A collaborative method for determining prestressed anchor support parameters in deep-buried soft rock tunnels based on measured loosening zones.
By measuring the loosening zone using the acoustic method and optimizing the anchor bolt parameters through numerical simulation, the quantitative design problem of anchor bolt support parameters in deeply buried soft rock tunnels was solved. This achieved precise matching of anchor bolt length and prestress, resolved the problem of insufficient or redundant support, and improved the safety and long-term stability of tunnel construction.
Patent Information
- Application Number
- CN202611282326.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-24
- Publication Date
- 2026-11-17
AI Technical Summary
Existing methods for determining anchor bolt support parameters lack quantitative design basis based on field measurement data, fail to consider the dynamic development law of loosening zone and the difference between left and right sides, and lack a closed-loop verification mechanism, leading to problems of insufficient or redundant support in the construction of deep-buried soft rock tunnels.
The loosening zone of a deep-buried soft rock tunnel at different excavation stages was measured using the acoustic method. The thickness difference between the left and right loosening zones was identified, the length of the prestressed anchor bolts and the asymmetric anchor bolt arrangement scheme were determined, and the prestress of the anchor bolts was optimized by combining numerical simulation. A closed-loop control process of measurement-design-construction-re-measurement was established.
It achieves precise matching of anchor bolt length and prestress, avoids material waste and insufficient support, effectively controls surrounding rock deformation, and improves tunnel construction safety and long-term stability.
Smart Images

Figure CN123109735A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel and underground engineering support design technology, specifically a method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones. Background Technology
[0002] As my country's transportation infrastructure construction continues to extend to the western mountainous areas, the number of deep-buried soft rock tunnel projects is increasing. Taking the Haba Snow Mountain Tunnel on the Lijiang-Xianggelila section of the Yunnan-Tibet Railway as an example, the tunnel is 9,523 meters long and has a maximum burial depth of 1,155 meters. It is located on the southeastern edge of the Qinghai-Tibet Plateau and belongs to the western boundary fault zone of the Sichuan-Yunnan rhomboid fault block. The geological structure is complex and the neotectonic movement is intense. The tunnel mainly passes through sandy slate, slate interbedded with limestone and foliated basalt strata. The overall strength of the surrounding rock is low and joints and fissures are well developed.
[0003] Under such conditions of extremely deep burial and high ground stress in soft rock, the tunnel construction process encountered extremely serious large deformation problems: the arch settlement reached 980.4 mm, the horizontal convergence reached 1935.27 mm, the initial support was severely damaged, the secondary lining collapsed as a whole for 189 m, and support failures such as steel frame twisting and breaking, shotcrete cracking and spalling, and anchor bolt breakage occurred many times during the construction process. The success or failure of large deformation control directly determines the construction safety and long-term operational stability of this type of tunnel.
[0004] For example, patent CN115796456B discloses a method for evaluating and controlling the stability of surrounding rock in complex underground engineering projects. Combining on-site geological conditions with traditional support design methods, it preliminarily determines the design parameters for anchored support and prepares a model of the surrounding rock under anchored support. Tests are conducted using a three-dimensional dynamic-static coupling loading system. Based on the range of the loosened zone of the surrounding rock after loading and the preset anchored support length, the design length of the support components is adjusted. Stability evaluation indicators for the surrounding rock support system are established based on preset roadway cross-sectional parameters and the amount of surrounding rock movement after loading, and the anchoring strength and density are adjusted. By combining the peak stress of the support system before adjustment with the bearing capacity of the surrounding rock support system after adjustment, a bearing safety index for the support components is established. The anchored support design parameters are then optimized to determine the anchored support design parameters that meet the requirements for surrounding rock stability control.
[0005] However, in existing technologies, the anchor support parameters for some deep-buried soft rock tunnels are mostly determined by engineering experience or pure numerical simulation to determine the anchor length. This fails to establish a quantitative matching relationship between the measured data of the loosened zone of the surrounding rock and the anchor parameters. The design process does not consider the dynamic evolution law of the gradual expansion of the loosened zone under the three-stage excavation process. At the same time, it ignores the problem of uneven thickness of the loosened zone on the left and right sides of the tunnel cross section caused by geological bias and rock stratum attitude. The symmetrical anchor layout with uniform specifications across the entire cross section is generally adopted, which easily leads to insufficient support in some areas and redundant support in other areas. Traditional support design only follows a one-way implementation process of exploration, design, and construction, and lacks a closed-loop control mechanism based on on-site measurement results for verification and reverse iterative optimization of support parameters. It is difficult to complete the precise design of anchor parameters based on the actual damage state of the surrounding rock.
[0006] To address the aforementioned issues, there is an urgent need for innovative design based on the existing method for collaboratively determining anchor bolt support parameters. Summary of the Invention
[0007] The purpose of this invention is to provide a collaborative method for determining prestressed anchor bolt support parameters in deep-buried soft rock tunnels based on actual measurements of loosening zones, in order to address the technical deficiencies of existing anchor bolt support parameter determination methods mentioned in the background art, such as lack of quantitative design basis based on field measured data, failure to consider the dynamic development law of loosening zones and differences between the left and right sides, and lack of closed-loop verification mechanism.
[0008] To achieve the above objectives, the present invention provides the following technical solution: a method for collaboratively determining prestressed anchor bolt support parameters for deep-buried soft rock tunnels based on measured loosening zones, the method comprising the following steps: S1. The acoustic method was used to conduct on-site tests on the loosening zone of the surrounding rock at different excavation stages of the deep-buried soft rock tunnel. The range of the loosening zone after the excavation of the upper bench, the middle bench, and the lower bench was obtained respectively, and the thickness difference of the loosening zone on the left and right sides of the tunnel was identified simultaneously.
[0009] S2. Based on the measured range of the loosening zone, determine the length of the prestressed anchor rod. The length of the prestressed anchor rod for each step shall be determined with the principle that the anchor rod length is not less than the thickness of the loosening zone of the corresponding step.
[0010] S3. Establish a tunnel deformation mechanical response model under different prestressed anchor bolt lengths and different anchor bolt prestress values through numerical simulation, and determine the optimal anchor bolt prestress value with the goal of minimizing tunnel arch settlement and horizontal convergence.
[0011] S4. Based on the measured thickness difference of the loosened ring on the left and right sides of the tunnel, the anchor bolt layout parameters on both sides of the tunnel are configured differently, and an asymmetric anchor bolt layout scheme is formulated to adapt to the characteristics of surrounding rock bias and uneven rock strata.
[0012] S5. The determined anchor length, anchor prestress, and asymmetric anchor arrangement scheme are applied to the on-site construction, and the loosening zone control effect is verified by retesting using the sonic method.
[0013] Preferably, the deeply buried soft rock is sandy slate, slate interbedded with limestone or foliated basalt, the tunnel burial depth is ≥800m, and the surrounding rock strength-stress ratio is ≤0.5.
[0014] Preferably, the field testing method in S1 is as follows: S1a. Drill holes in the test section using a drilling rig. The hole diameter is larger than the probe diameter. The drilling depth for the upper step is 8-12m, and the drilling depth for the lower step is 10-15m.
[0015] S1b. Place the acoustic test probe into the borehole at a position of 0.3-0.8m and inject water using a water injection system at a pressure of 15-25kPa to form acoustic coupling between the probe and the borehole wall.
[0016] S1c. The elastic longitudinal wave velocity of the rock mass is measured and recorded using an acoustic wave tester.
[0017] S1d: Push the probe into the hole 0.3-0.8m, and repeat S1b and S1c until the bottom of the hole is measured.
[0018] S1e, the critical depth of the loosening zone is taken as the endpoint where the wave velocity of the surrounding rock changes significantly. When the wave velocity tends to stabilize, it indicates that the loosening zone has been exceeded.
[0019] By adopting the above technical solutions, standardized and high-precision acoustic wave detection of surrounding rock can be completed at each excavation section of the tunnel. Stable good acoustic coupling between the probe and the borehole wall can be achieved. Longitudinal wave velocity data of rock mass can be continuously collected at equal intervals along the borehole. Based on the wave velocity change characteristics, the boundary of the loosened zone can be accurately determined. The thickness of the loosened zone corresponding to the upper, middle and lower steps and the thickness difference between the left and right sides of the section can be accurately obtained in stages. This provides reliable and continuous field measurement data support for the subsequent collaborative quantitative design of anchor bolt length, prestress, and asymmetric layout scheme.
[0020] Preferably, the S1 test obtains the evolution characteristics of the loosened zone in stages as follows: the range of the loosened zone of the surrounding rock continues to expand with the excavation of the upper, middle and lower benches; due to the influence of geological bias and rock stratum attitude, there is a difference in the thickness of the loosened zone on the left and right sides of the same excavation section.
[0021] By adopting the above technical solution, we can clearly understand the dynamic expansion law of the loosened zone of the surrounding rock under the three-stage step-by-step excavation, and accurately identify the thickness difference of the loosened zone on both sides of the cross section. This provides an objective geological basis for determining the anchor length and formulating an asymmetric anchor layout scheme based on the step-by-step differentiation, avoiding the problems of insufficient support or material waste caused by uniform support parameters, and achieving a precise anchoring design that matches the degree of damage to the surrounding rock.
[0022] Preferably, the length design of the S2 anchor bolt follows the following rules: the length of the arch anchor bolt penetrates the loosening ring of the upper step and extends into the intact surrounding rock by 0.5-1.0m; the length of the sidewall anchor bolt penetrates the maximum loosening ring after the middle and lower steps are excavated and extends into the intact surrounding rock by 1.0-2.0m.
[0023] By adopting the above technical solutions, it can be ensured that the arch and sidewall anchors can completely penetrate the loose and fractured surrounding rock formed in the corresponding excavation stage, and extend into the intact and stable surrounding rock behind to form a reliable anchoring foundation. This effectively connects the surface fractured rock mass with the deep intact rock mass into a whole. Differentiated anchoring depths are set according to the different development ranges of the loosening zone of the upper and middle-lower steps. This avoids large deformation diseases induced by the anchors being too short to restrain the deep fractured surrounding rock, and also avoids the waste of steel materials caused by blindly lengthening the anchors. It achieves precise matching between the anchor length and the actual damage range of the surrounding rock, and improves the overall stability of the arch and sidewall surrounding rock of the deep buried soft rock tunnel.
[0024] Preferably, in step S3, by comparing the deformation patterns of the surrounding rock through multiple sets of anchor bolt prestressing conditions, it can be seen that there is an optimal control range for the anchor bolt prestress. Specifically, when the anchor bolt prestress is 100-140kN, the deformation control effect of tunnel arch settlement and horizontal convergence reaches its optimal level; when the prestress is increased in the range of 20kN-100kN, the deformation suppression effect of the surrounding rock is significantly improved; when the prestress exceeds 100kN and continues to increase to the range of 180kN, the reduction in the deformation of the surrounding rock narrows significantly, and the deformation control effect tends to saturate.
[0025] By adopting the above technical solution, the nonlinear correlation between anchor prestress and tunnel surrounding rock deformation can be quantitatively clarified through multi-condition numerical simulation, and the critical inflection point of deformation control effect can be accurately identified. Increasing the prestress in the range of 20kN-100kN can effectively suppress crown settlement and horizontal convergence, while the benefit of surrounding rock improvement decreases significantly after the prestress exceeds 140kN. Continuing to increase the prestress will only needlessly increase the difficulty of tensioning construction and material costs. This solution locks in the optimal prestress range of 100-140kN, which takes into account the construction economy while achieving efficient control of surrounding rock deformation in deeply buried soft rock tunnels, and avoids the problems of insufficient support effect or cost waste caused by arbitrarily setting the prestress based on experience.
[0026] Preferably, in step S3, a deformation mechanical response model of the tunnel surrounding rock is constructed using finite difference numerical simulation software, and the surrounding rock calculation adopts the Mohr-Coulomb model or the pervasive joint model.
[0027] By adopting the above technical solutions, the finite difference numerical simulation software can realistically reproduce the stress and deformation evolution of the surrounding rock during the entire process of excavation and unloading of deep-buried soft rock tunnels and the application of prestressing to anchor bolts. By selecting the Mohr-Coulomb model or the pervasive joint model, it can be adapted to homogeneous soft rock and fractured slate strata with a large number of bedding planes and joints, respectively, accurately reflecting the mechanical behavior of rock mass shear failure and joint slip, improving the authenticity and reliability of tunnel deformation calculation results under multiple prestressing conditions, and providing an accurate numerical analysis basis that fits the actual engineering situation for selecting the optimal anchor bolt prestressing range.
[0028] Preferably, S4 designs an asymmetric anchor bolt arrangement scheme based on the difference in the measured thickness of the loosened ring on the left and right sides of the tunnel. Specifically, when the thickness of the loosened ring on the left is greater than that on the right, at least one of the following methods is used to improve the support strength of the left surrounding rock area: denser anchor bolt arrangement or longer anchor bolt length. When the thickness of the loosened ring on the right is greater than that on the left, at least one of the following methods is used to improve the support strength of the right surrounding rock area: denser anchor bolt arrangement or longer anchor bolt length.
[0029] By adopting the above technical solutions, the support strength can be matched according to the actual degree of damage of the surrounding rock on both sides of the cross section. For the side of the surrounding rock with a larger loose zone and more severe damage, reinforcement measures such as denser and longer anchor bolts are adopted to specifically constrain the large unilateral deformation caused by bias pressure and uneven rock strata. This breaks the inherent pattern of uniformly symmetrical anchor bolts throughout the cross section, avoids excessive anchor bolt placement on the side with a smaller loose zone, which would lead to material waste, and eliminates the hidden danger of insufficient support bearing capacity on the fractured side. It ensures that the anchor bolt support strength is matched with the degree of damage of the surrounding rock on both sides, balances the overall stress of the cross section, and effectively improves the engineering problems of bias deformation and excessive local convergence in soft rock tunnels with high ground stress.
[0030] Preferably, when the difference in thickness of the loosened ring on both sides of the tunnel is in the range of 0.5-1.5m, the anchor density on the side with the larger loosened ring is increased by 10%-30% compared to the other side, or the anchor length is increased by 1-2m compared to the other side.
[0031] By adopting the above technical solutions, quantitative reinforcement standards are provided for the most common working conditions of 0.5-1.5m loosening zone thickness difference in engineering, eliminating the need to rely on subjective experience to judge the extent of support reinforcement. By limiting the increase in anchor density to 10%-30% or the lengthening of anchors to 1-2m, the support shortcomings of the surrounding rock on the side with a larger loosening zone can be fully compensated, and the deformation of the surrounding rock on one side can be effectively controlled. At the same time, the amount of support materials used and the construction cost will not be excessively increased, and the stress on both sides of the surrounding rock can be balanced. This provides a quantitative construction basis that can be directly implemented for the design of asymmetric anchor bolts in deeply buried soft rock tunnels with eccentric pressure.
[0032] Preferably, in step S5, after implementing the support construction using the anchor bolt length (S2), anchor bolt prestress (S3), and asymmetric anchor bolt arrangement (S4), the loosened ring thickness is re-measured by acoustic wave, and the reduction range of the loosened ring before and after support is used as the evaluation criterion for the surrounding rock control effect; if the loosened ring reduction effect does not meet the standard, the process returns to step S1 to re-measure the loosened ring and iteratively adjust the anchor bolt support parameters.
[0033] By adopting the above technical solutions, a complete closed-loop control process of actual measurement, design, construction, re-measurement, and iteration is established. The degree of shrinkage of the loosened zone after support is intuitively quantified by sonic re-measurement, and the actual control effect of the entire set of anchor bolt support parameters is objectively evaluated. If the surrounding rock reinforcement effect does not meet expectations, the data can be re-collected by going back to the loosened zone measurement process. The entire set of support parameters, such as anchor bolt length, prestress, and left-right layout differences, can be optimized simultaneously to continuously match the actual state of the surrounding rock on site and continuously iterate and optimize the support system, thus ensuring the long-term stability of the surrounding rock of the deep-buried soft rock tunnel from the process level.
[0034] Compared with the prior art, the beneficial effects of the present invention are: 1. This invention achieves quantitative, tiered anchor bolt design based on field measurements. Using acoustic measurement data of the loosened rock zone as the core basis, it establishes a quantitative matching rule between the loosened zone range and the anchor bolt length, eliminating the reliance on empirical design methods that estimate anchor bolt lengths based on tunnel span ratios. Simultaneously, it elucidates the dynamic evolution law of the continuous expansion of the loosened zone during the three-stage excavation process, and differentiates the anchor bolt lengths for the upper stage and sidewalls, avoiding material waste or insufficient deep anchoring caused by uniform anchor bolts across the entire cross-section. Combined with the monitoring law of load sharing in the three-layer initial support, it is known that the first initial support bears nearly half of the surrounding rock load. This method specifically penetrates the surface loosened zone, strengthening the core load-bearing structure from the perspective of stress mechanism, achieving precise anchoring with a tailored approach for each tunnel, and effectively avoiding defects such as steel frame breakage and initial support collapse caused by insufficient anchor bolt length.
[0035] 2. This invention proposes an asymmetric anchor bolt arrangement scheme adapted to the uneven characteristics of surrounding rock, which effectively controls large deformation of biased surrounding rock. Addressing the engineering challenge of differences in the thickness of the loosened zone on the left and right sides of the tunnel cross-section caused by geological bias and rock strata attitude, the density or length of the anchor bolts is adjusted differentially according to the difference in damage on both sides. For the side with a larger loosened zone, reinforcement measures such as increasing the density and length of the anchor bolts are adopted to resolve the contradiction of excessive support on one side and insufficient bearing capacity on the other side in traditional symmetrical anchor bolts. When the difference in the loosened zone between the two sides is in the typical range of 0.5-1.5m, a density increase of 10%-30% or a length increase of 1-2m can balance the constraint strength of the surrounding rock on both sides, suppressing excessive convergence and settlement deformation on one side.
[0036] 3. This invention determines the economically optimal prestressing range for anchor bolts through numerical simulation, balancing the control effect on surrounding rock with construction costs; it analyzes the nonlinear variation law of surrounding rock deformation through multiple sets of prestressing conditions, identifying the optimal prestressing range of 100-140kN; when the prestress is increased from 20kN to 100kN, the effect of suppressing tunnel arch settlement is significantly improved, while the deformation improvement range narrows significantly after the prestress exceeds 140kN, and the marginal benefit is significantly saturated; by limiting the optimal prestress value, it avoids the problems of increased construction difficulty and increased material costs caused by blindly increasing the anchoring prestress, achieving optimal control of surrounding rock deformation with minimal cost input.
[0037] 4. This invention constructs a complete closed-loop system of measurement-design-remeasurement iteration, which can dynamically optimize support parameters and achieve outstanding engineering shape control effect. It no longer adopts the traditional unidirectional process of survey-design-construction. After the support is completed, the loosening zone is remeasured by sound wave. The control effect is judged according to the reduction range. If the standard is not met, the measurement is carried out again and the entire set of anchor bolt parameters are adjusted iteratively. The range of the loosening zone of the tunnel is greatly reduced, the settlement of the arch and the horizontal convergence deformation of the upper step are reduced, the problem of large deformation of deep buried soft rock tunnels is alleviated, and the tunnel construction safety and long-term operation stability are improved. Attached Figure Description
[0038] Figure 1 This is a schematic diagram of the process of the present invention.
[0039] Figure 2 This is a schematic diagram of the acoustic method for loosening coil testing according to the present invention.
[0040] Figure 3 This is a schematic diagram illustrating the development pattern of the loosened zone at different excavation stages of the present invention.
[0041] Figure 4 This is a graph showing the settlement variation of the tunnel arch under different anchor bolt lengths according to the present invention.
[0042] Figure 5 This is a curve showing the tunnel deformation control effect under different anchor prestresses according to the present invention.
[0043] Figure 6 This is a schematic diagram of the asymmetric anchor bolt arrangement scheme of the present invention. Detailed Implementation
[0044] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0045] Example 1, please refer to Figures 1-6The present invention provides the following technical solution: a method for collaboratively determining prestressed anchor bolt support parameters for deep-buried soft rock tunnels based on measured loosening zones, the method comprising the following steps: S1. The acoustic wave method was used to conduct on-site testing of the loosened zone of the surrounding rock at different excavation stages of a deep-buried soft rock tunnel. The range of the loosened zone was obtained after the excavation of the upper bench, the middle bench, and the lower bench. The thickness difference of the loosened zone on the left and right sides of the tunnel was identified simultaneously. The specific on-site testing method is as follows: S1a. Drill holes in the test section using a drilling rig. The hole diameter is larger than the probe diameter. The drilling depth for the upper step is 8-12m, and the drilling depth for the lower step is 10-15m.
[0046] S1b. Place the acoustic test probe into the borehole at a position of 0.3-0.8m and inject water using a water injection system at a pressure of 15-25kPa to form acoustic coupling between the probe and the borehole wall.
[0047] S1c. The elastic longitudinal wave velocity of the rock mass is measured and recorded using an acoustic wave tester.
[0048] S1d: Push the probe into the hole 0.3-0.8m, and repeat S1b and S1c until the bottom of the hole is measured; S1e, the critical depth of the loosening zone is taken as the endpoint where the wave velocity of the surrounding rock changes significantly. When the wave velocity tends to stabilize, it indicates that the loosening zone has been exceeded.
[0049] In this embodiment, the deeply buried soft rock is sandy slate, slate interbedded with limestone or foliated basalt, the tunnel burial depth is ≥800m, and the surrounding rock strength-stress ratio is ≤0.5.
[0050] The loosened zone is the overall thickness of the fractured area resulting from stress redistribution, rock mass fissure initiation and penetration, and structural damage after the three-stage excavation and unloading of a deeply buried soft rock tunnel. This zone is not a fixed value but expands dynamically with each excavation stage. It accurately reflects the degree of damage to the surrounding rock, the depth of unloading influence, and the stability of the rock mass at different construction stages, serving as the core measured basis for subsequent differentiated anchor bolt length design.
[0051] The difference in the thickness of the loosened zone on the left and right sides of the tunnel is an asymmetric difference in the thickness of the loosened zone at the left and right arch wall positions on the same test section of the tunnel. Affected by inherent geological differences such as stratum attitude, tectonic stress, and topographic bias, the unloading damage degree of the surrounding rock on both sides of the section is inconsistent, resulting in a significant deviation in the development depth of the fractured zone on both sides. This difference directly reflects the anisotropy and bias damage characteristics of the surrounding rock of the deeply buried soft rock tunnel, and is the direct basis for the asymmetric anchor bolt differentiated support design.
[0052] The amplitude of the change in wave velocity in the surrounding rock is the dynamic fluctuation of the elastic longitudinal wave of the rock mass along the borehole depth. In the fractured and loosened zone, the rock mass has developed fissures and a loose structure, resulting in high resistance to sound wave propagation, low overall wave velocity, and violent fluctuations. After entering the undisturbed and intact surrounding rock area, the rock mass structure becomes dense and continuous, the wave velocity increases rapidly and gradually stabilizes. The location of the abrupt change in wave velocity and the magnitude of the fluctuation can accurately define the interface between the damaged area and the intact rock mass, enabling precise quantitative identification of the loosened zone boundary.
[0053] In this embodiment, S1 obtained the following characteristics of the loosening zone evolution through phased testing: the range of the loosening zone of the surrounding rock continued to expand with the excavation of the upper, middle and lower benches; due to the influence of geological bias and rock stratum attitude, there was a difference in the thickness of the loosening zone on the left and right sides of the same excavation section.
[0054] Specifically: The loosened zone after excavation of the upper and middle steps ranges from 2.0 to 4.5 meters, with the left side measuring 4.0 to 4.5 meters and the right side measuring 3.0 to 3.5 meters.
[0055] The loosened zone after the middle bench excavation ranges from 4.5 to 8.0 meters, with the left side measuring 7.0 to 7.5 meters and the right side measuring 7.5 to 8.0 meters.
[0056] The loosened zone after the lower step excavation ranges from 5.5 to 11.0 meters, with the left side measuring 9.5 to 10.5 meters and the right side measuring 10.5 to 11.0 meters.
[0057] When a deep-buried soft rock tunnel is constructed using a three-stage excavation method, each stage of excavation disrupts the original stress balance of the strata. The continuous increase in the free face causes the stress within the surrounding rock to be released, transferred, and redistributed continuously. The excavation of the upper stage only causes local unloading damage to the upper surrounding rock, and the development of the loosening zone is limited. After the middle stage is excavated, the excavation section is further expanded, the constraint conditions of the upper surrounding rock are continuously weakened, the original fractures are further extended, and the overall depth of the loosening zone increases significantly. When the lower stage is excavated and the entire section is formed, the unloading disturbance of the surrounding rock reaches its peak, the degree of rock mass fracture penetration is the highest, and the loosening zone develops to the maximum depth of the entire process. The loosening zone exhibits a progressively expanding evolutionary pattern throughout the entire excavation process. The depth of surrounding rock damage corresponding to different excavation stages is not consistent, making it impossible to use uniform support parameters to match the surrounding rock state at each stage.
[0058] The diagonal distribution of geological strata, uneven regional tectonic stress, and external topographic pressure combine to cause differences in the equivalent geostress experienced by the surrounding rock on the left and right sides of the same tunnel cross-section. The rock mass on the side with higher stress is more prone to tensile and shear fractures, resulting in a deeper loosened zone. Conversely, the rock mass on the side with relatively lower stress exhibits better integrity, but the degree of damage is weaker, ultimately leading to an inconsistent thickness of the loosened zone on the left and right sides of the same cross-section. This thickness difference does not disappear with subsequent bench excavation but expands synchronously as a whole, making it a core measured indicator for designing asymmetric anchor support schemes.
[0059] Each excavation stage exhibits an asymmetric characteristic where one side has a deeper loosening zone and the other side is relatively shallower. As excavation progresses, the thickness of the loosening zones on both sides increases synchronously, with the difference between the two remaining stable within the range of 0.5-1.5m. This quantitative difference can be directly used as a quantitative basis for the differentiated adjustment of anchor bolt density and length, enabling precise guidance for asymmetric support design that reinforces one side while simplifying the other, thus avoiding the support imbalance problem caused by traditional uniform symmetrical support.
[0060] S2. Based on the measured range of the loosening zone, determine the length of the prestressed anchor rod. The length of the prestressed anchor rod for each step shall be determined with the principle that the anchor rod length is not less than the thickness of the loosening zone of the corresponding step.
[0061] In this embodiment, the design of the S2 anchor length follows the following rules: the length of the arch anchor penetrates the loosening ring of the upper step and extends into the intact surrounding rock by 0.5-1.0m; the length of the sidewall anchor penetrates the maximum loosening ring after the middle and lower steps are excavated and extends into the intact surrounding rock by 1.0-2.0m.
[0062] Specifically, the prestressed anchor bolts for the upper step in S2 are 5m long, penetrating the loosening zone of the upper step by 4.0-4.5m and entering the intact surrounding rock by 0.5-1.0m; the long anchor bolts for the sidewalls are 10-12m long, penetrating the loosening zones of the middle and lower steps by 7.5-11.0m and entering the intact surrounding rock by 1.0-2.0m.
[0063] The principle that the length of the anchor bolt should not be less than the thickness of the loosened ring of the corresponding step is the basic premise for ensuring that the anchoring system can play a supporting role. If the entire effective anchoring section of the anchor bolt is arranged in the loosened and fractured zone, the fractured rock mass has well-developed fissures and poor integrity, which cannot provide a stable gripping force for the anchor bolt and makes it difficult to restrain the continuous deformation of the surrounding rock. The requirement that the length of the anchor bolt covers the entire thickness of the loosened ring allows one end of the anchor bolt to be anchored into the surface fractured surrounding rock, and the other end to extend into the undisturbed intact rock mass behind it. Relying on the intact rock mass to provide a reliable anchoring support point, the shallow fractured rock mass and the deep stable rock mass are connected into a whole, preventing the further expansion and extension of the surrounding rock fissures.
[0064] The length of a prestressed anchor bolt refers to the overall effective anchorage length of the anchor bolt, which includes the free section passing through the fractured zone of the loosened ring and the anchorage section embedded in the intact bedrock. The length value is not a fixed and uniform standard, and needs to be dynamically adjusted according to the actual thickness of the loosened ring measured at each excavation stage, which is different from the experience-based design of traditional fixed-length anchor bolts. At the same time, the anchor bolt is equipped with tension prestress, which can actively apply confining pressure to the surrounding rock, close the internal cracks of the rock mass, and further improve the bearing capacity of the surrounding rock itself.
[0065] The arch is only disturbed by the excavation of the upper bench, and the loosening zone has a limited depth. Only short anchors are needed to meet the current reinforcement requirements. The sidewall will be continuously disturbed by the superimposed excavation of the middle and lower benches. The final depth of the loosening zone is much greater than that of the arch. Therefore, longer anchors are required. The differentiated length settings of the two types of anchors not only avoid the material waste and low construction efficiency caused by uniform long anchors across the entire section, but also achieve full coverage anchoring for different locations of surrounding rock damage, thus balancing support safety and engineering economy.
[0066] After penetrating the loosened ring, the anchor bolt extends an additional 0.5-2.0m into the intact surrounding rock. This section is the core load-bearing anchoring section. The intact rock mass has a dense structure and stable mechanical properties, which can fully bear the deformation pressure of the surrounding rock transmitted by the anchor bolt and prevent the anchor bolt from slipping and failing as a whole. The extension length is differentiated according to the degree of surrounding rock fragmentation. A shorter anchoring section is reserved for the arch where the surrounding rock disturbance is relatively weak. The surrounding rock in the deeper part of the sidewall has a higher risk of deformation, so the embedded section is lengthened accordingly to ensure the long-term stability and reliability of the anchoring structure.
[0067] This invention establishes for the first time a quantitative design method for determining the anchor bolt length by measuring the loosening zone using the acoustic method and aiming to penetrate the loosening zone. Specifically: Upward step loosening ring 2.0-4.5m → anchor bolt 5m; The loosening zone of the middle and lower steps is 7.5-11.0m → long anchor rod 10-12m; This method upgrades the determination of anchor bolt length from empirical values (such as anchor bolt length being 1 / 3 to 1 / 2 of the tunnel span) to scientific calculations based on on-site measured data, realizing precise support design for each tunnel. Taking Haba Snow Mountain Tunnel as an example, according to the traditional empirical method, the anchor bolt length is 1 / 3 to 1 / 2 of the tunnel span (about 7m), which is 2.3 to 3.5m, much smaller than the loosening zone of the upper step of 4.0 to 4.5m. This is one of the important reasons for the serious damage to the initial support.
[0068] System testing revealed the dynamic development pattern of the loosened zone at different excavation stages of deep-buried soft rock tunnels, specifically: Excavation stage Loosening range After the steps were excavated 2.0-4.5m After the middle bench was excavated 4.5-8.0m After the step-down excavation 5.5-11.0m As the excavation progresses, the loosened zone expands continuously. The excavation of the middle bench has a significant impact on the loosened zone of the upper bench, increasing it by 3-4m. After the excavation of the lower bench, the loosened zone further expands to 10.5-11.0m. Therefore, the anchor bolt design should be determined in stages. For the upper bench, 5m anchor bolts are used to penetrate the current loosened zone, and for the sidewalls, 10-12m long anchor bolts are used to penetrate the final loosened zone.
[0069] S3. Establish a tunnel deformation mechanical response model under different prestressed anchor bolt lengths and different anchor bolt prestress values through numerical simulation, and determine the optimal anchor bolt prestress value with the goal of minimizing tunnel arch settlement and horizontal convergence.
[0070] In this embodiment, by comparing the deformation patterns of the surrounding rock through multiple sets of anchor bolt prestressing conditions in S3, it can be seen that there is an optimal control range for the anchor bolt prestress. Specifically, when the anchor bolt prestress is 100-140kN, the deformation control effect of tunnel arch settlement and horizontal convergence reaches the optimal level; when the prestress is increased in the range of 20kN-100kN, the deformation suppression effect of the surrounding rock is significantly improved; when the prestress exceeds 100kN and continues to increase to the range of 180kN, the reduction in the deformation of the surrounding rock narrows significantly, and the deformation control effect tends to saturate.
[0071] The optimal control range for anchor prestress is an objective mechanical law formed by the coupling of the benefits of surrounding rock deformation control with engineering costs and construction difficulty. In the low prestress range, the active restraint effect of the anchor is insufficient, the surrounding rock fissures cannot be effectively closed, and the deformation control effect is poor. As the prestress gradually increases, the active support force of the anchor is fully utilized, and the deformation suppression effect of the surrounding rock is significantly improved. However, after the prestress exceeds the critical value, the overall integrity of the surrounding rock has basically stabilized. Continuing to increase the prestress cannot effectively reduce the deformation of the surrounding rock, but will only continue to increase the difficulty of anchor tensioning construction, anchor wear and tear, and engineering costs, resulting in performance saturation and cost redundancy. Thus, the optimal prestress value range that takes into account both support effect and economic benefits is formed.
[0072] In this embodiment, S3 uses finite difference numerical simulation software to construct a deformation mechanical response model of the tunnel surrounding rock, and the surrounding rock calculation adopts the Mohr-Coulomb model or the pervasive joint model.
[0073] The tunnel deformation mechanical response model is a refined numerical calculation model built based on actual tunnel excavation and support conditions. It can realistically reproduce the mechanical behavior of the entire process of excavation unloading, anchor installation, and prestressing tensioning in deep-buried soft rock tunnels. This model can accurately simulate the dynamic changes in stress redistribution, crack development, crown settlement, and sidewall horizontal convergence under different anchor lengths and different combinations of tensioning prestressing parameters. It can quantify the control effect of various support parameters on surrounding rock deformation, providing an intuitive and accurate numerical calculation carrier for multi-condition parameter comparison and optimal support parameter selection, avoiding the subjective bias of traditional experience-based selection.
[0074] The surrounding rock calculation employs either the Mohr-Coulomb model or the widespread joint model, providing a targeted modeling selection scheme for soft rock strata of different depths. The Mohr-Coulomb model is suitable for soft rock strata with relatively homogeneous integrity and low degree of joint and fracture development, and can accurately simulate core mechanical characteristics such as rock mass shear failure and plastic deformation. The widespread joint model is specifically adapted to slate and schistosified rock masses with well-developed bedding and numerous structural fractures, and can reproduce the special failure modes of rock mass anisotropy, joint slip, and layered deformation. The flexible selection of the two models can minimize the mechanical differences between numerical simulation and actual surrounding rock in the field, ensuring the accuracy and reliability of the calculation results.
[0075] Based on the geological information of the surrounding rock obtained from tunnel exploration and field testing, the model selection was completed: when the integrity of the surrounding rock mass is good and the bedding and joint development is weak, the Mohr-Coulomb model is selected; when the surrounding rock mass has dense development of foliation, schistosity, joints and fissures, and the rock mass exhibits obvious anisotropic characteristics, the model with widespread joints is selected. Then, the rock mass cohesion, internal friction angle, elastic modulus, and joint surface mechanical parameters obtained from indoor rock tests are assigned to the corresponding constitutive model. Then, the measured tunnel cross-sectional dimensions, three-stage excavation step distance, and anchor bolt geometric parameters are imported to establish a complete numerical calculation model including the surrounding rock, initial support, and prestressed anchor bolts.
[0076] After modeling, the excavation and support procedures were reconstructed step by step according to the on-site construction sequence. The upper, middle, and lower bench excavation units were activated in sequence, and different sizes of anchor prestress were applied step by step. Multiple sets of working condition calculations were carried out in batches. During the calculation process, the displacement output data of the arch crown and left and right sidewall measuring points were monitored simultaneously. The arch crown settlement and horizontal convergence results corresponding to each set of working conditions were collected. After all working condition calculations were completed, the deformation response of the surrounding rock under different prestress conditions was compared, and the anchor prestress value with the best deformation control effect was selected. This value was used as the design basis for on-site anchor tensioning construction, realizing the linkage application of the constitutive model with measured geological conditions and support parameter optimization process.
[0077] S4. Based on the measured thickness difference of the loosened ring on the left and right sides of the tunnel, the anchor bolt layout parameters on both sides of the tunnel are configured differently, and an asymmetric anchor bolt layout scheme is formulated to adapt to the characteristics of surrounding rock bias and uneven rock strata.
[0078] Differentiated configuration of anchor bolt layout parameters abandons the traditional design approach of having completely identical anchor bolt lengths and spacing on both sides of the tunnel cross section. Instead, it uses the degree of damage to the surrounding rock on both sides, measured on-site, as the basis for parameter control. This configuration is not simply about arbitrarily adjusting anchor bolt parameters, but rather using the difference in loosened ring thickness as a quantitative input condition. Under the premise of meeting the anchor bolt foundation anchoring requirements, it selectively allocates and adjusts two key parameters: the spacing between anchor bolts and the length of a single anchor bolt. For the side with more severe surrounding rock damage, parameters are adjusted to improve the overall stiffness and anchoring capacity of the support system in that area. For the other side with relatively less surrounding rock damage, the support input is moderately controlled while ensuring the stability and safety baseline of the surrounding rock. This ensures that the support capacity on both sides of the cross section matches the damage state of their respective surrounding rocks, achieving a match between support strength and the actual degree of surrounding rock damage. This avoids the extreme phenomenon of insufficient support strength on one side and redundant and wasteful support performance on the other side.
[0079] In this embodiment, S4 designs an asymmetric anchor bolt arrangement scheme based on the difference in the measured thickness of the loosened ring on the left and right sides of the tunnel. The specific rules are as follows: when the thickness of the loosened ring on the left is greater than that on the right, at least one of the following methods is used to improve the support strength of the left surrounding rock area: denser anchor bolt arrangement or longer anchor bolt length; when the thickness of the loosened ring on the right is greater than that on the left, at least one of the following methods is used to improve the support strength of the right surrounding rock area: denser anchor bolt arrangement or longer anchor bolt length.
[0080] Uneven stress distribution in the tunnel cross-section can be caused by biased pressure and uneven rock strata. The unloading damage and crack propagation processes of the surrounding rock on both sides are not synchronized. Symmetrical anchor bolt support mode is difficult to balance the deformation development of the surrounding rock on both sides. The asymmetric anchor bolt arrangement scheme aims to eliminate the uneven stress distribution in the cross-section of the surrounding rock. It integrates the adjustment results of the anchor bolt length and anchor bolt density on both sides to form a complete and feasible cross-section anchor bolt arrangement system. This scheme fully considers the anisotropy of the surrounding rock caused by inclined rock strata and tectonic bias. It no longer relies on experience to uniformly arrange anchor bolts. It uses the measured data of the loosening zone on site as a prerequisite for the scheme design. It improves the engineering risk of excessive deformation on one side and local support overload failure in high-stress soft rock tunnels. It enables the anchor bolt support system to adapt to the inherent characteristics of asymmetric damage of the surrounding rock and promotes the deformation of the surrounding rock in the tunnel cross-section to tend to be coordinated and uniform.
[0081] When the difference in thickness of the loosened ring on both sides of the tunnel is in the range of 0.5-1.5m, the anchor density on the side with the larger loosened ring should be increased by 10%-30% compared to the other side, or the anchor length should be increased by 1-2m compared to the other side.
[0082] In the Haba Snow Mountain Tunnel, the loosening zone on the left side of the upper step (4.0-4.5m) is larger than that on the right side (3.0-3.5m), with a difference of 0.5-1.5m. Based on this, this embodiment proposes that the anchor density on the left side be increased by 10%-30% compared to the right side, or the length of the anchor on the left side be increased by 1-2m compared to the right side. This solution solves the problem of insufficient anchors on one side and excessive anchors on the other side when the traditional symmetrical anchor arrangement is used under uneven surrounding rock conditions. The surrounding rock conditions on the right side are relatively better, and the anchors can be appropriately sparse without affecting the support effect. However, the loosening zone on the left side is larger, and denser anchors can effectively control the eccentric deformation.
[0083] S5. The determined anchor length, anchor prestress, and asymmetric anchor arrangement scheme are applied to the on-site construction, and the loosening zone control effect is verified by retesting using the sonic method.
[0084] Acoustic retesting is a method of verifying the effectiveness of the anchor bolt support system after its construction is completed and the surrounding rock stress has redistributed and stabilized over a certain period of time. The retesting section is preferably the same section as the initial loosening zone test conducted in the early stage. The drilling position, drilling depth, and acoustic testing process are kept consistent with the original test to eliminate data deviations caused by differences in testing conditions. Through retesting, the actual development state of the fractured zone of the surrounding rock after the support is completed can be obtained. It can intuitively reflect the actual degree of rock fracture compaction and damage zone shrinkage under the reinforcement of prestressed anchor bolts. Unlike the evaluation method that relies solely on tunnel surface displacement monitoring, it can directly penetrate the surface support structure to obtain damage changes inside the surrounding rock. It can evaluate the true reinforcement effect of the anchor bolt support system from the perspective of damage inside the surrounding rock, avoiding misjudgments of the internal state of the surrounding rock caused by relying solely on surface deformation data.
[0085] In this embodiment, in S5, after implementing the support construction using the anchor bolt length (S2), anchor bolt prestress (S3), and asymmetric anchor bolt arrangement (S4), the thickness of the loosened ring is re-measured by sonic wave. The reduction range of the loosened ring before and after support is used as the evaluation criterion for the control effect of the surrounding rock. If the reduction effect of the loosened ring does not meet the standard, the process returns to S1 to re-measure the loosened ring and iteratively adjust the anchor bolt support parameters.
[0086] Iterative adjustment of anchor bolt support parameters is a correction step in the closed-loop optimization process. When the retest results show that the reduction in the loosened zone does not meet the preset control index, it indicates that the current set of support parameters does not match the actual surrounding rock damage conditions on site. This process returns to S1 to re-measure the loosened zone. The purpose is to recapture the latest damage evolution state of the surrounding rock under the support action, obtain the updated loosened zone thickness and the thickness difference between the two sides of the cross section, and then, based on this new measured data, recalculate the anchor bolt length, re-conduct numerical simulation to optimize the anchor bolt prestress, and re-optimize the asymmetric anchor bolt layout differences to complete the synchronous update of the entire set of support parameters, rather than just changing a single parameter. The support parameters after iterative correction are then put into field application again for effect verification until the loosened zone control effect meets the design requirements, thereby continuously adapting to the dynamic changes of the surrounding rock under the high ground stress environment of deeply buried soft rock.
[0087] This embodiment reveals the nonlinear relationship between anchor prestress and deformation control effect through numerical simulation, specifically: Prestress range vault settlement changes Decrease 20→100kN 352.85→338.9mm 4.0% 100→180kN 338.9→334.6mm 1.3% Based on this, 100-140kN was determined to be the optimal prestressing range. When the prestress exceeds 140kN, the marginal benefit of deformation control effect drops sharply, with the decrease from 4.0% to 1.3%, while the construction difficulty and cost increase significantly. Therefore, 100-140kN was determined to be the economically reasonable optimal range.
[0088] Example 2: This example provides a collaborative method for determining prestressed anchor support parameters in deeply buried soft rock tunnels based on measured loosening zones. It is applied to the Haba Snow Mountain Tunnel project on the Lijiang-Shangri-La line of the Yunnan-Tibet Railway, as detailed below: (1) Project Overview The Haba Snow Mountain Tunnel is 9,523 meters long with a maximum burial depth of 1,155 meters, located on the southeastern edge of the Qinghai-Tibet Plateau. The tunnel mainly traverses sandy slate, slate interbedded with limestone and foliated basalt. The surrounding rock has low strength and well-developed joints and fissures. The measured maximum horizontal in-situ stress is 38.03 MPa, and the rock mass strength-stress ratio is 0.1-0.5, classifying it as an extremely high-stress soft rock tunnel. During construction, extremely severe large deformations occurred, with the arch crown settling by 980.4 mm, horizontal convergence reaching 1,935.27 mm, and the secondary lining collapsing entirely by 189 meters.
[0089] (2) On-site testing of loosened coils using acoustic wave method Test equipment: TGM-G302 loose ring test system, including TGM-WIS(B) type intelligent dry hole transducer water injection system, loose ring tester, probe, support rod and connecting pipe.
[0090] Test steps: ① A C6 drilling rig was used to drill holes at section DK55+745. The drilling depth was 10m for the upper step and 12m for the lower step.
[0091] ② Connect the water injection system, testing system and probe in sequence.
[0092] ③ Insert the probe into the borehole 0.5m deep and inject water using the water injection system, setting the water injection pressure to 20kPa.
[0093] ④ The elastic longitudinal wave velocity of the rock mass was measured and recorded using a testing instrument.
[0094] ⑤ Use a water injection system to return water. After the water return is complete, push the probe further into the hole by 0.5m.
[0095] ⑥ Repeat steps ③-⑤ until the bottom of the hole is measured.
[0096] Test results: Excavation stage Measurement point location Loosening range After the steps were excavated Left side 4.0-4.5m After the steps were excavated right side 3.0-3.5m After the middle bench was excavated Left side 7.0-7.5m After the middle bench was excavated right side 7.5-8.0m After the step-down excavation Left side 9.5-10.5m After the step-down excavation right side 10.5-11.0m (3) Determine the length of the anchor bolt Based on the principle that the length of the anchor bolt should not be less than the thickness of the corresponding loosening ring of the step: The length of the prestressed anchor bolt for the upper step is determined to be 5m, penetrating the loosened zone of the upper step by 4.0-4.5m and entering the intact surrounding rock by 0.5-1.0m.
[0097] The length of the sidewall anchor bolt is determined to be 12m, penetrating the loosened zone of the middle and lower steps by 9.5-10.5m and entering the intact surrounding rock by 1.5-2.0m.
[0098] (4) Determine the optimal anchor prestress A numerical model was established using FLAC3D to develop a tunnel deformation mechanical response model under different anchor prestress conditions (20kN, 40kN, 60kN, 80kN, 100kN, 120kN, 140kN, 160kN, 180kN).
[0099] The calculation results show that: Anchor bolt prestress (kN) Vault settlement (mm) Decrease 20 352.85 — 40 349.2 1.03% 60 345.8 2.00% 80 342.5 2.93% 100 338.9 3.95% 120 336.8 4.55% 140 335.5 4.92% 160 334.9 5.09% 180 334.6 5.17% Increasing the prestress from 100kN to 180kN only reduced the arch crown settlement by 4.3mm (1.3%), indicating that the improvement effect was approaching saturation. Considering both economic efficiency and construction feasibility, the optimal anchor prestress was determined to be 120kN.
[0100] (5) Determine the asymmetric anchor bolt arrangement scheme Since the loosening zone on the left side of the upper step (4.0-4.5m) is larger than that on the right side (3.0-3.5m), with a difference of 1.0m, an asymmetrical anchor bolt arrangement scheme is determined: the anchor bolt density on the left side is increased by 20% compared to the right side, while the anchor bolt length on the left side remains unchanged at 5m.
[0101] (6) Field application and verification Apply the above support parameters to on-site construction: The upper step: 5m prestressed anchor rods, prestress 120kN, circumferential longitudinal spacing 1.0m×1.0m.
[0102] Sidewall: 12m long anchor bolts, with a longitudinal spacing of 1.0m × 1.0m.
[0103] The anchor density on the left side is 20% higher than that on the right side. Post-construction re-measurement of loosening zone: Measurement point location Control the loosening ring Control the loosening ring Decrease amount Left side of the steps 4.0-4.5m 2.5-3.0m 1.0-2.0m Right side of the steps 3.0-3.5m 2.0-2.5m 1.0m Left side of the middle steps 7.0-7.5m 5.5-6.0m 1.5m Right side of the middle steps 7.5-8.0m 4.5-5.0m 3.0m Deformation monitoring results: Vault settlement: reduced by 189.98 mm compared to the section without the method of this invention.
[0104] The horizontal convergence of the step is reduced by 800mm.
[0105] The horizontal convergence of the lower step is reduced by 396.8 mm.
[0106] Compare cross-sections with and without the method of this invention: Section DK55+655 (not using this scheme): Arch settlement 980.4mm, upper step convergence 1935.27mm.
[0107] Section DK55+865 (using this scheme): Arch settlement 779.77mm, upper step convergence 1467.86mm.
[0108] The settlement of the arch was reduced by 20.5%, and the horizontal convergence of the upper step was reduced by 24.2%.
[0109] The effectiveness of the method of the present invention has been verified.
[0110] Example 3: This example verifies the rationality of the support parameters by conducting on-site stress monitoring of a three-layer initial support structure using the method of the present invention. Specifically: (1) Monitoring Plan Pressure cells and stress gauges were installed at section DK55+748 to monitor the contact pressure between the surrounding rock and the first initial support, between the first and second initial supports, and between the second and third initial supports, as well as the stress in each layer of steel frame and shotcrete. A total of six monitoring points were set up at the monitoring section: arch crown, left arch waist, right arch waist, left side wall, right side wall, and invert arch.
[0111] (2) Monitoring results Contact pressure sharing ratio: 0.51:0.37:0.12.
[0112] Surrounding rock - contact pressure: average value 1.82 MPa.
[0113] Contact pressure between the first and second pins: average value 1.34 MPa.
[0114] Two- to three-branch contact pressure: average value 0.44 MPa.
[0115] The stress-bearing ratio on the outer side of the steel frame is 0.47:0.29:0.24.
[0116] The average stress on the outer side of a steel frame is 239.52 MPa.
[0117] Stress on the outer side of the two steel frames: average value 148.22 MPa.
[0118] The average stress on the outer side of the three steel frames is 122.55 MPa.
[0119] The stress-bearing ratio on the outer side of the sprayed concrete is 0.41:0.32:0.27.
[0120] The average stress on the outer side of the sprayed concrete is 20.17 MPa.
[0121] The stress on the outer side of the two sprayed concrete sections is 15.55 MPa on average.
[0122] The average stress on the outer side of the three sprayed concrete sections is 13.50 MPa.
[0123] (3) Monitoring results The first layer of initial support bears approximately half of the surrounding rock load and is the primary load-bearing structure. Therefore, the anchor bolts of the first layer of initial support must penetrate the loosening ring of the upper step (5m) to effectively control the development of the loosening ring. The second and third layers of initial support serve as reinforcement, gradually bearing the load after the deformation of the previous layer, with the load-bearing ratio decreasing sequentially. This monitoring result verifies the rationality of the design method of determining the length of the anchor bolts of the first layer of initial support based on the actual measurement of the loosening ring. After the anchor bolts of the first layer of initial support penetrate the loosening ring, the further expansion of the loosening ring is effectively controlled, thereby reducing the load on subsequent support layers.
[0124] Example 4: This example verifies the adaptability of the method of the present invention under different burial depth conditions. Operating Condition 1: Burial depth 500m.
[0125] Actual measured loosening zone: 2.0-2.5m for the upper step and 4.0-4.5m for the middle step.
[0126] Determine the anchor bolt length: 3m for the upper step and 6m for the side wall.
[0127] Deformation after application: The arch settlement is about 150mm, and the horizontal convergence is about 400mm.
[0128] The loosened area decreases by approximately 0.5-1.0 mm.
[0129] Condition 2: Burial depth 800m.
[0130] Actual measured loosening zone: 3.0-3.5m for the upper step, 6.0-6.5m for the middle step, and 8.0-9.0m for the lower step.
[0131] Determine the anchor bolt length: 4m for the upper step and 9m for the side wall.
[0132] Deformation after application: The arch settlement is about 350mm, and the horizontal convergence is about 900mm.
[0133] The loosened area decreased by approximately 1.0-1.5m.
[0134] Condition 3: Burial depth 1155m (Haba Snow Mountain Tunnel).
[0135] Actual measured loosening zone: 4.0-4.5m for the upper step, 7.5-8.0m for the middle step, and 10.5-11.0m for the lower step.
[0136] Determine the anchor bolt length: 5m for the upper step and 12m for the side wall.
[0137] Deformation after application: The arch settlement is about 780mm, and the horizontal convergence is about 1468mm.
[0138] The loosened area decreases by approximately 1.5-3.0 mm.
[0139] All three sets of working conditions show that the method of the present invention can effectively control the loosening ring and significantly reduce deformation under different burial depths, verifying the universality of the method. The greater the burial depth and the larger the loosening ring, the longer the required anchor bolt needs to be, but the design principle of penetrating the loosening ring always applies.
[0140] Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for determining the supporting parameters of a deep-buried soft rock tunnel prestressed anchor based on the measured loose circle, characterized in that, The method for collaboratively determining anchor bolt support parameters includes the following steps: S1. The acoustic method was used to conduct on-site testing of the loosened zone of the surrounding rock at different excavation stages of the deep-buried soft rock tunnel. The range of the loosened zone after the excavation of the upper bench, the middle bench, and the lower bench was obtained respectively. The thickness difference of the loosened zone on the left and right sides of the tunnel was identified simultaneously. S2. Based on the measured range of the loosening ring, determine the length of the prestressed anchor rod. The length of the prestressed anchor rod for each step shall be determined with the principle that the length of the anchor rod shall not be less than the thickness of the loosening ring of the corresponding step. S3. Establish a tunnel deformation mechanical response model under different prestressed anchor bolt lengths and different anchor bolt prestress magnitudes through numerical simulation, and determine the optimal anchor bolt prestress value with the goal of minimizing tunnel arch settlement and horizontal convergence. S4. Based on the measured difference in the thickness of the loosened ring on the left and right sides of the tunnel, the anchor bolt layout parameters on both sides of the tunnel are configured differently, and an asymmetric anchor bolt layout scheme is formulated to adapt to the characteristics of surrounding rock bias and uneven rock strata. S5. The determined anchor length, anchor prestress, and asymmetric anchor arrangement scheme are applied to the on-site construction, and the loosening zone control effect is verified by retesting using the sonic method.
2. The method according to claim 1, characterized in that: The deep-buried soft rock is sandy slate, slate interbedded with limestone or foliated basalt, with a tunnel burial depth ≥800m and a surrounding rock strength-stress ratio ≤0.
5.
3. The method according to claim 1, characterized in that: The specific field testing method in S1 is as follows: S1a. Drill holes in the test section using a drilling rig. The hole diameter is larger than the probe diameter. The drilling depth for the upper step is 8-12m, and the drilling depth for the lower step is 10-15m. S1b. Place the acoustic test probe into the borehole at a position of 0.3-0.8m and inject water using a water injection system at a pressure of 15-25kPa to form acoustic coupling between the probe and the borehole wall. S1c. The elastic longitudinal wave velocity of the rock mass is measured and recorded using an acoustic wave tester. S1d: Push the probe into the hole 0.3-0.8m, and repeat S1b and S1c until the bottom of the hole is measured; S1e, the critical depth of the loosening zone is taken as the endpoint where the wave velocity of the surrounding rock changes significantly. When the wave velocity tends to stabilize, it indicates that the loosening zone has been exceeded.
4. The method according to claim 1, characterized in that: The S1 obtained the loosening zone evolution characteristics through phased testing, specifically as follows: The area of the loosened surrounding rock continues to expand with the excavation of the upper bench, middle bench, and lower bench. Due to geological bias and the occurrence of rock strata, there is a difference in the thickness of the loosened zone on the left and right sides of the same excavation section.
5. The method according to claim 1, characterized in that: The design of the S2 anchor bolt length follows these rules: The length of the arch anchor rod penetrates the loosening ring of the upper step and extends 0.5-1.0m into the intact surrounding rock; The long anchor rods of the sidewalls penetrate the largest loosening zone after the middle and lower steps have been excavated, and extend into the intact surrounding rock by 1.0-2.0m.
6. The method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones, as described in claim 1, is characterized in that: In S3, by comparing the surrounding rock deformation patterns through multiple sets of anchor prestressing conditions, it can be seen that there is an optimal control range for anchor prestressing. The specific pattern is as follows: When the prestress of the anchor bolt is 100-140kN, the deformation control effect of tunnel arch settlement and horizontal convergence is optimal. When the prestress is increased in the range of 20kN-100kN, the effect of suppressing deformation of the surrounding rock is significantly improved. When the prestress exceeds 100kN and continues to increase to the 180kN range, the reduction in surrounding rock deformation narrows significantly, and the deformation control effect tends to saturate.
7. The method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones, as described in claim 6, is characterized in that: The S3 uses finite difference numerical simulation software to construct a deformation mechanical response model of the tunnel surrounding rock, and the surrounding rock calculation adopts the Mohr-Coulomb model or the pervasive joint model.
8. The method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones, as described in claim 1, is characterized in that: Based on the measured difference in the thickness of the loosened ring on the left and right sides of the tunnel, S4 designs an asymmetric anchor bolt arrangement scheme, with the specific rules as follows: When the thickness of the loosened zone on the left is greater than that on the right, at least one of the following methods should be used to improve the support strength in the surrounding rock area on the left: denser anchor bolt arrangement or longer anchor bolt length. When the thickness of the loosened zone on the right is greater than that on the left, the support strength of the surrounding rock area on the right is improved by at least one of the following methods: denser anchor bolt arrangement or longer anchor bolt length.
9. The method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones, as described in claim 8, is characterized in that: When the difference in thickness of the loosened ring on both sides of the tunnel is in the range of 0.5-1.5m, the anchor density on the side with the larger loosened ring should be increased by 10%-30% compared to the other side, or the anchor length should be increased by 1-2m compared to the other side.
10. The method for collaboratively determining prestressed anchor support parameters for deep-buried soft rock tunnels based on measured loosening zones, as described in claim 1, is characterized in that: In S5, after implementing the support construction using the S2 anchor length, S3 anchor prestress, and S4 asymmetric anchor arrangement scheme, the thickness of the loosened ring is re-measured by acoustic wave, and the reduction of the loosened ring before and after support is used as the basis for judging the surrounding rock control effect. If the loosening effect is not satisfactory, return to S1 to re-conduct the loosening measurement and iteratively adjust the anchor bolt support parameters.