A construction technique for fully wrapping drainage pipes with premixed fluidized solidified soil.
By using a bottom flexible support layer and dynamic feedback control in the construction of drainage pipes wrapped in fluidized solidified soil, the problems of buoyancy and lateral pressure of the pipes during the process of wrapping in fluidized solidified soil were solved, realizing active control of the pipe posture and full-section compaction, thus improving construction stability and quality.
Patent Information
- Application Number
- CN202611374498.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-07
- Publication Date
- 2026-11-17
AI Technical Summary
Existing construction techniques neglect dynamic buoyancy and asymmetric lateral pressure during the process of wrapping drainage pipes with fluidized solidified soil, resulting in pipe floating, lateral displacement, and local voids, which affect installation accuracy and compactness.
The construction process employs a bottom flexible support layer, dynamic feedback wrapping on both sides, and pipe waist locking. By monitoring the liquid level, pipe displacement, and buoyancy in real time, the feeding rate is dynamically adjusted to form symmetrical clamping and static locking. After solidification, the top of the pipe is sealed.
It significantly improves the accuracy of pipeline installation and the tightness of full-section wrapping, ensuring the pipeline is under stress balance during the self-flowing filling process of fluidized solidified soil, thereby enhancing construction stability and project quality.
Smart Images

Figure CN123109261A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of construction technology for backfilling trenches for municipal drainage pipelines, specifically to a construction process for wrapping the entire cross-section of drainage pipelines with premixed fluidized solidified soil. Background Technology
[0002] Premixed fluidized bed soil, due to its good fluidity, strong self-compacting properties, and certain strength after hardening, has been gradually applied in drainage pipeline trench backfilling projects to replace traditional sand and gravel backfilling or plain soil compaction. Current construction methods typically use pumping equipment to inject the fluidized bed soil into the pipeline in one go or in layers, or to pour it simultaneously from both sides, relying on the material's own fluidity to fill the space at the bottom, sides, and top of the pipeline, in order to form a full-section wrap around the pipeline.
[0003] However, existing technologies often focus on the smooth delivery and filling of fluidized solidified soil during actual construction, neglecting the dynamic buoyancy and asymmetric lateral pressure exerted on the pipeline by the fluidized solidified soil during the wrapping process. When pouring continuously in one go or at the same rate on both sides, the difference in liquid level between the fluidized solidified soil on both sides of the pipeline and the buoyancy acting on the pipeline continuously change with the pouring process. This can cause the pipeline to float, shift laterally, or even experience partial detachment at the bottom before effective constraints are formed, severely affecting the pipeline installation accuracy and backfill compaction. Therefore, it is necessary to improve the construction process of wrapping drainage pipelines with fluidized solidified soil across the entire cross-section to achieve active control of the pipeline's posture during the pouring process.
[0004] In response to this problem, this application proposes a construction process that uses pre-mixed fluidized solidified soil to fully encase the drainage pipe, thereby solving the aforementioned issues. Summary of the Invention
[0005] The purpose of this invention is to provide a construction process for wrapping drainage pipes with premixed fluidized solidified soil across the entire cross section, in order to solve the problem that existing technologies often focus on the smooth delivery and filling of fluidized solidified soil, while neglecting the dynamic buoyancy and asymmetric lateral pressure generated by the fluidized solidified soil on the pipe during the wrapping process.
[0006] To achieve the above objectives, the present invention provides the following technical solution:
[0007] A construction process for fully encasing drainage pipes using pre-mixed fluidized solidified soil includes:
[0008] S1. Install the drainage pipe in the trench and obtain the initial centerline, elevation and lateral position of the pipe;
[0009] S2. Inject the first batch of premixed fluidized solidified soil between the bottom of the pipeline and the bottom of the trench to form a bottom flexible support layer, and make the liquid level of the bottom flexible support layer lower than the center line of the pipeline.
[0010] S3. Inject premixed fluidized solidified soil in layers on both sides of the pipeline, and obtain the liquid level height of the fluidized solidified soil, the lateral displacement of the pipeline, and the elevation of the pipeline in real time during the injection process.
[0011] Based on the height difference of the liquid level on the left and right sides, the lateral displacement of the pipeline, and the amount of buoyancy of the pipeline, the feeding rate on the left and right sides is dynamically adjusted so that the liquid level of the fluidized solidified soil on the left and right sides rises in a non-uniform manner until it reaches the height of the pipe waist on both sides, forming a symmetrical wrapping band on both sides.
[0012] S4. When the fluidized solidified soil on both sides reaches the height of the pipe waist, stop continuous injection or reduce the feeding rate so that the fluidized solidified soil on both sides forms symmetrical clamping in a static state, thus completing the pipe waist locking.
[0013] S5. Monitor the setting state of the fluidized solidified soil at the bottom and sides of the pipeline. When the preset setting conditions are met, inject the fluidized solidified soil into the top area of the pipeline to complete the full-section wrapping of the drainage pipeline.
[0014] Furthermore, in step S2, the height of the bottom flexible support layer is 1 / 5 to 1 / 3 of the outer diameter of the pipe, and is not higher than the center line of the pipe.
[0015] After step S2 is completed, the pipeline elevation and lateral position are remeasured. If the deviation exceeds the set value, it is corrected by bottom injection or lateral local injection.
[0016] Further, in step S3, the dynamic adjustment of the feeding rates on the left and right sides includes:
[0017] When the difference in liquid level between the left and right sides exceeds the first threshold, reduce the feeding rate on the side with the higher liquid level and increase the feeding rate on the side with the lower liquid level.
[0018] When the lateral displacement of the pipeline exceeds the second threshold, increase the feeding rate on the opposite side of the pipeline displacement or form support on the opposite side of the displacement in advance, while reducing the feeding rate on the same side of the displacement.
[0019] Furthermore, the first threshold is a liquid level difference ≤ 50 mm; the second threshold is a lateral displacement of the pipe ≤ 10 mm or ≤ 1% of the pipe's outer diameter.
[0020] Furthermore, in step S3, when the pipeline rise exceeds the preset rise threshold or the pipeline inclination exceeds the preset inclination threshold, the material supply rate on both sides is reduced or the injection is paused, and fluidized solidified soil is preferentially injected into the bottom of the pipeline to enhance bottom constraint.
[0021] Furthermore, in step S4, the height of the pipe waist is 1 / 2 to 2 / 3 of the height of the outer walls on both sides of the pipe;
[0022] The pipe waist locking includes stopping continuous injection and waiting, so that the fluidized solidified soil on both sides enters the pre-setting stage or the fluidity is reduced to a preset value.
[0023] Further, in step S5, the preset condensation conditions are:
[0024] The penetration resistance of the fluidized solidified soil at the bottom and sides of the pipeline reaches 0.1 to 0.5 MPa, or 60% to 90% of the initial setting time.
[0025] Furthermore, in step S2, the fluidity of the solidified soil used in the bottom support layer is 140–180 mm;
[0026] In steps S3 and S5, the fluidity of the solidified soil on both sides and the top of the pipe is 180-260 mm, and the fluidity of the solidified soil used in the bottom support layer is less than that of the solidified soil on both sides and the top of the pipe.
[0027] Further, in step S3, the material supply ratio on the left and right sides is determined as follows:
[0028] After normalizing the left and right liquid level difference Δh, the pipe lateral displacement δ, the pipe inclination angle θ, and the pipe buoyancy H, respectively, the following is applied:
[0029]
[0030] Calculate the package status index I, where a, b, c, and d are weighting coefficients;
[0031] Adjust the feeding rates on the left and right sides in opposite directions based on the sign and magnitude of I.
[0032] Furthermore, before step S5, the process also includes: roughening or spraying interface slurry on the solidified soil surfaces on both sides.
[0033] After step S5 is completed, the solidified soil on the top and sides of the pipe is covered with a membrane for curing, and then the trench is backfilled.
[0034] Compared with existing technologies, this invention provides a construction process for fully wrapping drainage pipes with pre-mixed fluidized solidified soil. This invention establishes a phased wrapping path of "bottom flexible support—dynamic feedback wrapping on both sides—pipe waist locking—pipe top delayed closure," transforming the flow process of the fluidized solidified soil around the pipe into an active control process of the pipe's attitude. During construction, the material supply rate on both sides is dynamically adjusted according to the difference in liquid level on the left and right sides, the lateral displacement of the pipe, and its upward floating trend. This ensures that the pipe remains in a state of force balance during the self-flowing filling process of the fluidized solidified soil, fundamentally suppressing pipe floating, lateral displacement, and local voids at the bottom of the pipe, significantly improving the pipe installation accuracy and the tightness of the full-section wrapping.
[0035] This invention utilizes the time-dependent nature of fluidized solidified soil. Symmetrical clamping is first formed at the pipe waist height and then statically locked. The pipe top is then sealed only after the solidified soil on both sides and the bottom has reached a certain solidification state. This "fix first, then seal" delayed sealing method avoids the additional buoyancy and disturbance to the unconstrained pipeline caused by the fluidized solidified soil at the top of the pipe in traditional continuous grouting. It allows the pipeline to gradually acquire increasing constraint stiffness throughout the solidification process, significantly improving the construction stability and engineering quality reliability of large-diameter, lightweight pipelines under high groundwater level conditions. Attached Figure Description
[0036] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this invention. For those skilled in the art, other drawings can be obtained based on these drawings.
[0037] Figure 1 This is a construction process flow diagram of using premixed fluidized solidified soil to wrap the entire cross-section of a drainage pipe, as provided in an embodiment of the present invention. Detailed Implementation
[0038] To enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.
[0039] As attached Figure 1 As shown:
[0040] Example 1:
[0041] I. Project Overview
[0042] A municipal drainage pipeline project uses DN800 reinforced concrete drainage pipes with an outer diameter of 960mm, a wall thickness of 80mm, a single pipe section length of 2.0m, a pipe burial depth of 3.5m, a trench bottom width of 1.6m, and groundwater level 0.8m above the trench bottom. After trench excavation, lightweight wellpoint dewatering is used, and a 100mm thick medium-coarse sand cushion layer is laid at the bottom of the trench for leveling.
[0043] II. The material parameters of premixed fluidized solidified soil are shown in Table 1 below;
[0044] Table 1
[0045] Material <![CDATA[Mix proportion (kg / m 3 )]]> Cement (P·O 42.5) 180 Fly ash (Grade II) 120 Fine sand (fineness modulus 1.8) 950 water 320 Polycarboxylate superplasticizer 2.0 Bentonite 15
[0046] Flowability of the bottom-supported solidified soil: 160mm;
[0047] Flowability of the solidified soil on both sides and at the top of the pipe: 220mm;
[0048] Initial setting time: 4 hours;
[0049] Final setting time: 8 hours;
[0050] 28-day unconfined compressive strength: ≥1.0MPa.
[0051] III. Construction Steps and Data:
[0052] S1. Piping Installation and Initial State Acquisition:
[0053] The DN800 reinforced concrete pipe was hoisted into the trench and installed according to the design centerline and elevation. The pipe joints were connected using socket joints and sealed. After installation, a total station and level were used to re-measure the pipes.
[0054] Lateral deviation of pipe centerline: 0mm;
[0055] Pipeline elevation deviation: +2mm;
[0056] Pipe inclination angle: 0°.
[0057] S2. Construction of the bottom flexible support layer:
[0058] The first batch of premixed fluidized solidified soil is injected between the bottom of the pipeline and the bottom of the trench using a pumping device. The soil is slowly injected from one end of the pipeline using a single-sided conduit, so that the fluidized solidified soil flows evenly at the bottom of the pipeline.
[0059] Target liquid level height: 250mm (approximately 1 / 4 of the pipe's outer diameter, 480mm below the pipe's centerline);
[0060] Actual liquid level after injection: 255mm;
[0061] Pipeline elevation deviation remeasured: +3mm;
[0062] The lateral deviation of the pipeline was remeasured: 1 mm;
[0063] No pipe floating occurred.
[0064] After the bottom flexible support layer is formed, the bottom of the pipeline is evenly supported by the fluidized solidified soil, but not to the center line, so as to avoid generating too much buoyancy too early.
[0065] S3, Dynamic feedback wrapping on both sides:
[0066] Feed pipes are arranged on the left and right sides of the pipeline, and level sensors, pipeline displacement gauges and tilt sensors are installed.
[0067] In the initial stage, the feeding rate on both the left and right sides is 0.4m. 3 / min. When the liquid level on the left reaches 550mm and the liquid level on the right reaches 510mm, the following is detected:
[0068] The height difference between the left and right liquid levels is Δh = 40mm (less than the first threshold of 50mm, but close).
[0069] The lateral displacement of the pipeline δ = a leftward offset of 5mm (less than the second threshold of 10mm, but still requires attention);
[0070] Pipeline buoyancy H = 3mm;
[0071] The pipe inclination angle θ = 0.2°.
[0072] Because the pipeline has shifted to the left and the liquid level on the left is slightly higher, the following adjustments are made based on the feedback control logic:
[0073] The feeding rate on the left side is 0.4m 3 / min decreased to 0.25m 3 / min;
[0074] The feeding rate on the right side is 0.4m 3 / min increased to 0.55m 3 / min.
[0075] After another 20 minutes of injection, the detection data became:
[0076] Liquid level on the left: 640mm;
[0077] Liquid level on the right side: 635mm;
[0078] The height difference between the left and right liquid levels is Δh = 5mm (restored to a value much less than 50mm);
[0079] Lateral displacement of the pipeline δ = offset to the left by 1mm;
[0080] Pipeline buoyancy H = 2mm;
[0081] The pipe inclination angle θ = 0.05°.
[0082] At this point, the liquid level of the fluidized solidified soil on both sides reaches the height of the pipe waist (approximately 2 / 3 of the pipe's outer diameter, i.e., 640mm), and continuous injection on both sides stops, entering the pipe waist locking stage.
[0083] S4, Waist Locking:
[0084] After stopping material supply from both sides, allow the mixture to stand for 30 minutes. During this period, the fluidity of the solidified soil decreases from 220 mm to approximately 150 mm, entering the pre-setting stage. The solidified soil on both sides of the pipeline forms a symmetrical clamp, and the lateral and elevation of the pipeline no longer change. The measured lateral displacement remains at 1 mm, and the elevation deviation remains at +3 mm.
[0085] Once the pipe waist is locked, the pipe's posture is effectively constrained.
[0086] S5, delayed capping at the top of the pipe:
[0087] Monitor the penetration resistance of the fluidized solidified soil at the bottom and sides:
[0088] Penetration resistance of the bottom support layer: 0.35 MPa;
[0089] Penetration resistance of the left-side encapsulation layer: 0.30 MPa;
[0090] Penetration resistance of the right-side encapsulation layer: 0.32 MPa;
[0091] It reaches about 70% of the initial setting time.
[0092] After the preset solidification conditions are met, fluidized solidified soil is injected into the top area of the pipe, and poured in one go to 300mm above the top of the pipe to form a full-section wrap.
[0093] After the top of the pipe is sealed, the surface of the solidified soil is covered with a film for 7 days for curing, and then the trench is backfilled.
[0094] IV. Effect Testing
[0095] The results were measured after 28 days of curing, as shown in Table 2 below;
[0096] Table 2
[0097] Testing items Test results Standard requirements Lateral deviation of pipeline centerline ≤5mm ≤15mm Pipeline elevation deviation ≤10mm ≤15mm Pipeline buoyancy ≤5mm ≤10mm Pipe bottom void area none none 28-day compressive strength of solidified soil 1.2MPa ≥0.8MPa Backfill density ≥97% ≥95%
[0098] The water tightness test passed on the first attempt, and there was no leakage in the pipeline.
[0099] Example 2:
[0100] I. Project Overview:
[0101] A stormwater drainage project uses DN1200 HDPE double-wall corrugated pipes with an outer diameter of 1200mm, ring stiffness SN8, a burial depth of 4.0m, and a trench bottom width of 2.4m. The groundwater level is high, with groundwater visible 0.5m below the trench bottom. This lightweight pipe is buoyancy-sensitive and is constructed using a full-section wrapping method with pre-mixed fluidized bedpan.
[0102] II. The material parameters of premixed fluidized solidified soil are shown in Table 3 below:
[0103] Table 3
[0104] Material <![CDATA[Mix proportion (kg / m 3 )]]> Cement (P·O 42.5) 160 Fly ash (Grade II) 140 fine sand 900 water 310 Polycarboxylate superplasticizer 1.8 Bentonite 20
[0105] Flowability of the bottom support layer solidified soil: 150mm;
[0106] Flowability of the solidified soil on both sides and at the top of the pipe: 200mm;
[0107] Initial setting time: 5 hours;
[0108] Final setting time: 10 hours;
[0109] 28-day unconfined compressive strength: ≥0.8MPa.
[0110] III. Construction Steps and Data:
[0111] S1. Pipeline installation:
[0112] Hoist the DN1200 HDPE double-wall corrugated pipe to the design position. The lateral deviation of the pipe centerline is 0mm, and the elevation deviation is -2mm.
[0113] S2. Construction of the bottom flexible support layer:
[0114] Fluidized solidified soil was injected into the bottom of the pipe, with a target liquid level of 350mm (approximately 1 / 3 of the pipe's outer diameter, 600mm below the pipe's centerline). The actual liquid level was 360mm. A re-measurement showed a pipe elevation deviation of -1mm and a lateral deviation of 0mm, indicating no upward movement.
[0115] S3, Dynamic feedback wrapping on both sides:
[0116] The initial feeding rate on both the left and right sides is 0.6m. 3 / min.
[0117] When the liquid level on the left side reached 900 mm and the liquid level on the right side reached 750 mm, monitoring revealed:
[0118] The height difference between the left and right liquid levels is Δh = 150 mm (exceeding the first threshold of 50 mm).
[0119] The lateral displacement of the pipeline δ = offset to the left by 12mm (exceeding the second threshold of 10mm).
[0120] Pipeline uplift H = 5mm;
[0121] The pipe inclination angle θ = 0.5°.
[0122] Based on the feedback control logic, the following adjustments will be implemented immediately:
[0123] The feeding rate on the left side is 0.6m 3 / min decreased to 0.2m 3 / min;
[0124] The feeding rate on the right side is 0.6m 3 / min increased to 0.8m 3 / min;
[0125] Pause material supply on the left side for 1 minute;
[0126] Add 0.1m of water to the bottom of the pipe. 3 Fluidized solidified soil enhances bottom constraint.
[0127] After adjustment, continue injection for 10 minutes, and then check the data:
[0128] Liquid level on the left: 1000mm;
[0129] Liquid level on the right side: 980mm;
[0130] The difference in liquid level between the left and right sides is Δh = 20 mm;
[0131] Lateral displacement of the pipeline δ = offset to the left by 3mm;
[0132] Pipeline buoyancy H = 2mm;
[0133] The pipe inclination angle θ = 0.1°.
[0134] Continue adjusting the left and right feeding rates until the liquid levels on both sides rise synchronously to a pipe waist height of 800mm (2 / 3 of the pipe's outer diameter). At this point, the difference in liquid level between the left and right sides is 10mm, the pipe shifts laterally by 2mm, and the upward displacement is 2mm. Stop the injection and enter the pipe waist locking phase.
[0135] S4, Waist Locking:
[0136] After stopping the material supply, the mixture was allowed to stand for 45 minutes. During this period, the fluidity of the solidified soil decreased from 200 mm to 140 mm, and the penetration resistance reached 0.20 MPa, approaching initial setting. Stable clamping was formed on both sides of the pipe, and the pipe did not shift further.
[0137] S5, delayed capping at the top of the pipe:
[0138] When the penetration resistance of the solidified soil at the bottom and both sides reaches 0.25 to 0.40 MPa and 60% to 80% of the initial setting time, the top of the pipe is capped and poured to 350 mm above the top of the pipe.
[0139] Subsequently, a membrane was applied for curing. Before applying the membrane, the surface of the pipe top was slightly roughened to enhance the interlayer bonding.
[0140] IV. Effect Testing:
[0141] After 28 days of curing, the results are shown in Table 4 below;
[0142] Table 4
[0143] Testing items Test results Standard requirements Lateral deviation of pipeline centerline ≤6mm ≤20mm Pipeline elevation deviation ≤10mm ≤20mm Pipeline buoyancy ≤8mm ≤15mm Pipe bottom void area none none 28-day compressive strength of solidified soil 0.9MPa ≥0.6MPa Backfill density ≥96% ≥95%
[0144] The pipeline inspection showed no deformation or leakage, and the project passed quality acceptance.
[0145] Comparative example:
[0146] I. Project Overview:
[0147] The DN1200 HDPE double-wall corrugated pipe rainwater pipeline project is the same as that in Example 2. The trench size, groundwater level, material mix ratio and pipe specifications are the same. However, the traditional "simultaneous equal speed continuous pouring to the top of the pipe" process is adopted. The bottom support layer is not constructed in stages, feedback control is not performed, and the pipe waist is not locked and the capping is delayed.
[0148] II. Construction Steps:
[0149] After the pipeline is installed, direct current to both sides of the pipeline at the same speed of 0.6m. 3 The fluidized solidified soil is continuously injected at a rate of / min until the liquid level reaches 350mm above the top of the pipe, completing the full-section wrapping in one go.
[0150] During the pouring process, the difference in liquid level between the left and right sides, the displacement of the pipeline, and the material supply rate were not monitored in real time.
[0151] After the pouring was completed, the pipe was left to cure statically without locking the pipe waist or sealing the pipe top.
[0152] Cover and cure for 7 days, then backfill the trench.
[0153] III. Phenomena and Data During Construction:
[0154] During the continuous pouring process, the following was discovered (as recorded in the post-construction traceability log):
[0155] When the liquid level on the left reaches 850mm, the liquid level on the right is only 720mm, and the height difference between the left and right liquid levels is 130mm.
[0156] The pipeline showed a significant leftward shift, with a maximum lateral displacement of 25 mm.
[0157] The maximum pipe float is 30mm;
[0158] The maximum pipe inclination angle is 1.2°;
[0159] Local voids appeared at the bottom of the pipe, with a maximum void depth of about 40 mm.
[0160] Because no dynamic adjustments were made, the difference in liquid level between the left and right sides continued to widen, and the pipeline was subjected to uneven lateral pressure and buoyancy in the fluidized solidified soil, resulting in loss of attitude control.
[0161] IV. Effect Testing:
[0162] The results were measured after 28 days of curing, as shown in Table 5 below.
[0163] Table 5
[0164] Testing items Comparative test results Standard requirements Is it qualified? Lateral deviation of pipeline centerline 22mm ≤20mm Unqualified Pipeline elevation deviation 35mm ≤20mm Unqualified Pipeline buoyancy 28mm ≤15mm Unqualified Pipe bottom void area Partial delamination, maximum depth 40mm none Unqualified 28-day compressive strength of solidified soil 0.8MPa ≥0.6MPa qualified Backfill density 92% ≥95% Unqualified
[0165] Pipeline endoscopic inspection revealed localized voids at the bottom of the pipe, leading to uneven settlement and minor leaks at the joints. This comparative project requires rework, increasing both project costs and time.
[0166] The effects of Example 1, Example 2, and the comparative example are summarized in Table 6 below;
[0167] Table 6
[0168] Comparison Projects Example 1 (DN800 reinforced concrete pipe) Example 2 (DN1200 HDPE pipe) Comparative Example 1 (DN1200 HDPE pipe, traditional process) Lateral displacement ≤5mm ≤6mm 22mm Elevation deviation ≤10mm ≤10mm 35mm Pipeline buoyancy ≤5mm ≤8mm 28mm Pipe bottom detachment none none Partial delamination, maximum depth 40mm Backfill density ≥97% ≥96% 92% 28-day compressive strength 1.2MPa 0.9MPa 0.8MPa Quality assessment qualified qualified Unqualified, requires rework
[0169] As shown in the table above, the "bottom flexible support - dynamic feedback wrapping on both sides - pipe waist locking - pipe top hysteresis sealing" process of the present invention can significantly suppress the floating, displacement and local voiding of the pipeline during the full-section wrapping of the fluidized solidified soil, ensuring the stability of the pipeline posture and the full-section dense wrapping, with reliable construction quality, and has obvious technical advantages and engineering application value.
[0170] As can be seen from the above, this invention transforms the flow process of fluidized solidified soil around the pipeline into an active control process of pipeline attitude by establishing a phased wrapping path of "bottom flexible support - dynamic feedback wrapping on both sides - pipe waist locking - pipe top hysteresis sealing". During construction, the material supply rate on both sides is dynamically adjusted according to the difference in liquid level on the left and right sides, the lateral displacement of the pipeline and the upward floating trend, so that the pipeline is always in a state of force balance during the self-flowing filling process of fluidized solidified soil. This fundamentally suppresses pipeline floating, lateral displacement and local voids at the bottom of the pipe, and greatly improves the pipeline installation accuracy and the full-section wrapping tightness.
[0171] This invention utilizes the time-dependent nature of fluidized solidified soil. Symmetrical clamping is first formed at the pipe waist height and then statically locked. The pipe top is then sealed only after the solidified soil on both sides and the bottom has reached a certain solidification state. This "fix first, then seal" delayed sealing method avoids the additional buoyancy and disturbance to the unconstrained pipeline caused by the fluidized solidified soil at the top of the pipe in traditional continuous grouting. It allows the pipeline to gradually acquire increasing constraint stiffness throughout the solidification process, significantly improving the construction stability and engineering quality reliability of large-diameter, lightweight pipelines under high groundwater level conditions.
[0172] The foregoing has only described certain exemplary embodiments of the present invention by way of illustration. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the foregoing drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
Claims
1. A construction process for full-face wrapping of a drainage pipeline using ready-mixed fluidified soil, characterized in that, include: S1. Install the drainage pipe in the trench and obtain the initial centerline, elevation and lateral position of the pipe; S2. Inject the first batch of premixed fluidized solidified soil between the bottom of the pipeline and the bottom of the trench to form a bottom flexible support layer, and make the liquid level of the bottom flexible support layer lower than the center line of the pipeline. S3. Inject premixed fluidized solidified soil in layers on both sides of the pipeline, and obtain the liquid level height of the fluidized solidified soil, the lateral displacement of the pipeline, and the elevation of the pipeline in real time during the injection process. Based on the height difference of the liquid level on the left and right sides, the lateral displacement of the pipeline, and the amount of buoyancy of the pipeline, the feeding rate on the left and right sides is dynamically adjusted so that the liquid level of the fluidized solidified soil on the left and right sides rises in a non-uniform manner until it reaches the height of the pipe waist on both sides, forming a symmetrical wrapping band on both sides. S4. When the fluidized solidified soil on both sides reaches the height of the pipe waist, stop continuous injection or reduce the feeding rate so that the fluidized solidified soil on both sides forms symmetrical clamping in a static state, thus completing the pipe waist locking. S5. Monitor the setting state of the fluidized solidified soil at the bottom and sides of the pipeline. When the preset setting conditions are met, inject the fluidized solidified soil into the top area of the pipeline to complete the full-section wrapping of the drainage pipeline.
2. The construction process for wrapping a drainage pipe with pre-mixed fluidized solidified soil across its entire cross-section according to claim 1, characterized in that, In step S2, the height of the bottom flexible support layer is 1 / 5 to 1 / 3 of the outer diameter of the pipe, and not higher than the center line of the pipe; After step S2 is completed, the pipeline elevation and lateral position are remeasured. If the deviation exceeds the set value, it is corrected by bottom injection or lateral local injection.
3. The construction process for wrapping a drainage pipe with premixed fluidized solidified soil across its entire cross-section according to claim 1, characterized in that, In step S3, the dynamic adjustment of the feeding rates on the left and right sides includes: When the difference in liquid level between the left and right sides exceeds the first threshold, reduce the feeding rate on the side with the higher liquid level and increase the feeding rate on the side with the lower liquid level. When the lateral displacement of the pipeline exceeds the second threshold, increase the feeding rate on the opposite side of the pipeline displacement or form support on the opposite side of the displacement in advance, while reducing the feeding rate on the same side of the displacement.
4. The construction process for wrapping a drainage pipe with premixed fluidized solidified soil across its entire cross-section according to claim 3, characterized in that, The first threshold is a liquid level difference ≤ 50 mm; the second threshold is a pipe lateral displacement ≤ 10 mm or ≤ 1% of the pipe outer diameter.
5. The construction process for wrapping a drainage pipe across its entire cross-section using pre-mixed fluidized solidified soil as described in claim 1, characterized in that... In step S3, when the pipeline rise exceeds the preset rise threshold or the pipeline inclination exceeds the preset inclination threshold, the material supply rate on both sides is reduced or the injection is paused, and fluidized solidified soil is injected first to the bottom of the pipeline to enhance bottom constraint.
6. The construction process for full-face wrapping of drainage pipes using ready-mixed fluidified solidified soil according to claim 1, characterized in that, In step S4, the height of the pipe waist is 1 / 2 to 2 / 3 of the height of the outer walls on both sides of the pipe; The pipe waist locking includes stopping continuous injection and waiting, so that the fluidized solidified soil on both sides enters the pre-setting stage or the fluidity is reduced to a preset value.
7. The construction process for full-face wrapping of drainage pipes using ready-mixed fluidified solidified soil according to claim 1, characterized in that, In step S5, the preset condensation conditions are: The penetration resistance of the fluidized solidified soil at the bottom and sides of the pipeline reaches 0.1 to 0.5 MPa, or 60% to 90% of the initial setting time.
8. The construction process for full-face wrapping of a drainage pipeline using ready-mixed fluidified solidified soil according to claim 1, characterized in that, In step S2, the fluidity of the solidified soil used in the bottom support layer is 140–180 mm. In steps S3 and S5, the fluidity of the solidified soil on both sides and the top of the pipe is 180-260 mm, and the fluidity of the solidified soil used in the bottom support layer is less than that of the solidified soil on both sides and the top of the pipe.
9. The construction process for full-face wrapping of a drainage pipeline using ready-mixed fluidified solidified soil according to claim 1, characterized in that, In step S3, the material supply ratio on the left and right sides is determined as follows: After normalizing the left and right liquid level difference Δh, the pipe lateral displacement δ, the pipe inclination angle θ, and the pipe buoyancy H, respectively, the following is applied: Calculate the package status index I, where a, b, c, and d are weighting coefficients; Adjust the feeding rates on the left and right sides in opposite directions based on the sign and magnitude of I.
10. The construction process for wrapping a drainage pipe across its entire cross-section using pre-mixed fluidized solidified soil, as described in claim 1, is characterized in that... Before step S5, the process also includes: roughening or spraying interface slurry on the solidified soil surfaces on both sides; After step S5 is completed, the top of the pipe and the solidified soil on both sides are covered with a membrane for curing, and then the trench is backfilled.