Sliding Positioning Method for Photovoltaic Portal Frames Above Existing Buildings

By setting monitoring points on the photovoltaic portal frame and using a PLC controller for differential speed correction control, the problem of insufficient attitude monitoring during the sliding process of the photovoltaic portal frame in the existing technology is solved, realizing the synchronization and stability of the sliding process, and improving construction safety and positioning accuracy.

CN123113648APending Publication Date: 2026-11-17SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611237354.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-14
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

During the installation of photovoltaic portal frames on existing buildings, the lack of effective attitude monitoring and synchronous closed-loop control means in the current technology leads to the frame being prone to torsion, jamming, and overturning during the sliding process, affecting construction safety and positioning accuracy.

Method used

Monitoring points are set up at the left beam-column connection, the mid-span of the crossbeam, and the right beam-column connection of the photovoltaic portal frame. The displacement signal is monitored in real time by a PLC controller, the relative displacement change is calculated, and the speed of the traction equipment on both sides is controlled by differential correction to achieve active closed-loop control and ensure the synchronization and stability of the sliding process.

Benefits of technology

It enables real-time attitude monitoring and active correction of photovoltaic portal frames, avoiding overall torsion and track jamming of sliding units caused by torsion, improving construction safety and positioning accuracy, and ensuring the smooth progress of the sliding process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123113648A_ABST
    Figure CN123113648A_ABST
Patent Text Reader

Abstract

This invention relates to the field of photovoltaic support technology and discloses a method for sliding and positioning a photovoltaic portal frame above an existing building. The invention sets three monitoring points at the beam-column joints and mid-span of the frame, quantifying the torsion around the vertical axis by measuring the relative displacement change between the mid-span and both ends, which is more comprehensive than simply measuring the longitudinal slip difference. When the limit is exceeded, the PLC determines the leading / lagging side based on the displacement direction and actively corrects the deviation using differential speed (decelerating for leading and accelerating for lagging), and links with the frequency converter drive to form a closed loop of monitoring, judgment, speed adjustment, and re-monitoring, ensuring that the displacement is controlled within the threshold δ throughout the entire process, avoiding unilateral braking impact and additional stress. Before the formal sliding, test sliding is conducted under no-load and loaded conditions with graded speed increases to verify the matching of δ and traction speed, ensuring the reliability of the criteria at each speed level.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of photovoltaic support technology, specifically to a method for sliding and positioning photovoltaic portal frames above existing buildings. Background Technology

[0002] With the rapid development of photovoltaic power generation technology, erecting photovoltaic portal frames and installing photovoltaic modules above existing large-space buildings such as industrial buildings and warehousing and logistics facilities has become an important way to improve the utilization rate of building space and develop clean energy. Existing industrial buildings, due to their open spaces and good lighting conditions, have become the main application scenario for photovoltaic installations.

[0003] Currently, the common method for installing photovoltaic portal frames above existing buildings is as follows: Construction track foundations are poured on the ground on both sides of the existing building; a temporary support system is erected inside or around the building; and the frame components are hoisted piece by piece to the air for assembly and installation, or a single frame is assembled on the ground and then hoisted onto the track for sliding into position. During the sliding process, traction equipment typically provides power, connecting multiple frames into sliding units via temporary connectors, and then sliding them forward one by one. After sliding into position, the base plate of the frame columns is permanently anchored to the foundation embedded parts, and then the temporary sliding track and supporting temporary facilities are removed.

[0004] However, during use, it was found that when multiple rigid frames are connected into sliding units by temporary connectors and accumulating sliding of each frame, the sliding synchronization between each rigid frame and the torsional state of a single rigid frame cannot be judged solely by manual observation or single-point displacement data. As the cumulative sliding progresses, the slight asynchrony between each rigid frame will gradually amplify, causing the sliding unit to twist, get stuck on the rails, or even overturn, seriously threatening construction safety and positioning accuracy. Summary of the Invention

[0005] This invention provides a sliding positioning method for a photovoltaic portal frame above an existing building, which solves the problems in the prior art where there is a lack of effective attitude monitoring and synchronous closed-loop control during the sliding process of the frame, which leads to cumulative sliding that is prone to torsional deviation and poor positioning accuracy, and the instability that easily occurs during the transition from a temporary sliding system to a permanent system due to constraint gaps.

[0006] The present invention provides a method for sliding and positioning a photovoltaic portal frame above an existing building. The frame spans above the existing building, and its bottom is supported by a longitudinal track. The frame is driven by traction devices arranged on both sides. The method includes: Measurement point layout: First monitoring point, second monitoring point, and third monitoring point are set up at the left beam-column connection, the mid-span of the crossbeam, and the right beam-column connection of the rigid frame, respectively, and a synchronous displacement difference threshold δ is preset; Displacement monitoring: During the sliding process, the displacement signals of the three monitoring points are collected in real time, and the current relative displacement between any two monitoring points is calculated based on the collected signals. The current relative displacement is compared with the initial relative displacement at the start of the sliding to obtain the relative displacement change; Torsion discrimination: The relative displacement change is compared with the synchronous displacement difference threshold δ. If any relative displacement change exceeds δ, it is determined that the rigid frame has undergone torsional deformation around the vertical axis, and the leading and lagging sides of the sliding on both sides of the rigid frame are determined based on the displacement signals of each monitoring point; Differential speed correction: A deceleration command is output to the traction equipment on the leading side of the sliding, and an acceleration command is output to the traction equipment on the lagging side of the sliding, so that the traction equipment on both sides generates a differential speed to correct the torsional posture of the rigid frame, and monitoring continues until the relative displacement change falls back to within the range of δ.

[0007] Beneficial Effects: By setting up three monitoring points at the beam-column joints on both sides of the rigid frame and at the mid-span of the crossbeam, the monitoring data is used as a relative configuration criterion to characterize the torsional deformation of the rigid frame in the plane. This not only reflects the longitudinal slip difference between the two columns, but also quantifies the degree of torsional deformation of the rigid frame around the vertical axis by measuring the relative displacement change between the mid-span measuring point and the two end measuring points. When the relative displacement change between any measuring point exceeds the limit, the PLC controller can accurately determine the leading and lagging sides of the slip based on the direction of the displacement difference, triggering speed adjustment to achieve real-time judgment and immediate response active closed-loop control. Furthermore, by directly linking the real-time monitoring signals of the three-point relative configuration with the variable frequency speed control drive system of the traction equipment on both sides, a complete closed-loop signal link of monitoring, judgment, speed adjustment, and re-monitoring is formed. When frame torsion is detected, the PLC controller outputs a deceleration command to the equipment on the leading side of the sliding mechanism and an acceleration command to the equipment on the lagging side. Through dynamic differential adjustment of the traction forces on both sides, the PLC actively corrects the frame's attitude, ensuring that the relative displacement change remains within a preset threshold δ range. This avoids impact loads and additional stress on the frame caused by unilateral forced braking, resulting in a smooth cumulative sliding process and improved positioning accuracy. Furthermore, before the formal sliding operation, a trial sliding test is conducted in the starting work area to verify the value of δ under no-load and loaded graded acceleration. The matching between δ and the traction speed is verified based on the measured relative displacement change data. This ensures that the sensitivity and anti-interference capability of the closed-loop control system are adapted to the actual track conditions, traction equipment performance, and frame stiffness characteristics, guaranteeing the reliability of the closed-loop criteria at each sliding speed level.

[0008] In one optional implementation, the left beam-column connection is the junction of the left column and the crossbeam of the rigid frame, the right beam-column connection is the junction of the right column and the crossbeam of the rigid frame, and the mid-span of the crossbeam is the midpoint of the crossbeam.

[0009] Beneficial effects: By setting the junction nodes of the left and right columns and the crossbeam, as well as the midpoint of the crossbeam, a point matrix is ​​constructed in the plane of the rigid frame. This allows the relative configuration of the three points to simultaneously and uniquely characterize the three rigid body motion states of the rigid frame in the horizontal plane, directly reflecting the torsional offset of the crossbeam at mid-span relative to the two end nodes. Furthermore, during the cumulative slip process, when any rigid frame exhibits a torsional tendency due to uneven traction forces on both sides or differences in track resistance, the displacement response at the beam-column node is the most direct and sensitive. Setting the monitoring point at this location allows the monitoring system to capture abnormal signals in the earliest stage of torsional development, providing the PLC controller with a judgment basis that anticipates torsional deterioration, significantly improving the response timeliness and anti-interference capability of the closed-loop speed control system. Furthermore, by adding a third measuring point at the midpoint of the beam, the relative displacement direction and magnitude between the mid-span measuring point and the measuring points at the beam-column nodes on both sides can be used to clearly distinguish between different states such as pure torsion and overall skew. This allows the PLC controller to trigger differential speed correction only when the frame actually undergoes torsional deformation, avoiding ineffective speed regulation due to misjudging overall skew as torsion, or even causing further attitude misalignment. This makes the closed-loop control decision more accurate and the control process more effective.

[0010] In one optional implementation, each monitoring unit also collects the vertical displacement of the corresponding monitoring point; in the torsion discrimination step, the horizontal displacement and vertical displacement are used together to calculate the relative displacement change.

[0011] Beneficial effects: By collecting the vertical displacement of the monitoring points, the detected horizontal displacement can be combined with the vertical displacement. Both are used in the calculation of relative displacement change, allowing the relative configuration formed by the first to third monitoring points to simultaneously characterize multiple deformation states of the frame, including torsion in the horizontal plane, tilting in the vertical plane, and lateral tilting of the beam around the longitudinal axis. This enhances the closed-loop criterion's ability to holistically perceive abnormal spatial attitudes of the frame. Furthermore, by incorporating both vertical and horizontal displacements into the calculation of relative displacement change, the PLC controller can detect instability trends from abnormal changes in vertical displacement difference at the early stages of torsion, initiating proactive intervention before horizontal torsion develops significantly, thus improving the response speed of closed-loop control.

[0012] In one optional implementation, before the formal sliding test, a trial sliding test is conducted in the starting work area: first, an unloaded trial sliding test and a loaded trial sliding test are conducted and the initial relative displacement of three points is recorded. Then, the traction speed is increased in stages, and the relative displacement change between the three monitoring points is collected at each traction speed level. The matching between the synchronous displacement difference threshold δ and the traction speed is checked. After confirming that there is no rail jamming or abnormal swaying at each speed level, the formal sliding test is started.

[0013] Beneficial effects: By adding an unloaded sliding stage, errors such as uneven rail joints, local gauge deviations, pulley bearing jamming, and gaps between anti-sway limiters and rail head sides can be identified in advance and incorporated into the measured benchmark of the initial relative configuration. This ensures that the closed-loop criterion for formal sliding is based on the measured initial state that includes actual mechanical errors, rather than a theoretical ideal state detached from engineering reality. This avoids the dual risks of frequent false alarms of exceeding limits or missed detection of actual torsion due to initial deviations in the mechanical system during the formal sliding initiation stage. Furthermore, by setting up a loaded trial sliding stage, multiple rigid frames connected as sliding units are tested under actual traction force. This allows for the early acquisition of key dynamic parameters such as starting frictional resistance, uniform traction force, and acceleration response characteristics of the sliding units under actual load conditions. These parameters are then correlated with the three-point relative configuration monitoring data to improve the synchronous control accuracy in the initial stage of sliding.

[0014] In one optional implementation, the rigid frame is a multi-frame rigid frame, and adjacent rigid frames are connected to form a sliding unit by temporary connecting rods and temporary scissor braces; the traction device is connected to the front end of the sliding unit, and the traction force is transmitted backward frame by frame through the temporary connecting rods, driving the multi-frame rigid frames to slide synchronously longitudinally along the track; the measuring point arrangement step, displacement monitoring step, torsion discrimination step, and differential speed correction step are continuously executed during the cumulative sliding process of the sliding unit.

[0015] Beneficial effects: By using temporary connecting rods and temporary scissor braces to form sliding units, during the cumulative sliding process, when a frame experiences a slight torsional tendency due to uneven traction forces on both sides, this torsional displacement must overcome the axial stiffness of the temporary connecting rods and the diagonal constraints of the scissor braces to be transmitted rearward frame by frame, thus structurally suppressing the amplification effect of torsion. Furthermore, by connecting the traction equipment to the front end of the sliding unit, the traction force is transmitted rearward frame by frame through the temporary connecting rods. When an intermediate frame experiences a displacement deviation relative to the preceding and following frames due to abnormal local resistance of the track, this deviation is immediately reflected in the relative displacement changes of the three measuring points—the left and right beam-column nodes and the mid-span of the crossbeam—of that frame, and is captured by the continuously operating monitoring system. This ensures that the torsional deviation at each moment is identified and corrected within the current sampling period, guaranteeing that the sliding unit's attitude is maintained within the δ threshold range throughout the entire stroke, achieving real-time control of the sliding unit's attitude throughout the entire process.

[0016] In one alternative implementation, the temporary scissor brace consists of two intersecting diagonal braces.

[0017] Beneficial effects: By using two intersecting diagonal braces to form a triangular stable structure, the temporary scissor bracing significantly enhances the overall stiffness and lateral displacement resistance of the temporary support system, effectively resisting horizontal and eccentric loads. Furthermore, the intersecting arrangement of the two diagonal braces provides a clear force transmission path, reduces the number of components, and improves on-site construction efficiency.

[0018] In one optional implementation, during the sliding process, the anti-sway limiting member provided on the rigid frame sliding support unit has a preset gap with the side of the track. When the lateral sway of the rigid frame reaches the gap value, the anti-sway limiting member contacts the side of the track to form a mechanical limit.

[0019] Beneficial effects: By setting a preset gap between the anti-sway limiter and the side of the track, once the lateral sway of the rigid frame reaches the critical value of this gap during sliding, the limiter immediately forms rigid contact with the side of the track, preventing further expansion of the sway from a geometrical perspective. Simultaneously, when the relative displacement change measured by the monitoring system is within the δ range, the limiter remains in a non-contact state with the track, generating no sliding resistance; once the displacement exceeds the limit and approaches the gap value due to traction failure, foreign objects on the track, or sudden impact, the limiter immediately engages, preventing the risk of runaway when closed-loop control fails.

[0020] In one alternative implementation, there is a gap between the anti-slip limiter and the side of the track, the gap providing a lateral slip tolerance greater than the lateral slip amount corresponding to the synchronous displacement difference threshold δ.

[0021] Beneficial effects: By setting a gap, the lateral runout tolerance provided is greater than the lateral runout amount corresponding to δ. During use, when the frame runout is still within the δ range, the anti-runout limiter does not contact the side of the track at all, and the sliding resistance is unaffected. The PLC controller drives the differential speed regulation via the frequency converter to perform active correction. Only when the runout continues to increase on the basis of δ after the differential correction is executed and exceeds the preset gap value, does the anti-runout limiter contact the side of the track to form a rigid mechanical limit. Thus, the active correction and mechanical limit form a logic of electronic control adjustment first, followed by mechanical limit, in terms of the timing of action. This avoids the mechanical limit contacting too early within the effective working range of active correction, which would generate additional sliding resistance and unnecessary wear. At the same time, it ensures that the mechanical limit can intervene in time when the electronic control adjustment capability is insufficient. The two types of protection measures perform their respective functions and are seamlessly connected.

[0022] In one optional implementation, during the differential correction step, the deceleration range of the leading traction device and the acceleration range of the lagging traction device are determined by the excess amount of the relative displacement change exceeding δ; when the relative displacement change falls back to within the range of δ, the two traction devices return to the same set traction speed.

[0023] Beneficial effects: By directly quantifying and determining the deceleration range on the leading side and the acceleration range on the lagging side based on the excess of relative displacement exceeding δ, the speed adjustment range is small when the sway just exceeds the limit during use. This avoids sudden changes in traction force and frame impact vibration caused by large speed adjustments. When the sway is large, the speed adjustment range increases accordingly to quickly correct the sway with sufficient differential torque. This achieves on-demand speed adjustment, ensuring that the correction force always matches the severity of the sway, avoiding under-adjustment or over-adjustment. Simultaneously, differential speed adjustment only exists temporarily within the time window of sway exceeding the limit; once the sway is eliminated, traction at the same speed is restored, preventing a cumulative deflection trend in the sliding unit due to a long-term speed difference between the two traction devices.

[0024] In one optional implementation, in the torsion discrimination step, the deformation type of the rigid frame is determined based on the distribution pattern of the relative displacement changes between the three monitoring points: when the relative displacement change between the left beam-column connection and the right beam-column connection does not exceed δ, but the relative displacement change between the mid-span of the crossbeam and the beam-column connection on either side exceeds δ, it is determined to be torsional deformation around the vertical axis; when the relative displacement changes between the three monitoring points along the sliding direction are in the same direction and have the same amplitude, it is determined to be overall translational skew.

[0025] Beneficial effects: By establishing a distribution pattern discrimination logic for the relative displacement changes between three measuring points, the original configuration data is further decoupled into identifiable deformation features. For example, when only the relative displacement change between the mid-span of the beam and the beam-column joint exceeds the limit, while the relative change between the beam-column joints on both sides does not exceed the limit, it is identified as torsional deformation around the vertical axis. When the three measuring points change in the same direction and with equal amplitude, it is identified as overall translational skew. Simultaneously, before initiating differential speed regulation, the deformation type is locked by the distribution pattern discrimination. Differential speed regulation is only executed on each side when torsional deformation is determined; when overall translational skew is determined, overall directional correction is adopted. This ensures that the correction measures accurately match the nature of the deformation, avoiding the problem of further deviation caused by incorrect correction strategies due to misjudgment of the deformation type. Attached Figure Description

[0026] To more clearly illustrate the technical solutions in the specific embodiments of the present invention, the drawings used in the description of the specific embodiments will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.

[0027] Figure 1 A schematic flowchart illustrating the sliding and positioning method for a photovoltaic portal frame above an existing building, provided in an embodiment of the present invention. Figure 2 A side view of the overall layout of a photovoltaic portal frame above an existing building, provided as an embodiment of the present invention. Figure 3 A front view schematic diagram of the overall layout of a photovoltaic portal frame above an existing building, provided as an embodiment of the present invention. Figure 4 A top-view schematic diagram of the overall layout of a photovoltaic portal frame above an existing building, provided as an embodiment of the present invention. Figure 5 A partial side view of the structure of a photovoltaic portal frame above an existing building, provided as an embodiment of the present invention; Figure 6 A top view schematic diagram of a partial structure of a photovoltaic portal frame above an existing building, provided as an embodiment of the present invention; Figure 7 This is a front view schematic diagram of a sliding system provided in an embodiment of the present invention; Figure 8 This is a side view schematic diagram of the sliding system provided in an embodiment of the present invention; Figure 9 This is a front view schematic diagram of the monitoring system provided in an embodiment of the present invention.

[0028] Explanation of reference numerals in the attached figures: 1. Existing building; 2. Independent foundation; 3. Embedded steel plate; 4. Embedded anchor bolt; 5. Sliding unit; 6. Steel rail; 7. Pressure plate bolt assembly; 8. Rubber gasket; 9. Pulley; 10. Pulley connector; 11. Temporary connecting bolt; 12. Column; 13. Beam; 14. Column base plate; 15. Anti-sway limiting component; 16. Temporary connecting rod; 17. Temporary scissor brace; 18. Traction equipment; 19. Traction cable; 20. Temporary fixing component; 21. Monitoring system; 22. First monitoring meter; 23. Second monitoring meter; 24. Third monitoring meter; 25. Permanent longitudinal tie rod; 26. Inter-column diagonal brace; 27. Roof horizontal brace; 28. Purlin; 29. ​​Photovoltaic module; K, Sliding direction; H, Safety clearance. Detailed Implementation

[0029] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0030] With the rapid development of photovoltaic power generation technology, erecting photovoltaic portal frames and installing photovoltaic modules above existing large-space buildings such as industrial buildings and warehousing and logistics facilities has become an important way to improve the utilization rate of building space and develop clean energy. Existing industrial buildings, due to their open spaces and good lighting conditions, have become the main application scenario for photovoltaic installations.

[0031] Currently, the common method for installing photovoltaic portal frames above existing buildings is as follows: Construction track foundations are poured on the ground on both sides of the existing building; a temporary support system is erected inside or around the building; and the frame components are hoisted piece by piece to the air for assembly and installation, or a single frame is assembled on the ground and then hoisted onto the track for sliding into position. During the sliding process, traction equipment typically provides power, connecting multiple frames into sliding units via temporary connectors, and then sliding them forward one by one. After sliding into position, the base plate of the frame columns is permanently anchored to the foundation embedded parts, and then the temporary sliding track and supporting temporary facilities are removed.

[0032] However, during use, it was found that when multiple rigid frames are connected into sliding units by temporary connectors and accumulating sliding of each frame, the sliding synchronization between each rigid frame and the torsional state of a single rigid frame cannot be judged solely by manual observation or single-point displacement data. As the cumulative sliding progresses, the slight asynchrony between each rigid frame will gradually amplify, causing the sliding unit to twist, get stuck on the rails, or even overturn, seriously threatening construction safety and positioning accuracy.

[0033] In view of the above-mentioned defects of the prior art, the embodiments of the present invention provide a method for sliding and positioning a photovoltaic portal frame above an existing building. The frame spans above the existing building 1, its bottom is supported by longitudinal rails, and the frame is provided with sliding driving force by traction devices 18 arranged on both sides.

[0034] In use, an independent foundation 2 completely detached from the main structure is set up on the exterior of the existing building 1, and a detachable longitudinal sliding track is erected on this foundation. After the photovoltaic portal frame is assembled on the ground, it is hoisted onto the track and connected to the sliding unit 5 by temporary connecting rods 16 and scissor braces for cumulative sliding. During the sliding process, the relative position of the three points of the beam-column nodes on both sides of the frame and the mid-span of the crossbeam 13 is used as the closed-loop criterion. The PLC controller uses the frequency converter to adjust the differential speed of the traction equipment 18 on both sides to achieve active correction. After positioning, the orderly force conversion from the temporary system to the permanent system is achieved through graded symmetrical fastening and continuous monitoring. Finally, all temporary sliding units 5 are dismantled and recycled to complete the installation of photovoltaic modules 29.

[0035] The following is combined Figures 1 to 9 This paper provides a detailed explanation of the sliding and positioning method for photovoltaic portal frames above existing buildings.

[0036] The skid system includes a longitudinal track, a skid support unit, a traction device 18, and an automatic control unit.

[0037] Among them, such as Figure 2 and Figure 3 As shown, the longitudinal track is set along the sliding direction K on both sides of the existing building 1, and its bottom is anchored to the load-bearing structure on both sides of the existing building 1 through the track foundation beam or directly.

[0038] The longitudinal rail is usually made of I-beams or channel steel. The top surface of the rail is the sliding working surface, and the side surface of the rail serves as the mating surface for anti-sway limit.

[0039] The sliding support unit is fixedly installed at the bottom of the rigid frame column 12, and its lower end is provided with a sliding pulley 9 or a sliding shoe. The sliding pulley 9 is embedded in the top surface of the track and can roll longitudinally along the track.

[0040] The traction device 18 is arranged in the front or end working area of ​​the sliding direction K. The traction device 18 includes a winch, a hydraulic traction device or an electric traction trolley. The output end of the traction device 18 is connected to the front end of the rigid frame or the sliding unit 5 through a traction rope (such as a steel wire rope or a high-strength fiber rope).

[0041] The automatic control unit includes a PLC controller, a frequency converter, and a signal acquisition module. The PLC controller is electrically connected to the drive motor of each traction device 18 through the frequency converter. The signal acquisition module is connected to the displacement sensor signal of each monitoring point to collect displacement signals in real time and transmit the signals to the PLC controller for processing.

[0042] It can be noted that the rigid frame is a photovoltaic portal frame, and its structural form is a portal frame system, including a left column 12, a right column 12, and a crossbeam 13. The two ends of the crossbeam 13 are connected to the upper ends of the left column 12 and the right column 12 respectively through rigid or hinged joints. Depending on the actual engineering needs, the rigid frame can be a single rigid frame or a sliding unit 5 composed of multiple rigid frames connected by temporary connecting members.

[0043] During sliding, the rigid frame spans above the existing building 1, with the left column 12 and right column 12 located on the left and right sides of the existing building 1, respectively, and the crossbeam 13 spans across the top of the existing building 1. The bottom of the rigid frame is supported by longitudinal rails, and the traction device 18 is connected to the front end of the rigid frame or sliding unit 5 to provide traction driving force for sliding.

[0044] Preferably, there are two frequency converters, which serve as the left frequency converter and the right frequency converter, respectively, and are communicatively connected to the traction equipment 18 on both sides.

[0045] It should be noted that the specific location of the measuring points is not strictly limited in the measuring point layout process, as long as they can effectively reflect the displacement and deformation state of the rigid frame in the horizontal plane.

[0046] For example, monitoring points can be set at the bottom of column 12, at the connection node between column 12 and beam 13, at the mid-span of beam 13, or at one-third point of beam 13.

[0047] Preferably, such as Figure 9 As shown, a first monitoring point, a second monitoring point, and a third monitoring point are set at the left beam-column connection point, the mid-span of the crossbeam 13, and the right beam-column connection point of the rigid frame, respectively. A first monitoring meter 22, a second monitoring meter 23, and a third monitoring meter 24 are also set up, and a synchronous displacement difference threshold δ is preset.

[0048] Specifically, the left beam-column connection is the junction between the upper end of the left column 12 of the rigid frame and the left end of the crossbeam 13. This junction is either a rigid or hinged connection, and a gusset plate or stiffening rib is provided at the junction to facilitate the installation and fixation of the displacement sensor. The right beam-column connection is the junction between the upper end of the right column 12 of the rigid frame and the right end of the crossbeam 13, and its construction is the same as that of the left beam-column connection. The mid-span of the crossbeam 13 is the midpoint of the crossbeam 13, that is, the geometric center point of the crossbeam 13 along its length.

[0049] By setting the intersection nodes of the left and right columns 12 and the crossbeam 13, as well as the midpoint of the crossbeam 13, a point matrix is ​​formed in the plane of the rigid frame. This allows the relative configuration of the three points to simultaneously and uniquely characterize the three rigid body motion states of the rigid frame in the horizontal plane, directly reflecting the torsional offset of the crossbeam 13 at mid-span relative to the two end nodes.

[0050] Meanwhile, during the cumulative slip process, when any frame tends to twist due to uneven traction forces on both sides or differences in track resistance, the displacement response at the beam-column joint is the most direct and sensitive. By setting the monitoring device at this location, the monitoring system 21 can capture abnormal signals in the earliest stage of torsion development, providing the PLC controller with a judgment basis that is ahead of the torsion deterioration, and greatly improving the response timeliness and anti-interference capability of the closed-loop speed control system.

[0051] Furthermore, by adding a third measuring point at the midpoint of beam 13, the relative displacement direction and magnitude between the mid-span measuring point and the measuring points at the beam-column nodes on both sides can be clearly distinguished from different states such as pure torsion and overall skew. This allows the PLC controller to trigger differential speed correction only when the rigid frame actually undergoes torsional deformation, avoiding ineffective speed regulation due to misjudging overall skew as torsion, or even causing further attitude misalignment. This makes the closed-loop control decision more accurate and the control process more effective.

[0052] When setting up monitoring points, displacement monitoring meters are fixedly installed at each monitoring point location. The displacement monitoring meters can be wire-type displacement sensors, laser displacement sensors, GPS displacement monitoring instruments, or total station reflective targets, etc.

[0053] Furthermore, the displacement monitoring meter can acquire horizontal displacement signals along the sliding direction K (i.e., longitudinal direction) of the corresponding monitoring point in real time, and can further acquire vertical and lateral displacement signals, using both horizontal and vertical displacements to calculate the relative displacement change. The signal output terminal of the displacement monitoring meter is connected to the signal acquisition module via a signal transmission cable or a wireless transmission module.

[0054] By setting the monitoring point at the beam-column node, the monitoring system 21 can capture abnormal signals in the earliest stage of torsional development, providing a judgment basis for subsequent closed-loop control that is ahead of torsional deterioration.

[0055] By collecting the vertical displacement of the monitoring points, the detected horizontal displacement can be combined with the vertical displacement, and the two can be used together to calculate the relative displacement change. This allows the relative configuration formed by the first to third monitoring points to simultaneously characterize the various deformation states of the frame, such as torsion in the horizontal plane, tilting in the vertical plane, and lateral tilting of the beam 13 around the longitudinal axis. This enhances the closed-loop criterion's ability to holographically perceive abnormal spatial attitude of the frame.

[0056] Meanwhile, by incorporating both vertical and horizontal displacements into the calculation of relative displacement changes, the PLC controller can detect instability trends from abnormal changes in vertical displacement difference at the early stage of torsion and initiate proactive intervention before horizontal torsion develops significantly, thereby improving the response speed of closed-loop control.

[0057] It should be noted that there are no specific restrictions on the height of the three monitoring points; they can be arranged as needed during installation.

[0058] For example, such as Figure 9 As shown, the vertical displacement of the second monitoring point increases positively relative to the first and third monitoring points, meaning that the mid-span of the beam 13 bulges upward in the vertical plane, while the left and right end nodes remain basically in their original positions.

[0059] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building includes the construction steps of an independent foundation 2.

[0060] It should be noted that there are no specific limitations on the specific structural form and construction process of the independent foundation 2. It can be a cast-in-place concrete spread foundation, pile foundation or raft foundation, etc.

[0061] Preferably, cast-in-place concrete independent spread foundations are used.

[0062] Specifically, foundation layout areas are demarcated on both sides of the exterior of the existing building 1 along its length. These areas maintain a set clearance from the exterior walls of the existing building 1 to avoid disturbing the main structure of the building during foundation construction and subsequent use.

[0063] Foundation points are arranged in pairs along the longitudinal direction of the existing building 1 according to the design spacing of the photovoltaic portal frame, and several independent foundations 2 are cast in place using concrete. The independent foundations 2 are arranged in pairs on both sides, and are arranged along the longitudinal direction of the building at a set spacing. There is no connection between the independent foundations 2 and the main structure of the existing building 1, and they do not transfer loads to each other, allowing all construction work to be completed outside the building without affecting production inside. During the casting of the independent foundations 2, pre-embedded steel plates 3 are embedded in the top surface of the foundation, and pre-embedded anchor bolts 4 are anchored to the pre-embedded steel plates 3 and the foundation concrete. The pre-embedded steel plates 3 serve as the shared installation interface for the temporary and permanent systems of this invention, and in subsequent steps, they also serve as a shared location and elevation benchmark for the temporary fixing of the rails 6 and the permanent anchoring of the column base plate 14. The next process can only proceed after the foundation concrete strength reaches the design requirements.

[0064] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building includes the step of erecting a detachable sliding unit 5.

[0065] It can be noted that there are no specific limitations on the fixing method between the rail 6 and the independent foundation 2. The fixing method can be the pressure plate bolt assembly 7, the gauge block or the elastic fastener, etc.

[0066] Preferably, a pressure plate bolt assembly 7 is used for detachable fixing.

[0067] Specifically, such as Figures 3 to 8 As shown, supported by independent foundations 2 on both sides, a steel rail 6 is laid on the top surface of each foundation along the longitudinal direction of the existing building 1. The two steel rails 6 are parallel to each other and have the same longitudinal slope. The laying length of the steel rail 6 covers the entire longitudinal length of the existing building 1, and extends outward to the starting end working area at one end, leaving a sliding allowance for the positioning end at the other end. The steel rail 6 is temporarily and detachably fixed to the embedded steel plate 3 on the top surface of the foundation by means of a pressure plate bolt assembly 7.

[0068] Furthermore, the pressure plate of the pressure plate bolt assembly 7 is pressed against the bottom flange of the rail 6. A rubber gasket 8 is provided between the pressure plate and the bottom flange of the rail 6 to provide cushioning and vibration reduction. The bolts of the pressure plate bolt assembly 7 are connected to the reserved connection holes on the embedded steel plate 3 or welded to the connection seat on the embedded steel plate 3. After the track is laid, a level is used to adjust the level and the parallelism and gauge of the two rails are re-measured to ensure that the sliding accuracy requirements are met.

[0069] It should be noted that the connection position of the pressure plate bolt assembly 7 on the embedded steel plate 3 is staggered from the anchoring position of the column base plate 14 on the embedded steel plate 3, and the pressure plate bolt assembly 7 and the temporary connecting bolt 11 are two independent sets of connecting parts. The former is used for temporary fixing between the rail 6 and the independent foundation 2, and the latter is used for temporary connection between the pulley connector 10 and the column base plate 14. The two do not interfere with each other structurally, avoiding accidental movement of the other set when removing one set. Therefore, the subsequent permanent anchoring construction can be carried out under the condition that the temporary fixing of the rail 6 is undisturbed. The temporary system and the permanent system overlap and coexist on the same embedded steel plate 3 interface and are carried out in parallel.

[0070] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building includes a ground assembly step for the photovoltaic portal frame.

[0071] It should be noted that there are no specific restrictions on the specific connection method of the photovoltaic portal frame; it can be welding, bolt connection, or a hybrid bolt-weld connection, etc.

[0072] Preferably, integral welding assembly is adopted.

[0073] Specifically, at the ground work area outside the existing building 1, where the starting end of the steel rail 6 is located, the steel columns 12 and beams 13 are assembled into a single independent photovoltaic portal frame. The span of the frame is adapted to the width of the existing building 1, and the height of the columns 12 is greater than the height of the existing building 1 to ensure sufficient safety clearance H when the frame spans over the existing building 1. The bottom plate 14 of the column 12 is welded to the bottom of the column.

[0074] Similarly, the specific configuration of the sliding support unit is not specifically limited. It can be that a pulley connector 10 is set below the column base plate 14 and the two are connected by bolts.

[0075] Preferably, at least two pulleys 9 are arranged along the direction of the rail 6 below each column base plate 14. The pulleys 9 are mounted to the pulley connector 10 via pulley 9 axles. The pulley connector 10 is attached to the bottom surface of the column base plate 14 and is detachably connected to the column base plate 14 via temporary connecting bolts 11. The column base plate 14, the pulley connector 10, and the pulleys 9 together constitute a sliding support unit.

[0076] In one embodiment, such as Figure 7 and Figure 8 As shown, in order to prevent the rigid frame from lateral swaying during the sliding process, the pulley connector 10 is also provided with an anti-sway limiter 15 that is clearance-fitted with the side of the rail 6.

[0077] It can be noted that the specific form of the anti-sway limiter 15 is not specifically limited; it can be a guide wheel or an anti-sway clamp.

[0078] In one embodiment, the anti-sway limiting member 15 is a guide wheel. The guide wheel is installed on the side of the pulley connector 10 facing the side of the rail head of the rail 6 and makes rolling contact with the side of the rail head of the rail 6.

[0079] In another implementation, the anti-sway limiting component 15 is an anti-sway clamp, which is clamped on both sides of the rail head of rail 6, with a fitting gap between it and the side of the rail head of rail 6. This anti-sway limiting component 15 geometrically limits the lateral sway and overturning angle of the frame during the sliding process, serving as a mechanical limiting measure to prevent overturning and swaying, and as backup protection for the differential speed correction step.

[0080] When in use, the mechanical limit switch serves as the first line of defense in the triple anti-overturning measures, and its action sequence naturally progresses with the second layer of closed-loop speed regulation active correction and the third layer of temporary guy rope passive safety.

[0081] That is, during normal sliding, the limiting component does not contact and there is no frictional wear; when the sway is small, it is eliminated in advance by active correction, and the limiting component still does not move to avoid mechanical contact and jamming resistance; the limiting component only passively contacts and limits when the active correction capability is insufficient or fails, and after contact, it can still be tied by the subsequent guy rope.

[0082] In one embodiment, an overall inspection should be carried out after the rigid frame is assembled.

[0083] For example: Specifically, the verticality of column 12 is checked using a theodolite, and the deviation should not exceed 1 / 1000 of the height of column 12 and not exceed 15mm; the flatness of beam 13 is checked using a level, and the flatness deviation within the span of beam 13 should not exceed 1 / 1500 of the span of beam 13 and not exceed 10mm. Only after the inspections are passed and rust prevention treatment is applied to the welds can the hoisting process begin.

[0084] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building includes a step of hoisting the frame onto the upper rail.

[0085] It should be noted that there are no specific restrictions on the hoisting method of the rigid frame; it can be two-point hoisting, four-point hoisting, or hoisting with the assistance of a balance beam, etc.

[0086] Preferably, a four-point hoisting method is adopted and a balance beam is configured.

[0087] Specifically, a truck crane is used to lift the qualified single photovoltaic portal frame as a whole. Four lifting points are symmetrically arranged on the crossbeam 13 near the beam-column joints, and a balance beam is configured to ensure that the frame is subjected to balanced forces and does not deform during the lifting process. The frame is slowly moved above the starting end of the rail 6 and precisely lowered, so that the pulleys 9 of the sliding support units on both sides land on the top surfaces of the two rails 6 respectively, completing the upper rail positioning of the frame. The frame spans the existing building 1, and a safe clearance H is maintained between the frame and the roof and walls of the existing building 1.

[0088] Furthermore, the safety clearance H is preferably 100mm to 500mm, and not less than the structural deformation value determined by calculation based on wind load, temperature deformation, and construction deviation, to achieve complete separation of the rigid frame from the existing building 1. After installation, the safety clearance H between the rigid frame and the existing building 1 should be re-measured to confirm that it meets the design requirements.

[0089] It can be explained that the process of assembling the photovoltaic portal frame on the ground and hoisting the frame onto the rails is repeated in the starting work area to complete the assembly, testing and rail installation of the next photovoltaic portal frame.

[0090] Adjacent pre-mounted rail frames are connected to form sliding units 5 via temporary connecting rods 16 and temporary scissor braces 17. The temporary connecting rods 16 and temporary scissor braces 17 together maintain the designed longitudinal spacing and spatial configuration of each frame within the sliding unit 5. The traction device 18, using an electric winch or hydraulic traction unit, is fixed to the end of the rail 6 or an independent foundation 2 at the positioning end. The traction cable 19 is connected to the column 12 of the first frame at the front of the sliding unit 5. The traction force is transmitted sequentially backward via the temporary connecting rods 16, causing all pre-mounted rail frames to slide synchronously longitudinally along the rail 6, freeing up assembly space in the starting work area. This process is repeated until all frames slide longitudinally to their designed positions. The traction force transmission path and the configuration of the sliding unit 5 share the same temporary rod system, preventing additional torsion caused by longitudinal spacing instability during cumulative sliding of a single frame.

[0091] In one embodiment, a trial sliding test must be conducted in the starting work area before the formal sliding begins. The specific procedure for the trial sliding test is as follows: first, a no-load trial sliding test and a loaded trial sliding test are conducted, and the initial relative displacement of three points is recorded. Then, the traction speed is increased in stages, and the relative displacement change between the three monitoring points is collected at each traction speed level. The matching between the synchronous displacement difference threshold δ and the traction speed is checked. After confirming that there is no rail jamming or abnormal swaying at each speed level, the formal sliding test begins.

[0092] By adding an unloaded sliding stage, errors such as unevenness at the rail joint 6, local deviation in track gauge, jamming of the pulley bearing 9, and gap between the anti-sway limiter 15 and the side of the rail head are identified in advance and incorporated into the measured benchmark of the initial relative configuration. This ensures that the closed-loop criterion for formal sliding is based on the measured initial state that includes actual mechanical errors, rather than a theoretical ideal state that is detached from engineering reality. This avoids the dual risks of frequent false alarms of exceeding limits or failure to judge the actual torsion in the formal sliding start-up stage due to the initial deviation of the mechanical system.

[0093] By further setting up a load-bearing test sliding stage, the multiple rigid frames connected to form sliding unit 5 are tested under actual traction force. This allows for the acquisition of key dynamic parameters such as starting friction resistance, uniform traction force, and acceleration response characteristics of sliding unit 5 under real load conditions in advance. These parameters are then correlated with the three-point relative configuration monitoring data to improve the synchronous control accuracy in the initial stage of sliding.

[0094] In one embodiment, during the actual sliding process, displacement signals from three monitoring points are acquired in real time, and the current relative displacement between any two monitoring points is calculated based on the acquired signals. This current relative displacement is then compared with the initial relative displacement at the start of the sliding process to obtain the change in relative displacement.

[0095] During the sliding process, the displacement signals collected by each monitoring instrument are transmitted to the PLC controller via the data acquisition unit (a multi-channel data acquisition instrument can be used). The PLC controller calculates the relative displacement change between any two measuring points according to the set sampling period and compares it with the preset synchronous displacement difference threshold δ. The relative displacement change is the change in the relative positional relationship between the two measuring points relative to the initial relative configuration during the sliding process.

[0096] The torsion discrimination step is then performed, that is, the relative displacement change is compared with the synchronous displacement difference threshold δ. If the relative displacement change between any two measuring points does not exceed δ, the sliding is determined to be stable and traction is maintained; if any relative displacement change exceeds δ, the rigid frame is determined to have undergone torsional deformation around the vertical axis, and the leading and lagging sides of the sliding on both sides of the rigid frame are determined according to the displacement signals of each monitoring point.

[0097] Then, a differential speed correction step is performed, that is, a deceleration command is output to the sliding leading side traction device 18, and an acceleration command is output to the sliding lagging side traction device 18, so that the two traction devices 18 generate a differential speed to correct the torsional posture of the rigid frame, and the monitoring continues until the relative displacement change falls back to the range of δ.

[0098] By setting up three monitoring points at the beam-column joints on both sides of the rigid frame and at the mid-span of the crossbeam 13, the monitoring data is used as a relative configuration criterion to characterize the torsional deformation of the rigid frame in the plane. This not only reflects the longitudinal slip difference of the columns 12 on both sides, but also quantifies the degree of torsional deformation of the rigid frame around the vertical axis by measuring the relative displacement change between the mid-span measuring point and the measuring points at both ends.

[0099] When the relative displacement change between any measuring points exceeds the limit, the PLC controller can accurately determine the leading and lagging sides of the slippage based on the direction of the displacement difference, trigger speed regulation, and realize active closed-loop control with real-time judgment and immediate response.

[0100] Furthermore, by directly linking the real-time monitoring signals of the three-point relative configuration with the variable frequency speed control drive system of the traction equipment 18 on both sides, a complete closed-loop signal link of monitoring, judgment, speed adjustment, and re-monitoring is formed. When the torsion of the rigid frame is detected, the PLC controller outputs a deceleration command to the sliding leading side equipment and an acceleration command to the lagging side equipment. Through the dynamic differential adjustment of the traction forces on both sides, the rigid frame attitude is actively corrected, so that the relative displacement change is always controlled within the preset threshold δ range. This avoids the impact load and additional stress on the rigid frame caused by unilateral forced braking, so that the cumulative sliding process proceeds smoothly and the positioning accuracy is improved.

[0101] In addition, before the formal sliding test, the value of δ was checked by the on-site sliding test in the starting work area under no-load and loaded grade speed increase. The matching between δ and traction speed was verified by the measured relative displacement change data. This ensured that the sensitivity and anti-interference capability of the closed-loop control system were adapted to the actual track conditions, traction equipment performance and frame stiffness characteristics, and ensured the reliability of the closed-loop criterion at each sliding speed level.

[0102] Furthermore, in the torsion discrimination step, the deformation type of the rigid frame is determined according to the distribution pattern of the relative displacement change between the three monitoring points: when the relative displacement change between the left beam-column connection and the right beam-column connection does not exceed δ, but the relative displacement change between the mid-span of the crossbeam 13 and the beam-column connection on either side exceeds δ, it is determined to be torsional deformation around the vertical axis; when the relative displacement change between the three monitoring points along the sliding direction K is in the same direction and of equal amplitude, it is determined to be overall translational skew.

[0103] By establishing a distribution pattern discrimination logic for the relative displacement changes between the three measuring points, the original configuration data is further decoupled into identifiable deformation features.

[0104] For example, when the relative displacement change between the beam and the column node in the middle of the 13th span of the crossbeam exceeds the limit, while the relative displacement change between the beam and column nodes on both sides does not exceed the limit, it is identified as torsional deformation around the vertical axis. When the three measuring points change in the same direction and with equal amplitude, it is identified as overall translational deviation.

[0105] Meanwhile, before starting differential speed regulation, the deformation type is first identified and locked through the distribution mode. Differential speed regulation is only executed when it is determined to be torsional deformation. When it is determined to be overall translational deviation, overall direction correction is adopted to ensure that the correction measures are accurately matched with the nature of the deformation and to avoid the problem of more deviation caused by incorrect correction strategies due to misjudgment of the deformation type.

[0106] It should be noted that the value of the synchronous displacement difference threshold δ is determined according to the span of the rigid frame. For example, when the rigid frame span is not less than 15m, δ is 5mm to 20mm and not greater than 1 / 3000 of the rigid frame span; when the rigid frame span is less than 15m, δ is 1 / 3000 of the rigid frame span. This threshold, along with the traction speed, is verified and corrected using data collected from the graded acceleration during the on-site sliding test.

[0107] It can be explained that, in the differential speed correction step, the deceleration range of the leading traction device 18 and the acceleration range of the lagging traction device 18 are determined by the excess amount of the relative displacement change exceeding δ; when the relative displacement change falls back to the range of δ, the two traction devices 18 return to the same set traction speed.

[0108] The deceleration magnitude on the leading side and the acceleration magnitude on the lagging side are directly quantified and determined by the excess amount of relative displacement exceeding δ. In use, when the sway just exceeds the limit, the speed adjustment range is small to avoid sudden changes in traction force and frame impact vibration caused by large speed adjustments; when the sway is large, the speed adjustment range is correspondingly increased to quickly correct the sway with sufficient differential torque. This achieves on-demand speed adjustment, ensuring that the correction force always matches the severity of the sway, avoiding under-adjustment or over-adjustment.

[0109] Meanwhile, differential speed regulation only exists temporarily within the time window when the sway exceeds the limit. Once the sway is eliminated, the same speed traction is restored, avoiding the cumulative deflection trend of the sliding unit 5 as a whole due to the long-term speed difference between the two traction devices 18.

[0110] It can be explained that during the sliding process, there is a preset gap between the anti-sway limiter 15 set on the rigid frame sliding support unit and the side of the track. When the lateral sway of the rigid frame reaches the gap value, the anti-sway limiter 15 contacts the side of the track to form a mechanical limit.

[0111] By setting a preset gap between the anti-sway limiter 15 and the side of the track, once the lateral sway of the rigid frame reaches the critical value of the gap during the sliding process, the limiter immediately forms rigid contact with the side of the track, thus preventing further expansion of the sway from a geometrical perspective.

[0112] Meanwhile, when the relative displacement change measured by the monitoring system 21 is within the range of δ, the limit component remains in a non-contact state with the track and does not generate slip resistance; once the displacement exceeds the limit and approaches the gap value due to traction failure, foreign objects on the track or sudden impact, the limit component immediately contacts the limit to prevent the risk of loss of control when the closed-loop control fails.

[0113] Furthermore, there is a gap between the anti-sway limiter 15 and the side of the track, and the lateral sway tolerance provided by this gap is greater than the lateral sway amount corresponding to the synchronous displacement difference threshold δ.

[0114] The lateral runout tolerance provided by the set gap is greater than the lateral runout amount corresponding to δ. When in use, when the frame runout amount is still within the range of δ, the anti-runout limiter 15 does not contact the side of the track at all, and the sliding resistance is not affected. The PLC controller drives the differential speed regulation through the frequency converter to perform active correction. Only when the runout amount continues to increase on the basis of δ after the differential correction is performed and exceeds the preset gap value, does the anti-runout limiter 15 contact the side of the track to form a rigid mechanical limit.

[0115] Thus, the active correction and mechanical limit are arranged in a sequence of action, with the electronic control adjustment preceding the mechanical limit. This avoids the mechanical limit from making premature contact within the effective working range of the active correction, which would generate additional sliding resistance and unnecessary wear. At the same time, it ensures that the mechanical limit can intervene in time when the electronic control adjustment capability is insufficient. The two types of protection measures perform their respective functions and are seamlessly connected.

[0116] In one embodiment, such as Figure 2 As shown, temporary connecting parts, such as temporary guy ropes or temporary diagonal braces, are also provided on both sides of the sliding unit 5. These temporary guy ropes or temporary diagonal braces provide a bottom-line tie constraint to the sliding unit 5 in abnormal working conditions such as sudden gusts or traction failures, constituting a passive safety measure.

[0117] This configuration allows the mechanical limiters to geometrically define the extreme positions of sway and overturning; the active correction eliminates sway and torsion before they reach the mechanical limiters; and the passive safety measure provides a backup in abnormal operating conditions. If any single measure fails, the other two measures can still limit the torsion, sway, and overturning of the frame through geometric limits, differential adjustment, or backup bracing, respectively, forming a safety redundancy.

[0118] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building also includes the step of permanently fixing and forming a spatial support system.

[0119] It can be explained that after all the photovoltaic portal frames have slid to the design position, the column base plate 14 is connected to the pre-embedded anchor bolts 4 and tightened symmetrically in stages.

[0120] Preferably, a three-stage symmetrical fastening method is used.

[0121] Specifically, during the entire period of graded symmetrical tightening, the monitoring system 21 continuously collects the displacement of three measuring points on the frame and calculates the relative displacement change, achieving continuous monitoring during the transition period. Between two adjacent tightening stages, the monitoring system 21 re-measures the relative configuration of the three measuring points on the frame. Only when the relative displacement change between any two measuring points does not exceed the synchronous displacement difference threshold δ, can the next level of tightening be initiated. If any relative displacement change exceeds δ during the tightening process, the tightening operation is stopped, the fit between the column base plate 14 and the embedded steel plate 3 and the tightening sequence of the embedded anchor bolts 4 are checked, and after eliminating any abnormalities, the tightening is restarted according to the graded sequence.

[0122] After the third stage of fastening is completed, and the load on the rigid frame is transferred from the sliding support unit to the permanent force transmission path formed by the column base plate 14, the pre-embedded anchor bolts 4, the pre-embedded steel plate 3, and the independent foundation 2, and the relative displacement change between the three measuring points does not exceed δ, the permanent force transmission path is confirmed to form an effective constraint. Then, the temporary connecting bolts 11 are removed, and the pulleys 9 and pulley connectors 10 are removed. That is, the load is transferred first, the configuration is confirmed first, and the temporary support is removed last. The rigid frame remains in an effective constraint state throughout the entire conversion process.

[0123] Meanwhile, before all the column base plates 14 of the same frame are permanently anchored, the temporary connecting rods 16 and temporary scissor braces 17 between that frame and adjacent frames shall not be removed. Only after all the column base plates 14 of the same frame are permanently anchored can the temporary connecting rods 16 and temporary scissor braces 17 between that frame and adjacent frames be removed, and permanent longitudinal tie rods 25 be installed in their place. Subsequently, inter-column diagonal braces 26 are installed between the columns 12 of adjacent frames, and roof horizontal braces 27 are installed on the roof, so that all individual frames are connected into a stable independent spatial support system, and the system is then subjected to overall testing.

[0124] In the above process, the same synchronous displacement difference threshold δ is reused in three links: the sliding speed regulation criterion, the inter-stage release criterion of graded symmetrical fastening, and the temporary connection bolt 11 removal and unlocking criterion, and runs through the entire process of the sliding period and the transition period.

[0125] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building also includes a step of dismantling and recycling the sliding unit 5.

[0126] Specifically, after the independent space support system passes the overall inspection, the detachable connection between the rail 6 and the embedded steel plate 3 will be released.

[0127] That is, first remove the pressure plate bolt assembly 7, then dismantle the rail 6 in sections from the positioning end to the starting end, and then classify and recycle the rail 6, pulley 9, pulley connector 10, temporary connecting bolt 11, pressure plate bolt assembly 7, and rubber gasket 8. All of the above components are detachable bolted connections. After dismantling, only the embedded steel plate 3 and embedded anchor bolt 4 are retained on the top surface of the independent foundation 2. No temporary structures are left on the construction site, and the materials can be reused.

[0128] In one embodiment, the method for sliding and positioning a photovoltaic portal frame above an existing building also includes a photovoltaic unit installation step.

[0129] Specifically, purlins 28 are laid on the beams 13 of the formed spatial support system.

[0130] It should be noted that there are no specific limitations on the laying method of purlin 28; it can be laid by welding, bolting, or by using purlin brackets.

[0131] Preferably, bolts are used to fix it to the crossbeam 13.

[0132] Photovoltaic modules 29 and associated electrical equipment are installed on purlins 28.

[0133] It should be noted that the installation method of photovoltaic module 29 is not specifically limited, and can be installed by means of clamping, bolting or adhesive bonding.

[0134] Preferably, the photovoltaic system is installed sequentially using clamping blocks. Then, the combiner box, inverter, and other auxiliary electrical equipment are installed to complete the wiring and commissioning of the photovoltaic system.

[0135] In one embodiment, the measuring point arrangement step, displacement monitoring step, torsion discrimination step, and differential speed correction step are continuously executed during the cumulative sliding process of the sliding unit 5.

[0136] When an intermediate frame experiences a displacement deviation relative to the preceding and following frames due to abnormal local resistance of the track, this deviation will be immediately reflected in the relative displacement changes of the left and right beam-column nodes and the three measuring points at the mid-span of the crossbeam 13 of that frame. This deviation will be captured by the continuously operating monitoring system 21, which will identify and correct the torsional deviation at each moment within the current sampling period, ensuring that the attitude of the sliding unit 5 is always maintained within the δ threshold range throughout the entire stroke, thereby achieving real-time control of the attitude of the sliding unit 5 throughout the entire process.

[0137] In one embodiment, the temporary scissor brace 17 consists of two intersecting diagonal braces.

[0138] By constructing the temporary scissor brace 17 from two intersecting diagonal braces, a triangular stable structure is formed, significantly enhancing the overall stiffness and lateral displacement resistance of the temporary support system, effectively resisting horizontal and eccentric loads. Simultaneously, the intersecting arrangement of the two diagonal braces provides a clear force transmission path, reduces the number of components, and facilitates improved on-site construction efficiency.

[0139] Furthermore, the torsional stiffness of the temporary scissor brace 17 is greater than the bending stiffness of the temporary connecting rod 16.

[0140] In use, the torsional constraint of the sliding unit 5 is mainly borne by the temporary scissor brace 17, and the longitudinal traction force transmission is mainly borne by the temporary connecting rod 16.

[0141] The sliding positioning method for photovoltaic portal frames above existing buildings provided in the above embodiments uses the same synchronous displacement difference threshold δ as the speed regulation criterion during the sliding period, the inter-stage release criterion for graded symmetrical tightening during the transition period, and the removal and unlocking criterion for temporary connecting bolts 11, spanning the entire process of the sliding and transition periods. This allows the quantitative configuration benchmark established during the sliding phase to continue as the tightening release and disassembly unlocking benchmark during the transition period without needing to be changed, avoiding benchmark conversion errors and criterion gaps caused by setting separate criteria during the transition period. Abnormal configuration changes during the transition period can be identified and disassembly operations can be stopped before the temporary constraints are released, eliminating the constraint gap where temporary supports and permanent anchors fail simultaneously.

[0142] The sliding positioning method for a photovoltaic portal frame above an existing building provided in the above embodiments uses a first monitoring device 22 and a third monitoring device 24 arranged at the beam-column nodes on both sides of the frame, and a second monitoring device 23 arranged at the mid-span of the crossbeam 13. The relative configuration formed by the three measuring points can identify the torsional deformation of the frame around the vertical axis, rather than just the longitudinal synchronization difference of the two columns 12. If only two measuring points are arranged at the beam-column nodes on both sides, only the longitudinal synchronization difference on both sides can be reflected, and the overall translational deviation and torsion around the vertical axis of the frame cannot be distinguished. After including the measuring point at the mid-span of the crossbeam 13, the relative displacement change between the mid-span measuring point and the measuring points at the beam-column nodes on both sides can directly characterize the torsional offset of the mid-span of the crossbeam 13 relative to the two end nodes, thereby incorporating torsional deformation into the closed-loop criterion. Meanwhile, by incorporating the vertical and horizontal displacements collected by each monitoring unit into the calculation of the relative displacement change, the relative configuration formed by the first to third monitoring points can simultaneously characterize the various deformation states of the frame, such as torsion in the horizontal plane, tilting in the vertical plane, and lateral tilting of the beam 13 around the longitudinal axis, thereby further enhancing the closed-loop criterion's ability to holographically perceive abnormal spatial attitude of the frame.

[0143] The sliding positioning method for photovoltaic portal frames above existing buildings provided in the above embodiments uses temporary connecting rods 16 and temporary scissor braces 17 to maintain the designed longitudinal spacing and spatial configuration of each frame within the sliding unit 5. Traction force is transmitted rearward frame by frame via the temporary connecting rods 16, and the traction force transmission path and unit configuration share the same temporary rod system. When a frame experiences a slight torsional tendency due to uneven traction forces on both sides, this torsional displacement must overcome the axial stiffness of the temporary connecting rods 16 and the diagonal constraints of the temporary scissor braces 17 to be transmitted rearward frame by frame, structurally suppressing the gradual amplification effect of torsion. The temporary scissor braces 17 consist of two intersecting diagonal braces, forming a triangular stable structure, significantly enhancing the overall stiffness and lateral displacement resistance of the temporary support system. During the cumulative slip process, when an intermediate frame experiences a displacement deviation relative to the front and rear frames due to abnormal local resistance of the track, this deviation will be immediately reflected in the relative displacement changes of the left and right beam-column nodes and the three measuring points at the mid-span of the crossbeam 13 of that frame, and will be captured by the continuously operating monitoring system 21, ensuring that the torsional deviation at each moment is identified and corrected within the current sampling period.

[0144] The sliding positioning method for photovoltaic portal frames above existing buildings provided in the above embodiments uses the embedded steel plate 3 as both the installation interface for temporary fixing of the rail 6 and the installation interface for permanent anchoring of the column base plate 14. The temporary and permanent systems share the same installation reference, with a unique interface reference and clear force transmission position, avoiding elevation and position deviations caused by separate interfaces for temporary fixing and permanent anchoring. The connection position of the pressure plate bolt assembly 7 on the embedded steel plate 3 is staggered from the anchoring position of the column base plate 14 on the embedded steel plate 3, and the pressure plate bolt assembly 7 and the temporary connecting bolt 11 are two independent sets of connectors, ensuring that the temporary fixing of the rail 6 is not disturbed during the permanent anchoring construction and that removing one set of connectors will not accidentally move the other set. The aforementioned staggered structure is a structural prerequisite for the implementation of sequential interlocking during the transition period. Combined with the orderly transition sequence and transition period criteria of first tightening the pre-embedded anchor bolts 4 in stages and symmetrically, continuously monitoring the relative configuration of the three points during tightening, forming a permanent force transmission path and ensuring that the configuration change does not exceed δ, removing the temporary connecting bolts 11 and removing the pulleys 9, retaining the temporary connecting rods 16 and temporary scissor braces 17 before the anchoring of all column base plates 14 of the same frame is completed, and only after the anchoring is completed can the rods be removed and replaced with permanent tie rods, the rigid frame is always in an effective constraint state throughout the entire process of transitioning from the temporary system to the permanent system, reducing the constraint gap during the transition period.

[0145] The sliding positioning method for photovoltaic portal frames above existing buildings provided in the above embodiments allows for the overall hoisting of the frame after it has been assembled and inspected on the ground, significantly reducing the amount of high-altitude work. Under ground assembly conditions, the inspection and adjustment of the verticality of the columns 12 and the flatness of the beams 13 are more convenient, assembly accuracy is easier to ensure, and the safety risks of high-altitude work are reduced. After ground assembly, an overall inspection is conducted, and hoisting can only proceed after the inspection is passed, avoiding rework at height.

[0146] Although embodiments of the invention have been described in conjunction with the accompanying drawings, those skilled in the art can make various modifications and variations without departing from the spirit and scope of the invention, and such modifications and variations all fall within the scope defined by the appended claims.

Claims

1. A method of slip-forming an over-roof photovoltaic portal frame to an existing building, characterised in that, A rigid frame is installed above an existing building (1), its bottom is supported by longitudinal rails, and the rigid frame is provided with sliding driving force by traction devices (18) arranged on both sides. The method includes the following steps: Measurement point layout: The first monitoring point, the second monitoring point and the third monitoring point are respectively set at the left beam-column connection part, the mid-span part of the crossbeam (13) and the right beam-column connection part of the rigid frame, and the synchronous displacement difference threshold δ is preset. Displacement monitoring: During the sliding process, displacement signals of three monitoring points are collected in real time, and the current relative displacement between any two monitoring points is calculated based on the collected signals. The current relative displacement is compared with the initial relative displacement at the start of the sliding to obtain the change in relative displacement. Torsional discrimination: The relative displacement change is compared with the synchronous displacement difference threshold δ. If any relative displacement change exceeds δ, it is determined that the frame has undergone torsional deformation around the vertical axis. The leading and lagging sides of the sliding on both sides of the frame are determined based on the displacement signals of each monitoring point. Differential speed correction: Output a deceleration command to the sliding leading side traction device (18) and simultaneously output an acceleration command to the sliding lagging side traction device (18) to generate a differential speed between the two traction devices (18) to correct the torsional posture of the rigid frame, and continuously monitor until the relative displacement change falls back to the range of δ.

2. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, The left beam-column connection is the junction of the left column (12) and the crossbeam (13) of the rigid frame. The right beam-column connection is the junction of the right column (12) and the crossbeam (13) of the rigid frame. The mid-span of the crossbeam (13) is the midpoint of the crossbeam (13).

3. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, Each monitoring unit also collects the vertical displacement of the corresponding monitoring point; in the torsion discrimination step, the horizontal displacement and vertical displacement are used together to calculate the relative displacement change.

4. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, Before the formal sliding test, a trial sliding test was conducted in the starting work area: first, an unloaded trial sliding test and a loaded trial sliding test were conducted and the initial relative displacement of three points was recorded. Then, the traction speed was increased in stages, and the relative displacement change between the three monitoring points was collected at each traction speed level. The matching between the synchronous displacement difference threshold δ and the traction speed was checked. After confirming that there was no rail jamming or abnormal swaying at each speed level, the formal sliding test was started.

5. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, The rigid frame consists of multiple rigid frames, and adjacent rigid frames are connected to form a sliding unit (5) by temporary connecting rods (16) and temporary scissor braces (17). The traction device (18) is connected to the front end of the sliding unit (5), and the traction force is transmitted backward frame by frame through the temporary connecting rods (16), driving the multiple rigid frames to slide synchronously longitudinally along the track. The measuring point arrangement step, displacement monitoring step, torsion discrimination step and differential speed correction step are continuously executed during the cumulative sliding process of the sliding unit (5).

6. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 5, characterized in that, The temporary scissor brace (17) consists of two intersecting diagonal braces.

7. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, During the sliding process, there is a gap between the anti-sway limiter (15) set on the rigid frame sliding support unit and the side of the track. When the lateral sway of the rigid frame reaches the gap value, the anti-sway limiter (15) contacts the side of the track to form a mechanical limit.

8. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 7, characterized in that, There is a gap between the anti-sway limiter (15) and the side of the track, and the lateral sway tolerance provided by the gap is greater than the lateral sway amount corresponding to the synchronous displacement difference threshold δ.

9. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, In the differential correction step, the deceleration range of the leading traction device (18) and the acceleration range of the lagging traction device (18) are determined by the excess amount of the relative displacement change exceeding δ; when the relative displacement change returns to the range of δ, the two traction devices (18) return to the same set traction speed.

10. The method for sliding and positioning a photovoltaic portal frame above an existing building according to claim 1, characterized in that, In the torsion discrimination step, the deformation type of the rigid frame is determined according to the distribution pattern of the relative displacement change between the three monitoring points: when the relative displacement change between the left beam-column connection and the right beam-column connection does not exceed δ, but the relative displacement change between the mid-span of the crossbeam (13) and the beam-column connection on any side exceeds δ, it is determined to be torsional deformation around the vertical axis; when the relative displacement change between the three monitoring points along the sliding direction (K) is in the same direction and has the same amplitude, it is determined to be overall translational deviation.