Integrated device for in-situ tracer sealing and testing of underground rock mass and its usage method
By designing an integrated underground rock mass in-situ tracer borehole placement and testing device, which integrates sealing, placement, and testing functions, the problems of low efficiency, poor accuracy, and large disturbance in traditional step-by-step operations are solved, and efficient and accurate rock mass borehole tracer tests are achieved.
Patent Information
- Application Number
- CN202611490444.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-23
- Publication Date
- 2026-11-17
AI Technical Summary
In existing rock mass borehole tracer tests, the separate operation of sealing, deployment, and testing leads to cumbersome processes, high costs, large disturbances in the seepage field, inaccurate tracer deployment, unreliable sealing quality, and a lack of integrated pressure management and fluid control mechanisms.
Design an integrated device for in-situ tracer sealing and testing in underground rock masses, including a multi-channel main pipe, a long-term pressure-maintaining flexible sealing system, a tracer delivery system, a pumping and acquisition system, a monitoring system, and a borehole control system. This device integrates borehole sealing and isolation, tracer delivery, and in-situ testing. It achieves borehole sealing through a flexible high-pressure expansion membrane, and combines the delivery, acquisition, and positioning device with the borehole control system to ensure stable sealing pressure and accurate tracer delivery.
It realizes the integrated operation of the entire process of rock mass borehole tracer test, simplifies the operation process, improves test efficiency and accuracy, reduces seepage field disturbance, ensures the quality of borehole sealing and the accuracy of tracer dosing, and adapts to the needs of in-situ rock mass tracer tests of different scales and purposes.
Smart Images

Figure CN123109645A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the fields of hydrogeology, engineering geology and rock mechanics testing technology, specifically to an integrated device for in-situ tracing and sealing testing of underground rock masses and its usage method. Background Technology
[0002] In-situ tracer testing of underground rock masses is an important field testing method in the fields of hydrogeology, engineering geology, and rock mechanics. It is widely used in engineering practices such as characterizing groundwater seepage fields, determining rock mass fracture connectivity, tracing pollutant transport paths, evaluating geothermal reservoir permeability, and assessing the suitability of high-level radioactive waste geological repositories. The basic principle of tracer testing is to release a certain amount of tracer into a borehole in the target rock mass. By detecting the arrival time, concentration changes, and other characteristic parameters of the tracer at downstream monitoring points, the hydraulic connections, seepage channels, and permeability parameters within the rock mass can be inferred.
[0003] Traditional rock borehole tracer tests typically employ a step-by-step approach: first, a packer is used to seal and isolate the target section of the borehole; then, tracer is injected into the sealed section through a separate delivery pipeline; finally, a separate testing device is used to monitor the tracer concentration or related physical quantities. This step-by-step approach has several inherent drawbacks:
[0004] Firstly, the three stages of sealing, placement, and testing are completed by different independent devices, and there is a lack of effective coordination and connection between the devices, resulting in a complicated testing process, long operation time, and high labor costs.
[0005] Secondly, during repeated deployments and device replacements, the packer is prone to displacement or sealing failure, resulting in unreliable sealing quality, which in turn affects the effective isolation of the tracer and the accuracy of test data.
[0006] Third, the independent operation of each stage inevitably increases the disturbance to the original seepage field in the borehole. In particular, the repeated raising and lowering of the device may change the stress state and permeability characteristics of the fractures around the borehole, causing the test results to deviate from the true in-situ state.
[0007] Fourth, the existing tracer placement mainly relies on testing the length of the placement pipeline at the borehole opening to determine the placement outlet location. However, the placement pipeline often experiences entanglement, floating, or stretching, which interferes with the accurate positioning of the tracer placement. Some rock fracture tracer tests have high requirements for the correspondence between the placement point and the fracture inside the borehole, and traditional placement methods are difficult to achieve accurate placement of the tracer inside the borehole.
[0008] Fifth, the existing sealing device and tracer delivery system lack an integrated pressure management and fluid control mechanism, making it difficult to achieve precise coordination between sealing pressure and injection pressure, which can easily lead to tracer leakage or crossflow in the sealing section.
[0009] In response to the aforementioned problems, some scholars and engineers have conducted relevant improvement research in recent years. For example, some studies have proposed an integrated drilling and solid-state testing device that combines drilling, sealing, fracturing, and multi-physics monitoring, achieving a high degree of integration of multiple processes. In the field of gas drainage drilling, there have also been reports of integrated sealing technology and integrated three-bag sealing devices. However, existing integrated devices are mainly designed for specific application scenarios such as fracturing modification testing or gas drainage, and there are no reports of a fully integrated device specifically for in-situ rock mass tracer testing with a complete sealing and delivery testing process. Current technologies still lack a systematic design that organically integrates the three functional modules of sealing isolation, precise tracer delivery, and in-situ testing into a single device; there is a lack of a linkage control mechanism between the sealing mechanism and the delivery mechanism, making it difficult to maintain a sealed state while completing the quantitative and constant-pressure injection of the tracer; and the integration degree of the testing sensors with the sealing and delivery system is insufficient, making it difficult to form a standardized in-situ tracer testing method.
[0010] These types of gas extraction sealing devices generally adopt a permanent sealing method of bag grouting and solidification, which only serves the long-term sealing of the gas extraction channel. They do not have the integrated functions of quantitative tracer dosing, in-hole water sampling and in-situ concentration monitoring, nor can they recover the device after the test and avoid residual damage to the original seepage channel of the rock mass by the sealing material. Summary of the Invention
[0011] In view of the shortcomings of the prior art, the purpose of the present invention is to provide an integrated device and method for in-situ tracing borehole sealing and testing of underground rock mass. The integrated device and method can realize the integrated operation of the entire process of rock mass borehole tracing test, and can overcome the technical problems of low test efficiency, poor deployment accuracy and large test disturbance caused by the separate operation of sealing, deployment and testing in the prior art.
[0012] To solve the above-mentioned technical problems, the present invention adopts the following technical solution:
[0013] An integrated device for in-situ tracing and sealing borehole deployment testing in underground rock mass includes an in-situ underground rock mass tracer and a borehole control system. The in-situ underground rock mass tracer and the borehole control system are connected via pipelines and valves. The in-situ underground rock mass tracer includes two sets of axially connected multi-channel main pipes, a long-term pressure-maintaining flexible sealing system sleeved on the outer wall of the multi-channel main pipes, a tracer deployment system for connecting the two multi-channel main pipes in series and providing feedback on the deployment position, a pumping and sampling system installed on the tracer deployment system, a monitoring system installed on the tracer deployment system, and a connection system. The multi-channel main tube is a hollow cylinder with multiple channels arranged parallel to the axis along the inner wall of the main tube. The multiple channels include a tracer delivery channel for delivering tracer, a sealing liquid injection channel for delivering sealing liquid, a data transmission channel for transmitting data, and a pumping and collecting channel for delivering collected liquid samples. The monitoring system is located on the outer wall of the tracer delivery system and is used to collect monitoring information. The connection system is located at the end of the multi-channel main tube to facilitate pipeline connection between each channel of the multi-channel main tube and the orifice control system.
[0014] Based on the aforementioned device, the long-term pressure-holding flexible sealing system includes at least one layer of flexible high-pressure expansion membrane, a sealing fluid outlet, and a sealing ring. The flexible high-pressure expansion membrane forms a sealed chamber with the outer wall of the multi-channel main tube. The sealed chamber is connected to the sealing fluid injection channel via the sealing fluid outlet located on the wall of the multi-channel main tube. The sealing ring is located at both ends of the flexible high-pressure expansion membrane, and its inner wall is sealed to the outer wall of the multi-channel main tube to seal the sealed chamber. Sealing fluid is injected into the sealed chamber through the sealing fluid injection channel and the sealing fluid outlet, causing the flexible high-pressure expansion membranes on the two multi-channel main tubes to expand outwards and tighten the inner wall of the borehole, achieving sealing and isolation of the target section of the borehole, forming a borehole sealing section.
[0015] The tracer delivery system includes a tracer delivery and acquisition section connector, a tracer delivery and acquisition section main tube, a delivery and acquisition positioning device, and a delivery port. The tracer delivery and acquisition section main tube is connected to a multi-channel main tube via the tracer delivery and acquisition section connector. The tracer delivery and acquisition section main tube has multiple channels corresponding to the multi-channel main tube. The delivery port is located on the side wall of the tracer delivery and acquisition section main tube and communicates with the tracer delivery channels to allow the tracer to be output from the delivery port into the borehole to be tested. The delivery and acquisition positioning device is mounted on the tracer delivery and acquisition section main tube. The delivery and acquisition positioning device is at least one of a depth gauge, altimeter, acoustic locator, or camera, and is connected to the borehole control system via a data transmission channel.
[0016] The water pumping and collection system includes a collection port, which is located on the side wall of the tracer delivery system and is connected to the water pumping and collection channel.
[0017] The connection system includes a first-section connector and an end-section connector. The first-section connector has a tracer channel connection hole, a sealing channel connection hole, a data channel connection port, a pumping channel connection port, a fixing connection port, and a hanging ring. The tracer channel connection hole, sealing channel connection hole, data channel connection port, and pumping channel connection port are respectively connected to the upper ends of the tracer dosing channel, the sealing injection channel, the data transmission channel, and the pumping acquisition channel. The hanging ring connects to the fixing connection port. The end-section connector is located at the lower end of the multi-channel main tube to seal the ends of each channel.
[0018] The monitoring system is installed on the outer wall of the tracer delivery system and is connected to the data transmission channel. The monitoring system includes at least one of a temperature sensor, a pressure sensor, an ion concentration sensor, and a fluorescence concentration sensor.
[0019] The orifice control system includes an injection pump, a tracer storage tank, a data acquisition unit, a pumping pump, a collection tank, a sealing pump, a sealing liquid tank, and a pressure gauge. The injection pump and tracer storage tank are connected to the tracer delivery channel via pipelines and valves. The pumping pump and collection tank are connected to the water collection channel via pipelines and valves. The sealing pump, sealing liquid tank, and pressure gauge are connected to the sealing injection channel via pipelines and valves. The data acquisition unit is connected to the data transmission channel via pipelines.
[0020] A method for using the aforementioned integrated device for in-situ tracer sealing and testing of underground rock mass includes a single-hole tracer method. After assembling the device and preparing the tracer, the in-situ tracer is lowered to the target location within the borehole and the borehole is sealed. Initial parameters are collected through a monitoring system, followed by sequential operations such as quantitative tracer injection, displacement with distilled water or in-situ groundwater, and collection of fluid from the borehole. After the test, the device is retrieved and the data is processed. During the sealing stage, sealing fluid or water is injected into the sealed chamber between the flexible high-pressure expansion membrane and the multi-channel main pipe, causing the membrane to expand and tighten against the borehole wall. Injection stops once the set sealing pressure is reached. The sealing pressure is monitored throughout the test, and pressure is replenished promptly when the pressure drop reaches 5% of the set value to maintain the sealed chamber pressure at no less than 95% of the set value. During the tracer delivery stage, tracer is first injected at a preset pressure or flow rate to the predetermined dosage, then distilled water or in-situ groundwater is used for displacement with the same parameters until the preset displacement amount is reached. During the liquid collection phase, a pump is used to collect liquid from the sealed section at a preset negative pressure or flow rate until the preset collection time or volume is reached.
[0021] The aforementioned method also includes a borehole tracing method. This method employs two sets of in-situ underground rock tracers, deployed in the tracer deployment borehole and the tracer acquisition borehole, respectively. Both sets of tracers share a single borehole control system. After sealing the borehole and acquiring initial parameters, the tracer in the deployment borehole injects tracer and performs distilled water or in-situ groundwater displacement operations, while the tracer in the acquisition borehole simultaneously performs liquid acquisition operations. Acquisition continues until the tracer in the deployment borehole stops injecting, at which point the tracer in the acquisition borehole stops acquiring liquid.
[0022] The aforementioned methods also include a multi-well tracing method. This method employs multiple sets of in-situ tracers for underground rock masses, including at least one set of tracer delivery well tracers and at least one set of tracer collection well tracers. Multiple wellhead control systems are configured, and each tracer collection well tracer is individually connected to a pumping pump and a collection tank. After sealing each well and acquiring initial parameters, all tracer delivery well tracers simultaneously perform tracer injection and distilled water or in-situ groundwater displacement operations, while all tracer collection well tracers perform liquid collection operations until all tracer delivery well tracers stop injection, at which point all tracer collection well tracers cease collection.
[0023] The beneficial effects of this invention are as follows:
[0024] First, this invention integrates three major functions—sealing and isolation, tracer delivery, and in-situ testing—into a single multi-channel main tube, enabling the underground rock mass in-situ tracer to complete all test operations in one go. This avoids the disturbance to the borehole seepage field caused by the multiple raising and lowering of the device in traditional step-by-step operations, which is beneficial to maintaining the in-situ authenticity of the test results. At the same time, it simplifies the test process and shortens the operation time.
[0025] Secondly, the present invention uses a long-term pressure-maintaining flexible sealing system in conjunction with a pressure gauge of the orifice control system for real-time monitoring. This allows for timely replenishment of sealing fluid based on pressure decay during long-term tracer tests, maintaining the sealing pressure at or above the set threshold. This ensures the sealing quality during long-term tests and prevents tracer leakage or cross-flow in the packer section due to packer seal failure.
[0026] Third, by setting up a placement acquisition and positioning device on the tracer placement system, the present invention can directly confirm the corresponding position of the placement port and the target crack inside the hole, avoiding the error caused by relying on the length of the pipeline to estimate the placement position in the traditional method, which is conducive to improving the positioning accuracy of tracer placement.
[0027] Fourth, this invention achieves integrated arrangement of various functional pipelines through the parallel arrangement of tracer delivery channels, sealing and injection channels, data transmission channels, and water pumping and collection channels within the multi-channel main pipe. Each channel is independent of the others and does not interfere with each other, which is conducive to achieving precise and coordinated control of sealing pressure and injection pressure.
[0028] Fifth, the application method of the present invention covers three modes: single-hole tracing, pair-hole tracing, and multi-hole tracing, which can adapt to the needs of in-situ rock mass tracing tests of different scales and purposes. In the multi-hole tracing method, each set of sampling hole tracers is equipped with a separate extraction pump and sampling tank, which helps to ensure the independence and accuracy of data from each hole when multiple holes are collected simultaneously. Attached Figure Description
[0029] Figure 1 This is a front view of an in-situ tracer for underground rock masses.
[0030] Figure 2 A three-dimensional structural line diagram of an in-situ tracer for underground rock masses;
[0031] Figure 3 for Figure 1 A cross-sectional diagram of the AA section shows the arrangement of the channels within the multi-channel main pipe;
[0032] Figure 4 for Figure 1 A schematic diagram of the cross-section of the BB system shows the cross-sectional structure of the long-term pressure-holding flexible sealing system;
[0033] Figure 5 for Figure 1 A schematic cross-sectional view of the CC section shows the cross-sectional structure of the tracer delivery system;
[0034] Figure 6 for Figure 1 A schematic diagram of the DD profile shows the overall longitudinal profile of the in-situ tracer for underground rock mass.
[0035] Figure 7 for Figure 6 An enlarged schematic diagram of the EE region shows the channel connection structure of the first connector.
[0036] Figure 8 A schematic diagram of the integrated device for in-situ tracing and sealing testing of underground rock mass (before sealing).
[0037] Figure 9 A schematic diagram of the integrated device for in-situ tracing and sealing testing of underground rock masses (after sealing).
[0038] Labeling Explanation: 1-Multi-channel main pipe, 2-Long-term pressure-holding flexible sealing system, 3-Tracer delivery system, 4-Pumping and data acquisition system, 5-Monitoring system, 6-Orifice control system, 7-Connection system, 8-Pipeline, 9-Valve, 10-In-situ tracer for underground rock mass, 11-Tracer delivery channel, 12-Sealing injection channel, 13-Data transmission channel, 14-Pumping and data acquisition channel, 21-Flexible high-pressure expansion membrane, 22-Sealing fluid outlet, 23-Sealing ring, 31-Tracer delivery and data acquisition section connector, 32-Tracer... 33-Submission and collection section main pipe, 34-Submission port, 41-Collection hole, 61-Injection pump, 62-Tracer storage tank, 63-Data collector, 64-Pumping pump, 65-Collection tank, 66-Sealing pump, 67-Sealing liquid tank, 68-Pressure gauge, 71-First section connector, 72-End connector, 711-Tracer channel connection hole, 712-Sealing channel connection hole, 713-Data channel connection port, 714-Pumping channel connection port, 715-Fixing connection port, 716-Hanging ring. Detailed Implementation
[0039] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be understood that the following embodiments are for illustrative purposes only and are not intended to limit the scope of protection.
[0040] like Figure 1-9 As shown, this embodiment provides an integrated device for in-situ tracing and sealing borehole deployment testing in underground rock mass, including an in-situ underground rock mass tracer 10 and a borehole control system 6. The in-situ underground rock mass tracer 10 and the borehole control system 6 are connected by pipelines 8 and valves 9. The in-situ underground rock mass tracer 10 includes a multi-channel main pipe 1, a long-term pressure-maintaining flexible sealing system 2, a tracer deployment system 3, a pumping and data acquisition system 4, a monitoring system 5, and a connection system 7.
[0041] like Figures 3-6As shown, the multi-channel main tube 1 is a hollow cylinder, and its material can be PVC, PP, metal, or alloy. Multiple channels are arranged parallel to the axis along the inner wall of the multi-channel main tube 1, including a tracer delivery channel 11, a sealing injection channel 12, a data transmission channel 13, and a water collection channel 14. Each channel is independent and not interconnected. The upper end of the tracer delivery channel 11 is connected to the injection pump 61 and tracer storage tank 62 of the orifice control system 6 via a connector, valve 9, and pipeline 8 (which is a fluid pipeline), and the lower end is connected to the tracer delivery system 3. The upper end of the sealing injection channel 12 is connected to the sealing pump 66 and sealing liquid tank 67 of the orifice control system 6 via a connector, valve 9, and pipeline 8 (which is a fluid pipeline), and the lower end is connected to the long-term pressure-maintaining flexible sealing system 2. The upper end of the data transmission channel 13 is connected to the data acquisition unit 63 of the orifice control system 6 via a connector and a pipeline 8 (which is a hollow pipe with data lines inside the data transmission channel 13 and the pipeline), and the lower end is connected to the monitoring system 5. The upper end of the pumping acquisition channel 14 is connected to the pumping pump 64 and the acquisition tank 65 of the orifice control system 6 via a pipeline 8 (which is a fluid pipe) and a valve 9, and the lower end is connected to the acquisition hole 41 of the pumping acquisition system 4.
[0042] like Figure 4 , Figure 5 and Figure 6 As shown, a long-term pressure-maintaining flexible sealing system 2 is fitted onto the outer wall of the multi-channel main pipe 1, including at least one flexible high-pressure expansion membrane 21, a sealing fluid outlet 22, and a sealing ring 23. A sealed chamber is formed between the flexible high-pressure expansion membrane 21 and the outer wall of the multi-channel main pipe 1. The sealed chamber is connected to the sealing fluid injection channel 12 via the sealing fluid outlet 22 on the multi-channel main pipe 1. The sealing ring 23 is located at both ends of the flexible high-pressure expansion membrane 21, and its inner wall surface is sealed to the outer wall surface of the multi-channel main pipe 1 (this sealing can be achieved by adhesive bonding) to seal both ends of the sealed chamber and prevent sealing fluid leakage. Sealing fluid or water at a certain pressure is injected into the sealed chamber through the sealing fluid injection channel 12, causing the flexible high-pressure expansion membrane 21 to expand outward and tighten the inner wall of the borehole, thereby achieving sealing and isolation of the target section of the borehole (forming a borehole sealing section). A pressure gauge 68 is installed on the pipeline 8 to monitor the pressure changes within the sealed chamber in real time. During long-term tracer tests, the sealing fluid or water can be replenished in a timely manner according to the pressure decay displayed by pressure gauge 68 to maintain the pressure in the sealed chamber and ensure the long-term sealing quality.
[0043] like Figure 5 and Figure 6As shown, the tracer delivery system 3 is located between two long-term pressure-holding flexible sealing systems 2, and includes a tracer delivery and acquisition section connector 31, a tracer delivery and acquisition section main tube 32, a delivery and acquisition positioning device 33, and a delivery port 34. The tracer delivery and acquisition section main tube 32 has the same structure as the multi-channel main tube 1, and is also equipped with a tracer delivery channel 11, a sealing liquid injection channel 12, a data transmission channel 13, and a water pumping and acquisition channel 14. The length can be adjusted to meet the requirements of actual experiments for the length of the tracer delivery and acquisition section. One end of the tracer delivery and acquisition section connector 31 is connected to the multi-channel main tube 1 (the tracer delivery and acquisition section connector 31 can be a flange, and the lower part of the multi-channel main tube 1 is equipped with a corresponding flange to realize the docking of the multi-channel main tube 1 and the tracer delivery and acquisition section main tube 32), and the other end is connected to the tracer delivery and acquisition section main tube 32. The corresponding tight connection of each channel is achieved by setting an embedded sealing pin and a sealing ring. The delivery port 34 is located on the side wall of the main tube 32 of the tracer delivery and collection section and is connected to the tracer delivery channel 11. It is used to deliver tracer into the sealing section inside the borehole. The delivery and collection positioning device 33 is located on the main tube 32 of the tracer delivery and collection section. It can be a depth gauge, altimeter, acoustic locator, or camera, etc., which can accurately locate or capture the borehole morphology of the expected delivery point. The data or images measured by the delivery and collection positioning device 33 are transmitted to the data acquisition unit 63 of the borehole control system 6 via the data transmission channel 13 through the data cable.
[0044] The pumping and sampling system 4 includes a sampling hole 41, which is located on the side wall of the main tube 32 of the tracer delivery and sampling section. The sampling hole 41 is connected to the pumping and sampling channel 14 and is used to collect liquid samples from the borehole sealing section.
[0045] The monitoring system 5 is installed on the outer wall of the main tube 32 of the tracer delivery and collection section and is connected to the data transmission channel 13. According to the test requirements, the monitoring system 5 may include various sensors such as temperature sensor, pressure sensor, ion concentration sensor, and fluorescence concentration sensor, which are used to monitor various physicochemical parameters in the isolation section in real time during the test. The monitoring data is transmitted to the data acquisition unit 63 of the orifice control system 6 through the data transmission channel 13 via the data cable for storage and analysis.
[0046] like Figure 1 , Figure 7As shown, the connection system 7 includes a first-section connector 71 and an end-section connector 72 located at the upper and lower parts of the in-situ tracer 10 in the underground rock mass. The first-section connector 71 is equipped with a tracer channel connection hole 711, a sealing channel connection hole 712, a data channel connection port 713, a pumping channel connection port 714, a fixing connection port 715, and a hanging ring 716. The tracer channel connection hole 711, the sealing channel connection hole 712, the data channel connection port 713, and the pumping channel connection port 714 are respectively connected to the upper ends of the tracer delivery channel 11, the sealing injection channel 12, the data transmission channel 13, and the pumping acquisition channel 14. The hanging ring 716 is connected to the fixed connection port 715 (the upper part of the hanging ring 716 is a ring body, and the lower part of the hanging ring 716 is a screw, which connects to the threaded hole of the fixed connection port 715). The upper part of the hanging ring 716 is used to connect a lowering rope or cable so as to lower the underground rock mass in-situ tracer 10 to a designated position in the borehole. The end connector 72 is set at the lower end of the multi-channel main tube 1 to strictly seal the end of each channel and prevent liquid from leaking from the lower end of the channel.
[0047] like Figure 8 and Figure 9 As shown, the orifice control system 6 includes an injection pump 61, a tracer storage tank 62, a data acquisition unit 63, an extraction pump 64, a collection tank 65, a sealing pump 66, a sealing liquid tank 67, and a pressure gauge 68. The injection pump 61 and the tracer storage tank 62 are tightly connected to the tracer channel connection port 711 of the first-section connector 71 via pipelines 8 and valves 9. The tracer in the tracer storage tank 62 is pressurized and released through the cooperation of the injection pump 61 and valves 9, allowing for precise control of the tracer release pressure and flow rate. The extraction pump 64 and the collection tank 65 are tightly connected to the water extraction channel connection port 714 of the first-section connector 71 via pipelines 8 and valves 9, and are used to extract liquid samples from the borehole sealing section and store them in the collection tank 65. The sealing pump 66, sealing liquid tank 67, and pressure gauge 68 are tightly connected to the sealing channel connection hole 712 of the first-section connector 71 via pipeline 8 and valve 9. The sealing liquid or water in the sealing liquid tank 67 is injected into the sealing chamber through the sealing pump 66, and the pressure gauge 68 is used to monitor the pressure in the sealing chamber in real time. The data acquisition unit 63 is tightly connected to the data channel connection port 713 of the first-section connector 71 via pipeline 8, and receives and stores the data transmitted by the monitoring system 5 and the deployment and acquisition positioning device 33 via data line.
[0048] The following details the usage of the device in this embodiment, including single-hole tracing, pair-hole tracing, and group-hole tracing methods.
[0049] The single-hole tracer method is suitable for experimental scenarios where tracer delivery and collection are carried out within a single borehole. The detailed steps are as follows:
[0050] The first step is to assemble the in-situ underground rock mass tracer 10. Adjust the length of the main tube 32 of the tracer deployment and acquisition section to meet the experimental requirements for the length of the tracer deployment and acquisition section; ensure that each channel of the multi-channel main tube 1 is tightly connected to each channel of the main tube 32 of the tracer deployment and acquisition section through the tracer deployment and acquisition section connector 31; ensure that the end of each channel of the multi-channel main tube 1 is strictly sealed by the end connector 72; ensure that each pipeline 8 is tightly connected to the connection hole on the first section connector 71; and ensure that all pipelines, channels, sensors, flexible high-pressure expansion membrane 21, sealing pressure ring 23, and other structures can function normally.
[0051] The second step is to assemble the orifice control system 6. Ensure that the injection pump 61, tracer storage tank 62, and tracer channel connection hole 711 are tightly connected via pipeline 8 and valve 9; ensure that the extraction pump 64, collection tank 65, and water pumping channel connection port 714 are tightly connected via pipeline 8 and valve 9; ensure that the sealing pump 66, sealing liquid tank 67, pressure gauge 68, and sealing channel connection hole 712 are tightly connected via pipeline 8 and valve 9; ensure that the data acquisition unit 63 and data channel connection port 713 are tightly connected via pipeline 8; ensure that the injection pump 61, tracer storage tank 62, extraction pump 64, collection tank 65, sealing pump 66, sealing liquid tank 67, data acquisition unit 63, and all pressure gauges 68, valves 9, and pipelines 8 are functioning properly; prepare the required tracer for the experiment and fill it into the tracer storage tank 62; fill the sealing liquid tank 67 with a sufficient amount of sealing liquid or water.
[0052] The third step is to lower the in-situ underground rock mass tracer 10. The in-situ underground rock mass tracer 10 is placed in the designated position of the borehole to be tested according to the test requirements. The position of the tracer section is ensured to meet the test requirements by deploying the acquisition and positioning device 33. The pipeline 8 connecting the in-situ underground rock mass tracer 10 is fixed at the borehole opening to ensure that the in-situ underground rock mass tracer 10 does not float up or down or fall off.
[0053] Step 4, sealing the borehole. Open the sealing pump 66 and related valves 9, injecting sealing fluid or water at the required test pressure into the sealed chamber formed by the flexible high-pressure expansion membrane 21 and the multi-channel main tube 1. This causes the flexible high-pressure expansion membrane 21 to expand and tighten against the borehole wall until the pressure values on the sealing pump 66 and pressure gauge 68 reach the required test sealing value P. fk Close injection valve 9 to stop injection. Throughout the tracer test, continuously observe the pressure reading displayed on pressure gauge 68. If the pressure drop reaches 5% of the test sealing requirement, repeat the above sealing injection steps to maintain the pressure in the sealed chamber at no less than 0.95P. fk To ensure the quality of the sealing, after sealing, let it stand for ten minutes until the water level inside the hole stabilizes before proceeding to the next step.
[0054] Step 5: Initial parameter acquisition. Turn on the various sensors of the data acquisition unit 63 and the monitoring system 5 to observe and acquire the initial values of various parameters in the release phase before the tracer is released.
[0055] Step 6: Tracer injection. Open injection pump 61 and related valve 9 to inject tracer at the preset test pressure or flow rate into the tracer injection and collection section. Once the volume of injected tracer, total solute, or injection time reaches the preset test values, close injection pump 61 and valve 9. Next, switch the tracer storage tank 62 containing the tracer to a water tank filled with distilled water or in-situ groundwater. Use injection pump 61 to inject distilled water or in-situ groundwater at the same pressure or flow rate into the tracer injection and collection section until the injection volume or time reaches the preset test values. Then, close injection pump 61 and valve 9 to stop the injection. Throughout this stage, data acquisition device 63 and monitoring system 5 are used to observe and statistically analyze relevant parameter information in real time.
[0056] Step 7: Liquid Collection. Open the extraction pump 64 and related valve 9, controlling the negative pressure or flow rate of the extraction pump 64 to reach the preset test value. Collect liquid from the tracer delivery collection section (i.e., the corresponding borehole sealing section) until the collection time or the volume of collected liquid reaches the preset test value. Then, close the extraction pump 64 and valve 9 to stop collection. Throughout this stage, the data acquisition device 63 and monitoring system 5 are used to observe and statistically analyze relevant parameter information in real time.
[0057] Step 8: End of Experiment. Upon completion of the experiment, shut off all devices and valves 9, remove the in-situ tracer 10 from the underground rock mass, clean the devices, pipelines 8 and valves 9, tidy up any remaining tracer and sealing fluid, preserve the collected borehole fluid, and promptly process and analyze the observed experimental data.
[0058] The borehole tracing method is suitable for experimental scenarios involving tracer transport testing between two boreholes, where one borehole serves as the tracer delivery borehole and the other as the tracer collection borehole. The detailed steps are as follows:
[0059] Prepare two sets of in-situ underground rock mass tracers 10, including a tracer deployment hole tracer (tracer A) and a tracer acquisition hole tracer (tracer B), as well as a borehole control system 6. Both sets of in-situ underground rock mass tracers 10 are assembled according to the assembly requirements in the above-mentioned single-hole tracer method.
[0060] Assemble the orifice control system 6 according to the test requirements. Specifically: the injection pump 61, tracer storage tank 62, and tracer channel connection port 711 of tracer A are tightly connected via pipeline 8 and valve 9; the sealing pump 66, sealing liquid tank 67, and pressure gauge 68 are tightly connected to the sealing channel connection ports 712 of tracers A and B via pipeline 8 and valve 9; the extraction pump 64 and collection tank 65 are tightly connected to the water extraction channel connection port 714 of tracer B via pipeline 8 and valve 9; and the data acquisition units 63 of tracers A and B are tightly connected to their respective data channel connection ports 713 via pipeline 8. Prepare the required tracer and fill it into the tracer storage tank 62. Fill the sealing liquid tank 67 with a sufficient amount of sealing liquid or water. Adjust all valves 9 and control data to the required test levels.
[0061] Place tracer A and tracer B into the designated positions of the tracer deployment borehole and tracer acquisition borehole respectively according to the test requirements. Use their respective deployment and acquisition positioning devices 33 to ensure that the positions of the tracer deployment and acquisition sections of tracer A and tracer B meet the test requirements. Fix the pipeline 8 connecting tracer A and tracer B at the borehole opening to ensure that the two tracers do not float up or down or fall off.
[0062] Open the sealing pump 66 and related valve 9 to inject sealing fluid or water at the required test pressure into the sealing chambers of tracer A and tracer B, respectively. This causes the flexible high-pressure expansion membrane 21 to expand and tighten the borehole wall until the pressure value on the pressure gauge 68 reaches the required test sealing value P. fk Close injection valve 9 to stop injection. Throughout the tracer test, continuously observe the pressure reading displayed on pressure gauge 68. If the pressure drop reaches 5% of the test sealing requirement, repeat the sealing and injection steps to maintain the pressure in the sealed chamber at no less than 0.95P. fk To ensure the quality of the sealing, after sealing, let it stand for ten minutes until the water level inside the hole stabilizes before proceeding to the next step.
[0063] Turn on the data acquisition unit 63 of tracer A and tracer B and the various sensors of monitoring system 5 to observe and obtain the initial values of various parameters in the release and acquisition stages before the tracer is released.
[0064] For tracer A, open injection pump 61 and related valve 9 to inject tracer at a preset test pressure or flow rate into the tracer delivery and collection section of tracer A. After the volume of injected tracer, total solute, or injection time reaches the preset test values, close injection pump 61 and valve 9. Then, switch the tracer storage tank 62 containing the tracer to a water tank filled with distilled water or in-situ groundwater. Use injection pump 61 to inject distilled water or in-situ groundwater at the same pressure or flow rate into the tracer delivery and collection section of tracer A until the injection volume or time reaches the preset test values. Then, close injection pump 61 and valve 9 to stop the injection.
[0065] Meanwhile, for tracer B, the extraction pump 64 and related valve 9 are opened, and the negative pressure or flow rate of the extraction pump 64 is controlled to reach the test preset value. Liquid is collected from the tracer release and collection section of tracer B until distilled water or in-situ groundwater is no longer injected into the tracer release and collection section of tracer A. Then, the extraction pump 64 and valve 9 are closed, and tracer B stops collecting.
[0066] Throughout the entire phase, data acquisition device 63 and monitoring system 5 are used to observe and statistically analyze the relevant parameter information of tracer A and tracer B in real time. The actual amount of tracer injected should fully consider the residual amount of tracer in pipeline 8 and in-situ tracer 10 in underground rock mass before and after the test.
[0067] After the experiment is completed, all devices and valves 9 are shut off, all in-situ tracers 10 in the underground rock mass are removed, the devices, pipelines 8 and valves 9 are cleaned, the remaining tracer and sealing fluid are cleaned up, the collected fluid in the borehole is preserved, and the experimental data obtained from the observation are processed and analyzed in a timely manner.
[0068] The multi-hole tracing method is suitable for experimental scenarios involving large-scale tracer transport testing across multiple boreholes. The detailed steps are as follows:
[0069] Prepare multiple sets of in-situ underground rock mass tracers 10, including at least one set of tracer deployment hole tracer and at least one set of tracer acquisition hole tracer, as well as multiple sets of wellhead control systems 6. The number of wellhead control systems 6 shall not be less than the larger number of the tracer deployment hole tracer and the tracer acquisition hole tracer. All underground rock mass in-situ tracers 10 shall be assembled according to the assembly requirements in the above-mentioned single-hole tracer method.
[0070] All orifice control systems 6 were assembled according to the test requirements. Specifically: the injection pump 61, tracer storage tank 62, and tracer channel connection holes 711 of each tracer release hole tracer were tightly connected via pipelines 8 and valves 9; the sealing pump 66, sealing liquid tank 67, and pressure gauge 68 were tightly connected via pipelines 8 and valves 9 to the sealing channel connection holes 712 of each tracer release hole tracer and each tracer acquisition hole tracer; the extraction pump 64 and acquisition tank 65 were tightly connected via pipelines 8 and valves 9 to the pumping channel connection ports 714 of each tracer acquisition hole tracer. Each set of tracer acquisition hole tracers was individually connected to an extraction pump 64 and acquisition tank 65. The tracer acquisition hole tracers of different holes did not share the same extraction pump 64 and acquisition tank 65; the data acquisition units 63 of all underground rock mass in-situ tracers 10 were tightly connected via pipelines 8 to their respective data channel connection ports 713. Prepare the required tracer for the test and put it into each tracer storage tank 62. Put a sufficient amount of sealing liquid or water into each sealing liquid tank 67. Adjust each valve 9 and control data to the required test level.
[0071] All underground rock mass in-situ tracers 10 were placed in the designated positions of the tracer deployment borehole and the tracer acquisition borehole according to the test requirements. The respective deployment and acquisition positioning devices 33 were used to ensure that the positions of the tracer deployment and acquisition sections of all tracers met the test requirements. The pipelines 8 that were fixedly connected to all underground rock mass in-situ tracers 10 at the borehole opening were used to ensure that all tracers did not float up or down or fall off.
[0072] Open all sealing pumps 66 and related valves 9, and inject sealing fluid or water at the required test pressure into the sealed chambers of all underground rock mass in-situ tracers 10, causing the flexible high-pressure expansion membrane 21 to expand and tighten the borehole wall until the pressure value on the pressure gauge 68 reaches the required test sealing value P. fk Close injection valve 9 to stop injection. Throughout the tracer test, continuously observe the pressure readings displayed on each pressure gauge 68. If the pressure drop reaches 5% of the test sealing requirement, repeat the sealing and injection process to maintain the pressure in the sealed chamber at no less than 0.95P. fk Ensure the sealing quality of all drilled holes. After sealing, let it stand for ten minutes to allow the water level in the hole to stabilize before proceeding to the next step.
[0073] Turn on the data acquisition unit 63 of all underground rock mass in-situ tracers 10 and the various sensors of the monitoring system 5 to observe and obtain the initial values of various parameters of all boreholes in the tracer delivery acquisition section before the tracer is delivered.
[0074] For each tracer at the tracer delivery well, open the injection pump 61 and the relevant valve 9 to inject tracer at the preset test pressure or flow rate into the tracer delivery and collection section of each tracer. After the volume of the injected tracer, the total amount of solute, or the injection time reaches the preset test values, close the injection pump 61 and valve 9. Then, switch the tracer storage tank 62 containing the tracer to a water tank filled with distilled water or in-situ groundwater. Use the injection pump 61 to inject distilled water or in-situ groundwater at the same pressure or flow rate into the tracer delivery and collection section of each tracer at the tracer delivery well until the injection volume or time reaches the preset test values. Then, close the injection pump 61 and valve 9 to stop the injection.
[0075] Simultaneously, for each tracer at the tracer collection well, the extraction pump 64 and related valve 9 are opened, and the negative pressure or flow rate of each extraction pump 64 is controlled to reach the preset test value. Liquid is collected from the tracer release and collection section of each tracer collection well until distilled water or in-situ groundwater is no longer injected into the tracer release and collection section of all tracer release wells. Then, the extraction pump 64 and valve 9 are closed, and all tracer collection wells stop collecting.
[0076] Throughout the entire phase, data acquisition device 63 and monitoring system 5 were used to observe and statistically analyze relevant parameter information for all boreholes in real time. The actual amount of tracer injected into all boreholes should fully consider the residual amount of tracer in pipeline 8 and in-situ tracer 10 in underground rock mass before and after the test.
[0077] After the experiment is completed, all devices and valves 9 are shut off, all in-situ tracers 10 in the underground rock mass are removed, the devices, pipelines 8 and valves 9 are cleaned, the remaining tracer and sealing fluid are cleaned up, the collected fluid in the borehole is preserved, and the experimental data obtained from the observation are processed and analyzed in a timely manner.
[0078] This patent can also achieve multi-segment tracing within the borehole. Specifically, it is implemented by adding several more sealing devices (i.e., long-term pressure-holding flexible sealing system 2) to the two sealing devices. After the flexible high-pressure expansion membrane 21 of the long-term pressure-holding flexible sealing system 2 expands, it can divide the borehole into several independent sealing segments, thereby achieving multi-segment tracing within the borehole. It can also achieve the functions of deploying one segment while extracting other segments, or deploying multiple segments simultaneously or in sequence. This can solve the problem of difficulty in measuring the seepage and mass transfer characteristics of the fractured rock mass around the borehole along the borehole axis.
[0079] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them; although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications can still be made to the specific implementation of the present invention or equivalent substitutions can be made to some technical features without departing from the spirit of the technical solutions of the present invention, and all such modifications and substitutions should be covered within the scope of the technical solutions claimed in the present invention.
Claims
1. An integrated device for in-situ tracer sealing borehole injection testing of an underground rock mass, characterized in that, The system includes an in-situ underground rock mass tracer (10) and a borehole control system (6). The in-situ underground rock mass tracer (10) and the borehole control system (6) are connected by pipelines (8) and valves (9). The in-situ underground rock mass tracer (10) includes two sets of axially connected multi-channel main pipes (1), a long-term pressure-maintaining flexible sealing system (2) sleeved on the outer wall of the multi-channel main pipes (1), a tracer delivery system (3) for connecting the two multi-channel main pipes (1) in series and for feedback on the delivery position, a pumping and acquisition system (4) installed on the tracer delivery system (3), a monitoring system (5) installed on the tracer delivery system (3), and a connection system (7). The main tube (1) is a hollow cylinder, and multiple channels are arranged parallel to the axis along the inner wall of the multi-channel main tube (1). The multiple channels include a tracer delivery channel (11) for delivering tracer, a sealing liquid injection channel (12) for delivering sealing liquid, a data transmission channel (13) for transmitting data, and a pumping collection channel (14) for delivering collected liquid samples. The monitoring system (5) is set on the outer wall of the tracer delivery system (3) and is used to collect monitoring information. The connection system (7) is set at the end of the multi-channel main tube (1) to connect the pipelines of each channel of the multi-channel main tube (1) with the orifice control system (6).
2. The device according to claim 1, wherein, The long-term pressure-holding flexible sealing system (2) includes at least one layer of flexible high-pressure expansion membrane (21), sealing liquid outlet (22), and sealing ring (23). The flexible high-pressure expansion membrane (21) forms a sealed chamber with the outer wall of the multi-channel main tube (1). The sealed chamber is connected to the sealing liquid injection channel (12) through the sealing liquid outlet (22) set on the wall of the multi-channel main tube (1). The sealing ring (23) is set at both ends of the flexible high-pressure expansion membrane (21). The inner wall surface of the sealing ring (23) is sealed to the outer wall surface of the multi-channel main tube (1) to seal the sealed chamber. Sealing liquid is injected into the sealed chamber through the sealing liquid injection channel (12) and the sealing liquid outlet (22) to make the flexible high-pressure expansion membrane (21) on the two multi-channel main tubes (1) expand outward and tighten the inner wall of the borehole to achieve sealing isolation of the target section of the borehole and form a borehole sealing section.
3. The device, as claimed in claim 1, wherein, The tracer delivery system (3) includes a tracer delivery and acquisition section connector (31), a tracer delivery and acquisition section main tube (32), a delivery and acquisition positioning device (33), and a delivery port (34). The tracer delivery and acquisition section main tube (32) is connected to the multi-channel main tube (1) through the tracer delivery and acquisition section connector (31). The tracer delivery and acquisition section main tube (32) is provided with multiple channels corresponding to the multi-channel main tube (1). The delivery port (34) is located on the side wall of the tracer delivery and acquisition section main tube (32) and communicates with the tracer delivery channel (11) so that the tracer is output from the delivery port (34) to the borehole to be tested. The delivery and acquisition positioning device (33) is located on the tracer delivery and acquisition section main tube (32).
4. The device according to claim 3, wherein, The deployment acquisition and positioning device (33) is at least one of a depth gauge, altimeter, acoustic locator or camera, and the deployment acquisition and positioning device (33) is connected to the orifice control system (6) through the data transmission channel (13).
5. The device of claim 1, wherein, The water collection system (4) includes a collection hole (41), which is located on the side wall of the tracer delivery system (3) and communicates with the water collection channel (14) to collect liquid samples in the borehole sealing section; the monitoring system (5) is located on the outer wall of the tracer delivery system (3) and communicates with the data transmission channel (13), and the monitoring system (5) includes at least one of a temperature sensor, a pressure sensor, an ion concentration sensor and a fluorescence concentration sensor.
6. The device of claim 1, wherein: The connection system (7) includes a first-section connector (71) and an end connector (72); the first-section connector (71) is provided with a tracer channel connection hole (711), a sealing channel connection hole (712), a data channel connection port (713), a water pumping channel connection port (714), a fixed connection port (715), and a hanging ring (716). The tracer channel connection hole (711), the sealing channel connection hole (712), the data channel connection port (713), and the water pumping channel connection port (714) are respectively connected to the upper ends of the tracer delivery channel (11), the sealing injection channel (12), the data transmission channel (13), and the water pumping collection channel (14). The hanging ring (716) is connected to the fixed connection port (715). The end connector (72) is located at the lower end of the multi-channel main tube (1) to seal the ends of each channel.
7. The device of claim 1, wherein: The orifice control system (6) includes an injection pump (61), a tracer storage tank (62), a data acquisition device (63), an extraction pump (64), a collection tank (65), a sealing pump (66), a sealing liquid tank (67), and a pressure gauge (68). The injection pump (61) and the tracer storage tank (62) are connected to the tracer delivery channel (11) through the pipeline (8) and the valve (9). The extraction pump (64) and the collection tank (65) are connected to the water pumping and collection channel (14) through the pipeline (8) and the valve (9). The sealing pump (66), the sealing liquid tank (67), and the pressure gauge (68) are connected to the sealing injection channel (12) through the pipeline (8) and the valve (9). The data acquisition device (63) is connected to the data transmission channel (13) through the pipeline (8).
8. A method of using an in-situ tracer borehole sealing and injection testing integrated device according to any one of claims 1 to 7, characterized in that, This includes single-hole tracing methods, pair-hole tracing methods, and group-hole tracing methods. The single-hole tracing method includes the following steps: S1. Assemble the underground rock mass in-situ tracer (10) and the borehole control system (6), prepare the tracer and put it into the tracer storage tank (62), and put the sealing liquid or water into the sealing liquid tank (67). S2. Place the underground rock mass in-situ tracer (10) at the designated location of the borehole to be tested, confirm the location of the tracer section by deploying the acquisition and positioning device (33), and fix the pipeline (8) at the borehole opening. S3, open the sealing pump (66) and the related valve (9), inject sealing liquid or water into the sealed chamber formed by the flexible high-pressure expansion membrane (21) and the multi-channel main body pipe (1) until the pressure reaches the test sealing required value P fk , close the valve (9) to stop injecting liquid; during the test, continuously observe the pressure gauge (68), if the pressure drop amplitude reaches 5% of P fk , repeat the injection to maintain the pressure in the sealed chamber not less than 0.95P fk ; after the sealing is completed, stand still until the water level in the hole is stable; S4. Turn on the sensors of the data acquisition unit (63) and the monitoring system (5) to obtain the initial parameter values before the tracer is released; S5. Open the injection pump (61) and related valves (9) to inject tracer into the tracer delivery system (3) at a preset pressure or flow rate. After reaching the preset injection amount, close the injection pump (61) and valves (9). Switch to a water storage tank filled with distilled water or in-situ groundwater and inject distilled water or in-situ groundwater at the same pressure or flow rate. After reaching the preset injection amount, close the injection pump (61) and valves (9). S6. Open the extraction pump (64) and related valves (9), control the negative pressure or flow rate of the extraction pump (64) to reach the preset value, collect liquid from the tracer delivery system (3), and close the extraction pump (64) and valves (9) after the preset collection time or collection volume is reached. S7. After the test is completed, close all devices and valves (9), remove the underground rock mass in-situ tracer (10), clean the device and organize the test data.
9. The method of use of claim 8, wherein, It also includes a borehole tracing method, which includes the following steps: preparing two sets of underground rock mass in-situ tracers (10), which are respectively used as tracer placement borehole tracers and tracer collection borehole tracers, and a borehole control system (6); placing the two sets of underground rock mass in-situ tracers (10) into the designated positions of the tracer placement borehole and the tracer collection borehole and completing the sealing; performing tracer injection and distilled water or in-situ groundwater displacement operation on the tracer placement borehole tracer, and performing liquid collection operation on the tracer collection borehole tracer until the tracer placement borehole tracer stops injecting, and the tracer collection borehole tracer stops collecting.
10. The method of use of claim 8, wherein, It also includes a multi-hole tracing method, which includes the following steps: preparing multiple sets of underground rock mass in-situ tracers (10), including at least one set of tracer delivery hole tracers and at least one set of tracer collection hole tracers, as well as multiple sets of borehole control systems (6), the number of borehole control systems (6) being no less than the larger number of tracer delivery hole tracers and tracer collection hole tracers; placing all underground rock mass in-situ tracers (10) into the designated positions of the corresponding boreholes and completing the sealing of the boreholes; simultaneously performing tracer injection and distilled water or in-situ groundwater displacement operations on all tracer delivery hole tracers, and simultaneously performing liquid collection operations on all tracer collection hole tracers, with each set of tracer collection hole tracers connected to a separate extraction pump (64) and collection tank (65), until all tracer delivery hole tracers stop injection, and all tracer collection hole tracers stop collection.