A construction method for long tunnels densely traversing fault fracture zones
By employing multi-level advanced geological forecasting, graded advanced pre-reinforcement, dynamic zoned drainage-grouting coordinated construction, and information-based control, the problems of insufficient forecasting accuracy, unbalanced reinforcement, inefficient drainage and grouting, uncontrolled deformation, and delayed progress in the construction of long tunnels densely crossing fault fracture zones have been solved. This has enabled high-precision forecasting, targeted reinforcement, coordinated and efficient drainage, and real-time deformation control, thereby improving construction safety and efficiency.
Patent Information
- Application Number
- CN202611382059.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-08
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies for constructing long tunnels that crisscross fault fracture zones suffer from problems such as insufficient accuracy in geological forecasting, limited reinforcement measures, imprecise coordination and control of drainage and grouting, and lack of information-based dynamic control during construction, leading to high construction risks and delays.
The method employs multi-level advanced geological forecasting and fault fracture zone classification, graded advanced pre-reinforcement, dynamic zoned drainage-grouting coordinated construction, step-by-step excavation and initial support, radial supplementary reinforcement and information-based dynamic control. Through multi-level forecasting, blind spots are reduced; graded reinforcement optimizes the economic and safety balance; zoned drainage and grouting improves efficiency; and information-based control enhances deformation control.
It has achieved high prediction accuracy, targeted reinforcement measures, efficient coordination of drainage and grouting, real-time control of deformation, and fast construction progress for long tunnels that densely cross fault fracture zones, significantly reducing construction risks and improving safety and efficiency.
Smart Images

Figure CN123109674A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel engineering construction technology, specifically to a construction method for long tunnels that densely traverse fault fracture zones. Background Technology
[0002] As transportation infrastructure construction continues to advance into the geologically complex mountainous areas of western China, the number of long tunnel projects has increased significantly. During tunnel construction, fault fracture zones, as typical unfavorable geological formations, are formed by the relative movement and compression of the two sides of a fault. These zones contain severely fractured rock masses with highly developed joints and fissures, extremely poor self-stabilizing capacity, and are often closely connected to groundwater systems. They exhibit strong characteristics of sudden onset, high stress, and high water pressure, making them highly susceptible to major engineering disasters such as water inrush, mudslides, and surrounding rock collapses. Especially for long tunnel projects, due to the long distances and varied geological environments, multiple fault fracture zones are often traversed consecutively, forming densely distributed and complex geological sections. Such densely packed crossing scenarios present multiple overlapping challenges: On the one hand, each fault fracture zone requires independent implementation of advanced geological forecasting, pre-reinforcement, and special excavation and support procedures, leading to frequent changes in the construction process and a significant increase in organizational coordination difficulties; on the other hand, the length of the intact rock mass segment between adjacent fault fracture zones is usually short, and the stress redistribution of the surrounding rock caused by the construction of the previous fracture zone has not yet fully stabilized before the tunnel enters the construction area of the next fracture zone, causing the cumulative effect of surrounding rock deformation to continue to amplify, significantly increasing the overall construction risk. In existing technologies, some construction methods focus on the treatment of a single fault fracture zone, such as using a ring-shaped layout of drainage holes and grouting holes to achieve drainage before grouting. Although this can alleviate the problem of single-point water abundance, it does not consider the dense spatial distribution characteristics of multiple fault fracture zones and lacks a systematic response strategy for continuous crossing of multiple faults. Another method proposes the concept of "upper blocking and lower drainage" for cross-sectional zoning, which is applicable to specific water-rich fault scenarios, but its reinforcement methods are relatively fixed and cannot implement differentiated treatment according to the degree of rock mass fracture and the state of groundwater enrichment, and it does not solve the dynamic coordination problem of construction connection between dense faults. Some technologies attempt to incorporate geological cloud maps to aid decision-making; however, advanced geological forecasting methods have limited coverage, insufficient accuracy in identifying the spatial distribution and properties of faults, and crude grading mechanisms, making it difficult to support refined reinforcement parameter design. Simultaneously, the coordinated control of drainage and grouting at the tunnel face lacks scientific zoning basis, and the grout diffusion path guidance effect is poor, leading to unstable reinforcement quality. Furthermore, the acquisition and analysis of monitoring data during construction are fragmented, failing to establish a real-time linkage feedback mechanism between surrounding rock deformation, seepage status, and construction parameters. During continuous crossing of dense faults, it is impossible to dynamically optimize subsequent procedures based on changes in actual geological conditions. These shortcomings result in existing technologies generally exhibiting problems such as large forecast blind spots, an imbalance between reinforcement economy and safety, low drainage and grouting efficiency, insufficient deformation control capabilities, and hindered construction progress when dealing with long tunnels with dense fault fracture zones, severely restricting project safety and efficiency. Summary of the Invention
[0003] The purpose of this application is to provide a construction method for long tunnels that densely cross fault fracture zones, which has the advantages of high prediction accuracy, targeted reinforcement measures, efficient coordination of drainage and grouting, real-time control of deformation, and fast construction progress.
[0004] This application provides a construction method for long tunnels densely traversing fault fracture zones, the technical solution of which includes the following steps: S1: Multi-level advanced geological prediction and fault fracture zone classification: A multi-level advanced geological prediction system consisting of TSP seismic wave prediction, ground-penetrating radar detection, infrared water detection and horizontal geological drilling is adopted to sequentially determine the spatial distribution, rock mass fracture degree and groundwater enrichment of multiple fault fracture zones in front of the tunnel. Based on the rock mass integrity index and single-hole water inflow, each fault fracture zone is divided into three levels: light fracture zone, moderate fracture zone and heavy fracture zone. At the same time, a geological cloud map containing the classification information of each fault fracture zone is generated. S2: Graded Advanced Pre-reinforcement: Based on the graded results of the fault fracture zone obtained in step S1, corresponding advanced pre-reinforcement schemes are adopted for different grades of fault fracture zones to form an advanced reinforcement ring matching the fracture grade outside the tunnel excavation outline; among them, advanced small pipe grouting reinforcement is adopted for lightly fractured zones, advanced pipe roof and small pipe combined grouting reinforcement is adopted for moderately fractured zones, and advanced curtain grouting reinforcement is adopted for severely fractured zones. S3: Dynamic Zonal Drainage-Grouting Coordinated Construction: Based on the geological cloud map obtained in step S1, the water-rich distribution on the working face is identified, and the borehole area on the working face is divided into three hydrological zones: weak water zone, transition zone, and strong water zone. Drainage holes and grouting holes of different densities and depths are laid out respectively, forming a double-layer borehole structure of drainage hole layer and grouting hole layer. During grouting, a combination of zonal progressive grouting and diagonal drainage guidance is adopted. First, the weak water zone is grouted and sealed, and then the process is advanced to the transition zone and strong water zone. At the same time, the grout is guided to diffuse through the drainage holes at diagonal positions. After grouting is completed, the drainage holes are opened for active drainage and pressure relief. S4: Step-by-step excavation and initial support: The three-stage temporary inverted arch method is used to excavate through the fault fracture zone in steps. The excavation length of the upper, middle and lower steps increases sequentially, and the longitudinal offset between the excavation surfaces of each step is not less than twice the tunnel diameter. During the excavation process, the cyclic advance is controlled according to the fault fracture zone grade. After the excavation, steel arch frames are erected in time, steel mesh is hung and shotcrete is sprayed to form the initial support structure. At the same time, anchor pipes are installed at the arch foot. S5: Radial supplementary reinforcement and information-based dynamic control: After the initial support is closed into a ring, radial supplementary grouting reinforcement is carried out behind the initial support based on the surrounding rock deformation monitoring data and water leakage situation; throughout the construction process, data is collected in real time through the deployed surrounding rock pressure sensors, displacement monitoring points and seepage flow monitoring devices, and analyzed and fed back using the information-based construction management system, and the reinforcement parameters and excavation parameters of the subsequent fault fracture zone are dynamically adjusted based on the feedback results; S6: Cyclic advancement through densely fractured zones: Repeat steps S1 to S5, sequentially forecasting, reinforcing, excavating, and supporting each subsequent fault fractured zone. The intact rock mass section between two adjacent fault fractured zones is quickly passed through using conventional construction methods until the construction of all densely fractured fault zone sections is completed.
[0005] Furthermore, this application also proposes that the implementation method of the multi-level advanced geological prediction system in step S1 is as follows: First, the TSP seismic wave predictor was used for long-distance prediction, with a prediction distance of 100m to 150m, to preliminarily delineate the approximate range of the fault fracture zone; Subsequently, ground-penetrating radar was used for medium-range fine exploration at a distance of 20m to 30m to further determine the boundary and internal structure of the fault fracture zone. Then, an infrared water detector is used to detect groundwater and determine the water abundance of the fault fracture zone; Finally, a horizontal geological drilling rig was used for advanced drilling verification. The drilling depth was 30m to 50m, and the overlap length of each cycle was not less than 5m. The actual parameters of the fault fracture zone were confirmed by core observation and water inflow monitoring.
[0006] Furthermore, this application also proposes that, in step S1, the classification standard for fault fracture zones is as follows: The rock mass integrity index Kv of the slightly fractured zone is ≥0.55, and the single-hole water inflow rate Q is ≤10m³ / h; The rock mass integrity index Kv of the moderately fractured zone is 0.35 to 0.55, and the single-hole water yield Q is 10 m³ / h to 30 m³ / h. The rock mass integrity index Kv of the severely fractured zone is <0.35, and the single-hole water inflow Q is >30 m³ / h.
[0007] Furthermore, this application also proposes that in step S2: The length of the pre-grouting reinforcement tubes is 3m to 5m, the diameter is Φ42mm to Φ50mm, the circumferential spacing is 30cm to 40cm, the external insertion angle is 10° to 15°, and the grouting pressure is 0.5MPa to 1.0MPa. The pipe roofs reinforced by grouting with combined advanced pipe roofs and small pipes have a length of 10m to 20m, a diameter of Φ89mm to Φ108mm, a circumferential spacing of 40cm to 50cm, and an external insertion angle of 1° to 3°. Advanced small pipes are used to supplement the reinforcement between the pipe roofs. The grouting reinforcement range of the advanced curtain grouting reinforcement is 5m to 8m outside the tunnel excavation outline, the grouting section length is 20m to 30m, the grouting pressure is 1.5 to 2.5 times the hydrostatic pressure, and the grouting holes are arranged in a ring and are constructed sequentially from the outer ring to the inner ring and from top to bottom.
[0008] Furthermore, this application also proposes that in step S3: The number of grouting holes in the weak water zone accounts for 20% to 30% of the total number of grouting holes, and the number of drainage holes accounts for 10% to 20% of the total number of drainage holes. The number of grouting holes in the transition zone accounts for 30% to 40% of the total number of grouting holes, and the number of drainage holes accounts for 30% to 40% of the total number of drainage holes. In areas with strong water flow, the number of grouting holes accounts for 30% to 50% of the total number of grouting holes, and the number of drainage holes accounts for 40% to 60% of the total number of drainage holes. The drainage hole layer is located outside the grouting hole layer, and the radial distance between the two layers is 1.5m to 2.5m. Drainage pipes with valves are installed inside the drainage holes.
[0009] Furthermore, this application also proposes that, in step S3, the specific implementation method of zoned progressive grouting and diagonal drainage guidance is as follows: First, grouting is carried out in the weak water area, and the grouting pressure is gradually increased from low to high. At the same time, the drainage holes at the diagonal positions of the strong water area are opened to release pressure and drain water, guiding the grout to diffuse towards the strong water area. After the grouting in the weak water zone is completed and the grout has initially set, the transition zone is grouted, and at the same time the drainage holes at the diagonal positions of the transition zone are opened. Finally, grouting is carried out in the high water area. Cement-water glass double-liquid grout is used for grouting in the high water area. During the grouting process, the diagonal drainage holes are kept drained continuously until grout comes out of the drainage holes and the grouting pressure reaches the design value. Then the drainage holes are closed to complete the grouting.
[0010] Furthermore, this application also proposes that in step S4: The excavation length of the upper step in the three-step temporary inverted arch method is 3m to 5m, the excavation length of the middle step is 5m to 8m, and the excavation length of the lower step is 8m to 15m. The cyclic advance is controlled according to the fault fracture zone grade: 1.0m to 1.5m for lightly fractured zones, 0.6m to 1.0m for moderately fractured zones, and 0.4m to 0.6m for heavily fractured zones; In the initial support structure, the spacing of the steel arch frames is determined according to the fault fracture zone grade: 80cm to 100cm for lightly fractured zones, 60cm to 80cm for moderately fractured zones, and 40cm to 60cm for heavily fractured zones; the thickness of the shotcrete is 20cm to 30cm, and the strength grade is not lower than C25.
[0011] Furthermore, this application also proposes that the implementation method of radial supplementary grouting reinforcement in step S5 is as follows: The radial grouting holes are arranged in a quincunx pattern, with a hole spacing of 1.0m to 1.5m and a hole depth of 3m to 5m. The grouting pipe is a Φ42mm steel perforated pipe. The grouting pressure is 0.5MPa to 1.5MPa, and the grouting material is cement grout or cement-water glass two-component grout. When the leakage flow rate is greater than 5L / min·m, first set up grouting holes around the leakage point for surrounding grouting, and then directly grout the leakage point to seal it.
[0012] Furthermore, this application also proposes that, in step S5, the dynamic control method of the information-based construction management system is as follows: Displacement monitoring points were set up at the tunnel arch, left and right sidewalls and invert arch. The monitoring frequency was twice a day for the first 7 days after excavation, once a day after 7 days, and once every 2 days after 15 days. When the rate of settlement of the arch is greater than 5 mm / d or the rate of convergence of the perimeter is greater than 3 mm / d, it is determined that the surrounding rock deformation is abnormal, and the system will automatically issue an early warning and prompt the adjustment of construction parameters. Adjustment measures include: reducing the excavation advance in the next cycle, increasing the density of the steel arch frame, increasing the grouting volume, or implementing secondary lining in advance.
[0013] Furthermore, this application also proposes that in step S6, when the length of the intact rock mass section between two adjacent fault fracture zones is less than 20m, the two fault fracture zones are merged into one construction section for unified reinforcement and excavation; when the length of the intact rock mass section is greater than 20m, the two fault fracture zones are constructed independently, and the middle intact rock mass section is quickly passed through using the full-face excavation method, and the excavation cycle advance of the intact rock mass section is 2m to 3m.
[0014] Compared with the prior art, the gain effect of the present invention is as follows: This application provides a construction method for long tunnels densely traversing fault fracture zones, comprising the following steps: multi-level advanced geological forecasting and fault fracture zone classification, graded advanced pre-reinforcement, dynamic zoned drainage-grouting coordinated construction, step-by-step excavation and initial support, radial supplementary reinforcement and information-based dynamic control, and cyclical advancement through densely fractured zones. By systematically implementing measures such as multi-level forecasting to reduce blind spots, graded reinforcement to optimize economic and safety balance, zoned drainage and grouting to improve efficiency, and information-based control to enhance deformation control, this method effectively solves the problems of insufficient forecast accuracy, reinforcement imbalance, inefficient drainage and grouting, deformation out-of-control, and slow progress in the construction of densely fractured fault zones. It has the advantages of high forecast accuracy, strong targeted reinforcement measures, efficient drainage and grouting coordination, real-time controllable deformation, and fast construction progress. Attached Figure Description
[0015] Figure 1 This is a flowchart of the construction method of the present invention. Detailed Implementation
[0016] The technical solution of the present invention will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0017] Traditional long tunnel construction methods, when traversing densely faulted and fractured zones, generally suffer from problems such as insufficient accuracy in geological forecasting, limited advanced reinforcement solutions, imprecise coordination and control of drainage and grouting, lack of dynamic information-based control during construction, and suboptimal organization of continuous construction across multiple fractured zones. These shortcomings significantly increase construction risks, making it prone to engineering geological disasters such as water inrush, mudslides, and collapses, severely impacting construction safety, progress, and economic benefits.
[0018] As attached Figure 1 As shown: This application proposes a construction method for long tunnels densely traversing fault fracture zones. This method aims to effectively address the complex working conditions of long tunnels densely traversing fault fracture zones by constructing a comprehensive, multi-layered construction system to achieve closed-loop control from geological perception to construction feedback. The method includes the following steps: like Figure 1As shown: First, multi-level advanced geological prediction and fault fracture zone classification are conducted. This step employs a multi-level advanced geological prediction system consisting of TSP seismic wave prediction, ground-penetrating radar detection, infrared water detection, and horizontal geological drilling to sequentially determine the spatial distribution, rock mass fracture degree, and groundwater enrichment of multiple fault fracture zones ahead of the tunnel. Subsequently, based on rock mass integrity indicators and single-hole water inflow, each fault fracture zone is classified into three levels: slightly fractured, moderately fractured, and severely fractured, while simultaneously generating a geological cloud map containing the classification information of each fault fracture zone.
[0019] Then, graded pre-reinforcement is implemented. Based on the fault fracture zone classification results obtained from the preceding steps, corresponding pre-reinforcement schemes are adopted for different grades of fault fracture zones, forming a pre-reinforcement ring matching the fracture grade outside the tunnel excavation outline. Specifically, pre-reinforcement with small-diameter pipe grouting is used for lightly fractured zones, combined pre-reinforcement with pipe roof and small-diameter pipe grouting is used for moderately fractured zones, and pre-reinforcement with curtain grouting is used for severely fractured zones.
[0020] Next, dynamic zoned drainage and grouting coordinated construction was carried out. Based on the geological cloud map obtained in the previous steps, the water-rich distribution on the working face was identified, and the borehole area on the working face was divided into three hydrological zones: a weak water zone, a transition zone, and a strong water zone. Drainage holes and grouting holes of different densities and depths were laid out for each zone, forming a double-layer borehole structure of drainage hole layer and grouting hole layer. During grouting, a combination of zoned progressive grouting and diagonal drainage guidance was adopted. First, the weak water zone was grouted and sealed, and then the grouting was advanced to the transition zone and the strong water zone. At the same time, the grout was guided to diffuse through the drainage holes at diagonal positions. After grouting was completed, the drainage holes were opened for active drainage and pressure relief.
[0021] Subsequently, phased excavation and initial support were carried out. This step employed a three-stage temporary inverted arch method to excavate through the fault fracture zone, with the excavation lengths of the upper, middle, and lower stages increasing sequentially, and a longitudinal offset of no less than twice the tunnel diameter maintained between the excavation faces of each stage. During the excavation process, the cyclic advance was controlled according to the fault fracture zone grade. After excavation, steel arch frames were promptly erected, steel mesh was installed, and shotcrete was applied to form the initial support structure. Simultaneously, anchor pipes were installed at the arch foot.
[0022] Radial reinforcement and dynamic information-based control were implemented. After the initial support was closed into a ring, radial reinforcement grouting was carried out behind the initial support based on the surrounding rock deformation monitoring data and water leakage. Throughout the construction process, data was collected in real time through deployed surrounding rock pressure sensors, displacement monitoring points, and seepage monitoring devices. The data was analyzed and fed back using an information-based construction management system, and the reinforcement and excavation parameters of the subsequent fault fracture zone were dynamically adjusted based on the feedback results.
[0023] Finally, the process involves cyclically advancing through densely fractured fault zones. This step repeats steps S1 to S5, sequentially forecasting, reinforcing, excavating, and supporting each subsequent fault fracture zone. Intact rock sections between adjacent fault fracture zones are traversed quickly using conventional construction methods until all densely fractured fault zone sections are completed.
[0024] The method provided in this embodiment will be described in detail below: When implementing multi-level advanced geological forecasting and fault fracture zone classification, a single ground-penetrating radar (GPR) probe or advanced drilling can be used for forecasting to obtain the approximate location of the fault fracture zone ahead of the tunnel and the degree of rock mass fracture. Subsequently, based on the rock core quality index (RQD) from borehole core samples or visual observation results, the fault fracture zone can be classified into two levels: moderately fractured and severely fractured. Geological information can be recorded in the form of written reports or simple two-dimensional profile diagrams.
[0025] When implementing graded pre-reinforcement, grading can be omitted, and a uniform pre-reinforcement scheme can be used for all fault fracture zones, such as pre-reinforcement with small-diameter grouting. Alternatively, for general fracture zones, prestressed anchor bolts can be used for reinforcement to improve the stability of the surrounding rock. For severely fractured zones, steel pipe piles or reinforcing cages can be used for pre-support to form a stronger support structure.
[0026] When implementing dynamic zoned drainage-grouting coordinated construction, the tunnel face can be divided into water-rich and non-water-rich zones based on geological forecasts. In the water-rich zone, grouting holes and drainage holes can be installed, but these holes can be mixed and arranged without forming a layered structure. During grouting, a one-time full-section grouting method can be used without zoning and progression. Drainage can be carried out before grouting, and diagonal drainage guidance is not used during grouting. After grouting, natural drainage can be relied upon, without active drainage and pressure relief.
[0027] When implementing phased excavation and initial support, a two-stage method can be used to divide the tunnel cross-section into upper and lower stages. The excavation length of each stage can be kept consistent, and the longitudinal misalignment between the excavation faces of the stages is not strictly controlled. During the excavation process, a uniform cyclic advance can be used for all fault fracture zones without differentiated control based on the fracture zone grade. After excavation, only shotcrete or anchor bolts can be used to form the initial support structure, without erecting steel arches or installing anchor pipes.
[0028] When implementing radial reinforcement and dynamic information-based control, after the initial support is closed into a ring, localized supplementary grouting reinforcement can be carried out only when significant deformation or leakage occurs in the surrounding rock, or by increasing the density of anchor bolts or steel mesh. The entire construction process can be monitored through manual inspection and periodic measurements, without the deployment of surrounding rock pressure sensors, displacement monitoring points, or seepage monitoring devices. Adjustments to construction parameters can rely on the experience and judgment of on-site engineers, without data analysis and feedback through an information-based construction management system.
[0029] When implementing cyclical advancement through densely fractured zones, the cyclical advancement method can be abandoned. Instead, all densely fractured zones can be treated as a whole and predicted and reinforced all at once. For intact rock sections between two adjacent fault fractured zones, the construction methods for the fractured zones can be followed, or the construction strategies for intact rock sections and fractured zones can be disregarded, and a uniform excavation and support method can be adopted.
[0030] The method provided in this application achieves accurate perception and classification of fault fracture zones through a multi-level advanced geological prediction system, effectively solving the problem of insufficient prediction accuracy. Differentiated, graded, and advanced pre-reinforcement schemes avoid insufficient or excessive reinforcement. Dynamic zoned drainage-grouting coordinated construction precisely controls the hydrogeological conditions of water-rich fracture zones. Information-based dynamic control and cyclical advancement strategies optimize construction organization and parameter adjustments. Therefore, it significantly reduces the construction risks of long tunnels densely traversing fault fracture zones, and improves construction safety and efficiency.
[0031] In some of the above-mentioned schemes in this application, a multi-level advanced geological forecasting system was proposed to explore the spatial distribution of fault fracture zones and rock mass properties in front of the tunnel. However, in actual engineering applications, single or extensive forecasting methods often cannot take into account both the depth and accuracy of the detection, resulting in fuzzy boundary positioning of fault fracture zones, unclear internal structure and inaccurate judgment of water-bearing conditions, which in turn affects the pertinence of subsequent graded reinforcement schemes and construction safety.
[0032] In response, this application further proposes an implementation method for the multi-level advanced geological prediction system in step S1 above. This implementation method first uses a TSP seismic wave predictor for long-range prediction at a distance of 100m–150m to initially delineate the approximate range of the fault fracture zone; then, ground-penetrating radar is used for medium-range fine detection at a distance of 20m–30m to further determine the boundaries and internal structure of the fault fracture zone; next, an infrared water detector is used to detect groundwater and determine the water abundance of the fault fracture zone; finally, a horizontal geological drilling rig is used for advanced drilling verification, with a drilling depth of 30m–50m and an overlap length of not less than 5m per cycle, confirming the actual parameters of the fault fracture zone through core observation and water inflow monitoring.
[0033] Through the above technical solutions, this application constructs a progressive multi-level forecasting system, progressing from far to near, from surface to point, and from geophysical exploration to drilling. First, the TSP seismic wave predictor performs long-range macroscopic detection, enabling rapid identification of potential fault fracture zones over a large area, providing directional guidance for overall construction deployment. Building upon this, the mid-range fine detection of ground-penetrating radar compensates for the shortcomings of long-range forecasting in local details, accurately depicting the boundaries and internal structure of fracture zones, avoiding problems of blurred boundaries and unclear structures. The introduction of an infrared water detector allows for timely and accurate assessment of groundwater enrichment, providing crucial hydrological data for subsequent drainage and grouting schemes, and solving the problem of inaccurate water-rich assessments. Finally, advanced drilling verification by a horizontal geological drilling rig, using intuitive data such as core observation and water inflow monitoring, verifies the aforementioned geophysical results in the field, ensuring the authenticity and reliability of geological parameters. This multi-level, multi-method collaborative forecasting system effectively solves the limitations of single forecasting methods in terms of both detection depth and accuracy. It significantly improves the accuracy of judging the spatial distribution of fault fracture zones, the degree of rock mass fracture, and the enrichment of groundwater, thereby providing accurate and reliable geological data support for subsequent graded advanced reinforcement, ensuring the relevance of the reinforcement plan and the safety of construction.
[0034] In some of the embodiments described above in this application, a graded treatment of fault fracture zones is proposed to achieve differentiated reinforcement. However, in actual engineering, due to the lack of clear and quantifiable grading standards, construction personnel often find it difficult to accurately judge the degree of fracture and water-rich characteristics of fault fracture zones, resulting in the inability to accurately match the corresponding reinforcement scheme, which in turn leads to improper allocation of construction resources or safety hazards.
[0035] In response, this application further proposes the following classification standards for fault fracture zones: for slightly fractured zones, the rock mass integrity index Kv ≥ 0.55 and the single-hole water inflow Q ≤ 10 m³ / h; for moderately fractured zones, the rock mass integrity index Kv is 0.35~0.55 and the single-hole water inflow Q is 10 m³ / h~30 m³ / h; for severely fractured zones, the rock mass integrity index Kv < 0.35 and the single-hole water inflow Q > 30 m³ / h.
[0036] Through the above technical solution, this application establishes a quantitative classification system based on the rock mass integrity index Kv and the single-hole water inflow Q, effectively solving the problems of ambiguous judgment and inaccurate scheme matching caused by the lack of clear classification standards in traditional construction. Specifically, by coupling the rock mass integrity index Kv with the single-hole water inflow Q, the physical and mechanical properties and hydrogeological characteristics of the fault fracture zone can be comprehensively reflected, thereby achieving accurate definition of the fracture zone level. The thresholds of Kv ≥ 0.55 and Q ≤ 10 m³ / h for the slightly fractured zone clearly define the working conditions where the surrounding rock is relatively stable and the impact of groundwater is minimal, providing a basis for subsequent lightweight reinforcement schemes. The range of Kv between 0.35 and 0.55 and Q between 10 and 30 m³ / h for the moderately fractured zone accurately captures the transitional state where the surrounding rock is moderately fractured and groundwater has a certain risk of outflow, ensuring the targeted nature of the reinforcement scheme. The stringent condition of Kv < 0.35 and Q > 30 m³ / h for the severely fractured zone defines the extreme working conditions where the surrounding rock is extremely fractured and severely water-rich, providing clear triggering conditions for adopting heavy reinforcement measures such as high-intensity curtain grouting. This grading method not only solves the ambiguity of experience-based judgments during construction but also achieves dynamic matching of construction resources and geological risks by directly linking geological parameters with construction schemes. This effectively avoids the safety risks and economic waste caused by blind construction, significantly improving the scientific nature and safety of construction.
[0037] In some of the embodiments described above in this application, a graded pre-reinforcement of fault fracture zones is proposed. However, in actual construction, if there is a lack of specific reinforcement parameter specifications and differentiated construction techniques for surrounding rock with different fracture grades, the reinforcement strength may not match the actual bearing capacity requirements of the surrounding rock, which may lead to the risk of collapse due to insufficient reinforcement or waste of resources and low construction efficiency due to excessive reinforcement.
[0038] In response, this application further proposes a pre-reinforcement scheme with specific parameters for different grades of fault fracture zones in step S2 above. Specifically, for lightly fractured zones, pre-reinforcement with small guide pipe grouting is adopted, wherein the length of the small guide pipe is set to 3m to 5m, its diameter is Φ42mm to Φ50mm, the circumferential spacing is 30cm to 40cm, the external insertion angle is 10° to 15°, and the grouting pressure is controlled at 0.5MPa to 1.0MPa. The length of the small guide pipe determines the longitudinal range of grout diffusion in the surrounding rock and the reinforcement depth. In addition to the length range of 3m to 5m, 2m to 3m can be selected for local shallow reinforcement, or 5m to 8m can be selected for reinforcement of deeper or less stable surrounding rock, depending on the stability of the surrounding rock, geological conditions, and design requirements. The diameter of the guide pipe affects grouting efficiency and grout diffusion radius. Besides the Φ42mm–Φ50mm diameter range, smaller diameter guide pipes (Φ32mm–Φ40mm) can be used to reduce drilling difficulty and cost, or larger diameter guide pipes (Φ50mm–Φ60mm) can be used to increase grout volume and diffusion range. The circumferential spacing determines the distribution density of the guide pipes around the tunnel excavation outline, affecting the uniformity and continuity of the reinforcement ring. Besides a spacing of 30cm–40cm, a denser spacing of 20cm–30cm can be used to enhance the reinforcement effect, or a more sparse spacing of 40cm–50cm can be used to adapt to better surrounding rock conditions, depending on the degree of rock fragmentation and grouting effect. The external insertion angle refers to the angle between the small guide pipe and the tunnel axis or excavation outline. Its size affects the diffusion direction of the grout in the surrounding rock and the shape of the reinforcement ring. In addition to an external insertion angle of 10° to 15°, a smaller external insertion angle of 5° to 10° can be used to form a gentler reinforcement ring, or a larger external insertion angle of 15° to 20° can be used to enhance the support for the edge of the excavation face, depending on the actual geological conditions and reinforcement requirements. The grouting pressure is the driving force for the grout to overcome the resistance of the surrounding rock and diffuse outward, affecting the penetration depth of the grout and the reinforcement effect. In addition to the pressure range of 0.5MPa to 1.0MPa, a lower pressure of 0.3MPa to 0.5MPa can be used to avoid disturbing the surrounding rock, or a higher pressure of 1.0MPa to 1.5MPa can be used to ensure the effective diffusion of the grout in dense surrounding rock, depending on the permeability of the surrounding rock, the viscosity of the grout, and the design requirements.
[0039] For moderately fractured zones, a combination of pre-support pipe roofs and small guide pipes is used for grouting reinforcement. The pipe roofs are 10m-20m long, 89mm-108mm in diameter, with a circumferential spacing of 40cm-50cm and an outward insertion angle of 1°-3°. Small guide pipes are used between the pipe roofs for supplementary reinforcement. The length of the pipe roofs determines the longitudinal range of the pre-support, providing long-distance stable support for subsequent excavation. Besides the 10m-20m length range, shorter pipe roofs of 8m-10m can be selected for narrower fractured zones, or longer pipe roofs of 20m-30m can be selected for particularly wide or extremely unstable fractured zones, depending on the width of the fault fracture zone and geological conditions. The diameter of the pipe roofs affects their stiffness and bearing capacity. Besides the 89mm-108mm diameter range, smaller diameter pipe roofs of 76mm-89mm can be used to reduce construction difficulty, or larger diameter pipe roofs of 108mm-127mm can be used to provide stronger support capacity. The circumferential spacing affects the continuity and uniformity of pipe roof support. Besides a spacing of 40cm–50cm, a denser spacing of 30cm–40cm can be used to enhance the overall support effect, or a more sparse spacing of 50cm–60cm can be used to adapt to better surrounding rock conditions, depending on the stability of the surrounding rock. The outer angle of the pipe roof is usually small to ensure stable advance support along the tunnel axis. Besides an outer angle of 1°–3°, a near-horizontal arrangement of 0°–1° or a slightly larger outer angle of 3°–5° can be used to adapt to specific stress requirements, depending on the tunnel slope or special geological structure. Supplementary reinforcement is achieved by using advance small guide pipes between pipe roofs. This combination aims to compensate for any weak areas between pipe roofs and improve the overall reinforcement effect. In addition to small guide pipes, other auxiliary reinforcement measures such as short anchors and fiberglass anchors can be used to further enhance the stability of the surrounding rock between pipe roofs.
[0040] For severely fractured zones, advanced curtain grouting reinforcement is adopted. The grouting reinforcement range is 5m to 8m outside the tunnel excavation outline, the grouting section length is 20m to 30m, and the grouting pressure is 1.5 to 2.5 times the hydrostatic pressure. The grouting holes are arranged in a ring, and are constructed sequentially from the outer ring to the inner ring and from top to bottom. The grouting reinforcement range determines the thickness of the waterproof and reinforcement ring formed by the curtain grouting. In addition to the 5m to 8m range, a smaller range of 3m to 5m can be selected for moderately water-rich conditions, or a larger range of 8m to 10m can be selected for high water pressure and strongly water-rich areas, depending on the groundwater pressure, surrounding rock permeability, and design requirements. The grouting section length determines the coverage range of the curtain grouting in the longitudinal direction of the tunnel. In addition to the 20m to 30m length, a shorter grouting section of 15m to 20m or a longer grouting section of 30m to 40m can be selected to ensure effective treatment of the entire fractured zone, depending on the longitudinal width of the fault fracture zone and geological conditions. Grouting pressure is related to hydrostatic pressure to ensure that the grout can effectively overcome water pressure and penetrate into the fractured rock mass. Besides 1.5 to 2.5 times the hydrostatic pressure, a lower multiple of 1.2 to 1.5 times can be used to avoid excessive disturbance to the surrounding rock, or a higher multiple of 2.5 to 3.0 times can be used to cope with extremely high water pressure conditions, depending on the permeability of the surrounding rock, the type of grout, and the actual water pressure. Grouting holes are arranged in a ring, proceeding from the outer ring to the inner ring and from top to bottom. This grouting sequence aims to form a closed curtain structure, effectively blocking groundwater and reinforcing the surrounding rock. In addition to the outer ring to the inner ring and from top to bottom, a bottom-up and inner-ring to outer ring sequence can also be used. Alternatively, depending on the actual geological conditions and groundwater flow direction, various flexible grouting sequences such as zoning, segmentation, and skipping holes can be adopted to optimize grout diffusion and reinforcement effects.
[0041] Through the above technical solutions, this application achieves precise and differentiated advanced pre-reinforcement of fault fracture zones with different fracture levels. For lightly fractured zones, advanced small-diameter pipe grouting reinforcement with appropriate parameters is adopted. The length, diameter, circumferential spacing, external insertion angle, and grouting pressure of the small-diameter pipes have all been optimized, which can effectively control construction costs and efficiency while ensuring the stability of the surrounding rock and avoid over-reinforcement. For moderately fractured zones, advanced pipe roof and small-diameter pipe combined grouting reinforcement is used. The pipe roof provides long-distance, high-rigidity advanced support, effectively suppressing large deformation of the surrounding rock. At the same time, the small-diameter pipes are used for localized densified grouting, which compensates for possible weak reinforcement areas between pipe roofs, significantly enhancing the integrity and self-stabilizing ability of the surrounding rock, and effectively addressing the deformation risk of the surrounding rock under moderately complex geological conditions. For severely fractured zones, advanced curtain grouting reinforcement is employed. By setting a large grouting reinforcement range and grouting section length, and dynamically adjusting the grouting pressure according to hydrostatic pressure, it ensures that the grout can fully penetrate and seal the extremely fractured rock mass and enriched groundwater. Combined with the sequential arrangement of grouting holes from the outer circle to the inner circle and from top to bottom, a closed and continuous waterproof reinforcement curtain can be formed, effectively preventing groundwater inflow, reducing water pressure, and significantly improving the bearing capacity and stability of the surrounding rock. This graded and differentiated pre-reinforcement strategy ensures that the reinforcement strength is highly matched with the actual bearing capacity requirements of the surrounding rock, avoiding the safety hazards caused by insufficient reinforcement and the waste of resources caused by excessive reinforcement, and significantly improving the safety and economy of long tunnels densely crossing fault fracture zones.
[0042] In response, this application further points out that during the dynamic zoned drainage-grouting coordinated construction process, due to the huge differences in water inflow pressure and rock mass fracturing degree in different hydrological zones, if there is a lack of targeted pore density and depth configuration, it will lead to uneven diffusion of grout and incomplete release of water pressure, which in turn will cause problems such as poor grouting sealing effect or instability of the working face.
[0043] In step S3 of the aforementioned dynamic zoning drainage-grouting coordinated construction, after dividing the hole layout area of the working face into three hydrological zones—weak water zone, transition zone, and strong water zone—the specific layout method is as follows: in the weak water zone, the number of grouting holes accounts for 20%–30% of the total number of grouting holes, and the number of drainage holes accounts for 10%–20% of the total number of drainage holes; in the transition zone, the number of grouting holes accounts for 30%–40% of the total number of grouting holes, and the number of drainage holes accounts for 30%–40% of the total number of drainage holes; in the strong water zone, the number of grouting holes accounts for 30%–50% of the total number of grouting holes, and the number of drainage holes accounts for 40%–60% of the total number of drainage holes; the drainage hole layer is located outside the grouting hole layer, and the radial distance between the two layers is 1.5m–2.5m, and the drainage holes are equipped with drainage pipes with valves.
[0044] Through the aforementioned technical solution, this application achieves differentiated and refined layout of grouting holes and drainage holes in dynamic zoned drainage-grouting coordinated construction, targeting weak water zones, transition zones, and strong water zones identified at the working face. Specifically, by significantly increasing the proportion of drainage holes in strong water zones, groundwater pressure in high-pressure areas can be reduced efficiently and quickly, effectively avoiding risks such as water inrush and mudslide. Simultaneously, the reasonable distribution of grouting holes within different hydrological zones ensures that the grout can be precisely filled and reinforced according to the rock mass's fracturing degree and water abundance, avoiding resource waste and reinforcement blind spots caused by blind hole layout. Placing the drainage hole layer outside the grouting hole layer, maintaining a radial spacing of 1.5m to 2.5m, forms an effective pre-pressure relief barrier, reducing water pressure in the grouting area before grouting, creating favorable conditions for effective grout diffusion, and significantly improving the grouting success rate and sealing effect. In addition, the drainage pipe with valve is installed in the drainage hole, which allows the drainage process to be actively and flexibly controlled. Construction personnel can precisely adjust the drainage state according to the grouting progress and the stratum response. This can guide the grout diffusion by draining water and achieve complete sealing after grouting is completed. This significantly improves the construction safety and reinforcement quality of complex water-rich fault fracture zones and effectively solves problems such as uneven grout diffusion, incomplete release of drainage pressure, poor grouting sealing effect, or instability of the working face.
[0045] In some of the embodiments described above in this application, a zoned progressive grouting and diagonal drainage guidance are proposed to achieve coordinated control of drainage and grouting in the fault fracture zone of the tunnel. However, in the process of implementation, if the grouting sequence and drainage guidance lack a refined logical connection, it is easy to cause uneven diffusion of grout in the fracture zone, resulting in grout loss or local grouting not being dense. Moreover, when grouting in a strong water area, if the balance between grout solidification and pressure relief drainage cannot be effectively controlled, it is very easy to cause insufficient grouting pressure or grout being diluted by groundwater, thereby affecting the overall water blocking and reinforcement effect.
[0046] In response, this application further proposes a specific implementation method for zoned progressive grouting and diagonal drainage guidance, which includes: first, grouting is carried out in the weak water zone, with the grouting pressure gradually increasing from low to high, while simultaneously opening the drainage holes at the diagonal positions of the strong water zone to release pressure and drain water, guiding the grout to diffuse towards the strong water zone; after the grouting in the weak water zone is completed and the grout has initially set, grouting is carried out in the transition zone, while simultaneously opening the drainage holes at the diagonal positions of the transition zone; finally, grouting is carried out in the strong water zone, using cement-water glass dual-liquid grout, and during the grouting process, the diagonal drainage holes are kept continuously draining water until grout comes out of the drainage holes and the grouting pressure reaches the design value, at which point the drainage holes are closed to complete the grouting.
[0047] Through the above technical solution, this application constructs a rigorous grouting and drainage coordinated operation process, achieving precise guidance and control of the grout diffusion path within the fault fracture zone. First, by grouting in the weak water zone and coordinating diagonal drainage in the strong water zone, the resulting pressure difference effectively guides the grout to directionally penetrate from the weak water zone to the strong water zone, ensuring effective filling and diffusion of the grout within the fractured rock mass and significantly avoiding blind loss and waste. Second, after grouting in the weak water zone is completed and the grout has initially set, grouting is then carried out in the transition zone. The solidified grout serves as a barrier for subsequent grouting, gradually advancing the grouting operation and effectively preventing backflow or dilution of the grout in its unsolidified state, ensuring the continuity and integrity of the reinforcement. Finally, during grouting in the high-water zone, the use of a fast-setting cement-water glass dual-liquid grout, combined with continuous diagonal drainage guidance, ensured that the grout could quickly seal the cracks under high water pressure until grout emerged from the drainage holes and reached the design pressure, marking the successful completion of the grouting reinforcement and water-blocking operation. This phased, guided, and feedback-based grouting strategy not only significantly improved the reliability and water-blocking efficiency of grouting reinforcement under complex geological conditions, but also effectively solved problems such as uneven grout diffusion, localized incomplete grouting, and poor grouting effects in high-water zones through refined zoning control. This provides a safer and more efficient construction guarantee for long tunnels densely traversing fault fracture zones.
[0048] In some of the embodiments described above in this application, a three-stage temporary inverted arch method is proposed to pass through fault fracture zones. However, in actual construction, if differentiated excavation advance control and support parameter design are not adopted for surrounding rock with different fracture levels, it is easy to cause insufficient self-stabilizing capacity of the excavation face, resulting in excessive deformation or even collapse of the surrounding rock. Moreover, the support structure is not matched with the degree of fracture of the surrounding rock, making it difficult to achieve effective constraint on the surrounding rock.
[0049] In this regard, this application further proposes that, in step S4, the excavation length of the upper step of the three-step temporary inverted arch method is 3m to 5m, the excavation length of the middle step is 5m to 8m, and the excavation length of the lower step is 8m to 15m; the cyclic advance is controlled according to the fault fracture zone grade: 1.0m to 1.5m for lightly fractured zones, 0.6m to 1.0m for moderately fractured zones, and 0.4m to 0.6m for heavily fractured zones; in the initial support structure, the spacing of the steel arch frames is determined according to the fault fracture zone grade: 80cm to 100cm for lightly fractured zones, 60cm to 80cm for moderately fractured zones, and 40cm to 60cm for heavily fractured zones; the thickness of the shotcrete is 20cm to 30cm, and the strength grade is not lower than C25.
[0050] Specifically, the three-stage temporary invert arch method is a commonly used tunnel excavation method. It involves dividing the tunnel cross-section into three stages—upper, middle, and lower—for phased excavation, with temporary invert arches constructed in a timely manner to improve the stability of the excavation face. The upper stage is typically shorter and primarily used to form the arch space; the middle stage has a moderate excavation length, connecting to the upper stage and extending downwards; the lower stage has a relatively longer excavation length, used to complete the bottom excavation and form the temporary invert arch. In this application, the upper stage excavation length is set at 3m–5m, the middle stage at 5m–8m, and the lower stage at 8m–15m. This phased excavation strategy helps to disperse excavation stress, reduce the exposed area of the surrounding rock, and thus effectively control the deformation of the surrounding rock. (The specific length ranges are not provided in this application.)
[0051] Through the above technical solutions, this application achieves precise matching between excavation operations and surrounding rock geological conditions by classifying the excavation length of the three-stage temporary inverted arch method and establishing a correspondence between excavation cycle advance and fault fracture zone grade. By controlling the cycle advance according to the fault fracture zone grade, the area of surrounding rock exposed in a single excavation can be effectively limited, preventing instability due to poor self-stabilizing capacity of the surrounding rock. By determining the spacing of the steel arch frames according to the fault fracture zone grade, the stiffness of the initial support structure can be ensured to be compatible with the degree of surrounding rock fracture, avoiding redundancy or inadequacy of the support structure while ensuring construction safety. By limiting the thickness and strength grade of shotcrete, the necessary sealing and bearing capacity are provided for the initial support, ensuring that the support structure can form a whole in a timely manner and effectively controlling the deformation and displacement of the surrounding rock. By combining the detailed classification of the fault fracture zone in step S1 with the differentiated pre-reinforcement in step S2, this scheme can more accurately adjust the excavation and support parameters according to the actual situation of the surrounding rock, thereby significantly improving the construction safety, stability and economy when passing through the fault fracture zone, and effectively avoiding risks such as excessive deformation or collapse of the surrounding rock.
[0052] In some of the above-mentioned schemes in this application, radial supplementary grouting reinforcement is proposed after the initial support is closed into a ring to improve the stability of the surrounding rock. However, in the actual construction process, due to the complexity of the degree of fracture of the surrounding rock and the leakage situation, if there is a lack of targeted grouting process specifications and emergency treatment mechanisms for sudden leakage, it is easy to cause uneven grouting reinforcement, grout loss or failure to effectively seal local leakage points, thereby affecting the load-bearing capacity and waterproofing effect of the overall support structure.
[0053] In response, this application further proposes the following implementation method for radial supplementary grouting reinforcement: the radial grouting holes are arranged in a quincunx pattern with a hole spacing of 1.0m to 1.5m and a hole depth of 3m to 5m; the grouting pipe is a Φ42mm steel perforated pipe; the grouting pressure is 0.5MPa to 1.5MPa; the grouting material is cement grout or cement-water glass double-liquid grout; when the leakage flow rate is greater than 5L / min·m, grouting holes are first arranged around the leakage point for containment grouting, and then the leakage point is directly grouted and sealed.
[0054] Specifically, the radial grouting holes are arranged in a quincunx pattern, a common hole arrangement where adjacent holes are staggered, resembling plum blossom petals. This arrangement ensures that the grout forms a uniform and overlapping reinforcement zone within the surrounding rock, effectively avoiding reinforcement blind spots and thus improving the overall density and uniformity of the grouting reinforcement.
[0055] When the leakage flow rate exceeds 5 L / min·m, this application proposes a special treatment strategy. When the leakage flow rate reaches or exceeds the threshold of 5 L / min·m, it indicates that the water pressure in the area is high and the cracks are well developed. Direct grouting may cause the grout to be washed away, diluted, or lost by the water flow.
[0056] Through the above technical solution, after the initial support is closed into a ring, this application can implement refined and differentiated radial supplementary grouting reinforcement based on the complexity of the surrounding rock and water leakage. The quincunx-shaped arrangement of grouting holes, combined with appropriate hole spacing and depth, ensures that the grout forms a uniform and overlapping reinforcement zone within the surrounding rock behind the initial support, effectively eliminating reinforcement blind spots and significantly improving the overall density and bearing capacity of the surrounding rock. The use of Φ42mm steel perforated pipes ensures the stability of the grouting channel and the uniform diffusion of the grout. Simultaneously, based on the degree of fissure development and water content of the surrounding rock, cement grout or cement-water glass dual-liquid grout is flexibly selected as the grouting material, and the grouting pressure is precisely controlled between 0.5MPa and 1.5MPa, allowing the grout to effectively fill various fissures and bond well with the surrounding rock, thereby achieving reliable structural reinforcement and waterproofing effects. Especially when facing complex hydrological conditions with seepage flow rates exceeding 5 L / min·m, this application innovatively adopts a stepped treatment mechanism of first containing and then sealing. This involves first installing grouting holes around the leak point to reduce water pressure and flow, and then directly sealing the leak point with grout. This strategy effectively avoids erosion and loss of the grout under high water flow conditions, ensuring that the grout can fully exert its water-stopping and reinforcement functions, and greatly improving the grouting success rate and engineering safety in complex water-rich fault fracture zones. Overall, this scheme significantly improves the stability and waterproofing performance of the surrounding rock behind the initial support, providing a more reliable guarantee for subsequent reinforcement of long tunnels densely traversing fault fracture zones.
[0057] In some of the embodiments described above in this application, it is proposed to use an information-based construction management system to analyze and provide feedback in order to dynamically adjust construction parameters. However, in actual construction, due to the lack of a refined processing mechanism for the surrounding rock deformation monitoring data and a clear early warning triggering logic, it is difficult for construction personnel to accurately determine whether the surrounding rock condition is within the safety threshold. As a result, it is impossible to take timely and scientific remedial measures, which leads to the lag and blindness in the dynamic control of tunnel construction under complex geological conditions.
[0058] In response, this application further proposes a dynamic control method for an information-based construction management system. This method includes: setting up displacement monitoring points at the tunnel arch, left and right sidewalls, and invert arch positions; monitoring frequency is twice daily for the first 7 days after excavation, once daily after 7 days, and once every 2 days after 15 days; when the arch subsidence rate exceeds 5 mm / d or the perimeter convergence rate exceeds 3 mm / d, it is determined to be an abnormal deformation of the surrounding rock, and the system automatically issues an early warning and prompts adjustments to construction parameters; adjustment measures include: reducing the excavation advance in the next cycle, increasing the density of the steel arch frame, increasing the grouting volume, or implementing secondary lining ahead of schedule.
[0059] Through the aforementioned technical solution, this application enables the comprehensive and timely acquisition of deformation data of the surrounding rock during the construction of long tunnels densely traversing fault fracture zones. This is achieved by deploying displacement monitoring points at key stress-bearing locations such as the tunnel arch, left and right sidewalls, and invert arch, and employing phased monitoring frequencies. This ensures accurate perception of the surrounding rock condition. Especially during the initial stage of active surrounding rock deformation, high-frequency monitoring effectively captures sudden deformations, providing a reliable basis for subsequent decision-making. By setting clear thresholds for the arch settlement rate and the surrounding convergence rate, this method elevates the assessment of surrounding rock stability from empirical judgment to a quantitative standard. This allows the information-based construction management system to automatically identify abnormal surrounding rock conditions and issue early warnings, effectively overcoming the subjectivity and lag of manual judgment and significantly improving the timeliness and accuracy of risk identification. When the system issues an early warning, it can automatically prompt targeted adjustment measures, including reducing the excavation advance in the next cycle, increasing the density of the steel arch frame, increasing the grouting volume, or implementing secondary lining in advance, forming a closed-loop management mechanism from monitoring and early warning to decision-making and intervention. This dynamic control method enables the construction plan to be optimized in real time based on the actual response of the surrounding rock, effectively suppressing the further development of surrounding rock deformation, ensuring the structural safety and construction continuity of long tunnels under complex geological conditions of dense fault fracture zones, and avoiding safety hazards and economic losses caused by delayed decision-making or blind intervention.
[0060] In some embodiments described above in this application, a method of cyclically advancing through densely fractured zones to complete tunnel construction is proposed. However, in actual engineering, if the distance between adjacent fault fractured zones is too short, simple cyclical construction often leads to frequent switching of construction procedures, repetitive resource input, and accumulation of surrounding rock disturbance, thereby reducing construction efficiency and increasing safety risks. To address this, this application further proposes a specific implementation method for cyclically advancing through densely fractured zones in step S6, which includes: when the length of the intact rock mass section between two adjacent fault fractured zones is less than 20m, the two fault fractured zones are merged into one construction section for unified reinforcement and excavation; when the length of the intact rock mass section is greater than 20m, the two fault fractured zones are constructed independently, and the intermediate intact rock mass section is quickly passed using a full-face excavation method, with a cyclic advance of 2m to 3m for the intact rock mass section.
[0061] Through the above technical solutions, this application optimizes the construction organization for long tunnels densely traversing fault fracture zones. When the length of the intact rock mass section between adjacent fault fracture zones is less than 20m, the two fracture zones are merged into one construction section for unified reinforcement and excavation. This effectively avoids frequent switching of construction procedures and parameters over short distances, reduces the difficulty of construction organization and the repetitiveness of resource input, and also reduces the cumulative effect of surrounding rock disturbance caused by continuous construction, thereby improving the continuity and safety of construction. When the length of the intact rock mass section is greater than 20m, the two fault fracture zones are allowed to be constructed independently, and the better self-stabilizing ability of the intermediate intact rock mass section is utilized to quickly pass through using the full-face excavation method, with the excavation cycle advance set at 2m to 3m. This differentiated construction strategy fully utilizes the characteristics of different geological conditions, significantly improves the excavation efficiency of the intact rock mass section while ensuring construction safety, and thus accelerates the construction progress of the entire long tunnel densely traversing fault fracture zones. Overall, the scheme achieves dynamic optimization of construction organization, balances construction efficiency and surrounding rock stability, and effectively solves the problems of poor connection and low efficiency in continuous construction of densely fractured zones.
[0062] In the description of this invention, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing the invention and for simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0063] In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. For those skilled in the art, the specific meaning of the above terms in this invention can be understood according to the specific circumstances.
Claims
1. A construction method for long tunnels densely traversing fault fracture zones, characterized in that, Includes the following steps: S1: Multi-level advanced geological prediction and fault fracture zone classification: A multi-level advanced geological prediction system consisting of TSP seismic wave prediction, ground-penetrating radar detection, infrared water detection and horizontal geological drilling is adopted to sequentially determine the spatial distribution, rock mass fracture degree and groundwater enrichment of multiple fault fracture zones in front of the tunnel. Based on the rock mass integrity index and single-hole water inflow, each fault fracture zone is divided into three levels: light fracture zone, moderate fracture zone and heavy fracture zone. At the same time, a geological cloud map containing the classification information of each fault fracture zone is generated. S2: Graded Advanced Pre-reinforcement: Based on the graded results of the fault fracture zone obtained in step S1, corresponding advanced pre-reinforcement schemes are adopted for different grades of fault fracture zones to form an advanced reinforcement ring matching the fracture grade outside the tunnel excavation outline; among them, advanced small pipe grouting reinforcement is adopted for lightly fractured zones, advanced pipe roof and small pipe combined grouting reinforcement is adopted for moderately fractured zones, and advanced curtain grouting reinforcement is adopted for severely fractured zones. S3: Dynamic Zonal Drainage-Grouting Coordinated Construction: Based on the geological cloud map obtained in step S1, the water-rich distribution on the working face is identified, and the borehole area on the working face is divided into three hydrological zones: weak water zone, transition zone, and strong water zone. Drainage holes and grouting holes of different densities and depths are laid out respectively, forming a double-layer borehole structure of drainage hole layer and grouting hole layer. During grouting, a combination of zonal progressive grouting and diagonal drainage guidance is adopted. First, the weak water zone is grouted and sealed, and then the process is advanced to the transition zone and strong water zone. At the same time, the grout is guided to diffuse through the drainage holes at diagonal positions. After grouting is completed, the drainage holes are opened for active drainage and pressure relief. S4: Step-by-step excavation and initial support: The three-stage temporary inverted arch method is used to excavate through the fault fracture zone in steps. The excavation length of the upper, middle and lower steps increases sequentially, and the longitudinal offset between the excavation surfaces of each step is not less than twice the tunnel diameter. During the excavation process, the cyclic advance is controlled according to the fault fracture zone grade. After the excavation, steel arch frames are erected in time, steel mesh is hung and shotcrete is sprayed to form the initial support structure. At the same time, anchor pipes are installed at the arch foot. S5: Radial supplementary reinforcement and information-based dynamic control: After the initial support is closed into a ring, radial supplementary grouting reinforcement is carried out behind the initial support based on the surrounding rock deformation monitoring data and water leakage situation; throughout the construction process, data is collected in real time through the deployed surrounding rock pressure sensors, displacement monitoring points and seepage flow monitoring devices, and analyzed and fed back using the information-based construction management system, and the reinforcement parameters and excavation parameters of the subsequent fault fracture zone are dynamically adjusted based on the feedback results; S6: Cyclic advancement through densely fractured zones: Repeat steps S1 to S5, sequentially forecasting, reinforcing, excavating, and supporting each subsequent fault fractured zone. The intact rock mass section between two adjacent fault fractured zones is quickly passed through using conventional construction methods until the construction of all densely fractured fault zone sections is completed.
2. The method according to claim 1, wherein, In step S1, the implementation method of the multi-level advanced geological prediction system is as follows: First, the TSP seismic wave predictor was used for long-distance prediction, with a prediction distance of 100m to 150m, to preliminarily delineate the approximate range of the fault fracture zone; Subsequently, ground-penetrating radar was used for medium-range fine exploration at a distance of 20m to 30m to further determine the boundary and internal structure of the fault fracture zone. Then, an infrared water detector is used to detect groundwater and determine the water abundance of the fault fracture zone; Finally, a horizontal geological drilling rig was used for advanced drilling verification. The drilling depth was 30m to 50m, and the overlap length of each cycle was not less than 5m. The actual parameters of the fault fracture zone were confirmed by core observation and water inflow monitoring.
3. The method according to claim 1, wherein, In step S1, the grading standard for fault fracture zones is as follows: The rock mass integrity index Kv of the slightly fractured zone is ≥0.55, and the single-hole water inflow rate Q is ≤10m³ / h; The rock mass integrity index Kv of the moderately fractured zone is 0.35 to 0.55, and the single-hole water inflow Q is 10 m³ / h to 30 m³ / h. The rock mass integrity index Kv of the severely fractured zone is <0.35, and the single-hole water inflow Q is >30 m³ / h.
4. The method according to claim 1, wherein, In step S2: The length of the pre-grouted small guide tube for reinforcement is 3m to 5m, the diameter is Φ42mm to Φ50mm, the circumferential spacing is 30cm to 40cm, the external insertion angle is 10° to 15°, and the grouting pressure is 0.5MPa to 1.0MPa. The pipe roofs reinforced by grouting the advanced pipe roofs and small pipes have a length of 10m to 20m, a diameter of Φ89mm to Φ108mm, a circumferential spacing of 40cm to 50cm, and an external insertion angle of 1° to 3°. The pipe roofs are supplemented with advanced small pipes for additional reinforcement. The grouting reinforcement range of the advanced curtain grouting reinforcement is 5m to 8m outside the tunnel excavation outline, the grouting section length is 20m to 30m, the grouting pressure is 1.5 to 2.5 times the hydrostatic pressure, and the grouting holes are arranged in a ring and are constructed sequentially from the outer ring to the inner ring and from top to bottom.
5. The method according to claim 1, wherein, In step S3: The number of grouting holes in the weak water zone accounts for 20% to 30% of the total number of grouting holes, and the number of drainage holes accounts for 10% to 20% of the total number of drainage holes; The number of grouting holes in the transition zone accounts for 30% to 40% of the total number of grouting holes, and the number of drainage holes accounts for 30% to 40% of the total number of drainage holes. The number of grouting holes in the high-water zone accounts for 30% to 50% of the total number of grouting holes, and the number of drainage holes accounts for 40% to 60% of the total number of drainage holes; The drainage hole layer is located outside the grouting hole layer, and the radial distance between the two layers is 1.5m to 2.5m. The drainage hole is equipped with a drainage pipe with a valve.
6. The method according to claim 1, wherein, In step S3, the specific implementation method of zoned progressive grouting and diagonal drainage guidance is as follows: First, grouting is carried out in the weak water area, and the grouting pressure is gradually increased from low to high. At the same time, the drainage holes at the diagonal positions of the strong water area are opened to release pressure and drain water, guiding the grout to diffuse towards the strong water area. After the grouting in the weak water zone is completed and the grout has initially set, the transition zone is grouted, and at the same time the drainage holes at the diagonal positions of the transition zone are opened. Finally, grouting is carried out in the high water area. Cement-water glass double-liquid grout is used for grouting in the high water area. During the grouting process, the diagonal drainage holes are kept drained continuously until grout comes out of the drainage holes and the grouting pressure reaches the design value. Then the drainage holes are closed to complete the grouting.
7. The method according to claim 1, wherein, In step S4: The excavation length of the upper step of the three-step temporary inverted arch method is 3m to 5m, the excavation length of the middle step is 5m to 8m, and the excavation length of the lower step is 8m to 15m. The cyclic advance is controlled according to the fault fracture zone level: 1.0m to 1.5m for lightly fractured zones, 0.6m to 1.0m for moderately fractured zones, and 0.4m to 0.6m for heavily fractured zones; In the initial support structure, the spacing of the steel arch frames is determined according to the fault fracture zone grade: 80cm to 100cm for lightly fractured zones, 60cm to 80cm for moderately fractured zones, and 40cm to 60cm for heavily fractured zones; the thickness of the shotcrete is 20cm to 30cm, and the strength grade is not lower than C25.
8. The method according to claim 1, wherein, In step S5, the implementation method of radial supplementary grouting reinforcement is as follows: The radial grouting holes are arranged in a quincunx pattern, with a hole spacing of 1.0m to 1.5m and a hole depth of 3m to 5m. The grouting pipe is a Φ42mm steel perforated pipe. The grouting pressure is 0.5MPa to 1.5MPa, and the grouting material is cement grout or cement-water glass two-component grout. When the leakage flow rate is greater than 5L / min·m, first set up grouting holes around the leakage point for surrounding grouting, and then directly grout the leakage point to seal it.
9. The method according to claim 1, wherein, In step S5, the dynamic control method of the information-based construction management system is as follows: Displacement monitoring points were set up at the tunnel arch, left and right sidewalls and invert arch. The monitoring frequency was twice a day for the first 7 days after excavation, once a day after 7 days, and once every 2 days after 15 days. When the rate of settlement of the arch is greater than 5 mm / d or the rate of convergence of the perimeter is greater than 3 mm / d, it is determined that the surrounding rock deformation is abnormal, and the system will automatically issue an early warning and prompt the adjustment of construction parameters. Adjustment measures include: reducing the excavation advance in the next cycle, increasing the density of the steel arch frame, increasing the grouting volume, or implementing secondary lining in advance.
10. The construction method for long tunnels densely traversing fault fracture zones according to claim 1, characterized in that, In step S6, when the length of the intact rock mass section between two adjacent fault fracture zones is less than 20m, the two fault fracture zones are merged into one construction section for unified reinforcement and excavation; when the length of the intact rock mass section is greater than 20m, the two fault fracture zones are constructed independently, and the middle intact rock mass section is quickly passed through using the full-face excavation method, with the excavation cycle advance of the intact rock mass section being 2m to 3m.