A method for atmospheric pressure open-cell reinforcement construction of shield tunnels in deeply buried gravel strata.

By using segmented rotary drilling pile technology to form a continuous water-stop curtain in deeply buried gravel strata, the permeability and self-stability problems of shield tunneling under normal pressure in deeply buried gravel strata were solved, achieving efficient, safe and economical construction results and improving the efficiency of shield tunneling machine cutterhead replacement.

CN123109682APending Publication Date: 2026-11-17GUANGDONG NO 2 HYDROPOWER ENGINEERING COMPANY LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611277210.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-21
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The shield tunneling in deep gravel strata faces challenges such as extremely high permeability, poor self-stabilization, and high construction risks. In particular, under the interference of high-pressure water and large-diameter boulders, conventional reinforcement techniques are difficult to form a continuous water-stop curtain, and there are also potential construction quality risks and high costs.

Method used

The segmented rotary drilling pile technology is adopted, including deep well dewatering, steel casing installation, segmented rotary drilling pile holes and casting of rotary drilling piles, forming segmented heterogeneous pile bodies. Underwater air bubbles are used to mix lightweight soil and high-strength underwater concrete to form a continuous water-stop curtain. Combined with the interlocking joints of the rotary drilling piles, a water-stop zone is formed, which is suitable for the high permeability of gravel strata and large-diameter boulders.

Benefits of technology

It achieves effective water-stopping and soil-retaining in deeply buried gravel strata, adapts to highly permeable water-flow strata, ensures construction safety and economy, reduces construction risks and costs, and improves the controllability of construction quality and the efficiency of shield machine cutterhead replacement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109682A_ABST
    Figure CN123109682A_ABST
Patent Text Reader

Abstract

This invention, entitled "A Method for Under-Pressure Opening and Reinforcement Construction of Shield Tunneling Machines in Deeply Buried Gravelly Soil," belongs to the field of shield tunneling technology. The technical problem to be solved is the difficulty of under-pressure opening of shield tunnels in deeply buried gravelly soil. The key technical solution is a method for under-pressure opening and reinforcement construction of shield tunnels in deeply buried gravelly soil, comprising the following steps: construction preparation and surveying; deep well dewatering; steel casing installation; segmented rotary drilling of pile holes; segmented casting of rotary drilling piles to form segmented heterogeneous pile bodies; curing and inspection. By utilizing the segmented heterogeneous pile bodies of the rotary drilling piles, after ensuring the water-stop curtain can stably support and isolate groundwater, the lower-strength shield tunneling section allows the shield machine to advance rapidly within the water-stop curtain, significantly improving the efficiency of shield machine opening and cutterhead replacement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel boring machine (TBM) technology, and in particular to a method for atmospheric pressure tunneling reinforcement of TBMs in deeply buried gravel strata. Background Technology

[0002] With the increasing density of urban shield tunnel construction, tool wear, mud cake formation, and frequent failures occur in complex water-rich sand layers and fractured weathered rock strata. Pressurized tunneling faces high risks, high costs, and harsh working environments. Atmospheric pressure tunneling, with its advantages of high safety, convenient operation, and controllable cost, has become the mainstream maintenance process. Ground reinforcement is the core key to ensuring the stability of the tunnel face during atmospheric pressure tunneling and preventing water inrush, sand inrush, and collapse accidents, and has significant engineering application value.

[0003] Currently, commonly used reinforcement technologies in engineering can be divided into three major systems: surface reinforcement, in-tunnel pre-reinforcement, and dewatering-assisted reinforcement. Each technology has significantly different applicable geological formations and working conditions. Surface sleeve valve grouting and high-pressure jet grouting are simple to construct and economical, suitable for shallowly buried soft soil and ordinary sandy strata with open construction sites. However, their reinforcement effect on highly confined water strata is limited, and construction in densely populated urban areas is restricted. The MJS method and surface freezing reinforcement have minimal disturbance and excellent water-stopping reinforcement effects, suitable for water-rich confined sandy strata, fault fracture zones, and environmentally sensitive conditions. However, they have drawbacks such as long construction periods and high costs. For deeply buried urban underpass projects with no surface working face, in-tunnel horizontal grouting and horizontal jet grouting are more applicable and can precisely reinforce the soil in front of the tunnel face. However, due to space limitations within the tunnel, construction efficiency is lower, and reinforcement blind spots are easily created. While dewatering techniques are inexpensive, they can only be used as a supplementary method and cannot alone meet the requirements for soil self-stabilization and water-stopping under normal pressure. In engineering projects, it is necessary to consider geological conditions, burial depth, and the surrounding environment, taking into account both safety and economy to select the optimal reinforcement scheme.

[0004] The planned tunnel boring machine (TBM) opening point is located at a depth of approximately 31 meters. The tunnel strata consist of sand and gravel layers. The core construction challenge lies in reinforcing the deep gravel strata. Extremely permeable: The pores of the pebbles are interconnected, the permeability coefficient is large, and the deep dynamic water pressure is high. Ordinary cement slurry is prone to runaway over long distances and be diluted by water flow, making it difficult to form a continuous reinforced water-stop curtain.

[0005] Extremely poor self-stabilizing ability: The formation has no cohesion, and deep drilling is prone to hole collapse, diameter reduction, and sand inrush, resulting in poor hole quality, reinforcement hole position deviation, and many blind spots.

[0006] Boulder interference: Large-diameter boulders are embedded in the deep layers, causing pile breakage and stone inclusion in the mixing and jet grouting piles, resulting in poor forming quality of conventional reinforcement processes.

[0007] Construction risks are extremely high: Opening the chamber at atmospheric pressure results in no air pressure balance, and the entire process relies on the strength of the reinforced body. Defects in the reinforcement can easily lead to safety accidents such as face collapse, piping, and excessive ground settlement. Summary of the Invention

[0008] The purpose of this invention is to provide: A method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata is proposed to solve the technical problem of difficulty in atmospheric pressure opening of shield tunnels in deeply buried gravel strata.

[0009] Terminology Explanation: Unless otherwise defined, all technical terms used herein have the same meanings as commonly understood by one of ordinary skill in the art. Unless otherwise stated, all patents, patent inventions, and publications cited in this document are incorporated herein by reference in their entirety. If multiple definitions exist for terms, the definition provided in this chapter shall prevail.

[0010] It should be understood that the above brief description and the following detailed description are exemplary and for illustrative purposes only, and do not limit the subject matter of the invention in any way. In this invention, the singular is used in conjunction with the plural unless otherwise specifically stated. It should also be noted that, unless otherwise stated, the use of “or” or “or” means “and / or”. Furthermore, the use of the term “comprising” and other forms such as “including,” “containing,” and “contains” are not limiting.

[0011] In a first aspect, the present invention provides: a method for atmospheric pressure tunneling reinforcement of shield tunnels in deeply buried pebble strata, comprising the following steps: Construction preparation and surveying / layout; Deep well dewatering; Steel casing installation; Segmented rotary drilling pile holes, segmented casting of rotary drilling piles, forming segmented heterogeneous pile bodies; Maintenance and testing.

[0012] Furthermore, during construction preparation and surveying, the pile positions and water-stop curtain are planned in advance. The curtain range is: ≥3m in front of the cutterhead, ≥4m above the tunnel arch, ≥3m on both sides of the tunnel, and the pile bottom is embedded in the stable pebble layer 1.5-2.0m below the tunnel floor.

[0013] Furthermore, when installing the steel casing, a 2-4m long casing is installed on the surface to correct the center and verticality; in the deep sand and gravel section, an extended recirculating casing is used for follow-up drilling.

[0014] Furthermore, rotary drilling piles include a shield tunneling section and a bearing section. The bearing section has higher strength than the shield tunneling section. The shield tunneling section and the bearing section are different parts of the rotary drilling pile body. The shield tunneling section is used for rapid cutting and excavation by the tunnel boring machine, while the bearing section supports the shield tunneling section.

[0015] Furthermore, the length of the shield tunneling section is greater than or equal to the spacing between the shield excavation edges.

[0016] Furthermore, the length of the shield tunneling section is less than or equal to the theoretical requirement, which makes the length of the bearing section greater than or equal to the theoretical requirement.

[0017] Furthermore, the shield tunneling section uses underwater air-bubble mixed lightweight soil, while the load-bearing section uses underwater concrete with a strength ≥ C30.

[0018] Furthermore, the water-cement ratio of the underwater bubble-mixed lightweight soil is 0.54-0.77, and the 28-day compressive strength is controlled at 1.0-2.0 MPa.

[0019] Furthermore, during deep well dewatering, the bottom of the well is 2-3m lower than the bottom of the pile, and continuous dewatering is carried out 7-15 days in advance, with the water level dropping to ≥1.5m below the tunnel floor.

[0020] Furthermore, rotary drilling piles are constructed in alternating A and B sequence; adjacent B piles are constructed before the initial setting of the A pile concrete, and the cut overlap surface forms a 200-300mm interlocking waterstop.

[0021] The beneficial effects of this invention are as follows: 1. It has strong overall integrity in water-stopping and soil-retaining structures, and is suitable for gravel strata with high permeability and dynamic water flow.

[0022] Rotary drilling interlocking piles form a continuous rigid concrete closed curtain, which can completely seal the seepage channels through the pebble layer. It does not have the defects of long-distance grout leakage in sleeve valve grouting, pile body defects when encountering boulders in ordinary jet grouting piles, and insufficient grouting reinforcement depth in the tunnel. Compared with the traditional MJS method, which relies on high-pressure jet grouting to form cement soil, the high-pressure grout is easy to diffuse and lose along the gaps in the pebble in the environment of large pore pebbles and strong dynamic water. The probability of sand inclusion and leakage at the pile body is high, and it cannot form a complete water barrier. In contrast, the solid concrete structure of rotary drilling piles is not diluted or eroded by groundwater, and the water-stopping reliability is far superior to various jet grouting reinforcement methods.

[0023] 2. It is highly compatible with boulders and isolated rock formations.

[0024] Compared to the traditional MJS method, which relies on high-pressure water flow to cut the soil, it cannot effectively break and replace large-diameter boulders. Large pebbles also obstruct the diffusion of the sprayed grout, easily forming voids in the pile body and creating seepage channels, making it difficult to guarantee the integrity of the reinforcement. The rotary drilling rig with a casing drill can directly break and retrieve large boulders from the strata, forming a continuous and complete curtain without any natural weak points for seepage.

[0025] 3. Sufficient safety reserves for long-term operation in deep-buried conditions.

[0026] Compared to traditional MJS reinforced concrete, which is a cement-soil structure with significantly lower strength and stiffness than cast-in-place concrete, rotary drilling piles are prone to softening and compression deformation under long-term water immersion, and the soil at the tunnel face is easily spalled off. They can only meet short-term, short-term opening requirements and are unsuitable for the long-term cutterhead overhaul conditions of this project. Rotary drilling piles, on the other hand, have high concrete strength and overall stiffness, strong resistance to deformation under high water and soil pressure, and can support continuous multi-day pressure opening and maintenance.

[0027] 4. Lower cost, large-scale curtain wall reinforcement has significant economic advantages.

[0028] The MJS method requires extremely high investment in specialized equipment, high-pressure pipelines, and cement consumables, with a unit cost 1.8-2.5 times that of rotary drilling piles. The total cost of large-area cutterhead perimeter enclosed curtain construction is significantly higher. Rotary drilling piles use conventional rotary drilling equipment and commercial concrete, with controllable material and equipment costs. They do not require high investment in specialized machinery, resulting in a clear overall cost advantage.

[0029] 5. Construction quality is intuitive and controllable, and the reliability of testing and acceptance is high.

[0030] Compared to traditional MJS (Medium-Soil Mixed Casing), cement-soil piles are concealed in their formation, and the cavities and sand inclusions inside the gravel strata are difficult to identify through conventional testing, posing a high risk of hidden leakage. The safety hazards of opening the silo under normal pressure cannot be thoroughly investigated. Rotary drilling piles, on the other hand, allow for complete inspection of the concrete density and interlocking quality of the pile body through core drilling, making defects readily visible and easy to identify.

[0031] 6. Compared with the ground freezing method, there is no risk of frost heave and thaw settlement, and it has better environmental adaptability.

[0032] There is no need to install refrigeration units or freezing pipelines, and there are no issues such as soil frost heave, surface cracking due to subsequent thawing and settlement, or pipeline displacement. There is also no need for long-term settlement monitoring and thawing and settlement treatment. At the same time, it saves on the continuous investment of liquid nitrogen and brine materials, and the overall construction period and cost are better than the freezing solution.

[0033] 7. Compared with grouting reinforcement inside the tunnel, it has the ability to provide deep support.

[0034] The effective reinforcement depth of radial grouting inside the tunnel is only 1-4m, and the deep buried section cannot balance the water pressure of the overlying soil; rotary drilling piles can be embedded 1.5-2m into the tunnel bottom, fully wrapping the cutterhead arch, both sides, and deep soil at the tunnel bottom, forming an independent soil retaining and water-stopping system, without relying on shield equipment support, and with sufficient safety redundancy.

[0035] 8. Strong construction stability and lower risk of failure.

[0036] The MJS method involves cumbersome drill rod connection and the high-pressure nozzle is easily blocked by pebbles. Deep construction carries risks of drill bit sticking, rod breakage, and drill bit burial. Rotary drilling with full casing follows the drilling process, resulting in a stable hole formation process, fewer problems in pebble formations, stronger construction continuity, and controllable reinforcement period.

[0037] 9. Rotary drilling piles adopt segmented heterogeneous pile bodies, which meet the bearing strength requirements while enabling the tunnel boring machine to quickly excavate within the cutoff wall, significantly improving the efficiency of tunnel boring machine cutterhead opening and replacement. Attached Figure Description

[0038] Figure 1 It is a diagram showing the cross-sectional layout of the water-stop curtain.

[0039] Figure 2 This is a layout diagram of rotary drilling piles. Detailed Implementation

[0040] The following non-limiting embodiments are intended to enable those skilled in the art to gain a more comprehensive understanding of the present invention, but do not limit the invention in any way. The following content is merely an exemplary description of the scope of protection claimed by the present invention, and those skilled in the art can make various changes and modifications to the present invention based on the disclosed content, and such changes should also fall within the scope of protection claimed by the present invention.

[0041] The present invention will be further described below by way of specific embodiments. Unless otherwise specified, all instruments, devices, equipment, reagents, products, etc., used in the embodiments of the present invention are obtained through conventional commercial means.

[0042] The construction method for shield tunneling reinforcement under normal pressure in deeply buried gravel strata includes the following steps: S1, Construction preparation and surveying / layout.

[0043] The site was leveled and compacted, and mud pits and slag dumping areas were planned; underground pipelines were identified, geological surveys were completed, and the distribution of pebbles and boulders was determined; raw materials (concrete, bentonite, steel casing) were inspected upon arrival at the site.

[0044] Pre-planning of pile locations, water-stop curtains, etc.: Combination Figure 1 and Figure 2 The soil layers at the planned tunnel boring machine (TBM) opening point, from top to bottom, are: miscellaneous fill, medium-fine sand, silty clay, silty clay, and fine-coarse gravelly soil. The outer diameter of the TBM segment is D = 12.2 meters, the overburden thickness is H1 = 31.5 meters, and the reinforcement range extends to the bottom of the TBM, H2 = 3 meters, for a total reinforcement depth of approximately H = H1 + D + H2 = 12.2 + 31.5 + 3 = 46.7 meters. Since the soil layers within the TBM section, from top to bottom, consist of silty clay, interbedded medium-fine sand, and fine-coarse gravelly soil, full-span rotary drilling piles are used for reinforcement of the planar dimension A. The range of B is defined as follows: A = shield length 14 meters + cutterhead front reinforcement 6 meters = 20 meters; B = shield cutterhead diameter 12.6 meters + outer reinforcement thickness 3.2 meters. 2 = 19 meters. Rotary drilling piles are 1.2m @ 0.9m, with a 300mm interlocking length. In the reinforcement zone, solid piles are used from the top 10.3m to the bottom 3m of the excavation face, while empty piles are used from the top 21.2m to the ground. Insufficient solid piles reaching the ground can easily lead to borehole collapse; therefore, at least 50% of the piles must reach the ground during construction. The water-stop curtain is formed by the interlocking rotary drilling piles.

[0045] Curtain area: ≥3m in front of the cutterhead, ≥4m above the tunnel arch, ≥3m on both sides of the tunnel, and the pile bottom is embedded in the stable gravel layer 1.5-2.0m below the tunnel floor; Piling method: Double-row rotary drilling interlocking piles, pile diameter Φ800-1200mm, interlocking overlap 200-300mm, forming a fully enclosed water-proof and soil-retaining curtain; Mark the center line of the pile position and the edge line of the curtain wall, mark the pile position, and verify the pile spacing and interlocking width; set up leveling points and verticality monitoring benchmarks.

[0046] S2, deep well dewatering.

[0047] Construct dewatering wells outside the cutoff wall, with the bottom of the wells 2-3m lower than the bottom of the piles, and fill them with filter material to prevent sand leakage; continuously dewater for 7-15 days in advance, and lower the water level to ≥1.5m below the tunnel floor to reduce dynamic water pressure.

[0048] S3, steel casing installation.

[0049] A 2-4m long steel casing is buried on the surface to correct the center and verticality; in the deep sand and gravel section, an extended recirculating steel casing is used for follow-up drilling.

[0050] S4, segmented rotary drilling pile holes, segmented casting of rotary drilling piles.

[0051] The rotary drilling rig is aligned with the pile position and drills at a low speed; small pebbles are scooped with a sand bucket, while large boulders are crushed and graded using a core drill; mud slurry is used for wall protection throughout the process, and casing is simultaneously installed to isolate loose pebbles from pressurized water.

[0052] After drilling to the designed pile bottom elevation, repeatedly remove the sediment from the bottom of the hole; perform a second cleaning of the hole, controlling the sediment thickness to ≤100mm and maintaining the mud specific gravity at 1.15-1.30.

[0053] Lower the grouting pipe, with the bottom of the pipe 300-500mm from the bottom of the hole; seal the bottom with sufficient first batch; pour continuously, controlling the burial depth of the pipe to 2-6m, and slowly pull out the sleeve as pouring progresses.

[0054] Rotary drilling piles adopt a segmented heterogeneous pile body structure, specifically including a shield tunneling section and a bearing section. The shield tunneling section and the bearing section are distinguished according to the shield excavation edge line. The shield bearing section covers the area between the shield excavation edge line and uses underwater air bubbles mixed with lightweight soil to form a pile body with relatively low strength, which facilitates the rapid tunneling of the shield machine. The bearing section is the area outside the shield excavation edge line, which is used for bearing the shield tunneling section and the surrounding soil, forming a stable environment inside the water-stop curtain. The bearing section can also be cut by the shield machine.

[0055] This creates a composite water-stop curtain with an external bearing section for support and an internal shield tunneling section for easy access by the tunnel boring machine (TBM). The high strength of the bearing section supports the surrounding soil and the shield tunneling section, maintaining the overall stability of the water-stop curtain. After the TBM breaks through the surface bearing section, it enters the water-stop curtain for tunneling. The internal shield tunneling section has lower strength, allowing the TBM to quickly complete cutting and tunneling. The TBM can also quickly complete positioning for subsequent cutterhead replacement, effectively improving the efficiency of TBM cutterhead replacement.

[0056] Understandably, depending on actual needs, rotary drilling piles can be formed entirely from the bearing section, but not entirely from the shield tunneling section. The length of the shield tunneling section must be greater than or equal to the distance between the shield excavation edges, thus providing sufficient adjustment space for the tunnel boring machine (TBM) to always travel within the shield tunneling section. Simultaneously, to ensure strength requirements, the length of the shield tunneling section can be less than or equal to the theoretical requirement, ensuring that the length of the bearing section is greater than or equal to the theoretical requirement. When there is a conflict between the length ratio of the shield tunneling section to the bearing section and the requirement that the length of the shield tunneling section must be greater than or equal to the distance between the shield excavation edges, the length ratio of the shield tunneling section to the bearing section takes priority.

[0057] The underwater aerated lightweight soil used in the shield tunneling section comprises cement, fly ash, composite foaming agent, and anti-dispersing agent. Hard coarse aggregate is removed, and the water-cement ratio is controlled at 0.54-0.77. The 28-day compressive strength is controlled at 1.0-2.0 MPa, exhibiting good cohesive and erosion-resistant properties, while meeting the dual requirements of shield cutting capability and self-stable operation in open-cell configuration. The load-bearing section uses high-strength (strength ≥ C30) underwater concrete, balancing load-bearing capacity and shield cutting capability requirements.

[0058] Construction is carried out in two phases: A-sequence and B-sequence piles. The adjacent B-sequence piles are constructed before the concrete of the A-sequence piles has initially set, and the overlapping surfaces are cut to form a 200-300mm interlocking waterstop.

[0059] S5, maintenance and testing.

[0060] Concrete curing shall be carried out for no less than 14 days; core drilling shall be performed in the reinforced area to check the integrity of the pile body, and the water inflow and soil self-stability shall be tested by internal probes.

[0061] Finally, it should be noted that the above content is only used to illustrate the technical solution of the present invention, and is not intended to limit the scope of protection of the present invention. Simple modifications or equivalent substitutions made by those skilled in the art to the technical solution of the present invention do not depart from the essence and scope of the technical solution of the present invention.

Claims

1. A method for atmospheric pressure tunneling reinforcement of deeply buried gravel strata using a shield tunneling machine, characterized in that: Includes the following steps: Construction preparation and surveying / layout; Deep well dewatering; Steel casing installation; Segmented rotary drilling pile holes, segmented casting of rotary drilling piles, forming segmented heterogeneous pile bodies; Maintenance and testing.

2. The method for reinforcing deep-buried gravel strata using shield tunneling under normal pressure according to claim 1, characterized in that: During construction preparation and surveying, the pile positions and water-stop curtain should be planned in advance. The curtain range is as follows: ≥3m in front of the cutterhead, ≥4m above the tunnel arch, ≥3m on both sides of the tunnel, and the pile bottom should be embedded in the stable pebble layer 1.5-2.0m below the tunnel floor.

3. The method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata according to claim 1, characterized in that: When installing steel casing, a 2-4m long casing is installed on the surface to correct the center and verticality; in the deep sand and gravel section, an extended recirculating casing is used for follow-up drilling.

4. The method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata according to claim 1, characterized in that: Rotary drilling piles consist of a shield tunneling section and a bearing section. The bearing section has higher strength than the shield tunneling section. The shield tunneling section and the bearing section are different parts of the rotary drilling pile body. The shield tunneling section is used for rapid cutting and excavation by the tunnel boring machine, while the bearing section supports the shield tunneling section.

5. The method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata according to claim 4, characterized in that: The length of the shield tunneling section is greater than or equal to the spacing between the shield excavation edges.

6. The method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata according to claim 4, characterized in that: The length of the shield tunneling section is less than or equal to the theoretical requirement, which makes the length of the bearing section greater than or equal to the theoretical requirement.

7. The method for atmospheric pressure tunneling reinforcement of deep-buried gravel strata using a shield tunneling machine according to claim 4, characterized in that: The shield tunneling section uses underwater air-bubbled lightweight soil, while the load-bearing section uses underwater concrete with a strength ≥ C30.

8. The method for reinforcing deep-buried gravel strata shield tunneling under normal pressure according to claim 7, characterized in that: The water-cement ratio of the underwater bubble-mixed lightweight soil is 0.54-0.77, and the 28-day compressive strength is controlled at 1.0-2.0 MPa.

9. The method for reinforcing deep-buried gravel strata shield tunneling under normal pressure according to claim 1, characterized in that: When dewatering deep wells, the bottom of the well is 2-3m lower than the bottom of the pile. Dewatering is carried out continuously for 7-15 days in advance, and the water level drops to ≥1.5m below the bottom of the tunnel.

10. The method for atmospheric pressure opening and reinforcement construction of shield tunnels in deeply buried gravel strata according to claim 1, characterized in that: Rotary drilling piles are constructed in alternating A and B sequence. Adjacent B piles are constructed before the initial setting of the A pile concrete, and the overlapping surfaces are cut to form a 200-300mm interlocking waterstop.