A wedge-lock grouting connection assembly for coarse aggregate UHPC slab components
The design of the wedge-lock grouting connection component solves the problems of synchronous alignment and uneven grout distribution in multi-layer structures in plate component connections, realizing active joint sealing and uniform grout injection, thus improving connection quality and construction efficiency.
Patent Information
- Application Number
- CN202611611909.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-19
- Publication Date
- 2026-11-17
AI Technical Summary
In the existing process of connecting plate components, it is difficult to synchronously guide and actively close the multi-layer connection structure. There is a lack of stable mechanical locking before grouting. The connection load is easily concentrated in a local position. The formwork structure at the bottom of the connection joint is independent of the grouting channel, making the operation complicated and the grout distribution uneven.
The wedge-lock grouting connection assembly includes first and second force transmission connection boxes, staggered force transmission plates and vertical wedge locks. The wedge locks guide and tighten the multi-layer staggered force transmission plates. Combined with the spliced support distribution plate and grout receiving groove plate, a continuous force transmission path and a stable distribution channel are formed to ensure uniform distribution of grout.
It achieves active joint sealing and mechanical locking of plate components, reduces the concentration of connection loads, simplifies construction operations, and improves the uniformity of grout filling and the overall quality of connection nodes.
Smart Images

Figure CN123109290A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of building construction technology, and specifically to a wedge-lock grouting connection assembly for coarse aggregate UHPC slab components. Background Technology
[0002] Coarse aggregate ultra-high performance concrete has high compressive strength, crack resistance, and durability, making it suitable for manufacturing precast slab components. To facilitate transportation, hoisting, and on-site assembly, large-sized slab structures are typically broken down into multiple precast slab components, which are then connected on-site using embedded connectors, mechanical fastening structures, or cast-in-place joints to form a whole.
[0003] Existing panel component connection structures typically involve pre-embedding steel plates, reinforcing rings, connector boxes, or plug-in fittings at the connection ends of two panel components. After on-site butt jointing, the connection is completed using pins, bolts, welding, or grouting. When using multi-layered steel plates or staggered reinforcing bars for connection, due to dimensional errors and installation deviations that occur during prefabrication, transportation, and hoisting, the through-holes or plug-in positions of multi-layered connectors are difficult to accurately align at once. On-site adjustments to the panel component positions are usually necessary, making the connection operation quite difficult.
[0004] Some connection structures use ordinary cylindrical pins or bolts to pass through multiple layers of connectors. These connectors mainly serve the functions of insertion and preventing detachment, but it is difficult to simultaneously correct the positions of connectors at different heights during insertion, and it is also difficult to actively move the two plate components closer together. When there is still a large installation gap between the two plate components, ordinary pins cannot actively eliminate the gap. Before grouting, temporary clamps, supports, or external traction equipment are still needed to maintain the position of the plate components, increasing the on-site construction steps.
[0005] Furthermore, the loads of existing multi-layer connectors are typically concentrated on a single connector plate, local welds, or a small number of anchors, which can easily lead to localized stress concentrations in the interface between the embedded connection structure and the coarse aggregate ultra-high performance concrete (UHPC). While dense reinforcement or steel plates are used to improve anchorage capacity, this can obstruct the flow of coarse aggregate during precasting, making it difficult for the coarse aggregate to fully penetrate the interior and back side of the anchorage structure. This can negatively impact the compactness of the concrete surrounding the embedded connection structure and the stability of load transfer.
[0006] After the initial connection of adjacent slab components is completed, it is usually necessary to inject connecting grout into the joint formed between the two connection ends. Current construction methods often involve erecting a separate bottom formwork below the joint and securing it to the bottom of the two slab components using supports, top rods, or bolts. For slab components with large installation heights, limited operating space below, or long joints, the installation, leveling, and dismantling of the bottom formwork are difficult. Furthermore, gaps can easily form between the bottom formwork and the bottom surface of the slab component due to surface errors, leading to grout leakage during pressure grouting.
[0007] In existing joint seams, the bottom formwork typically only serves to seal and support the grout, with the grouting pipeline, distribution structure, and bottom formwork operating independently. When the grout enters the joint through a single grouting port, it tends to rise preferentially along areas of lower flow resistance, potentially leading to uneven grout distribution on both sides of the joint bottom, between multiple connecting plates, and around the embedded box. Furthermore, when the grout is injected directly from the top or a specific location, air may be trapped at the bottom of the joint or between intersecting connecting structures, creating air pockets, cavities, or unfilled areas.
[0008] Although some structures are equipped with bottom flow channels or slurry distribution tanks, these flow channels are usually pre-sealed independent channels that lack a matching relationship with the bottom template of the joint. The bottom template cannot be used to simultaneously complete the flow channel sealing, flow channel support, and joint sealing. There is no structural correlation between the installation status of the bottom template and whether the distribution path is complete. When the connectors are not fully locked or the bottom template is not pressed tightly, the slurry is difficult to be stably transported along the set path, and leakage, deviation, or insufficient local filling may occur.
[0009] Therefore, there is a need for a connection component for coarse aggregate UHPC slab components, which enables multi-layer connection structures to complete layer-by-layer alignment, active joint closing, and mechanical locking under the action of the same component. It also enables the structure responsible for locking and load transfer to participate in grout distribution simultaneously. Furthermore, it is necessary to ensure that the grout-bearing component at the bottom of the connection joint directly cooperates with the distribution structure to form a stable left and right grout distribution channel while completing bottom sealing and sealing, thereby improving the uniformity of grout filling from the bottom of the connection joint upwards and the overall construction quality of the connection node. Summary of the Invention
[0010] The purpose of this application is to provide a wedge-lock grouting connection assembly for coarse aggregate UHPC slab components, in order to solve the problems in the existing slab component connection process, such as the difficulty in synchronously guiding and actively closing the multi-layer connection structure, the lack of stable mechanical locking before grouting, and the tendency of the connection load to concentrate at a local connection position; at the same time, it solves the problems in the existing connection joint bottom formwork structure and grouting channel being independent of each other, the formwork operation being complicated, the bottom sealing stability being insufficient, and the grout easily concentrating at a single position and causing insufficient local filling.
[0011] To achieve the above objectives, this application provides the following technical solution: a wedge-lock grouting connection assembly for coarse aggregate UHPC slab components, comprising a first force-transmitting connection box and a second force-transmitting connection box respectively disposed at the connection ends of a first slab component and a second slab component. The first and second force-transmitting connection boxes are respectively provided with a plurality of first staggered force-transmitting plates and a plurality of second staggered force-transmitting plates. The two sets of staggered force-transmitting plates alternately interspersed along the thickness direction of the slab component and are jointly provided with vertical wedge-locking members for bringing the two force-transmitting connection boxes closer together. The lower parts of the two force-transmitting connection boxes are respectively provided with a first splicing support distribution plate and a second... The two-piece support distribution plate has a vertical wedge locking component with an injection channel and two discharge holes. The bottom of each of the two-piece support distribution plates has a lower opening distribution groove. When the vertical wedge locking component moves down into place, the two discharge holes are connected to the two lower opening distribution grooves respectively. A grout receiving plate is set below the two-piece support distribution plates. After the grout receiving plate is inserted along the length of the joint, it seals the bottom of the joint and the lower openings of the two lower opening distribution grooves. Thus, the vertical wedge locking component can complete the alignment of the multi-layer staggered force transmission plate and the active joint closing of the two plate components, and the grout receiving plate can complete the bottom sealing of the joint and the formation of the distribution path.
[0012] Furthermore, the first force transmission connection box includes a first embedded box body, and a plurality of first staggered force transmission plates are spaced apart along the height direction of the first embedded box body. The second force transmission connection box includes a second embedded box body, and a plurality of second staggered force transmission plates are spaced apart along the height direction of the second embedded box body. A first insertion interval is formed between two adjacent first staggered force transmission plates for inserting a second staggered force transmission plate, and a second insertion interval is formed between two adjacent second staggered force transmission plates for inserting a first staggered force transmission plate. After the plurality of first staggered force transmission plates and the plurality of second staggered force transmission plates are connected, they are continuously and alternately arranged along the thickness direction of the plate component. Thus, a multi-layer staggered force transmission relationship can be formed, increasing the effective force transmission area of the connection node.
[0013] Furthermore, each first staggered force transmission plate is provided with a first wedge lock channel, and each second staggered force transmission plate is provided with a second wedge lock channel. Multiple first wedge lock channels and multiple second wedge lock channels are arranged vertically in correspondence. The side of the first wedge lock channel away from the first embedded box forms a first inclined bearing surface, and the side of the second wedge lock channel away from the second embedded box forms a second inclined bearing surface. When the vertical wedge lock member moves downward, it squeezes the first inclined bearing surface and the second inclined bearing surface respectively. Thus, the downward force on the vertical wedge lock member can be converted into a lateral force that drives the two force transmission connecting boxes to move closer to each other, thereby realizing the active joint closing of the two plate components.
[0014] Furthermore, the vertical wedge lock is provided with a lower guiding section, a middle wedge tightening section, and an upper limiting section in sequence from bottom to top. The lateral dimension of the lower guiding section is smaller than the initial passing dimension of the first wedge lock channel and the second wedge lock channel. The lateral dimension of the middle wedge tightening section gradually increases from bottom to top. Locking inclined surfaces that cooperate with the first inclined bearing surface and the second inclined bearing surface are formed on both sides of the middle wedge tightening section. The lateral dimension of the upper limiting section is larger than the passing dimension of the first wedge lock channel and the second wedge lock channel. Thus, the lower guiding section can correct multiple wedge lock channels layer by layer, the middle wedge tightening section can apply a wedge tightening effect to multiple layers of staggered force transmission plates simultaneously, and the upper limiting section can limit the final downward movement position of the vertical wedge lock.
[0015] Furthermore, a circumferential limiting groove is provided at the lower part of the vertical wedge lock. The opposite sides of the first and second assembled support distribution plates form a first half-groove and a second half-groove, respectively. The groove walls of the first and second half-grooves are respectively provided with semi-annular limiting edges. After the two assembled support distribution plates are assembled, the first and second half-grooves together form the lock groove. The two semi-annular limiting edges enter the circumferential limiting groove, thereby restricting the vertical wedge lock from exiting upward and restricting the vertical wedge lock from swaying laterally within the connection node.
[0016] Furthermore, the injection channel extends axially along the vertical wedge lock, and the upper end of the injection channel penetrates the upper limiting section to form an injection port. Two discharge holes are located on opposite sides of the lower guiding section and below the circumferential limiting groove. A first distribution inlet is provided on the groove wall of the first half-groove, and a second distribution inlet is provided on the groove wall of the second half-groove. Both the first and second distribution inlets are elongated along the moving direction of the vertical wedge lock. Thus, the two discharge holes can correspond to the first and second distribution inlets respectively after the vertical wedge lock moves down to its position. The elongated distribution inlets can compensate for a small height error of the vertical wedge lock.
[0017] Furthermore, the two lower opening distribution channels are respectively a first lower opening distribution channel located at the bottom of the first splicing support distribution plate and a second lower opening distribution channel located at the bottom of the second splicing support distribution plate. The first lower opening distribution channel extends from the first distribution inlet toward the direction of the first plate-type component, and the second lower opening distribution channel extends from the second distribution inlet toward the direction of the second plate-type component. The upper part of the two lower opening distribution channels is respectively formed with multiple upward grout outlets communicating with the interior of the connecting joint. After the grout receiving plate closes the lower openings of the two lower opening distribution channels, the two lower opening distribution channels and the grout receiving plate together form distribution channels. Thus, the connecting grout can diffuse to both sides of the bottom of the connecting joint and fill upward from different positions through multiple upward grout outlets.
[0018] Furthermore, the bottom surfaces of both the first and second combined support distribution plates are higher than the bottom surfaces of the first and second plate components, and an insertion space extending along the length of the connecting joint is formed below the two combined support distribution plates. The bottom of each of the two combined support distribution plates is provided with a support plate guide, and the two sides of the grouting groove plate are respectively formed with insertion edges that slide with the support plate guide. After the grouting groove plate is inserted along the insertion space, it covers the bottom opening of the connecting joint between the two plate components. Thus, the grouting groove plate can be inserted from the end of the connecting joint, and the combined support distribution plates can guide, support, and position the height of the grouting groove plate.
[0019] Furthermore, an elastic sealing layer is provided on the upper surface of the grout-receiving trough plate, and at least one set of lifting ramps is provided along the length of the joint. The bottom of the first and second combined support distribution plates is provided with pressing ramps that correspond to the lifting ramps. When the grout-receiving trough plate approaches the final insertion position, the lifting ramps and pressing ramps squeeze each other, causing the grout-receiving trough plate to move upward and the elastic sealing layer to press the bottom of the two combined support distribution plates and the two plate components. Thus, the elastic sealing layer can be actively pressed at the end of the insertion of the grout-receiving trough plate, while sealing the bottom of the joint and the lower openings of the two lower opening distribution channels.
[0020] Furthermore, a first sector-shaped anchoring structure is provided on the side of the first embedded box away from the connection seam, and a second sector-shaped anchoring structure is provided on the side of the second embedded box away from the connection seam. Both the first and second sector-shaped anchoring structures include multiple anchoring ribs that radiate from the corresponding embedded box into the interior of the corresponding plate component. A coarse aggregate passage area is formed between adjacent anchoring ribs, which is connected to the casting space of the corresponding plate component. The anchoring ribs are aligned with the first or second staggered force transmission plate at the corresponding height along the height direction. Thus, the coarse aggregate UHPC can pass through the area between adjacent anchoring ribs and cover the anchoring ribs, while the load borne by the staggered force transmission plate is transferred to the anchoring ribs along the corresponding height.
[0021] The technical solution provided in this application has the following advantages compared with the prior art: 1. This application uses multiple first staggered force transmission plates and multiple second staggered force transmission plates to alternately intersect along the thickness direction of the plate component, and uses vertical wedge locks to sequentially complete the alignment and wedge tightening of the multi-layer wedge lock channel. This can convert the vertical force into a lateral force that drives the two plate components to move closer to each other, so that the two plate components actively close the joint and form a mechanical connection before grouting. At the same time, the two splicing support distribution plates splice together as the plate components move closer, and the vertical wedge locks are restricted from exiting by the semi-circular limiting edge and the circumferential limiting groove. This makes the vertical wedge locks, staggered force transmission plates, force transmission connection boxes and fan-shaped anchoring structures form a continuous force transmission path, reducing the possibility of the connection load being concentrated in a local position.
[0022] 2. This application uses the injection channel inside the vertical wedge lock and two discharge holes to deliver the connecting grout. After the vertical wedge lock moves down into place, the two discharge holes correspond to the first distribution inlet and the second distribution inlet, respectively. After the grout receiving plate is inserted along the length of the connecting joint, it simultaneously seals the bottom of the connecting joint and the lower openings of the first and second lower opening distribution channels, so that the two lower opening distribution channels and the grout receiving plate together form distribution channels. The elastic sealing layer is pressed upward by the lifting slope and the pressing slope, thereby reducing the traditional bottom formwork erection and top support operation, and allowing the connecting grout to fill upward from both sides of the bottom of the connecting joint, reducing the possibility of grout leakage, deviation, air cavitation and insufficient local filling. Attached Figure Description
[0023] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0024] Figure 1 This is a schematic diagram of the overall structure of the first plate-type component and the second plate-type component in the embodiments of this application; Figure 2 This is a schematic diagram of the structure of the first force transmission connection box and the second force transmission connection box in the embodiments of this application; Figure 3 This is a cross-sectional view of the first plate-type component and the second plate-type component in the embodiments of this application; Figure 4 This is a schematic diagram of the structure of the first and second pre-embedded boxes in the embodiments of this application; Figure 5 This is a schematic diagram of the structure of the first embedded box, the second embedded box, and the vertical wedge lock in this embodiment of the application; Figure 6 This is a schematic diagram of the vertical wedge locking component in an embodiment of this application; Figure 7 This is a schematic diagram of the structure of the first and second assembled support distribution plates in the embodiments of this application; Figure 8 This is a schematic diagram of the structure of the first force transmission connection box in the embodiments of this application; Figure 9 for Figure 8 Enlarged view of the structure of part A in the middle.
[0025] Explanation of icon numbers: 1. First plate-type component; 2. Second plate-type component; 3. First force transmission connection box; 31. First embedded box body; 32. First staggered force transmission plate; 33. First wedge lock channel; 34. First sector-shaped anchoring structure; 4. Second force transmission connection box; 41. Second embedded box body; 42. Second staggered force transmission plate; 43. Second wedge lock channel; 44. Second sector-shaped anchoring structure; 5. Vertical wedge locking component; 51. Lower guide section; 52. Middle wedge tightening section; 53. Upper limiting section; 54. Injection channel; 55. Discharge hole; 56. Circumferential limiting groove; 6. First assembly supporting the distribution plate; 7. Second assembled support distribution plate; 8. Grouting groove plate. Detailed Implementation
[0026] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0027] The present application will be further described below with reference to embodiments.
[0028] Example 1: See attached document Figure 1 - Figure 9 This first embodiment of the present application provides a wedge-lock grouting connection assembly for coarse aggregate UHPC slab components. The connection assembly is used for assembly positioning, active joint closing, mechanical locking, joint sealing and grouting between two adjacent coarse aggregate UHPC slab components.
[0029] This embodiment includes a first plate component 1 and a second plate component 2 arranged opposite to each other. Both the first plate component 1 and the second plate component 2 are prefabricated using coarse aggregate UHPC. After the first plate component 1 and the second plate component 2 are installed, their connecting end faces are arranged opposite to each other, and a connecting seam extending along the length direction of the plate component is formed between the two connecting end faces.
[0030] The first plate component 1 has a first force transmission connection box 3 embedded at its connection end, and the second plate component 2 has a second force transmission connection box 4 embedded at its connection end. The first force transmission connection box 3 and the second force transmission connection box 4 are arranged opposite each other along the width direction of the connection joint.
[0031] The first force transmission connection box 3 includes a first embedded box body 31, and the second force transmission connection box 4 includes a second embedded box body 41. The first embedded box body 31 and the second embedded box body 41 can be formed by welding steel plates, and connection openings are formed on the side facing the connection seam, respectively. The thickness of the steel plates used for the first embedded box body 31 and the second embedded box body 41 can be set to 8mm to 16mm, preferably 12mm.
[0032] The first embedded box 31 is provided with a plurality of first interlaced force transmission plates 32. The plurality of first interlaced force transmission plates 32 are spaced apart along the thickness direction of the first plate component 1. One end of the first interlaced force transmission plate 32 is fixedly connected to the first embedded box 31, and the other end extends into the connecting seam through the connecting opening of the first embedded box 31.
[0033] The second embedded box 41 is provided with a plurality of second staggered force transmission plates 42. The plurality of second staggered force transmission plates 42 are spaced apart along the thickness direction of the second plate member 2. One end of the second staggered force transmission plate 42 is fixedly connected to the second embedded box 41, and the other end extends into the connection seam through the connection opening of the second embedded box 41.
[0034] In this embodiment, four first staggered force transmission plates 32 are provided, and three second staggered force transmission plates 42 are provided. An interval is formed between two adjacent first staggered force transmission plates 32 for the insertion of a second staggered force transmission plate 42, and an interval is formed between two adjacent second staggered force transmission plates 42 for the insertion of a first staggered force transmission plate 32.
[0035] After the first plate component 1 and the second plate component 2 are initially connected, multiple first staggered force transmission plates 32 and multiple second staggered force transmission plates 42 are alternately inserted along the thickness direction of the plate component. The thickness of the first staggered force transmission plates 32 and the second staggered force transmission plates 42 can be set to 8mm to 16mm, preferably 12mm.
[0036] The net distance between two adjacent staggered force transmission plates on the same side is greater than the thickness of the staggered force transmission plate on the other side inserted within that distance. After the staggered force transmission plates on both sides are wedged together, a grouting gap is retained. For example, when the thickness of the staggered force transmission plate is 12mm, the net distance between two adjacent staggered force transmission plates on the same side can be set to 20mm to 30mm, preferably 22mm.
[0037] Each first staggered force transmission plate 32 is provided with a first wedge lock channel 33, and each second staggered force transmission plate 42 is provided with a second wedge lock channel 43. After the first plate component 1 and the second plate component 2 are initially connected, the multiple first wedge lock channels 33 and the multiple second wedge lock channels 43 correspond to each other in the vertical direction, and together form a multi-layer wedge lock channel through which the vertical wedge lock component 5 passes.
[0038] The first wedge lock channel 33 forms a first inclined pressure-bearing surface on the side away from the first pre-embedded box 31, and the second wedge lock channel 43 forms a second inclined pressure-bearing surface on the side away from the second pre-embedded box 41. The angle between the first inclined pressure-bearing surface and the second inclined pressure-bearing surface and the vertical direction can be set to 5° to 12°, preferably 8°.
[0039] The vertical wedge locking member 5 includes, from bottom to top, a lower guiding section 51, a middle wedge tightening section 52 and an upper limiting section 53. The lower end of the lower guiding section 51 forms an arc-shaped or chamfered inlet end, and its lateral dimension is smaller than the initial passage dimension of the first wedge locking channel 33 and the second wedge locking channel 43.
[0040] The middle wedge section 52 is located above the lower guide section 51. The lateral dimension of the middle wedge section 52 gradually increases from bottom to top. Locking slopes are formed on both sides of the middle wedge section 52 facing the first plate member 1 and the second plate member 2, respectively. The two locking slopes cooperate with the first inclined bearing surface and the second inclined bearing surface, respectively.
[0041] The upper limiting section 53 is located above the middle wedge section 52. Its lateral dimension is larger than the passage dimension of the first wedge lock channel 33 and the second wedge lock channel 43. After the vertical wedge lock 5 reaches the locking position, the upper limiting section 53 abuts against the uppermost staggered force transmission plate or the limiting surface set on the top of the connecting box to restrict the vertical wedge lock 5 from continuing to move downward.
[0042] A limiting structure is provided between adjacent first staggered force transmission plates 32 and second staggered force transmission plates 42. The limiting structure can be a limiting boss or a limiting strip fixed on the surface of the staggered force transmission plates, and its protrusion height can be set to 5mm to 10mm, preferably 8mm.
[0043] Each first staggered force transmission plate 32 can have two spaced-limiting bosses on its surface facing the adjacent second staggered force transmission plate 42. The two spaced-limiting bosses are located on both sides of the first wedge lock channel 33. The spaced-limiting bosses can be cylindrical or rectangular. When cylindrical bosses are used, their diameter can be set to 10mm to 20mm, preferably 14mm.
[0044] After the vertical wedge lock 5 reaches the locking position, the limiting structure abuts against the adjacent staggered force transmission plates, so that a grouting gap is maintained between the first staggered force transmission plate 32 and the second staggered force transmission plate 42, to prevent the staggered force transmission plates on both sides from being completely attached, and to allow the connecting grout to enter between the adjacent staggered force transmission plates from around the limiting structure.
[0045] The lower part of the first pre-embedded box 31 is fixedly provided with a first splicing support distribution plate 6, and the lower part of the second pre-embedded box 41 is fixedly provided with a second splicing support distribution plate 7.
[0046] The first combined support distribution plate 6 and the second combined support distribution plate 7 are both located below the staggered force transmission plate and extend into the connection seam from the corresponding pre-embedded box. The bottom surfaces of the first combined support distribution plate 6 and the second combined support distribution plate 7 are higher than the bottom surfaces of the first plate member 1 and the second plate member 2, so as to form a space below them for the insertion of the grouting groove plate 8.
[0047] The first assembled support distribution plate 6 forms a first half-groove on the side facing the second assembled support distribution plate 7, and the second assembled support distribution plate 7 forms a second half-groove on the side facing the first assembled support distribution plate 6.
[0048] The lower guide section 51 of the vertical wedge lock 5 adopts a cross section that is compatible with the lock slot at least at the height of the first assembled support distribution plate 6 and the second assembled support distribution plate 7, and a circumferential limiting groove 56 is provided on the outer periphery of this part.
[0049] Both the first half-slot and the second half-slot adopt a groove body that is adapted to the shape of the corresponding part of the vertical wedge lock 5. The groove walls of the first half-slot and the second half-slot respectively form limiting edges that extend toward the circumferential limiting groove 56.
[0050] Before the first plate component 1 and the second plate component 2 have finished closing the joint, the first splicing support distribution plate 6 and the second splicing support distribution plate 7 are separated from each other. The distance between the two limiting edges is greater than the maximum lateral dimension of the corresponding part of the lower guide section 51 of the vertical wedge lock 5, so that the vertical wedge lock 5 can pass downward between the two half slots.
[0051] When the vertical wedge lock 5 moves downward and causes the two plate components to approach each other, the first assembled support distribution plate 6 and the second assembled support distribution plate 7 approach the corresponding pre-embedded box synchronously.
[0052] The joining positions of the first and second combined support distribution plates 6 and 7, the height of the circumferential limiting groove 56, and the lower stop position of the upper limiting section 53 correspond to each other. When the upper limiting section 53 reaches the lower stop position, the center height of the circumferential limiting groove 56 corresponds to the center height of the two semi-circular limiting edges.
[0053] As the first and second assembled support distribution plates 6 and 7 continue to approach the plate-type components, the two semi-circular limiting edges enter the circumferential limiting groove 56 from the opposite sides of the vertical wedge lock 5, and the first and second half-grooves together form the lock groove.
[0054] The vertical width of the circumferential limiting groove 56 can be set to 8mm to 12mm, preferably 10mm, and the groove depth of the circumferential limiting groove 56 can be set to 3mm to 5mm, preferably 4mm. An assembly gap of 0.3mm to 0.8mm is maintained between the limiting edge and the circumferential limiting groove 56.
[0055] After the two semi-circular limiting edges enter the circumferential limiting groove 56, they can restrict the vertical wedge lock 5 from exiting upwards. The first half-groove and the second half-groove together restrict the vertical wedge lock 5 from swinging laterally, and the upper limiting section 53 restricts the vertical wedge lock 5 from continuing to move downwards.
[0056] The lower end of the vertical wedge lock 5 terminates above the bottom surface of the first combined support distribution plate 6 and the second combined support distribution plate 7, and does not extend into the insertion space of the grouting trough plate 8, so as to avoid motion interference between the vertical wedge lock 5 and the grouting trough plate 8.
[0057] The vertical wedge locking member 5 has an injection channel 54 extending along its axial direction inside. The upper end of the injection channel 54 passes through the upper limiting section 53 and forms an injection inlet. The inner diameter of the injection channel 54 can be set to 12mm to 20mm, preferably 16mm.
[0058] The lower part of the vertical wedge lock 5 is provided with two discharge holes 55 that communicate with the injection channel 54. The two discharge holes 55 are arranged opposite to each other, with one discharge hole 55 facing the first splicing support distribution plate 6 and the other discharge hole 55 facing the second splicing support distribution plate 7.
[0059] The two discharge holes 55 are located below the circumferential limiting groove 56 and at the same height. The diameter of the discharge holes 55 can be set to 6mm to 10mm, preferably 8mm.
[0060] The inner wall of the first half-slot is provided with a first flow distribution inlet corresponding to one of the discharge holes 55, and the inner wall of the second half-slot is provided with a second flow distribution inlet corresponding to the other discharge hole 55.
[0061] Both the first and second distribution inlets can be configured as elongated oval openings extending vertically, with a vertical length greater than the diameter of the discharge hole 55, to compensate for the slight height error generated during the installation of the vertical wedge lock 5.
[0062] Elastic sealing gaskets can be installed around the periphery of the first and second distribution inlets. After the first and second combined support distribution plates 6 and 7 are assembled, the elastic sealing gaskets press against the outer surface of the vertical wedge lock 5 to reduce leakage of the connecting slurry from the mating position between the discharge hole 55 and the distribution inlet into the lock groove. The elastic sealing gaskets are part of the sealing structure of the distribution inlet and are not separately labeled.
[0063] When the vertical wedge lock 5 has not reached the locking position, the two discharge holes 55 have not formed a stable correspondence with the first distribution inlet and the second distribution inlet. When the vertical wedge lock 5 reaches the locking position, and the first combined support distribution plate 6 and the second combined support distribution plate 7 have completed the combination, the two discharge holes 55 correspond with the first distribution inlet and the second distribution inlet respectively.
[0064] The bottom surface of the first assembled support distribution plate 6 is provided with a first lower opening distribution groove extending from the first distribution inlet to the direction of the first plate component 1, and the bottom surface of the second assembled support distribution plate 7 is provided with a second lower opening distribution groove extending from the second distribution inlet to the direction of the second plate component 2.
[0065] Before the slurry receiving plate 8 is installed, both the first and second bottom opening distribution channels are in a downward open state. The width of the first and second bottom opening distribution channels can be set to 12mm to 25mm, preferably 18mm, and the channel depth can be set to 8mm to 15mm, preferably 10mm.
[0066] The upper part of the first and second lower opening distribution channels is provided with multiple upward slurry outlets. The multiple upward slurry outlets are spaced apart along the extension direction of the corresponding lower opening distribution channels and connect upward to the interior of the connecting joint.
[0067] The minimum net width of the upward slurry outlet is greater than the maximum particle size of the solid particles in the connecting slurry, preferably not less than 3 times the maximum particle size of the connecting slurry, in order to reduce the possibility of the upward slurry outlet being blocked.
[0068] The bottom of the first and second assembled support distribution plates 6 and 7 are respectively provided with support plate guides. The support plate guides can be support steps or L-shaped guide edges. Multiple sets of support plate guides are set at the same height along the length of the joint.
[0069] The grout-receiving groove plate 8 extends along the length of the joint, and each side of it is provided with an insert edge that slides with the guide part of the bearing plate. The grout-receiving groove plate 8 can be formed of a steel plate with a thickness of 6mm to 10mm, preferably with a thickness of 8mm.
[0070] The bearing plate guide restricts the lateral and height positions of the grouting groove plate 8 and bears part of the downward force transmitted by the grouting groove plate 8 during the grouting process.
[0071] An elastic sealing layer is provided on the upper surface of the grout receiving plate 8. The elastic sealing layer can be made of alkali-resistant rubber or elastic resin material, and its initial thickness can be set to 3mm to 5mm, preferably 4mm.
[0072] The guide section of the bearing plate reserves a lifting gap for the grouting groove plate 8 in the vertical direction, so that the grouting groove plate 8 can slide along the length of the joint during the initial insertion process and can move upward when it reaches the final position.
[0073] A lifting and fitting structure is provided between the grout receiving trough plate 8, the first assembled support distribution plate 6, and the second assembled support distribution plate 7. The lifting and fitting structure can be a lifting slope provided on the upper surface of the grout receiving trough plate 8 and a pressing slope provided at the bottom of the assembled support distribution plate.
[0074] The grouting trough plate 8 is provided with lifting slopes along the length of the joint, which correspond to the assembly support distribution plates of each group, so that when the grouting trough plate 8 approaches the final position, each lifting slope contacts the corresponding pressing slope.
[0075] As the grout-receiving trough plate 8 continues to move towards its final position, each lifting ramp moves upward synchronously under the action of the corresponding pressing ramp, causing the grout-receiving trough plate 8 to be lifted as a whole. The lifting amount of the grout-receiving trough plate 8 can be set to 1.5mm to 3mm, preferably 2mm.
[0076] After the grouting trough plate 8 is lifted, the compression of the elastic sealing layer can be set to 20% to 30% of its initial thickness, preferably 25%.
[0077] After the grout receiving plate 8 reaches its final position, its upper surface simultaneously covers the lower openings of the first lower opening distribution channel and the second lower opening distribution channel. The first lower opening distribution channel and the grout receiving plate 8 together form the first distribution channel, and the second lower opening distribution channel and the grout receiving plate 8 together form the second distribution channel.
[0078] The grouting trough plate 8 also covers the bottom opening of the connection joint between the first plate component 1 and the second plate component 2, and the elastic sealing layer presses the bottom surfaces of the first plate component 1, the second plate component 2, the first combined support distribution plate 6, and the second combined support distribution plate 7 respectively.
[0079] The grouting groove plate 8 has end sealing structures at both ends along the length of the joint to seal the two ends of the joint. The end sealing structures can be formed by end plates and sealing materials, and no separate structure number is set.
[0080] The first embedded box 31 is provided with a first fan-shaped anchoring structure 34 on the side away from the connecting seam, and the second embedded box 41 is provided with a second fan-shaped anchoring structure 44 on the side away from the connecting seam.
[0081] The first sector-shaped anchoring structure 34 and the second sector-shaped anchoring structure 44 both include multiple anchoring ribs that radiate from the corresponding pre-embedded box into the interior of the plate component, and a coarse aggregate passage area is formed between adjacent anchoring ribs.
[0082] The anchoring rib is aligned with the first staggered force transmission plate 32 or the second staggered force transmission plate 42 at the corresponding height along the height direction, so that the force borne by the staggered force transmission plate can be transmitted to the anchoring rib at the corresponding height through the corresponding embedded box.
[0083] The minimum clear distance between adjacent anchoring ribs shall not be less than 2.5 times the maximum nominal particle size of the coarse aggregate in the coarse aggregate UHPC, so that the coarse aggregate and slurry can enter the area between the anchoring ribs and the back side area of the anchoring ribs.
[0084] A top exhaust channel is formed above the first staggered force transmission plate 32 and the second staggered force transmission plate 42. The lower end of the top exhaust channel is connected to the interior of the connecting seam, and the upper end extends to the top of the connecting seam.
[0085] The top venting channel can be an vent hole, vent groove, or vent pipe, and its equivalent inner diameter can be set to 8mm to 16mm, preferably 12mm. The top venting channel is preferably set at the highest grouting position of the joint so that when the joint grout is filled from bottom to top, the air inside the joint can be smoothly discharged to the outside.
[0086] A top sealing member is provided at the top of the joint. The top sealing member is installed after grouting and venting are completed. It is used to cover the grouting inlet of the grouting channel 54, the top venting channel and the upper part of the vertical wedge locking member 5.
[0087] The top closure can be a long strip cover plate. The two sides of the top closure are supported on the top of the first plate member 1 and the second plate member 2 respectively. The top closure can be connected to the pre-embedded threaded sleeve by bolts, or it can be fixed by a mechanical snap-fit structure that can withstand the axial limiting force of the vertical wedge lock member 5.
[0088] The top closure has a limiting recess on the side facing the vertical wedge lock 5 that mates with the upper limiting section 53. After the top closure is installed, the upper limiting section 53 enters the limiting recess to further restrict the axial movement of the vertical wedge lock 5.
[0089] A sealing gasket can also be installed on the lower surface of the top seal. The sealing gasket presses against the top of the joint, the injection port, and the outlet of the top venting channel to reduce the entry of moisture and debris into the joint from the top of the joint.
[0090] The first plate component 1 and the second plate component 2 are prefabricated using coarse aggregate UHPC. The connecting grout injected into the joint on site is a high-flowability, low-shrinkage connecting grout. The maximum particle size of the connecting grout should be smaller than the minimum flow size of the injection channel 54, the discharge hole 55, the distribution inlet and the upward grout outlet.
[0091] The construction process in this embodiment is as follows.
[0092] First, during the prefabrication of the first plate component 1, the first force transmission connecting box 3, the first splicing support distribution plate 6, and the first fan-shaped anchoring structure 34 are fixed in the prefabrication mold.
[0093] The first splicing support distribution plate 6 is fixedly connected to the lower part of the first pre-embedded box 31, so that the first half slot faces the connection end and the first lower opening distribution groove faces the bottom of the plate component.
[0094] The first sector-shaped anchoring structure 34 extends from the first pre-embedded box 31 into the interior of the first plate component 1. When the coarse aggregate UHPC is poured, the coarse aggregate and grout enter the back side of the anchoring rib through the coarse aggregate passage area between adjacent anchoring ribs and cover the anchoring rib after curing.
[0095] The second plate component 2 is prefabricated in a manner corresponding to the first plate component 1, and the second force transmission connection box 4, the second splicing support distribution plate 7, and the second fan-shaped anchoring structure 44 are fixed in the corresponding positions.
[0096] During on-site installation, the first plate component 1 is hoisted to the set position, and then the second plate component 2 is moved so that the second staggered force transmission plate 42 enters between the adjacent first staggered force transmission plates 32.
[0097] After the two sets of staggered force transmission plates have completed their initial insertion, an installation gap is still maintained between the first plate component 1 and the second plate component 2, and the first assembled support distribution plate 6 and the second assembled support distribution plate 7 are in a separated state.
[0098] At this time, the first half-slot and the second half-slot have not yet formed a complete locking slot, and space is reserved between the two semi-circular limiting edges for the lower part of the vertical wedge lock 5 to pass through.
[0099] Subsequently, the vertical wedge lock 5 is inserted downward from the top of the joint, and the lower guide section 51 sequentially enters multiple first wedge lock channels 33 and second wedge lock channels 43.
[0100] When there is a small lateral deviation in the wedge lock channels at different heights, the inlet end of the lower guide section 51 contacts the inner wall of the wedge lock channel and pushes the corresponding staggered force transmission plate to produce a small range of lateral movement, so that the multi-layer wedge lock channels gradually return to the vertical correspondence.
[0101] The vertical wedge lock 5 continues to move downwards, and the middle wedge tightening section 52 enters the multi-layer wedge lock channel. The locking slopes on both sides of the middle wedge tightening section 52 respectively squeeze the first inclined bearing surface and the second inclined bearing surface.
[0102] The lateral force acting on the first staggered force transmission plate 32 causes the first force transmission connecting box 3 to move toward the second plate member 2, and the lateral force acting on the second staggered force transmission plate 42 causes the second force transmission connecting box 4 to move toward the first plate member 1.
[0103] The first force transmission connecting box 3 and the second force transmission connecting box 4 respectively drive the first plate component 1 and the second plate component 2 to move closer to each other, so that the width of the connection seam gradually decreases.
[0104] As the two plate components approach each other, the first assembled support distribution plate 6 and the second assembled support distribution plate 7 approach each other synchronously, and the lower part of the vertical wedge lock 5 is located between the first half slot and the second half slot.
[0105] When the limiting boss set between adjacent staggered force transmission plates abuts against the adjacent staggered force transmission plates, a set grouting gap is maintained between the first staggered force transmission plate 32 and the second staggered force transmission plate 42, and the two plate components reach the set connection position.
[0106] At the same time, the upper limiting section 53 reaches the lower stop position, the circumferential limiting groove 56 is at the same height as the two semi-annular limiting edges, the first splicing support distribution plate 6 and the second splicing support distribution plate 7 complete the splicing, and the two semi-annular limiting edges enter the circumferential limiting groove 56 respectively.
[0107] At this time, the first half-slot and the second half-slot together restrict the lateral movement of the vertical wedge lock 5, the two semi-circular limiting edges restrict the vertical wedge lock 5 from moving upward, and the upper limiting section 53 restricts the vertical wedge lock 5 from continuing to move downward.
[0108] After the first and second combined support distribution plates 6 and 7 are assembled, the two discharge holes 55 correspond to the first and second distribution inlets, respectively.
[0109] After the vertical wedge lock 5 is installed, grouting is not carried out immediately. At this time, the first and second lower opening distribution channels are still open downwards, and the bottom of the connection joint is not yet closed.
[0110] Subsequently, the grouting groove plate 8 is inserted from one end along the length of the joint. The insertion edges on both sides of the grouting groove plate 8 enter the bearing plate guide section and move along the insertion plate space below the first splicing support distribution plate 6 and the second splicing support distribution plate 7.
[0111] During the insertion of the front section of the grouting groove plate 8, an installation gap is maintained between the elastic sealing layer and the upper structure to reduce insertion resistance and wear of the sealing layer.
[0112] When the grout-receiving groove plate 8 approaches its final position, each of its lifting ramps contacts the corresponding pressing ramp, and continues to push the grout-receiving groove plate 8. Each lifting ramp moves along the pressing ramp, causing the grout-receiving groove plate 8 to be lifted upward as a whole.
[0113] After the grouting trough plate 8 is raised into place, the elastic sealing layer presses against the bottom surfaces of the first plate component 1, the second plate component 2, the first assembled support distribution plate 6, and the second assembled support distribution plate 7.
[0114] The grout-receiving trough plate 8 seals the bottom of the connection joint and seals the lower openings of the first and second lower opening distribution channels respectively, so that the two lower opening distribution channels form the first and second closed distribution channels respectively.
[0115] End sealing structures are installed at both ends of the joint to seal the bottom and both ends of the joint, while the top of the joint retains the injection port and the top venting channel.
[0116] Connect the external grouting equipment to the upper end of the grouting channel 54, and control the grouting pressure and grouting speed according to the construction requirements of the grouting material.
[0117] The connecting slurry flows from top to bottom along the injection channel 54, and after reaching the lower part of the vertical wedge lock 5, it is discharged through the two discharge holes 55 respectively.
[0118] One of the discharge holes 55 sends the connecting slurry into the first distribution channel, and the other discharge hole 55 sends the connecting slurry into the second distribution channel.
[0119] The connecting slurry diffuses along the two distribution channels to one side of the first plate component 1 and the other side of the second plate component 2, and enters the bottom of the connecting joint through multiple upward slurry outlets.
[0120] The connecting grout flows upward from different positions at the bottom of the connecting joint, sequentially filling the space above the splicing support distribution plate, the grouting gap between adjacent staggered force transmission plates, the space around the vertical wedge lock 5, and the upper space of the connecting joint.
[0121] As the connecting grout rises, it pushes the air inside the joint upwards, and the air is discharged through the top exhaust channel.
[0122] When the top venting channel continuously discharges grout and there are no obvious air bubbles in the discharged grout, stop grouting and seal the upper end of the grouting channel 54 and the top venting channel.
[0123] After the grout reaches the specified strength, the top sealing member is installed to seal the upper part of the vertical wedge lock 5, the injection port and the top venting position. The limiting recess on the lower surface of the top sealing member cooperates with the upper limiting section 53 to further restrict the vertical wedge lock 5 from moving upward.
[0124] The grout-bearing groove plate 8 is retained at the bottom of the joint, and together with the cured grout, it forms the bottom sealing and protective structure of the joint node.
[0125] Before the connecting slurry solidifies, the first staggered force transmission plate 32, the second staggered force transmission plate 42, the vertical wedge lock 5, the first combined support distribution plate 6, and the second combined support distribution plate 7 together maintain the relative positions of the first plate component 1 and the second plate component 2.
[0126] After the connecting grout has cured, the force borne by the first plate component 1 is transmitted to the connection area through the first sector anchoring structure 34, the first embedded box 31 and the first staggered force transmission plate 32, and then transmitted to the second embedded box 41, the second sector anchoring structure 44 and the second plate component 2 through the vertical wedge lock 5, the cured connecting grout and the second staggered force transmission plate 42.
[0127] Example 2: See attached document Figure 2 Based on Embodiment 1, this is the second embodiment of the present application. This embodiment is applicable to the case where multiple sets of connecting components are arranged along the length of the connecting seam, and the remaining structural relationships are the same as in Embodiment 1.
[0128] Multiple sets of first force transmission connection boxes 3 are arranged at intervals along the connecting end of the first plate component 1, and multiple sets of second force transmission connection boxes 4 are arranged along the connecting end of the second plate component 2. A vertical wedge lock 5 is provided between each set of first force transmission connection boxes 3 and second force transmission connection boxes 4.
[0129] During on-site installation, vertical wedge locks 5 can be inserted sequentially from the middle of the joint to both ends, so that the two plate components can be gradually guided and closed from the middle to both ends, reducing the possibility of overall skewing caused by locking one end of the long joint first.
[0130] After each vertical wedge lock 5 reaches the locking position, the corresponding first and second combined support distribution plates 6 and 7 are assembled respectively, and the two discharge holes 55 are aligned with the corresponding distribution inlets respectively.
[0131] The bottom guide portions of the first and second assembled support distribution plates 6 and 7 are at the same height and together form the installation path of the grouting groove plate 8 that runs through the length of the joint.
[0132] When a continuous extending slurry receiving plate 8 is used, the upper surface of the slurry receiving plate 8 is provided with a lifting slope corresponding to each group of assembled support distribution plates, and the bottom of each group of assembled support distribution plates is provided with a corresponding pressing slope.
[0133] When the grout-receiving trough plate 8 approaches its final position, each set of lifting ramps enters the working area of the corresponding pressing ramp in sequence. After the grout-receiving trough plate 8 reaches its final position, each set of lifting ramps is in the lifting and holding section of the corresponding pressing ramp, so that the grout-receiving trough plate 8 maintains a basically consistent lifting height along its length.
[0134] After the grouting trough plate 8 is raised, the bottom openings of each group of distribution channels and the bottom of the entire connecting joint are closed at the same time. The guide parts of each group of bearing plates support the grouting trough plate 8 in sections to reduce the deflection of the grouting trough plate 8 under the weight of the connecting grout and the grouting pressure.
[0135] Multiple top venting positions are set along the length of the joint, and each top venting position is connected to the upper space of the joint, so that when the joint grout flows upward from multiple bottom grouting positions, the air in each area can be discharged separately.
[0136] During grouting, connecting grout can be sequentially delivered to the grouting channels 54 within each vertical wedge locking member 5, or multiple grouting channels 54 can be connected simultaneously via an external distribution pipe.
[0137] When grouting is performed sequentially, it should be done from the middle of the joint to both ends, so that the grout gradually fills the joint from the middle area to both ends, and the air is discharged from the top of the joint to the venting position.
[0138] When using synchronous grouting, the grouting pressure and grouting speed at each grouting location should be kept basically consistent to avoid premature closure of the air venting path in other areas due to excessively rapid rise in local areas.
[0139] Each set of connecting grout flows downward through the injection channel 54 in the corresponding vertical wedge locking member 5, and enters the two distribution channels through the two discharge holes 55 respectively, and then fills the bottom of the connecting joint upward through multiple upward grout outlets.
[0140] After the grout without obvious air bubbles is continuously discharged from each venting position at the top of the joint, stop grouting and seal the grouting inlet and each top venting position. After the grout reaches the specified strength, install the top sealing parts to cover the upper part of each vertical wedge locking part 5 and the corresponding venting position.
[0141] As can be seen from Embodiments 1 and 2, during the downward insertion process, the vertical wedge lock 5 first guides the multi-layer wedge lock channel, and then the two plate components move closer to each other through the middle wedge tightening section 52. After the two plate components reach the set connection position, the first splicing support distribution plate 6 and the second splicing support distribution plate 7 complete the splicing, and at the same time form the lock slot and make the two discharge holes 55 correspond to the two distribution inlets respectively. After the slurry receiving trough plate 8 is inserted and lifted, the bottom of the connection joint and the two lower opening distribution troughs are sealed at the same time, so that the connecting slurry can be filled from both sides of the bottom of the connection joint upward.
[0142] The working principle of this application is as follows: The first staggered force transmission plate 32 and the second staggered force transmission plate 42 are alternately inserted along the thickness direction of the plate component. When the vertical wedge lock 5 is inserted from top to bottom, the lower guide section 51 corrects multiple wedge lock channels layer by layer, and the middle wedge tightening section 52 converts the vertical force into a lateral force that drives the two plate components to move closer to each other.
[0143] The first and second combined support distribution plates 6 and 7 are joined together as the two plate components approach each other. The two semi-circular limiting edges enter the circumferential limiting groove 56 to limit the lower part of the vertical wedge lock 5. At the same time, the two discharge holes 55 correspond to the two distribution inlets respectively.
[0144] The grouting trough plate 8 is inserted below the splicing support distribution plate and lifted upward at the final position to seal the bottom of the joint and the two lower opening distribution troughs. The connecting grout enters the two distribution channels through the injection channel 54 and the two discharge holes 55, and then fills the joint from the bottom upward through multiple upward grout outlets. The air inside the joint is discharged through the top exhaust channel.
[0145] In summary, this application can sequentially complete the alignment of the staggered connection structure, the active sealing of the plate component, the vertical wedge locking component 5 limiting, the alignment of the discharge position, the sealing of the bottom of the connection joint, the sealing of the distribution channel and the bidirectional grouting at the bottom, and form mechanical locking and composite force transmission connection before and after the connection grout has solidified.
[0146] The above embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions will not cause the essence of the corresponding technical solutions to deviate from the protection scope of the technical solutions of the embodiments of this application.
Claims
1. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components, comprising a first force-transmitting connection box (3) and a second force-transmitting connection box (4) respectively disposed at the connection ends of a first plate component (1) and a second plate component (2), characterized in that: The first force transmission connection box (3) and the second force transmission connection box (4) are respectively provided with multiple first staggered force transmission plates (32) and multiple second staggered force transmission plates (42). The two sets of staggered force transmission plates are alternately inserted along the thickness direction of the plate component and are jointly provided with vertical wedge locks (5) for bringing the two force transmission connection boxes closer to each other. The lower part of the two force transmission connection boxes is respectively provided with a first splicing support distribution plate (6) and a second splicing support distribution plate (7). The vertical wedge lock (5) is provided with an injection channel (54) and two discharge holes (55). The bottom of the two splicing support distribution plates is respectively provided with a lower opening distribution groove. When the vertical wedge lock (5) moves down to the position, the two discharge holes (55) are respectively connected to the two lower opening distribution grooves. The bottom of the two splicing support distribution plates is provided with a slurry receiving trough plate (8). After the slurry receiving trough plate (8) is inserted along the length direction of the connection joint, it closes the bottom of the connection joint and the lower opening of the two lower opening distribution grooves.
2. The wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 1, characterized in that: The first force transmission connection box (3) includes a first embedded box body (31), and a plurality of first staggered force transmission plates (32) are spaced apart along the height direction of the first embedded box body (31). The second force transmission connection box (4) includes a second embedded box body (41), and a plurality of second staggered force transmission plates (42) are spaced apart along the height direction of the second embedded box body (41). A first insertion interval is formed between two adjacent first staggered force transmission plates (32) for the insertion of the second staggered force transmission plate (42), and a second insertion interval is formed between two adjacent second staggered force transmission plates (42) for the insertion of the first staggered force transmission plate (32). After the plurality of first staggered force transmission plates (32) and the plurality of second staggered force transmission plates (42) are connected, they are continuously and alternately arranged along the thickness direction of the plate component.
3. The wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 2, characterized in that: Each first staggered force transmission plate (32) is provided with a first wedge lock channel (33), and each second staggered force transmission plate (42) is provided with a second wedge lock channel (43). Multiple first wedge lock channels (33) and multiple second wedge lock channels (43) are arranged vertically. The side of the first wedge lock channel (33) away from the first pre-embedded box (31) forms a first inclined bearing surface, and the side of the second wedge lock channel (43) away from the second pre-embedded box (41) forms a second inclined bearing surface. When the vertical wedge lock (5) moves downward, it squeezes the first inclined bearing surface and the second inclined bearing surface respectively, so as to drive the first force transmission connecting box (3) and the second force transmission connecting box (4) to move closer to each other.
4. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 3, characterized in that: The vertical wedge locking member (5) is provided with a lower guiding section (51), a middle wedge tightening section (52) and an upper limiting section (53) in a vertical direction from bottom to top. The lateral dimension of the lower guiding section (51) is smaller than the initial passing dimension of the first wedge locking channel (33) and the second wedge locking channel (43). The lateral dimension of the middle wedge tightening section (52) gradually increases from bottom to top. Locking inclined surfaces that cooperate with the first inclined bearing surface and the second inclined bearing surface are formed on both sides of the middle wedge tightening section (52). The lateral dimension of the upper limiting section (53) is larger than the passing dimension of the first wedge locking channel (33) and the second wedge locking channel (43).
5. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 4, characterized in that: The lower part of the vertical wedge lock (5) is provided with a circumferential limiting groove (56). The first half-groove and the second half-groove are respectively formed on the opposite sides of the first splicing support distribution plate (6) and the second splicing support distribution plate (7). The groove walls of the first half-groove and the second half-groove are respectively provided with limiting edges. After the first splicing support distribution plate (6) and the second splicing support distribution plate (7) are spliced, the first half-groove and the second half-groove together form a lock groove. The two limiting edges enter the circumferential limiting groove (56) to restrict the vertical wedge lock (5) from exiting upward.
6. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 5, characterized in that: The injection channel (54) extends along the axial direction of the vertical wedge lock (5). The upper end of the injection channel (54) passes through the upper limiting section (53) and forms an injection port. Two discharge holes (55) are set on opposite sides of the lower guiding section (51) and located below the circumferential limiting groove (56). The first half of the slot is provided with a first distribution inlet, and the second half of the slot is provided with a second distribution inlet. The first and second distribution inlets are both elongated along the moving direction of the vertical wedge lock (5).
7. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 6, characterized in that: The two lower opening distribution channels are respectively the first lower opening distribution channel set at the bottom of the first splicing support distribution plate (6) and the second lower opening distribution channel set at the bottom of the second splicing support distribution plate (7). The first lower opening distribution channel extends from the first distribution inlet to the direction of the first plate component (1), and the second lower opening distribution channel extends from the second distribution inlet to the direction of the second plate component (2). The upper part of the first lower opening distribution channel and the second lower opening distribution channel respectively forms multiple upward slurry outlets that communicate with the inside of the joint. After the slurry receiving plate (8) closes the lower opening of the two lower opening distribution channels, the two lower opening distribution channels and the slurry receiving plate (8) respectively form a distribution channel together.
8. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 7, characterized in that: The bottom surfaces of the first and second combined support distribution plates (6) and the second combined support distribution plate (7) are both higher than the bottom surfaces of the first plate component (1) and the second plate component (2), and an insert plate space is formed below the two combined support distribution plates along the length of the connecting joint. The bottom of the two combined support distribution plates is provided with a support plate guide. The two sides of the grouting groove plate (8) are respectively formed with insert edges that slide with the support plate guide. After the grouting groove plate (8) is inserted along the insert plate space, it covers the bottom opening of the connecting joint between the first plate component (1) and the second plate component (2).
9. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 8, characterized in that: The upper surface of the grout-receiving trough plate (8) is provided with an elastic sealing layer. The grout-receiving trough plate (8) is provided with at least one set of lifting slopes along the length of the joint. The bottom of the first spliced support distribution plate (6) and the second spliced support distribution plate (7) is provided with pressing slopes that correspond to the lifting slopes. When the grout-receiving trough plate (8) is close to the final insertion position, the lifting slopes and the pressing slopes squeeze each other, causing the grout-receiving trough plate (8) to move upward and causing the elastic sealing layer to press the bottom of the first spliced support distribution plate (6), the second spliced support distribution plate (7), the first plate component (1), and the second plate component (2).
10. A wedge-lock grouting connection assembly for coarse aggregate UHPC plate components according to claim 2, characterized in that: The first embedded box (31) is provided with a first fan-shaped anchoring structure (34) on the side away from the connecting seam, and the second embedded box (41) is provided with a second fan-shaped anchoring structure (44) on the side away from the connecting seam. The first fan-shaped anchoring structure (34) and the second fan-shaped anchoring structure (44) both include multiple anchoring ribs that radiate from the corresponding embedded box into the interior of the corresponding plate component. A coarse aggregate passage area is formed between adjacent anchoring ribs and is connected to the casting space of the corresponding plate component. The anchoring ribs are aligned with the first staggered force transmission plate (32) or the second staggered force transmission plate (42) of the corresponding height along the height direction.