A Safety Control Method for Manually Excavated Bored Pile Construction of High-Speed Railway Platforms During Operation
By establishing a three-dimensional numerical model of four types of control units and preset load combinations, and combining monitoring data for segmented construction and dynamic adjustment, the problems of disconnected load risk prediction and lack of monitoring linkage in traditional construction have been solved, thereby improving the safety and efficiency of high-speed railway platform construction.
Patent Information
- Application Number
- CN202611271424.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-20
- Publication Date
- 2026-11-17
AI Technical Summary
Traditional manual excavation of bored piles presents several challenges in the construction of high-speed railway platforms during the operational phase. These challenges include a disconnect between load determination and risk prediction, difficulty in balancing safety and efficiency with fixed excavation depth, a lack of linkage between monitoring indicators and protection measures, and a lack of closed-loop control between single-section construction and closed-loop management. These issues result in low construction safety and efficiency.
Four types of control units (pile holes, platforms, tracks, and roadbeds) were established and preset load combinations were determined. The excavation and wall protection processes were simulated through a three-dimensional numerical model. Combined with monitoring data, segmented construction and dynamic adjustments were carried out to achieve closed-loop control of comprehensive disturbance classification and structural protection measures.
The deformation risk caused by the construction of high-speed railway platforms during the operation period was effectively controlled, balancing construction safety and efficiency, and achieving both the continuity of train operation and the safety of construction.
Smart Images

Figure CN123109204A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of construction safety control technology near railway operating lines, and in particular to a method for safety control of manually excavated bored pile construction at high-speed railway platforms during the operation period. Background Technology
[0002] The renovation and expansion of high-speed railway platforms during the operational period must be carried out under the condition of continuous train operation, and is subject to multiple rigid constraints: Space constraints: Existing platform canopies, passenger passages, and equipment rooms limit the working area, making it difficult for large rotary drilling rigs and other machinery to enter the site. Manually excavated bored piles are a feasible option for foundation renovation in the platform area because the equipment occupies little space and the drilling process facilitates the exposure and inspection of the strata.
[0003] Load constraints: Train operating loads are transmitted downwards through the rail-sleeper-ballast-subgrade-roadbed system, forming a continuous dynamic load. Simultaneously, the segmented excavation of manually dug piles removes soil from the borehole, weakening the lateral constraints of the borehole wall and causing stress redistribution around the borehole. The area adjacent to the pile hole simultaneously bears the coupled effects of operating load loading and excavation unloading, and its mechanical mechanism differs from pile foundation construction under conditions of new line construction or shutdown.
[0004] Deformation constraints: High-speed railway tracks have strict requirements for geometric state, with allowable deviations in indicators such as track alignment, track gauge, and track surface elevation measured in millimeters; the requirements for differential settlement control of platform structures are higher than those for general civil buildings. Additional deformations caused by construction must be recoverable within the gaps between train passages; otherwise, it will affect train operation safety and passenger comfort.
[0005] Traditional manual excavation pile construction specifications are mainly applicable to general site conditions, and their technical framework includes: Segmented excavation and timely wall protection: Excavation is carried out in segments with a fixed advance, and a concrete wall is constructed after each segment is completed. The advance value is determined empirically based on the stability of the strata, pile diameter, and groundwater conditions, and is usually 0.5m to 1.0m. The limitation of this method is that the fixed advance does not consider the additional impact of the continuous load of operating trains on the stability of the borehole wall, nor does it establish a quantitative relationship between the advance value and the deformation response of the surrounding structure.
[0006] Deformation monitoring: Displacement and settlement are monitored around the pile holes, with the monitoring frequency set at a fixed frequency according to the construction stage. The monitoring data is used to determine the safety status of construction, but there is no direct mapping relationship between the monitoring indicators and the adjustment of construction parameters. How to adjust the advance after a monitoring alarm, whether to suspend construction, and when to resume construction all rely on the experience judgment of the engineers, and no executable closed-loop control rules have been formed.
[0007] Numerical simulation application: Some projects use finite element software to simulate foundation pit excavation or pile foundation construction. However, traditional simulations usually simplify train loads to static loads or ignore the dynamic load effect of trains, and do not establish a coupled calculation model of the maximum equivalent static load envelope of the train and the unloading process of segmented excavation. The simulation results are used for qualitative risk assessment and are not directly converted into the basis for determining the initial construction advance.
[0008] In the scenario of adjacent tracks at a station where the load of operating trains is continuously applied, the above-mentioned traditional technologies have the following specific technical problems: 1. Disconnect between load determination and risk prediction Traditional methods for determining the initial excavation advance either rely on empirical values derived from the geological descriptions in the survey report or employ numerical simulations with simplified static loads or neglect of train dynamic load effects. Train operating loads are speed-dependent; different train speeds or models exist on the same track, resulting in varying dynamic amplification factors. Furthermore, when multiple tracks operate simultaneously, the spatial distribution of loads across each track is complex. Traditional methods fail to determine the maximum equivalent static load based on the dynamic amplification factors of each track, fail to apply this maximum equivalent static load independently to the corresponding track load zones to form a pre-defined unfavorable operating load combination, and fail to use this load combination as a boundary condition in a three-dimensional numerical model for a sequential, coupled simulation of segmented excavation and retaining wall construction. Consequently, the determination of the initial excavation advance lacks quantitative basis.
[0009] 2. Fixed advance makes it difficult to balance safety and efficiency. While traditional standards allow for empirical adjustments to borehole depth based on geological conditions, they lack a systematic approach that directly determines depth through quantitative analysis and dynamically corrects it based on monitoring feedback. Loose overburden or unloading-sensitive strata require smaller depths to control borehole stability, while more stable lower strata allow for larger depths to improve efficiency. Traditional schemes lack a stratified depth adjustment mechanism—one that directly determines the initial depth based on excavation and unloading coupled risk assessment and corrects subsequent depths based on single-section monitoring responses. This results in uncontrollable risks when depth is too large in the upper strata and efficiency losses when depth is too small in the lower strata.
[0010] 3. Lack of linkage between monitoring indicators and protection measures Traditional monitoring schemes typically focus on a single structure (such as monitoring only the convergence of pile holes or only the settlement of tracks), failing to treat pile holes, platforms, tracks, and roadbeds as interconnected control units for multi-source coordinated monitoring; monitoring data is mainly cumulative, without systematically extracting multi-dimensional features such as increments between adjacent monitoring periods, rates of change, continuous growth trends, and deformation that does not recover after a train passes; after monitoring alarms, there is no automatic matching mechanism between comprehensive disturbance levels and graded protection measures, and anomaly handling relies on experience, resulting in a delayed response.
[0011] 4. Lack of a closed loop in the construction and release of individual sections. Traditional methods use the completion of the entire pile as the acceptance unit, failing to establish a unitized control mechanism encompassing single-section excavation, timely wall protection, monitoring and verification, and closure and release. After multiple sections are continuously excavated, wall protection is applied centrally, resulting in accumulated unsupported exposed height and exposure time of the borehole wall, leading to superimposed unloading effects. Existing information-based construction ledgers are primarily used for data recording, lacking a closed-loop update mechanism that uses the overall disturbance level change process and anomaly handling results as input to directly correct subsequent pile hole construction batches, excavation progress, monitoring frequency, and protection measures.
[0012] In summary, traditional methods suffer from the following core deficiencies: the coupling effect of train operating load and excavation unloading is not included in the preliminary analysis for determining the initial advance; the fixed advance is not optimized through layered approaches determined by numerical simulation and corrected by monitoring feedback; multi-source monitoring data is not transformed into actionable graded protection measures; and there is a lack of closed-loop management between single-section construction and parameter feedback. Therefore, there is an urgent need for a safety control method for manually excavated bored pile construction at high-speed railway platforms during the operational period. This method takes the prediction of the coupling risk between the train's maximum equivalent static load envelope and excavation unloading as prerequisites, layered variable advance and timely single-section wall protection as the main construction approach, and multi-source monitoring of four types of control units as the core feedback mechanism. It also aims to achieve closed-loop matching of comprehensive disturbance grading, structural protection measures, and construction release conditions. Summary of the Invention
[0013] The purpose of this invention is to solve at least one technical problem in the background art and to provide a method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation.
[0014] To achieve the above objectives, the present invention provides a method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, comprising: Establish control units and determine preset loads: Divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds, and determine the preset unfavorable operating load combinations for construction risk prediction based on the train operation load of each track. Risk prediction of excavation unloading coupling: A three-dimensional numerical model including the four types of control units and the stratum is established. The preset unfavorable operating load combination is used as the load boundary condition. The segmented excavation and retaining wall construction process is simulated under the load boundary condition. The displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of the load boundary condition and excavation unloading are extracted. The qualified criterion is that the response of the four types of control units is lower than the corresponding warning threshold and no plastic zone deformation zone continuously developing from the pile hole to the track subgrade is formed. The segmented excavation advance is then determined. Single-section construction and monitoring feedback: Single-section excavation and wall construction are carried out in accordance with the segmented excavation advance and the batch and inter-hole sequence. During the construction process, monitoring data of four types of control units are collected simultaneously. The monitoring data includes the monitoring response value of the train passing window. Comprehensive disturbance classification and dynamic adjustment: Based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes, the comprehensive disturbance level of the four types of control units is determined; when the comprehensive disturbance level is in a normal state, the train is allowed to proceed to the next section of construction; when the comprehensive disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceeding the limit are implemented, and after the handling and retesting, the retesting results are fed back to update the subsequent construction parameters and protection measures.
[0015] According to one aspect of the present invention, the preset unfavorable operating load combination is formed by independently applying the maximum equivalent static load corresponding to each track to its respective track load zone; The maximum equivalent static load is determined by multiplying the static load converted from the train's self-weight by the dynamic amplification factor; the dynamic amplification factor is determined based on the train's operating speed, track structure type, and track smoothness of the corresponding track.
[0016] According to one aspect of the invention, the maximum equivalent static load is determined by the following formula: q eq,j =γ d,j ·q s,j ; Where, q eq,j Let q be the maximum equivalent static load of the j-th track load zone. s,j For the static load converted from the train's own weight, γ d,j γ is the power amplification factor; d,j Based on the train speed, track structure type, track smoothness, and design documents or current railway technical standards for track j, when multiple train speeds or train types exist for the same track, the corresponding γ is used. d,j The maximum value in; the static load q converted from the train's self-weight. s,j =w j / b j Determined, where w j Let b be the standard uniformly distributed line load of the j-th track. j b is the equivalent load-bearing width of the top surface of the roadbed after the load has diffused through the sleepers, ballast layer, and subgrade surface; j The load diffusion angle method or a validated numerical load diffusion analysis is used to determine the values given in the design documents.
[0017] According to one aspect of the present invention, the bottom surface of the three-dimensional numerical model is constrained by triaxial displacement, the lateral boundary is constrained by normal displacement, and the top surface is a free boundary. The significant impact range of excavation unloading is determined by sensitivity analysis of the computational domain boundary. The convergence criterion of the sensitivity analysis is: when the relative changes in the maximum vertical displacement of the platform, the maximum horizontal displacement of the track, and the range of the plastic zone around the hole are all less than or equal to a preset ratio, the expanded computational domain is compared with the previous level computational domain.
[0018] According to one aspect of the present invention, the construction organization of the single-section construction adopts a combination of trial and control methods, starting from the farthest point and proceeding to the nearest. Adjacent pile holes in the same batch are excavated in a staggered manner, and adjacent holes are constructed in a staggered order. Furthermore, adjacent pile holes in the same construction batch shall not be in a state where they have been excavated but have not yet been protected. When the comprehensive disturbance level of any pile hole reaches the alarm level, the pile hole in the same batch that is close to the existing track shall suspend the excavation of the next section.
[0019] According to one aspect of the present invention, based on the geological stability zoning revealed by the exploration, after excavation enters the lower, more stable strata, the candidate excavation advances larger than the current segmented excavation advances are reviewed according to the excavation unloading coupling risk prediction, and the increased segmented excavation advance is determined; the increased segmented excavation advance is only adopted when the previous section of the retaining wall has passed the acceptance test, there is no convergence or spalling of the borehole wall and an increase in water seepage, and the monitoring values of the four types of control units are lower than the corresponding warning thresholds.
[0020] According to one aspect of the present invention, the key time periods for synchronously collecting monitoring data include at least: before each section of excavation, after excavation, after wall protection, before the next section of excavation, at the stratum transition position, during the enlarged head excavation stage, during the construction stage of adjacent pile holes, and during the train passage period; for the train passage period, the baseline value before passage, the response value during passage, and the recovery value after passage are recorded, wherein the unrecovered deformation after the train passage is the absolute value of the difference between the recovery value after passage and the baseline value before passage.
[0021] According to one aspect of the invention, determining the overall disturbance level includes: Three-level cumulative thresholds for early warning, alarm, and control are set for each monitoring indicator, as well as three-level incremental thresholds for early warning, alarm, and control. For early warning, alarm, and control, the normalized response value is calculated based on the corresponding cumulative threshold and incremental threshold: r i,k =max(|X i | / C i,k ,|ΔX i | / ΔC i,k ), k∈{early warning, alarm, control}; Among them, X i Let ΔX be the cumulative value of the i-th monitoring indicator. i For the increment between adjacent monitoring periods, C i,k and ΔC i,kThese are the cumulative threshold and incremental threshold of the i-th monitoring indicator at level k, respectively; the level of the i-th monitoring indicator is determined by satisfying r. i,k The highest level is ≥1; when each r i,k If all values are less than 1 but the monitoring indicator increases in the same direction for two consecutive monitoring cycles, or if there is a blockage in the borehole wall, visible collapse, a sudden increase in water seepage, or a continuous increase in deformation after a train passes through without recovery, the monitoring indicator will be upgraded by one level, but the maximum level shall not exceed the control level; the comprehensive disturbance level shall be the highest level among the monitoring indicator levels.
[0022] According to one aspect of the present invention, the structural protection and anomaly handling measures are matched according to the comprehensive disturbance level: under normal conditions, construction continues according to the current parameters and the borehole loading limit is implemented; under the warning level, monitoring is intensified, borehole loading is limited, and the excavation of adjacent pile holes in the same batch to the next segment is suspended; under the alarm level, subsequent excavation of the current segment is suspended, the excavation advance of subsequent segments is reduced, and temporary support or drainage measures are implemented; under the control level, construction of the relevant pile holes is stopped, the borehole wall is sealed, and backfilling and counterpressure or local reinforcement are implemented; when all monitoring indicators are lower than the threshold of the next level for two consecutive monitoring cycles after the treatment and there are no abnormalities in the borehole wall, retaining wall, or seepage, the comprehensive disturbance level is reduced by one level.
[0023] According to one aspect of the present invention, when all monitoring indicators of the four types of control units are in normal condition, the increments of each indicator in two or more consecutive monitoring cycles are less than or equal to the corresponding increment warning value and do not continue to increase, the unrecovered deformation in two consecutive train passage periods is less than or equal to the corresponding warning value and does not continue to increase, and there are no new through cracks in the retaining wall, no visible collapse or continuous blockage in the hole wall, the current segment is determined to be closed and released; the closure record is updated to the digital construction safety ledger for feedback and correction of subsequent construction parameters and protection measures.
[0024] To achieve the above objectives, the present invention also provides a safety control system for manually excavated bored pile construction at high-speed railway platforms during operation, comprising: The control unit and the preset load determination module divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds. Based on the train operation load of each track, the module determines the preset unfavorable operation load combination for construction risk prediction. The excavation unloading coupled risk prediction module establishes a three-dimensional numerical model including the four types of control units and the stratum. The preset unfavorable operating load combination is used as the load boundary condition. Under the load boundary condition, the segmented excavation and retaining wall construction process is simulated. The displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of the load boundary condition and excavation unloading are extracted. The qualified criterion is that the response of the four types of control units is lower than the corresponding early warning threshold and no plastic zone deformation zone continuously developing from the pile hole to the track subgrade is formed. The segmented excavation advance is then determined. The single-section construction and monitoring feedback module excavates and constructs retaining walls in accordance with the segmented excavation advance and the sequence of batch and inter-hole excavation. During the construction process, monitoring data of four types of control units are collected simultaneously. The monitoring data includes the monitoring response value of the train passing window. The integrated disturbance classification and dynamic adjustment module determines the integrated disturbance level of four control units based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes. When the integrated disturbance level is in a normal state, the train is allowed to proceed to the next section of construction. When the integrated disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceedance are implemented, and the retest results are fed back to update subsequent construction parameters and protection measures after the retest.
[0025] To achieve the above objectives, the present invention also provides an electronic device, including a processor, a memory, and a computer program stored in the memory and executable on the processor. When the computer program is executed by the processor, it implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation as described above.
[0026] To achieve the above objectives, the present invention also provides a computer-readable storage medium storing a computer program, which, when executed by a processor, implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation, as described above.
[0027] According to the present invention, the present invention integrates the coupled calculation of operating train load and excavation unloading, layered variable advance control, multi-source monitoring of four types of control units, comprehensive disturbance classification, and digital ledger feedback into a closed-loop control system. This realizes the transformation from experience-based qualitative judgment to calculation-based quantitative prediction, from single-point lag monitoring to multi-source real-time graded response, and from fixed advance to dynamic parameter optimization. It effectively controls the deformation risks of platforms, roadbeds, and tracks caused by manual bored pile construction without interrupting train operation, and takes into account both construction safety and work efficiency. Attached Figure Description
[0028] Figure 1 This schematic diagram illustrates a safety control method for manually excavated bored pile construction at high-speed railway platforms during operation, according to one embodiment of the present invention. Figure 2 This is a control diagram of layered variable advance, timely wall protection, and single-section closure in Example 1; Figure 3 This is a diagram showing the layout of the platform, track, roadbed, pile hole control unit, and monitoring system for Example 1. Figure 4 This is a feedback diagram of multi-source monitoring, train passage time periods, and digital ledgers for Example 1. Detailed Implementation
[0029] The invention will now be discussed with reference to exemplary embodiments. It should be understood that the described embodiments are merely intended to enable those skilled in the art to better understand and thus implement the invention, and are not intended to imply any limitation on the scope of the invention.
[0030] As used herein, the term "comprising" and its variations are to be interpreted as open-ended terms meaning "including but not limited to". The term "based on" is to be interpreted as "at least partially based on". The terms "one embodiment" and "an embodiment" are to be interpreted as "at least one embodiment".
[0031] Figure 1 This is a schematic flowchart illustrating a safety control method for manually excavated bored pile construction at high-speed railway platforms during operation, according to one embodiment of the present invention. Figure 1 As shown, a safety control method for manually excavated bored pile construction at high-speed railway platforms during operation includes: Establish control units and determine preset loads: Divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds, and determine the preset unfavorable operating load combinations for construction risk prediction based on the train operation load of each track. Risk prediction of excavation and unloading coupling: A three-dimensional numerical model including four types of control units and strata is established. The preset unfavorable operating load combination is used as the load boundary condition. The segmented excavation and retaining wall construction process is simulated under the load boundary condition. The displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of load boundary condition and excavation and unloading are extracted. The qualified criterion is that the response of the four types of control units is lower than the corresponding warning threshold and no plastic deformation zone that continuously develops from the pile hole to the track subgrade is formed. The segmented excavation advance is determined. Single-section construction and monitoring feedback: Single-section excavation and wall construction are carried out in accordance with the segmented excavation advance and the order of batch and alternate holes. During the construction process, monitoring data of four types of control units are collected simultaneously. The monitoring data includes the monitoring response value of the train passing window. Comprehensive disturbance classification and dynamic adjustment: Based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes, the comprehensive disturbance level of the four types of control units is determined; when the comprehensive disturbance level is in a normal state, the train is allowed to proceed to the next section of construction; when the comprehensive disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceeding the limit are implemented, and after the handling and retesting, the retesting results are fed back to update the subsequent construction parameters and protection measures.
[0032] In this implementation, firstly, before construction, comprehensive basic parameters (including existing platform structure, track and rail structure, train operating load and dynamic amplification factor, pile diameter and length, enlarged head size, retaining wall structure, strata and groundwater conditions, track geometric reference, etc.) are obtained from design documents and survey data. The construction impact zone is strictly divided into pile hole control unit, platform control unit, track control unit, and subgrade control unit. Each unit is configured with three levels of thresholds: early warning, alarm, and control, including cumulative values and adjacent period increments. Secondly, based on the train operating load, the most unfavorable preset unfavorable operating load combination under simultaneous operation of multiple tracks is calculated and used as the boundary condition of the three-dimensional numerical model. The actual process of segmented excavation, activation of the retaining wall of the previous section, and excavation of the next section is simulated in detail in the model, and the displacement and plastic zone under the combined action of train dynamic load and unloading are extracted. The core criterion is that the response of the four types of control units is lower than the early warning threshold and no plastic deformation zone continuously developing from the pile hole to the track subgrade is formed. Based on this, the initial segmented excavation advance is deduced. Subsequently, the construction was strictly organized on-site according to the principles of calculated advance, phased, staggered, and sequential work to ensure that each section was excavated and protected immediately. Monitoring data from four types of control units were collected simultaneously, and the baseline before train passage, peak value during passage, and recovery time window response were specifically recorded for the period of train passage. Finally, the overall disturbance level was determined based on the cumulative value, increment, rate of change, and unrecovered deformation after train passage; if normal, passage was allowed; if exceeding limits, graded protection measures were initiated, re-measurement was conducted, and the results were fed back to subsequent construction.
[0033] In this implementation, risk prediction, dynamic construction, hierarchical feedback, and closed-loop release are integrated into an iterative safety control system, which changes the traditional extensive mode of determining the advance based on experience and lagging response of single-point monitoring, and improves the matching degree between construction safety and high-speed rail operation.
[0034] Furthermore, according to one embodiment of the present invention, the preset unfavorable operating load combination is formed by independently applying the maximum equivalent static load corresponding to each track to its respective track load zone; The maximum equivalent static load is determined by multiplying the static load converted from the train's self-weight by the dynamic amplification factor; the dynamic amplification factor is determined based on the train's operating speed, track structure type, and track smoothness of the corresponding track.
[0035] In this embodiment, the preset unfavorable operating load combination is not simply a superposition of loads from multiple tracks, but rather the application of the maximum equivalent static load of each track independently to its corresponding track load zone, so as to truly reflect the spatial load distribution when multiple tracks are operating simultaneously. This maximum equivalent static load is obtained by multiplying the static load converted from the train's self-weight by a dynamic amplification factor. This dynamic amplification factor is not a fixed value; it strictly depends on the actual operating speed of the train on the j-th track, the track structure type, and the track smoothness.
[0036] In this embodiment, the present invention overcomes the load distortion problem caused by simple superposition in traditional calculations. The power amplification factor is dynamically selected based on the actual vehicle condition and track status, ensuring a safety margin for the load envelope and providing boundary inputs for numerical simulation that are closest to the real physical environment.
[0037] Furthermore, according to one embodiment of the present invention, the maximum equivalent static load is determined by the following formula: q eq,j = γ d,j · q s,j ; Where, q eq,j Let q be the maximum equivalent static load of the j-th track load zone. s,j For the static load converted from the train's own weight, γ d,j γ is the power amplification factor; d,j Based on the train speed, track structure type, track smoothness, and design documents or current railway technical standards for track j, when multiple train speeds or train types exist for the same track, the corresponding γ is used. d,j The maximum value in; the static load q converted from the train's self-weight. s,j =w j / b j Determined, where w j Let b be the standard uniformly distributed line load of the j-th track. j b is the equivalent load-bearing width of the top surface of the roadbed after the load has diffused through the sleepers, ballast layer, and subgrade surface; j The load diffusion angle method or a validated numerical load diffusion analysis is used to determine the values given in the design documents.
[0038] In this embodiment, to ensure the objectivity and accuracy of the physical boundary input, a rigorous calculation formula is provided. The dynamic amplification factor γ... d,j The design documents or current railway technical standards must be consulted. If multiple train types exist on the same track, the maximum value must be used. The static load q calculated based on the train's self-weight. s,j Divide the standard uniform wiring load by the equivalent load-bearing width b j Obtained. j The load diffusion angle method can be used for accurate calculation, and its expansion formula is b. j =b 0,j +2∑ m k=1 t k· tanα k Where m is the number of layers involved in load diffusion, and b 0,j The effective lateral load-bearing width at the bottom of the sleeper, t k and α k These represent the thickness and design diffusion angle of the kth layer, including the ballast layer and the subgrade surface layer.
[0039] In this embodiment, the dynamic load of the train is transformed from a qualitative description into a quantitative mathematical formula, providing objective and unique mathematical support for the load input of the three-dimensional numerical simulation, which greatly enhances the rigor and credibility of risk prediction.
[0040] Furthermore, according to one embodiment of the present invention, the bottom surface of the three-dimensional numerical model is constrained by triaxial displacement, the lateral boundary is constrained by normal displacement, and the top surface is a free boundary. The significant impact range of excavation unloading was determined by sensitivity analysis of the computational domain boundary. The convergence criterion for the sensitivity analysis was: when the relative changes in the maximum vertical displacement of the platform, the maximum horizontal displacement of the track, and the range of the plastic zone around the hole are all less than or equal to a preset ratio, the expanded computational domain is compared with the previous level computational domain.
[0041] In this implementation, to ensure that the numerical simulation results are not affected by artificial boundary errors, the model adopts bottom-constrained triaxial displacement (simulating deep bedrock), lateral-constrained normal displacement (simulating frictionless slippage of soil), and top-free boundary. To scientifically select a reasonable range of the computational domain, it is necessary to use computational domain boundary sensitivity analysis, that is, to gradually expand the lateral and longitudinal boundaries; when the relative changes in the maximum vertical displacement of the platform, the maximum horizontal displacement of the track, and the range of the plastic zone around the borehole are all less than or equal to a preset proportion (such as 5%) compared to the previous level of computational domain, the computational domain is determined to have converged, and the final boundary size is locked.
[0042] In this embodiment, the present invention avoids the problems of mechanical distortion caused by blindly setting boundaries, resulting in too small a size or waste of resources due to too large a size, thus ensuring that the risk prediction model is economical and accurate.
[0043] Furthermore, according to one embodiment of the present invention, the construction organization for single-section construction adopts a combination of trial and control methods, starting from the farthest point and proceeding to the nearest. Adjacent pile holes within the same batch are excavated in a staggered manner, and adjacent holes are constructed in a staggered order. Furthermore, adjacent pile holes within the same construction batch must not be in a state where they have not yet been excavated and the retaining wall has not been constructed at the same time. When the comprehensive disturbance level of any pile hole reaches the alarm level, the pile hole in the same batch that is close to the existing track will suspend the excavation of the next section.
[0044] In this implementation, staggered construction refers to the staggered excavation of adjacent pile holes in different excavation segments to avoid adjacent pile holes being at the same or similar excavation depth at the same time, thereby preventing the concentrated superposition of the unloading effect of the pile group. Specifically, if pile A is excavating the nth segment, the adjacent pile B should be in a state where the retaining wall of the (n-1)th segment is completed or the (n+1)th segment has not yet been excavated, ensuring that the unloading influence zone of adjacent pile holes does not form a continuous connection. To ensure the absolute safety of the high-speed railway track, the on-site organization follows the principle of combining test control with distant ones, that is, priority is given to selecting test control piles far away from the existing track for construction, and after successfully verifying various parameters, the construction of pile holes near the line is then advanced. Within the same batch, adjacent pile holes must be excavated alternately, and adjacent holes must be constructed in a staggered sequence to prevent adjacent pile holes from being in an unsupported exposed state of newly excavated without retaining wall at the same time. In addition, when the comprehensive disturbance level of any pile hole reaches the alarm level, the adjacent piles near the existing track in the same batch must immediately suspend the excavation of the next segment.
[0045] In this implementation, the method of proceeding from far to near avoids the risk of blindly constructing near the line; the staggered excavation and inter-hole skipping effectively prevent the overlapping and superposition of the unloading effect of the pile group; and the alarm-based forced shutdown mechanism builds a solid physical barrier for the safety of high-speed rail tracks.
[0046] Furthermore, according to one embodiment of the present invention, based on the geological stability zoning revealed by the exploration, after excavation enters the lower, more stable strata, the candidate excavation advances that are larger than the current segmented excavation advances are reviewed according to the excavation unloading coupling risk prediction, and the increased segmented excavation advances are determined; the increased segmented excavation advances are only adopted when the previous section of the retaining wall has passed the acceptance test, there is no convergence or spalling of the borehole wall and an increase in water seepage, and the monitoring values of the four types of control units are lower than the corresponding warning thresholds.
[0047] In this embodiment, to balance safety and efficiency, the invention introduces a layered variable advance mechanism. First, the geological stability is zoned based on the geological survey report. After excavation enters a lower, more stable stratum, candidate advances larger than the current advance are numerically verified. Once verified and approved, the increased segmented advance is confirmed. However, if the actual geological conditions or environment change, the following stringent conditions must be met simultaneously before increasing the advance: ① The previous section of the retaining wall has passed inspection; ② On-site measurements show no convergence, spalling, or increased water seepage in the borehole wall; ③ Monitoring values from all four control units are below the corresponding warning thresholds; ④ No plastic deformation zone has formed, continuously extending from the pile hole to the track subgrade. If any condition is not met, the original advance must be forcibly reverted or a smaller advance must be used.
[0048] In this embodiment, the present invention scientifically resolves the contradiction between safety and efficiency when a fixed excavation depth is difficult to achieve in different geological formations. In the upper, softer formations, a small excavation depth ensures safety, while in the lower, more stable formations, verification data supports acceleration. Furthermore, stringent verification thresholds are set to eliminate the safety risks associated with blindly over-excavating.
[0049] Furthermore, according to one embodiment of the present invention, the key time periods for synchronously collecting monitoring data include at least: before each section of excavation, after excavation, after wall protection, before the next section of excavation, at the stratum transition position, during the enlarged head excavation stage, during the construction stage of adjacent pile holes, and during the train passage period; for the train passage period, the baseline value before passage, the response value during passage, and the recovery value after passage are recorded, and the unrecovered deformation after the train passes is the absolute value of the difference between the recovery value after passage and the baseline value before passage.
[0050] In this implementation, monitoring is strictly limited to all critical construction nodes, including before / after each section of excavation, after retaining wall construction, ground transition, enlarged head construction, and adjacent pile construction. Especially during train passage periods, the baseline value before passage, the response value during passage, and the recovery value after passage must be accurately recorded. The system defines the absolute value of the difference between the recovery value after passage and the baseline value before passage as the unrecovered deformation after the train passes, serving as the core indicator for determining whether the high-frequency impact of the train has caused irreversible damage to the borehole perimeter.
[0051] In this embodiment, the present invention completely eliminates the blind spot of traditional monitoring that only considers absolute cumulative settlement. By capturing the time window of train passage and unrecovered deformation, it effectively identifies the microscopic cumulative plastic damage caused by the high-frequency reciprocating impact of the train, realizing a leap from static observation to dynamic assessment in monitoring.
[0052] Furthermore, according to one embodiment of the present invention, determining the overall disturbance level includes: Three-level cumulative thresholds for early warning, alarm, and control are set for each monitoring indicator, as well as three-level incremental thresholds for early warning, alarm, and control. For early warning, alarm, and control, the normalized response value is calculated based on the corresponding cumulative threshold and incremental threshold: r i,k =max(|X i | / C i,k ,|ΔX i | / ΔC i,k ), k∈{early warning, alarm, control}; Among them, X i Let ΔX be the cumulative value of the i-th monitoring indicator. i For the increment between adjacent monitoring periods, C i,k and ΔC i,k These are the cumulative threshold and incremental threshold of the i-th monitoring indicator at level k, respectively; the level of the i-th monitoring indicator is determined by satisfying r. i,k The highest level is ≥1; when each r i,kIf all values are less than 1 but the monitoring indicator increases in the same direction for two consecutive monitoring cycles, or if there is a blockage in the borehole wall, visible collapse, a sudden increase in water seepage, or a continuous increase in deformation after a train passes through without recovery, the monitoring indicator will be upgraded by one level, but the maximum level shall not exceed the control level; the comprehensive disturbance level shall be the highest level among the monitoring indicator levels.
[0053] In this embodiment, to unify monitoring data with different dimensions under a single command system, this invention constructs a rigorous mathematical model. For the i-th indicator, a three-level cumulative threshold and an incremental threshold are pre-set, and the normalized response value formula r is used. i,k A dimensionless comparison is performed to directly determine the level of the item. The most core innovation lies in the trend-based ranking rule: even if r i,k If the level is below 1 (not exceeding the limit), but the indicator shows a continuous increase in the same direction for two consecutive weeks, or if the inspection finds that the block has fallen, water has suddenly surged, or the deformation has continued to increase without recovery, the system must intelligently determine to raise the level by one level, and finally take the highest level among all individual items as the comprehensive disturbance level.
[0054] In this implementation, the normalized response value addresses the pain point of inconsistent dimensions and difficulty in comparison of multi-source data. The trend enhancement mechanism enables the system to trigger early warnings at the nascent stage of accelerated deformation, achieving true prevention and far surpassing the lagging mode of traditional alarms that only sound when values exceed limits.
[0055] Furthermore, according to one embodiment of the present invention, structural protection and abnormal handling measures are matched according to the comprehensive disturbance level: under normal conditions, construction continues according to the current parameters and the borehole load limit is implemented; under the warning level, monitoring is intensified, borehole load is limited, and the excavation of adjacent pile holes in the same batch to the next segment is suspended; under the alarm level, subsequent excavation of the current segment is suspended, the excavation advance of subsequent segments is reduced, and temporary support or drainage measures are implemented; under the control level, construction of the relevant pile holes is stopped, the borehole wall is sealed, and backfilling and counterpressure or local reinforcement are implemented; when all monitoring indicators are lower than the threshold of the next level for two consecutive monitoring cycles after the treatment and there are no abnormalities in the borehole wall, retaining wall, or seepage, the comprehensive disturbance level is reduced by one level.
[0056] In this implementation, the system generates a mandatory stepped response based on the overall disturbance level: Under normal conditions, the borehole load limit is maintained; under warning conditions, monitoring is immediately intensified, load is limited, and adjacent pile construction is suspended; under alarm conditions, excavation is immediately halted, subsequent advance is reduced, and temporary steel casing, segmented support, or drainage measures are selected as needed; under control conditions, all construction is stopped, the borehole wall is sealed, and backfilling and counter-pressure or local reinforcement are applied. After the measures are completed, re-measurements are conducted. Only when all indicators are below the next lower level threshold for two consecutive monitoring cycles, and there are no abnormalities in the borehole wall, retaining wall, or seepage, can the level be lowered by one level.
[0057] The next lower-level threshold is distinguished according to the direction of degradation as follows: The control level is downgraded to the alarm level when the cumulative value and increment of all monitoring indicators are lower than the threshold corresponding to the alarm level. The alarm level was downgraded to the warning level when the cumulative value and increment of all monitoring indicators were lower than the threshold corresponding to the warning level. The warning level was downgraded to the normal level: none of the monitoring indicators met the triggering conditions for the warning level, and there were no abnormal signs such as a continuous upward trend, no falling of the borehole wall, visible collapse, sudden increase in water seepage, or continuous increase in deformation after a train passed through, and no recovery after the train passed.
[0058] Taking the downgrade of an alarm level after handling as an example: If a certain indicator is currently at the alarm level, after handling, it is necessary to meet the following conditions for two consecutive monitoring cycles: the cumulative value of each monitoring indicator is lower than the warning cumulative threshold and the increment is lower than the warning increment threshold (i.e., r is not met). i,预警 The alert level can be downgraded to the warning level only if there are no abnormalities in the pore wall, protective wall, or water seepage (≥1 trigger condition). If it is necessary to continue to downgrade to the normal level after being downgraded to the warning level, it is necessary to meet the condition that all monitoring indicators have not reached the warning level trigger condition for two consecutive monitoring cycles, and the trend is stable with no abnormal signs.
[0059] A light-load control zone is set up near the borehole opening. Excavated soil, reinforcing cages, formwork, retaining materials, and construction machinery are arranged on the side away from the existing track, and drainage around the platform, roadbed, and pile hole is kept unobstructed. If borehole wall convergence, spalling, local loosening, increased seepage, or superimposed unloading of adjacent pile holes occurs, the unsupported exposed height should be reduced immediately or excavation should be suspended. Construction should be resumed after temporary steel casing, segmented support, drainage interception, or low-pressure grouting is completed. Low-pressure grouting adopts a low-pressure, segmented, multi-cycle method, and the control condition is that the existing platform and track structure must not be lifted.
[0060] In this embodiment, the present invention constructs a precise engineering response matrix for early warning, alarm, and control, completely eliminating the uncertainty of traditional construction decisions that rely on subjective experience to make stoppage and resumption decisions. The light-load control zone at the orifice and the material layout requirements physically isolate the construction load from interference with the existing line; the lifting control conditions of low-pressure grouting ensure that the reinforcement measures themselves do not become a new source of disturbance. The mandatory application of progressively degrading conditions ensures that the safety factor is absolutely met before construction resumes.
[0061] Furthermore, according to one embodiment of the present invention, when all monitoring indicators of the four types of control units are in normal condition, the increments of each indicator in two or more consecutive monitoring cycles are less than or equal to the corresponding increment warning value and do not continue to increase, the unrecovered deformation in two consecutive train passage periods is less than or equal to the corresponding warning value and does not continue to increase, and there are no new through cracks in the retaining wall, no visible collapse or continuous blockage in the hole wall, the current segment is determined to be closed and released; the closure record is updated to the digital construction safety ledger for feedback and correction of subsequent construction parameters and protection measures.
[0062] In this implementation, the final closure and release of a single construction section must simultaneously meet five conditions: ① All four control unit indicators are normal; ② The increments for two or more consecutive cycles are less than the warning value and do not increase; ③ The unrecovered deformation during two consecutive train passes is stable and does not increase; ④ There are no through cracks in the retaining wall, no collapse or continuous spalling of the borehole wall; ⑤ The seepage is lower than the warning value and there is no sudden water inrush. After meeting these standards, all information for this section, including pile number, segment number, soil layer type, excavation advance, excavation and retaining wall time, retaining wall parameters, train running windows, cumulative monitoring values and increments, rate of change, continuous growth trend, unrecovered deformation after train passage, comprehensive disturbance level, handling measures, retest results, and release conclusion, is written into the digital construction safety ledger. This ledger is not a simple archive record, but directly serves as core input data. Based on the maximum single-item level, comprehensive disturbance level, level change process, and abnormal handling results of the completed pile holes in the ledger, the system actively provides feedback to correct the construction batches, excavation advances, monitoring frequencies, and protection measures for subsequent pile holes.
[0063] In this implementation, the traditional isolated single-point construction is upgraded to a chain-like closed loop. Through real-time feedback from digital ledgers, the success or failure experience of previous piles is directly transformed into optimization parameters for subsequent piles, thus constructing a dynamically iterative and self-evolving safe construction system.
[0064] Furthermore, to achieve the above objectives, the present invention also provides a safety control system for the construction of manually excavated bored piles at high-speed railway platforms during operation, comprising: The control unit and the preset load determination module divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds. Based on the train operation load of each track, the module determines the preset unfavorable operation load combination for construction risk prediction. The excavation unloading coupled risk prediction module establishes a three-dimensional numerical model including four types of control units and the stratum. It uses a preset unfavorable operating load combination as the load boundary condition and simulates the segmented excavation and retaining wall construction process under the load boundary condition. It extracts the displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of load boundary condition and excavation unloading. The qualified criterion is that the response of the four types of control units is lower than the corresponding warning threshold and no plastic deformation zone that continuously develops from the pile hole to the track subgrade is formed. The segmented excavation advance is then determined. The single-section construction and monitoring feedback module excavates and constructs retaining walls in a segmented excavation sequence and in batches and at intervals. During the construction process, monitoring data from four types of control units are collected simultaneously. The monitoring data includes the monitoring response values of the train passing window. The integrated disturbance classification and dynamic adjustment module determines the integrated disturbance level of four control units based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes. When the integrated disturbance level is in a normal state, the train is allowed to proceed to the next section of construction. When the integrated disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceedance are implemented, and the retest results are fed back to update subsequent construction parameters and protection measures after the retest.
[0065] The above-mentioned safety control system for the construction of manually excavated bored piles at high-speed railway platforms during the operation period, according to the present invention, can realize the above-mentioned safety control method for the construction of manually excavated bored piles at high-speed railway platforms during the operation period. The specific process steps are as described above and will not be repeated here.
[0066] Furthermore, to achieve the above objectives, the present invention also provides an electronic device, including a processor, a memory, and a computer program stored in the memory and executable on the processor. When the computer program is executed by the processor, it implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation as described above.
[0067] Furthermore, to achieve the above objectives, the present invention also provides a computer-readable storage medium storing a computer program, which, when executed by a processor, implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation, as described above.
[0068] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely one preferred embodiment of the invention and are only used to explain the invention. They do not limit the scope of protection of the invention. All other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this invention.
[0069] Example 1
[0070] This embodiment is implemented in the following order: parameter acquisition and load combination determination, excavation unloading risk prediction, layered variable advance and single-section closure, multi-source monitoring and disturbance classification, and abnormal handling and closure release.
[0071] For the renovation and expansion project of high-speed railway platforms during the operation period, the existing platform structure, track and track structure, train operating load, power amplification factor, and number of manually excavated bored piles (N) are obtained from design documents, survey data, track data, and construction organization. p Pile diameter D, pile length L of the p-th pile p Enlarged head diameter D b Minimum clearance d from pile hole to existing line min , retaining wall structure, construction batch, number of tracks Nt The parameters include track structure hierarchy, geological and groundwater parameters, track geometric datum, and three-level thresholds for early warning, alarm, and control, where p = 1, 2, ..., N. p The above parameters are all determined based on the proposed project; this embodiment does not limit the values to specific projects.
[0072] A three-dimensional calculation model was established based on the spatial relationship between the pile hole and the existing platform, track, and roadbed. The bottom surface constrained three-dimensional displacement, the lateral boundary constrained normal displacement, and the top surface was set as a free boundary. The lateral and longitudinal calculation domains were progressively expanded until the changes in the maximum vertical displacement of the platform, the maximum horizontal displacement of the track, and the extent of the plastic zone around the pile hole compared to the previous calculation domain were all no greater than 5%. Based on this, the significant impact range of excavation unloading and the final boundary location were determined. Locally refined meshes were used around the pile hole, at the platform edge, along the track load zone, and at the soil interface.
[0073] For track j, the standard uniform line load w is determined based on the design train load. j Dynamic amplification factor γ d,j Determined based on train speed, track structure type, track smoothness, and design documents or railway technical standards; equivalent load-bearing width of the roadbed top surface, b. j The design value should be used first, or b can be used. j =b 0,j +2∑ m k=1 t k ·tanα k Calculate, where m is the number of layers involved in load diffusion, and b 0,j The effective lateral load-bearing width at the bottom of the sleeper, t k and α k These represent the thickness and design diffusion angle of the k-th layer, including the ballast layer and the subgrade surface layer. (q) s,j =w j / b j and q eq,j =γ d,j ·q s,j Calculate the maximum equivalent static load and apply it to the corresponding track load zones respectively; for multi-track operation conditions, the simultaneous action of each load zone is taken as the preset unfavorable operating load combination.
[0074] The calculation first completes the initial ground stress balance and resets the initial displacement to zero, then inputs the preset unfavorable operating load combination; for the upper loose fill or unloading sensitive strata, multiple candidate segmented excavation lengths are set from small to large according to the specifications, and the entire process of manually excavated bored pile construction is simulated according to the construction sequence of excavating the soil in the segmented hole, activating the upper section of the retaining wall first, and then excavating the next section. The first batch of multiple manually excavated bored piles can be excavated in segments at the maximum design pile length simultaneously as the upper limit calculation condition for determining h1, and the corresponding maximum equivalent static load is applied simultaneously in each track load zone; the upper limit condition is only used for risk prediction, and the on-site construction is still carried out in batches, alternate holes, and staggered sequence. Extract the maximum vertical displacement, the maximum displacement in two horizontal directions, the maximum total displacement, the vertical stress, the equivalent strain, and the equivalent plastic strain of each process step to identify the construction risk links; take the fact that the response of the four types of control units is lower than the corresponding warning threshold and no plastic deformation zone that continuously develops from the pile hole to the track subgrade as the qualification criterion, and take the maximum value among the qualified candidate advance as the first segment excavation advance h1.
[0075] Table 1 General Parameter Acquisition and Control Applications
[0076] After completing parameter acquisition, determining the pre-set unfavorable operating load combination, and predicting the excavation unloading risk, the layered advance is determined and single-section closure construction is organized in the following manner.
[0077] like Figure 2 As shown, the first segment excavation advance h1 is adopted for the upper loose fill or unloading sensitive strata. After entering the lower, more stable strata, candidate advances greater than h1 are reviewed according to the simulation method and qualification criteria for excavation-unloading coupling risk prediction, and the maximum value among the qualified candidate advances is determined as the second segment advance h2. h2 is adopted only when the previous section of the retaining wall meets the strength and quality requirements specified in the design or construction plan, there is no convergence or spalling of the borehole wall, the seepage volume has not increased, the monitoring indicators of the four control units of pile hole, platform, track and subgrade are all below the corresponding warning thresholds, and no plastic deformation zone continuously developing from the pile hole to the track and subgrade has formed; if any condition is not met, h1 is maintained or a smaller advance is adopted. The first and second segment excavation advances should also be determined in combination with pile diameter, soil self-stabilizing capacity, allowable unsupported exposure height, groundwater conditions and construction monitoring response.
[0078] Establish a baseline advance condition and a layered variable advance condition, keeping the model, materials, loads, and boundary conditions consistent except for the advance parameters. Compare the number of excavation-walling cycles, maximum total displacement, maximum vertical displacement, maximum horizontal displacement in both directions, vertical stress, equivalent strain, and the connectivity of the plastic zone. Only when the responses of all four control units under the layered variable advance condition are below the corresponding warning thresholds, and no plastic deformation zone continuously extending from the pile hole to the track subgrade has formed, can these parameters be used for field optimization.
[0079] On-site, a monitoring baseline is first established at a test pile or test segment far from the track using the first segment excavation advance h1. After the single-segment closure condition is met, the second segment advance h2 is then used in the lower, more stable strata according to the above verification results. When any control unit's monitoring index reaches the warning level, or when the borehole wall shows convergence and spalling, increased seepage, or superimposed unloading of adjacent piles, h1 is immediately restored or a smaller advance is used. Each segment can only proceed to the next segment after excavation, wall protection, curing, monitoring verification, and closure release are completed.
[0080] Table 2. Comparison of Risk Prediction between Standard Progress and Layered Variable Progress
[0081] During the construction of a single section, multi-source monitoring is implemented in the following manner, and the monitored quantities are converted into a comprehensive disturbance level.
[0082] like Figure 3 and Figure 4 As shown, the platform control unit is equipped with monitoring systems for vertical displacement, horizontal displacement along the track direction, horizontal displacement perpendicular to the track direction, and structural cracks; the track control unit is equipped with monitoring systems for track alignment, track gauge, track surface elevation, track surface level, and settlement; the roadbed control unit is equipped with monitoring systems for settlement, lateral displacement, and drainage status; and the pile hole control unit is equipped with monitoring systems for borehole settlement, borehole perimeter convergence, wall cracks or strain, borehole wall spalling, and water seepage.
[0083] A stable baseline is established before construction, and records are made before each section of excavation, after excavation, after retaining wall construction, and before the next section of excavation. During ground transitions, enlarged head excavation, adjacent pile construction, increased rainfall or seepage, and before and after train passage, the monitoring frequency is increased to twice the normal frequency, and to four times the normal frequency when the overall disturbance reaches an alarm state. For train passage periods, the baseline value before passage, the response value during passage, and the recovery value after passage are recorded, and the unrecovered deformation after train passage is calculated, i.e., the absolute value of the difference between the recovery value after passage and the baseline value before passage. The monitoring cycle, sampling frequency, and instrument accuracy are determined based on the design documents, operational requirements, and construction monitoring plan.
[0084] The cumulative threshold C for the three levels of early warning, alarm, and control for each monitoring item i,k and incremental threshold ΔC i,k The values are determined by the design unit, railway operation and management unit, and construction monitoring plan, taking into account the line grade, structural condition, and allowable deformation. This invention does not use fixed engineering values. The i-th monitoring indicator is determined by r. i,k =max(|X i | / C i,k ,|ΔX i | / ΔC i,k Calculate the normalized response value for the k-th level; for each level, take the value that satisfies r.i,k The highest level is ≥1. When each r i,k If all values are less than 1 but the indicator increases in the same direction for two consecutive monitoring cycles, or if there is evidence of hole wall spalling, visible collapse, sudden increase in seepage, or continuous increase in deformation after a train passes without recovery, the level of this item will be raised by one level, but the maximum level will not exceed the control level; the comprehensive disturbance level G is the highest level among all individual levels, i.e., G = max(G1, G2, ..., G...). Nind ), where Nind is the total number of monitoring indicators.
[0085] Each segment's station number, segment number, soil type, excavation advance, excavation and wall protection time, wall protection parameters, train operation window, cumulative monitoring value and increment, rate of change, continuous growth trend, unrecovered deformation after train passage, comprehensive disturbance level, handling measures, re-measurement results, and release conclusion are recorded in a closed log. When any indicator reaches the warning level or is raised to the warning level due to continuous growth or borehole wall abnormalities, even if the alarm or control threshold has not yet been reached, warning handling must be initiated and the adjacent pile hole must be suspended from proceeding to the next segment.
[0086] Table 3 Multi-source monitoring indicators and three-level threshold settings
[0087] When the overall disturbance level reaches the warning, alarm, or control state, structural protection, abnormal handling, and closed-loop release shall be implemented in the following manner.
[0088] When the overall disturbance level is in a warning state, monitoring must be intensified, borehole loading must be limited, and the progress of adjacent pile holes into the next section must be suspended. When it is in an alarm state, excavation of the current section must be suspended and subsequent advances reduced. At least one targeted measure must be selected based on the cause of the anomaly: if the borehole wall converges, sags, or becomes locally loose, temporary steel casings or segmented supports must be installed and the wall protection completed promptly; if seepage or rainfall infiltration increases, interception and drainage and in-hole pumping must be implemented, and low-pressure grouting around the borehole may be used if necessary. When the situation reaches a control state or persistent, unrecoverable deformation occurs, the relevant pile holes must be suspended, the borehole wall must be sealed promptly, and at least one of the following measures must be selected: backfilling counterpressure, temporary support, or local reinforcement. If, after the measures are taken, the overall disturbance level is below the next lower level threshold for two consecutive monitoring cycles and there are no abnormalities in the borehole wall, wall protection, or seepage, the overall disturbance level will be reduced by one level.
[0089] A light-load control zone is set up near the borehole opening. Excavated soil, reinforcing cages, formwork, retaining materials, and construction machinery are placed away from the existing track and must not be piled up or parked for extended periods. Drainage is kept unobstructed around the platform, roadbed, and pile holes to prevent rainwater infiltration from reducing soil strength. Low-pressure grouting adopts a low-pressure, segmented, multi-cycle method, and the control condition is that the existing platform and track structure must not be lifted.
[0090] After handling any anomalies, multi-source monitoring and key period recording must be repeated, and the overall disturbance level must be re-determined. The four control units—piles, platforms, tracks, and roadbeds—must be re-measured. A closed record is only formed and the current segment or construction batch is allowed to proceed if: the overall disturbance level gradually decreases to the normal level; the increments of all parameters in two or more consecutive monitoring cycles are not greater than the corresponding warning values, and the subsequent cycle is not greater than the previous cycle; the unrecovered deformation during two consecutive train passage periods is not greater than the corresponding warning values, and the subsequent period is not greater than the previous period; there are no new through cracks in the retaining wall; there are no visible collapses or continuous spalling in the borehole wall; and the seepage is lower than the warning value with no sudden water inrush. Otherwise, handling and re-measurement continue. The closed record is used to update the advance, construction sequence, monitoring frequency, and protection measures for the next segment or pile.
[0091] Through the above implementation methods, train operating load, excavation unloading risk prediction, construction batches, layered advance, timely wall protection, multi-source monitoring and structural protection form an executable closed-loop chain.
[0092] According to the above-described scheme of the present invention, the present invention is applicable to the reconstruction and expansion of existing high-speed railway platforms during the operational period, and is particularly suitable for manually excavated bored pile construction where construction space is limited, the pile holes are adjacent to ballasted track, train operating loads are continuous, and the requirements for platform-subgrade-track deformation control are high. The required parameters can be obtained through conventional surveying, construction schemes, numerical analysis, track inspection, and construction monitoring. The segmented excavation, concrete retaining wall, temporary steel casing, drainage, low-pressure grouting, and backfill counterpressure adopted are all feasible engineering measures with good engineering application conditions.
[0093] Those skilled in the art will recognize that the modules and algorithm steps described in conjunction with the embodiments disclosed herein can be implemented using electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementations should not be considered beyond the scope of this invention.
[0094] Those skilled in the art will clearly understand that, for the sake of convenience and brevity, the specific working process of the above-described apparatus and equipment can be referred to the corresponding process in the foregoing method implementation, and will not be repeated here.
[0095] In the embodiments provided in this application, it should be understood that the disclosed apparatus and methods can be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative; for instance, the division of modules is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple modules or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces; the indirect coupling or communication connection between apparatuses or modules may be electrical, mechanical, or other forms.
[0096] The modules described as separate components may or may not be physically separate. The components shown as modules may or may not be physical modules; that is, they may be located in one place or distributed across multiple network modules. Some or all of the modules can be selected to achieve the objectives of the embodiments of the present invention, depending on actual needs.
[0097] In addition, the functional modules in the embodiments of the present invention can be integrated into one processing module, or each module can exist physically separately, or two or more modules can be integrated into one module.
[0098] If the aforementioned functions are implemented as software functional modules and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this invention, essentially, or the part that contributes to conventional solutions, or a portion of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the sending / receiving methods of various embodiments of this invention. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, ROM, RAM, magnetic disks, or optical disks.
[0099] The above description is merely a preferred embodiment of this application and an explanation of the technical principles employed. Those skilled in the art should understand that the scope of the invention involved in this application is not limited to technical solutions formed by specific combinations of the above-described technical features, but should also cover other technical solutions formed by arbitrary combinations of the above-described technical features or their equivalents without departing from the inventive concept. For example, technical solutions formed by substituting the above-described features with (but not limited to) technical features with similar functions disclosed in this application.
[0100] It should be understood that the sequence number of each step in the invention and its embodiments does not absolutely imply the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present invention.
Claims
1. A method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, characterized in that... include: Establish control units and determine preset loads: Divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds, and determine the preset unfavorable operating load combinations for construction risk prediction based on the train operation load of each track. Risk prediction of excavation unloading coupling: A three-dimensional numerical model including the four types of control units and the stratum is established. The preset unfavorable operating load combination is used as the load boundary condition. The segmented excavation and retaining wall construction process is simulated under the load boundary condition. The displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of the load boundary condition and excavation unloading are extracted. The qualified criterion is that the response of the four types of control units is lower than the corresponding warning threshold and no plastic zone deformation zone continuously developing from the pile hole to the track subgrade is formed. The segmented excavation advance is then determined. Single-section construction and monitoring feedback: Single-section excavation and wall construction are carried out in accordance with the segmented excavation advance and the batch and inter-hole sequence. During the construction process, monitoring data of four types of control units are collected simultaneously. The monitoring data includes the monitoring response value of the train passing window. Comprehensive disturbance classification and dynamic adjustment: Based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes, the comprehensive disturbance level of the four types of control units is determined; when the comprehensive disturbance level is in a normal state, the train is allowed to proceed to the next section of construction; when the comprehensive disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceeding the limit are implemented, and after the handling and retesting, the retesting results are fed back to update the subsequent construction parameters and protection measures.
2. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The preset unfavorable operating load combination is formed by independently applying the maximum equivalent static load corresponding to each track to its respective track load zone. The maximum equivalent static load is determined by multiplying the static load converted from the train's self-weight by the dynamic amplification factor; the dynamic amplification factor is determined based on the train's operating speed, track structure type, and track smoothness of the corresponding track.
3. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 2, is characterized in that... The maximum equivalent static load is determined by the following formula: q eq,j = γ d,j · q s,j ; Where, q eq,j Let q be the maximum equivalent static load of the j-th track load zone. s,j For the static load converted from the train's own weight, γ d,j γ is the power amplification factor; d,j Based on the train speed, track structure type, track smoothness, and design documents or current railway technical standards for track j, when multiple train speeds or train types exist for the same track, the corresponding γ is used. d,j The maximum value in; the static load q converted from the train's self-weight. s,j =w j / b j Determined, where w j Let b be the standard uniformly distributed line load of the j-th track. j b is the equivalent load-bearing width of the top surface of the roadbed after the load has diffused through the sleepers, ballast layer, and subgrade surface; j The load diffusion angle method or a validated numerical load diffusion analysis is used to determine the values given in the design documents.
4. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The bottom surface of the three-dimensional numerical model is constrained by triaxial displacement, the lateral boundary is constrained by normal displacement, and the top surface is a free boundary. The significant impact range of excavation unloading is determined by sensitivity analysis of the computational domain boundary. The convergence criterion of the sensitivity analysis is: when the relative changes in the maximum vertical displacement of the platform, the maximum horizontal displacement of the track, and the range of the plastic zone around the hole are all less than or equal to a preset ratio, the expanded computational domain is compared with the previous level computational domain.
5. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The construction organization of the single-section construction adopts a combination of trial and control methods, starting from the farthest point and proceeding to the nearest. Adjacent pile holes in the same batch are excavated in a staggered manner, and adjacent holes are constructed in a staggered order. Furthermore, adjacent pile holes in the same construction batch must not be in a state of excavation without wall protection at the same time. When the comprehensive disturbance level of any pile hole reaches the alarm level, the pile holes in the same batch that are close to the existing track will suspend the excavation of the next section.
6. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... Based on the geological stability zoning revealed by the exploration, after excavation enters the lower, more stable strata, the candidate excavation advances that are larger than the current segmented excavation advances are reviewed according to the excavation unloading coupling risk prediction to determine the increased segmented excavation advances. The increased segmented excavation advances are only adopted when the previous section of the retaining wall has passed the acceptance test, there is no convergence or spalling of the borehole wall and an increase in water seepage, and the monitoring values of the four types of control units are lower than the corresponding warning thresholds.
7. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The key time periods for synchronously collecting monitoring data include at least: before each section of excavation, after excavation, after wall protection, before the next section of excavation, at the stratum transition position, during the enlarged head excavation stage, during the construction stage of adjacent pile holes, and during the train passage period; for the train passage period, the baseline value before passage, the response value during passage, and the recovery value after passage are recorded, and the unrecovered deformation after the train passes is the absolute value of the difference between the recovery value after passage and the baseline value before passage.
8. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The determination of the overall disturbance level includes: Three-level cumulative thresholds for early warning, alarm, and control are set for each monitoring indicator, as well as three-level incremental thresholds for early warning, alarm, and control. For early warning, alarm, and control, the normalized response value is calculated based on the corresponding cumulative threshold and incremental threshold: r i,k =max(|X i | / C i,k ,|ΔX i | / ΔC i,k ), k∈{early warning, alarm, control}; Among them, X i Let ΔX be the cumulative value of the i-th monitoring indicator. i For the increment between adjacent monitoring periods, C i,k and ΔC i,k These are the cumulative threshold and incremental threshold of the i-th monitoring indicator at level k, respectively; the level of the i-th monitoring indicator is determined by satisfying r. i,k The highest level is ≥1; when each r i,k If all values are less than 1 but the monitoring indicator increases in the same direction for two consecutive monitoring cycles, or if there is a blockage in the borehole wall, visible collapse, a sudden increase in water seepage, or a continuous increase in deformation after a train passes through without recovery, the monitoring indicator will be upgraded by one level, but the maximum level shall not exceed the control level; the comprehensive disturbance level shall be the highest level among the monitoring indicator levels.
9. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... The structural protection and anomaly handling measures are matched according to the comprehensive disturbance level: under normal conditions, construction continues according to the current parameters and the borehole load limit is implemented; under the warning level, monitoring is intensified, borehole load is limited, and the excavation of adjacent pile holes in the same batch to the next segment is suspended; under the alarm level, the subsequent excavation of the current segment is suspended, the excavation progress of subsequent segments is reduced, and temporary support or interception and drainage measures are implemented; under the control level, the construction of the relevant pile holes is stopped, the borehole wall is sealed, and backfilling and counterpressure or local reinforcement are implemented; after the treatment, if all monitoring indicators are lower than the threshold of the next level for two consecutive monitoring cycles and there are no abnormalities in the borehole wall, retaining wall, or seepage, the comprehensive disturbance level is reduced by one level.
10. The method for safety control during the construction of manually excavated bored piles for high-speed railway platforms in operation, as described in claim 1, is characterized in that... When all monitoring indicators of the four types of control units are in normal condition, the increments of each indicator in two or more consecutive monitoring cycles are less than or equal to the corresponding increment warning value and do not continue to increase, the unrecovered deformation in two consecutive train passage periods is less than or equal to the corresponding warning value and does not continue to increase, and there are no new through cracks in the retaining wall, no visible collapse or continuous blockage in the hole wall, the current segment is determined to be closed and released; the closure record is updated to the digital construction safety ledger for feedback and correction of subsequent construction parameters and protection measures.
11. A safety control system for manually excavated bored pile construction at high-speed railway platforms during operation, characterized in that, include: The control unit and the preset load determination module divide the construction impact area into four types of control units: pile holes, platforms, tracks and roadbeds. Based on the train operation load of each track, the module determines the preset unfavorable operation load combination for construction risk prediction. The excavation unloading coupled risk prediction module establishes a three-dimensional numerical model including the four types of control units and the stratum. The preset unfavorable operating load combination is used as the load boundary condition. Under the load boundary condition, the segmented excavation and retaining wall construction process is simulated. The displacement, stress, strain and plastic zone distribution of the four types of control units under the combined action of the load boundary condition and excavation unloading are extracted. The qualified criterion is that the response of the four types of control units is lower than the corresponding early warning threshold and no plastic zone deformation zone continuously developing from the pile hole to the track subgrade is formed. The segmented excavation advance is then determined. The single-section construction and monitoring feedback module excavates and constructs retaining walls in accordance with the segmented excavation advance and the sequence of batch and inter-hole excavation. During the construction process, monitoring data of four types of control units are collected simultaneously. The monitoring data includes the monitoring response value of the train passing window. The integrated disturbance classification and dynamic adjustment module determines the integrated disturbance level of four control units based on the cumulative values of each monitoring indicator obtained through monitoring data, the increment of adjacent monitoring cycles, the rate of change, and the unrecovered deformation after the train passes. When the integrated disturbance level is in a normal state, the train is allowed to proceed to the next section of construction. When the integrated disturbance level exceeds the limit, structural protection and abnormal handling measures matching the level of exceedance are implemented, and the retest results are fed back to update subsequent construction parameters and protection measures after the retest.
12. An electronic device, characterized in that, The method includes a processor, a memory, and a computer program stored in the memory and executable on the processor. When executed by the processor, the computer program implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation, as described in any one of claims 1-10.
13. A computer-readable storage medium, characterized in that, A computer program is stored on the computer-readable storage medium, and when the computer program is executed by a processor, it implements the safety control method for manually excavated bored pile construction of high-speed railway platforms during operation, as described in any one of claims 1-10.