wind and solar power generation systems to store short-circuit current calculation results under different operating conditions and different control mode switching scenarios, and optimizing the parameter settings of the short-circuit current calculation model through statistical analysis of historical data.
9. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 6, characterized in that, In step 4, the short-circuit current calculation adopts the multi-region aggregation model method, which aggregates multiple inverter units that are geographically adjacent and have similar control characteristics into an equivalent inverter model for short-circuit current calculation, and considers Monte Carlo analysis of parameter uncertainty. In the multi-region aggregation model, when there are inconsistencies in the control mode states of each inverter unit within a region, a majority voting mechanism is used to determine the current control mode state of the equivalent inverter model.
10. The method for calculating the short-circuit current of a wind and solar power generation system considering control switching as described in claim 1, characterized in that, The output of the short-circuit current calculation result in step 5 adopts a standardized data model and interface protocol. The data model includes fault event information, system operating condition information, short-circuit current calculation result and metadata information. The interface protocol supports both synchronous and asynchronous call modes, and employs data compression and consistency verification mechanisms to ensure the reliability of data transmission.