A modular building double-beam shear wall connection structure
By setting pre-embedded bases, pressure pads, and damping components within the shear wall body, combined with multi-dimensional sliding holes and alignment sealing mechanisms, the problems of low assembly error tolerance, stress concentration, and poor joint sealing durability in the connection between double beams and shear walls are solved, achieving efficient and stable connection and seismic performance.
Patent Information
- Application Number
- CN202611265423.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-20
- Publication Date
- 2026-11-17
AI Technical Summary
The existing connection method between double beams and shear walls has problems such as low assembly error tolerance, obvious stress concentration, insufficient seismic energy dissipation, and poor joint sealing durability.
The design employs a pre-embedded base within the shear wall body, with pressure pads and damping components installed between the pre-embedded base and the upper and lower beams. Combined with multi-dimensional sliding holes and alignment sealing mechanisms, it achieves flexible connection and directional sealing. Energy is dissipated through damping components, and buffering is provided by high-elasticity rubber and high-strength glass fiber. Bolts and multi-dimensional sliding holes provide position adjustment margin.
It improves the stress stability and seismic performance of the connection nodes, reduces stress concentration and joint seepage problems, enhances assembly efficiency and long-term durability of the nodes, and facilitates post-earthquake maintenance.
Smart Images

Figure CN123109302A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of prefabricated building structure connection technology, specifically a modular building double-beam shear wall connection structure. Background Technology
[0002] Currently, modular buildings prefabricate main components such as beams and wall panels in factories and then transport them to the construction site for assembly and connection. This approach features short construction cycles, minimal on-site wet work, and a high degree of component standardization. In high-rise or large-span modular buildings, to improve floor load-bearing capacity and overall structural rigidity, a double-beam structure with parallel upper and lower beams is often used. Shear walls bear vertical loads and horizontal forces. Therefore, the connection nodes between the double beams and the shear walls have a significant impact on structural stability and construction quality.
[0003] The existing connection methods between double beams and shear walls mostly adopt on-site rebar installation and cast-in-place connection or external steel plate bolt connection. On-site rebar installation and cast-in-place connection requires drilling, rebar installation, formwork, pouring and curing, which involves many construction procedures and is not conducive to the rapid assembly of modular buildings. Although external steel plate bolt connection can reduce some wet work, the beam, steel plate and shear wall are mostly rigidly locked, which requires high prefabrication accuracy and hoisting alignment. When there are dimensional errors or installation deviations in the components, cutting, grinding or hole enlargement is required, which will affect the stress reliability of the connection.
[0004] Meanwhile, existing rigid connection nodes lack buffer and energy dissipation structures, and the stiffness changes between the double beams and the shear wall are concentrated. Under long-term loads, temperature deformation, or seismic action, stress concentration will occur at the nodes, leading to bolt shearing, joint cracking, or beam end loosening. Traditional connection structures do not adequately consider the sealing of beam-wall joints. Water vapor can enter and cause steel components to rust and concrete to age. Therefore, a connection structure that takes into account assembly adjustment, node energy dissipation, and joint sealing is needed. Summary of the Invention
[0006] To address the shortcomings of existing technologies, this invention provides a modular building double-beam shear wall connection structure, which solves the problems of low assembly fault tolerance, significant stress concentration, insufficient seismic energy dissipation, and poor joint sealing durability of existing rigid connection nodes between double beams and shear walls.
[0007] To achieve the above objectives, the present invention provides the following technical solution: a modular building double-beam shear wall connection structure, comprising a shear wall body, an embedded base fixedly connected inside the shear wall body, an upper beam and a lower beam provided outside the embedded base, a support plate fixedly connected to the top of both the upper and lower beams, a disassembly mechanism provided outside the support plate, the disassembly mechanism being used to replace rigid connections and graded seismic energy dissipation, and an alignment sealing mechanism provided outside the embedded base, the alignment sealing mechanism being used to guide and seal the installation of the double beams.
[0008] Preferably, the disassembly mechanism includes a pressure pad disposed on the outside of the pre-embedded base, a damping element disposed on the outside of the support plate, a weakening groove formed on the outside of the damping element, a housing fixedly connected inside the damping element, a sliding rod slidably connected inside the housing, a storage groove formed on the outside of the sliding rod, an arc-shaped block slidably connected to the outside of the sliding rod, a second spring fixedly connected to the bottom of the arc-shaped block, a stop block fixedly connected to the other end of the second spring, and the stop block slidably connected inside the housing.
[0009] Preferably, the alignment sealing mechanism includes a multi-dimensional sliding hole, which is opened on the outside of the pre-embedded base. A water-stop strip is fixedly connected to the outside of the pre-embedded base, and sealant is fixedly connected to the inside of the water-stop strip. A bolt is provided inside the pre-embedded base, and an upper beam is slidably connected to the outside of the bolt. A base is fixedly connected to the outside of the pre-embedded base. Lugs are fixedly connected to the bottom of both the upper beam and the lower beam. A fixing plate is fixedly connected to the outside of the pre-embedded base, and a moving rod is slidably connected inside the fixing plate. A third spring is sleeved on the outside of the moving rod, and a pressing block is fixedly connected to the top of the moving rod.
[0010] Preferably, the pressure pad is internally fixedly connected with high-elastic rubber and high-strength glass fiber.
[0011] Preferably, a first spring is provided inside the outer casing, with one end of the first spring fixedly connected to the bottom of the sliding rod and the other end of the first spring fixedly connected to the inner side of the outer casing.
[0012] Preferably, the stop block abuts against the outer side of the support plate, and the outer shell is slidably connected inside the support plate.
[0013] Preferably, a washer is slidably connected to the outside of the bolt, and a nut is threadedly connected to the outside of the bolt.
[0014] Preferably, one end of the third spring is fixedly connected to the inner side of the fixed plate, and the other end of the third spring is fixedly connected to the outer side of the moving rod.
[0015] Preferably, the clamping block is in contact with the outer side of the upper beam, and the hanging ear is slidably connected to the inner side of the base.
[0016] Preferably, the bolt passes through the multi-dimensional sliding hole, and the diameter of the multi-dimensional sliding hole is larger than the diameter of the bolt, so as to provide lateral and vertical position adjustment margins when the upper beam and the lower beam are installed.
[0017] In summary, the present invention has at least one of the following beneficial technical effects:
[0018] 1. This invention provides a pre-embedded base within the shear wall body, and a pressure pad between the pre-embedded base and the upper and lower beams. The pressure pad is made of high-elastic rubber and high-strength fiberglass, which provides a certain buffering and pressure-bearing capacity when the beam end load is transferred. Compared with the direct rigid connection of double beams, this structure can reduce the abrupt change in stiffness at the beam-wall connection, reduce local stress concentration at the node, and reduce problems such as cracking and pressure loss at the corner of the shear wall, which is beneficial to improving the stress stability of the connection node between the double beam and the shear wall.
[0019] 2. This invention, by setting damping components on the outside of the support plate and creating weakening grooves on the damping components, enables the damping components to deform and dissipate energy before the main connecting components when the node is subjected to seismic action or large horizontal impact, thereby reducing the risk of impact loads directly acting on bolts, embedded bases, and shear wall bodies. At the same time, the damping components are installed in conjunction with a shell, sliding rod, arc block, spring, and stop block, and can be disassembled and replaced individually in the later stage without damaging the upper beam, lower beam, or shear wall body, which facilitates post-earthquake maintenance and node repair.
[0020] 3. This invention, by setting multi-dimensional sliding holes on the pre-embedded base and locking them with bolts, washers, and nuts, allows for a certain positional adjustment margin during installation of the upper and lower beams. This accommodates dimensional deviations of prefabricated components and on-site hoisting errors, reducing secondary processing such as cutting, grinding, or hole enlargement. Furthermore, the hanging lugs cooperate with the base to provide guidance and limitation, the clamping block assists in clamping the beam under the action of the third spring, and the waterstop strip and sealant seal the beam-wall joints, thus balancing assembly efficiency, installation stability, and joint waterproofing durability. Attached Figure Description
[0021] Figure 1 This is a perspective view of the present invention;
[0022] Figure 2 This is a side view of the present invention;
[0023] Figure 3 This is a schematic diagram of the structure of the pressure pad of the present invention;
[0024] Figure 4 This is a schematic diagram of the damping component of the present invention;
[0025] Figure 5 This is a schematic diagram of the disassembly mechanism of the present invention;
[0026] Figure 6 For the present invention Figure 5 A magnified view of point A;
[0027] Figure 7 This is a schematic diagram of the alignment and sealing mechanism of the present invention;
[0028] Figure 8 This is a schematic diagram of the pre-embedded base of the present invention.
[0029] The components include: 1. Shear wall body; 2. Upper beam; 3. Lower beam; 4. Support plate; 5. Disassembly mechanism; 51. High-elastic rubber; 52. High-strength fiberglass; 53. Damping component; 54. Weakening groove; 55. Outer shell; 56. Sliding rod; 57. Storage groove; 58. First spring; 59. Arc block; 510. Second spring; 511. Stop block; 512. Pressure pad; 6. Embedded base; 7. Alignment and sealing mechanism; 71. Multi-dimensional sliding hole; 72. Waterstop strip; 73. Sealant; 74. Bolt; 75. Gasket; 76. Nut; 77. Fixing plate; 78. Pressing block; 79. Third spring; 710. Moving rod; 711. Base; 712. Hanging lug. Detailed Implementation
[0030] The following is in conjunction with the appendix Figure 1 - Appendix Figure 8 The present invention will be further described in detail below.
[0031] Please see the appendix Figure 1 - Appendix Figure 2 This invention provides a modular building double-beam shear wall connection structure, including a shear wall body 1, an embedded base 6 fixedly connected inside the shear wall body 1, an upper beam 2 and a lower beam 3 on the outside of the embedded base 6, a support plate 4 fixedly connected to the top of both the upper beam 2 and the lower beam 3, a disassembly mechanism 5 on the outside of the support plate 4, the disassembly mechanism 5 being used to replace rigid connections and graded seismic energy dissipation, and an alignment sealing mechanism 7 on the outside of the embedded base 6, the alignment sealing mechanism 7 being used to guide and seal the installation of the double beams;
[0032] Specifically, the shear wall body 1 serves as the load-bearing foundation of the overall structure. An embedded base 6 is pre-fixed inside the shear wall body 1, allowing the upper beam 2 and lower beam 3 to connect with the shear wall body 1 via the embedded base 6. A support plate 4 is fixed to the top of the upper beam 2 and lower beam 3, providing an installation position for the dismantling mechanism 5, enabling the dismantling mechanism 5 to be positioned in the connection area between the double beams and the embedded base 6. An alignment and sealing mechanism 7 is located outside the embedded base 6, guiding, positioning, and sealing the beams during installation of the upper beam 2 and lower beam 3, thereby ensuring a more stable connection between the double beams and the shear wall body 1.
[0033] Please see the appendix Figure 3 - Appendix Figure 6 In a preferred embodiment of the present invention, the disassembly mechanism 5 includes a pressure pad 512, which is disposed on the outside of the pre-embedded base 6. A damping element 53 is disposed on the outside of the support plate 4. A weakening groove 54 is formed on the outside of the damping element 53. A housing 55 is fixedly connected inside the damping element 53. A sliding rod 56 is slidably connected inside the housing 55. A storage groove 57 is formed on the outside of the sliding rod 56. An arc-shaped block 59 is slidably connected to the outside of the sliding rod 56. A second spring 510 is fixedly connected to the bottom of the arc-shaped block 59. The other end of the second spring 510 is fixedly connected to a stop block 511, which is slidably connected inside the outer shell 55; a high-elastic rubber 51 is fixedly connected inside the pressure pad 512, and a high-strength fiberglass 52 is fixedly connected inside the pressure pad 512; a first spring 58 is provided inside the outer shell 55, one end of the first spring 58 is fixedly connected to the bottom of the sliding rod 56, and the other end of the first spring 58 is fixedly connected to the inner side of the outer shell 55; the stop block 511 abuts against the outer side of the support plate 4, and the outer shell 55 is slidably connected inside the support plate 4;
[0034] Specifically, the pressure pad 512 is located outside the pre-embedded base 6, and can form a pressure transition between the upper beam 2, the lower beam 3 and the shear wall body 1; the high-elastic rubber 51 in the pressure pad 512 is used to withstand the small deformation at the connection, and the high-strength glass fiber 52 is used to improve the structural strength of the pressure pad 512, so that the connection node will not form a local rigid impact when under force; the damping element 53 forms a preset deformation position through the weakening groove 54. When the node is subjected to a large external force, the damping element 53 can dissipate energy through the deformation at the weakening groove 54; the sliding rod 56, the arc block 59, the second spring 510 and the stop block 511 cooperate to enable the damping element 53 to form a limiting connection with the support plate 4; when disassembly is required, the sliding rod 56 slides in the outer shell 55, and the arc block 59 can enter the storage groove 57, thereby releasing the abutment state between the stop block 511 and the support plate 4, making it easy to remove and replace the damping element 53.
[0035] Please see the appendix Figure 7 - Appendix Figure 8In a preferred embodiment of the present invention, the alignment sealing mechanism 7 includes a multi-dimensional sliding hole 71, which is formed on the outside of the pre-embedded base 6. A waterstop strip 72 is fixedly connected to the outside of the pre-embedded base 6, and a sealant 73 is fixedly connected to the inside of the waterstop strip 72. A bolt 74 is provided inside the pre-embedded base 6, and an upper beam 2 is slidably connected to the outside of the bolt 74. A base 711 is fixedly connected to the outside of the pre-embedded base 6. A hanging lug 712 is fixedly connected to the bottom of both the upper beam 2 and the lower beam 3. A fixing plate 77 is fixedly connected to the outside of the pre-embedded base 6, and a moving rod 710 is slidably connected inside the fixing plate 77. A sleeve is fitted on the outside of the moving rod 710. A third spring 79 is provided, and a clamping block 78 is fixedly connected to the top of the moving rod 710; a washer 75 is slidably connected to the outside of the bolt 74, and a nut 76 is threadedly connected to the outside of the bolt 74; one end of the third spring 79 is fixedly connected to the inside of the fixed plate 77, and the other end of the third spring 79 is fixedly connected to the outside of the moving rod 710; the clamping block 78 contacts the outside of the upper beam 2, and the hanging ear 712 is slidably connected to the inside of the base 711; the bolt 74 passes through the multi-dimensional sliding hole 71, and the diameter of the multi-dimensional sliding hole 71 is larger than the diameter of the bolt 74, which is used to provide lateral and vertical position adjustment margins when the upper beam 2 and the lower beam 3 are installed;
[0036] Specifically, during the installation of the upper beam 2 and lower beam 3, the lug 712 first slides into the inner side of the base 711, providing initial guidance and positioning for the beam during installation. After the bolt 74 passes through the multi-dimensional sliding hole 71, it is locked by the washer 75 and nut 76. Since the diameter of the multi-dimensional sliding hole 71 is larger than the diameter of the bolt 74, the upper beam 2 and lower beam 3 can be finely adjusted in both lateral and vertical positions during assembly, facilitating adaptation to installation deviations. The fixing plate 77 provides a sliding installation position for the moving rod 710, and the third spring 79 applies an elastic force to the moving rod 710, allowing the clamping block 78 to contact the outer side of the upper beam 2, providing auxiliary clamping for the beam. The waterstop strip 72 and sealant 73 are installed in the joint area on the outer side of the embedded base 6, sealing the joint gaps and reducing the entry of moisture from the beam-wall connection.
[0037] Working principle: When connecting the double beams to the shear wall body 1, the pre-embedded base 6 is first fixed inside the shear wall body 1, so that the pre-embedded base 6 serves as the main connecting load-bearing component between the upper beam 2 and the lower beam 3 and the shear wall body 1; during the installation process, the upper beam 2 and the lower beam 3 are moved to the corresponding positions outside the pre-embedded base 6, so that the support plates 4 on the upper beam 2 and the lower beam 3 correspond to the pre-embedded base 6, and at the same time, the hanging lug 712 slides into the inner side of the base 711, thereby initially limiting and guiding the installation position of the upper beam 2 and the lower beam 3, and preventing the beam from shifting during the assembly process;
[0038] When the upper beam 2 and lower beam 3 are aligned with the pre-embedded base 6, the upper beam 2 and lower beam 3 pass through the bolts 74 inside the multi-dimensional sliding hole 71 and are locked by the washers 75 and nuts 76. Since the multi-dimensional sliding hole 71 can provide a certain position adjustment margin for the bolts 74, it can compensate for factory prefabrication errors and on-site hoisting deviations in the front-back, left-right and vertical directions, so that the upper beam 2 and lower beam 3 can be quickly aligned and installed without secondary cutting, grinding or hole enlargement, thus improving the on-site assembly efficiency of modular buildings. During the beam locking process, the waterstop strip 72 and sealant 73 are set at the joint position on the outside of the pre-embedded base 6. The waterstop strip 72 can elastically seal the joint gap, and the sealant 73 further fills the tiny gaps, thus forming a double-layer sealing structure. When the connection node is affected by rainwater, moisture or temperature deformation, the waterstop strip 72 and sealant 73 can jointly block the water vapor penetration channel, reduce the problems of joint water seepage, steel component corrosion and local aging of shear wall body 1, and improve the long-term durability of the connection node.
[0039] After the upper beam 2 and lower beam 3 are installed in place, the moving rod 710 inside the fixing plate 77 drives the clamping block 78 to move towards the beam body under the elastic force of the third spring 79, so that the clamping block 78 contacts the outer side of the upper beam 2, thereby assisting in clamping and positioning the beam body; after the connection is completed, the pressure pad 512 is set between the pre-embedded base 6 and the support plate 4. The high-elastic rubber 51 and high-strength glass fiber 52 inside the pressure pad 512 form a composite pressure-bearing structure; the high-elastic rubber 51 can absorb the small deformation and vibration between the beam end and the shear wall body 1, and the high-strength glass fiber 52 can enhance the overall strength and compressive stability of the pressure pad 512, so that a transitional force structure from flexible to rigid is formed at the node, avoiding stress concentration between the upper beam 2, lower beam 3 and shear wall body 1 due to a sudden change in stiffness;
[0040] When the building is subjected to earthquake or large horizontal impact, the damping component 53 in the dismantling mechanism 5 participates in energy dissipation; the damping component 53 is provided with a weakening groove 54 on the outside. The weakening groove 54 enables the damping component 53 to yield and deform preferentially according to the predetermined position under strong earthquake, thereby dissipating earthquake energy step by step, reducing the strength of the impact force directly transmitted to the bolt 74, the embedded base 6 and the shear wall body 1, and avoiding brittle failures such as bolt 74 shearing, joint cracking or beam end anchorage failure.
[0041] When it is necessary to disassemble the damping component 53, the sliding rod 56 is pushed. At this time, the first spring 58 is compressed and the sliding rod 56 moves downward. This causes the second spring 510 between the arc block 59 and the stop block 511 to release its elastic potential energy and slide into the storage groove 57, thus unlocking it. The damping component 53 can then be removed and replaced without damaging the main structure of the upper beam 2, lower beam 3, or shear wall body 1.
[0042] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A modular building double-beam shear wall connection structure, comprising a shear wall body (1), characterized in that, The shear wall body (1) is internally fixedly connected to a pre-embedded base (6). An upper beam (2) is provided on the outside of the pre-embedded base (6), and a lower beam (3) is provided on the outside of the pre-embedded base (6). A support plate (4) is fixedly connected to the top of both the upper beam (2) and the lower beam (3). A disassembly mechanism (5) is provided on the outside of the support plate (4). The disassembly mechanism (5) is used to replace rigid connections and graded seismic energy dissipation. An alignment sealing mechanism (7) is provided on the outside of the pre-embedded base (6). The alignment sealing mechanism (7) is used to guide and seal the installation of the double beams.
2. The modular building double-beam shear wall connection structure according to claim 1, characterized in that... The disassembly mechanism (5) includes a pressure pad (512), which is located on the outside of the pre-embedded base (6). A damping element (53) is provided on the outside of the support plate (4). A weakening groove (54) is provided on the outside of the damping element (53). A shell (55) is fixedly connected inside the damping element (53). A sliding rod (56) is slidably connected inside the shell (55). A storage groove (57) is provided on the outside of the sliding rod (56). An arc-shaped block (59) is slidably connected on the outside of the sliding rod (56). A second spring (510) is fixedly connected to the bottom of the arc-shaped block (59). A stop block (511) is fixedly connected to the other end of the second spring (510). The stop block (511) is slidably connected inside the shell (55).
3. The modular building double-beam shear wall connection structure according to claim 1, characterized in that, The alignment sealing mechanism (7) includes a multi-dimensional sliding hole (71), which is opened on the outside of the pre-embedded base (6). A water-stop strip (72) is fixedly connected to the outside of the pre-embedded base (6). A sealant (73) is fixedly connected to the inside of the water-stop strip (72). A bolt (74) is provided inside the pre-embedded base (6). An upper beam (2) is slidably connected to the outside of the bolt (74). A base (711) is fixedly connected to the outside of the pre-embedded base (6). A hanging lug (712) is fixedly connected to the bottom of both the upper beam (2) and the lower beam (3). A fixing plate (77) is fixedly connected to the outside of the pre-embedded base (6). A moving rod (710) is slidably connected inside the fixing plate (77). A third spring (79) is sleeved on the outside of the moving rod (710). A pressing block (78) is fixedly connected to the top of the moving rod (710).
4. The modular building double-beam shear wall connection structure according to claim 2, characterized in that, The pressure pad (512) is internally fixedly connected with high-elastic rubber (51) and high-strength glass fiber (52).
5. The modular building double-beam shear wall connection structure according to claim 2, characterized in that, The outer casing (55) is provided with a first spring (58), one end of the first spring (58) is fixedly connected to the bottom of the sliding rod (56), and the other end of the first spring (58) is fixedly connected to the inside of the outer casing (55).
6. The modular building double-beam shear wall connection structure according to claim 2, characterized in that, The stop block (511) abuts against the outer side of the support plate (4), and the outer shell (55) is slidably connected inside the support plate (4).
7. The modular building double-beam shear wall connection structure according to claim 3, characterized in that, A washer (75) is slidably connected to the outside of the bolt (74), and a nut (76) is threadedly connected to the outside of the bolt (74).
8. The modular building double-beam shear wall connection structure according to claim 3, characterized in that, One end of the third spring (79) is fixedly connected to the inner side of the fixed plate (77), and the other end of the third spring (79) is fixedly connected to the outer side of the moving rod (710).
9. The modular building double-beam shear wall connection structure according to claim 3, characterized in that, The clamping block (78) is in contact with the outer side of the upper beam (2), and the hanging ear (712) is slidably connected to the inner side of the base (711).
10. The modular building double-beam shear wall connection structure according to claim 3, characterized in that, The bolt (74) is inserted inside the multi-dimensional sliding hole (71), and the diameter of the multi-dimensional sliding hole (71) is larger than the diameter of the bolt (74), which is used to provide lateral and vertical position adjustment margins when the upper beam (2) and the lower beam (3) are installed.