Metal Roofing Base Plate Leak-Proof Overlap Joint Structure and Construction Method

By using butyl tape, elastic sealing gaskets, and longitudinal vapor barrier membranes in a staggered arrangement at the overlapping joints of metal roofing slabs, the leakage problem at these joints was solved, achieving higher sealing performance and construction efficiency.

CN123109343APending Publication Date: 2026-11-17MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611498219.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-24
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Leakage is prone to occur at the overlapping joints of existing metal roofing panels, especially due to the aging and failure of the tape, the formation of gaps under negative wind pressure, and water seepage caused by misalignment of longitudinal joints.

Method used

The system employs butyl tape for interlayer sealing, elastic sealing gaskets under the heads of self-tapping screws, transverse vapor barrier membrane for sealing, and staggered longitudinal seams. Combined with the integrated design of self-adhesive longitudinal vapor barrier membrane and self-tapping screws, a multi-layer sealing structure is formed.

Benefits of technology

It improves the sealing reliability of the overlapping joints of metal roofing base plates, reduces the risk of leakage, and ensures construction quality and ease of installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109343A_ABST
    Figure CN123109343A_ABST
Patent Text Reader

Abstract

This invention discloses a waterproof overlapping joint structure and construction method for metal roof slabs. The joint structure includes a lower, middle, and upper slab supported on steel purlins. These three slabs are stacked in a transverse overlapping section, with butyl tape placed between adjacent slabs. Self-tapping screws pass through the slabs and butyl tape and are fixed to the steel purlins. An elastic sealing washer is placed between the screw head and the upper slab. A transverse vapor barrier is placed at the lower edge of the overlapping section along the slope. A longitudinal vapor barrier spans above the longitudinal joint and is self-adhesive to the crests on both sides of the joint. The longitudinal joints of the upper and lower slabs or adjacent rows are staggered transversely. During construction, the stacked slabs are fixed and the transverse sealing, longitudinal joint sealing, staggered longitudinal joint construction, and cyclic laying are performed sequentially to seal the interlayer spaces, nail holes, and longitudinal joints, and to reduce continuous seepage paths formed by aligned longitudinal joints.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of steel structure construction technology, and more specifically, to a leak-proof overlapping joint structure and construction method for metal roofing base plates. Background Technology

[0002] Metal roofing systems can be used in large-span steel structure buildings and typically include a base slab, insulation layer, waterproofing layer, and roof panels. The base slab, serving as both the load-bearing and backing layer, can be made of profiled steel sheet or aluminum-magnesium-manganese sheet, overlapped and fixed to purlins or roof beams. For flat lap joint systems without standing seams, the sealing structure at the base slab overlap directly affects the leak-proof performance at the joints.

[0003] In existing lap joint structures, transverse lap joints can be treated by applying butyl tape between the layers of the slabs and fixing it with self-tapping screws, while longitudinal lap joints are constructed using overlapping slabs. When relying solely on interlayer tape for sealing, the tape may age and fail under long-term pressure and temperature changes, turning the lap joints into seepage channels. Furthermore, longitudinally overlapping slab joints may also develop gaps under negative wind pressure. In addition, when the longitudinal joints of the upper and lower slabs are aligned, the joints easily become continuous weak points, allowing rainwater or condensate to seep in along the joints.

[0004] Therefore, it is necessary to coordinate and seal the interlayer overlaps, screw holes, and longitudinal joints of the metal roofing base plate, and improve the arrangement of longitudinal joints to reduce the risk of leakage at the overlap nodes due to poor sealing, condensate penetration, or construction errors. Summary of the Invention

[0005] To address the problems existing in the prior art, the present invention aims to provide a leak-proof overlapping joint structure and construction method for metal roof base plates. By combining interlayer sealing, nail hole sealing, vapor barrier covering sealing, and staggered arrangement of longitudinal joints, the problem of leakage easily occurring at the overlapping joints of the base plate is solved.

[0006] The present invention adopts the following technical solution:

[0007] This invention provides a waterproof overlapping joint structure for a metal roof base plate, comprising steel purlins and a metal base plate supported on the steel purlins. The metal base plate, in its transverse overlapping section, comprises a lower base plate, a middle base plate, and an upper base plate stacked from bottom to top; a first butyl adhesive tape is provided between the lower base plate and the middle base plate, and a second butyl adhesive tape is provided between the middle base plate and the upper base plate.

[0008] Self-tapping screws are installed in the transverse overlapping section, passing through the upper base plate, the second butyl tape, the middle base plate, the first butyl tape, and the lower base plate, and are fixed to the steel purlin. An elastic sealing washer is installed between the screw head and the upper base plate, and a transverse vapor barrier is installed at the lower end of the transverse overlapping section to form a covering seal at the screw hole position.

[0009] A self-adhesive longitudinal vapor barrier is placed over the longitudinal joint of adjacent metal base plates, and the vapor barrier is fixed to the corrugated surfaces on both sides of the longitudinal joint on the upper base plate. Within the same construction area, the longitudinal joints of upper and lower metal base plates or adjacent rows of metal base plates are staggered from each other in the transverse direction.

[0010] Furthermore, the first butyl tape and the second butyl tape each include at least one continuously closed butyl tape, and are respectively pressed between the lower base plate and the middle base plate, and between the middle base plate and the upper base plate.

[0011] Furthermore, the width of the longitudinal vapor barrier is greater than the width of the longitudinal joint, and it spans the longitudinal joint, with both sides self-adhesive to the crests of the joint; the longitudinal vapor barrier is laid continuously and closed on the upper bottom plate surface, and sealed by a slope-adhesive method.

[0012] Furthermore, the longitudinal joints are staggered by a distance of not less than one metal base plate pitch in the transverse direction; or, the longitudinal joints are staggered by a distance of not less than 300 mm in the transverse direction.

[0013] Furthermore, the resilient sealing washer is integrated with the self-tapping screw. The self-tapping screw is arranged at transverse intervals along the transverse lap section.

[0014] This invention also provides a construction method for the above-mentioned node structure, comprising the following steps:

[0015] Step S1: Laying, overlapping, fixing, and lateral sealing of the base plate: Position the lower base plate on the steel purlin, apply the first butyl tape to its lateral overlap end, and then overlap the middle base plate; apply the second butyl tape to the overlap between the middle and upper base plates, and then overlap the upper base plate, so that the two butyl tapes are pressed together between the adjacent plates; use self-tapping screws with elastic sealing washers to pass through each plate and the two butyl tapes, and fix them to the steel purlin, so that the elastic sealing washers are located between the screw heads and the upper base plate; arrange a lateral vapor barrier at the lower end of the lateral overlap section to cover and seal the screw hole positions.

[0016] Step S2, sealing and fixing the longitudinal seam: clean the surface of the longitudinal joint of the adjacent metal base plate, cover the longitudinal seam with the self-adhesive longitudinal vapor barrier, and fix it to the crest surface on both sides of the joint on the upper base plate.

[0017] Step S3, perform longitudinal joint staggered construction: Continue laying the next row of metal base plates, adjusting its starting position so that the longitudinal joint formed is staggered laterally from the longitudinal joint of the previous row of metal base plates. The staggered distance is not less than one metal base plate wave pitch, or not less than 300 mm.

[0018] Step S4: Perform cyclical work: Repeat steps S1 to S3 until all metal base plates in the construction area are laid and joints are sealed.

[0019] Beneficial effects

[0020] This invention provides butyl tape between the lower and middle bottom plates and between the middle and upper bottom plates to seal the two interlayer interfaces at the three-layer overlap. The elastic sealing washer under the self-tapping screw head seals the screw hole position, and the transverse vapor barrier forms a covering seal at the lower edge of the slope, which helps to improve the sealing reliability of the transverse overlap node.

[0021] The longitudinal vapor barrier membrane crosses the longitudinal joint and self-adheres to the crests on both sides of the joint. By continuously laying it, the longitudinal joint is covered and sealed, which helps to reduce the chance of moisture entering from the longitudinal joint.

[0022] By staggering the longitudinal joints of the upper and lower layers or adjacent columns of metal base plates in the transverse direction, the continuous seepage path formed by the alignment of the joints is reduced, thereby reducing the overall risk of leakage from both the aspects of node sealing and joint arrangement.

[0023] Using butyl tape, self-adhesive vapor barrier membrane, and self-tapping screws with elastic sealing washers facilitates construction by following the sequence of laying, fixing, sealing, and staggering joints. When the elastic sealing washers and self-tapping screws are integrated, it is beneficial for on-site installation and joint quality inspection. Attached Figure Description

[0024] Figure 1 This is a schematic diagram of the overlapping arrangement of the metal base plate of the present invention.

[0025] Figure 2 This is a cross-sectional schematic diagram of the anti-leakage overlapping node structure of the present invention.

[0026] Reference numerals: 1. Steel purlin; 2. Self-tapping screw; 3. Lower base plate; 4. First butyl tape; 5. Middle base plate; 6. Second butyl tape; 7. Upper base plate; 8. Transverse vapor barrier; 9. Longitudinal vapor barrier. Detailed Implementation

[0027] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention.

[0028] In this embodiment, "lateral" refers to the direction perpendicular to the steel purlin 1, "longitudinal" refers to the direction parallel to the steel purlin 1, and "slope" refers to the direction downward along the roof slope. The names of the lower base plate 3, the middle base plate 5, and the upper base plate 7 are used to indicate the relative stacking positions of the three metal base plates within the lateral overlap section.

[0029] As shown in the figure, an embodiment of the present invention discloses a waterproof overlapping joint structure for a metal roof base plate, including steel purlins 1 and metal base plates supported on the steel purlins 2. The metal base plates, in the transverse overlapping section, include a lower base plate 3, a middle base plate 5, and an upper base plate 7 stacked from bottom to top. The lower base plate 3 is located on the steel purlins 1, the middle base plate 5 overlaps the lower base plate 3, and the upper base plate 7 overlaps the middle base plate 5, so that the three metal base plates form a bottom-to-top stacking relationship in the transverse overlapping section. A first butyl tape 4 is located between the lower base plate 3 and the middle base plate 5, and a second butyl tape 6 is located between the middle base plate 5 and the upper base plate 7. Each of the two butyl tapes uses at least one continuously closed tape, so that a sealing layer is formed between the adjacent layers after they are stacked.

[0030] Self-tapping screws 2 are installed at transverse intervals above the transverse overlap section. During installation, the self-tapping screws 2 pass through the upper base plate 7, the second butyl tape 6, the middle base plate 5, the first butyl tape 4, and the lower base plate 3 from above in sequence, and are fixed to the steel purlin 1, so that the overlapping base plate is fixed on the steel purlin 1, and at the same time the two butyl tapes are pressed together between the adjacent base plates.

[0031] An elastic sealing washer is provided between the head of the self-tapping screw 2 and the upper base plate 7, and the elastic sealing washer is integrated with the self-tapping screw 2. This elastic sealing washer seals the screw hole between the screw head and the plate surface, cooperating with the sealing effect of the interlayer butyl tape. A transverse vapor barrier 8 is also arranged at the lower edge of the transverse overlap section to further cover and seal the screw hole. Therefore, the transverse overlap joint forms a seal at the interlayer interface, the contact point between the screw head and the plate surface, and the area covered by the vapor barrier.

[0032] A longitudinal vapor barrier 9 is installed above the longitudinal joint of adjacent metal base plates. The longitudinal vapor barrier 9 is a self-adhesive vapor barrier, its width is greater than the width of the longitudinal joint, and it spans the longitudinal joint, self-adhesively fixed to the corrugated surfaces on both sides of the joint on the upper base plate 7. During installation, the longitudinal vapor barrier 9 is arranged in a continuous closed loop on the surface of the upper base plate 7, and a seal is formed by self-adhesion along the slope to cover the longitudinal joint between adjacent metal base plates.

[0033] Within the same construction area, the longitudinal joints of upper and lower metal base plates or adjacent columns of metal base plates are not aligned, but rather staggered laterally. For the laying of adjacent columns, staggering is achieved by changing the starting position of the next column of metal base plates. The staggering distance can be set to be no less than one metal base plate wave pitch; or no less than 300 mm. After the longitudinal joints are staggered, the continuous weak points formed by aligned joints can be reduced, which is coordinated with the sealing of the longitudinal vapor barrier 9 at the joints.

[0034] This invention also discloses a construction method for a waterproof lap joint structure of a metal roof base plate, comprising the following steps:

[0035] Step S1: Laying, overlapping, fixing, and lateral sealing of the base plates. First, the first metal base plate, serving as the lower base plate 3, is positioned on the steel purlin 1, and a first butyl tape 4 is applied to its lateral overlapping end. Then, the second metal base plate, serving as the middle base plate 5, is overlapped onto the lower base plate 3, with the first butyl tape 4 positioned between the two plates. A second butyl tape 6 is applied at the overlap between the middle base plate 5 and the upper base plate 7. Then, the third metal base plate, serving as the upper base plate 7, is overlapped onto the middle base plate 5, with the second butyl tape 6 positioned between the two plates. This forms an overlapping section where the lower base plate 3, the first butyl tape 4, the middle base plate 5, the second butyl tape 6, and the upper base plate 7 are stacked sequentially.

[0036] Self-tapping screws 2 with elastic sealing washers are used to pass through each layer of the board and two butyl tapes at the overlapping section to fix each layer of the board to the steel purlin 1. After fixing, the first butyl tape 4 and the second butyl tape 6 are pressed into the corresponding interlayer, and the elastic sealing washers are located between the nail heads and the upper bottom plate 7. A transverse vapor barrier 8 is arranged at the lower edge of the lap section to form a covering seal at the nail hole position, completing the fixing and sealing of the transverse lap joint.

[0037] Step S2, longitudinal seam sealing and fixing. Clean the surface of the plate at the longitudinal joint of the two adjacent metal base plates, and cover the joint with a longitudinal vapor barrier 9 that is wider than the longitudinal joint width, so that its two sides are bonded to the crest surfaces on both sides of the joint. The longitudinal vapor barrier 9 is fixed by self-adhesion, and is laid continuously and closedly on the surface of the upper base plate 7, forming a seal along the slope.

[0038] Step S3, staggered longitudinal joint construction. Continue laying the next row of metal base plates, adjusting its starting position during laying so that the longitudinal joints formed in the next row are staggered laterally from the longitudinal joints of the previous row. The stagger distance should be set according to the adopted stagger distance, ensuring it is not less than one metal base plate wave pitch, or not less than 300 mm.

[0039] Step S4, repeat the process. Repeat steps S1 to S3 to complete the subsequent laying, fixing, sealing of horizontal and vertical joints, and staggered construction of longitudinal joints of the metal base plate in sequence, until the laying of all base plates and sealing of joints in the construction area are completed.

[0040] After construction, the two butyl tapes on the transverse overlap section, the elastic sealing gasket under the nail head, and the transverse vapor barrier 8 together seal the transverse overlap joint; the longitudinal vapor barrier 9 covers the longitudinal joint and is staggered with the longitudinal joint, which helps to reduce the risk of rainwater or condensate leakage along the overlap of the base plate.

Claims

1. A waterproof lap joint structure for metal roofing base plates, characterized in that, It includes a steel purlin (1) and a metal base plate supported on the steel purlin (1). The metal base plate includes a lower base plate (3), a middle base plate (5) and an upper base plate (7) stacked from bottom to top in the transverse overlapping section. A first butyl tape (4) is provided between the lower base plate (3) and the middle base plate (5), and a second butyl tape (6) is provided between the middle base plate (5) and the upper base plate (7). The transverse overlapping section is provided with self-tapping screws (2), which pass through the upper bottom plate (7), the second butyl tape (6), the middle bottom plate (5), the first butyl tape (4) and the lower bottom plate (3) and are fixed to the steel purlin (1). An elastic sealing washer is provided between the head of the self-tapping screw (2) and the upper bottom plate (7). A transverse vapor barrier (8) is provided at the lower end of the slope of the transverse overlapping section. The transverse vapor barrier (8) is used to form a covering seal at the nail hole position. A self-adhesive longitudinal vapor barrier membrane (9) is covered above the longitudinal joint of the adjacent metal base plate. The longitudinal vapor barrier membrane (9) is fixed to the crest surface on both sides of the longitudinal joint on the upper base plate (7). Within the same construction area, the longitudinal joints of the upper and lower metal base plates or adjacent columns of metal base plates are staggered from each other in the transverse direction.

2. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The first butyl tape (4) and the second butyl tape (6) each include at least one continuously closed butyl tape, and are respectively pressed between the lower base plate (3) and the middle base plate (5), and between the middle base plate (5) and the upper base plate (7).

3. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The width of the longitudinal vapor barrier membrane (9) is greater than the width of the longitudinal joint. The longitudinal vapor barrier membrane (9) spans the longitudinal joint and its two sides are self-adhesive to the crest surfaces on both sides of the longitudinal joint.

4. The anti-leakage lap joint structure for metal roofing base plates according to claim 3, characterized in that, The longitudinal vapor barrier membrane (9) is laid continuously and closed on the surface of the upper bottom plate (7) and sealed by a slope self-adhesion method.

5. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The longitudinal joints are staggered from each other in the transverse direction by a distance not less than one metal base plate pitch.

6. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The longitudinal joints are staggered by a distance of not less than 300mm in the transverse direction.

7. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The elastic sealing gasket is integrated with the self-tapping screw (2).

8. The anti-leakage lap joint structure for metal roofing base plates according to claim 1, characterized in that, The self-tapping screws (2) are arranged at transverse intervals along the transverse lap section.

9. A construction method for a waterproof lap joint structure for a metal roof base plate, used to form the waterproof lap joint structure for a metal roof base plate as described in claim 1, characterized in that... Includes the following steps: Step S1: Place the lower base plate (3) on the steel purlin (1), apply the first butyl tape (4) at the transverse overlap end of the lower base plate (3), overlap the middle base plate (5) on the lower base plate (3), apply the second butyl tape (6) at the overlap between the middle base plate (5) and the upper base plate (7), and overlap the upper base plate (7) on the middle base plate (5), so that the two butyl tapes are pressed together between the adjacent plates; use self-tapping screws (2) with elastic sealing washers to pass through each plate and the two butyl tapes, and fix them to the steel purlin (1), so that the elastic sealing washers are located between the nail heads and the upper base plate (7), and arrange a transverse vapor barrier (8) at the lower end of the transverse overlap section to form a covering seal at the nail hole position; Step S2: Clean the surface of the longitudinal joint of the adjacent metal base plate, cover the longitudinal joint with the self-adhesive longitudinal vapor barrier (9), and self-adhere it to the crest surface on both sides of the longitudinal joint on the upper base plate (7). Step S3: Continue laying the next column of metal base plates, and adjust the starting position of the next column of metal base plates so that the longitudinal joints formed are staggered from the longitudinal joints of the previous column of metal base plates in the transverse direction. Step S4: Repeat steps S1 to S3 until the laying of the metal base plate and the sealing of the joints in the construction area are completed.

10. The construction method according to claim 9, characterized in that, In step S3, the longitudinal joint of the next column of metal base plates is offset from the longitudinal joint of the previous column of metal base plates by a distance of not less than one metal base plate pitch, or the distance is not less than 300mm.