A lining repair device and its usage method

By designing a lining repair device that includes a base carrier, a top plate, a working arm, and a working platform, the problems of low efficiency and poor safety in railway tunnel lining repair operations have been solved, achieving efficient, safe, and flexible lining repair results.

CN123109698APending Publication Date: 2026-11-17HENAN RAIL TRANSIT RES INST CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611484081.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-22
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies for railway tunnel lining repair operations are characterized by low efficiency, long cycle, high intensity, high cost, poor safety, and poor mobility of manned work vehicles.

Method used

A lining repair device was designed, comprising a base vehicle, a top plate, a working arm, and a working platform. It utilizes a track-type bottom travel system and a telescopic rod structure to assist workers in lining repair. It is equipped with detection components and a dust shielding component to improve safety and applicability.

Benefits of technology

It achieves efficient, safe, and flexible lining repair, reduces manual intervention, improves operational efficiency and safety, and enhances the applicability of the device in tunnels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109698A_ABST
    Figure CN123109698A_ABST
Patent Text Reader

Abstract

This application discloses a lining repair device and its usage method, relating to the field of repair equipment technology. By optimizing and improving the structure of existing railway tunnel lining repair equipment, a vehicle equipped with a robotic arm that can move on the track is used to assist operators in flexibly, safely, and efficiently completing lining repair work. The robotic arm on the vehicle is equipped with a platform that can rotate to a specific angle as needed and provides footholds for operators. This achieves the technical effect that the lining repair device can assist manual labor in completing railway tunnel lining repair, requires minimal human intervention, has high work efficiency, high safety, and strong flexibility and applicability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of repair equipment technology, and in particular to a lining repair device and its usage method. Background Technology

[0002] As an important component of railway tunnels, the quality of tunnel lining is crucial to the safe operation of railway tunnels. However, due to the continuous changes in the external environment and geological conditions, as well as the influence of design, construction, management and construction of other surrounding buildings, tunnel linings often suffer from defects such as cracks, water leakage, deformation, delamination and spalling during operation, which seriously threaten the normal and safe use of the tunnel. To address these defects, it is necessary to completely or partially dismantle the secondary lining structure and re-line it.

[0003] In existing technologies, due to the high location of the maintenance area and the curved working surface, the process of completely or partially dismantling and relining the secondary lining structure is generally carried out manually with the help of aerial work platforms (lifting work platforms). This process is characterized by low work efficiency, long work cycle, high work intensity, and high labor costs. During the excavation process, working at height and the risk of concrete falling can pose serious threats to the safety and health of the workers. Furthermore, because the tunnel is an arched structure with internal tracks, the flexibility and applicability of using aerial work platforms to move within the tunnel are poor, which is not conducive to efficient operation.

[0004] Therefore, there is a need for a lining repair device that can assist manual labor in completing railway tunnel lining repair, requires minimal human intervention, has high operational efficiency, high safety, and strong flexibility and applicability. Summary of the Invention

[0005] This application provides a lining repair device that solves the technical problems of low work efficiency, long operation cycle, high work intensity, high labor cost, poor safety, and poor mobility of manned operation vehicles in the prior art when carrying out railway tunnel lining repair work. It achieves the technical effect that the lining repair device can assist manual labor in completing railway tunnel lining repair, without excessive human intervention, with high work efficiency, high safety, and strong flexibility and applicability.

[0006] This application provides a lining repair device, including a base vehicle, a top plate, a working arm, and a working platform assembly; The base vehicle has a track-type bottom travel system positioned at the bottom; the top plate is a horizontally placed rigid plate positioned on the base vehicle, and a controlled rotating load-bearing turntable is positioned on the top; a support frame is fixed at the top center of the load-bearing turntable; The working arm is a telescopic rod structure that can extend and retract in a controlled manner. One end is rotatably connected to the support frame, and the axis of rotation is parallel to the horizontal ground and can rotate in a controlled manner. Multiple floating telescopic rods are positioned at the end of the working arm away from the support frame; the floating telescopic rods are telescopic rods with built-in compression springs and built-in detection components for measuring their real-time length, and an end wheel carrier is fixed at the end away from the working arm; the end wheel is a horizontally placed cylindrical wheel body, positioned on the end wheel carrier. The end wheel carrier has a component carrier positioned on it; the component carrier is a rod-shaped or plate-shaped frame, with one end rotatably connected to the side of the end wheel carrier. The axis of rotation is the same as the axis of the end wheel, and it rotates in a controlled manner to carry the positioning components. The work platform component is positioned on the work arm near the floating telescopic rod, and is used to carry workers to the target processing location as needed for work.

[0007] Furthermore, the work platform component includes a connecting positioning body and a work platform; The connecting positioning body is positioned on the working arm and serves as a connecting support; The working platform is located on one side of the working arm and is a horizontal rectangular plate-shaped platform. One side is rotatably connected to the side of the connecting positioning body. The axis of rotation is parallel to the horizontal ground. It rotates under the control of the power component and the control unit and can rotate at an angle greater than 180 degrees. The connecting positioning body is tubular, sleeved and slidably positioned on the working arm, and can slide under control; during operation, the working platform can be controlled to slide as needed.

[0008] Preferably, a lifting assembly is positioned on the top of the base vehicle; The lifting assembly is a combination of multiple vertical telescopic rods fixed to the top of the base vehicle, which can be extended and retracted in a controlled manner, thereby driving the components it carries to rise and fall. The top plate is provided with multiple horizontal plate-shaped support frames around its perimeter. There are four or more support frames, and each support frame has a vertical support rod positioned at its bottom. Each support rod has a caster wheel positioned at its bottom; When the lifting assembly is retracted to its shortest state, the casters touch the ground, causing the bottom travel system to be suspended in the air; due to the presence of the casters, the base vehicle can travel off-track.

[0009] Preferably, a limiting and reinforcing component is also positioned on the top of the carrying turntable; The restraint and reinforcement components include a vertical frame, a top drum, and a safety rope; The vertical support frame is a vertical column-shaped frame with a height greater than one-third of the working arm in its fully retracted state. Its bottom is fixed to the top of the bearing turntable and located on one side of the support frame, serving as a load-bearing and supporting element. The top drum is a horizontally positioned winch structure, located at the top of the vertical frame, and rotates under control. The safety rope is a steel wire rope, with one end fixed to the working arm and the other end wound and positioned on the top drum; The safety rope is fixed at a point near the middle of the boom; when the boom rotates, the top drum rotates synchronously to maintain the tautness of the safety rope and ensure the safety of the boom's rotation.

[0010] Preferably, it also includes a reinforcement frame assembly; The reinforcement frame assembly includes a first telescopic body; the first telescopic body is a telescopic rod structure, one end of which is rotatably connected to the support frame body, the axial direction of the rotation axis is the same as the axial direction of the rotation axis of the working arm and is located on one side of the working arm, and is controlled to extend, retract and rotate. After the base vehicle moves close to the center of the tunnel's arched section, the first telescopic body is controlled to rotate and extend to contact the inner wall of the tunnel, thereby clamping the entire device through compressive force.

[0011] Preferably, the reinforcement frame assembly further includes a second telescopic body and a connecting assembly frame; The structure of the second telescopic body is the same as that of the first telescopic body. One end is rotatably connected to the support frame. The axial direction of the rotation axis is the same as that of the rotation axis of the working arm and is located on the other side of the working arm. It can extend, retract and rotate under control. The connecting frame is a horizontally placed rigid rod or a plate-shaped frame. The connecting frame is fixed at the ends of the second telescopic body and the first telescopic body that are away from their own positioning points, serving as a connecting element.

[0012] Preferably, a horizontally positioned rotating drum is located near the first telescopic body and the second telescopic body of the connecting assembly frame; A pulling rope is positioned on the rotating drum; The pulling rope is a steel wire rope, with one end wound and positioned on the rotating drum and the other end fixed to the working arm, always in a taut state; when the working arm rotates, the rotating drum also rotates at the same time, maintaining the taut state of the pulling rope and thus ensuring the safety and stability of the working arm operation.

[0013] Preferably, the end wheel carrier is provided with side guide wheels and side wheel carriers for supporting the side guide wheels on both sides; The load-bearing turntable directly below the boom is equipped with a drum support and a bottom drum positioned on the drum support. A horizontally positioned rotating drum is located near the first telescopic body and the second telescopic body of the connecting assembly frame. The side guide wheel is a horizontally placed rigid cylindrical wheel with the same diameter as the end wheel and coaxial with the end wheel. It is rotatably connected to the side wheel carrier around its own axis. The drum support is a rigid frame fixed on the load-bearing turntable; the bottom drum is a horizontally placed drum structure positioned on the drum support.

[0014] Preferably, it also includes a dust-shielding component; The dust removal and shielding assembly includes a shielding strip, a U-shaped dust removal body, a combination joint, an air extraction and dust filtration assembly, and a pump-liquid assembly. One end of the shielding tape is wound and positioned on the rotating drum, and the other end is wound and positioned on the bottom drum, always abutting against the two side guide wheels; The shielding strip has multiple rectangular through slots positioned on it; the width of the through slots is greater than the axial length of the end wheel and less than 1.5 times the axial length of the end wheel. The U-shaped dust collector is a U-shaped flexible plate that is tightly attached to and fixed to the side of the shielding belt away from the working arm and surrounds the through slots. It corresponds one-to-one with the through slots, has built-in fluid channels, and has dense through holes on the side away from the shielding belt. The combination connector is positioned on the shielding strip near the working arm and is a quick-connect connector that connects to the fluid channel built into the U-shaped dust collector. There are two types of rotary dust collectors, and the diameters of the through holes on the two types of rotary dust collectors are different. The two types of rotary dust collectors are used for spray dust suppression and suction dust collection, respectively, namely spray dust collector and suction dust collector. The air extraction and dust filtration assembly is connected to the air suction and dust removal body in a timely manner; the pump-liquid assembly is used to supply liquid to the spray dust removal body in a timely manner.

[0015] One or more technical solutions provided in the embodiments of this application have at least the following technical effects or advantages: By optimizing and improving the structure of existing railway tunnel lining repair equipment, a mobile vehicle equipped with a robotic arm that can move on the track is used to assist workers in completing lining repair work flexibly, safely, and efficiently. The robotic arm on the vehicle is equipped with a platform for workers to step on. This effectively solves the technical problems of low work efficiency, long work cycle, high work intensity, high labor costs, poor safety, and poor mobility of the mobile vehicle in existing railway tunnel lining repair work. As a result, the lining repair device can assist workers in completing railway tunnel lining repair, requires less human intervention, has high work efficiency, high safety, and strong flexibility and applicability. Attached Figure Description

[0016] Figure 1 This is a schematic diagram showing the positional relationship of the components of the lining repair device in this application; Figure 2 This is a schematic diagram of the external structure of the lining repair device of this application; Figure 3 This is a schematic diagram of the bottom structure of the lining repair device of this application; Figure 4 This is a schematic diagram showing the movement of the lining repair device of this application; Figure 5 This is a schematic diagram of the structure of a floating telescopic rod; Figure 6 This is a structural diagram of the limiting insurance component; Figure 7 This is a schematic diagram showing the positional relationship between the reinforcement frame assembly and other components; Figure 8 A schematic diagram showing the positional relationship between the dust removal component and other parts; Figure 9 This diagram illustrates the positional relationship between the end wheel carrier, end wheel, accessory carrier, working accessories, and side guide wheels and guide rollers. Figure 10 A simplified structural diagram of the shielding strip and its positioning components; Figure 11 A simplified diagram showing the arrangement of the combination joints on the shielding strip; Figure 12 This is a diagram showing the usage status of the work accessories.

[0017] In the picture: 100 base vehicle, 110 bottom travel system, 120 lifting assembly, 200 top plate, 210 load-bearing turntable, 220 support frame, 300 working arm, 310 limiting and safety assembly, 311 limiting plate, 312 limiting pin, 313 base plate, 314 rotating bend, 315 end stop, 316 end spring, 317 pulling assembly, 320 limiting and reinforcing assembly, 321 vertical frame, 322 top drum, 323 safety rope, 330 floating telescopic rod, 331 detection assembly, 340 end wheel carrier, 350 end wheel, 360 accessory carrier, etc. Components 370, side guide wheel 380, side wheel carrier 381, guide roller 390, work platform assembly 400, connecting positioning body 410, work platform 420, guardrail assembly 430, first telescopic body 510, second telescopic body 520, connecting combination frame 530, rotating drum 540, pulling work rope 550, safety work rope 560, bottom drum 580, drum bracket 581, shielding belt 610, with side notch 611, through slot 620, U-shaped dust collector 630, combination joint 640, air extraction and dust filter assembly 650, pump liquid assembly 660. Detailed Implementation

[0018] To facilitate understanding of the present invention, a more complete description of this application will be given below with reference to the accompanying drawings, which illustrate preferred embodiments of the invention. However, the invention can be implemented in many different forms and is not limited to the embodiments described herein. Rather, these embodiments are provided to enable a more thorough and complete understanding of the disclosure of the present invention.

[0019] It should be noted that the terms "vertical," "horizontal," "up," "down," "left," "right," and similar expressions used in this article are for illustrative purposes only and do not represent the only possible implementation.

[0020] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains; the terminology used herein in the description of the invention is for the purpose of describing particular embodiments only and is not intended to limit the invention; the term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0021] Example 1

[0022] like Figures 1 to 5 As shown, the lining repair device of this application includes a base carrier 100, a top carrier plate 200, a working arm 300, a working platform assembly 400, a power assembly, and a control unit.

[0023] The basic carrier vehicle 100 is a transverse rigid frame that serves as a load-bearing and supporting structure. It has a bottom travel system 110 positioned at the bottom and a lifting assembly 120 positioned at the top. The bottom travel system 110 is a track-type travel system, controlled by the control unit, which is existing technology; the lifting assembly 120 is a combination of multiple vertical telescopic rods fixed to the top of the base vehicle 100, which extend and retract under the coordinated control of the power assembly and the control unit, thereby driving the components it carries to rise and fall.

[0024] The top plate 200 is a horizontally placed rigid plate that serves as a load-bearing and supporting element and is fixed to the top of the lifting assembly 120. The top of the top plate 200 is positioned with a load-bearing turntable 210; the load-bearing turntable 210 is a horizontal turntable that rotates around its own axis under the coordinated control of the power component and the control unit. A support frame 220 is fixed at the top center of the bearing turntable 210; the support frame 220 is a rigid block, rigid plate or rigid frame, which serves to support the working arm 300.

[0025] The working arm 300 is a telescopic rod structure, which can be a single-stage or multi-stage telescopic rod. It extends and retracts under the coordinated control of the power component and the control unit. Its length in the fully extended state is greater than the radius of the tunnel to be processed. One end is rotatably connected to the support frame 220. The axis of rotation is parallel to the horizontal ground. It rotates under the coordinated control of the power component and the control unit. Multiple floating telescopic rods 330 are positioned at the end of the working arm 300 away from the support frame 220. Each floating telescopic rod 330 is a telescopic rod with a built-in compression spring. When compressed, the internal spring is compressed; when uncompressed, it extends under the elastic force of the spring. Each of the multiple floating telescopic rods 330 has one end fixed to the end of the working arm 300 away from the support frame 220 and is aligned with the axis of the working arm 300. Each floating telescopic rod 330 has a built-in detection component 331. The detection component 331 is a length sensor connected to the control unit signal, used to measure the real-time length of the floating telescopic rod 330, which is existing technology. like Figure 1 and Figure 5 As shown, an end wheel carrier 340 is fixed to the end of the floating telescopic rod 330 away from the working arm 300; the end wheel carrier 340 is a U-shaped rigid frame with its opening facing away from the floating telescopic rod 330, used to support the positioning end wheel 350; the end wheel 350 is a horizontally placed cylindrical wheel that is rotatably connected to the end wheel carrier 340 around its own axis, and the axis of rotation is perpendicular to the axis of the floating telescopic rod 330, and is further away from the floating telescopic rod 330 relative to the end wheel carrier 340; The end wheel carrier 340 is equipped with accessory carriers 360. Each accessory carrier 360 is a rod-shaped or plate-shaped frame, and there are two of them. Each accessory carrier is rotatably connected at one end to the side of the end wheel carrier 340, with its rotation axis aligned with the axis of the end wheel 350. It rotates under the coordinated control of the power assembly and control unit, and is used to support positioning accessories 370. The two accessory carriers 360 are located on opposite sides of the end wheel carrier 340, supporting different accessories 370. The accessories 370 are of various types, including at least saw blades, water jets, and impact drills. They are detachably fixed to the ends of different accessory carriers 360 furthest from their own rotation points. During operation, different accessories 370 are installed on the accessory carriers 360 as needed.

[0026] The work platform assembly 400 is positioned on the work arm 300 near the floating telescopic rod 330, and is used to carry workers to the target processing position as needed. It includes a connecting positioning body 410 and a work platform 420. The connecting positioning body 410 is positioned on the work arm 300 and serves as a connecting support. The work platform 420 is a horizontally placed rectangular plate-shaped platform, rotatably connected to one side of the connecting positioning body 410. The axis of rotation is parallel to the horizontal ground. It rotates under the control of the power assembly and control unit, and can rotate at an angle greater than 180 degrees. The work platform 420 is located on one side of the work arm 300.

[0027] Furthermore, a guardrail assembly 430 is positioned on the work platform 420; the guardrail assembly 430 is a rigid fence.

[0028] The power assembly is used to provide power for the operation of each component of the lining repair device of this application, and the control unit plays the role of controlling the coordinated operation of each component of the lining repair device. Both are existing technologies and will not be described in detail here.

[0029] Preferably, the control unit is a combination of a programmable logic controller and control buttons.

[0030] When the lining repair device of this application is in use: under normal conditions, the working arm 300 is in a horizontal position with its length direction being the same as its own travel direction; the working accessory 370 carried by the accessory carrier 360 is located near the side of the floating telescopic rod 330. When auxiliary operations are required, first proceed along the track to the vicinity of the target repair location in the tunnel; Then, control the load-bearing turntable 210 to rotate 90 degrees, and control the working arm 300 to rotate and extend, so that the end wheel 350 abuts against the lining inside the tunnel and the floating telescopic rod 330 is in a compressed state. Then, the working arm 300 is rotated so that the end wheel 350 rolls against the lining to be repaired and its surrounding lining. The data measured by the detection component 331 is used to know the amount of extension and retraction of the floating telescopic rod 330, and thus the shape of the lining to be repaired and its surrounding lining is known, so that the working accessory 370 can be used for subsequent work. The floating telescopic rod 330 is controlled to retract, causing the end wheel 350 to detach from the tunnel wall; The control accessory carrier 360 rotates some of the working accessories 370 to a position away from the floating telescopic rod 330; Based on the data measured by the detection component 331, the operator remotely controls the extension and retraction of the working arm 300, the rotation of the working arm 300, the movement of the base carrier 100, and the rotation of the accessory carrier 360, and uses one or more working accessories 370 to complete the removal of the problematic lining. Control the boom 300 to rotate to a horizontal position, and the operator climbs onto the work platform assembly 400; control the boom 300 to rotate and extend, and complete the lining repair work on the work platform assembly 400; Clean up the work site and complete the lining repair.

[0031] Preferably, the base vehicle 100 has one or more telescopic outriggers positioned at its bottom; the telescopic outriggers extend as needed, making the base vehicle 100 more stable during operation.

[0032] Furthermore, such as Figure 4As shown, the top plate 200 is provided with multiple horizontally placed plate-shaped support frames around its perimeter, with four or more support frames. Each support frame has a vertical support rod positioned at its bottom. Each support rod has a caster wheel positioned at its bottom. When the lifting assembly 120 is retracted to its shortest state, the caster wheel touches the ground, causing the bottom travel system 110 to be suspended in the air. Due to the presence of the caster wheel, the base vehicle 100 can travel off-track.

[0033] Preferably, some or all of the omnidirectional wheels are controllable and self-powered, enabling them to move in a controlled manner as needed.

[0034] Furthermore, when the base carrier 100 travels along the track to a position close to the target work location, it is controlled to derail and move to the midpoint of the tunnel width. Then, the working arm 300 is rotated as a whole so that its rotation axis is the same as (or approximately the same as) the length of the tunnel. After that, the lifting assembly 120 is controlled to operate so that the rotation axis of the working arm 300 coincides with (as closely as possible with) the center of the tunnel arch section. Then, the working arm 300 is subjected to luffing and telescopic movements. In this state, the demolition of the problematic lining does not require frequent telescopic control of the working arm 300 to adapt to the curved surface of the tunnel wall, resulting in higher demolition efficiency and better results.

[0035] Preferred, such as Figure 2 and Figure 4 As shown, the connecting positioning body 410 is tubular, sleeved and slidably positioned on the working arm 300, and slides under the coordinated control of the power component and the control unit; during operation, the working platform 420 can be controlled to slide as needed.

[0036] Preferably, when using the work accessory 370 for demolition work, the work platform 420 is rotated to an angle with the bottom facing upwards to reduce dirt and reduce the labor intensity required for cleaning.

[0037] To further improve the safety of the boom 300 during rotation, preferably, such as Figure 1 As shown, it also includes a limiting safety component 310; the limiting safety component 310 is used to limit the rotation of the working arm 300 as needed through the cooperation of pins and pin holes; the limiting safety component 310 includes a limiting plate 311 positioned on the support frame 220, and a limiting pin 312 positioned on the side wall of the working arm 300; the limiting plate 311 is an upright rigid plate with a row of pin holes arranged in an arc shape; the limiting pin 312 is an electric pin, which is controlled to extend and retract and matches the pin holes; when the operator climbs onto the working platform 420 and the working arm 300 is in a stationary state, the limiting pin 312 is controlled to insert into one of the pin holes on the limiting plate 311 to achieve fixation and thus ensure stability.

[0038] Preferred, such as Figure 6 As shown, the limiting plate 311 is fan-shaped, including a fan-shaped base plate 313 and a rotating bend 314 slidably positioned on the base plate 313. It also includes end blocks 315, end springs 316, and a pulling assembly 317. The base plate 313 is fixed to the support frame 220. The rotating bend 314 is a rigid rod-shaped strip with a row of pin holes arranged in an arc. The rotating bend 314 slides along the arc surface of the base plate 313. There are two end blocks 315, which are rigid blocks positioned on the arc surface of the base plate 313 and near its two corners, respectively, to limit the movement range of the rotating bend 314 and ensure safety. The end spring 316 is a metal tension spring. One end is fixed to one of the end blocks 315, and the other end is fixed to the end of the rotating bend 314, which is used to use elastic force to assist the rotating bend 314 in resetting; the pulling component 317 is a winch structure, which is directly or indirectly fixed to the base plate 313. It operates under the coordinated control of the power component and the control unit and then controls the rotating bend 314 to slide as needed by pulling; when the working arm 300 is controlled to rotate, the rotating bend 314 is controlled to slide, thereby extending the time for the limit pin 312 to be inserted into the pin hole; because the rotating bend 314 can slide along the arc surface of the rotating bend 314, the working arm 300 can be suspended at any angle as needed under the premise of ensuring safety and stability, and both flexibility and safety are better guaranteed.

[0039] Preferably, in order to further improve the stability and safety of the boom 300 during rotation, such as Figure 1 As shown, a restraining and reinforcing component 320 is also positioned on the top of the carrying turntable 210; the restraining and reinforcing component 320 includes a vertical frame 321, a top drum 322, and a safety rope 323; the vertical frame 321 is a vertical column-shaped frame, with a height greater than one-third of the working arm 300 in its fully retracted state, and its bottom is fixed to the top of the carrying turntable 210 and located on one side of the supporting frame 220, serving a load-bearing and supporting function; the top drum 322 is a horizontally placed winch structure. Positioned at the top of the vertical frame 321, it rotates under the coordinated control of the power unit and the control unit; the safety rope 323 is a steel wire rope, one end of which is fixed to the working arm 300, and the other end is wound and positioned on the top drum 322; the fixing point of the safety rope 323 on the working arm 300 is close to the middle of the working arm 300; when the working arm 300 rotates, the top drum 322 rotates synchronously to maintain the taut state of the safety rope 323 to ensure the safety of the working arm 300 rotation.

[0040] The technical solutions described in the embodiments of this application have at least the following technical effects or advantages: This invention solves the technical problems of low work efficiency, long operation cycle, high work intensity, high labor cost, poor safety, and poor mobility of manned operation vehicles in the existing technology for railway tunnel lining repair. It achieves the technical effect of enabling the lining repair device to assist manual labor in completing railway tunnel lining repair, without requiring excessive human intervention, with high work efficiency, high safety, and strong flexibility and applicability.

[0041] Example 2

[0042] To further improve the stability and safety of the lining repair device during use, this embodiment adds a reinforcing frame assembly based on the above embodiments; during operation, the entire device is secured within the tunnel by contacting the tunnel wall, thereby ensuring stability. Specifically: like Figure 7 As shown, the reinforcement frame assembly includes a first telescopic body 510; the first telescopic body 510 is a telescopic rod structure, one end of which is rotatably connected to the support frame 220, the axial direction of the rotation axis is the same as the axial direction of the rotation axis of the working arm 300 and is located on one side of the working arm 300, and it extends, retracts and rotates under the coordinated control of the power component and the control unit; a soft pad is positioned at the end of the first telescopic body 510 away from its own positioning point; After the base carrier 100 moves close to the center of the tunnel arch section, the first telescopic body 510 is controlled to rotate and extend to contact the inner wall of the tunnel, and the entire device is clamped by the squeezing force; the optimal contact position of the soft pad is the inner wall of the tunnel directly above the base carrier 100; if the lining to be treated is located at the inner top of the tunnel, the first telescopic body 510 is controlled to extend and contact the inner wall of the tunnel diagonally above the base carrier 100 through the soft pad.

[0043] Preferably, to further ensure stability and safety during the operation, such as Figure 7 As shown, the reinforcement frame assembly also includes a second telescopic body 520 and a connecting assembly frame 530. The structure of the second telescopic body 520 is the same as that of the first telescopic body 510. One end is rotatably connected to the support frame 220. The axial direction of the rotation axis is the same as that of the rotation axis of the working arm 300 and is located on the other side of the working arm 300. It extends and rotates under the coordinated control of the power assembly and the control unit. The connecting assembly frame 530 is a horizontal rigid rod or plate-shaped frame with a soft pad on the top surface. The connecting assembly frame 530 is fixed at the ends of the second telescopic body 520 and the first telescopic body 510 away from their own positioning points, serving as a connector. After the base vehicle 100 moves closer to the center of the tunnel arch section, it controls the first telescopic body 510 and the second telescopic body 520 to rotate synchronously and extend synchronously, contacting the inner wall of the tunnel through the connecting assembly frame 530. The entire device is clamped by the squeezing force.

[0044] Preferably, in order to further improve the stability and safety of the boom 300 during rotation, such as Figure 7 As shown, a horizontally positioned rotating drum 540 is located near the first telescopic body 510 and the second telescopic body 520 of the connecting assembly frame 530. The rotating drum 540 rotates under the coordinated control of the power component and the control unit. A pulling rope 550 is positioned on the rotating drum 540. The pulling rope 550 is a steel wire rope, with one end wound and positioned on the rotating drum 540 and the other end fixed to the working arm 300, always in a taut state. When the working arm 300 rotates, the rotating drum 540 also rotates simultaneously, maintaining the taut state of the pulling rope 550 and thus ensuring the safety and stability of the working arm 300 operation.

[0045] Preferred, such as Figure 7 As shown, another drum is arranged side by side on one side of the rotating drum 540. This drum is also arranged laterally and rotates under the coordinated control of the power component and the control unit. For ease of description, this drum is defined as the working drum. A safety working rope 560 is positioned on the working drum. The safety working rope 560 is a steel wire rope, with one end wound and positioned on the working drum and the other end fixed to the working platform 420. It is always in a taut state to improve the safety of the working platform 420.

[0046] Example 3

[0047] To reduce the impact of the work process on the work environment, thereby facilitating post-work cleanup, such as... Figures 8 to 12 As shown, this embodiment adds a dust-removing and shielding component to the above embodiment, and adds side guide wheels 380 and side wheel supports 381 for supporting the side guide wheels 380 on both sides of the end wheel support 340. A drum support 581 and a bottom drum 580 positioned on the drum support 581 are added to the support turntable 210 directly below the working arm 300. The flexible belt body simultaneously achieves the functions of dust reduction, dust isolation, and enhancing the luffing stability of the working arm 300. Specifically: A horizontally positioned rotating drum 540 is located near the first telescopic body 510 and the second telescopic body 520 on the connecting assembly frame 530; the rotating drum 540 rotates under the coordinated control of the power component and the control unit. The side wheel carrier 381 is a rigid support, preferably a U-shaped plate frame, fixed on the end wheel carrier 340, and is used to support the side guide wheel 380 without hindering the rotation of the accessory carrier 360. The side guide wheel 380 is a horizontally placed rigid cylindrical wheel with the same diameter as the end wheel 350 and coaxial with the end wheel 350. It is rotatably connected to the side wheel carrier 381 around its own axis and is used to guide the shielding belt 610 of the dust removal component to move. The drum support 581 is a rigid frame that is fixed on the bearing turntable 210; The bottom drum 580 is a horizontally placed drum structure, positioned on the drum support 581, and its axial direction is the same as the axial direction of the rotation axis of the working arm 300. It rotates under the coordinated control of the power component and the control unit. The dust removal and shielding assembly includes a shielding strip 610, a U-shaped dust removal body 630, a combination joint 640, an air extraction and dust filtration assembly 650, and a pump-liquid assembly 660. The shielding strip 610 is a non-metallic strip with a width greater than 50 cm. One end is wound and positioned on the rotating drum 540, and the other end is wound and positioned on the bottom drum 580, always in contact with the two side guide wheels 380. The sum of the axial length of the end wheel 350 and the axial length of the side guide wheels 380 is greater than the width of the shielding strip 610. The rotating drum 540 and the bottom drum 580 work together with the working arm 300. The shielding strip 610 has multiple rectangular through slots 620 positioned on it; the through slots 620 are rectangular through slots for the work accessory 370 to pass through; the width of the through slots 620 is greater than the axial length of the end wheel 350 and less than 1.5 times the axial length of the end wheel 350; the difference between the length and the width of the through slots 620 is less than 20 centimeters. The U-shaped dust collector 630 is a U-shaped flexible plate that is tightly attached to and fixed to the surface of the shielding strip 610 away from the working arm 300 and surrounds the through slot 620, corresponding one-to-one with the through slot 620; the U-shaped dust collector 630 has a built-in fluid channel and densely distributed through holes on the surface away from the shielding strip 610. The combination connector 640 is positioned on the surface of the shielding belt 610 near the working arm 300. It is a quick-connect connector and communicates with the fluid channel built into the U-shaped dust collector 630. When the shielding belt 610 moves, the combination connector 640 passes through the gap between the side guide wheel 380 and the end wheel 350. There are two types of rotary dust collectors 630, and the diameters of the through holes on the two types of rotary dust collectors 630 are different. The two types of rotary dust collectors 630 are used for spray dust suppression and suction dust collection, respectively. For the convenience of description, the two types of rotary dust collectors 630 are defined here as spray dust collectors and suction dust collectors, respectively. The air extraction and dust filtration assembly 650 is a combination of an air pump, an air delivery hose and a dust collection filter element, which is existing technology. It is positioned on the work platform 420 and is controlled by the control unit. When in use, it is connected to the air extraction and dust removal body as needed. The pump-liquid assembly 660 is a combination of a liquid pump, a liquid delivery hose, and a water tank, which is existing technology. It is positioned on the work platform 420 and is controlled by the control unit. When in use, it is connected to the spray dust removal body as needed.

[0048] When the railway tunnel lining repair device of this application embodiment is used: In the process of using the data measured by the detection component 331 to know the amount of extension and retraction of the floating telescopic rod 330 and thus to know the lining that needs to be repaired and the shape of its surrounding lining, the extension and retraction of the working arm 300 and the rotation of the rotating drum 540 and the bottom drum 580 are coordinated to ensure that the shielding belt 610 remains in a slack state throughout the process (although slack, it is still attached to the side guide wheel 380 and will not droop). Before removing the target lining using the working accessory 370, based on factors such as the material, condition, location of the lining to be treated and the requirements of the work site, a comprehensive consideration is made to select either spray dust suppression or suction dust collection (selecting a spray dust collector or a suction dust collector near the side guide wheel 380); the shielding belt 610 is kept taut and one of the loop dust collectors 630 is moved to a position close to the side guide wheel 380, so that the working accessory 370 can pass through the through slot 620 to contact the lining for operation; the loop dust collector 630 is connected to the suction filter assembly 650 or the pump assembly 660, and the shielding belt 610 is kept taut during subsequent operations and dust suppression is carried out by spraying or suction. The shielding belt 610 also serves as a dust barrier, reducing pollution to the work site environment; During manual operation on the work platform 420, the shielding belt 610 is kept taut to increase the safety of the boom 300 during variable-amplitude movement.

[0049] Preferably, the number of each type of U-shaped dust collector 630 on the shielding strip 610 is multiple, for use as spare parts.

[0050] Preferably, one or more side notches 611 are provided on one side of the shielding strip 610; the side notches 611 are trapezoidal notches; the presence of the side notches 611 can prevent the shielding strip 610 from obstructing the work platform 420 from approaching the target work position.

[0051] Preferably, one or more guide rollers 390 are positioned on the side wheel carrier 381 or the end wheel carrier 340; the guide rollers 390 are rigid cylindrical rollers used to guide the shielding belt 610 to prevent it from interfering with the working arm 300; when the working arm 300 is in a horizontal position, the guide rollers 390 are located directly below the side guide rollers 380.

[0052] Preferably, the shielding strip 610 has a row of pin holes positioned along its own length direction; the side wheel carrier 381 has an electric pin that matches the pin holes on the shielding strip 610; during operation, the shielding strip 610 and the working arm 300 are fixed together as needed using the pins and pin holes to further enhance the stability (stable hovering) of the working arm 300.

[0053] Preferably, the two ends of the shielding strip 610 are detachably positioned on the rotating drum 540 and the bottom drum 580, respectively, and can be disassembled and cleaned as needed.

[0054] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. For those skilled in the art, the present invention can have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A lining repair device, characterized in that: Includes a base vehicle (100), a top load plate (200), a boom (300), and a work platform assembly (400); The base vehicle (100) has a track-type bottom travel system (110) positioned at the bottom; the top plate (200) is a horizontal rigid plate positioned on the base vehicle (100), and a controlled rotating load-bearing turntable (210) is positioned at the top; a support frame (220) is fixed at the top center of the load-bearing turntable (210); The working arm (300) is a telescopic rod structure that can extend and retract in a controlled manner. One end is rotatably connected to the support frame (220), and the axis of rotation is parallel to the horizontal ground and can rotate in a controlled manner. Multiple floating telescopic rods (330) are positioned at the end of the working arm (300) away from the support frame (220); the floating telescopic rods (330) are telescopic rods with built-in compression springs and built-in detection components (331) for measuring their own real-time length; an end wheel carrier (340) is fixed at the end away from the working arm (300); the end wheel (350) is a horizontally placed cylindrical wheel body, positioned on the end wheel carrier (340); A component carrier (360) is positioned on the end wheel carrier (340); the component carrier (360) is a rod-shaped or plate-shaped frame, one end of which is rotatably connected to the side of the end wheel carrier (340), and the axis of rotation is the same as the axis of the end wheel (350), and it is rotated in a controlled manner to carry the positioning operation component (370). The work platform component (400) is positioned on the work arm (300) near the floating telescopic pole (330) to carry workers to the target processing location as needed for work.

2. The lining repair device as described in claim 1, characterized in that: The work platform component (400) includes a connecting positioning body (410) and a work platform (420); The connecting positioning body (410) is positioned on the working arm (300) and serves as a connecting support; The working platform (420) is located on one side of the working arm (300). It is a horizontal rectangular plate platform with one side rotatably connected to the side of the connecting positioning body (410). The axis of the rotation shaft is parallel to the horizontal ground. It rotates under the control of the power component and the control unit, and can rotate at an angle greater than 180 degrees. The connecting positioning body (410) is tubular, sleeved and slidably positioned on the working arm (300), and slides under control; During the operation, the work platform (420) is controlled to slide as needed.

3. The lining repair device as described in claim 2, characterized in that: A lifting assembly (120) is positioned on the top of the base vehicle (100); The lifting assembly (120) is a combination of multiple vertical telescopic rods fixed to the top of the base vehicle (100), which are controlled to extend and retract, thereby driving the components it carries to rise and fall. The top plate (200) is provided with multiple horizontal plate-shaped support frames around its perimeter. The number of support frames is four or more, and each of these support frames has a vertical support rod positioned at its bottom. Each support rod has a caster wheel positioned at its bottom; When the lifting assembly (120) is retracted to its shortest state, the casters touch the ground and the bottom travel system (110) is suspended in the air; due to the presence of the casters, the base vehicle (100) can travel off track.

4. The lining repair device as described in any one of claims 1 to 3, characterized in that: The top of the load-bearing turntable (210) is also positioned with a limiting and reinforcing component (320); The restraint and reinforcement assembly (320) includes a vertical support frame (321), a top drum (322), and a safety rope (323); The vertical support frame (321) is a vertical column-shaped frame with a height greater than one-third of the working arm (300) in its fully retracted state. Its bottom is fixed to the top of the bearing turntable (210) and located on one side of the support frame (220), serving as a bearing and support function. The top drum (322) is a horizontally placed winch structure, positioned on top of the vertical frame (321), and rotates under control. The safety rope (323) is a steel wire rope, with one end fixed to the working arm (300) and the other end wound and positioned on the top drum (322); The fixing point of the safety rope (323) on the working arm (300) is close to the middle of the working arm (300); when the working arm (300) rotates, the top drum (322) rotates synchronously to maintain the taut state of the safety rope (323) to ensure the safety of the working arm (300) rotation.

5. The lining repair device as described in any one of claims 1 to 3, characterized in that: It also includes reinforcement frame components; The reinforcement frame assembly includes a first telescopic body (510); the first telescopic body (510) is a telescopic rod structure, one end of which is rotatably connected to the support frame body (220), the axis of rotation is the same as the axis of rotation of the working arm (300) and is located on one side of the working arm (300), and is controlled to extend and rotate. After the base vehicle (100) moves close to the center of the tunnel arch section, the first telescopic body (510) is controlled to rotate and extend to contact the inner wall of the tunnel, and the entire device is clamped by the squeezing force.

6. The lining repair device as described in claim 5, characterized in that: The reinforcement frame assembly also includes a second telescopic body (520) and a connecting assembly frame (530); The structure of the second telescopic body (520) is the same as that of the first telescopic body (510). One end is rotatably connected to the support frame (220). The axis of rotation is the same as that of the working arm (300) and is located on the other side of the working arm (300). It is controlled to extend and rotate. The connecting assembly frame (530) is a horizontally placed rigid rod or a plate-shaped frame; The connecting assembly frame (530) is fixed to the ends of the second telescopic body (520) and the first telescopic body (510) that are far from their own positioning points, and serves as a connector.

7. The lining repair device as described in claim 6, characterized in that: A horizontally positioned rotating drum (540) is located near the first telescopic body (510) and the second telescopic body (520) of the connecting assembly frame (530); A pulling rope (550) is positioned on the rotating drum (540); The pulling rope (550) is a steel wire rope, with one end wound and positioned on the rotating drum (540) and the other end fixed on the working arm (300), always in a taut state; when the working arm (300) rotates, the rotating drum (540) also rotates at the same time, maintaining the taut state of the pulling rope (550) and thus ensuring the safety and stability of the working arm (300) operation.

8. The lining repair device as described in claim 6, characterized in that: The end wheel carrier (340) is provided with side guide wheels (380) and side wheel carriers (381) for supporting the side guide wheels (380) on both sides; The carrying turntable (210) directly below the working arm (300) is equipped with a drum support (581) and a bottom drum (580) positioned on the drum support (581): A horizontally positioned rotating drum (540) is located near the first telescopic body (510) and the second telescopic body (520) of the connecting assembly frame (530); The side guide wheel (380) is a horizontally placed rigid cylindrical wheel body with the same diameter as the end wheel (350) and coaxial with the end wheel (350), and is rotatably connected to the side wheel carrier (381) around its own axis. The drum support (581) is a rigid frame fixed on the bearing turntable (210); the bottom drum (580) is a horizontally placed drum structure positioned on the drum support (581).

9. The lining repair device as described in claim 8, characterized in that: It also includes dust shielding components; The dust removal and shielding assembly includes a shielding strip (610), a U-shaped dust removal body (630), a combination joint (640), an air extraction and dust filtration assembly (650), and a pump-liquid assembly (660). One end of the shielding strip (610) is wound and positioned on the rotating drum (540), and the other end is wound and positioned on the bottom drum (580), always in contact with the two side guide wheels (380); The shielding strip (610) has multiple rectangular through slots (620) positioned on it; the width of the through slot (620) is greater than the axial length of the end wheel (350) and less than 1.5 times the axial length of the end wheel (350); The circular dust collector (630) is a circular flexible plate that is tightly attached to and fixed on the surface of the shielding strip (610) away from the working arm (300) and surrounds the through slot (620). It corresponds one-to-one with the through slot (620), has a built-in fluid channel, and has dense through holes on the surface away from the shielding strip (610). The combination connector (640) is positioned on the surface of the shielding strip (610) near the working arm (300), and is a quick-connect connector that communicates with the fluid channel built into the rotary dust collector (630). There are two types of rotary dust collectors (630), and the diameters of the through holes on the two types of rotary dust collectors (630) are different. The two types of rotary dust collectors (630) are used for spray dust suppression and suction dust collection, respectively, and are spray dust collectors and suction dust collectors. The air extraction and dust removal assembly (650) is connected to the air extraction and dust removal body in a timely manner; the pump-liquid assembly (660) is used to supply liquid to the spray dust removal body in a timely manner.

10. A method of using a lining repair device, characterized in that: The steps are as follows: (The text abruptly ends here, so the translation stops as well.) When auxiliary operations are required, first proceed along the track to the vicinity of the target repair location in the tunnel; Then, control the load-bearing turntable (210) to rotate 90 degrees, and control the working arm (300) to rotate and extend, so that the end wheel (350) abuts against the lining inside the tunnel and the floating telescopic rod (330) is in a compressed state. Then, the working arm (300) is rotated so that the end wheel (350) rolls against the lining to be repaired and its surrounding lining; the data measured by the detection component (331) is used to know the amount of extension and retraction of the floating telescopic rod (330) and thus the shape of the lining to be repaired and its surrounding lining. The floating telescopic rod (330) is retracted, causing the end wheel (350) to detach from the tunnel wall; The control accessory carrier (360) rotates some of the working accessories (370) to a position away from the floating telescopic rod (330); Based on the data measured by the detection component (331), the extension and retraction of the working arm (300), the rotation of the working arm (300), the movement of the base carrier (100) and the rotation of the accessory carrier (360) are coordinated by remote control, and the removal of the problematic lining is completed by using one or more working accessories (370). Control the boom (300) to rotate to a horizontal position, and the operator climbs onto the work platform assembly (400); control the boom (300) to rotate and extend, and complete the lining repair work on the work platform assembly (400); Clean up the work site and complete the lining repair.