Stern ramp load test method

By replacing the piers with gantry cranes during the stern ramp assembly stage and using a flat-back trolley and a crane in tandem, the dependence of the stern ramp load test on the dry dock was solved, enabling a safe and low-difficulty load test.

CN123111663APending Publication Date: 2026-11-17GUANGZHOU SHIPYARD INTERNATIONAL LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611233163.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-14
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In existing technologies, the stern ramp load test needs to be completed in a dry dock, which leads to a longer commissioning cycle, greater construction difficulty, higher safety risks, and higher requirements for dry dock configuration.

Method used

During the stern ramp assembly stage, the front ramp section is lifted and some supports are replaced with gantry frames. The middle ramp section is supported by the gantry frames. The load test of the stern ramp is completed through the coordinated operation of the flat-back trolley and the crane.

Benefits of technology

The load test was completed on the ground during the stern ramp assembly stage, avoiding the influence of the test in the dock and reducing the difficulty of construction operations and safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123111663A_ABST
    Figure CN123111663A_ABST
Patent Text Reader

Abstract

This invention belongs to the technical field of stern ramp load testing and discloses a method for testing stern ramp loads. This method involves lifting the front ramp section and replacing the support pier below the first end of the front ramp section with a gantry. The middle ramp section is then installed on the front ramp section, with the end of the middle ramp section furthest from the front ramp section supported by another gantry. Subsequently, the front and middle ramp sections are lifted and all supports are removed. After lowering, the front and middle ramp sections are supported only by the gantry at both ends, allowing for load testing of the stern ramp. This stern ramp load testing method is performed during the stern ramp assembly stage, can be completed on land, does not affect the commissioning cycle of the stern ramp in the dry dock, and has low construction difficulty and low safety risk.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of stern ramp load testing technology, and more particularly to a stern ramp load testing method. Background Technology

[0002] The stern ramp is a crucial structure for car carriers to achieve their roll-on / roll-off function. It typically consists of three sections: forward, midway, and aft, and its complex structure requires high standards for installation and use. To ensure that the stern ramp structure meets operational requirements after delivery, a load test is necessary.

[0003] Current technology typically involves hoisting the stern ramp onto the ship for installation, then using a gantry crane to open it in the dry dock, and arranging numerous high-level supports to secure the ramp before conducting load tests. The problems with this approach are twofold: firstly, the load test must be completed in the dry dock after the stern ramp is installed, resulting in a late testing period that impacts the overall commissioning cycle of the stern ramp and also affects other work such as the installation, grinding, and touch-up coating of the adhesive groove, further lengthening the commissioning period; secondly, opening the stern ramp for load testing in the dry dock requires numerous high-level support fixtures, posing high safety risks and presenting significant construction difficulties; and thirdly, the stern ramp load test places high demands on the dry dock configuration, and there are cases where the stern ramp cannot be opened in the dry dock. Summary of the Invention

[0004] This invention provides a method for load testing of stern ramps to solve the problems in the prior art, such as the extended commissioning cycle, high construction difficulty, and high requirements for dock configuration caused by the need to complete the load test of stern ramps in a dry dock.

[0005] To achieve the above objectives, the present invention adopts the following technical solution: Stern ramp load test method, the stern ramp includes the fore ramp and the middle ramp; The stern ramp load test method includes: S100: Lift up the front section of the scaffolding, which is supported by multiple piers; S200: Remove the support block located below the end of the first end of the front section of the scaffold, and install a gantry below the end of the first end of the front section of the scaffold; S300: Lower the front section of the scaffolding so that the front section of the scaffolding is supported by the gantry and the several of the supports; S400: A gantry and several supports for supporting the middle section of the scaffold are installed on the outer side of the second end of the front section scaffold. S500: The middle section of the scaffold is installed on the front section of the scaffold, and the end of the middle section of the scaffold near the front section of the scaffold is supported by a plurality of the supports, and the end away from the front section of the scaffold is supported by the gantry. S600: Lift up the front section of the springboard and the middle section of the springboard; S700: Remove all the aforementioned supports; S800: Lower the front section springboard and the middle section springboard; S900: Conduct a load test on the stern ramp.

[0006] As a preferred embodiment of the stern ramp load test method, the stern ramp further includes a rear ramp section; The stern ramp load test method also includes the following steps following step S500: In step S400, a number of supports are placed on the side of the gantry away from the front section of the gantry to support the rear section of the gantry. The rear section of the scaffold is installed at the end of the middle section scaffold that is furthest from the front section scaffold.

[0007] As a preferred embodiment of the stern ramp load test method, the stern ramp further includes a rear ramp section; The stern ramp load test method further includes steps following step S400 and preceding step S500: In step S400, a number of supports are placed on the side of the gantry away from the front section of the gantry to support the rear section of the gantry. Assemble the rear section springboard with the middle section springboard.

[0008] As a preferred method for stern ramp load testing, Step S100 includes: S1001: Drive the flatback vehicle under the front ramp; S1002: Control the support plane of the flat-back vehicle to rise, so as to lift the front section of the ramp; Step S300 includes: S3001: Control the support plane of the flat-back vehicle to descend, and lower the front section ramp; S3002: Drive the flat-back vehicle out of the area below the front ramp.

[0009] As a preferred method for stern ramp load testing, Step S600 includes: S6001: Drive the flatbed vehicle under the front ramp and the middle ramp; S6002: Control the support plane of the flat-back vehicle to rise, and use a crane to lift the front section and the middle section of the ramp, so as to lift the front section and the middle section of the ramp. Step S800 includes: S8001: Control the support plane of the flat-back vehicle to descend, and remove the hook of the crane to lower the front section and the middle section of the scaffolding. S8002: Drive the flat-back vehicle out of the area below the front ramp and the middle ramp.

[0010] As a preferred embodiment of the stern ramp load test method, the gantry includes: A crossbeam is used to support the stern ramp; Several columns are connected to the crossbeam, and the columns are used to support the ground; A reinforcing plate is connected to the column and is used to support the ground.

[0011] As a preferred embodiment of the stern ramp load test method, the gantry further includes a herringbone brace, which includes a bracing rod and a mounting rod. One end of the bracing rod supports the side wall of the crossbeam, and the other end is used to support the ground. The mounting rod is connected to the bracing rod and is used to support the ground.

[0012] As a preferred embodiment of the stern ramp load test method, the gantry further includes a circular tube, one end of which supports the bottom wall of the crossbeam, and the other end of which is used to support the ground.

[0013] As a preferred embodiment of the stern ramp load test method, in step S200, the number of gantry frames installed below the first end of the front ramp is multiple; and / or, In step S400, the number of gantry frames installed on the outer side of the second end of the front section of the gantry is multiple.

[0014] As a preferred embodiment of the stern ramp load test method, the support includes a cylindrical support body and a support pad placed above the support body.

[0015] The beneficial effects of this invention are: This invention provides a method for load testing of a stern ramp, comprising the following steps: lifting the front ramp section supported by multiple supports; removing the supports located below the first end of the front ramp section and installing a gantry below the first end of the front ramp section; lowering the front ramp section so that it is supported by the gantry and several supports; installing a gantry and several supports for supporting the middle ramp section on the outer side of the second end of the front ramp section; installing the middle ramp section on the front ramp section, with the end of the middle ramp section closer to the front ramp section supported by several supports and the end farther from the front ramp section supported by the gantry; lifting the front ramp section and the middle ramp section; removing all supports; lowering the front ramp section and the middle ramp section; and conducting a load test on the stern ramp. This stern ramp load test method involves lifting the fore ramp and replacing the support pier below the first end of the fore ramp with a gantry. The middle ramp is then installed on the fore ramp, with the end of the middle ramp furthest from the fore ramp supported by another gantry. Subsequently, the fore and middle ramps are lifted and all supports are removed. After lowering, the fore and middle ramps are supported only by the gantry at both ends, allowing for a load test on the stern ramp. This stern ramp load test is conducted during the assembly phase of the stern ramp, can be completed on land, does not affect the commissioning cycle of the stern ramp in the dry dock, and has low construction difficulty and low safety risk. Attached Figure Description

[0016] Figure 1 This is a flowchart of the stern ramp load test method in an embodiment of the present invention; Figure 2 This is a schematic diagram of the first structure of the stern ramp in an embodiment of the present invention; Figure 3 This is a schematic diagram of the second structure of the stern ramp in an embodiment of the present invention; Figure 4 This is a schematic diagram of the third structure of the stern ramp in an embodiment of the present invention; Figure 5 This is a schematic diagram of the fourth structure of the stern ramp in an embodiment of the present invention; Figure 6 This is a schematic diagram of the fifth structure of the stern ramp in an embodiment of the present invention; Figure 7 This is a schematic diagram of the first structure of the gantry in an embodiment of the present invention; Figure 8 This is a schematic diagram of the second structure of the gantry in an embodiment of the present invention; Figure 9 yes Figure 6 Sectional view of section AA; Figure 10 yes Figure 6 Sectional view of section BB; Figure 11 yes Figure 6 A sectional view of section CC.

[0017] In the picture: 1. Stern springboard; 11. Front springboard; 12. Middle springboard; 13. Rear springboard; 2. Buttress; 3. Portal frame; 31. Crossbeam; 311. Crossbeam sleeper; 32. Column; 33. Reinforcing plate; 34. A-frame brace; 341. Bracing rod; 342. Mounting rod; 35. Round tube; 4. Flat-backed cart; 5. Hook installation structure; 6. Press iron. Detailed Implementation

[0018] The present invention will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and not intended to limit it. Furthermore, it should be noted that, for ease of description, the accompanying drawings show only the parts relevant to the present invention, and not all of the structures.

[0019] In the description of this invention, unless otherwise explicitly specified and limited, the terms "connected," "linked," and "fixed" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0020] In this invention, unless otherwise explicitly specified and limited, "above" or "below" the second feature can include direct contact between the first and second features, or contact between the first and second features through another feature between them. Furthermore, "above," "over," and "on top" of the second feature includes the first feature directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature includes the first feature directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.

[0021] In the description of this embodiment, the terms "upper," "lower," "left," and "right," etc., refer to the orientation or positional relationship shown in the accompanying drawings. They are used only for ease of description and simplification of operation, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the present invention. In addition, the terms "first" and "second" are used only for distinction in description and have no special meaning.

[0022] Example 1 The stern ramp is a crucial structure for car carriers to achieve their roll-on / roll-off (Ro-Ro) function. To ensure the stern ramp structure meets operational requirements after delivery, load testing is necessary. Current technology typically involves hoisting the stern ramp onto the ship, then using a gantry crane in the dry dock to open it and deploy numerous high-level supports for fixation before conducting the load test. This approach has several problems. First, the load test must be completed in the dry dock after the stern ramp is hoisted and installed, resulting in a late testing period that impacts the overall commissioning cycle and delays other work such as adhesive application, grinding, and touch-up coating. Second, opening the stern ramp for load testing in the dry dock requires extensive high-level support equipment, posing significant safety risks and increasing construction difficulty. Furthermore, the stern ramp load test places high demands on the dry dock configuration, and there are cases where the stern ramp cannot be opened in the dry dock.

[0023] In response, this embodiment provides a stern ramp load test method to solve the problems in the prior art, such as the extended commissioning cycle, high construction difficulty, and high requirements for dock configuration caused by the need to complete the stern ramp load test in a dry dock. It can be used in the field of stern ramp load test technology.

[0024] The stern ramp 1 includes a forward ramp 11, a mid-section ramp 12, and a rear ramp 13, arranged sequentially from bow to stern. The forward ramp 11 is installed on the hull. One end of the mid-section ramp 12 is installed on the forward ramp 11, and the other end is installed on the rear ramp 13. It mainly serves as a transition and vehicle support. The end of the rear ramp 13 furthest from the mid-section ramp 12 freely connects to the dock to compensate for the dock's elevation difference and tidal changes.

[0025] Reference Figure 1 The stern ramp load test method includes the following steps.

[0026] S100: The front section of the scaffold 11, supported by multiple piers 2, is lifted up.

[0027] The stern ramp load test method is carried out during the assembly stage of the stern ramp 1. Before the stern ramp 1 is assembled, the front ramp 11 is supported by several supports 2.

[0028] Specifically, step S100 includes steps S1001-S1002.

[0029] S1001: Drive the flatback vehicle 4 under the front ramp 11.

[0030] S1002: Control the rise of the support plane of the flat-back vehicle 4 to lift the front ramp 11.

[0031] like Figure 2 As shown, the front section of the ramp 11 can be lifted by the flat-backed vehicle 4 without the need for a crane, making the operation simple.

[0032] S200: Remove the support 2 located below the end of the first end of the front section 11, and install the gantry 3 below the end of the first end of the front section 11.

[0033] This step allows the support 2 located below the first end of the front section scaffold 11 to be replaced with the gantry 3.

[0034] S300: Lower the front section of the scaffolding 11 so that the front section of the scaffolding 11 is supported by the mounting gantry 3 and several supports 2.

[0035] Specifically, step S300 includes steps S3001-S3002.

[0036] S3001: Control the lowering of the support plane of the flat-back vehicle 4 to lower the front section ramp 11.

[0037] S3002: Drive the flatback vehicle 4 out from under the front ramp 11.

[0038] It is understandable that, such as Figure 3 As shown, in step S100, the flatbed vehicle 4 drives in along the set path. However, since the gantry 3 will be installed in step S200, the gantry 3 may be placed on the set path, making it impossible for the flatbed vehicle 4 to drive out along the original set path. A new driving path needs to be planned. If the driving path is blocked by the support 2, the position of the support 2 can be moved appropriately before lowering the front section of the ramp 11.

[0039] S400: A gantry 3 and several supports 2 are installed on the outer side of the second end of the front section 11 to support the middle section 12.

[0040] The first and second ends of the front section 11 are the bow and stern ends of the front section 11, respectively.

[0041] Optionally, in step S200, multiple masts 3 are installed below the first end of the front section 11. This arrangement provides stable support for the first end of the front section 11 through multiple masts 3. And / or, in step S400, multiple masts 3 are installed on the outer side of the second end of the front section 11. This arrangement provides stable support for the end of the middle section 12 away from the front section 11 through multiple masts 3. This embodiment exemplarily provides a scheme in which multiple masts 3 are installed below the first end of the front section 11 in step S200, and multiple masts 3 are installed on the outer side of the second end of the front section 11 in step S400.

[0042] S500: The middle section scaffold 12 is installed on the front section scaffold 11, and the end of the middle section scaffold 12 near the front section scaffold 11 is supported by several piers 2, while the end away from the front section scaffold 11 is supported by the gantry 3.

[0043] Specifically, in step S400, the gantry 3 and several supports 2 should be installed according to the actual size of the middle section scaffold 12, so that in step S500, after the middle section scaffold 12 is installed on the front section scaffold 11, the gantry 3 is located exactly below the end of the middle section scaffold 12 away from the front section scaffold 11.

[0044] In this embodiment, the stern ramp load test method further includes the following steps following step S500.

[0045] In step S400, several supports 2 are placed on the side of the gantry 3 away from the front section 11 to support the rear section 13.

[0046] The rear section of the scaffold 13 is installed at the end of the middle section scaffold 12 that is away from the front section scaffold 11.

[0047] The above steps allow the aft ramp 13 to be installed onto the middle ramp 12, completing the assembly of the entire stern ramp 1 and making subsequent load tests on the stern ramp 1 more closely resemble actual operating conditions. The overall structure of the assembled stern ramp 1 is as follows: Figure 4 As shown.

[0048] S600: Lift up the front section springboard 11 and the middle section springboard 12.

[0049] In step S100, the front section of the scaffold 11 can be lifted by the flat-back vehicle 4 alone. However, after the front section of the scaffold 11 and the middle section of the scaffold 12 are assembled, their overall weight is relatively high. It may be difficult to lift the front section of the scaffold 11 and the middle section of the scaffold 12 as a whole by the flat-back vehicle 4 alone. Therefore, in this embodiment, step S600 includes steps S6001-S6002.

[0050] S6001: Drive the flatback vehicle 4 under the front ramp 11 and the middle ramp 12.

[0051] S6002: Control the rise of the support plane of the flat-back vehicle 4, and lift the front section 11 and the middle section 12 by the crane to lift the front section 11 and the middle section 12.

[0052] like Figure 5 As shown, through the above steps, the front section 11 and the middle section 12 can be lifted by the flat-back vehicle 4 in conjunction with the crane.

[0053] S700: Remove all piers 2.

[0054] S800: Lower the front section springboard 11 and the middle section springboard 12.

[0055] After steps S700-S800, the lowering process ensures that the front ramp 11 and the middle ramp 12 are supported only by the masts 3 at both ends. At this point, a load test can be performed on the stern ramp 1.

[0056] Specifically, step S800 includes steps S8001-S8002.

[0057] S8001: Control the lowering of the support plane of the flat-back vehicle 4 and remove the hook of the crane to lower the front section 11 and the middle section 12.

[0058] S8002: Drive the flatback vehicle 4 out from under the front ramp 11 and the middle ramp 12.

[0059] S900: Conduct a load test on the stern ramp 1.

[0060] Load tests can be conducted based on relevant regulations or classification society requirements. For example, static load tests can be performed according to the "Stern Ram Load Test Manual." Specifically, such as... Figure 6 As shown, the test is conducted by placing a pressure iron 6 above the front section 11 and the middle section 12. The specific test principle and procedure will not be elaborated here.

[0061] The stern ramp load test method involves lifting the fore ramp 11 and replacing the support 2 below the first end of the fore ramp 11 with a gantry 3. The middle ramp 12 is then installed on the fore ramp 11, with the end of the middle ramp 12 furthest from the fore ramp 11 supported by another gantry 3. Subsequently, the fore ramp 11 and the middle ramp 12 are lifted, and all supports 2 are removed. After lowering, the fore ramp 11 and the middle ramp 12 are supported only by the gantry 3 at both ends, allowing for a load test on the stern ramp 1. This stern ramp load test is conducted during the assembly stage of the stern ramp 1, can be completed on land, does not affect the commissioning cycle of the stern ramp in the dry dock, and has low construction difficulty and low safety risk.

[0062] Continue to refer to Figures 2-6 The support pier 2 includes a cylindrical support pier body and a support pier pad placed on top of the support pier body. The removal of support pier 2 in steps S200 and S700 can specifically be to move the entire support pier 2 out, or to remove only the support pier pad located on top of the support pier body.

[0063] Reference Figures 7-11The gantry 3 includes a crossbeam 31, a reinforcing plate 33, and several uprights 32. The crossbeam 31 supports the stern ramp 1; the uprights 32 are connected to the crossbeam 31 and are used to support the ground; the reinforcing plate 33 is connected to the uprights 32 and is used to support the ground, thereby enabling the gantry 3 to be stably placed on the ground, thus providing stable support for the front ramp 11 or the middle ramp 12. Optionally, a crossbeam pad 311 is placed above the crossbeam 31, and the stern ramp 1 is supported by the crossbeam pad 311.

[0064] Continue to refer to Figures 7-11 The gantry 3 also includes a herringbone brace 34, which includes a brace rod 341 and a mounting rod 342. One end of the brace rod 341 supports the side wall of the crossbeam 31, and the other end is used to support the ground. The mounting rod 342 is connected to the brace rod 341 and is used to support the ground. Thus, the side wall of the crossbeam 31 can be supported by the herringbone brace 34, preventing the gantry 3 from tilting to one side.

[0065] Continue to refer to Figures 7-11 The gantry 3 also includes a circular tube 35. One end of the circular tube 35 supports the bottom wall of the crossbeam 31, and the other end is used to support the ground. Thus, the bottom wall of the crossbeam 31 can be supported by the circular tube 35, thereby increasing the overall structural strength of the gantry 3. In this embodiment, the side wall of the crossbeam 31 is supported by the herringbone brace 34, and the bottom wall of the crossbeam 31 is supported by the circular tube 35, which can further improve the overall structural stability of the gantry 3.

[0066] Example 2 This embodiment provides another method for testing the load on the stern ramp, which is basically similar in process to the method for testing the load on the stern ramp in Embodiment 1. The difference is that the assembly process of the aft ramp 13 is different from that in Embodiment 1.

[0067] Specifically, in this embodiment, the stern ramp load test method includes the following steps.

[0068] S100: The front section of the scaffold 11, supported by multiple piers 2, is lifted up.

[0069] S200: Remove the support 2 located below the end of the first end of the front section 11, and install the gantry 3 below the end of the first end of the front section 11.

[0070] S300: Lower the front section of the scaffolding 11 so that the front section of the scaffolding 11 is supported by the mounting gantry 3 and several supports 2.

[0071] S400: A gantry 3 and several supports 2 are installed on the outer side of the second end of the front section 11 to support the middle section 12.

[0072] In this embodiment, the stern ramp load test method further includes the following steps after step S400 and before step S500.

[0073] In step S400, several supports 2 are placed on the side of the gantry 3 away from the front section 11 to support the rear section 13.

[0074] Assemble the rear section springboard 13 with the middle section springboard 12.

[0075] S500: The middle section scaffold 12 is installed on the front section scaffold 11, and the end of the middle section scaffold 12 near the front section scaffold 11 is supported by several piers 2, while the end away from the front section scaffold 11 is supported by the gantry 3.

[0076] After installing the gantry 3 and several supports 2 for supporting the middle section 12 on the outer side of the second end of the front section 11 through the above steps, several supports 2 for supporting the rear section 13 are placed on the side of the gantry 3 away from the front section 11. Then, the rear section 13 is assembled with the middle section 12, and the middle section 12 is installed on the front section 11, thus completing the assembly of the front section 11, the middle section 12, and the rear section 13. That is, in this embodiment, the rear section 13 is assembled with the middle section 12 first, and then the middle section 12 is installed on the front section 11.

[0077] S600: Lift up the front section springboard 11 and the middle section springboard 12.

[0078] S700: Remove all piers 2.

[0079] S800: Lower the front section springboard 11 and the middle section springboard 12.

[0080] S900: Conduct a load test on the stern ramp 1.

[0081] The above description is merely a preferred embodiment of the present invention and an explanation of the technical principles employed. Those skilled in the art should understand that the scope of disclosure in this invention is not limited to technical solutions formed by specific combinations of the above-described technical features, but should also cover other technical solutions formed by arbitrary combinations of the above-described technical features or their equivalents without departing from the above-disclosed concept. For example, technical solutions formed by substituting the above features with (but not limited to) technical features with similar functions disclosed in this invention.

Claims

1. A method for testing the load on a stern ramp, characterized in that, The stern ramp consists of the fore ramp and the middle ramp; The stern ramp load test method includes: S100: Lift up the front section of the scaffolding, which is supported by multiple piers; S200: Remove the support block located below the end of the first end of the front section of the scaffold, and install a gantry below the end of the first end of the front section of the scaffold; S300: Lower the front section of the scaffolding so that the front section of the scaffolding is supported by the gantry and the several of the supports; S400: A gantry and several supports for supporting the middle section of the scaffold are installed on the outer side of the second end of the front section scaffold. S500: The middle section of the scaffold is installed on the front section of the scaffold, and the end of the middle section of the scaffold near the front section of the scaffold is supported by a plurality of the supports, and the end away from the front section of the scaffold is supported by the gantry. S600: Lift up the front section of the springboard and the middle section of the springboard; S700: Remove all the aforementioned supports; S800: Lower the front section springboard and the middle section springboard; S900: Conduct a load test on the stern ramp.

2. The stern ramp load test method according to claim 1, characterized in that, The stern ramp also includes a rear ramp; The stern ramp load test method also includes the following steps following step S500: In step S400, a number of supports are placed on the side of the gantry away from the front section of the gantry to support the rear section of the gantry. The rear section of the scaffold is installed at the end of the middle section scaffold that is furthest from the front section scaffold.

3. The stern ramp load test method according to claim 1, characterized in that, The stern ramp also includes a rear ramp; The stern ramp load test method further includes steps following step S400 and preceding step S500: In step S400, a number of supports are placed on the side of the gantry away from the front section of the gantry to support the rear section of the gantry. Assemble the rear section springboard with the middle section springboard.

4. The stern ramp load test method according to claim 1, characterized in that, Step S100 includes: S1001: Drive the flatback vehicle under the front ramp; S1002: Control the support plane of the flat-back vehicle to rise, so as to lift the front section of the ramp; Step S300 includes: S3001: Control the support plane of the flat-back vehicle to descend, and lower the front section ramp; S3002: Drive the flat-back vehicle out of the area below the front ramp.

5. The stern ramp load test method according to claim 1, characterized in that, Step S600 includes: S6001: Drive the flatbed vehicle under the front ramp and the middle ramp; S6002: Control the support plane of the flat-back vehicle to rise, and use a crane to lift the front section and the middle section of the ramp, so as to lift the front section and the middle section of the ramp. Step S800 includes: S8001: Control the support plane of the flat-back vehicle to descend, and remove the hook of the crane to lower the front section and the middle section of the scaffolding. S8002: Drive the flat-back vehicle out of the area below the front ramp and the middle ramp.

6. The stern ramp load test method according to any one of claims 1-5, characterized in that, The gantry includes: A crossbeam is used to support the stern ramp; Several columns are connected to the crossbeam, and the columns are used to support the ground; A reinforcing plate is connected to the column and is used to support the ground.

7. The stern ramp load test method according to claim 6, characterized in that, The gantry also includes a herringbone brace, which includes a bracing rod and a mounting rod. One end of the bracing rod supports the side wall of the crossbeam, and the other end is used to support the ground. The mounting rod is connected to the bracing rod and is used to support the ground.

8. The stern ramp load test method according to claim 6, characterized in that, The gantry also includes a circular tube, one end of which supports the bottom wall of the crossbeam, and the other end of which is used to support the ground.

9. The stern ramp load test method according to any one of claims 1-5, characterized in that, In step S200, the number of gantry frames installed below the first end of the front section scaffold is multiple; and / or, In step S400, the number of gantry frames installed on the outer side of the second end of the front section of the gantry is multiple.

10. The stern ramp load test method according to any one of claims 1-5, characterized in that, The support includes a cylindrical support body and a support pad placed on top of the support body.