A method for precise excavation of trenches in rock formations for gravity-flow sewage pipelines
By establishing a final rock excavation control surface during the construction of gravity-flow sewage pipelines in rock strata, differentiating treatment areas and setting up a fine-tuning protective layer, and precisely controlling blasting holes, the problem of inaccurate blasting during construction in rock strata was solved, achieving efficient rock removal and base formation.
Patent Information
- Application Number
- CN202611492045.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-23
- Publication Date
- 2026-11-17
AI Technical Summary
When constructing gravity-flow sewage pipeline trenches in rock strata, existing technologies make it difficult to select appropriate treatment methods based on the actual remaining rock conditions after mechanical initial excavation. This results in inaccurate blasting removal, which can easily lead to under-excavation or over-excavation, affecting the difficulty and efficiency of construction control.
By establishing a final rock excavation control face, determining the thickness of the remaining rock layers in the local area based on the actual rock surface after mechanical initial excavation, distinguishing between direct non-blasting treatment areas and controlled blasting areas, and setting up a fine-tuning protective layer in the controlled blasting area, the drilling depth and charge amount of the blasting holes are precisely controlled. Combined with non-blasting methods, the layers are finely tidied up layer by layer, ultimately forming a stable base elevation.
It improved the accuracy and efficiency of rock excavation, reduced the risk of blasting disturbing the final foundation, and ensured the continuity of the longitudinal slope and construction quality of gravity flow sewage pipelines.
Smart Images

Figure CN123109675A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of pipeline trench construction technology, and in particular to a method for precise excavation and construction of trenches in rock strata for gravity flow sewage pipelines. Background Technology
[0002] Gravity-flow sewage pipelines rely primarily on the longitudinal slope of the pipeline itself for sewage transport, thus requiring high standards for the pipeline foundation elevation and the continuity of the slope along the route. When excavating trenches in rock strata, the excavation elevation of the rock surface at the bottom of the trench directly affects the subsequent laying of sand cushion layers and pipeline installation. When the bottom of the trench is under-excavated in some areas, further rock breaking is required; when there is over-excavation in some areas, backfilling or repair is necessary, both of which increase the difficulty of construction control.
[0003] Existing methods for constructing pipe trenches in rock formations typically involve initial excavation using mechanical equipment over a large area, followed by further excavation using methods such as mechanical breaking, manual trimming, or blasting, depending on the remaining rock layer thickness. Due to variations in rock strength, weathering degree, and fissure development, coupled with the fact that the actual rock surface after mechanical excavation usually has some undulations, even with a uniform pre-reserved thickness for initial mechanical excavation, the actual remaining rock layer thickness at different locations often varies.
[0004] For areas with thick remaining rock layers, blasting can improve rock removal efficiency. However, in actual construction, relying primarily on the designed reserved thickness or using relatively uniform drilling depths for blasting makes it difficult to adapt to local undulations in the actual rock surface after mechanical initial excavation. In some locations with thick remaining rock layers, significant under-excavation may occur after blasting, while in other locations with thin remaining rock layers, the blast holes and blasting actions may approach the final designed rock surface too closely, increasing the risk of local over-excavation and disturbance to the ultimately retained rock mass.
[0005] Furthermore, when using blasting to directly excavate rock to the final design elevation, blasting is responsible for both the rapid removal of most of the rock and the control of the final rock surface formation, making it difficult to simultaneously meet these two construction requirements. Reducing the blasting force to avoid over-excavation can easily increase the workload of subsequent finishing of the remaining rock; conversely, excessively strong blasting may damage the final base rock surface, resulting in local elevations below the design requirements. While passive finishing using manual labor or small equipment after blasting can address some under-excavated areas, it is difficult to eliminate the localized over-excavation already caused by the initial blasting.
[0006] Therefore, for the construction of trenches in rock formations for gravity-flow sewage pipelines, the following issues need to be addressed in current construction: how to select subsequent treatment methods based on the actual remaining rock conditions after mechanical initial excavation, control the blasting removal range in areas where blasting is required, efficiently remove most of the rock while avoiding direct impact on the final excavation control face, and then achieve precise shaping of the final rock surface through low-disturbance methods. Summary of the Invention
[0007] The purpose of this invention is to provide a method for precise excavation and construction of trenches in rock formations for gravity-flow sewage pipelines, so as to solve the problems existing in the prior art.
[0008] To achieve the above objectives, the present invention adopts the following technical solution: A method for precise excavation of trenches in rock strata for gravity-flow sewage pipelines includes the following steps: S1. Establish the final rock excavation control surface that varies along the pipeline axis based on the design elevation of the outer bottom of the pipeline and the design thickness of the sand cushion layer. S2. Using a reserved position higher than the final excavation control surface of the rock as the target for mechanical initial excavation, perform mechanical initial excavation on the trench rock, measure the actual rock surface after mechanical initial excavation, and determine the local remaining rock layer thickness of the actual rock surface relative to the final excavation control surface of the rock. S3. Rock breaking is no longer performed in areas where the thickness of the remaining rock layer is less than or equal to 0. In areas where the thickness of the remaining rock layer is greater than 0, the areas for direct non-blasting treatment and controlled blasting treatment are determined based on the thickness of the remaining rock layer. In the controlled blasting area, a fine-repair protective layer is set above the final rock excavation control surface, and the thickness of the local target blasting removal is determined based on the thickness of the remaining rock layer and the thickness of the fine-repair protective layer. S4. Arrange blasting holes in the controlled blasting area, and determine the drilling depth of the corresponding blasting hole according to the local target blasting removal thickness at each blasting hole position, so that the bottom of the blasting hole is located at or above the upper boundary of the fine-finishing protective layer. S5. Determine the charging parameters based on the hole position and drilling depth, and implement controlled blasting after drilling, charging and plugging are completed. S6. Remove the loose rock formed by controlled blasting. Based on the rock surface elevation measurement results, refine the remaining finishing layer after blasting and the rock in the direct non-blasting treatment area that is higher than the final excavation control surface of the rock layer by layer using a non-blasting method. Stop rock breaking at the position that reaches the final excavation control surface of the rock layer. For local positions that are lower than the final excavation control surface of the rock layer after mechanical initial excavation, controlled blasting or layer-by-layer finishing, restore them to the final excavation control surface of the rock layer before laying the design sand cushion layer. The leveling compensation layer or repair layer formed by restoration is not included in the thickness of the design sand cushion layer.
[0009] Preferably, step S1 specifically includes: When the design drawings provide the design elevation of the inner bottom of the pipe At that time, the design elevation of the outer bottom of the pipe Determined according to the following formula: ; in, It is the vertical distance between the lowest point of the inner bottom of the pipe and the lowest point of the outer wall of the pipe; Final rock excavation control elevation Determined according to the following formula: ; in, This refers to the design thickness of the compacted sand cushion layer; The longitudinal design slope is Within the slope section, the design elevation of the outer bottom of the pipeline is determined according to the following formula: ; in, The design elevation of the outer bottom of the pipe at the starting point of the slope section is given. It is the distance from the starting point of the slope section along the direction of water flow.
[0010] Preferably, a rock strata condition investigation step is included before step S2: The lithology, uniaxial compressive strength, weathering grade, and fracture development grade of the rocks within the trench area are obtained, and the trench is divided into multiple construction units along the pipeline axis based on the changes in lithology, weathering grade, and fracture development grade.
[0011] Preferably, step S2 specifically includes: Multiple measuring points were set after the initial mechanical excavation. Local residual rock layer thickness at each measuring point Determined according to the following formula: ; in, For the first The rock surface elevation at each measuring point after initial mechanical excavation The final excavation control elevation for the corresponding rock location; Establish the distribution of remaining rock layer thickness based on the location of each measuring point and the local remaining rock layer thickness; For an area to be blasted, when the difference between the maximum and minimum local remaining rock layer thickness is not greater than the allowable grouping difference, the area is designated as a blasting sub-area; when the difference is greater than the allowable grouping difference, the area is divided into multiple blasting sub-areas, such that the variation in local remaining rock layer thickness within each blasting sub-area is not greater than the allowable grouping difference.
[0012] Preferably, step S3 specifically includes: Let the switching thickness between direct non-blasting treatment and controlled blasting be . The minimum feasible borehole depth corresponding to the drilling and charging structure adopted. for: ; in, The minimum allowable length of the bottom buffer section. The minimum allowable length of the orifice blocking section. The minimum effective charge length is required to meet the requirements of minimum controllable charge quantity and reliable detonation. When the thickness of the local remaining rock layer is greater than 0 and not greater than When this occurs, the corresponding area is designated as the direct non-explosive processing area; When the thickness of the local remaining rock layer is greater than At that time, the thickness of the refined protective layer is determined, and the target blasting removal thickness is determined based on the difference between the local remaining rock layer thickness and the refined protective layer thickness; when the target blasting removal thickness is not less than When the target blasting removal thickness is less than the specified area, the corresponding area is defined as the controlled blasting area; when the target blasting removal thickness is less than the specified area, the controlled blasting area is defined as the controlled blasting area. At that time, the corresponding area is determined as the direct non-explosive processing area.
[0013] Preferably, in step S3: For the first time, the controlled blasting was determined to be carried out. For each blasting sub-zone, the thickness of the fine-finish protective layer is determined based on the rock strength, weathering grade, and degree of fracture development. And when there are blasting results in similar existing construction sections, the thickness of the fine-finish protective layer is adjusted according to the blasting results. Adjustments were made to the thickness of the refined protective layer. The range is 0.05–0.10 m.
[0014] Preferably, in step S4: According to the Distribution of remaining rock strata thickness and thickness of fine-finished protective layer in each blasting sub-zone Determine the target blasting removal thickness distribution, and determine the hole spacing based on the target blasting removal thickness distribution, rock condition, and test section results. and row spacing According to the hole spacing and row spacing Determine the location of each blasting hole.
[0015] Preferably, in step S4: No. The first explosive sub-zone Each blasting hole is drilled vertically downwards from the actual rock surface after the initial mechanical excavation. The local target blasting removal thickness at the hole location is calculated according to... It is confirmed that, among them, This represents the local remaining rock layer thickness at the borehole location. To refine the thickness of the protective layer; No. Drilling depth of each blast hole satisfy This ensures that the bottom of the blasting hole does not enter the fine-finishing protective layer; the blasting hole is sequentially provided with a bottom buffer section, a charging section, and a hole-mouth plugging section from the bottom to the opening, with the bottom buffer section having a length of... Not less than Length of the blocked section at the orifice Not less than Effective charge length according to Determine and satisfy ; For blasting holes that cannot simultaneously meet the above relationships, the hole pattern, zoning, drilling depth, or charge structure should be adjusted and rechecked. If the adjustment still fails to meet the requirements, the corresponding local area should be incorporated into the direct non-blasting treatment area, and the charge space requirements should not be met by drilling into the fine-tune protective layer.
[0016] Preferably, in step S5: For the The first explosive sub-zone For each blast hole, the theoretical single-hole charge amount is determined according to the following formula. : ; in, The unit consumption of explosives was determined through the test construction section; For internal conventional blasting holes, the design single-hole charge amount for: ; For edge blasting holes located near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks, the design single-hole charge amount Determined according to the following formula: ; in, Let be the charge reduction factor determined based on the results of the test construction section, and: ; Let the minimum controllable single-hole charge of the explosive device be... The maximum effective linear charge density allowed by the charge structure is The designed single-hole charge amount satisfies: ; When the designed single-hole charge amount does not meet the above relationship, adjust the hole spacing, row spacing, blasting sub-zone division, drilling depth, charge structure or construction method, and re-verify the feasibility of the charge.
[0017] Preferably, in step S6, after removing the loose rock formed by the controlled blasting and before performing non-blasting layer-by-layer finishing of the remaining finishing layer after blasting, the step further includes a step of measuring and correcting the blasting results: Multiple post-blasting measuring points are set on the actual rock surface after slag removal in the current blasting sub-area. The actual remaining finishing layer thickness is determined based on the actual rock surface elevation of each post-blasting measuring point and the corresponding final excavation control elevation of the rock. The average remaining thickness, over-excavation measuring point ratio, and maximum over-excavation depth of the current blasting sub-area are determined based on the actual remaining finishing layer thickness of each post-blasting measuring point. Let the uniaxial compressive strength of the current blasting sub-region be... The uniaxial compressive strength of the blasting sub-zone in subsequent construction is Both were obtained using the same test method and the same value caliber; when the weathering grade and fracture development grade of the subsequent blasting sub-zone are the same as those of the current blasting sub-zone, and the conditions are met... At that time, based on the average remaining thickness, the proportion of over-excavation measuring points, and the maximum over-excavation depth, at least one of the following should be corrected for the thickness of the fine protective layer, the unit consumption of explosives, the hole spacing, the row spacing, and the local drilling depth of the blasting sub-area in the subsequent construction: When the maximum over-excavation depth exceeds the preset maximum over-excavation control value, the explosive consumption per unit should not be increased when correcting the parameters of the blasting sub-zone for subsequent construction. At least one of the following measures should be adopted: increasing the thickness of the fine-tune protective layer, reducing the charge of blasting holes near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks, reducing the local drilling depth, and increasing the density of local measurements and zoning.
[0018] The present invention has the following beneficial effects.
[0019] This invention establishes the final rock excavation control surface based on the design elevation of the outer bottom of the pipeline and the design sand cushion layer thickness, and determines the local remaining rock layer thickness based on the actual rock surface after mechanical initial excavation. This enables subsequent construction control to reflect the actual rock surface undulation and remaining rock layer state after mechanical initial excavation, reducing control deviations caused by relying solely on theoretically reserved thicknesses for subsequent construction.
[0020] This invention determines the direct non-blasting treatment area and the controlled blasting area based on the thickness of the remaining local rock layers. A fine-tuning protective layer is actively set above the final excavation control surface of the rock in the controlled blasting area. This allows the controlled blasting to mainly undertake the rapid removal of most of the rock, rather than directly undertaking the precise shaping of the final rock surface. This helps to reduce the risk of blasting directly entering the final retained bedrock and local over-excavation.
[0021] This invention determines the local target blasting removal thickness and corresponding drilling depth based on the local remaining rock layer thickness at each blasting hole location. This allows blasting holes at different locations to adapt to the local undulations of the rock surface after mechanical initial excavation, and keeps the bottom of the blasting holes at or above the upper boundary of the finishing protective layer. This avoids the situation where the local hole depth is too large and penetrates the finishing protective layer when a uniform hole depth is used.
[0022] After the controlled blasting is completed, the remaining finishing layers and the areas directly treated without blasting are finished layer by layer using non-blasting methods. This separates the rough removal by blasting from the final shaping with low disturbance, thereby improving the elevation control accuracy of the final rock base while taking into account the efficiency of rock excavation.
[0023] By restoring local areas below the final rock excavation control surface and then laying a sand cushion layer of the designed thickness, it is possible to avoid local over-excavation directly changing the actual thickness of the sand cushion layer. This maintains a relatively stable geometric relationship between the rock base, the top surface of the sand cushion layer, and the design elevation of the outer bottom of the pipe, which is beneficial to the continuous control of the longitudinal slope of gravity flow sewage pipes. Attached Figure Description
[0024] Figure 1 This is a schematic diagram of the process for the precise excavation and construction of a gravity-flow sewage pipeline trench in rock strata according to the present invention.
[0025] Figure 2 This is a longitudinal cross-sectional schematic diagram of the construction control relationship of the rock trench of the present invention, wherein... Figure 2 (a) indicates the design elevation relationship between the pipe and the sand cushion layer. Figure 2 (b) indicates the control relationship between the initial mechanical excavation of the rock surface, the finishing of the protective layer, and the blasting holes.
[0026] Figure 3 This is a schematic diagram of the division of blasting sub-zones and the planar arrangement of blasting holes in the controlled blasting area according to the present invention.
[0027] Attached reference numerals: 1. Original rock strata; 2. Final rock excavation control surface; 3. Finished protective layer; 4. Target blasting removal layer; 5. Actual rock surface after mechanical initial excavation; 6. Blasting hole; 7. Designed sand cushion layer; 8. Gravity flow sewage pipe; 9. Trench boundary; 10. Blasting sub-zone boundary; 11. First blasting sub-zone; 12. Second blasting sub-zone; 13. Obvious fissure. Detailed Implementation
[0028] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.
[0029] In the description of this invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.
[0030] Example
[0031] Please see Figure 1 This embodiment provides a method for precise excavation of trenches in rock formations for gravity-flow sewage pipelines, including the following steps: S1. Establish the final rock excavation control surface that varies along the pipeline axis based on the design elevation of the outer bottom of the pipeline and the design thickness of the sand cushion layer. When the design drawings give the location Design elevation of the bottom of the pipe at the location At that time, the vertical distance between the lowest point of the inner bottom of the pipe and the lowest point of the outer wall of the pipe is determined according to the cross-sectional dimensions of the pipe. The design elevation of the outer bottom of the pipe is determined according to the following formula. : ; In the formula: For position The design elevation of the bottom of the pipe at the location, in meters; For position The design elevation of the outer bottom of the pipe at the specified location, in meters; It is the vertical distance between the lowest point of the inner bottom of the pipe and the lowest point of the outer wall of the pipe, in meters. Its value is determined according to the cross-sectional dimensions of the actual pipe material used.
[0032] When the pipeline is located at a longitudinal design slope of When within a slope section, the design elevation of the outer bottom of the pipe at any location can also be determined based on the design elevation of the outer bottom of the pipe at the starting point of the slope section: ; In the formula: The design elevation of the outer bottom of the pipe at the starting point of the slope section is given in meters. The longitudinal slope of the pipeline is dimensionless. The distance is measured in meters (m) from the starting point of the slope section along the direction of water flow.
[0033] Let the thickness of the compacted design sand cushion layer be... If the unit is meters, then the position is... The final excavation control elevation of the rock at the location Determined according to the following formula: ; Continuously varying along the pipeline axis This constitutes the final control face for rock excavation.
[0034] like Figure 2 As shown in (a), the gravity flow sewage pipe 8 and the designed sand cushion layer 7 represent the designed positions after construction is completed; the top surface of the designed sand cushion layer 7 corresponds to the design elevation of the outer bottom of the pipe. The bottom surface corresponds to the final excavation control surface 2 of the rock, and its designed thickness after compaction is... ,satisfy .
[0035] Figure 2 (b) indicates the construction control relationship between the actual rock surface 5 after mechanical initial excavation before blasting, the target blasting removal layer 4, the fine repair protective layer 3, and the blasting hole 6.
[0036] The two parts use the same elevation definition, but are used to indicate different construction stages. This does not mean that the pipes and sand cushion layer have been installed at the time of blasting.
[0037] in, , , as well as Derived from pipeline design drawings; Derived from pipe dimensions; This originates from the design requirements of pipeline foundations.
[0038] The inputs for this step include the pipe axis, the design elevation of the inner bottom or the design elevation of the outer bottom of the pipe, the cross-sectional dimensions of the pipe, the longitudinal design slope of the pipe, and the thickness of the design sand cushion layer after compaction.
[0039] This step outputs the final control surface for rock excavation. This control surface serves as a unified elevation benchmark for subsequent mechanical preliminary excavation, calculation of local remaining rock layer thickness, setting of fine protective layers, evaluation of post-blast remaining thickness, and final fine finishing.
[0040] In this embodiment, a rock strata condition survey is conducted before step S2.
[0041] By utilizing existing engineering geological data, on-site rock surface exposure, core drilling, rock sample testing, or on-site geological surveys, the lithology, uniaxial compressive strength, weathering grade, and fracture development grade of the rocks within the trench area can be obtained.
[0042] Among them, the uniaxial compressive strength of the rock is obtained through rock sample testing; the weathering grade and fracture development grade are determined based on geological survey data and on-site exposure.
[0043] Based on the variations in lithology, weathering grade, and fracture development grade along the pipeline axis, the trench is divided into multiple construction units.
[0044] The rock mass condition within the same construction unit remains relatively continuous; when the lithology, weathering degree, or fracture development degree changes significantly, a new construction unit is established.
[0045] This step outputs the rock mass state parameters corresponding to each construction unit, which serve as the basis for subsequent construction method determination, fine protective layer thickness determination, borehole mesh parameter determination, and subsequent similar construction section identification. Before carrying out large-scale controlled blasting construction, a section with similar lithology, weathering grade and fracture development degree to the proposed construction section should be selected as the test construction section.
[0046] Based on the engineering blasting design, rock mass condition, and existing construction experience, determine the initial finishing protective layer thickness, hole spacing, row spacing, explosive consumption per unit, charge reduction coefficient for edge blasting holes, length of bottom buffer section, and length of orifice plugging section for the test construction section.
[0047] After the test blasting was completed and the loose rocks were removed, the actual rock surface after the blast was measured to obtain the actual remaining thickness of the finishing layer, the proportion of over-excavation measuring points, and the maximum over-excavation depth. At the same time, the degree of rock fragmentation, the continuity of the finishing protective layer, and the local over-excavation situation were observed.
[0048] Based on the test results, the initial fine-repair protective layer thickness, hole spacing, row spacing, explosive consumption per unit, and the reduction coefficient of explosive charge in the edge blasting holes were adjusted to ensure that a fine-repair layer for subsequent non-blasting low-disturbance fine-repair was retained after blasting, and that local over-excavation met the engineering quality control requirements.
[0049] The parameters determined through the trial construction section shall be used as the initial construction parameters for construction sections with the same or similar geological conditions.
[0050] S2. Using a reserved position higher than the final excavation control surface of the rock as the target for mechanical initial excavation, perform mechanical initial excavation on the trench rock, measure the actual rock surface after mechanical initial excavation, and determine the local remaining rock layer thickness of the actual rock surface relative to the final excavation control surface of the rock. During the initial mechanical excavation, the final rock excavation control surface is not directly used as the endpoint of the large-scale mechanical rough excavation. Instead, a reserved position higher than the final rock excavation control surface is used as the target for the initial mechanical excavation.
[0051] Assume the initial excavation thickness is... If the unit is meters, then the initial mechanical excavation target elevation at a certain location is... Represented as: ; The initial excavation thickness is determined based on the control precision of the mechanical equipment, the integrity of the rock mass, and on-site construction experience. For example, 0.20 to 0.30 m can be used as an initial reference value.
[0052] The target elevation for the initial mechanical excavation is a construction control target. The actual rock surface after the initial mechanical excavation is not required to be exactly equal to this elevation everywhere. Instead, the actual measured rock surface on site will be used as the basis for subsequent construction control.
[0053] After the initial mechanical excavation is completed, multiple measuring points are set in the longitudinal and transverse directions of the trench.
[0054] Let the first The actual rock surface elevation after mechanical initial excavation at each measuring point is: The final excavation control elevation for the corresponding rock location is... The local remaining rock layer thickness at that measuring point is... Determined according to the following formula: ; In the formula: For the first The local remaining rock layer thickness at each measuring point, in meters; For the first The actual rock surface elevation after mechanical initial excavation at each measuring point is expressed in meters. For the first The final control elevation of the rock excavation corresponding to each measuring point is in meters.
[0055] when When this occurs, it indicates that there are still rock layers at that location that need to be removed; when When this time, it indicates that the final rock excavation control surface has been reached at that location; when When this occurs, it indicates that the actual rock surface at that location is already lower than the final excavation control surface, which is a local over-excavation location, and rock breaking treatment will no longer be carried out there.
[0056] The distribution of remaining rock layer thickness is established based on the location of each measuring point and the local remaining rock layer thickness to characterize the spatial variation of the remaining rock layer thickness after mechanical initial excavation within the trench area.
[0057] For the area where blasting is planned, let the maximum local remaining rock layer thickness in that area be... The minimum local remaining rock layer thickness is The allowed group difference is .
[0058] when: ; At that time, the area is designated as a blasting sub-region.
[0059] when: ; Then, the area is further divided into multiple blasting sub-zones, so that the local remaining rock layer thickness variation in each blasting sub-zone is not greater than the allowable grouping difference.
[0060] in, This represents the allowable variation in the thickness of the remaining rock strata within the same blasting sub-zone, expressed in meters (m). Its value is determined based on the drilling equipment's depth adjustment capability, the requirements for fine-tuning protective layer control, and the results of the test construction section.
[0061] The input for this step is the final rock excavation control face established in step S1 and the pre-reserved requirements for mechanical initial excavation.
[0062] This step outputs the local remaining rock layer thickness at each location, the distribution of remaining rock layer thickness, and, if necessary, the blasting sub-zones obtained.
[0063] S3. Rock breaking is no longer performed in areas where the thickness of the remaining rock layer is less than or equal to 0. In areas where the thickness of the remaining rock layer is greater than 0, the areas for direct non-blasting treatment and controlled blasting treatment are determined based on the thickness of the remaining rock layer. In the controlled blasting area, a fine-repair protective layer is set above the final rock excavation control surface, and the thickness of the local target blasting removal is determined based on the thickness of the remaining rock layer and the thickness of the fine-repair protective layer. for: ; At that location, rock breaking treatment will no longer be carried out.
[0064] for: ; The location will be used to further determine whether direct non-blasting or controlled blasting should be adopted.
[0065] Let the switching thickness between direct non-blasting treatment and controlled blasting be . The unit is meters (m). The initial reference value can be determined based on rock strength, construction equipment capacity, construction efficiency, and the results of test sections. For example, 0.20m can be used as an initial reference value.
[0066] when: ; At that time, the corresponding area will be designated as the direct non-explosive treatment area.
[0067] when: ; At that time, the corresponding area is designated as a candidate controlled blasting area, and the fine-tuning protective layer is further determined and the feasibility of blasting is verified.
[0068] For the For each candidate controlled blasting sub-zone, the thickness of the fine-finish protective layer is determined based on rock strength, weathering grade, and degree of fracture development. .
[0069] When similar blasting results already exist in a construction section, the blasting results should be used to... Adjustments will be made.
[0070] Preferably: ; Based on the local residual rock layer thickness distribution and the thickness of the fine-tuned protective layer in the candidate controlled blasting sub-zone Determine the target blasting removal thickness at the corresponding location: ; In the formula: The thickness removed by blasting at the corresponding target location, in meters; This represents the local remaining rock layer thickness at the corresponding location, in meters (m). The thickness of the fine-finish protective layer in the blasting sub-zone is given in meters (m).
[0071] To determine whether there is still sufficient space to meet the requirements for drilling, charging, and plugging after deducting the finishing protective layer, the minimum feasible borehole depth needs to be determined. : ; In the formula: This is the minimum allowable length of the bottom buffer section, in meters (m). The minimum allowable length of the orifice blockage section, in meters; The minimum effective charge length, measured in meters, is required to meet the minimum controllable charge quantity and reliable detonation requirements. The minimum feasible borehole depth corresponding to the adopted drilling and charging structure, in meters.
[0072] The above parameters are determined based on the actual borehole diameter, blasting materials, charge structure, plugging requirements, and the results of the test construction section.
[0073] For candidate controlled blasting areas, when the target blasting removal thickness at the corresponding location satisfies: ; At that time, the corresponding area will be designated as the controlled blasting zone.
[0074] when: ; At that time, the corresponding location will be incorporated into the direct non-blasting treatment area, instead of forcibly carrying out blasting by increasing the depth of the blast hole and entering the fine-maintenance protective layer.
[0075] Therefore, this step forms a processing relationship of "remaining rock layer thickness distribution - regional construction method classification - determination of fine protection layer - determination of target blasting removal thickness - judgment of blasting feasibility".
[0076] This step determines the regional construction method based on the distribution of the remaining rock layer thickness. It does not use the blasting hole locations that have not yet been formally determined for hole-by-hole calculation in this step.
[0077] This step outputs the direct non-blasting treatment area, the controlled blasting area, the thickness of the fine-tuning protective layer, and the distribution of the target blasting removal thickness.
[0078] S4. Arrange blasting holes in the controlled blasting area, and determine the drilling depth of the corresponding blasting hole according to the local target blasting removal thickness at each blasting hole position, so that the bottom of the blasting hole is located at or above the upper boundary of the fine-finishing protective layer. According to the The hole spacing was determined based on the target blasting removal thickness distribution, rock condition, and results of the test construction section for each blasting sub-zone. and row spacing .
[0079] like Figure 3 As shown, the controlled blasting area can be divided into a first blasting sub-area 11 and a second blasting sub-area 12 according to the variation in the thickness of the remaining rock strata. A blasting sub-area boundary 10 is formed between adjacent blasting sub-areas, and each blasting hole 6 is arranged within the trench boundary 9. The horizontal spacing between adjacent blasting holes 6 within a blasting sub-zone is the hole spacing. The longitudinal spacing is the row spacing. For locations near the trench boundary 9, the blasting sub-zone boundary 10, or obvious cracks 13, the corresponding blasting holes 6 can be adjusted specifically based on the results of the test construction section during subsequent charge design.
[0080] The official values for hole spacing and row spacing are verified by the degree of rock fragmentation, the continuity of the fine protective layer, and the local over-excavation in the test construction section, and fixed and uniform empirical values are not adopted.
[0081] According to the hole spacing and row spacing Determine the location of each blasting hole.
[0082] After determining the location of the blasting holes, the thickness distribution of the remaining rock strata established in step S2 is used to obtain the first... The first explosive sub-zone The local remaining rock layer thickness at the location of each blast hole .
[0083] like Figure 2 As shown, the actual rock surface 5 after mechanical excavation undulates along the pipeline axis, and the thickness of the remaining rock layer at different blasting hole 6 locations varies. There are differences. (The first...) The thickness of the fine-tuned protective layer in each blasting sub-zone is 3. The rock strata located between the actual rock surface 5 after mechanical initial excavation and the upper boundary of the fine-repair protective layer 3 constitute the target blasting removal layer 4, which is in the first The thickness of the local target blasting removal at the 6th blasting hole position is [missing information]. The drilling depth of each blast hole 6 was determined based on the thickness of the material removed by the blasting of the local target. This ensures that the bottom of each blasting hole 6 is located at or above the upper boundary of the finishing protective layer 3.
[0084] Corresponding local target blasting removal thickness Determined according to the following formula: ; In the formula: For the first The first explosive sub-zone The local target blasting removal thickness at each blasting hole location, in meters; This represents the local remaining rock layer thickness at the location of the blast hole, in meters. For the first The thickness of the fine-tuning protective layer in each blasting sub-zone is measured in meters (m).
[0085] In this embodiment, the blasting holes are drilled vertically downwards from the actual rock surface after the initial mechanical excavation. The thickness of the remaining local rock layer, the target blasting removal thickness, and the thickness of the finishing protective layer are all determined vertically. The first explosive sub-zone Drilling depth of each blast hole Not greater than This ensures that the bottom of the hole is located at or above the upper boundary of the finishing protective layer.
[0086] The blasting hole is constructed with a bottom buffer section, a charging section, and a hole-mouth plugging section arranged sequentially from the bottom to the opening. The length of the bottom buffer section is... and the length of the orifice blockage section Each satisfies , Effective charge length according to Calculate and satisfy The unit for all the lengths mentioned above is meters (m). The meaning and determination basis of the minimum length are the same as in step S3.
[0087] When the drilling equipment can continuously adjust the hole depth and the length of each section within the hole meets the above requirements, it is preferable to choose... When the drilling equipment can only adjust the depth in stages, the holes are grouped according to the thickness of the local target blasting at the hole location. The depth of each group of holes shall not exceed the minimum local target blasting thickness of the group, and the length of each section inside the hole shall be checked for each hole in the group.
[0088] If the above relationships are not met, the borehole pattern, zoning, drilling depth, or charge structure should be adjusted and rechecked. If the adjustments still fail to meet the requirements, the corresponding local area should be incorporated into the direct non-blasting treatment area. Each officially determined borehole should also meet the charge feasibility check in step S5, and any adjustments must not allow the bottom of the borehole to enter the finishing protective layer.
[0089] The inputs for this step are the controlled blasting area, the target blasting removal thickness distribution, the rock mass condition, and the results of the test construction section determined in step S3.
[0090] This step outputs the actual blasting hole positions, hole spacing, row spacing, drilling depth per hole, and effective charge length for each blasting hole.
[0091] S5. Determine the charging parameters based on the hole position and drilling depth, and implement controlled blasting after drilling, charging and plugging are completed. The first section was determined through trial construction. The explosive consumption per unit area used in each blasting sub-zone The unit is kg / m 3 .
[0092] For the The first explosive sub-zone One blasting hole, benchmark theoretical single-hole charge amount Determined according to the following formula: ; In the formula: The baseline theoretical single-hole charge amount is expressed in kg. The explosive consumption per unit area, determined through the trial construction section, is expressed in kg / m³. 3 ; The hole spacing is in meters (m). This refers to the row spacing, in meters (m). The thickness removed by blasting of a local target is measured in meters (m).
[0093] For ordinary blasting holes within the blasting sub-zone, the designed single-hole charge quantity is:
[0094] For blasting holes located near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks, the designed single-hole charge is: ; in: ; In the formula: For the first The first explosive sub-zone The design charge per blast hole, in kg, is used for the actual charge of the blast hole and for verifying the feasibility of the charge. The charge reduction factor for edge blasting holes is dimensionless and its value is determined based on the degree of rock fragmentation and local over-excavation in the test construction section near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks.
[0095] Let the minimum controllable single-hole charge of the explosive device be... The unit is kg; the maximum allowable effective linear charge density for the charge structure is If the unit is kg / m, then the design single-hole charge amount should meet the following requirements: ; in, This represents the maximum allowable charge amount for the blast hole under the current effective charge length and charge structure conditions, expressed in kg.
[0096] When the design charge per hole does not meet the above relationship, adjust at least one of the following: hole spacing, row spacing, blasting sub-zone division, drilling depth, charge structure, or construction method, and re-verify the feasibility of the charge.
[0097] After verification, drilling is completed according to the determined blasting hole positions and drilling depths. The charge is completed according to the designed single-hole charge amount, and the hole opening is plugged according to the plugging requirements. Then, controlled blasting is carried out according to the approved blasting construction plan.
[0098] This step requires input including blasting hole location, hole spacing, row spacing, local target blasting removal thickness of each hole, drilling depth, effective charge length, rock mass condition, and test section results.
[0099] S6. Remove the loose rock formed by controlled blasting. Based on the rock surface elevation measurement results, refine the remaining finishing layer after blasting and the rock in the direct non-blasting treatment area that is higher than the final excavation control surface of the rock layer by layer using a non-blasting method. Stop rock breaking at the position that reaches the final excavation control surface of the rock layer. For local positions that are lower than the final excavation control surface of the rock layer after mechanical initial excavation, controlled blasting or layer-by-layer finishing, restore them to the final excavation control surface of the rock layer before laying the design sand cushion layer. The leveling compensation layer or repair layer formed by restoration is not included in the thickness of the design sand cushion layer.
[0100] After the controlled blasting is completed, the loose rocks formed by the blasting are first removed.
[0101] Multiple post-blast testing points were set on the actual rock surface after slag removal.
[0102] Let the first The first explosive sub-zone The actual rock surface elevation at each post-explosion measuring point is: The final excavation control elevation for the corresponding rock location is... The actual remaining finishing layer thickness for: ; In the formula: This represents the actual remaining thickness of the finishing layer after the explosion, in meters (m). This is the actual rock surface elevation after blasting and debris removal, in meters. The final control elevation for rock excavation at the corresponding location is given in meters (m).
[0103] when At this time, it indicates that a finishing layer is still retained; when When the time is reached, it indicates that the final rock excavation control surface has been reached; when When this occurs, it indicates that over-excavation by blasting has occurred at that location.
[0104] Let the first Each explosive sub-zone is set up The average remaining thickness is obtained from each post-explosion measurement point. Determined according to the following formula: ; In the formula, For the first The average remaining finishing layer thickness of each blasting sub-zone, in meters.
[0105] Let the number of over-excavation measuring points where the actual remaining finishing layer thickness is less than 0 be... The proportion of over-excavation measuring points for: ; In the formula, The percentage of over-excavation measurement points is dimensionless.
[0106] Maximum over-drilling depth Determined according to the following formula: ; In the formula, For the first The maximum over-excavation depth of each blasting sub-zone is expressed in meters (m).
[0107] The average remaining thickness is used to evaluate the overall strength of the blasting effect; the over-excavation measurement point ratio is used to reflect the range of over-excavation; and the maximum over-excavation depth is used to evaluate the degree of over-excavation at the most unfavorable local location.
[0108] After the post-blast measurement is completed, the remaining finishing layers after the blast and the areas to be directly treated without blasting, as determined in step S3, are finished layer by layer using a non-blasting method.
[0109] The non-explosive method can employ pneumatic picks, small hydraulic splitting equipment, low-impact crushing equipment, or other low-disturbance rock breaking equipment capable of controlling the local rock removal depth.
[0110] Let the actual rock surface elevation after refinement be... The elevation deviation of the refined rock surface relative to the final excavation control surface is... for: ; when At that time, continue non-explosive, layer-by-layer fine-tuning of the location; when Stop rock breaking at that location; when At that time, the rock will no longer be broken downwards, and the local depression will be restored to the final rock excavation control surface according to the base restoration steps described later; For subsequent blasting sub-zones, the current blasting sub-zone providing feedback is used as the benchmark for uniaxial compressive strength comparison.
[0111] Let the uniaxial compressive strength of the current blasting sub-region be... The uniaxial compressive strength of the blasting sub-zone in subsequent construction is Both were obtained using the same experimental method and the same data set, and the units are both... The relative difference in uniaxial compressive strength is based on calculate.
[0112] When the weathering grade and fracture development grade of the subsequent blasting sub-zone are the same as those of the current blasting sub-zone, and the relative difference is no greater than [value missing], At that time, based on the average remaining thickness of the current blasting sub-zone, the proportion of over-excavation measuring points, and the maximum over-excavation depth, at least one of the following should be corrected for the thickness of the fine protective layer, the unit consumption of explosives, the hole spacing, the row spacing, and the local drilling depth of the subsequent blasting sub-zone:
[0113] For construction sections where geological conditions have changed significantly or do not meet the above-mentioned similar conditions, the feedback results from the previous blasting sub-area are not directly used. Instead, the initial parameters are re-determined based on the actual rock mass condition and the test construction section.
[0114] Based on the average remaining thickness, over-excavation measurement point ratio, and maximum over-excavation depth obtained from the current blasting sub-region, at least one of the following parameters for subsequent similar blasting sub-regions shall be corrected: Refine the thickness of the protective layer; Explosive consumption per unit; Hole spacing; Row spacing; Local drilling depth.
[0115] Among them, the correction of the thickness of the fine protective layer is used to change the thickness of the rock layer retained between the blasting zone and the final rock excavation control surface; the correction of the explosive consumption is used to adjust the blasting energy corresponding to the target rock per unit volume; the correction of the hole spacing and row spacing is used to change the control rock range corresponding to each blasting hole; and the correction of the local drilling depth is used to control the positional relationship between the bottom of the local blasting hole and the fine protective layer.
[0116] After feedback correction of the hole spacing and row spacing, the hole mesh parameters of the previous blasting sub-area are still re-verified based on the target blasting removal thickness distribution, rock mass condition, and test construction section results of the subsequent blasting sub-area, rather than directly and mechanically applying the hole mesh parameters of the previous blasting sub-area.
[0117] Let the maximum over-excavation control value be... The unit is m, and its value is determined according to the project's quality control requirements for the maximum allowable over-excavation depth of the rock trench base.
[0118] when: ; Even if the average remaining thickness indicates that the overall effect of the current blasting is weak, the explosive consumption per unit area should not be increased when correcting parameters for subsequent similar blasting sub-regions. Instead, at least one of the following measures should be adopted: Increase the thickness of the finishing protective layer; Reduce the amount of explosive charge in blast holes near the trench sidewalls, the edge of the blasting sub-area, or obvious cracks; Reduce local drilling depth; Encrypted local measurements and further subdivision of blasting sub-regions.
[0119] Therefore, the maximum over-excavation depth is used as the priority constraint for the most unfavorable local state, so as to avoid the serious local over-excavation being masked by evaluating the blasting effect only based on the average remaining thickness.
[0120] The above feedback process forms a construction feedback relationship of "current blasting sub-zone construction - post-blast status measurement - blasting effect evaluation - subsequent similar blasting sub-zone parameter correction".
[0121] For local areas below the final excavation control surface of the rock formed during mechanical initial excavation, controlled blasting, or low-disturbance finishing, the base should be restored before the sand cushion layer is laid.
[0122] For areas of shallow over-excavation, layered compaction with graded materials permitted by the design or materials compatible with the subbase system can be used for restoration; for areas of deeper local over-excavation or local rock surface fracture, repair materials permitted by the design can be used for restoration.
[0123] Restored base elevation satisfy: ; The leveling compensation layer or repair layer used to restore local over-excavation is not included in the design sand cushion layer thickness.
[0124] Then, the designed thickness is laid on the restored base. The sand cushion layer.
[0125] Elevation of top surface of sand cushion layer for: ; because: ; as well as: ; therefore: ; Therefore, local over-excavation of rock will not further affect the design elevation of the outer bottom of the pipeline by changing the thickness of the design sand cushion layer.
[0126] After the sand cushion layer is completed and accepted, the pipeline is installed, and the elevation of the inner bottom or outer bottom of the pipeline is re-measured along the pipeline axis to confirm that the longitudinal slope of the pipeline meets the design requirements and there is no reverse slope.
[0127] The following hypothetical numerical values illustrate the methods for elevation conversion, hole depth determination, and post-blast measurement parameters. The listed values are not intended as actual engineering test results, nor do they imply that they can be directly applied to construction under specific rock mass conditions; the actual borehole network, lengths of each section within the borehole, and charge parameters are determined based on the aforementioned test construction sections and feasibility verification.
[0128] A gravity-flow sewage pipeline traverses a section of moderately weathered granite. The pipeline is DN400, and the design longitudinal slope is: ; The design elevation of the bottom of the pipe at a certain control section is: ; The vertical distance between the lowest point of the inner bottom of the pipe and the lowest point of the outer wall of the pipe is: ; The thickness of the compacted sand cushion layer is: ; This yields the design elevation of the pipe's outer bottom: ; The final control elevation for rock excavation is: ; Pre-excavation thickness for mechanical excavation: ; The target elevation for the initial mechanical excavation is: ; To illustrate the regional classification of construction methods, it is assumed that the measurement results after mechanical initial excavation are as follows: the local remaining rock layer thickness of construction unit U1 is mainly 0.12 to 0.18 m, and the local remaining rock layer thickness of construction unit U2 is mainly 0.42 to 0.50 m.
[0129] Initial switching thickness setting: ; Therefore, U1 was directly finished using a non-explosive, low-disturbance method.
[0130] To illustrate the zoning process within the same construction unit, it is assumed that U2 includes two candidate blasting sub-zones, U2-1 and U2-2, with local residual rock layer thicknesses of 0.42–0.45 m and 0.47–0.50 m, respectively, and the thickness variation in each zone satisfies the allowable grouping difference determined in step S2. The following examples of hole depths assume that the corresponding location has already passed the area feasibility assessment in step S3; after determining the hole depth, the length verification of each segment within the hole in step S4 and the charge feasibility verification in step S5 are still required before controlled blasting can be implemented.
[0131] Based on the integrity of the rock mass and the development of fractures, the initial finishing protective layer thickness for both blasting sub-zones is taken as: ; After the blasting holes are officially determined, taking a certain blasting hole location within U2-1 as an example, the local remaining rock layer thickness at that location is: ; The thickness of the target removed by blasting at this hole location is: ; When the drilling equipment can continuously adjust the hole depth, the drilling depth of this hole is taken as: ; Another blast hole is numbered The thickness of the remaining rock layer at the borehole location is The thickness of the local target removed by blasting is... Under the condition that the lengths of each section within the borehole and the feasibility of the charge are verified as described above, the corresponding borehole depth is taken as... .
[0132] Therefore, the drilling depth of different holes in the same blasting sub-area is determined according to the actual local remaining rock layer thickness, so that the bottom of each blasting hole does not enter the fine protection layer.
[0133] U2-1 hole spacing and row spacing The determination is based on the target blasting removal thickness distribution, rock mass condition, and the results of the test construction section.
[0134] For any ordinary blast hole, the corresponding controlling rock volume is approximately: ; in, The unit is m 3 .
[0135] Let the explosive consumption per unit area be determined in the test construction section. The baseline theoretical single-hole charge capacity is: ; For internal conventional blast holes: ; For blast holes located near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks: ; The designed single-hole charge capacity was verified as follows: ; Only blasting holes that meet the above requirements will be charged according to the corresponding design parameters; if they do not meet the requirements, the hole pattern, drilling depth, charging structure, or local construction method will be readjusted.
[0136] To illustrate the calculation of the post-blast evaluation index, it is assumed that the remaining finishing layer thicknesses at the eight measuring points after slag removal from U2-1 are 0.074 m, 0.081 m, 0.078 m, 0.086 m, 0.069 m, 0.083 m, 0.077 m, and 0.080 m, respectively.
[0137] The average remaining finishing layer thickness is: ; The calculation yielded: ; All 8 measuring points meet the following requirements: ; Therefore, the proportion of over-excavation measuring points is: ; The maximum over-digging depth is: ; Based on the above assumed data, the average remaining thickness of the finishing layer at the eight measuring points is 0.0785 m, which is not lower than the final rock excavation control surface. The over-excavation ratio at the measuring points is 0, and the maximum over-excavation depth calculated based on these measuring points is 0. The above results only illustrate the remaining thickness and corresponding statistical indicators of the listed measuring points and cannot prove that the finishing protective layer of the entire blasting sub-area is continuous or that there is no over-excavation at any location. The actual condition of the entire area should be determined in conjunction with on-site rock surface inspection and corresponding measurement results.
[0138] The remaining finishing layers were then removed layer by layer using a non-explosive method.
[0139] If the deviation of the actual rock surface after final finishing at a certain location from the final excavation control surface is: ; This indicates that the location is locally 6mm below the final excavation control surface of the rock.
[0140] Before designing the sand cushion layer, first restore this position to: ; Then, a sand cushion layer with a designed thickness of 0.150m is laid. The elevation of the top surface of the sand cushion layer is: ; The elevation is consistent with the design elevation of the outer bottom of the pipe at this cross-section.
[0141] For a blasting sub-zone within subsequent construction unit U3, U2-1, with the previously obtained data from eight post-blast measurement points, is designated as the current blasting sub-zone. The weathering grade, fracture development grade, and uniaxial compressive strength of this subsequent blasting sub-zone are compared with those of U2-1 according to the aforementioned similarity judgment criteria. If the criteria are met, the average remaining finishing layer thickness of U2-1 (0.0785 m), the over-excavation measurement point ratio (0), and the maximum over-excavation depth calculated based on this set of measurement points (0) are used as feedback evaluation inputs to determine whether the finishing protective layer thickness, explosive consumption per unit, hole spacing, row spacing, or local drilling depth of this subsequent blasting sub-zone needs to be corrected. If post-blast measurement data for U2-2 is not obtained, the indicators of U2-1 are not directly used as the summary indicators for the entire U2.
[0142] If local over-excavation occurs in a subsequent blasting sub-area, and its maximum over-excavation depth exceeds the maximum over-excavation control value determined by the project quality control requirements... Even if the average remaining finishing layer of the blasting sub-zone is still too thick, the explosive consumption per unit of the next similar blasting sub-zone should not be increased. Instead, the risk of local over-excavation should be controlled by increasing the thickness of the finishing protective layer, reducing the amount of explosive in the blasting holes near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks, reducing the local drilling depth, or increasing the density of local measurements and subdividing the blasting sub-zone.
[0143] Through the above construction process, a continuous data and construction control relationship is formed between the pipeline design elevation, the final rock excavation control surface, the actual remaining rock strata state after mechanical initial excavation, the fine protection layer, the depth of each blasting hole, the design charge quantity, the actual remaining fine protection layer after blasting, and the construction parameters of subsequent similar sections, thereby realizing the staged and precise excavation of the rock strata trench for gravity flow sewage pipelines.
[0144] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A method of precision trenching of a rock formation for a gravity flow sewer pipeline, characterised by, Includes the following steps: S1. Establish the final rock excavation control surface that varies along the pipeline axis based on the design elevation of the outer bottom of the pipeline and the design thickness of the sand cushion layer. S2. Using a reserved position higher than the final excavation control surface of the rock as the target for mechanical initial excavation, perform mechanical initial excavation on the trench rock, measure the actual rock surface after mechanical initial excavation, and determine the local remaining rock layer thickness of the actual rock surface relative to the final excavation control surface of the rock. S3. Rock breaking is no longer performed in areas where the thickness of the remaining rock layer is less than or equal to 0. In areas where the thickness of the remaining rock layer is greater than 0, the areas for direct non-blasting treatment and controlled blasting treatment are determined based on the thickness of the remaining rock layer. In the controlled blasting area, a fine-repair protective layer is set above the final rock excavation control surface, and the thickness of the local target blasting removal is determined based on the thickness of the remaining rock layer and the thickness of the fine-repair protective layer. S4. Arrange blasting holes in the controlled blasting area, and determine the drilling depth of the corresponding blasting hole according to the local target blasting removal thickness at each blasting hole position, so that the bottom of the blasting hole is located at or above the upper boundary of the fine-finishing protective layer. S5. Determine the charging parameters based on the hole position and drilling depth, and implement controlled blasting after drilling, charging and plugging are completed. S6. Remove the loose rock formed by controlled blasting. Based on the rock surface elevation measurement results, refine the remaining finishing layer after blasting and the rock in the direct non-blasting treatment area that is higher than the final excavation control surface of the rock layer by layer using a non-blasting method. Stop rock breaking at the position that reaches the final excavation control surface of the rock layer. For local positions that are lower than the final excavation control surface of the rock layer after mechanical initial excavation, controlled blasting or layer-by-layer finishing, restore them to the final excavation control surface of the rock layer before laying the design sand cushion layer. The leveling compensation layer or repair layer formed by restoration is not included in the thickness of the design sand cushion layer.
2. The method of precision excavation of rock strata trenches for gravity flow sewer pipelines according to claim 1, characterized in that, Step S1 specifically includes: When the design drawings provide the design elevation of the inner bottom of the pipe At that time, the design elevation of the outer bottom of the pipe Determined according to the following formula: ; in, It is the vertical distance between the lowest point of the inner bottom of the pipe and the lowest point of the outer wall of the pipe; Final rock excavation control elevation Determined according to the following formula: ; in, This refers to the design thickness of the compacted sand cushion layer; The longitudinal design slope is Within the slope section, the design elevation of the outer bottom of the pipeline is determined according to the following formula: ; in, The design elevation of the outer bottom of the pipe at the starting point of the slope section is given. It is the distance from the starting point of the slope section along the direction of water flow.
3. The method for precise excavation of rock strata trenches for gravity flow sewage pipelines according to claim 1, characterized in that, The rock strata condition investigation step is included before step S2: The lithology, uniaxial compressive strength, weathering grade, and fracture development grade of the rocks within the trench area are obtained, and the trench is divided into multiple construction units along the pipeline axis based on the changes in lithology, weathering grade, and fracture development grade.
4. The method for precise excavation and construction of trenches in rock strata for gravity-flow sewage pipelines according to claim 1, characterized in that, Step S2 specifically includes: Multiple measuring points were set after the initial mechanical excavation. Local residual rock layer thickness at each measuring point Determined according to the following formula: ; in, For the first The rock surface elevation at each measuring point after initial mechanical excavation The final excavation control elevation for the corresponding rock location; Establish the distribution of remaining rock layer thickness based on the location of each measuring point and the local remaining rock layer thickness; For an area to be blasted, when the difference between the maximum and minimum local remaining rock layer thickness is not greater than the allowable grouping difference, the area is designated as a blasting sub-area; when the difference is greater than the allowable grouping difference, the area is divided into multiple blasting sub-areas, such that the variation in local remaining rock layer thickness within each blasting sub-area is not greater than the allowable grouping difference.
5. The method for precise excavation of rock strata trenches for gravity-flow sewage pipelines according to claim 4, characterized in that, Step S3 specifically includes: Let the switching thickness between direct non-blasting treatment and controlled blasting be . The minimum feasible borehole depth corresponding to the drilling and charging structure adopted. for: ; in, This is the minimum allowable length of the bottom buffer section. The minimum allowable length of the orifice blocking section. The minimum effective charge length is required to meet the requirements of minimum controllable charge quantity and reliable detonation. When the thickness of the local remaining rock layer is greater than 0 and not greater than When this occurs, the corresponding area is designated as the direct non-explosive processing area; When the thickness of the local remaining rock layer is greater than At that time, the thickness of the refined protective layer is determined, and the target blasting removal thickness is determined based on the difference between the local remaining rock layer thickness and the refined protective layer thickness; when the target blasting removal thickness is not less than When the target blasting removal thickness is less than 1, the corresponding area is determined as the controlled blasting area; when ... At that time, the corresponding area is determined as the direct non-explosive processing area.
6. The method for precise excavation of rock strata trenches for gravity-flow sewage pipelines according to claim 5, characterized in that, In step S3: For the first time, the controlled blasting was determined to be carried out. For each blasting sub-zone, the thickness of the fine-finish protective layer is determined based on the rock strength, weathering grade, and degree of fracture development. And when there are blasting results in existing similar construction sections, the thickness of the fine-finish protective layer is adjusted according to the blasting results. Adjustments were made to the thickness of the refined protective layer. The range is 0.05–0.10 m.
7. The method for precise excavation of rock strata trenches for gravity-flow sewage pipelines according to claim 6, characterized in that, In step S4: According to the Distribution of remaining rock strata thickness and thickness of fine-finished protective layer in each blasting sub-zone Determine the target blasting removal thickness distribution, and determine the hole spacing based on the target blasting removal thickness distribution, rock condition, and test section results. and row spacing According to the hole spacing and row spacing Determine the location of each blasting hole.
8. The method for precise excavation of rock strata trenches for gravity-flow sewage pipelines according to claim 7, characterized in that, In step S4: No. Within the first explosive sub-zone Each blasting hole is drilled vertically downwards from the actual rock surface after the initial mechanical excavation. The local target blasting removal thickness at the hole location is calculated according to... It is confirmed that, among them, This represents the local remaining rock layer thickness at the borehole location. To refine the thickness of the protective layer; No. Drilling depth of each blast hole satisfy This ensures that the bottom of the blasting hole does not enter the finishing protective layer; the blasting hole is sequentially provided with a bottom buffer section, a charging section, and a hole opening plugging section from the bottom to the opening, with the bottom buffer section having a length of... Not less than Length of the blocked section at the orifice Not less than Effective charge length according to Determine and satisfy ; For blasting holes that cannot simultaneously meet the above relationships, the hole pattern, zoning, drilling depth, or charge structure should be adjusted and rechecked. If the adjustment still fails to meet the requirements, the corresponding local area should be incorporated into the direct non-blasting treatment area, and the charge space requirements should not be met by drilling into the fine-tune protective layer.
9. The method for precise excavation of rock strata trenches for gravity-flow sewage pipelines according to claim 8, characterized in that, In step S5: For the Within the first explosive sub-zone For each blast hole, the theoretical single-hole charge amount is determined according to the following formula. : ; in, The unit consumption of explosives was determined through the test construction section; For internal conventional blasting holes, the design single-hole charge amount for: ; For edge blasting holes located near the trench sidewall, the edge of the blasting sub-zone, or obvious fracture locations, the design single-hole charge amount Determined according to the following formula: ; in, Let be the charge reduction factor determined based on the results of the test construction section, and: ; Let the minimum controllable single-hole charge of the explosive device be... The maximum effective linear charge density allowed by the charge structure is The designed single-hole charge amount satisfies: ; When the designed single-hole charge amount does not meet the above relationship, adjust the hole spacing, row spacing, blasting sub-zone division, drilling depth, charge structure or construction method, and re-verify the feasibility of the charge.
10. The method for precise excavation of rock strata trenches for gravity flow sewage pipelines according to claim 4, characterized in that, In step S6, after removing the loose rock formed by the controlled blasting and before performing non-blasting layer-by-layer finishing of the remaining finishing layer after blasting, the step also includes a blasting result measurement and feedback correction step: Multiple post-blasting measuring points are set on the actual rock surface after slag removal in the current blasting sub-area. The actual remaining finishing layer thickness is determined based on the actual rock surface elevation of each post-blasting measuring point and the corresponding final excavation control elevation of the rock. The average remaining thickness, over-excavation measuring point ratio, and maximum over-excavation depth of the current blasting sub-area are determined based on the actual remaining finishing layer thickness of each post-blasting measuring point. Let the uniaxial compressive strength of the current blasting sub-region be... The uniaxial compressive strength of the blasting sub-zone in subsequent construction is Both were obtained using the same test method and the same value caliber; when the weathering grade and fracture development grade of the subsequent blasting sub-zone are the same as those of the current blasting sub-zone, and the conditions are met... At that time, based on the average remaining thickness, the proportion of over-excavation measuring points, and the maximum over-excavation depth, at least one of the following should be corrected for the thickness of the fine protective layer, the unit consumption of explosives, the hole spacing, the row spacing, and the local drilling depth of the blasting sub-area in the subsequent construction: When the maximum over-excavation depth exceeds the preset maximum over-excavation control value, the explosive consumption per unit should not be increased when correcting the parameters of the blasting sub-zone for subsequent construction. At least one of the following measures should be adopted: increasing the thickness of the fine-tune protective layer, reducing the charge of blasting holes near the trench sidewall, the edge of the blasting sub-zone, or obvious cracks, reducing the local drilling depth, and increasing the density of local measurements and zoning.