A method, apparatus, equipment, medium, and product for multi-energy complementary coordinated optimization scheduling.
By constructing a multi-energy complementary coordinated optimization scheduling model, the prediction deviation of wind and solar power output is corrected in real time, linking peak-shaving responsibility with economic initiative, solving the problem of insufficient anti-peak-shaving and flexible adjustment capabilities caused by the high proportion of new energy access, and stimulating the enthusiasm of generating units to consume energy.
Patent Information
- Application Number
- CN202611252015.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-18
- Publication Date
- 2026-11-10
AI Technical Summary
The high proportion of renewable energy access leads to insufficient anti-peak shaving and flexible adjustment capabilities, while existing adjustment resources are unevenly distributed and peak shaving entities lack enthusiasm.
A multi-entity source-grid-load-storage multi-energy complementary model is constructed. By leveraging the profit margin of peak shaving initiative, day-ahead and intraday rolling scheduling is carried out, and the wind and solar power output forecast deviation is corrected in real time. This model links peak shaving responsibility, economic initiative, and physical regulation capabilities to achieve optimized scheduling across multiple time scales.
This significantly expands the grid connection space for new energy sources, effectively offsets the peak-shaving characteristics of new energy sources, solves the problem of insufficient flexible adjustment capacity caused by a high proportion of new energy connections, and stimulates the enthusiasm of generating units for auxiliary consumption.
Smart Images

Figure CN123073973A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of power system optimization dispatching, and in particular to a multi-energy complementary coordinated optimization dispatching method, device, equipment, medium and product. Background Technology
[0002] Currently, the grid connection rate of renewable energy sources such as wind power and solar power is continuously increasing. However, due to the significant anti-peak-shaving and uncertain characteristics of wind and solar power output, the peak-valley difference in load is widened. This dual pressure from source and load greatly increases the peak-shaving burden on the power system. Against this backdrop, fully exploring the flexible adjustment capabilities of source, load, and storage, and establishing a multi-source complementary coordination mechanism, has become crucial to ensuring the high proportion of renewable energy consumption.
[0003] In the existing regulatory resources, thermal power units undertaking deep peak shaving tasks has gradually become the norm. However, in actual operation, deep peak shaving of thermal power not only faces the problems of reduced energy efficiency and worsened economics, but also involves complex interest distribution. Some researchers have analyzed the economics of deep peak shaving scheduling schemes for thermal power units under large-scale wind power grid connection from multiple perspectives, but the coal consumption models they used did not consider the coal consumption characteristics of the units during deep peak shaving, which differs from the actual situation. Other researchers have proposed a joint optimization scheduling model of hydropower and thermal power with clean energy priority, but it is mostly based on conventional peak shaving characteristics and fails to fully consider the randomness of wind power output, thus failing to accurately reflect the actual coal consumption and oil injection costs of the units under deep peak shaving operation.
[0004] In addition, the flexible adjustment of the complementary role of power sources has also been a research hotspot in recent years. The main implementation methods include: establishing a dynamic economic dispatch model for the joint output of multiple power sources, but the effect on changing the peak-valley difference of load is limited; using wind-storage combined systems for peak shaving and valley filling, but its regulation effect is limited by the installed capacity of pumped storage; using energy storage to assist the deep regulation of thermal power in a hierarchical dispatch strategy, but the current compensation mechanism often ignores the quantification of the actual contribution of each entity to the system's peak shaving; proposing a peak shaving cost sharing method, most of which are based on game theory and rarely take into account the actual peak shaving capacity of participating units, making it difficult to reflect the fairness of system peak shaving, resulting in low enthusiasm of entities to participate in peak shaving.
[0005] Therefore, it is urgent to solve the problem of insufficient peak-shaving and flexible adjustment capabilities caused by the high proportion of renewable energy access. Summary of the Invention
[0006] The purpose of this application is to provide a multi-energy complementary coordinated optimization scheduling method, device, equipment, medium and product that can solve the problems of insufficient anti-peak shaving and flexible adjustment capabilities caused by a high proportion of new energy access.
[0007] To achieve the above objectives, this application provides the following solution: Firstly, this application provides a multi-energy complementary coordinated optimization scheduling method, including: Based on the multi-energy complementary model of source-grid-load-storage involving multiple entities, the net load sequence of each grid bus node and the power sequence of each entity are determined for each time period within the current rolling window. The cost allocation results for each entity are determined based on the power sequence, the net load sequence, and the predicted power deviation of new energy output. The proactive profit margin for peak shaving is determined based on the segmented comprehensive cost incurred by thermal power units when undertaking peak shaving tasks, the cost allocation results, and the proactive profit margin model for peak shaving of thermal power units. Based on the aforementioned proactive peak-shaving profit margin, day-ahead and intraday rolling scheduling is performed. During the day-ahead phase, the start-up and shutdown of generating units, the benchmark output for peak shaving, and the energy storage target are determined. During the intraday phase, the available power of new energy sources is updated, and the output of thermal power, hydropower, and generalized energy storage is adjusted on a rolling basis. When the proactive peak-shaving profit margin is insufficient, compensation price feedback, energy storage target reconstruction, or hydropower output substitution and reservoir capacity status feedback are performed. The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
[0008] Secondly, this application provides a multi-energy complementary coordinated optimization scheduling device, comprising: The data generation module is used to determine the net load sequence of each grid bus node and the power sequence of each entity in each time period within the current rolling window, based on a multi-entity source-grid-load-storage multi-energy complementary model that includes multiple entities. The cost allocation result determination module is used to determine the cost allocation result of each entity based on the power sequence, the net load sequence, and the predicted power deviation of new energy output. The peak-shaving initiative profit margin determination module is used to determine the peak-shaving initiative profit margin based on the segmented comprehensive cost incurred by the thermal power unit when undertaking peak-shaving tasks, the cost allocation result, and the thermal power unit peak-shaving initiative profit margin model. The day-ahead-intraday rolling scheduling module is used to perform day-ahead-intraday rolling scheduling based on the aforementioned proactive peak-shaving profit margin. During the day-ahead phase, it determines the unit start-up and shutdown, peak-shaving benchmark output, and energy storage targets. During the intraday phase, it updates the available power of new energy sources, and makes rolling corrections to the output of thermal power, hydropower, and generalized energy storage. When the proactive peak-shaving profit margin is insufficient, it provides compensation price feedback, energy storage target reconstruction, or hydropower output substitution, as well as reservoir capacity status feedback. The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
[0009] Thirdly, this application provides a computer device, including: a memory, a processor, and a computer program stored in the memory and capable of running on the processor, wherein the processor executes the computer program to implement the multi-energy complementary coordinated optimization scheduling method described above.
[0010] Fourthly, this application provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the multi-energy complementary coordinated optimization scheduling method described above.
[0011] Fifthly, this application provides a computer program product, including a computer program that, when executed by a processor, implements the multi-energy complementary coordinated optimization scheduling method described above.
[0012] According to the specific embodiments provided in this application, this application has the following technical effects: This application provides a multi-energy complementary coordinated optimization scheduling method, device, equipment, medium, and product. By constructing a multi-entity source-grid-load-storage multi-energy complementary model, it fully explores the regulation potential of the source, load, and storage sides. Based on the profit margin of peak-shaving initiative, it performs day-ahead and intraday rolling scheduling. Through day-ahead and intraday two-stage rolling optimization, it corrects the prediction deviation of wind and solar power output in real time, transforming the traditional source-follow-load dynamic into source-load-storage coordinated regulation, significantly releasing the space for new energy grid connection, and effectively offsetting the anti-peak-shaving characteristics of new energy. This application links peak-shaving responsibility, economic initiative, and physical regulation capacity, and solves the problems of insufficient anti-peak-shaving and flexible regulation capacity caused by high proportion of new energy grid connection through day-ahead and intraday multi-timescale rolling optimization. Attached Figure Description
[0013] To more clearly illustrate the technical solutions in the embodiments of this application or related technologies, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0014] Figure 1 A flowchart illustrating a multi-energy complementary coordinated optimization scheduling method provided in an embodiment of this application; Figure 2 This is a schematic diagram of peak shaving for thermal power units provided in an embodiment of this application; Figure 3 This is a schematic diagram of the day-to-day scheduling framework provided in the embodiments of this application; Figure 4 This is a schematic diagram of day-to-day rolling optimization provided in the embodiments of this application; Figure 5This application provides a topology diagram of an IEEE 30-node system. Figure 6 A schematic diagram of energy storage output every 15 minutes provided for an embodiment of this application; Figure 7 A schematic diagram of wind, solar and load forecast results at 15-minute intervals provided for an embodiment of this application; Figure 8 A schematic diagram of the wind, solar, hydro, thermal and energy storage scheduling results every 15 minutes, considering peak-shaving characteristics, provided for an embodiment of this application. Figure 9 A schematic diagram of the wind, solar, hydro, thermal and energy storage scheduling results every 15 minutes without considering peak-shaving characteristics, provided for an embodiment of this application; Figure 10 A schematic diagram of the functional modules of a multi-energy complementary coordinated optimization scheduling device provided in an embodiment of this application; Figure 11 This is a schematic diagram of the structure of a computer device provided in an embodiment of this application. Detailed Implementation
[0015] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0016] This application provides a multi-energy complementary coordinated optimization scheduling method, device, equipment, medium, and product, taking into account peak-shaving initiative. First, a generalized multi-energy complementary model is constructed, encompassing wind, solar, hydro, thermal power, and integrated electrochemical energy storage with demand-side resilient loads, providing multi-dimensional regulation support. Second, a sharing compensation mechanism is established based on the impact coefficient of quantified peak-shaving contribution to address the issue of unfair sharing. Third, by coupling deep-shaving costs, an initiative constraint is constructed, transforming external incentives into endogenous motivation and stimulating the enthusiasm of generating units for auxiliary consumption. Finally, a two-stage rolling optimization architecture (day-ahead and intraday) is adopted to adjust output with the goal of maximizing renewable energy consumption. This application effectively solves the problems of insufficient anti-peak-shaving and flexible regulation capabilities caused by high-proportion renewable energy access through the coordination of deep-shaving of thermal power and generalized energy storage across multiple time scales.
[0017] To make the above-mentioned objectives, features and advantages of this application more apparent and understandable, the application will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0018] In one exemplary embodiment, such as Figure 1 As shown, a multi-energy complementary coordinated optimization scheduling method is provided, including: Step 101: Based on the multi-energy complementary model of source-grid-load-storage involving multiple entities, determine the net load sequence of each grid bus node and the power sequence of each entity in each time period within the current rolling window.
[0019] Step 102: Determine the cost allocation results for each entity based on the power sequence, the net load sequence, and the predicted power deviation of new energy output.
[0020] Among them, the predicted power deviation of new energy output is the deviation between the available power of new energy obtained in the previous rolling window and the actual available power in the current rolling window.
[0021] Specifically, peak and valley periods are divided according to power sequence and net load sequence. Dynamic peak shaving impact coefficients are constructed based on the output differences of each entity during peak and valley periods, prediction deviations, and peak shaving sensitivity of the nodes. The cost allocation results of each entity are determined based on the dynamic peak shaving impact coefficients.
[0022] Step 103: Determine the proactive profit margin for peak shaving based on the segmented comprehensive cost incurred by the thermal power unit when undertaking peak shaving tasks, the cost allocation results, and the proactive profit margin model for peak shaving of the thermal power unit.
[0023] The segmented comprehensive cost includes coal consumption, lifespan loss, and oil injection for stable combustion.
[0024] Step 104: Based on the aforementioned proactive peak-shaving profit margin, perform day-ahead and intraday rolling scheduling. During the day-ahead phase, determine unit start-up and shutdown, peak-shaving benchmark output, and energy storage targets. During the intraday phase, update the available power of new energy sources, and continuously adjust the output of thermal power, hydropower, and generalized energy storage. When the proactive peak-shaving profit margin is insufficient, provide compensation price feedback, reconstruct energy storage targets, or substitute hydropower output and provide reservoir capacity status feedback. Input the scheduling results of the current rolling window into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
[0025] The scheduling results include: unit start-up and shutdown, peak-shaving benchmark output, energy storage target, thermal power output, hydropower output, generalized energy storage output, peak-shaving compensation price, and reservoir capacity status.
[0026] In this embodiment, step 101 maps the output and constraints of each resource to the node power balance equation through the source-grid-load-storage multi-energy complementary model, outputting various power sequences and net load sequences. Steps 102-104 calculate peak-shaving responsibility, calculate proactive profit, and execute optimized scheduling, linking peak-shaving responsibility, economic initiative, and physical regulation capability. Through rolling optimization at multiple time scales from day-ahead to intraday, the problem of insufficient anti-peak-shaving and flexible regulation capability caused by high proportion of new energy access is solved.
[0027] In another exemplary embodiment of this application, the multiple entities include: wind power, photovoltaic power, hydropower, thermal power, electrochemical energy storage, and demand-side resilient loads; generalized energy storage includes: electrochemical energy storage and demand-side resilient loads. The source-grid-load-storage multi-energy complementary model refers to a simulation calculation model that, for regional power systems, uniformly models multiple entities on the power generation side, grid side, load side, and energy storage side to achieve synergistic and mutually supportive effects among multiple types of energy resources. In the source-grid-load-storage multi-energy complementary model, the source refers to various power generation entities, the grid refers to the grid topology and node constraints, the load refers to node-side loads, and the storage refers to generalized energy storage entities. The source-grid-load-storage multi-energy complementary model achieves mutual compensation of output characteristics among different entities. The source-grid-load-storage multi-energy complementary model also outputs the available new energy power, adjustable range of thermal power, adjustable range of hydropower, adjustable capacity of generalized energy storage, and equivalent load for each node at each time period.
[0028] In another exemplary embodiment of this application, the method for constructing the source-grid-load-storage multi-energy complementary model includes: A four-stage peak-shaving output characteristic model for thermal power units is constructed. The four stages include: unit shutdown stage, deep oil injection peak-shaving stage, non-oil injection deep peak-shaving stage, and conventional peak-shaving stage. The four-stage peak-shaving output characteristic model includes a thermal power peak-shaving output model and a segmented comprehensive cost calculation model. The conventional peak-shaving stage, also known as the non-deep peak-shaving stage, represents the basic peak-shaving capability that the unit should inherently possess. The output in this stage is between the unit's maximum output and the minimum output for conventional peak-shaving (i.e., the lower limit of conventional peak-shaving). The deep peak-shaving stage includes: deep oil injection peak-shaving stage and non-oil injection deep peak-shaving stage, which are divided by the lower limits of conventional peak-shaving, non-oil injection deep peak-shaving, and oil injection deep peak-shaving.
[0029] A generalized energy storage regulation support model is constructed; the generalized energy storage regulation support model includes: an adjustable capacity model of electrochemical energy storage and demand-side resilient load, a physical constraint model of electrochemical energy storage, and an equivalent load model of demand-side resilient load response.
[0030] Construct wind, solar and hydropower output models; the wind, solar and hydropower output models include: wind power output model, photovoltaic power output model and hydropower output model.
[0031] Based on the four-stage peak-shaving output characteristic model of the thermal power unit, the generalized energy storage regulation support model, and the wind, solar and hydropower output model, a multi-energy coordinated balance model that satisfies the spatial coupling of source-grid-load-storage is constructed, and the multi-energy coordinated balance model is determined as the source-grid-load-storage multi-energy complementary model.
[0032] As an optional implementation, step 101 maps the output and constraints of each resource to a node power balance equation, and the output power sequences and net load sequences serve as inputs for step 102 to calculate peak-shaving responsibility, step 103 to calculate proactive profit, and step 104 to execute optimized scheduling. The specific method for constructing the source-grid-load-storage multi-energy complementary model is as follows.
[0033] (1) Four-stage peak-shaving output characteristic model of conventional thermal power units.
[0034] according to Figure 2 The operating states of thermal power units are divided into shutdown stage, deep oil injection peak shaving stage, no oil injection deep peak shaving stage, and conventional peak shaving stage. The peak shaving output model for thermal power is as follows: (1) In the formula, , represents the start-up and shutdown status of the i-th thermal power unit; Let be the output of the i-th thermal power unit during time period t; , , For the i-th thermal power unit, the conventional peak shaving lower limit, the non-oil injection deep adjustment lower limit, and the oil injection deep adjustment lower limit are: This is the shutdown phase; and This is during the peak-shaving phase of oil injection. This is during the period of deep peak shaving without oil injection; when This is during the regular peak-shaving period. The corresponding segmented comprehensive cost (peak-shaving cost) calculation model is as follows: (2) In the formula Let be the segmented comprehensive cost of the i-th thermal power unit during time period t. P G,i,min and P G,i,max Let be the minimum and maximum output of the i-th thermal power unit; This represents the coal consumption cost of a conventional unit. P G For thermal power units; Costs associated with rotor life loss due to deep peak shaving; C oil To stabilize fuel costs through deep peak shaving and oil injection; C off,i,t Let be the downtime cost of the i-th thermal power unit during time period t.
[0035] To characterize the overall cost change of thermal power units after entering the deep peak-shaving range from the conventional peak-shaving range, the lower limit of conventional peak-shaving is used. Based on the corresponding operating cost, the change in the overall cost of deep peak shaving is defined as: (3) In the formula, This represents the change in the overall cost of the i-th thermal power unit after it enters deep peak shaving during time period t. The segmented comprehensive cost corresponding to the actual operating output of the unit; This represents the baseline comprehensive cost when the unit operates at the lower limit of normal peak shaving. When P G,i,t >P a,i At that time, the unit had not entered the deep adjustment range. .
[0036] (2) Generalized energy storage regulation support model.
[0037] Generalized energy storage consists of physical energy storage and demand-side resilient loads. The adjustable capacity model is as follows: (4) In the formula, This provides upscaling capacity for generalized energy storage; This refers to the down-regulation capacity that can be provided for generalized energy storage; For load nodes n exist t Time-based load shedding; For load nodes n exist t The load factor during a given time period; The maximum discharge power of energy storage e during time period t; The maximum charging power of energy storage e during time period t; e Number the energy storage device.
[0038] The physical constraint model for electrochemical energy storage is as follows: (5) (6) Demand-side resilient loads based on price incentives provide bidirectional adjustment support, and their equivalent load model for load response is as follows: (7) In the formula: L eq,t Equivalent load; L base,t Basic load; Δ L re,t This represents the power transfer from resilient loads driven by time-of-use pricing, serving as virtual energy storage. SOC t for t State of charge of energy stored over a period of time; SOC min and SOC maxThese represent the minimum and maximum states of charge for energy storage. E e This refers to the rated capacity of the energy storage. η c , η d For charge / discharge efficiency; I ch,t , I dis,t This refers to the energy storage charge / discharge coefficient. Δ L DR,t for t The response offset of the time-dependent resilient load, with positive values indicating increased load and negative values indicating decreased load; ΔL DR,min and Δ L DR,max for t Minimum and maximum response offsets under time-dependent toughness loads; P ch,t , P dis,t For energy storage charging and discharging power; P ch,t,min , P dis,t,max This represents the minimum and maximum charging and discharging power for energy storage.
[0039] (3) Wind, solar and hydropower output model.
[0040] Wind power, photovoltaic power, and hydropower not only participate in node power balance as power sources, but also contribute to the system's peak-shaving support capacity through available output, actual grid-connected power, curtailed wind and solar power, and adjustable hydropower output. Among them, wind power and photovoltaic power mainly affect the system's net load through predictable output, limited generation space, and surplus new energy consumption demand; hydropower relies on reservoir capacity, power generation flow, and output adjustment range to provide the ability to quickly adjust upward, downward, and replace deep adjustment of thermal power. Its hydropower output substitution and reservoir capacity status feedback are shown in equations (31) and (32).
[0041] ① Wind power output model.
[0042] Wind power output should not be considered as a single variable, but rather modeled as a function affected by the randomness of wind speed, with the wind speed-power conversion curve as follows: (8) wind speed v follow Weibull Distribution, and then introducing prediction bias. , Constructing credibility constraints for wind power integration: (9) In the formula: This is the wind speed-power conversion function; Let be the wind speed probability density function; v in , v out , v rat The cut-in wind speed, cut-out wind speed, and rated wind speed are specified. P w,rat Rated wind power; v i,t for t Periodic wind farm i wind speed; for t Periodic wind farm i The predicted power; k , c for Weibull The shape and scale parameters of the distribution v This refers to wind speed.
[0043] ② Photovoltaic power output model.
[0044] Photovoltaic output is significantly affected by the environment. The usable photovoltaic output after taking into account irradiance and temperature compensation is: (10) In the formula: λ t The power temperature coefficient; G t , G STC The actual light irradiance under standard conditions at the given time; P STC This represents the maximum power under standard test conditions. α , β for Beta Distribution shape parameters; T t , T STC The actual ambient temperature and the standard battery temperature; It is the probability density function; This is a Beta function.
[0045] The system requires priority to utilize wind and solar resources, but its actual grid-connected power is constrained by the predicted upper limit: (11) In the formula: for t Available photovoltaic power output during certain periods; for t Available wind power output during certain periods; fort Periodic photovoltaic j The predicted power; for t Time-of-use wind power i The predicted power.
[0046] ③ Hydropower station output model under water conservancy linkage (hydropower output model).
[0047] The hydropower output model needs to consider the spatiotemporal dynamic balance of flow rate and water level to achieve hydropower complementarity. Its hydropower output is: (11) In the formula: The efficiency coefficient of the hydro-generator; ρ The density of water; g It is the acceleration due to gravity; H h,t Effective head height; q h,t This refers to the power generation flow rate.
[0048] Reservoir water balance constraints: (13) Head and flow constraints: (14) In the formula: V h,t Real-time reservoir capacity; V h,min , V h,max The minimum and maximum reservoir capacities; q h,min , q h,max For minimum and maximum power generation flow rates; I h,t This refers to the natural inflow of water into the reservoir. S h,t This refers to the amount of water discarded.
[0049] ④ Balance of source-grid-load-storage nodes.
[0050] By integrating electrochemical energy storage and resilient load, a multi-energy coordinated balance model that satisfies the spatial coupling of source-grid-load-storage is constructed: (15) In the formula: M G , M H , M w , M pv ,M e This is a node association matrix for thermal power, hydropower, wind power, photovoltaic, and energy storage. L eq,t Equivalent load; B bus Here is the nodal admittance matrix; The node voltage phase angle vector; This represents the actual grid-connected power of the wind power. This represents the actual grid-connected power of the photovoltaic system. This represents the output of the thermal power unit during time period t. This represents the power output of the hydropower station during time period t.
[0051] In another exemplary embodiment of this application, step 102 specifically includes: dividing peak periods, valley periods, and flat periods according to the power sequence and the net load sequence; constructing a dynamic peak-shaving influence coefficient based on the output differences of each entity during peak, valley, and flat periods, the predicted power deviation of new energy output, and the peak-shaving sensitivity of the node; determining a deep peak-shaving compensation pool based on the actual paid peak-shaving electricity of thermal power units entering the deep peak-shaving range; and determining the cost-sharing result of each entity based on the dynamic peak-shaving influence coefficient and the deep peak-shaving compensation pool.
[0052] As an optional implementation, a more specific process for step 102 is as follows: (1) Using the net load sequence generated in step 101 and the output (power sequence) of each main body as input, calculate the net load and divide the peak, valley and normal periods: (16) N t Let t be the net system load during time period t; according to N t The quantiles or scheduling rules determine the set of peak periods. T peak Valley period collection T valley Peacetime assembly T flat For the main body m The expression for the dynamic peak-shaving impact coefficient is: (17) in, Representing the subject The dynamic peak-shaving impact coefficient; Representing the subject The contribution of reverse peak shaving caused by high incidence during trough periods and low incidence during peak periods; Representing the subject The degree of mismatch between the output curve and the net load curve; This indicates the extent to which forecast deviations affect peak-shaving reserves. Representing the subject The topology sensitivity of the node to the system's ability to downgrade or upgrade; , , and The corresponding weights; This is the normalization function.
[0053] (2) Determine the deep peak-shaving compensation pool.
[0054] The deep peak-shaving compensation pool is determined by the actual paid peak-shaving electricity generated by thermal power units entering the deep peak-shaving range. The expression for the deep peak-shaving compensation pool is: (18) in, This refers to the total compensation pool fee for system deep peak shaving during the trading day; The unit price for deep peak shaving compensation; For the first i The lower limit of conventional peak shaving for thermal power units in Taiwan; For the first i The actual output of the thermal power units in Taiwan during time period t (deep peak shaving phase); This refers to reducing the power output of the generating unit by a deeper peak shaving operation relative to the lower limit of conventional peak shaving. This refers to the collection of thermal power units currently in a deep peak-shaving state. Duration of the current scheduling period This is the lower limit of the conventional peak-shaving capacity for the i-th thermal power unit; Let i be the i-th thermal power unit. C D,t In the day-ahead phase, a pre-compensation pool is calculated based on the adjustable range of thermal power and the initial output plan output in step 101; in the intraday rolling phase, the pool is calculated based on the actual corrections made in step 104. It is updated on a rolling basis.
[0055] (3) Establish a cost-sharing model based on the impact coefficient.
[0056] Cost allocation uses a weighted allocation system comprised of an impact coefficient, electricity consumption, and a penalty factor. The total compensation cost will be... C D,t The impact of peak shaving on electricity consumption is allocated according to the peak shaving impact coefficient and the proportion of electricity generated by each entity. m The cost to be shared by each entity is as follows: (19) in, This represents the cost allocation result for the m-th entity during time period t. The amount of electricity generated by the main body m during the time period t or scheduling cycle; The penalty factor for the main unit m during the t period is divided into multiple tiers based on the unit load rate. When the unit load rate is high and refuses to execute the downward adjustment instruction, its penalty coefficient is increased, and its cost allocation base is increased, forcing it to actively adjust downward. j Sum index for the main body; , , , and Indexes for wind power, photovoltaic power, electrochemical energy storage, thermal power, and hydropower, respectively. The dynamic peak-shaving impact coefficient of the main body m during the time period t; For traversing the main body j The dynamic peak-shaving coefficient; For traversing the main body j The amount of electricity used for internet access; For traversing the main body j The depth assessment penalty factor. The result of Equation (18) is used as the input of the proactive profit margin of thermal power units in step 103, and also as the economic parameter of the day-ahead objective function and intraday feedback correction in step 104.
[0057] In another exemplary embodiment of this application, step 103 specifically includes: Couple the segmented comprehensive cost of the thermal power unit obtained in step 101 (formula (2)) with the compensation and allocation results obtained in step 102 (formula (18)) to analyze whether the compensation is sufficient to incentivize the thermal power unit to actively engage in deep peak shaving. For the i-th thermal power unit, the profit margin for peak shaving initiative is: (20) in, , For the first i The change in the overall cost of a thermal power unit after entering deep peak shaving in time period t (relative to the lower limit of deep peak shaving without oil injection). (deep adjustment of new costs); The profit margin for the peak-shaving initiative of the i-th thermal power unit during time period t; The deep peak-shaving compensation obtained by the i-th thermal power unit during time period t; This represents the actual output of the i-th thermal power unit during time period t. This is the lower limit of the conventional peak-shaving capacity for the i-th thermal power unit; For the first i The segmented comprehensive cost corresponding to the actual operating output of the thermal power unit; For the first i The benchmark comprehensive cost of a thermal power unit operating at the lower limit of conventional peak shaving; The feed-in tariff for time period t is used to calculate the opportunity gain loss corresponding to the reduced power generation. The duration of the current scheduling period; This represents the cost allocation result (cost allocation amount) of the i-th thermal power unit during time period t. The unit price for deep peak shaving compensation during period t. This refers to the opportunity revenue loss corresponding to the reduced power generation.
[0058] Set the minimum proactive profit margin as Π min When Π G,i,t ≥Π min Let the peak-shaving initiative state variable of the i-th thermal power unit be... A G,i,t =1 indicates that the i-th thermal power unit is allowed to use the deep peak shaving interval, and its effective output lower limit is reduced to 1. P c,i When Π G,i,t <Π min season A G,i,t =0 indicates that the unit is not allowed to perform deep peak shaving that is not economical, and the lower limit of the effective output of the thermal power unit is restored to P a,i, And initiate a compensation price feedback adjustment, using the following formula: (twenty one) (twenty two) In the formula: This is the lower limit of the unit's effective output. This is the maximum output of the unit; For the revised version t Time-based peak shaving compensation price; p peak,t for t Time-based peak shaving compensation price; The larger the value of the compensation price feedback adjustment coefficient, the greater the increase in the compensation price when the profit of thermal power peak shaving is insufficient. This represents a profit shortfall for thermal power units. Deep peak-shaving power supply for thermal power units; , To compensate for the lower and upper limits of the price. It is a very small positive number, used to prevent the denominator from being 0.
[0059] The compensation price feedback adjustment coefficient The basic feedback coefficient is determined based on historical operating data and actual intraday operating conditions. First, a sensitivity analysis is conducted based on historical deep peak-shaving compensation prices, thermal power deep-shaving costs, and proactive profit margins to determine the fundamental feedback coefficient. During intraday operation, the basic feedback coefficient is adjusted based on the proactive profit gap and the system's remaining peak-shaving demand. (twenty three) In the formula, ∈[0.1,0.2] represents the basic feedback adjustment coefficient of the compensation price; , These are the upper and lower limits of the feedback adjustment coefficient; ∈[0,0.2] represents the adjusted weight corresponding to the proactive profit gap; ∈[0,0.2] represents the corrected weight corresponding to the remaining peak-shaving demand of the system; The proactive profit gap rate; This is the ratio of remaining peak-shaving demand to the system's available flexible adjustment capacity. This refers to the peak-shaving power that needs to be borne by other resources after insufficient initiative. This provides downward absorption capacity for generalized energy storage; The compensation price adjustment capability available for hydropower will be stopped when the compensation price reaches its upper limit, the proactive profit margin reaches its lower limit, or the number of feedback times reaches its upper limit.
[0060] When the proactive profit margin of a thermal power unit falls below a preset lower limit, the deep peak-shaving compensation price is first adjusted according to the compensation price feedback formula, and the unit's proactive profit margin is recalculated. If the adjusted profit margin reaches the preset lower limit, the unit is allowed to enter the deep peak-shaving range. If the compensation price reaches the upper limit or the proactive profit margin remains below the preset lower limit after completing a preset number of feedback cycles, the proactive state variable is reset. =0, and restore the effective output lower limit of thermal power units to the normal peak-shaving lower limit. The resulting surplus peak-shaving demand is subsequently borne by generalized energy storage and hydropower. Therefore, equation (20) is not only an economic evaluation indicator, but also directly affects the feasible domain and resource allocation order of intraday scheduling.
[0061] In another exemplary embodiment of this application, step 104 uses the proactive profit margin for peak shaving as a feasibility criterion and feedback adjustment amount for day-ahead-intraday rolling scheduling. Step 104 specifically includes: In the day-ahead phase, the first step is to solve the day-ahead global pre-schedule model based on the day-ahead forecasts of wind power, solar power, hydropower, and load sequences, as well as the operating parameters of thermal power units and generalized energy storage resources. This determines the start-up and shutdown status of thermal power units, the benchmark output for peak shaving of thermal power units, and the target SOC of energy storage. Based on this, when the output of a thermal power unit to be scheduled is lower than the conventional peak shaving lower limit and a deep peak shaving interval is required, it is determined whether the proactive profit margin for peak shaving of the thermal power unit is not lower than the set minimum proactive profit margin. If this condition is met, the thermal power unit is allowed to use the deep peak shaving output interval, but it is not mandatory for the unit to enter the deep peak shaving interval. If the proactive profit margin for peak shaving is lower than the set minimum proactive profit margin, the thermal power unit is temporarily not allowed to perform uneconomical deep peak shaving, its effective output lower limit is restored to the conventional peak shaving lower limit, and compensation price feedback correction is initiated.
[0062] During the intraday phase, the available power of new energy sources is updated based on measured wind speed, irradiance, and load deviation. While maintaining the day-ahead start-stop status, the output of thermal power, hydropower, and generalized energy storage is adjusted on a rolling basis. When the proactive profit margin for peak shaving is lower than the minimum proactive profit margin, compensation price feedback is performed first. If the proactive requirements are still not met after the adjustment, the energy storage SOC target reconstruction, hydropower output substitution, and reservoir capacity status feedback are performed in sequence.
[0063] The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for the next rolling window of optimized scheduling, thus achieving rolling optimization.
[0064] As an optional implementation, a more specific process for step 104 is as follows: (1) The overall pre-scheduling is carried out in 24-hour cycles with a step size of 1 hour to determine the start-up and shutdown status of the units, the peak-shaving benchmark output and the cost sharing plan.
[0065] ①The current global pre-scheduling objective function is: (twenty four) In the formula: C up,i , C down,i Costs associated with the start-up and shutdown of thermal power units; , For the first i Taiwan thermal power units t A 0-1 state variable indicating whether the time period has started; α curt The penalty coefficient for clean energy curtailment; P curt,t for t The amount of renewable energy power wasted during certain periods; The cost of the demand response call during time period t; αdev This refers to the penalty coefficient for power output fluctuations in thermal power units. Deep peak-shaving compensation and cost sharing are economic settlements between market entities and are not repeatedly included in the system operating cost objective function. Instead, they are addressed through proactive profit margin Π. G,i,t The feasible range for deep peak shaving of thermal power units is affected. During the day-ahead phase, equations (1) to (14) in step 101, equations (16) to (19) in step 102, and equation (20) in step 103 are satisfied. When a thermal power unit enters the deep peak shaving range, the proactive profit margin constraint should be met: (25) When this constraint is not met, the system does not force the thermal power unit to enter the deep peak-shaving range, but restores its lower output limit to the normal peak-shaving lower limit: (26) If thermal power plants have the economic initiative to implement deep regulation, then the deep regulation range can be used; if not, then deep regulation of thermal power plants without economic viability will not be forced, and the required peak regulation capacity will be transferred to generalized energy storage or hydropower as substitutes.
[0066] The day-ahead global pre-scheduling model includes: the day-ahead global pre-scheduling objective function and constraints.
[0067] (2) Intraday rolling adjustment scheduling, using a 15-minute step size and rolling window. H The power output will be updated without changing the current start / stop status: Intraday optimization uses a rolling window with a step size of 15 minutes to correct power fluctuations caused by prediction errors.
[0068] ① Objective function (intraday rolling optimization model): (27) In the formula: β 1 , β 2 、β 3 、β 4 These are the weighting coefficients for each objective item; Available power from new energy sources; Let SOC be the target SOC of the energy storage device in time period t; This represents the actual grid-connected power of new energy sources. To adjust the daily output of thermal power units; Contribute to the day-to-day schedule of thermal power units; This represents the actual state of charge of the e-th energy storage device; The corresponding target state of charge (SOC) is defined as follows: the first term minimizes the amount of renewable energy curtailed, the second term restricts thermal power from deviating from the day-ahead plan, the third term constrains energy storage to operate around the target SOC, and the fourth term penalizes insufficient initiative from thermal power.
[0069] Available power of new energy sources during the day Updated based on measured wind speed and irradiance, using the following formula: (28) In the formula: v real,t for t Measured wind speed during the specified time period; To measure solar irradiance; The actual ambient temperature was measured. This represents the usable power of the wind farm, calculated based on the measured wind speed. This represents the usable power of a photovoltaic power station, calculated based on measured irradiance and measured temperature; when... When the power output is higher than the current forecast and may lead to excessive deep regulation of thermal power, the alternative peak-shaving power to be undertaken by generalized energy storage is: (29) In the formula, This refers to the alternative peak-shaving power undertaken by generalized energy storage; This refers to the surplus peak-shaving demand generated after the thermal power units' initiative is insufficient; when >0 and SOC e,t <SOC e,max At that time, the existing energy storage SOC target reconfiguration is performed, as shown in the following formula: (30) In the formula: To enable the device to achieve its target SOC after reconstruction at the end of the current rolling window in time period t+H; The target SOC for the e-th energy storage device during the day-ahead dispatch phase in time period t+1; This represents the previously predicted available power of new energy sources. , γ represents the lower and upper limits of the energy storage SOC; γ is the proportional coefficient for the transfer of new energy deviation to energy storage. clip This is a limiting function used to ensure that the corrected target SOC does not exceed the energy storage operation boundary.
[0070] Equation (27) indicates that when new energy sources are actually abundant, the energy storage and charging target is increased to make room for the consumption of new energy; when new energy sources are insufficient, maxIf the value is zero or a reverse correction is used, the energy storage retains its discharge capacity. If the energy storage SOC reaches its upper limit, the energy storage charging power reaches its upper limit, or the generalized energy storage absorbable power is less than the remaining peak-shaving demand, then hydropower output substitution and reservoir capacity status feedback are implemented, as shown in the following formula: (30) (31) In the formula: This refers to the alternative peak-shaving power provided by hydropower. To provide power for the hydropower station's intraday adjustments; To contribute to the planned hydropower station project; The alternative regulation power undertaken by the hydropower station; Adjust the power generation flow rate of the hydropower station within the day; The comprehensive efficiency coefficient of the turbine generator in a hydropower station reflects the efficiency of converting water energy into electrical energy; updated by equation (13). V h,t+1 That is, in the hydropower substitution formula (12) P h,t Reservoir capacity V h,t These are the state constraints and state feedback quantities of the substitution process. If neither generalized energy storage nor hydropower can fully meet the surplus peak-shaving demand caused by insufficient initiative from thermal power, then the unabsorbed surplus power will be included in the amount of renewable energy curtailment. (32) In the formula, For the abandoned electricity of new energy sources; This refers to the alternative peak-shaving power undertaken by generalized energy storage; This is for the remaining peak-shaving demand generated after the thermal power units' initiative is insufficient; when the profit margin of the thermal power units' initiative is insufficient, the compensation price is adjusted first; when the compensation price reaches the upper limit or the maximum number of feedbacks is reached and still cannot meet the initiative requirements, the remaining peak-shaving demand is successively undertaken by generalized energy storage and hydropower, and the part that still cannot be balanced is included in the abandoned power of new energy.
[0071] The multi-source coordinated optimization scheduling framework for the day-to-day period is as follows: Figure 3 As shown, the specific intraday real-time rolling optimization is as follows: Figure 4As shown. In the day-ahead phase, based on the unified source-grid-load-storage model established in step 101, the system inputs wind power, photovoltaic, hydropower, and load forecast sequences, as well as the number of generating units and energy storage units. Combined with the dynamic peak-shaving impact coefficient constructed in step 102, it forms a deep peak-shaving compensation pool and a cost-sharing plan. Based on the calculation of the proactive profit margin and proactive state criterion for thermal power units in step 103, it solves the day-ahead global pre-scheduling model to obtain the thermal power start-up and shutdown status, the planned output of thermal power and hydropower, the generalized energy storage SOC target, and the day-ahead cost-sharing results. In the intraday phase, without changing the day-ahead start-up and shutdown status, a 15 min Let the rolling step size be and the number of rolling cycles throughout the day be . K In the first k In each rolling cycle, the system collects real-time data on wind speed, irradiance, load deviation, and status information such as energy storage SOC and reservoir capacity, updating the available power and net load of new energy sources. Subsequently, based on the proactive profit margin criterion from step 103, it continuously adjusts the output of thermal power, hydropower, and generalized energy storage. When thermal power units possess economic initiative, they are allowed to enter the deep peak-shaving range; when initiative is insufficient, a compensation price feedback correction is triggered, and priority is given to reconfiguring the generalized energy storage SOC target and replacing hydropower output. Each round of rolling optimization only executes the optimal scheduling command for the current time period, using the latest SOC, reservoir capacity, and unit output status as the initial conditions for the next round. k < K Continue to update continuously; when k = K At that time, the intraday scheduling ends, and the intraday scheduling results for the entire day are output, thus forming a closed-loop coordination and optimization mechanism within a finite time domain.
[0072] This embodiment of the multi-energy complementary coordinated optimization scheduling method aims to solve the technical problem of increased peak-valley load differences caused by the anti-peak-shaving and uncertain characteristics of wind power and photovoltaic output. Specifically: ① Construct a source-grid-load-storage multi-energy complementary model that includes wind power, photovoltaic, hydropower, thermal power, electrochemical energy storage, and demand-side resilient loads, outputting the available power of new energy sources, the adjustable range of thermal power, the adjustable range of hydropower, the adjustable capacity of generalized energy storage, the equivalent load, and the net load of each node at each time period; ② Divide the peak period, normal period, and valley period according to the net load of the nodes output in step ①, and construct a dynamic peak-shaving impact coefficient by combining the output differences of each market entity in the peak-valley and normal periods, the predicted power deviation of new energy output, and the peak-shaving sensitivity of the node, thereby determining the deep peak-shaving compensation pool and the cost-sharing plan of each entity; ③ Based on four operating stages: thermal power unit shutdown, deep peak-shaving with oil injection, deep peak-shaving without oil injection, and conventional peak-shaving. The method establishes a segmented comprehensive cost that includes coal consumption, lifespan loss, and oil-fired power plant stabilization. The compensation and allocation results obtained in step ② are substituted into the proactive profit margin model for thermal power units to obtain a proactive criterion for whether thermal power units are willing to enter the deep peak-shaving range. In the day-ahead stage, the physical constraints, cost allocation plans, and proactive criteria obtained in steps ①-③ are used as constraints to determine unit start-up / shutdown, output benchmarks, and generalized energy storage SOC targets. In the intraday stage, the available power of new energy sources is updated based on measured wind speed, irradiance, and load deviation. The output of thermal power, hydropower, and generalized energy storage is continuously adjusted without changing the day-ahead start-up / shutdown status. When the proactive profit margin is insufficient, compensation price adjustments, energy storage SOC target reconstruction, or hydropower capacity substitution are triggered. This method achieves coordinated optimization of deep peak-shaving of thermal power and generalized energy storage across multiple time scales, effectively solving the problems of insufficient anti-peak-shaving and flexible adjustment capabilities caused by a high proportion of new energy access.
[0073] The multi-energy complementary coordinated optimization scheduling method in this embodiment has the following advantages.
[0074] (1) By constructing a multi-energy complementary model that includes wind, solar, hydro, thermal and generalized energy storage, the regulation potential of the source, load and storage sides is fully explored. Through day-ahead and intraday rolling optimization, the prediction deviation of wind and solar power output is corrected in real time, and the traditional source follows load is transformed into source-load-storage coordinated regulation, which greatly releases the space for new energy grid connection and effectively offsets the anti-peak-shaving characteristics of new energy.
[0075] (2) A layered nested architecture of day-ahead global balancing and intraday local correction is adopted to effectively cope with wide-range random fluctuations in wind speed and irradiance. The rapid response capability of generalized energy storage resources is used to smooth high-frequency disturbances, and the deep peak shaving of thermal power is used to support trend deviations on a large time scale. This realizes the spatiotemporal optimization and complementarity of all elements of source, load and storage regulation resources, significantly reduces the net load volatility, and ensures the safe and stable operation of the power grid.
[0076] (3) The peak-shaving impact coefficient is introduced to quantify the actual contribution of each market entity to the system's peak-shaving burden, measure the cost loss caused by the new energy anti-peak-shaving fluctuations to the system, protect the economic interests of thermal power entities that are damaged by deep peak-shaving, and guide new energy power plants to actively allocate regulation resources.
[0077] The following example analyzes and verifies the multi-energy complementary coordinated optimization scheduling method of this embodiment.
[0078] (1) System parameter settings: To verify the operating mechanism of the multi-energy complementary system considering peak-shaving initiative, the IEEE 30-bus system was used as the research object. The system includes traditional thermal power units, run-of-river hydropower, wind farms and photovoltaic power stations, as well as an electrochemical energy storage system. The system topology is as follows: Figure 5 As shown, the specific parameter settings are shown in Table 1 and Table 2.
[0079] Furthermore, to simulate the system's behavior under extreme constraints without considering deep peak-shaving characteristics, the mandatory minimum operating output of thermal power units is set to a fraction of their rated capacity, and unit shutdowns are not permitted; the peak-shaving impact factor is not included. The system scheduling cycle is 24 hours, with a time step of 15 minutes, and the energy storage output is as follows: Figure 6 As shown, the load, wind power, and photovoltaic output forecast curves are as follows: Figure 7 As shown.
[0080] Table 1 Parameters of Conventional Thermal Power Units
[0081] Table 2 Parameters of Wind, Solar, Hydro, and Storage Units
[0082] (2) Analysis of scheduling results.
[0083] Simulation analysis was conducted using a 15-minute time step to compare the multi-source power output with and without considering the peak-shaving impact coefficient. The specific power output of wind, solar, hydro, thermal, and storage sources is as follows: Figure 8 and Figure 9 As shown, through comparative analysis, we can conclude that: 1) When peak-shaving characteristics are taken into account, thermal power exhibits strong flexibility, and can significantly adjust its operation during the low load periods in the early morning and late at night, reducing output and releasing valuable grid connection space for the consumption of new energy. However, when the impact of peak-shaving is not taken into account, thermal power is constrained by minimum output and exhibits a rigid base, with the change in output throughout the day being smaller compared to the change when the impact of peak-shaving is taken into account.
[0084] 2) After taking into account the peak-shaving characteristics, energy storage can more flexibly cooperate with the load curve to shave peaks and fill valleys. It is no longer the only means of regulation, but shares the regulation role with flexible thermal power. However, when the peak-shaving impact is not taken into account, energy storage can carry out emergency charging under high load voltage drop to reduce power curtailment. This is extremely burdensome and there is still overflow.
[0085] 3) Taking peak-shaving characteristics into account, the system is capable of coping with high-frequency load fluctuations; while without taking peak-shaving characteristics into account, the load fluctuations are relatively low-frequency and gentle. However, even under such circumstances, the unit generates substantial power surplus, further proving that peak-shaving flexibility is more important than the stability of the load itself.
[0086] Based on the same inventive concept, this application also provides a multi-energy complementary coordinated optimization scheduling device for implementing the multi-energy complementary coordinated optimization scheduling method described above. The solution provided by this device is similar to the implementation scheme described in the above method. Therefore, the specific limitations in one or more embodiments of the multi-energy complementary coordinated optimization scheduling device provided below can be found in the limitations of the multi-energy complementary coordinated optimization scheduling method described above, and will not be repeated here.
[0087] In one exemplary embodiment, such as Figure 10 As shown, a multi-energy complementary coordinated optimization scheduling device is provided, comprising: a data generation module, used to determine the net load sequence of each grid bus node and the power sequence of each entity in each time period within the current rolling window based on a multi-energy complementary model including multiple entities (source-grid-load-storage); a cost allocation result determination module, used to determine the cost allocation result of each entity based on the power sequence, the net load sequence, and the predicted power deviation of new energy output; and a peak-shaving initiative profit margin determination module, used to determine the peak-shaving initiative profit margin based on the segmented comprehensive cost generated when thermal power units undertake peak-shaving tasks, the cost allocation result, and the thermal power unit peak-shaving initiative profit margin model. The day-ahead-intraday rolling scheduling module is used to perform day-ahead-intraday rolling scheduling based on the aforementioned proactive peak-shaving profit margin. During the day-ahead phase, it determines the unit start-up and shutdown, peak-shaving benchmark output, and energy storage targets. During the intraday phase, it updates the available power of new energy sources, and makes rolling corrections to the output of thermal power, hydropower, and generalized energy storage. When the proactive peak-shaving profit margin is insufficient, it provides compensation price feedback, energy storage target reconstruction, or hydropower output substitution, as well as reservoir capacity status feedback. The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
[0088] In one exemplary embodiment, a computer device is provided, which may be a server or a terminal, and its internal structure diagram may be as follows. Figure 11As shown, this computer device includes a processor, memory, input / output (I / O) interfaces, and a communication interface. The processor, memory, and I / O interfaces are connected via a system bus, and the communication interface is also connected to the system bus via the I / O interfaces. The processor provides computational and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system, computer programs, and a database. The internal memory provides the environment for the operating system and computer programs stored in the non-volatile storage media. The database stores the output of thermal power, hydropower, and generalized energy storage. The I / O interfaces are used for exchanging information between the processor and external devices. The communication interface is used for communication with external terminals via a network connection. When executed by the processor, the computer program implements a multi-energy complementary coordinated optimization scheduling method.
[0089] Those skilled in the art will understand that Figure 11 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the computer equipment to which the present application is applied. Specific computer equipment may include, for example, [the following is a list of possible additional structures]. Figure 11 The embodiments show more or fewer components, combinations of certain components, or different component arrangements. In one exemplary embodiment, a computer device is provided, including a memory and a processor, the memory storing a computer program, which the processor executes to implement the steps in the above-described method embodiments.
[0090] In one exemplary embodiment, a computer-readable storage medium is provided storing a computer program that, when executed by a processor, implements the steps in the above-described method embodiments.
[0091] In one exemplary embodiment, a computer program product is provided, including a computer program that, when executed by a processor, implements the steps in the above-described method embodiments.
[0092] Those skilled in the art will understand that all or part of the processes in the methods of the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium, and when executed, it can include the processes of the embodiments of the above methods. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM).
[0093] The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, etc., and are not limited to these.
[0094] This application discloses a multi-energy complementary coordinated optimization scheduling method, device, equipment, medium, and product. First, it establishes a unified source-grid-load-storage model for wind power, photovoltaic power, hydropower, thermal power, electrochemical energy storage, and demand-side resilient loads, generating the available power of new energy sources, equivalent load, adjustable capacity of generalized energy storage, and peak-valley status of net load for each node. Then, based on peak-valley status, anti-peak-shaving contribution, predicted power deviation of new energy output, and node peak-shaving sensitivity, a dynamic peak-shaving influence coefficient is constructed, forming a deep peak-shaving compensation pool and cost allocation results. Second... This paper couples the energy consumption cost, lifespan loss cost, and oil-fired power plant stabilization cost of four-stage deep peak shaving for thermal power units with the allocation results to obtain the profit margin for proactive peak shaving of thermal power units. This profit margin is then used as the feasibility criterion and feedback adjustment amount for day-ahead and intraday rolling scheduling. Finally, the paper determines the unit start-up and shutdown, peak shaving benchmark output, and energy storage targets at the day-ahead stage. During the intraday stage, the output is rolled over based on measured wind speed, irradiance, and load deviation. A closed loop is formed through generalized energy storage SOC target reconstruction, hydropower output substitution, reservoir capacity status feedback, and compensation price feedback. This application links peak shaving responsibility, economic initiative, and physical regulation capacity, and solves the problem of insufficient anti-peak shaving and flexible regulation capacity caused by high proportion of new energy access through rolling optimization at multiple time scales from day-ahead to intraday.
[0095] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0096] This document uses specific examples to illustrate the principles and implementation methods of this application. The descriptions of the above embodiments are only for the purpose of helping to understand the methods and core ideas of this application. Furthermore, those skilled in the art will recognize that, based on the ideas of this application, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this application.
Claims
1. A multi-energy complementary coordinated optimization scheduling method, characterized in that, include: Based on the multi-energy complementary model of source-grid-load-storage involving multiple entities, the net load sequence of each grid bus node and the power sequence of each entity are determined for each time period within the current rolling window. The cost allocation results for each entity are determined based on the power sequence, the net load sequence, and the predicted power deviation of new energy output; The proactive profit margin for peak shaving is determined based on the segmented comprehensive cost incurred by thermal power units when undertaking peak shaving tasks, the cost allocation results, and the proactive profit margin model for peak shaving of thermal power units. Based on the aforementioned proactive profit margin for peak shaving, day-ahead and intraday rolling scheduling is performed. During the day-ahead phase, the start-up and shutdown of generating units, peak shaving benchmarks, and energy storage targets are determined. During the intraday phase, the available power of new energy sources is updated, and the output of thermal power, hydropower, and generalized energy storage is adjusted on a rolling basis. When the proactive profit margin for peak shaving is insufficient, compensation price feedback, energy storage target reconstruction, or hydropower output substitution and reservoir capacity status feedback are performed. The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
2. The multi-energy complementary coordinated optimization scheduling method according to claim 1, characterized in that, Multiple entities include: wind power, photovoltaic power, hydropower, thermal power, electrochemical energy storage, and demand-side resilient loads; broadly defined energy storage includes: electrochemical energy storage and demand-side resilient loads. The method for constructing the source-grid-load-storage multi-energy complementary model includes: A four-stage peak-shaving output characteristic model for thermal power units is constructed. The four stages include: thermal power unit shutdown stage, deep oil injection peak-shaving stage, non-oil injection deep peak-shaving stage, and conventional peak-shaving stage. The four stages are divided based on the set lower limits of conventional peak-shaving, non-oil injection deep peak-shaving, and oil injection deep peak-shaving. The four-stage peak-shaving output characteristic model for thermal power units includes: a thermal power peak-shaving output model and a segmented comprehensive cost calculation model. A generalized energy storage regulation support model is constructed; the generalized energy storage regulation support model includes: an adjustable capacity model of electrochemical energy storage and demand-side resilient load, a physical constraint model of electrochemical energy storage, and an equivalent load model of demand-side resilient load response; Construct wind, solar, and hydropower output models; the wind, solar, and hydropower output models include: wind power output model, photovoltaic power output model, and hydropower output model; Based on the four-stage peak-shaving output characteristic model of the thermal power unit, the generalized energy storage regulation support model, and the wind, solar and hydropower output model, a multi-energy coordinated balance model that satisfies the spatial coupling of source-grid-load-storage is constructed, and the multi-energy coordinated balance model is determined as the source-grid-load-storage multi-energy complementary model.
3. The multi-energy complementary coordinated optimization scheduling method according to claim 1, characterized in that, The cost allocation results for each entity are determined based on the power sequence, the net load sequence, and the predicted power deviation of new energy output, specifically including: The peak period, valley period, and normal period are divided according to the power sequence and the net load sequence; A dynamic peak-shaving impact coefficient is constructed based on the differences in power output of each entity during peak, valley and normal periods, the predicted power deviation of new energy output, and the peak-shaving sensitivity of the node. The deep peak-shaving compensation pool is determined based on the actual paid peak-shaving electricity generated by thermal power units entering the deep peak-shaving zone. The cost allocation results for each entity are determined based on the dynamic peak-shaving impact coefficient and the deep peak-shaving compensation pool.
4. The multi-energy complementary coordinated optimization scheduling method according to claim 3, characterized in that, The expression for the dynamic peak-shaving influence coefficient is as follows: ; in, Representing the subject The dynamic peak-shaving impact coefficient; Representing the subject The contribution of reverse peak shaving caused by high incidence during trough periods and low incidence during peak periods; Representing the subject The degree of mismatch between the output curve and the net load curve; This indicates the extent to which forecast deviations affect peak-shaving reserves. Representing the subject The topology sensitivity of the node to the system's ability to downgrade or upgrade; , , and The corresponding weights; This is the normalization function; The expression for the deep peak-shaving compensation pool is: ; in, This refers to the total compensation pool fee for system deep peak shaving during the trading day; The unit price for deep peak shaving compensation; For the first i The lower limit of conventional peak shaving for thermal power units in Taiwan; For the first i The actual output of the thermal power unit in the t-hour period; This refers to reducing the power output of the generating unit by a deeper peak shaving operation relative to the lower limit of conventional peak shaving. This refers to the collection of thermal power units currently in a deep peak-shaving state. The duration of the current scheduling period; The formula for calculating the cost allocation result is as follows: ; in, This represents the cost allocation result for the m-th entity during time period t. The amount of electricity consumed by the user (m) during the time period t; The main body m is the in-depth assessment and penalty factor during the t period; j Sum index for the main body; , , , and Indexes for wind power, photovoltaic power, electrochemical energy storage, thermal power, and hydropower, respectively. The dynamic peak-shaving impact coefficient of the main body m during the time period t; For traversing the main body j The dynamic peak-shaving coefficient; For traversing the main body j The amount of electricity used for internet access; For traversing the main body j In-depth assessment and punishment factors.
5. The multi-energy complementary coordinated optimization scheduling method according to claim 1, characterized in that, The expression for the profit margin of the peak-shaving initiative is: ; in, , For the first i The change in the overall cost of a thermal power unit after entering deep peak shaving in time period t; For the first i Profit margin for proactive peak shaving of thermal power units in time period t; For the first i The deep peak-shaving compensation obtained by the thermal power unit in time period t; For the first i The actual output of the thermal power unit in the t-hour period; For the first i The lower limit of conventional peak shaving for thermal power units in Taiwan; For the first i The segmented comprehensive cost corresponding to the actual operating output of the thermal power unit; For the first i The benchmark comprehensive cost of a thermal power unit operating at the lower limit of conventional peak shaving; The feed-in tariff for time period t is used to calculate the opportunity gain loss corresponding to the reduced power generation. The duration of the current scheduling period; For the first i Cost allocation results for the thermal power units in time period t; The unit price for deep peak shaving compensation during period t.
6. The multi-energy complementary coordinated optimization scheduling method according to claim 1, characterized in that, Based on the aforementioned proactive peak-shaving profit margin, day-ahead and intraday rolling scheduling is implemented. During the day-ahead phase, unit start-up and shutdown, peak-shaving baseline output, and energy storage targets are determined. During the intraday phase, the available power of new energy sources is updated, and the output of thermal power, hydropower, and generalized energy storage is continuously adjusted. When the proactive peak-shaving profit margin is insufficient, compensation price feedback, energy storage target reconstruction, or hydropower output substitution and reservoir capacity status feedback are implemented. Specifically, this includes: During the day-ahead phase, the day-ahead global pre-schedule model is solved to determine the start-up and shutdown status, peak-shaving baseline output, and energy storage targets. When the output of the thermal power unit to be scheduled is lower than the conventional peak-shaving lower limit and a deep peak-shaving interval is required, it is determined whether the proactive profit margin for peak-shaving of the thermal power unit is not lower than the set minimum proactive profit margin. If this condition is met, the thermal power unit is allowed to use the deep peak-shaving output interval, but the unit is not forced to enter the deep peak-shaving interval. If the proactive profit margin for peak-shaving is lower than the set minimum proactive profit margin, the thermal power unit is temporarily not allowed to carry out uneconomical deep peak-shaving, the effective output lower limit of the thermal power unit is restored to the conventional peak-shaving lower limit, and the compensation price feedback correction is initiated. During the intraday phase, the available power of new energy sources is updated based on measured wind speed, irradiance, and load deviation. While maintaining the day-ahead start-stop status, the output of thermal power, hydropower, and generalized energy storage is adjusted on a rolling basis. When the proactive profit margin for peak shaving is lower than the set minimum proactive profit margin, compensation price feedback is performed first. If the proactive requirements are still not met after the adjustment, energy storage target reconstruction, hydropower output substitution, and reservoir capacity status feedback are performed in sequence.
7. A multi-energy complementary coordinated optimization scheduling device, characterized in that, The multi-energy complementary coordinated optimization scheduling device employs the multi-energy complementary coordinated optimization scheduling method according to any one of claims 1-6, and the multi-energy complementary coordinated optimization scheduling device comprises: The data generation module is used to determine the net load sequence of each grid bus node and the power sequence of each entity in each time period within the current rolling window, based on a multi-entity source-grid-load-storage multi-energy complementary model that includes multiple entities. The cost allocation result determination module is used to determine the cost allocation result of each entity based on the power sequence, the net load sequence, and the predicted power deviation of new energy output. The peak-shaving initiative profit margin determination module is used to determine the peak-shaving initiative profit margin based on the segmented comprehensive cost incurred by the thermal power unit when undertaking peak-shaving tasks, the cost allocation result, and the thermal power unit peak-shaving initiative profit margin model. The day-ahead-intraday rolling scheduling module is used to perform day-ahead-intraday rolling scheduling based on the aforementioned proactive peak-shaving profit margin. During the day-ahead phase, it determines the unit start-up and shutdown, peak-shaving benchmark output, and energy storage targets. During the intraday phase, it updates the available power of new energy sources, and makes rolling corrections to the output of thermal power, hydropower, and generalized energy storage. When the proactive peak-shaving profit margin is insufficient, it provides compensation price feedback, energy storage target reconstruction, or hydropower output substitution, as well as reservoir capacity status feedback. The scheduling results of the current rolling window are input into the source-grid-load-storage multi-energy complementary model for scheduling in the next rolling window.
8. A computer device, comprising: A memory, a processor, and a computer program stored in the memory and capable of running on the processor, characterized in that the processor executes the computer program to implement the multi-energy complementary coordinated optimization scheduling method according to any one of claims 1-6.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the multi-energy complementary coordinated optimization scheduling method as described in any one of claims 1-6.
10. A computer program product, comprising a computer program, characterized in that, When the computer program is executed by the processor, it implements the multi-energy complementary coordinated optimization scheduling method as described in any one of claims 1-6.