Precast assembled roof eaves and their construction methods
By using the prefabricated assembled roof eaves construction method, and utilizing the combination of embedded steel plates and connecting purlins, efficient and safe roof eaves construction is achieved, solving the safety risks and quality control problems existing in traditional construction, and improving construction efficiency and environmental protection.
Patent Information
- Application Number
- CN202611488198.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-23
- Publication Date
- 2026-11-17
AI Technical Summary
Traditional concrete roof eaves construction suffers from high safety risks, low construction efficiency, difficulty in quality control, poor durability, and insufficient environmental protection, especially in high-rise buildings.
The prefabricated roof eaves are constructed by embedding steel plates in the parapet wall as load-bearing bases, pre-fixing the purlins and roof tile components, and hoisting them to the parapet wall position as a whole using hoisting equipment, thus achieving construction without support frames. This method combines dry assembly with on-site formwork and pouring.
It eliminates the risk of falling from heights, shortens the construction period, avoids construction joints and thermal shrinkage cracks, enables the components to be disassembled and recycled, and reduces the generation of construction waste.
Smart Images

Figure CN123109346A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of roof eaves technology, and in particular to a prefabricated assembled roof eaves and its construction method. Background Technology
[0002] Eaves are a common roof structure in building construction, primarily serving for drainage and aesthetic purposes. However, traditional concrete roof eaves present challenges such as long construction perimeter, high construction risks in high-rise buildings, and difficulty in quality control.
[0003] Currently, the common method for constructing roof eaves is to use formwork to erect and cast the roof eaves, which has the following disadvantages: 1. High safety risks: The construction of eaves on high-rise roofs requires the erection of ground support frames or cantilever frames with a height of more than 8m. It is a sub-project with a high risk of exceeding a certain scale. There is a large amount of work at height and near the edge, and the risk of collapse and falls from height is prominent. In addition, expert demonstration must be organized, and the preliminary procedures are complicated and the cycle is long.
[0004] 2. Low construction efficiency and great dependence on the environment: The cast-in-place process includes multiple steps such as scaffolding erection, layered formwork, layered concrete pouring, curing, and formwork removal, resulting in a long construction cycle. Concrete pouring operations cannot be carried out in rainy or low-temperature weather, making the construction progress uncontrollable.
[0005] 3. Frequent structural and waterproofing defects: Layered pouring easily creates through construction joints; the concrete vibration space in the curved eaves area is narrow, which easily leads to appearance and structural defects such as honeycomb, pitting, and exposed reinforcement; the waterproof membrane at the junction of the inner side of the eaves and the wall is difficult to adhere tightly, which easily forms cavities and causes roof leakage problems after long-term use.
[0006] 4. Poor durability and environmental performance: Concrete eaves are prone to cracking due to thermal shrinkage and drying shrinkage; after construction, a large amount of formwork and timber construction waste is generated, which cannot be recycled and reused, and the cost of construction waste transportation and treatment is high, resulting in insufficient environmental performance. Summary of the Invention
[0007] The problem solved by this invention is to provide a prefabricated assembled roof eaves and its construction method.
[0008] In a first aspect, the present invention discloses a prefabricated assembled roof eaves for mounting on a parapet wall, comprising an embedded steel plate, connecting purlins, and a roof tile assembly; the embedded steel plate is pre-embedded within the wall body of the parapet wall, and at least one end face of the embedded steel plate protrudes from the surface of the parapet wall; one end of the connecting purlin is fixedly connected to the roof tile assembly; the roof tile assembly and the connecting purlin are hoisted to the position of the parapet wall by a hoisting device; and the other end of the connecting purlin is fixedly connected to the end face of the embedded steel plate protruding from the parapet wall.
[0009] In some embodiments, the embedded steel plate includes a plurality of top steel plates and side steel plates, wherein the plurality of top steel plates are spaced apart along the length direction of the top surface of the parapet wall, and the plurality of side steel plates are spaced apart along the length direction of the outer side surface of the parapet wall.
[0010] In some embodiments, the spacing between adjacent top steel plates and the spacing between adjacent side steel plates are equal to the height of the parapet wall.
[0011] In some embodiments, the connecting purlins include a plurality of horizontal connecting purlins and vertical connecting purlins; the roof tile assembly is inclined relative to the parapet wall, one end of the plurality of horizontal connecting purlins is fixedly connected to the roof tile assembly, and the other end is fixedly connected to a plurality of side steel plates; one end of the plurality of vertical connecting purlins is fixedly connected to the roof tile assembly, and the other end is fixedly connected to a top steel plate.
[0012] In some embodiments, the roof tile assembly includes main purlins, secondary purlins, additional purlins, and roof tiles; the main purlins are arranged in a plurality of parallel and spaced-apart structures, each of which is fixedly connected to a connecting purlin; the secondary purlins are arranged in a plurality of parallel and spaced-apart structures and are fixedly mounted on the main purlins; the additional purlins are arranged in a plurality of parallel and spaced-apart structures and are fixedly mounted on the secondary purlins; and a plurality of the roof tiles are fixedly mounted on the additional purlins.
[0013] In some embodiments, the main purlins, the secondary purlins, and the additional purlins are all galvanized square tubes, and the spacing between adjacent main purlins is 1500 mm, and the spacing between adjacent secondary purlins is less than or equal to 800 mm.
[0014] In some embodiments, the roof tile assembly further includes a plurality of screw connectors, and the roof tiles and the additional purlins are provided with a plurality of through holes, the screw connectors engaging with the through holes to fix the roof tiles onto the additional purlins.
[0015] In some embodiments, the embedded steel plate includes a panel and threaded anchor bars, with multiple threaded anchor bars fixed to one end face of the panel embedded in the parapet wall.
[0016] In some embodiments, each of the threaded anchor bars is equidistant from the center of the panel.
[0017] Secondly, the present invention discloses a construction method for prefabricated assembled roof eaves, used for constructing the prefabricated assembled roof eaves described in the first aspect, the construction method comprising: During the reinforcement binding and formwork sealing stage of the parapet wall, the embedded steel plate is fixed to the reinforcement skeleton of the parapet wall, and at least one end face of the embedded steel plate is flush with or protrudes from the surface of the parapet wall. The concrete of the parapet wall is poured so that the embedded steel plate and the parapet wall form an integral whole. On the ground or roof structure slab, one end of the connecting purlin is fixedly connected to the roof tile assembly to form an eaves unit; The eaves unit was hoisted as a whole to the position of the parapet wall using hoisting equipment; After adjusting the position of the eaves unit, the other end of the connecting purlin is welded and fixed to the end face of the pre-embedded steel plate protruding from the parapet wall, so that the roof tile assembly is cantilevered and supported on the parapet wall.
[0018] The beneficial effects of this invention are as follows: The prefabricated assembled roof eaves and their construction method disclosed in this invention utilize a pre-embedded steel plate embedded in the parapet wall during its pouring, with its end face protruding from the surface of the parapet wall as a load-bearing base. The roof tile components are pre-fixed to the connecting purlins to form a whole, and then hoisted to the parapet wall position by hoisting equipment and fixedly connected to the protruding end face of the pre-embedded steel plate. This achieves eaves assembly construction without support frames, eliminating the risk of collapse and falls from heights, and eliminating the need for expert review procedures. Dry assembly replaces on-site formwork and pouring, simplifying the process, shortening the construction period, and freeing construction from rain, snow, and low temperatures. It also eliminates construction joints, vibration defects, and thermal shrinkage cracking, eradicating the risk of root leakage. Through prefabrication, assembly, and fixed connection of components, the components can be disassembled, recycled, and reused, without generating construction waste such as formwork and timber. Attached Figure Description
[0019] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the following description of the embodiments will be briefly introduced. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0020] Figure 1 This is an overall cross-sectional view of the prefabricated roof eaves provided in an embodiment of the present invention; Figure 2 A top view of the main purlin and secondary purlin in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 3 A top view of the secondary purlins and additional purlins in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 4 A cross-sectional view of the roof tile assembly in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 5This is a structural diagram of the roof tiles in a prefabricated roof eaves provided in an embodiment of the present invention; Figure 6 The structural diagram of the embedded steel plate in the prefabricated roof eaves provided in the embodiment of the present invention.
[0021] Reference numerals: 10. Parapet wall; 20. Embedded steel plate; 21. Top steel plate; 22. Side steel plate; 23. Panel; 24. Threaded anchor bar; 30. Connecting purlin; 31. Horizontal connecting purlin; 32. Vertical connecting purlin; 40. Roof tile assembly; 41. Main purlin; 42. Secondary purlin; 43. Additional purlin; 44. Roof tile; 45. Threaded connector; 46. Roof tile end. Detailed Implementation
[0022] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0023] It should be understood that, when used in this specification and the appended claims, the terms "comprising" and "including" indicate the presence of the described features, integrals, steps, operations, elements and, or components, but do not exclude the presence or addition of one or more other features, integrals, steps, operations, elements, components and, or collections thereof.
[0024] It should also be noted that, unless otherwise explicitly specified and limited, terms such as "installation," "connection," "linking," "fixing," and "setting" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. When an component is referred to as being "on" or "below" another component, the component can be located "directly" or "indirectly" on the other component, or there may be one or more intermediary components. The terms "first," "second," "third," etc., are only for the convenience of describing this technical solution and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Therefore, features defined with "first," "second," "third," etc., may explicitly or implicitly include one or more of that feature. For those skilled in the art, the specific meaning of the above terms in this invention can be understood according to the specific circumstances.
[0025] It should also be understood that the terminology used in this specification is for the purpose of describing particular embodiments only and is not intended to limit the invention. As used in this specification and the appended claims, the singular forms “a,” “an,” and “the” are intended to include the plural forms unless the context clearly indicates otherwise.
[0026] It should also be further understood that the terms “and” and “or” as used in this specification and the appended claims refer to any combination of one or more of the associated listed items and all possible combinations, and include such combinations.
[0027] like Figures 1 to 6 As shown, Figure 1 This is an overall cross-sectional view of the prefabricated roof eaves provided in an embodiment of the present invention; Figure 2 A top view of the main purlin and secondary purlin in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 3 A top view of the secondary purlins and additional purlins in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 4 A cross-sectional view of the roof tile assembly in the prefabricated roof eaves provided in an embodiment of the present invention; Figure 5 This is a structural diagram of the roof tiles in a prefabricated roof eaves provided in an embodiment of the present invention; Figure 6 The structural diagram of the embedded steel plate in the prefabricated roof eaves provided in the embodiment of the present invention.
[0028] See also Figures 1 to 6 This invention discloses a prefabricated assembled roof eaves for mounting on a parapet wall 10, comprising an embedded steel plate 20, connecting purlins 30, and a roof tile assembly 40; the embedded steel plate 20 is pre-set within the wall body of the parapet wall 10, and at least one end face of the embedded steel plate 20 protrudes from the surface of the parapet wall 10; one end of the connecting purlin 30 is fixedly connected to the roof tile assembly 40; the roof tile assembly 40 and the connecting purlin 30 are hoisted to the position of the parapet wall 10 by a hoisting device; the other end of the connecting purlin 30 is fixedly connected to the end face of the embedded steel plate 20 protruding from the parapet wall 10.
[0029] In this embodiment, the prefabricated assembled roof eaves are assembled onto the parapet wall 10. An embedded steel plate 20 is pre-embedded within the parapet wall 10 during concrete pouring, and at least one end face of the embedded steel plate 20 protrudes from the surface of the parapet wall 10, forming an exposed connection base. One end of the connecting purlin 30 is fixedly connected to the roof tile assembly 40, and the other end is fixedly connected to the end face of the embedded steel plate 20 protruding from the surface of the parapet wall 10, thereby cantilevering the roof tile assembly 40 onto the parapet wall 10.
[0030] Among them, the embedded steel plate 20 is a load-bearing base integrated with the main structure, transferring all the load of the eaves to the parapet wall 10; the connecting purlin 30 is a connecting transition component, connecting the roof tile assembly 40 and the embedded steel plate 20 into a load-transfer unit; the roof tile assembly 40 is the main functional component of the eaves, and also undertakes the functions of enclosure drainage and facade design. The connection relationship of the three forms a complete load transfer path: the roof load is transferred through the roof tile assembly 40 to the connecting purlin 30, then through the connecting purlin 30 to the embedded steel plate 20, and finally through the embedded steel plate 20 and its anchoring structure to the concrete of the parapet wall 10.
[0031] This embodiment transforms the traditional wet operation process of on-site formwork, pouring, and curing of cast-in-place concrete eaves into a dry operation process of factory / ground prefabrication, overall hoisting, and welding. During construction, the embedded steel plate 20 is first completed during the parapet wall 10 pouring stage; then, the connecting purlins 30 and roof tile components 40 are assembled and welded into an integral eaves unit on the ground or roof structural slab; finally, the unit is hoisted to the parapet wall 10 position using hoisting equipment (such as a truck crane), and the exposed ends of the connecting purlins 30 and the embedded steel plate 20 are welded and fixed, thus completing the eaves installation. Workers (welders) operate entirely on the roof surface, eliminating the need for high-altitude ground support frames or cantilevered scaffolding.
[0032] Existing technologies for cast-in-place concrete eaves require the erection of ultra-high support frames exceeding 8 meters, making them large-scale and hazardous projects. These projects involve high-altitude operations with significant risks, and the construction period is subject to weather constraints. Furthermore, they suffer from issues such as leakage and cracking due to construction joints and vibration defects. This embodiment, through the aforementioned prefabricated structure, eliminates the support frame system, simplifies the construction process, and removes common concrete quality defects.
[0033] In some embodiments, the embedded steel plate 20 includes a plurality of top steel plates 21 and side steel plates 22. The plurality of top steel plates 21 are spaced apart along the length direction of the top surface of the parapet wall 10, and the plurality of side steel plates 22 are spaced apart along the length direction of the outer side surface of the parapet wall 10.
[0034] In this embodiment, the top steel plate 21 is spaced along the length of the top surface of the parapet wall 10, with its surface parallel to or slightly lower than the top surface of the parapet wall 10, and one end protruding beyond the top surface of the parapet wall 10; the side steel plates 22 are spaced along the length of the outer side surface of the parapet wall 10 (i.e., the side facing the cantilever direction of the eaves), embedded in the outer side surface near the top, and one end protruding beyond the outer side surface of the parapet wall 10. The top steel plate 21 and the side steel plates 22 are arranged vertically in a corresponding manner in the vertical plane, forming an L-shaped force-bearing combination with top surface bearing and side surface ties.
[0035] The top steel plate 21 primarily bears the vertical pressure and bending moment transmitted from the connecting purlins 30, vertically transferring the load to the compression zone of the parapet wall 10. The side steel plates 22, connected to the connecting purlins 30, bear the horizontal tension and overturning moment generated by the cantilevered end of the eaves, preventing the eaves from overturning outwards around the base. The two work together to ensure that the embedded node possesses both good bearing capacity and anti-overturning capacity, compensating for the insufficient anchoring force of a single-direction embedded plate.
[0036] Both the top steel plate 21 and the side steel plate 22 have threaded anchor bars 24 welded to one end embedded in the wall body, which are then anchored to the parapet wall 10 concrete to form a whole. The ends of the top steel plate 21 and the side steel plate 22 protruding from the wall surface are welded to the horizontal connecting purlin 31 and the vertical connecting purlin 32, respectively. The interval between adjacent top steel plates 21 and adjacent side steel plates 22 is the plain concrete area of the parapet wall 10, and the position of the steel plates is positioned by the steel reinforcement cage of the parapet wall 10 during pouring.
[0037] In some embodiments, the spacing between adjacent top steel plates 21 and the spacing between adjacent side steel plates 22 are equal to the height of the parapet wall 10.
[0038] In this embodiment, the spacing between adjacent top steel plates 21 and adjacent side steel plates 22 is equal to the height of the parapet wall 10. For example, when the height of the parapet wall 10 is 1500mm, the top steel plates 21 and side steel plates 22 are arranged at equal intervals along the length of the wall at 1500mm intervals.
[0039] The aforementioned spacing, equal to the height of the parapet wall 10, ensures that the load-bearing area served by each embedded node is square in planar projection, the eaves load is evenly distributed along the length of the wall, and the stress on a single set of embedded steel plates 20 is consistent. This facilitates structural calculations, factory prefabrication, and batch processing of embedded nodes according to unified standards, enabling modular design. At the same time, this spacing corresponds to the spacing of the connecting purlins 30, ensuring that each connecting purlin 30 corresponds to one embedded steel plate 20, with a clear force transmission path and no missing support points.
[0040] In some embodiments, the connecting purlin 30 includes a plurality of horizontal connecting purlins 31 and vertical connecting purlins 32; the roof tile assembly 40 is inclined relative to the parapet wall 10, one end of the plurality of horizontal connecting purlins 31 is fixedly connected to the roof tile assembly 40, and the other end is fixedly connected to a plurality of side steel plates 22; one end of the plurality of vertical connecting purlins 32 is fixedly connected to the roof tile assembly 40, and the other end is fixedly connected to a top steel plate 21.
[0041] In this embodiment, each main purlin 41 is connected to a horizontal connecting purlin 31 and a vertical connecting purlin 32 at its end, forming a double-limb force transmission node. The vertical connecting purlin 32 transmits the vertical load and bending moment from the roof tile assembly 40 to the top steel plate 21, and is the main load-bearing force transmission member; the horizontal connecting purlin 31 transmits the horizontal tension and overturning moment generated by the eaves overhang to the side steel plate 22, and is the main anti-overturning force transmission member. The horizontal connecting purlin 31 is welded to the end of the main purlin 41 in the roof tile assembly 40 or bolted to facilitate disassembly and reuse. The other end of the horizontal connecting purlin 31 is fully welded to the exposed end face of the side steel plate 22; the vertical connecting purlin 32 is welded to the side end of the main purlin 41, and the other end is fully welded to the exposed end face of the side steel plate 22. After welding, it forms a rigid node with the embedded steel plate 20.
[0042] By combining the horizontal and vertical double-connecting purlins 30 with the side and top double-embedded steel plates 20, this embodiment solves the problems of weak anti-overturning ability and easy loosening of nodes in single-point connection. The base of the eaves forms a spatial force system with high overall rigidity and strong resistance to wind and snow loads.
[0043] In some embodiments, the roof tile assembly 40 includes main purlins 41, secondary purlins 42, additional purlins 43, and roof tiles 44; the main purlins 41 are arranged in a plurality of parallel and spaced-apart structures, and each main purlin 41 is fixedly connected to the connecting purlin 30; the secondary purlins 42 are arranged in a plurality of parallel and spaced-apart structures and are fixedly mounted on the main purlins 41; the additional purlins 43 are arranged in a plurality of parallel and spaced-apart structures and are fixedly mounted on the secondary purlins 42; and a plurality of roof tiles 44 are fixedly mounted on the additional purlins 43.
[0044] In this embodiment, the main purlin 41 is the main keel of the roof tile assembly 40, directly bearing the supporting reaction force of the connecting purlin 30 and spanning adjacent support points, bearing the main bending moment, and is the main load-bearing component of the cantilevered eaves; the secondary purlin 42 is laid vertically on the main purlin 41, distributing the load from the roof tile 44 to multiple main purlins 41, while also increasing the spacing between support points, so that the spacing of the main purlins 41 can be increased to 1500mm without affecting the support of the tile surface; the additional purlin 43 directly supports the roof tile 44, provides a base material for the self-drilling screws, and ensures that the tile surface is laid flat; the roof tile 44 is the enclosure and drainage surface layer, and also serves as an antique-style design.
[0045] The main purlin 41 is welded to the connecting purlin 30 to form an integral node; the secondary purlin 42 is fully welded to the upper surface of the main purlin 41 around its perimeter; the additional purlin 43 is welded to the upper surface of the secondary purlin 42; the roof tile 44 is fixed to the additional purlin 43 by bolts 45. The purlins of each level are interwoven to form a spatial grid framework. The assembly sequence from bottom to top is: main purlin 41 → secondary purlin 42 → additional purlin 43 → roof tile 44. All levels are welded together to form a rigid unit that can be subjected to overall force and hoisted as a whole.
[0046] The three-level load-bearing system composed of the main purlin 41, secondary purlin 42, and additional purlin 43 solves the problems of insufficient stiffness, limited tile span, and large amount of keel used in the single-layer purlin system: the large-spacing main purlin 41 reduces the number of pre-embedded nodes, the medium-spacing secondary purlin 42 distributes the load, and the closely spaced additional purlin 43 adapts to the fixed module of the tile, thus achieving an optimized match between material usage and load-bearing performance.
[0047] In some embodiments, the main purlin 41, the secondary purlin 42, and the additional purlin 43 are all galvanized square tubes, and the spacing between adjacent main purlins 41 is 1500 mm, and the spacing between adjacent secondary purlins 42 is less than or equal to 800 mm.
[0048] In this embodiment, the main purlins 41, secondary purlins 42, and additional purlins 43 are all made of hot-dip galvanized square tubing, utilizing the galvanized layer to provide long-term corrosion protection under atmospheric conditions, adapting to open-air roof conditions. The spacing between adjacent main purlins 41 is 1500 mm, corresponding to the spacing of the embedded steel plates 20 and the height of the parapet wall 10; the spacing between adjacent secondary purlins 42 is less than or equal to 800 mm, preferably 750 mm, and 750 mm matches the width module of the 750-type roof tile 44, so that the fixing point of each tile falls evenly within the secondary purlin grid (i.e., the grid formed by the secondary purlins 42).
[0049] The main purlin 41 is made of 100×150×3 (unit: mm, width×height×wall thickness, the same below) galvanized square tube, with a large cross section and high bending stiffness, serving as the main load-bearing frame for the cantilever; the secondary purlin 42 is made of 50×50×3 galvanized square tube, fully welded to the main purlin 41 on all four sides, with a spacing of 750 mm; the auxiliary purlin 43 is made of 20×40×2 galvanized square tube, vertically welded to the secondary purlin 42 with a 40 mm edge, with a spacing of 750 mm.
[0050] In some embodiments, the roof tile assembly 40 further includes a plurality of screw connectors 45, and the roof tile 44 and the additional purlin 43 are provided with a plurality of through holes, and the roof tile 44 is fixed to the additional purlin 43 by the screw connectors 45 engaging with the through holes.
[0051] In this embodiment, the screw connector 45 is preferably a hexagonal self-drilling screw, which is installed using a hexagonal head and an electric wrench. It has both drilling and tightening functions, resulting in high construction efficiency and controllable tightening force. The screw connectors 45 are arranged in rows along the additional purlins 43 at the crest positions of the roof tiles 44. The spacing between each row is the same as the spacing between the additional purlins 43, i.e., 750 mm, ensuring that each tile has a reliable fixing point at the crest, and the tile surface does not bulge under the action of wind suction.
[0052] The roof tile 44 is made of 750-type antique-style metal tile, with a thickness of 1.2 mm and an aluminum-magnesium-manganese alloy plate. The tile is 750 mm wide, and the length is customized according to the overhang length. Adjacent roof tiles 44 overlap along the width direction, and through holes are provided at the overlap to share the same bolt 45 for fixing. The overlap seam is pressed in the direction of water flow to prevent rainwater backflow. The cantilevered ends of the roof tiles 44 are fitted with pre-finished tile ends 46 for edging. The tile ends 46 are made of the same material as the end roof tiles 44, serving to finish the eaves shape and prevent wind from blowing off the ends.
[0053] In some embodiments, the embedded steel plate 20 includes a panel 23 and threaded anchor bars 24, with multiple threaded anchor bars 24 fixedly disposed on one end face of the panel 23 embedded in the parapet wall 10.
[0054] In this embodiment, after pouring, the threaded anchor bars 24 are completely embedded inside the concrete of the parapet wall 10. The panel 23 is a rectangular steel plate, made of 200 mm × 300 mm × 10 mm thick Q235B hot-dip galvanized steel plate; the galvanized layer of the panel 23 provides rust protection in the pre-embedded state.
[0055] The threaded anchor bar 24 consists of four Φ12 mm threaded steel bars, each 100 mm long. One end is welded to the back of the panel 23, and the other end is a free end. After being embedded in the concrete, it relies on the mechanical interlocking of the ribs with the concrete to provide anchoring force. The specific pre-embedded construction method is as follows: After the parapet wall 10 is erected, the pre-embedded steel plate 20 is positioned on the reinforcing steel skeleton of the parapet wall 10 according to the design spacing. The panel 23 is temporarily fixed to the reinforcing steel skeleton of the parapet wall 10 using binding wire. After checking the elevation and flatness, the formwork is sealed and concrete is poured. During pouring, the vibrator should be prevented from directly impacting the panel 23. After demolding, the laitance around the exposed end face of the panel 23 is removed to expose a clean steel plate surface for welding with the connecting purlin 30. The threaded anchor bar 24 can prevent the embedded steel plate 20 from being pulled out of the concrete under the vertical load and overturning moment of the eaves, so that the embedded node has reliable pull-out and overturning resistance, and solves the defects of insufficient anchoring depth and easy loosening under long-term load of post-installed expansion anchor bolt type embedded plate.
[0056] In some embodiments, each of the threaded anchor bars 24 is equidistant from the center of the panel 23.
[0057] In this embodiment, the distance from each threaded anchor bar 24 to the center of the panel 23 is equal, meaning that the multiple threaded anchor bars 24 are arranged symmetrically about the geometric center of the panel 23. Specifically, four Φ12 mm threaded anchor bars 24 are distributed in four quadrants with the center of the panel 23 as the origin, symmetrically arranged in pairs along the length and width of the panel 23, forming a grid shape. The distance from the center of each threaded anchor bar 24 to the center of the panel 23 is equal, for example, offset by 60 mm along the length and 75 mm along the width.
[0058] The purpose of the symmetrical arrangement is to ensure that when the eaves load is transmitted to each threaded anchor bar 24 through the panel 23, the tensile force borne by each anchor bar is equal and the force is applied synchronously, thus avoiding the situation where individual bars are overloaded and the panel 23 warps due to the eccentric arrangement of the anchor bars; at the same time, the symmetrical arrangement makes the local bearing pressure zone of the concrete evenly distributed, reducing the risk of concrete splitting and ensuring the anchorage reliability of the embedded nodes under long-term repeated wind loads.
[0059] In some embodiments, the connecting purlin 30 is a galvanized square tube.
[0060] In this embodiment, the connecting purlins 30 are galvanized square tubes. Specifically, the horizontal connecting purlins 31 are 100×150×3 galvanized square tubes of the same specifications as the main purlins 41, and the vertical connecting purlins 32 are also 100×150×3 galvanized square tubes. The galvanized square tubes have a closed rectangular cross-section, providing high bending and torsional stiffness and a smooth surface, facilitating welding with the square-tube main purlins 41 and the flat panel 23. The hot-dip galvanized layer allows the connecting purlins 30 to adapt to the damp, open-air environment of the roof, resulting in a long service life.
[0061] The construction method for the above-mentioned prefabricated roof eaves is as follows: During the reinforcement binding and formwork sealing stage of the parapet wall, the embedded steel plate is fixed to the reinforcement skeleton of the parapet wall, and at least one end face of the embedded steel plate is flush with or protrudes from the surface of the parapet wall. The concrete of the parapet wall is poured so that the embedded steel plate and the parapet wall form an integral whole. On the ground or roof structure slab, one end of the connecting purlin is fixedly connected to the roof tile assembly to form an eaves unit; The eaves unit was hoisted as a whole to the position of the parapet wall using hoisting equipment; After adjusting the position of the eaves unit, the other end of the connecting purlin is welded and fixed to the end face of the pre-embedded steel plate protruding from the parapet wall, so that the roof tile assembly is cantilevered and supported on the parapet wall.
[0062] This construction method specifically includes the following stages: Pre-embedded stage: During the stage of binding the parapet wall reinforcement and sealing the formwork, the pre-embedded steel plates (including the welded threaded anchor bars) are fixed to the parapet wall reinforcement skeleton at 1500 mm intervals. The exposed end face of the control panel is flush with the surface of the parapet wall or a welding operation surface is reserved. Then the parapet wall concrete is poured. Unit assembly stage: On the ground or roof structural slab, first weld the main purlins and horizontal connecting purlins and vertical connecting purlins, then weld the secondary purlins and additional purlins in sequence to form a grid frame; then lay the roof tiles and fix them to the additional purlins with hexagonal self-drilling screws through the through holes, install the finished tile ends, and assemble into an overall eaves unit; Lifting stage: The truck crane enters the site and is set up within the working radius outside the parapet wall. The lifting slings are attached to the junction of the main purlin and the connecting purlin. The crane is slowly lifted and positioned above the parapet wall. In-place welding stage: After adjusting the elevation, levelness and cantilever length of the eaves unit, fully weld the horizontal connecting purlins to the side steel plates and the vertical connecting purlins to the top steel plate to form a rigid connection; Final inspection stage: Apply zinc-rich paint to the weld seams, check the flatness of the tile surface and the tightness of the bolts, and complete the flashing at the base of the eaves and the waterproof membrane on the roof.
[0063] The above are merely specific embodiments of the present invention, but the scope of protection of the present invention is not limited thereto. Any person skilled in the art can easily conceive of various equivalent modifications or substitutions within the technical scope disclosed in the present invention, and these modifications or substitutions should all be covered within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be determined by the scope of the claims.
Claims
1. A prefabricated assembled roof eaves for mounting on a parapet wall, characterized in that, The system includes an embedded steel plate, connecting purlins, and roof tile assemblies. The embedded steel plate is pre-installed within the parapet wall, and at least one end face of the embedded steel plate protrudes from the surface of the parapet wall. One end of the connecting purlin is fixedly connected to the roof tile assembly. The roof tile assembly and the connecting purlin are hoisted to the position of the parapet wall using hoisting equipment. The other end of the connecting purlin is fixedly connected to the end face of the embedded steel plate protruding from the parapet wall.
2. The prefabricated assembled roof eaves according to claim 1, characterized in that, The embedded steel plate includes a plurality of top steel plates and side steel plates. The plurality of top steel plates are spaced apart along the length of the top surface of the parapet wall, and the plurality of side steel plates are spaced apart along the length of the outer side surface of the parapet wall.
3. The prefabricated assembled roof eaves according to claim 2, characterized in that, The spacing between adjacent top steel plates and the spacing between adjacent side steel plates are equal to the height of the parapet wall.
4. The prefabricated assembled roof eaves according to claim 2, characterized in that, The connecting purlins include a plurality of horizontal connecting purlins and vertical connecting purlins; the roof tile assembly is inclined relative to the parapet wall, one end of the plurality of horizontal connecting purlins is fixedly connected to the roof tile assembly, and the other end is fixedly connected to a plurality of side steel plates; one end of the plurality of vertical connecting purlins is fixedly connected to the roof tile assembly, and the other end is fixedly connected to a plurality of top steel plates.
5. The prefabricated assembled roof eaves according to claim 4, characterized in that, The roof tile assembly includes main purlins, secondary purlins, additional purlins, and roof tiles; the main purlins are arranged in a series of parallel and spaced-apart sections, each of which is fixedly connected to a connecting purlin; the secondary purlins are arranged in a series of parallel and spaced-apart sections and are fixed to the main purlins; the additional purlins are arranged in a series of parallel and spaced-apart sections and are fixed to the secondary purlins; and several roof tiles are fixed to the additional purlins.
6. The prefabricated assembled roof eaves according to claim 5, characterized in that, The main purlins, the secondary purlins, and the additional purlins are all galvanized square tubes, and the spacing between adjacent main purlins is 1500 mm, while the spacing between adjacent secondary purlins is less than or equal to 800 mm.
7. The prefabricated assembled roof eaves according to claim 5, characterized in that, The roof tile assembly also includes several screw connectors. The roof tiles and the additional purlins are provided with several through holes. The screw connectors cooperate with the through holes to fix the roof tiles to the additional purlins.
8. The prefabricated assembled roof eaves according to claim 1, characterized in that, The embedded steel plate includes a panel and threaded anchor bars, with multiple threaded anchor bars fixed to one end face of the panel embedded in the parapet wall.
9. The prefabricated assembled roof eaves according to claim 8, characterized in that, Each of the threaded anchor bars is equidistant from the center of the panel.
10. A construction method for prefabricated assembled roof eaves, characterized in that, Used for constructing the prefabricated assembled roof eaves as described in any one of claims 1-9; the construction method includes: During the reinforcement binding and formwork sealing stage of the parapet wall, the embedded steel plate is fixed to the reinforcement skeleton of the parapet wall, and at least one end face of the embedded steel plate is flush with or protrudes from the surface of the parapet wall. The concrete of the parapet wall is poured so that the embedded steel plate and the parapet wall form an integral whole. On the ground or roof structure slab, one end of the connecting purlin is fixedly connected to the roof tile assembly to form an eaves unit; The eaves unit was hoisted as a whole to the position of the parapet wall using hoisting equipment; After adjusting the position of the eaves unit, the other end of the connecting purlin is welded and fixed to the end face of the pre-embedded steel plate protruding from the parapet wall, so that the roof tile assembly is cantilevered and supported on the parapet wall.