Construction method for assembling cement-graded crushed stone backfill and compaction for culverts under operating railway lines
By employing technologies such as BIM+GIS digital twin modeling, prefabricated culvert production, and intelligent compaction systems, the problems of long construction cycles, difficulty in quality control, and numerous safety hazards in railway underpass projects have been solved. This has enabled efficient, safe, and intelligent culvert construction, making it suitable for railway underpass projects with different geological conditions and track maintenance periods.
Patent Information
- Application Number
- CN202611456196.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-18
- Publication Date
- 2026-11-17
AI Technical Summary
In existing railway line crossing projects, the current construction methods have problems such as long construction period, large impact on operation, low construction efficiency, difficulty in quality control, many safety hazards, and high risk of exceeding the time limit of the track opening window. In particular, under the condition of short track opening window, there is a lack of intelligent management and risk closed-loop technology.
By employing technologies such as BIM+GIS digital twin modeling, prefabricated culvert section factory production, dual excavators excavating in opposite directions, portable ground-penetrating radar scanning, prefabricated snap-on waterstops, layered graded crushed stone backfilling, intelligent compaction system, and layered progressive grouting, combined with micro fiber optic stress sensors and intelligent scheduling modules, the system achieves precise assembly and intelligent management of the entire culvert process.
It significantly shortens construction time, improves backfill density, eliminates structural damage risks, realizes intelligent management and risk closed-loop control throughout the construction process, reduces overall costs, and improves construction quality and safety. It is applicable to railway underpass projects with different geological conditions and track maintenance window durations.
Smart Images

Figure CN123109133A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of railway engineering construction technology, specifically to a method for constructing culverts under operating railway lines using assembled cement-graded crushed stone backfilling and compaction. Background Technology
[0002] With the rapid development of my country's railway transportation industry, the technical upgrading of existing lines and the construction of new lines are constantly increasing. During the implementation of underpass projects on existing operating railway lines, ensuring the safety of line operation while achieving rapid and efficient construction of culvert structures has become a core issue that urgently needs to be addressed in the current construction technology field. my country's railway network operating mileage continues to grow, and a large number of existing lines have long been under high-density, high-intensity transportation conditions. The capacity of passageways, drainage channels, and intersections along these lines have been formed under the original standards and demand conditions. With the development of urbanization and the advancement of integrated transportation along the lines, the demand for new or reconstructed underpasses has increased significantly, especially in projects such as station renovation, freight corridor improvement, and drainage system upgrades, where it is necessary to complete the construction of underpasses on existing lines without interrupting or minimizing operational disruptions.
[0003] Due to the high frequency of train operations on operating lines, short maintenance windows, narrow construction sites, and complex surrounding pipelines, construction can generally only be organized using a "short maintenance window + multiple parallel and overlapping processes" approach. Traditional underpass construction methods mainly include cast-in-place and incremental launching methods. Cast-in-place methods require on-site processes such as rebar tying, formwork erection, and concrete pouring, resulting in a long construction cycle, significant occupation of maintenance windows, and substantial impact on railway operations. While incremental launching methods can reduce interference with existing lines, they require complex construction equipment, are costly, and have strict requirements regarding geological conditions.
[0004] In culvert backfilling construction, traditional methods typically use ordinary soil or graded crushed stone for backfilling, followed by manual or mechanical compaction. This method has the following drawbacks: First, it is difficult to guarantee the backfill density, easily leading to uneven settlement and affecting the safe operation of existing lines; second, construction efficiency is low, requiring a large amount of manpower and time, making it difficult to complete the construction task within limited maintenance windows; third, there is a lack of effective quality control measures, with backfill quality relying mainly on the experience of construction personnel, which can easily lead to potential quality problems.
[0005] In recent years, prefabricated culvert technology has been applied to some extent, transferring some on-site operations to factories and improving construction efficiency. However, in practical applications, there are still many technical shortcomings: First, the assembly accuracy of precast culvert sections is difficult to control. Traditional back-attached waterstops require on-site drilling and bolting, which is slow and easily damages the culvert concrete. Minor misalignments can easily lead to sealing failure. Second, the foundation treatment lacks rapid detection methods, making it impossible to identify local soft soil layers in a timely manner. The replacement construction within the skylight point takes too long and can easily lead to project delays. Third, backfilling construction relies solely on manual control of symmetry. During rush work, there is a high risk of a large difference in backfilling rates on both sides, causing lateral deformation or even cracking of the culvert section. Fourth, the grouting construction adopts the method of "unified grouting after all backfilling is completed," which can easily lead to incomplete grouting, excessive grouting pressure in the upper layer causing cracking of the lower backfill layer, and the sequential construction of grouting and backfilling wastes skylight point time. Fifth, the existing digital twin technology can only realize pre-construction simulation and cannot cope with sudden equipment failures, process delays, etc. during construction, resulting in a high risk of exceeding the skylight point time limit.
[0006] Furthermore, existing research on culvert construction under operational railway lines primarily focuses on overall construction organization and safety protection, with a serious lack of research on the refined control of these key aspects. Especially under short construction windows of 90-120 minutes, how to achieve intelligent management and risk control throughout the entire construction process remains a pressing technical challenge. Current technologies have not organically combined rapid foundation detection and reinforcement, self-healing waterstops, adaptive structural stress control, layered progressive grouting, and intelligent scheduling to form a complete culvert assembly, backfilling, and compaction technology system suitable for short-window construction under operational railway lines. Summary of the Invention
[0007] To address the problems in existing technologies, this invention provides a method for constructing culverts under railway operating lines by assembling cement-graded crushed stone for backfilling and compaction. This method can effectively shorten the construction time during maintenance windows, improve the backfill density, eliminate the risk of structural damage, and achieve intelligent management and risk closed-loop control throughout the entire construction process.
[0008] The technical solution adopted by this invention to solve its technical problem is: a construction method for assembling cement-graded crushed stone and backfilling and compacting culverts under operating railway lines, including the following steps: (1) Construction preparation and digital twin modeling: BIM+GIS technology is used to construct a three-dimensional model, import the skylight point plan for process simulation, and embed an intelligent scheduling module based on genetic algorithm; complete the factory production of prefabricated culvert sections, embed micro fiber optic stress sensors in the inner wall of the culvert sections, and embed waterstop installation slots at the ends; complete site leveling, pipeline relocation and culvert section pre-positioning before the skylight point. (2) Excavation and foundation treatment of the foundation pit: After the skylight point is closed, two excavators are used to excavate in opposite directions. After excavating to the design elevation, a portable high-frequency ground radar is used to scan the foundation, identify weak areas, and use a portable high-pressure jet grouting equipment for in-situ reinforcement; a graded crushed stone cushion layer with 5% cement is laid, leveled and compacted to a compaction degree ≥96%; (3) Precision assembly of precast culvert sections: a forklift is used in conjunction with a total station and a laser marking instrument for positioning. The precast snap-on self-healing waterstop is inserted into the end slot of the culvert section without the need for on-site drilling. After hoisting and positioning, the misalignment is controlled to be ≤2mm. The settlement joint is filled with polyethylene foam board and PVC mortar is injected. (4) Layered gradient backfilling and intelligent compaction: Graded crushed stone with 5% cement is used for symmetrical layered backfilling, with each layer being 25-30cm thick and the backfill height difference between the two sides being ≤30cm; the stress on the culvert is monitored in real time by fiber optic sensors, and the backfilling rate is adaptively adjusted when the pressure difference exceeds 0.05MPa; the vibration parameters are controlled by an intelligent compaction system, and each layer is compacted to a compaction degree ≥97%; (5) Layered progressive grouting reinforcement: After each 3 layers of backfill are compacted and qualified, the corresponding grouting pipe section of the layer is pre-grouted at 0.2-0.3MPa. After initial setting, the upper layer is backfilled. After all backfilling is completed, the whole layer is supplemented with grout at 0.3-0.5MPa. (6) Line restoration and settlement monitoring: A small hydraulic tamping machine is used in conjunction with a track lifting machine to restore the line. The digital twin platform schedules the process in real time, and an adjustment plan is automatically generated if the delay exceeds 5 minutes. A full-cycle graded settlement monitoring system is established, and reinforcement is carried out in a timely manner when abnormalities occur.
[0009] Specifically, the intelligent scheduling module in step (1) collects the process progress in real time through on-site cameras and sensors, and presets 12 types of emergency response procedures with a response time of ≤2 minutes.
[0010] Specifically, the high-frequency ground-penetrating radar scanning speed in step (2) is ≥50m. 2 / minute, reinforcement depth of weak areas is 0.5-1.0m, and the bearing capacity of the base after reinforcement is ≥200kPa.
[0011] Specifically, the prefabricated snap-on self-healing waterstop described in step (3) has a water-swellable rubber strip pre-installed on the inner side and an elastic sealant coated on the contact surface, which can adapt to misalignment deformation of ≤3mm.
[0012] Specifically, the miniature fiber optic stress sensor described in step (4) is uniformly arranged along the circumferential and longitudinal directions of the inner wall of the culvert, with a sampling frequency ≥10Hz, and the data is synchronously transmitted to the digital twin platform.
[0013] Specifically, the intelligent compaction system described in step (4) includes a vibration sensor, an acceleration sensor and a data processing unit, which automatically adjusts the number of tamping blows and the walking speed. The top 0.5m of the culvert is compacted manually in conjunction with a small tamping machine.
[0014] Specifically, the grouting pipe in step (5) is a φ50mm steel pipe with holes spaced 20-30cm apart in a quincunx pattern. Grouting is carried out in sections from bottom to top until the pressure is stable and the grouting volume meets the standard.
[0015] Specifically, in step (6), the track restoration first uses a "little bee" tamping machine for initial tamping, and then uses a small hydraulic tamping machine for fine tamping twice, with the lower clamps being inserted and compacted 8 times each time. The track surface elevation is controlled in real time using a level.
[0016] Specifically, the frequency of graded settlement monitoring in step (6) is as follows: once every 2 hours during the construction period, once every 6 hours for the first 3 days after the line is opened, and once a week thereafter, until the settlement is stable.
[0017] Specifically, the cement-graded crushed stone mix ratio is cement:crushed stone:sand = 5:65:30, the crushed stone particle size is 5-31.5mm, and the gradation is continuous.
[0018] The beneficial effects of this invention are: Significantly improving construction efficiency and reducing disruption to railway operations: By transferring a large amount of on-site work to the factory through prefabrication, combined with techniques such as dual excavators working in opposite directions and rapid assembly of prefabricated culvert sections, the construction time for a single culvert during track maintenance windows is significantly reduced, effectively addressing the core pain point of tight construction schedules on operational railway lines with short track maintenance windows. Simultaneously, relying on the process simulation and intelligent scheduling of a digital twin platform, efficient collaboration of multiple parallel and overlapping operations is achieved, significantly shortening the overall project construction period and minimizing the impact of underpass construction on the normal transportation order of existing railways.
[0019] To comprehensively improve the quality of engineering construction and eliminate potential quality hazards at the source: portable high-frequency ground-penetrating radar is used to quickly identify and reinforce weak areas of the foundation, avoiding uneven settlement of the foundation; high-precision positioning technology is used to control the assembly accuracy of culvert sections, and prefabricated snap-on self-healing waterstops are used to significantly improve the waterproof performance and integrity of the structure; cement-graded crushed stone layered gradient backfilling combined with an intelligent compaction system is used to ensure the overall density of the backfill layer; an innovative layered progressive grouting process is used to effectively solve problems such as incomplete grouting and cracking of the backfill layer that exist in traditional integral grouting, greatly enhancing the overall stability of the backfill layer.
[0020] To effectively ensure structural safety and prevent structural damage during construction: Fiber optic stress sensors are pre-embedded in the inner wall of the culvert section to monitor the stress state in real time. This allows for adaptive adjustment of the backfilling rate on both sides, precisely controlling the lateral deformation of the culvert section and avoiding structural damage such as cracking and displacement caused by asymmetrical backfilling. Simultaneously, a refined compaction process is employed for sensitive areas such as the top of the culvert section to prevent impact damage to the culvert structure caused by direct rolling of large machinery, ensuring the structural safety of the culvert during construction and subsequent operation.
[0021] To achieve intelligent management and control of the entire process and completely avoid the risk of exceeding the time limit for construction windows: a digital twin construction management and control platform based on BIM+GIS is built, which is embedded with an intelligent scheduling module to collect on-site process progress and equipment operation data in real time. When process delays or emergencies occur, the optimal adjustment plan can be automatically generated and the emergency response process can be quickly initiated to achieve closed-loop management of construction risks and ensure that all construction processes are completed smoothly within the time limit.
[0022] Significantly reduce overall construction costs and improve project economic benefits: The factory-standardized production model greatly reduces on-site material waste and reduces on-site labor input; the significant reduction in construction period effectively reduces indirect costs such as equipment rental and project management; the comprehensive improvement in construction quality significantly reduces the cost of subsequent settlement treatment, waterproofing repair and other maintenance and reinforcement, thus reducing the overall cost of the project throughout its entire life cycle.
[0023] Significantly reduces construction safety risks and improves on-site safety management: High-risk operations such as rebar tying and concrete pouring are reduced by replacing a large amount of manual labor with intelligent equipment, lowering the probability of accidents caused by human error. A comprehensive risk prediction and emergency control system can promptly identify and address various safety hazards during construction, achieving inherent safety on the construction site.
[0024] With a wide range of applications and good promotion and application value, this construction method has formed a complete technical system. It has good adaptability to railway operating line underpass small and medium culvert projects with different geological conditions, different track opening lengths, and different spans. The technology is mature and reliable and can be directly replicated and promoted to various railway operating line renovation and new underpass culvert projects across the country. Attached Figure Description
[0025] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0026] Figure 1 This is a flowchart illustrating the overall process flow of the construction method for assembling cement-graded crushed stone backfilling and compaction in the underpass culvert of an operational railway line according to the present invention. Figure 2 This is a schematic diagram of the plan layout for two excavators digging a foundation pit from opposite directions. Figure 3Schematic diagram of pre-embedded slots and snap-on self-healing waterstops at the ends of precast culvert sections; Figure 4 A schematic diagram showing the arrangement of fiber optic stress sensors on the inner wall of the culvert. Figure 5 Flowchart of the layered progressive grouting process; Figure 6 Hardware architecture and data transmission diagram for a robust intelligent system; Figure 7 Functional block diagram of the intelligent scheduling system for skylight points; Figure 8 This is a schematic diagram of the plan layout of existing railway line subgrade settlement monitoring points. Detailed Implementation
[0027] To make the technical means, creative features, objectives and effects of this invention easier to understand, the invention will be further described below in conjunction with specific embodiments.
[0028] like Figures 1-8 As shown, the construction method for assembling and backfilling with cement-graded crushed stone for culverts under operating railway lines according to the present invention includes the following steps: Construction Preparation and Digital Twin Modeling: A 3D model of the culvert and its surrounding environment was constructed using BIM+GIS technology. The construction plan for each time window was imported to simulate and analyze the work processes, identifying and optimizing bottlenecks that could hinder the project schedule. An intelligent scheduling module based on a genetic algorithm was embedded in the digital twin platform. Real-time progress data for each process was collected via on-site cameras and sensors. If a process was delayed by more than 5 minutes, an optimal adjustment plan was automatically generated and pushed to the on-site management personnel's terminal. Emergency response procedures for 12 types of unforeseen events, such as excavator malfunctions and pipeline damage, were also pre-set. Prefabricated culvert sections were manufactured in a factory. Miniature fiber optic stress sensors were evenly deployed along the circumferential and longitudinal directions on the inner wall of each section, with a sampling frequency ≥10Hz. Prefabricated waterstops with mounting slots were installed at the ends of the culvert sections, eliminating the need for on-site drilling. Before the time windows, site leveling, pipeline relocation, and culvert pre-positioning were completed, and the necessary materials and equipment were transported to the designated locations.
[0029] Excavation and Foundation Treatment: After the skylight closure order is issued, the foundation pit is excavated using a dual-excavator counter-excavation process. The two excavators are symmetrically arranged along the centerline of the pit, alternating excavation operations to improve efficiency. After excavation to the design elevation, a portable high-frequency ground-penetrating radar is used to perform a full-coverage scan of the foundation, with a scanning speed ≥50m / s. 2A distribution map of weak areas in the foundation is generated within 10 minutes. Identified weak areas are reinforced in situ using portable high-pressure jet grouting equipment to a depth of 0.5-1.0m, without the need for excavation and replacement. After reinforcement, the foundation bearing capacity is ≥200kPa. Then, a 30cm thick layer of graded crushed stone mixed with 5% cement is laid, and leveled and compacted using an excavator in conjunction with manual labor, achieving a foundation compaction degree of not less than 96%.
[0030] Precision assembly of precast culvert sections: Forklifts, total stations, and laser marking instruments are used to hoist and position the culvert sections. The centerline and edge control lines of the culvert sections are marked at the bottom of the foundation pit. Precast self-healing snap-on waterstops are directly inserted into the pre-embedded grooves at the ends of the culvert sections. Water-swellable rubber strips are pre-installed on the inner side of the waterstop, and the contact surface is coated with elastic sealant, accommodating misalignment deformation ≤3mm, eliminating the need for on-site expansion bolts. After the culvert sections are hoisted into position, their position is adjusted in real time using a laser rangefinder to control the misalignment to ≤2mm. After assembly, polyethylene foam boards are filled into the settlement joints, and polyvinyl chloride sealant is injected for waterproofing.
[0031] Layered gradient backfilling and intelligent compaction: Layered backfilling is performed using graded crushed stone mixed with 5% cement, with a mix ratio of cement:crushed stone:sand = 5:65:30. The crushed stone particle size is 5-31.5mm, and the gradation is continuous. The thickness of each layer is dynamically adjusted to 25-30cm according to the performance of the compaction equipment. Backfilling is carried out symmetrically on both sides of the culvert section, with the backfill height difference between the two sides not exceeding 30cm. Miniature fiber optic stress sensors embedded in the inner wall of the culvert section collect real-time data on the soil pressure difference and structural strain on both sides of the culvert section. The data is synchronously transmitted to the digital twin platform. When the pressure difference between the two sides exceeds 0.05MPa, the system automatically instructs the backfilling equipment to slow down the paving speed on the side with higher pressure and increase the compaction frequency on the side with lower pressure. An intelligent compaction system is used for compaction operations, which monitors the vibration frequency and acceleration in real time and automatically adjusts the number of blows and the travel speed to ensure that each layer is compacted to a degree of not less than 97%. Within 0.5m of the top of the culvert section, manual compaction is carried out in conjunction with a small rammer. The use of large machinery for direct compaction is strictly prohibited.
[0032] Layered progressive grouting reinforcement: During backfilling, one grouting pipe is installed every three layers. The grouting pipe uses φ50mm steel pipe with φ10mm holes drilled in the pipe wall. The holes are spaced 20-30cm apart in a quincunx pattern, and both ends are sealed for protection. A layered progressive grouting process is adopted. After every three layers of backfilling and compaction, the corresponding grouting pipe section is immediately pre-grouted at 0.2-0.3MPa. Backfilling continues until the grout has initially set. After all backfilling is completed, overall supplementary grouting at 0.3-0.5MPa is performed. Grouting is carried out in sections, from bottom to top, until the grouting pressure stabilizes and the grout volume meets the design requirements.
[0033] Track restoration and settlement monitoring: Initial tamping was performed using a "small bee" tamping machine, followed by two rounds of fine tamping using a small hydraulic tamping machine, with eight insertions and clampings per round. During tamping, a level was used to monitor the track surface elevation in real time to ensure the track's geometric dimensions met operational requirements. A digital twin platform was used to schedule each process in real time, automatically initiating emergency response procedures in case of unforeseen circumstances. A full-cycle, tiered settlement monitoring system was established, with settlement observation points deployed on both sides of the roadbed. Observations were taken every 2 hours during construction, every 6 hours for the first 3 days after the line opened, and then weekly until settlement stabilized. Reinforcement measures were promptly implemented when the settlement rate exceeded the warning threshold.
[0034] Example 1: This example provides a method for constructing a culvert under an existing railway line by assembling cement-graded crushed stone and backfilling with compaction. The culvert is a 1-4.0m frame culvert with a total length of 20m, located under an existing railway line with a train speed of 80km / h and a daily maintenance window of 120 minutes.
[0035] Construction preparation and digital twin modeling: First, a BIM model of the culvert was created using Revit software, including precast culvert sections, the foundation pit, existing railway lines, and the surrounding environment. The BIM model was then imported into a GIS platform to construct a 3D geographic information model. Next, the construction schedule for the skylight points was imported into a digital twin platform for process simulation. Simulation revealed that foundation treatment and waterstop installation were bottlenecks restricting the construction period in traditional methods, necessitating optimization of the construction organization.
[0036] To address this issue, a genetic algorithm-based intelligent scheduling module is embedded in the digital twin platform, pre-programming emergency response procedures for 12 types of emergencies, including excavator malfunctions and pipeline damage. Precast culvert sections are manufactured in a standardized factory. A miniature fiber optic stress sensor is installed every 2 meters circumferentially along the inner wall of each section, and one every 3 meters longitudinally, with a sampling frequency of 10Hz. Waterstops are prefabricated at the ends of the culvert sections and fitted with slots. After production, the culvert sections undergo quality inspection, including visual inspection, dimensional measurement, concrete strength testing, and sensor calibration. Only those that pass inspection are transported to the construction site. Three days before the scheduled construction window, the culvert sections are transported to the construction site and pre-positioned in safe areas on both sides of the foundation pit.
[0037] Excavation and foundation treatment of the foundation pit: Upon issuance of the skylight closure order, excavation of the foundation pit commenced immediately. Two 220-type excavators were symmetrically positioned along the centerline of the pit, excavating in opposite directions. While one excavator retracted its bucket to dispose of excavated soil, the other extended its bucket to excavate, alternating operations, which increased excavation efficiency by 40%. During the excavation process, a designated person was assigned to direct the operation, and collisions between the excavators and existing power lines and equipment were strictly prohibited.
[0038] After excavation to the design elevation, a portable high-frequency ground-penetrating radar was used to conduct a full-coverage scan of the foundation at a scanning speed of 55m. 2 A map of the weak foundation area was generated within 8 minutes, at a rate of 1000 m / min. The scan results showed a weak area of approximately 2 meters in the southeast corner of the foundation pit. 2 The weak zone, approximately 0.6m deep, was immediately reinforced by in-situ grouting using a portable high-pressure jet grouting system. The grouting material was P.O42.5 ordinary Portland cement with a water-cement ratio of 0.8:1, the grouting pressure was 0.5MPa, and the reinforcement depth was 0.7m. After reinforcement, a plate load test was conducted to check the bearing capacity of the base, and the result was 210kPa, meeting the design requirements.
[0039] Then, a 30cm thick layer of graded crushed stone mixed with 5% cement was laid. An excavator was used to spread the graded crushed stone evenly, followed by manual compaction with the back of the excavator bucket, and then fine compaction with a small vibratory roller. After compaction, the compaction degree of the base was tested using the ring cutter method, and the test result was 96.8%, which met the design requirements.
[0040] Precision assembly of prefabricated culvert sections: Two 20t forklifts were used to lift and position the culvert sections. At the bottom of the pit, the centerline and edge control lines of the culvert sections were marked using a total station and laser level. Prefabricated self-healing waterstops were directly inserted into the pre-embedded grooves at the end of the first culvert section. Water-swellable rubber strips were pre-installed on the inner side of the waterstops, and the contact surfaces were coated with elastic sealant. The forklifts gently lifted the culvert section, transported it to the designated position, and then slowly lowered it. The position and angle of the culvert section were measured in real time using a laser rangefinder, and the position and height of the forklifts were adjusted to ensure the accuracy of the culvert section assembly.
[0041] Repeat the above steps to complete the assembly of all culvert sections. After assembly, check the misalignment between culvert sections; the maximum misalignment is 1.2mm, which meets the requirements. Then, fill the settlement joint with polyethylene foam boards and inject polyvinyl chloride sealant for waterproofing. The entire process of installing the waterstop and assembling the culvert sections took only 18 minutes, which is 72% shorter than the traditional method.
[0042] Layered gradient backfilling and intelligent compaction: Backfilling was carried out in layers using graded crushed stone mixed with 5% cement. The mix ratio was cement:crushed stone:sand = 5:65:30, with crushed stone particle size of 5-31.5mm and continuous gradation. The thickness of each backfill layer was controlled at 30cm, and backfilling was carried out symmetrically on both sides of the culvert section. A dedicated person was assigned to supervise the work to ensure that the height difference between the backfill layers on both sides did not exceed 30cm.
[0043] Miniature fiber optic stress sensors embedded in the inner wall of the culvert section collect real-time data on the soil pressure difference and structural strain on both sides of the culvert section, and the data is synchronously transmitted to a digital twin platform. During the backfilling process, when the pressure difference between the two sides reaches 0.04 MPa, the system automatically issues an early warning, instructing the backfilling equipment to slow down the paving speed on the left side while increasing the compaction frequency on the right side, until the pressure difference recovers to below 0.02 MPa. Throughout the entire backfilling process, the maximum lateral deformation of the culvert section is 0.3 mm, far lower than the 1.5 mm of traditional construction.
[0044] A smart compaction system was used for the compaction operation. This system includes vibration sensors, acceleration sensors, and a data processing unit mounted on a vibratory roller. The system collects the vibration frequency and acceleration in real time during the compaction process and automatically adjusts the number of blows and the travel speed according to the preset compaction threshold. When the vibration frequency reaches 30Hz and the acceleration reaches 1.5g, it indicates that the layer has been properly compacted. Within 0.5m of the top of the culvert section, manual compaction was carried out in conjunction with a small rammer; direct compaction by large machinery was strictly prohibited. After each layer was compacted, the compaction degree was tested using the sand cone method. The test results were all above 97.5%, meeting the design requirements.
[0045] Layered progressive grouting reinforcement: During the backfilling process, one grouting pipe is installed every three layers. The grouting pipe is made of φ50mm steel pipe with φ10mm holes drilled in the pipe wall. The holes are spaced 25cm apart and arranged in a quincunx pattern. Both ends are sealed with plastic sheeting.
[0046] A layered, progressive grouting process was adopted. After each three layers of backfill and compaction, the corresponding grouting pipe section was immediately subjected to low-pressure pre-grouting at 0.25 MPa. The grouting material used was P.O42.5 ordinary Portland cement with a water-cement ratio of 0.6:1. After the grout had initially set (approximately 30 minutes), the next layer was backfilled. After all backfilling was completed, a 0.4 MPa overall supplementary grouting was performed. Grouting was carried out in segments, from bottom to top, with each segment being 3 meters long. Grouting was stopped when the grouting pressure stabilized and the grout volume met the design requirements. After grouting, the grouting pipe openings were sealed with cement mortar. The grout fullness test result was 99.2%, which was 12 percentage points higher than that of traditional overall grouting.
[0047] Line restoration and settlement monitoring: Initial tamping was performed using a "little bee" tamping machine, followed by two rounds of fine tamping using a small hydraulic tamping machine, with eight insertions and clampings per round. During the tamping process, a level was used to monitor the track surface elevation in real time to ensure the track's geometric dimensions met operational requirements. During construction, a minor malfunction in one excavator caused a 6-minute delay in the excavation process. The intelligent scheduling module of the digital twin platform immediately and automatically generated an adjustment plan, changing the originally sequential culvert section assembly and subbase paving processes to partially parallel operations. Ultimately, the entire track maintenance window construction was completed in 102 minutes, without any timeouts.
[0048] Continuous settlement monitoring was conducted on the existing roadbed throughout the construction process and for six months afterward. Monitoring results showed that the maximum settlement was 6 mm and the settlement rate was 0.15 mm / d, which met the design requirements.
[0049] In this embodiment, the construction time for a single culvert skylight point was 102 minutes, which was 42.5% shorter than the traditional method. The average backfill compaction reached 98.6%, achieving good construction results.
[0050] Example 2: This example provides a method for constructing a culvert under an existing railway line using a precast concrete-graded crushed stone backfill and compaction method. The culvert is a 1-3.0m frame culvert with a total length of 15m, located under an existing railway line with a train speed of 120km / h and a daily maintenance window of 90 minutes.
[0051] Construction preparation and digital twin modeling: Similar to Example 1, BIM+GIS technology was used to construct a 3D model of the culvert and its surrounding environment for process simulation. The simulation revealed that due to the short time window for track maintenance, the construction process needs further optimization, with some procedures completed before the track maintenance window.
[0052] The optimized construction plan includes: pre-assembling the culvert sections and installing the waterstops before the scheduled maintenance window, then transporting the entire culvert section to the vicinity of the foundation pit; setting up protective facilities and completing construction preparations around the foundation pit before the scheduled maintenance window. An equipment status monitoring function has been added to the digital twin platform to monitor the operating status of construction machinery in real time and predict equipment failures in advance.
[0053] After the precast culvert sections are manufactured in the factory, they are pre-assembled to check their dimensions and assembly accuracy. Once the pre-assembly is deemed satisfactory, precast snap-on self-healing waterstops are installed, and the entire culvert section is then transported to the construction site. One day before the scheduled construction window, the culvert section is pre-positioned on dedicated supports on both sides of the foundation pit.
[0054] Excavation and foundation treatment of the foundation pit: After the skylight closure order was issued, two 220-type excavators were used for diagonal excavation. Due to the short skylight period, rapid excavation technology was employed to excavate to the design elevation in one go, reducing intermediate steps. During the excavation process, a laser scanner was used to monitor the stability of the pit slope in real time, and measures were taken promptly upon detecting any abnormalities.
[0055] After excavation to the design elevation, a portable high-frequency ground-penetrating radar was used to conduct a full-coverage scan of the foundation at a scanning speed of 60m. 2 The scan was completed within 6 minutes at a speed of [speed per minute]. The scan results showed that there were no obvious weak areas in the base and the bearing capacity was uniform. A 25cm thick layer of graded crushed stone mixed with 5% cement was then laid, spread using a grader, and compacted with a vibratory roller. After compaction, the base compaction degree was tested using a nuclear density meter, and the result was 96.5%, meeting the design requirements.
[0056] Precision assembly of prefabricated culvert sections: Two 20t forklifts were used to hoist the pre-assembled culvert sections into place. At the bottom of the pit, the position of each culvert section was marked using a total station, and the forklifts accurately placed them in the designed location. The elevation and level of the culvert section were precisely adjusted by adjusting the jacks at its base.
[0057] After the culvert sections were in place, the misalignment and settlement joint width between them were checked. The maximum misalignment was 1.0 mm, and the settlement joint width was 2 cm, which met the requirements. Then, a second waterproofing treatment was applied to the settlement joints, followed by the injection of polyvinyl chloride sealant. The entire culvert section assembly process took only 12 minutes, which is 75% shorter than traditional methods.
[0058] Layered gradient backfilling and intelligent compaction: Backfilling was carried out in layers using graded crushed stone mixed with 5% cement, with each layer controlled to a thickness of 25cm, and symmetrical backfilling was performed on both sides of the culvert section. The stress on the culvert section was monitored in real time using pre-embedded fiber optic stress sensors. When the pressure difference between the two sides exceeded 0.05MPa, the backfilling rate was automatically adjusted. Throughout the backfilling process, the maximum lateral deformation of the culvert section was 0.2mm, demonstrating structural safety and reliability.
[0059] An intelligent compaction system was used for compaction operations. The vibration frequency and number of blows were adjusted according to the performance of the compaction equipment and the site geological conditions. Within 0.5m of the top of the culvert section, manual compaction was carried out in conjunction with a plate compactor, with each layer thickness controlled at 15cm. After each layer was compacted, the compaction degree was tested using the ring cutter method. The test results were all above 98%, meeting the design requirements.
[0060] Layered progressive grouting reinforcement: During backfilling, one grouting pipe was installed every three layers. The grouting pipes were made of φ40mm steel pipes with 20cm spacing between the holes, arranged in a quincunx pattern. A layered progressive grouting process was adopted. After every three layers of backfilling and compaction, a 0.2MPa low-pressure pre-grouting was performed. After initial setting, the next layer was backfilled. After all backfilling was completed, a 0.3MPa overall supplementary grouting was performed, with an appropriate amount of early-strength agent added to accelerate the solidification speed of the grout. The grout fullness test result was 99.5%, meeting the design requirements.
[0061] Line restoration and settlement monitoring: A small hydraulic tamping machine was used for track restoration. During the tamping process, the tamping depth and frequency were strictly controlled to avoid affecting the culvert structure. After tamping was completed, track quality was tested, and all indicators met the operational requirements of V≤120km / h.
[0062] During construction, the digital twin platform coordinated each process in real time to ensure seamless integration of all stages. The entire skylight construction took 78 minutes, a 46.7% reduction compared to traditional methods. Six months post-construction monitoring showed a maximum settlement of 5mm and a settlement rate of 0.12mm / d, meeting design requirements.
[0063] Example 3: This example provides a method for constructing a culvert under an existing railway line using a precast concrete-graded crushed stone backfill and compaction method. The culvert is a 1-5.0m frame culvert with a total length of 25m, located under an existing railway line with a train speed of 100km / h and a daily maintenance window of 150 minutes.
[0064] Construction preparation and digital twin modeling: Similar to Example 1, BIM+GIS technology was used to construct a 3D model of the culvert and its surrounding environment for process simulation. Due to the large span of the culvert, structural safety during the culvert section assembly and backfilling processes required special attention.
[0065] A finite element model of the culvert structure was established in the digital twin platform to simulate the stress and deformation of the culvert segments during backfilling. The simulation revealed that the difference in earth pressure on both sides of the culvert segment during backfilling causes lateral displacement, requiring symmetrical backfilling and layered compaction to control this. Simultaneously, a more sophisticated intelligent scheduling system was embedded in the platform, enabling collaborative scheduling of multiple devices and processes.
[0066] After the precast culvert sections are manufactured in the factory, they undergo structural performance testing, including load-bearing capacity and impermeability tests. Once the tests are passed, fiber optic stress sensors are densely deployed on the inner wall of the culvert section, one every 1.5m circumferentially and one every 2m longitudinally. Precast waterstops are installed at the ends of the culvert sections using slots. Two days before the scheduled excavation window, the culvert sections are transported to the construction site and pre-positioned on both sides of the foundation pit.
[0067] Excavation and foundation treatment of the foundation pit: After the order to close the excavation window was issued, three 220-type excavators were used for excavation. Two excavators dug from opposite sides of the pit, while one excavator assisted in excavation at the end of the pit. During the excavation process, a total station was used to monitor the deformation of the pit in real time to ensure its stability.
[0068] After excavation to the design elevation, a portable high-frequency ground-penetrating radar was used to conduct a full-coverage scan of the foundation at a scanning speed of 50m. 2 The scan was completed within 12 minutes at a rate of 1000 m / min. The scan results showed a 3m deep depression in the middle of the pit. 2 The weak zone, approximately 0.8m deep, was immediately reinforced by in-situ grouting using a portable high-pressure jet grouting device to a depth of 0.9m. After reinforcement, a plate load test was conducted to check the bearing capacity of the base, which yielded a result of 220kPa, meeting the design requirements.
[0069] Then, a 30cm thick layer of graded crushed stone mixed with 5% cement is laid, using a paver to ensure uniform thickness. It is then compacted with a vibratory roller. After compaction, a nuclear density meter is used to test the compaction degree of the base layer, which is 97.0%, meeting the design requirements.
[0070] Precision assembly of prefabricated culvert sections: Two 25t truck cranes, in conjunction with forklifts, were used to lift and position the culvert sections. At the bottom of the pit, a three-dimensional control network was established using a total station and level to precisely control the position and elevation of the culvert sections. Prefabricated self-healing waterstops were inserted into the pre-embedded slots at the ends of the culvert sections before lifting and positioning. After positioning, the culvert sections were secured using specialized clamps to prevent displacement.
[0071] Two waterstops were installed between adjacent culvert sections: one was a prefabricated self-healing snap-on waterstop, and the other was a centrally embedded rubber waterstop, to improve waterproofing. After assembly, the misalignment between the culvert sections was checked, and the maximum misalignment was 1.5mm, which met the requirements. Then, the settlement joint was waterproofed. The entire process of waterstop installation and culvert section assembly took 25 minutes, which is 70% shorter than traditional methods.
[0072] Layered gradient backfilling and intelligent compaction: Backfilling was carried out in layers using graded crushed stone mixed with 5% cement, with each layer controlled to a thickness of 30cm. Backfilling was symmetrical on both sides of the culvert section, with the height difference between the two sides not exceeding 20cm. The stress on the culvert section was monitored in real time using densely deployed fiber optic stress sensors. When the pressure difference between the two sides exceeded 0.04MPa, the backfilling rate was automatically adjusted. Throughout the backfilling process, the maximum lateral deformation of the culvert section was 0.4mm, demonstrating structural safety and reliability.
[0073] An intelligent compaction system was used for compaction operations, and compaction parameters for different parts were adjusted based on finite element simulation results. Within 1m of the top of the culvert section, manual labor combined with a small rammer was used for compaction, with each layer thickness controlled at 20cm. After each layer was compacted, the compaction degree was tested using the sand cone method, and the test results were all above 98.5%, meeting the design requirements.
[0074] Layered progressive grouting reinforcement: During backfilling, one grouting pipe was installed every two layers to increase the density of the pipes. The grouting pipes were φ50mm steel pipes with a hole spacing of 30cm, arranged in a quincunx pattern. A layered progressive grouting process was adopted. After every two layers of backfilling and compaction, a 0.3MPa low-pressure pre-grouting was performed, followed by backfilling of the next layer after initial setting. After all backfilling was completed, a 0.5MPa overall supplementary grouting was performed using a cement-water glass dual-liquid grout to improve the reinforcement effect. The grout saturation test result was 99.3%, meeting the design requirements.
[0075] Line restoration and settlement monitoring: Large tamping machines were used in conjunction with small hydraulic tamping machines for track restoration, first performing coarse tamping and then fine tamping. During the tamping process, a track inspection vehicle was used to monitor the track's geometric dimensions in real time to ensure that the track quality met operational requirements.
[0076] During construction, a sudden downpour caused an 8-minute delay in the backfilling process. The intelligent scheduling module of the digital twin platform immediately and automatically generated an adjustment plan, allocating a small rammer to increase the compaction area and simultaneously advancing some preparatory work for the restoration of the railway line. Ultimately, the entire construction of the skylight point took 132 minutes, without any overtime issues.
[0077] The monitoring results six months after construction showed that the maximum settlement was 7 mm and the settlement rate was 0.18 mm / d, which met the design requirements.
[0078] Compared with Example 1, the traditional construction method was used to construct a culvert under an operating railway line, specifically applied to the same engineering conditions as Example 1. The traditional method uses a cast-in-place concrete culvert body, manual backfilling with ordinary soil, mechanical compaction, and a back-attached waterstop fixed with expansion bolts through on-site drilling. The foundation treatment involves manual excavation and replacement, and grouting is done uniformly after all backfilling is completed.
[0079] During construction, the excavation of the foundation pit took 60 minutes, and the culvert body pouring took 120 minutes, requiring two skylights. During foundation treatment, manual excavation revealed weak areas, and the replacement work took 45 minutes, causing the first skylight to exceed its time limit. The installation of the waterstop took 65 minutes, during which drilling damaged the culvert section concrete. Backfilling was done manually, with mechanical compaction, each layer being 30cm thick, and the average compaction degree was 92%. Grouting took 30 minutes, and the grout fullness was 87%. The line restoration time was 40 minutes.
[0080] The total construction time for a single culvert was 18 days, with 420 minutes of time spent during skylight periods. Monitoring results six months after construction showed a maximum settlement of 28 mm and a settlement rate of 0.9 mm / d, indicating uneven settlement. Furthermore, leakage occurred at the culvert joints, requiring secondary reinforcement and waterproofing.
[0081] Comparing with Example 2, a prefabricated assembly method combined with traditional backfilling was used for the construction of a culvert under an operating railway line, specifically applied to the same engineering conditions as Example 2. The prefabricated culvert sections were manufactured in the factory and assembled on-site. The backfill consisted of graded crushed stone, manually compacted, and a traditional back-attached waterstop was used. The foundation treatment employed conventional testing methods, and the grouting was done using an integral grouting method.
[0082] During construction, the excavation of the foundation pit took 40 minutes, and the foundation treatment took 20 minutes; no obvious weak areas were found. The culvert section assembly took 45 minutes, and the waterstop installation took 35 minutes. Backfilling took 70 minutes, and the average compaction degree was 94%. Grouting took 25 minutes, and the grout fullness was 89%. Line restoration took 20 minutes. The construction time for a single culvert skylight point was 190 minutes, exceeding the time limit by 40 minutes.
[0083] The monitoring results six months after construction showed that the maximum settlement was 20 mm, the settlement rate was 0.6 mm / d, and the maximum lateral deformation of the culvert section was 1.6 mm. Although these met the minimum requirements of the specifications, there were certain safety hazards.
[0084] Effect Comparison Table:
[0085]
[0086] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of protection claimed by the present invention. The scope of protection of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for assembling cement-graded crushed stone and backfilling and compacting culverts under operating railway lines, characterized in that... Includes the following steps: (1) Construction preparation and digital twin modeling: BIM+GIS technology is used to construct a three-dimensional model, import the skylight point plan for process simulation, and embed an intelligent scheduling module based on genetic algorithm; complete the factory production of prefabricated culvert sections, embed micro fiber optic stress sensors in the inner wall of the culvert sections, and embed waterstop installation slots at the ends; complete site leveling, pipeline relocation and culvert section pre-positioning before the skylight point. (2) Excavation and foundation treatment of the foundation pit: After the skylight point is closed, two excavators are used to excavate in opposite directions. After excavating to the design elevation, a portable high-frequency ground radar is used to scan the foundation, identify weak areas, and use a portable high-pressure jet grouting equipment for in-situ reinforcement; a graded crushed stone cushion layer with 5% cement is laid, leveled and compacted to a compaction degree ≥96%; (3) Precision assembly of precast culvert sections: a forklift is used in conjunction with a total station and a laser marking instrument for positioning. The precast snap-on self-healing waterstop is inserted into the end slot of the culvert section without the need for on-site drilling. After hoisting and positioning, the misalignment is controlled to be ≤2mm. The settlement joint is filled with polyethylene foam board and PVC mortar is injected. (4) Layered gradient backfilling and intelligent compaction: Graded crushed stone with 5% cement is used for symmetrical layered backfilling, with each layer being 25-30cm thick and the backfill height difference between the two sides being ≤30cm; the stress on the culvert is monitored in real time by fiber optic sensors, and the backfilling rate is adaptively adjusted when the pressure difference exceeds 0.05MPa; the vibration parameters are controlled by an intelligent compaction system, and each layer is compacted to a compaction degree ≥97%; (5) Layered progressive grouting reinforcement: After each 3 layers of backfill are compacted and qualified, the corresponding grouting pipe section of the layer is pre-grouted at 0.2-0.3MPa. After initial setting, the upper layer is backfilled. After all backfilling is completed, the whole layer is supplemented with grout at 0.3-0.5MPa. (6) Line restoration and settlement monitoring: A small hydraulic tamping machine is used in conjunction with a track lifting machine to restore the line. The digital twin platform schedules the process in real time, and an adjustment plan is automatically generated if the delay exceeds 5 minutes. A full-cycle graded settlement monitoring system is established, and reinforcement is carried out in a timely manner when abnormalities occur.
2. The construction method for assembling cement-graded crushed stone backfilling and compaction for culverts under operating railway lines according to claim 1, characterized in that: The intelligent scheduling module described in step (1) collects the process progress in real time through on-site cameras and sensors, and presets 12 types of emergency response procedures with a response time of ≤2 minutes.
3. The construction method for assembling cement-graded crushed stone backfilling and compaction for culverts under operating railway lines according to claim 1, characterized in that: The high-frequency ground-penetrating radar scanning speed in step (2) is ≥50m. 2 / minute, reinforcement depth of weak areas is 0.5-1.0m, and the bearing capacity of the base after reinforcement is ≥200kPa.
4. The construction method for assembling cement-graded crushed stone backfilling and compaction for culverts passing under operating railway lines according to claim 1, characterized in that: The prefabricated snap-on self-healing waterstop described in step (3) has a water-swellable rubber strip pre-installed on the inner side and an elastic sealant applied to the contact surface, which can accommodate misalignment deformation of ≤3mm.
5. The construction method for assembling cement-graded crushed stone backfilling and compaction for culverts passing under operating railway lines according to claim 1, characterized in that: The miniature fiber optic stress sensor described in step (4) is uniformly arranged along the circumferential and longitudinal directions of the inner wall of the culvert, with a sampling frequency ≥10Hz, and the data is synchronously transmitted to the digital twin platform.
6. The construction method for assembling cement-graded crushed stone backfilling and compaction of culverts under operating railway lines according to claim 1, characterized in that: The intelligent compaction system described in step (4) includes a vibration sensor, an acceleration sensor and a data processing unit. It automatically adjusts the number of tamping blows and the walking speed. The top 0.5m of the culvert is compacted manually in conjunction with a small tamping machine.
7. The construction method for assembling cement-graded crushed stone backfilling and compaction of culverts under operating railway lines according to claim 1, characterized in that: The grouting pipe mentioned in step (5) is a φ50mm steel pipe with holes spaced 20-30cm apart in a quincunx pattern. Grouting is carried out in sections from bottom to top until the pressure is stable and the grouting volume meets the standard.
8. The construction method for assembling cement-graded crushed stone backfilling and compaction for culverts passing under operating railway lines according to claim 1, characterized in that: In step (6), the track restoration first uses a "little bee" tamping machine for initial tamping, and then a small hydraulic tamping machine for fine tamping twice, with the lower clamps inserted 8 times each time. The track surface elevation is controlled in real time using a level.
9. The construction method for assembling and backfilling with cement-graded crushed stone for culverts under operating railway lines according to claim 1, characterized in that: The frequency of graded settlement monitoring in step (6) is as follows: once every 2 hours during the construction period, once every 6 hours for the first 3 days after the line is opened, and once a week thereafter until the settlement is stable.
10. The construction method for assembling cement-graded crushed stone backfilling and compaction of a culvert under an operating railway line according to claim 1, characterized in that: The cement-graded crushed stone mix ratio is cement:crushed stone:sand = 5:65:30, the crushed stone particle size is 5-31.5mm, and the gradation is continuous.