A BIM-based full-process simulation method and system for construction progress based on virtual entities
By constructing virtual entities in the BIM model, binding the planning information of non-physical construction events, and establishing a linkage triggering mechanism, the blind spots in the coverage of non-physical events in BIM progress simulation are solved, achieving progress simulation coverage of all elements and processes of the project, and improving the real-time performance and accuracy of progress simulation.
Patent Information
- Application Number
- CN202611261665.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-19
- Publication Date
- 2026-11-17
AI Technical Summary
Existing BIM schedule simulation technology cannot incorporate non-physical construction events into the schedule simulation system, resulting in a disconnect between the schedule plan and actual construction.
Construct a BIM model of the main project, bind the planning information of non-physical construction events by building virtual entities in the model, and establish a linkage triggering mechanism between virtual entities and physical construction process objects to realize the synchronous update of progress data of non-physical construction events.
It fills the gaps in BIM progress simulation regarding non-physical construction events, improves the real-time performance and accuracy of progress simulation, ensures that progress management is consistent with actual engineering constraints, and reduces the problems of omissions and misjudgments caused by manual recording and communication.
Smart Images

Figure CN123116574A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building information modeling technology, and in particular to a method and system for simulating the entire construction progress process of BIM based on virtual entities. Background Technology
[0002] BIM technology, with its advantages of 3D visualization and dynamic simulation, has been widely applied in construction schedule management for various projects such as architecture, water conservancy, and dredging. Through 4D (3D, time) and 5D (3D, time, and cost) simulations, it can intuitively present the construction progress, process connections, and resource allocation of physical construction components, providing important support for project schedule control. However, in actual engineering applications, construction schedule plans not only include physical construction processes (such as dredging, pouring, and installation), but also cover a large number of non-physical construction events. Although these events do not have specific geometric entities, they directly affect the progress of construction and are an important part of the schedule plan. These mainly include construction permit processing, site preparation, design-related events, and collaborative events.
[0003] Existing BIM schedule simulation technology can only model and simulate construction procedures with clear geometric entities, and cannot incorporate the aforementioned non-physical construction events into the schedule simulation system. This results in significant blind spots in BIM schedule simulation and a disconnect between the schedule plan and actual construction. Summary of the Invention
[0004] Therefore, it is necessary for the present invention to provide a method and system for simulating the entire process of BIM construction progress based on virtual entities, in order to solve at least one of the above-mentioned technical problems.
[0005] To achieve the above objectives, a BIM-based full-process simulation method for construction progress based on virtual entities includes the following steps: Step S1: Construct the main body BIM model of the project. The main body BIM model of the project contains multiple physical construction process objects. Each physical construction process object has start time parameters and progress status parameters. Step S2: Construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of the non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction events and the identifier of the physical construction process objects that they constrain. Step S3: Based on the plan information, establish a linkage triggering mechanism between virtual entities and physical construction process objects; Step S4: Obtain the progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; update the status of virtual entities based on the progress data, and through a linkage triggering mechanism, synchronously update the progress simulation results of the main body BIM model of the project based on the updated status of the virtual entities.
[0006] This invention also provides a virtual entity-based BIM construction progress full-process simulation system for executing the virtual entity-based BIM construction progress full-process simulation method described above. The virtual entity-based BIM construction progress full-process simulation system includes: The model building module is used to build the main BIM model of the project. The main BIM model of the project contains multiple entity construction process objects, and each entity construction process object has start time parameters and progress status parameters. The virtual mapping module is used to construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction event and the identifier of the physical construction process object that it is constrained by. The linkage configuration module is used to establish a linkage triggering mechanism between virtual entities and physical construction process objects based on the plan information; The simulation update module is used to acquire progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; it updates the status of virtual entities based on the progress data, and through a linkage triggering mechanism, it synchronously updates the progress simulation results of the main project BIM model based on the updated status of the virtual entities.
[0007] This invention constructs virtual entities as data carriers for non-physical construction events within the main BIM model of the project, incorporating these events (which lack physical geometry) into the BIM progress simulation system. This fills the gap in existing BIM progress simulation technologies regarding non-physical construction events such as construction permit approvals, land acquisition and demolition, and pipeline relocation, achieving full-element and full-process progress simulation coverage. By establishing a linkage triggering mechanism between virtual entities and physical construction process objects, the corresponding physical construction process is automatically triggered upon completion of a non-physical construction event, and the start time parameter of the corresponding physical construction process is automatically postponed when a non-physical construction event is delayed. This allows changes in the progress of non-physical construction events to be transmitted to the main BIM model in real time, avoiding the omissions and misjudgments caused by reliance on manual records and offline communication in existing technologies, thus improving the real-time performance and accuracy of progress simulation.
[0008] This invention addresses the issue of multiple non-physical construction events simultaneously constraining the same physical construction process object. The forward triggering condition employs conjunctive logic, triggering the process only when all constraining events are completed. The reverse triggering condition uses the maximum value of each delay duration as the sequential delay duration for the process start time parameter. This solves the problem of existing technologies lacking solutions for many-to-one constraint scenarios, ensuring that the progress simulation results match the actual engineering constraints. After the linkage triggering mechanism is activated, the delay impact propagates hierarchically along the construction sequence, starting from the affected physical construction process object. The critical path is dynamically updated, and progress deviations are marked, enabling progress managers to promptly grasp the transmission effect of non-physical construction event delays on the overall project duration, providing accurate basis for progress control decisions. A local update strategy is adopted, updating only the affected local process objects and their corresponding process paths after each progress data update. This avoids the performance overhead of global recalculation and improves the update efficiency of large-scale project progress simulation. Attached Figure Description
[0009] Other features, objects, and advantages of the invention will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings: Figure 1 This is a flowchart illustrating the steps of a BIM-based full-process simulation method for construction progress based on virtual entities. Figure 2 This is a schematic diagram illustrating the full-process simulation of the BIM construction progress of a dredging project, as shown in one embodiment. Figure 3 This is a schematic diagram simulating the progress of a building demolition delay of 5 days before and after one embodiment. Figure 4 This is a schematic diagram illustrating the mapping relationship and attributes between virtual entities and physical construction process objects in one embodiment. Figure 5 This is a schematic diagram of a BIM-based full-process simulation system for construction progress based on virtual entities. Detailed Implementation
[0010] The technical method of the present invention will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.
[0011] Furthermore, the accompanying drawings are merely illustrative of the invention and are not necessarily drawn to scale. The same reference numerals in the drawings denote the same or similar parts, and therefore repeated descriptions of them will be omitted. Some block diagrams shown in the drawings are functional entities and do not necessarily correspond to physically or logically independent entities. These functional entities can be implemented in software, in one or more hardware modules or integrated circuits, or in different network and / or processor methods and / or microcontroller methods.
[0012] It should be understood that although the terms "first," "second," etc., may be used herein to describe various units, these units should not be limited by these terms. These terms are used merely to distinguish one unit from another. For example, without departing from the scope of the exemplary embodiments, a first unit may be referred to as a second unit, and similarly, a second unit may be referred to as a first unit. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0013] To achieve the above objectives, please refer to Figures 1 to 5 This invention provides a method for simulating the entire construction progress process based on virtual entities using BIM, the method comprising the following steps: Step S1: Construct the main body BIM model of the project. The main body BIM model of the project contains multiple physical construction process objects. Each physical construction process object has start time parameters and progress status parameters. Step S2: Construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of the non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction events and the identifier of the physical construction process objects that they constrain. Step S3: Based on the plan information, establish a linkage triggering mechanism between virtual entities and physical construction process objects; Step S4: Obtain the progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; update the status of virtual entities based on the progress data, and through a linkage triggering mechanism, synchronously update the progress simulation results of the main body BIM model of the project based on the updated status of the virtual entities.
[0014] Furthermore, step S1 includes the following steps: Step S11: Obtain the design data of the project and construct the main body BIM model of the project based on the design data. The main body BIM model of the project contains multiple physical construction process objects, and each physical construction process object corresponds to a physical construction process in the project. In one embodiment, the design data includes engineering drawings, geological survey reports, and bill of quantities. Based on the above data, three-dimensional geometric models are created for the engineering components corresponding to each physical construction process in the project. Each engineering component corresponds to a physical construction process in the project, forming a physical construction process object.
[0015] In actual engineering projects, BIM models are often created separately by multiple disciplines such as architecture, structure, and mechanical and electrical engineering. The coordinate references and component naming rules of each discipline's models may differ. When integrating multi-disciplinary models, the coordinate references should be unified, and duplicate components caused by inter-discipline overlap should be removed to ensure that each physical construction process has one and only one corresponding physical construction process object in the main BIM model of the project, thus avoiding ambiguity in the correspondence between subsequent progress data and process objects.
[0016] Step S12: Configure construction attributes for each entity construction process object. The construction attributes include the identifier of the entity construction process object and the construction content. In one embodiment, the configuration of construction attributes forms the basis for establishing the linkage between virtual entities and physical construction process objects. The identifier of a physical construction process object must be unique within the scope of the main project BIM model and must not be duplicated with the identifier of other physical construction process objects. This identifier will be recorded in the planning information of the corresponding virtual entity to establish the mapping relationship between the virtual entity and the physical construction process object. The construction content records the specific construction task description of the process for progress management personnel to review and verify.
[0017] It should be noted that the process division in the construction organization plan in actual engineering projects may not be completely consistent with the component division in the BIM model. Some processes may span multiple components. In this case, multiple components need to be merged and mapped to the same entity construction process object. Some components may also cover multiple processes. In this case, the component needs to be split and mapped to multiple entity construction process objects to ensure that the correspondence between the identifier and the process is accurate.
[0018] Step S13: Based on the pre-acquired construction organization plan, determine the construction sequence relationship between each entity construction process object, and associate the construction sequence relationship with the corresponding entity construction process object; In one embodiment, the construction sequence between various construction processes is determined based on the process logic constraints in the construction organization plan. In actual engineering, some processes have a mandatory sequential relationship, meaning that if a preceding process is not completed, the subsequent process cannot be started objectively; other processes can proceed in parallel without mandatory sequential constraints.
[0019] Step S14: Configure start time parameters and progress status parameters for each entity construction process object, wherein the start time parameter is assigned a value according to the construction organization plan, and the progress status parameter is initialized to not started.
[0020] In one embodiment, the start time parameter is assigned a value based on the planned start time of the corresponding process in the construction organization plan, while the progress status parameter is uniformly initialized to "not started" during the modeling phase to reflect the initial situation where all processes are in a "waiting to start" state before the project commences. The start time parameter and progress status parameter will be dynamically updated based on actual progress data; therefore, the assigned values only represent the planned baseline state and do not represent the actual execution status.
[0021] Taking dredging projects as an example, the dredging process corresponds to underwater earthwork excavation components, the foundation construction process corresponds to pile foundation components, and the road construction process corresponds to pavement components. Each component forms a corresponding physical construction process object and is assigned a unique identifier. According to the construction organization plan, foundation construction can only proceed after the dredging process is completed, and road construction can only proceed after the foundation construction is completed. This sequential relationship is associated with each physical construction process object. The start time parameter of each physical construction process object is assigned a value based on the planned start date of the corresponding process in the construction organization plan, and the progress status parameters are all initialized to "not started".
[0022] Furthermore, step S2 includes the following steps: Step S21: Obtain non-physical construction events of the project. Non-physical construction events are events in the project that do not form physical construction procedures but restrict the progress of physical construction procedures. In one embodiment, the sources for identifying non-physical construction events include the application plan, key milestones stipulated in the contract, preconditions explicitly listed in the construction organization design, and customary constraints known from engineering experience. Identifying non-physical construction events is the starting point for the entire schedule simulation process; failure to identify them will result in the missing corresponding constraints in the model, thus creating blind spots in the schedule simulation.
[0023] In actual engineering projects, some non-physical construction events are clearly recorded in the contract documents, such as the approval of construction permits and the handling of navigation safety assessment approvals; other events are engineering practices and may not be explicitly stipulated in the contract, such as site clearing before equipment arrives and construction can only begin after the drawings are handed over. These events must also be included in the identification scope, otherwise the progress simulation will show systematic deviations.
[0024] Step S22: Based on the type of the mapped non-physical construction event, classify the non-physical construction events into three categories: procedure handling, site preparation, and design collaboration. In one embodiment, non-physical construction events are categorized into three types based on their nature. The first type involves administrative approvals, including navigation safety assessment approvals, construction permit approvals, and environmental approvals. These events are primarily administrative approvals, and their completion depends on the approval progress of the relevant authorities, exhibiting significant external uncertainty. The second type involves site preparation, including land acquisition and demolition, work area handover, pipeline relocation, and obstacle removal. These events are primarily on-site operations, and their progress is affected by site conditions and resource input. The third type involves design coordination, including design document changes, drawing handover, testing and acceptance, and equipment arrival. These events primarily involve coordination among all participating parties, and their completion is affected by the progress of multi-party coordination.
[0025] It should be noted that the purpose of the above three classifications is to enable virtual entities to form an orderly hierarchical structure in the main BIM model of the project, so that progress managers can quickly locate and view the progress status of non-physical construction events according to their type.
[0026] Step S23: In the main BIM model of the project, construct virtual entities that correspond one-to-one with each non-physical construction event, and configure the virtual entities to the corresponding levels according to the type of non-physical construction event, where the first level corresponds to the procedure handling category, the second level corresponds to the site preparation category, and the third level corresponds to the design collaboration category.
[0027] In one embodiment, the construction of virtual entities corresponds one-to-one with non-physical construction events, with each non-physical construction event corresponding to a unique virtual entity, and different non-physical construction events do not share virtual entities. Virtual entities are configured into corresponding levels according to the type of non-physical construction event: the first level corresponds to procedures, the second level corresponds to site preparation, and the third level corresponds to design collaboration. The virtual entities of different levels form a clear hierarchical structure in the main BIM model of the project.
[0028] It should be noted that different types of non-physical construction events in the same project often intertwine and proceed in parallel. Hierarchical division allows progress managers to filter and view the progress status of various non-physical construction events by level in the 4D progress simulation, avoiding management chaos caused by the mixing of different types of events.
[0029] Furthermore, step S2 also includes the following steps: Step S24: Determine the physical construction process object constrained by each non-physical construction event, and associate the identifier of the physical construction process object with the corresponding virtual entity; In one embodiment, determining the physical construction procedures constrained by each non-physical construction event requires a step-by-step verification based on the construction organization plan and the actual constraints of the project. In actual engineering projects, constraints often present complex one-to-many or many-to-one relationships. A non-physical construction event may simultaneously constrain multiple physical construction procedures. For example, if the navigation safety assessment approval is not obtained, the dredging and temporary wharf construction procedures within the assessed water area cannot be initiated. Conversely, a physical construction procedure may also be constrained by multiple non-physical construction events simultaneously. For example, the dredging procedure may be constrained by both the navigation safety assessment approval process and the building demolition event; the dredging procedure cannot be initiated if neither event is completed.
[0030] The aforementioned constraints must be confirmed one by one in step S24, and the identifiers of the constrained entity construction process objects must be associated with the corresponding virtual entities. No omissions are allowed; otherwise, the establishment of the linkage triggering mechanism in step S3 will result in incomplete coverage.
[0031] Step S25: Configure the progress status for each virtual entity. The progress status is initialized to not started. The progress status includes not started, in progress, completed, and delayed. In one embodiment, the progress status of each virtual entity is uniformly configured as "Not Started" in the initial stage to reflect the initial situation where all non-physical construction events are in a pending state before the project commences. The progress status is dynamically updated based on actual progress data, with the update path being "Not Started" → "In Progress" → "Completed." When the actual completion time of a non-physical construction event exceeds the planned completion time, the progress status is updated to "Delayed." It should be noted that the identification of the delayed status is a prerequisite for triggering the reverse linkage relationship. All four values of the progress status must be configured completely and cannot be missing; otherwise, it is impossible to accurately determine whether the triggering conditions are met.
[0032] Step S26: Bind the planning information of the corresponding non-physical construction event to each virtual entity. The planning information includes the event name of the non-physical construction event, the planned completion time, and the identifier of the associated physical construction process object.
[0033] In one embodiment, the binding of planning information is the data foundation for the operation of the linkage triggering mechanism. The event name is used to identify and display the corresponding non-physical construction event in the progress simulation interface, facilitating intuitive identification by progress management personnel. The planned completion time serves as the time benchmark for judging delays in the reverse linkage; if the planned completion time is entered incorrectly, the calculated delay duration will be biased. The associated physical construction process object's identifier corresponds to the identifier, establishing a linkage triggering mechanism between the virtual entity and the physical construction process object.
[0034] For example, the processing of navigation safety assessment approval is a non-physical construction event of the procedure type, corresponding to the first-level virtual entity. The progress status is initialized to not started. The event name recorded in the plan information is "processing of navigation safety assessment approval", the planned completion time is the corresponding planned node date, and the associated physical construction process object is the identifier of the dredging process object.
[0035] Building demolition is a non-physical construction event in the site preparation category, corresponding to a second-level virtual entity. Its progress status is initialized to "not started". The event name recorded in the plan information is "building demolition", the planned completion time is the corresponding planned node date, and the associated physical construction process object identifier is also the identifier of the dredging process object.
[0036] Furthermore, step S3 includes the following steps: Step S31: Assign a unique identifier to each non-physical construction event, and establish a one-to-one mapping relationship between non-physical construction events and virtual entities based on the unique identifier; In one embodiment, the unique identifier assigned to each non-physical construction event and the identifier assigned to physical construction process objects together constitute the identifier system for all objects in the main BIM model of the project. Both types of identifiers must use distinguishable coding rules to avoid confusion between the identifiers of non-physical construction events and the identifiers of physical construction process objects; otherwise, matching errors will occur when determining dependencies.
[0037] For example, non-physical construction events can be identified by hierarchical prefixes: procedures are prefixed with "L1", site preparation with "L2", and design coordination with "L3". Physical construction process objects are prefixed with "S". The two types of identifiers are naturally distinguishable in terms of format.
[0038] Step S32: Determine the dependency relationship between each virtual entity and the physical construction process object based on the identifier of the physical construction process object associated in the plan information bound to the virtual entity; In one embodiment, the dependency relationship is determined by using the entity construction process object identifier associated with the bound plan information as an index, and retrieving the corresponding entity construction process object one by one in the main project BIM model to establish the dependency relationship between the virtual entity and the entity construction process object.
[0039] It should be noted that in actual engineering projects, dependencies often take the form of many-to-one relationships, meaning that multiple virtual entities simultaneously depend on the same entity's construction process object. In this case, the configuration of dependencies must ensure that the same entity's construction process object can be associated with multiple virtual entities simultaneously, and that multiple associations do not lead to dependency overwriting or loss.
[0040] Step S33: Configure positive triggering conditions for virtual entities and entity construction process objects that have a dependency relationship. The positive triggering condition is that when the progress status of the virtual entity is updated to "completed", the entity construction process object with a dependency relationship is triggered to start, and the progress status parameter of the corresponding entity construction process object is updated to "in progress".
[0041] In one embodiment, the configuration of positive triggering conditions must consider the scenario where multiple virtual entities simultaneously constrain the same entity's construction process object. If the process is triggered simply because the progress status of one of the virtual entities is updated to "completed," the process will be erroneously triggered before the other constraining events are completed, causing the progress simulation results to deviate from the actual engineering constraints. Therefore, the determination of positive triggering conditions should be based on the premise that the progress status of all virtual entities constraining the same entity's construction process object is updated to "completed" before the process can be triggered.
[0042] Furthermore, step S3 also includes the following steps: Step S34: Configure reverse triggering conditions for virtual entities and physical construction process objects that have a dependency relationship. The reverse triggering condition is to calculate the delay duration when the actual completion time of the non-physical construction event corresponding to the virtual entity exceeds the planned completion time, and delay the start time parameter of the physical construction process object that has a dependency relationship by the delay duration. In one embodiment, when multiple virtual entities simultaneously constrain the same construction process object and all experience delays, the delay durations for each virtual entity may differ. If the smaller delay duration is used to postpone the process start time, the process will still be scheduled to start before the constraint event with the larger delay duration is completed, leading to simulation distortion. Therefore, the maximum value among the delay durations should be used as the postponement duration for the construction process object's start time parameter to ensure that the progress simulation results match the actual engineering constraints.
[0043] For example, if the navigation safety assessment approval is delayed by 3 days and the building demolition is delayed by 5 days, both of which restrict the dredging process, then the start time parameter for the dredging process should be postponed by 5 days.
[0044] Step S35: Determine the critical path of the main body BIM model of the project based on the start time parameters of the physical construction process objects and the construction sequence relationship between the physical construction process objects; In one embodiment, the critical path is determined based on the start time parameters and duration of each construction operation, combined with the construction sequence. All possible operation paths from the first to the last construction operation are traversed, and the path duration of each path is calculated. The operation path with the longest path duration is identified as the critical path. Delays in operations on the critical path will directly affect the overall project duration; delays in operations on non-critical paths within their float time range will not necessarily affect the overall project duration. The critical path serves as the benchmark for critical path updates.
[0045] Step S36: A linkage triggering mechanism is formed between the virtual entity and the physical construction process object by positive triggering conditions and negative triggering conditions. The linkage triggering mechanism is used to update the critical path according to the delayed start time parameter when the start time parameter of the physical construction process object is delayed, and to mark the progress deviation of the physical construction process object according to the updated critical path.
[0046] In one embodiment, after the linkage triggering mechanism is established, when the start time parameter of a construction process object is delayed due to a reverse triggering condition, the affected process objects must be determined step by step along the construction sequence, starting from that process object. Their start time parameters are updated synchronously, and the path duration of the process path containing the affected process objects is recalculated, thereby updating the critical path. The updated critical path is compared with the original critical path, and both newly added process objects entering and exiting the critical path are marked with schedule deviations.
[0047] It should be noted that the critical path update only recalculates the process path containing the affected process object, and does not involve the process path of the affected process object to maintain the original path duration, so as to avoid unnecessary overhead caused by global recalculation.
[0048] For example, if a 5-day delay in building demolition causes a 5-day delay in the start time parameter of the dredging process, the start time parameters of the foundation construction process and the road construction process are updated step by step along the construction sequence, starting with the dredging process. The path duration of the process paths containing the above processes is recalculated, the critical path is updated, and the schedule deviations of newly added process objects entering the critical path are marked. Based on this, the schedule management personnel identify schedule risks and take corresponding adjustment measures.
[0049] Of particular importance are steps S33 and S34, when multiple virtual entities in the main BIM model of the project constrain the same construction process object: The positive trigger condition is that the construction process object of the same entity is triggered to start only when the progress status of all virtual entities that constrain the same entity construction process object is updated to "completed", and the progress status parameter of the construction process object of the entity construction process object is updated to "in progress". When any virtual entity constraining the same construction process object has a progress status that has not been updated to completed, the start of the construction process object will not be triggered. The reverse trigger condition is that when the non-physical construction events corresponding to multiple virtual entities that constrain the same physical construction process object are all delayed, the delay duration of each non-physical construction event is calculated, the maximum value of each delay duration is determined as the extension duration of the start time parameter of the physical construction process object, and the start time parameter of the physical construction process object is delayed by the extension duration.
[0050] In one embodiment, failure to complete any constraint event means that the process cannot start in actual engineering. If the process is triggered by updating the progress status of one of the virtual entities to complete, the process will be incorrectly marked as in progress before the other constraints are lifted, thus distorting the progress simulation results.
[0051] For example, the dredging process is simultaneously constrained by two virtual entities: the processing of the navigation safety assessment approval and the demolition of structures. When the navigation safety assessment approval has been approved (the progress status of the corresponding virtual entity is updated to "completed"), but the demolition of structures has not yet been completed, the dredging process should not be triggered to start. The dredging process should only be triggered to start and its progress status parameter should be updated to "in progress" when the progress status of both virtual entities is updated to "completed".
[0052] In one embodiment, when multiple constraint events are delayed simultaneously, the actual start time of the process depends on the constraint event that is completed last. If the smaller delay time is used to postpone the process start time, the process will still be scheduled to start before the constraint event with the larger delay time is completed, resulting in simulation distortion.
[0053] For example, if the navigation safety assessment approval is delayed by 3 days and the building demolition is delayed by 5 days, both of which restrict the dredging process, then the maximum value of 5 days will be taken as the extension period for the dredging process start time parameter. The start time parameter of the dredging process will be delayed by 5 days to ensure that the progress simulation results are consistent with the actual engineering constraints.
[0054] Of particular importance is that step S32 determines the dependencies between each virtual entity and the physical construction process object, including: Obtain the affected area of each non-physical construction event, where the affected area is the scope of the project affected by the non-physical construction event; The affected area is mapped to the main BIM model of the project to obtain the spatial range of the affected area in the main BIM model of the project. Identify the physical construction process objects located within the spatial range of the main project BIM model; The physical construction process objects located within the spatial range are identified as physical construction process objects that have a dependency relationship with the virtual entity corresponding to the non-physical construction event, and the identifiers of the physical construction process objects located within the spatial range are associated with the virtual entity.
[0055] In one embodiment, the impact area of each non-physical construction event is obtained, where the impact area is the actual scope of the project affected by the non-physical construction event; the impact area is mapped to the main BIM model of the project to obtain the spatial range corresponding to the impact area in the model; then, the physical construction process objects located within the spatial range in the main BIM model of the project are determined, and the above-mentioned physical construction process objects are identified as physical construction process objects that have a dependency relationship with the virtual entity corresponding to the non-physical construction event, and their identifiers are associated with the virtual entity.
[0056] For example, the area affected by the navigation safety assessment approval is the navigable waterway. After mapping this area to the main project BIM model, dredging operations within the navigable waterway are identified as physical construction operations subject to its constraints, and their identifiers are associated with the virtual entity corresponding to the navigation safety assessment approval. The area affected by building demolition is the site occupied by the building to be demolished. Dredging operations and foundation construction operations within this area are identified as physical construction operations subject to its constraints, and their identifiers are associated with the virtual entity corresponding to the building demolition.
[0057] Furthermore, step S35 determines the critical path of the main BIM model of the project, including: Based on the construction sequence relationship between the physical construction process objects, generate multiple process paths from the first physical construction process object to the last physical construction process object; In one embodiment, the generation of process paths is based on the established construction sequence relationship between each entity construction process object as the topological basis. Starting from an entity construction process object that does not have a preceding process, the path extends step by step along the construction sequence relationship until it reaches the final entity construction process object that does not have a subsequent process. All possible extension paths are traversed to form multiple process paths.
[0058] When there are parallel branches in the construction sequence, the same preceding process may lead to multiple extension paths. Each path must be generated completely separately and cannot be merged. Otherwise, some process paths will be missed, resulting in incorrect calculation results for subsequent critical paths.
[0059] For example, after the dredging process is completed, the foundation construction process and the temporary wharf construction process can proceed in parallel, extending to the road construction process and the wharf ancillary works process respectively, thereby generating two independent process paths, which are respectively involved in the calculation of the subsequent path construction period.
[0060] Based on the start time parameters and duration of each physical construction process, the completion time of the last physical construction process corresponding to each process path is determined, and the time span between the start time of the first physical construction process and the completion time of the last physical construction process is determined as the path duration of the corresponding process path. In one embodiment, the path duration of each process path is calculated from the start time of the first process in the path to the completion time of the last process. The completion time of the last process is calculated by progressively adding the start time parameters of each physical construction process object on the path with the process duration—the completion time of the preceding process is the earliest possible start time of the subsequent process. The difference between the two times calculated progressively along the path to the last process is the path duration.
[0061] The duration of each process must be fully configured during the modeling phase. If the duration of any process is missing, the path duration of that path cannot be accurately calculated, which will affect the determination of the critical path.
[0062] For example, if the dredging process starts on day 1 and lasts for 10 days, followed by the foundation construction process for 15 days, and the road construction process for 8 days, then the final process of this route will be completed on day 33, and the total construction period of the route will be 33 days.
[0063] The process path with the longest construction period is identified as the critical path before the update, and the critical path before the update is used as the critical path for the current maintenance of the main body BIM model of the project.
[0064] In one embodiment, the process path with the longest path duration is identified as the critical path and saved as the currently maintained critical path in the main project BIM model for comparison during subsequent critical path updates. The critical path is not fixed once identified. When the start time parameter of a construction process object is delayed due to a linkage triggering mechanism, the path duration of each process path will change accordingly. The original critical path may be surpassed by other paths and no longer be the process path with the longest path duration. Therefore, the critical path identified here only represents the baseline critical path under the current progress status, and a critical path update process must be triggered to re-determine it each time the start time parameter changes.
[0065] For example, the current path with the longest duration is dredging → foundation construction → road construction, with a duration of 33 days. This path is identified as the critical path for current maintenance. If subsequent building demolition delays cause a 5-day delay in the start of the dredging process, the duration of this path will become 38 days, and a critical path update must be triggered to re-determine the path.
[0066] Furthermore, the critical path for updating the main BIM model of the project in step S36 includes: In response to an update in the state of a virtual entity, the entity construction process object affected by the virtual entity is determined as the starting object for the update based on the dependency relationship between the virtual entity and the entity construction process object. In one embodiment, when the progress status of a virtual entity is updated, the entity construction process object that has a dependency relationship with the virtual entity is first located by using the entity construction process object identifier associated with the plan information bound to the virtual entity, and the entity construction process object is determined as the starting object of this critical path update.
[0067] For example, when the status of the virtual entity corresponding to the building demolition is updated to delayed, the dredging process object is located based on its bound identifier, and the dredging process object is determined as the update starting object.
[0068] Starting with the initial object, the subsequent entity construction process objects affected are determined level by level along the construction sequence relationship between entity construction process objects, forming a set of affected processes; and the start time parameters of each entity construction process object in the set of affected processes are updated simultaneously. In one embodiment, starting with the update start object, the process iterates sequentially along the established construction sequence, adding each subsequent entity construction process object to the affected process set until no subsequent process objects remain. During the traversal, the start time parameters of the subsequent process objects are recalculated based on the process duration of each process object, ensuring that the start time parameters of each process object in the affected process set remain consistent with the start time of the update start object.
[0069] For example, if the start time of the dredging process is delayed by 5 days, the foundation construction process and the temporary wharf construction process are included in the affected process set as their direct successor processes, and the road construction process and the wharf ancillary works process are also included in the set as indirect successor processes. The start time parameters of each process are simultaneously delayed by 5 days.
[0070] Recalculate the path duration for process paths that include the affected process set, while keeping the path duration unchanged for process paths that do not include the affected process set; In one embodiment, the recalculation of path duration is performed only on path processes that contain at least one process object from the affected process set. Path processes that do not contain any process objects from the affected process set directly retain their original path duration without recalculation. This partial recalculation strategy ensures that after each virtual entity state update, only the affected process processes are recalculated, rather than a full recalculation of all process processes in the main BIM model of the project. This can significantly reduce the amount of computation in projects with a large number of processes and complex paths.
[0071] For example, if the dredging process is delayed by 5 days, the timelines for the two process paths that include the dredging process (dredging → foundation construction → road construction, dredging → temporary wharf construction → wharf ancillary works) will be recalculated, while the timelines for the remaining process paths that do not include the dredging process will remain unchanged.
[0072] The critical path is updated based on the recalculated path duration, where the path duration is the time span from the start of the initial process to the completion of the final process. In one embodiment, after recalculating the path duration of each affected process path, the path durations of all process paths (including those recalculated and those not recalculated) are compared uniformly, and the process path with the longest path duration is determined as the updated critical path. The definition of path duration here is consistent with that used when determining the critical path; both are the time span between the start time of the initial process and the completion time of the final process. Both must use the same calculation method; otherwise, the comparison between the updated critical path and the original critical path will be meaningless.
[0073] For example, the path duration of the dredging → foundation construction → road construction route changes from 33 days to 38 days, exceeding the path duration of other routes. This route is still the updated critical path.
[0074] The updated critical path is compared with the original critical path to identify newly added critical process objects and process objects that have exited the critical path, and the schedule deviations of the corresponding entity construction process objects are updated.
[0075] In one embodiment, the updated critical path is compared step-by-step with the critical path maintained before the update to identify two types of changes: first, process objects that were not originally on the critical path but have been added to the critical path after the update; and second, process objects that were originally on the critical path but have been removed from the critical path after the update. The schedule deviation labels for these two types of process objects are then updated to reflect the impact of the critical path changes on the schedule control priority of each process.
[0076] For example, a delay in building demolition caused the dredging process and all subsequent processes to be postponed by 5 days. The critical path after the update is the same as before the update, but the progress deviations of the dredging process and the foundation construction process are marked as 5 days, so that the progress management personnel can identify and take corresponding adjustment measures.
[0077] Furthermore, step S4 includes the following steps: Step S41: Obtain the progress data of each non-physical construction event, determine the progress status and actual completion time of the virtual entity based on the progress data, and update the status information of the virtual entity. In one embodiment, the method for obtaining progress data varies depending on the type of non-physical construction event. For procedural processing events, the approval status can be automatically obtained by connecting to the government approval system; the progress of site preparation events typically relies on manual entry by on-site personnel; and for design collaboration events, the progress can be obtained through a drawing management system or inspection and acceptance records. After obtaining the progress data, the progress status and actual completion time are written into the status information of the corresponding virtual entity, completing the status update of the virtual entity.
[0078] It should be noted that the progress data of multiple virtual entities may be updated at the same time. The status update must be performed separately for each virtual entity without omission. Otherwise, the subsequent judgment of the triggering conditions will be based on incomplete status information, resulting in incorrect linkage results.
[0079] For example, if the actual completion time of building demolition exceeds the planned completion time by 5 days, the progress status of the corresponding virtual entity will be updated to "delayed" and the actual completion time will be updated to the corresponding date.
[0080] Step S42: Determine whether the updated virtual entity meets the triggering conditions of the corresponding linkage triggering mechanism. When the positive triggering conditions are met, generate the start command for the corresponding entity construction process object; when the negative triggering conditions are met, generate the start time adjustment command for the corresponding entity construction process object. In one embodiment, after the virtual entity's state is updated, its triggering conditions are judged one by one according to the linkage triggering mechanism. The judgment of the positive triggering condition requires checking the current progress status of all virtual entities that restrict the construction process of the same entity. Only when all are updated to "completed" will a start command be generated. The judgment of the negative triggering condition requires calculating the difference between the actual completion time and the planned completion time of the non-entity construction event corresponding to the current virtual entity. When the actual completion time exceeds the planned completion time, a start time adjustment command is generated, and the delay duration is written into the command.
[0081] For example, the progress status of the virtual entity corresponding to the general aviation safety assessment approval is updated to "completed," but the actual completion time is 3 days later than the planned completion time. This triggers a positive trigger condition to generate a start command, and simultaneously triggers a negative trigger condition to generate a start time adjustment command, with a delay duration of 3 days.
[0082] Step S43: In response to the start command or start time adjustment command, perform state propagation based on the dependency relationship between the virtual entity and the physical construction process object and the construction sequence relationship between the physical construction process objects, determine the local update object, and use the local update object as the local update scope of the main body BIM model of the project. In one embodiment, in response to a start command or a start time adjustment command, the directly affected physical construction process object is first located through the dependency relationship between the virtual entity and the physical construction process object. Then, the process is traversed step by step along the construction sequence to include all subsequent physical construction process objects affected by the transmission into a local update object set, which is used as the local scope of this model update.
[0083] For example, after a building demolition delay triggers a start time adjustment instruction, the dependency is located to the dredging process object, and then the foundation construction process and road construction process are determined as the subsequent affected processes according to the construction sequence. The three together constitute a set of local update objects.
[0084] Step S44: Invoke the critical path update process to perform a local update on the main body BIM model of the project corresponding to the local update object, and simultaneously update the progress simulation results of the main body BIM model of the project.
[0085] In one embodiment, the set of objects to be locally updated is used as input. The start time parameters of each construction process object in the set are updated, and the path duration of the process path containing the process objects in the set is recalculated. Based on this, the critical path and the progress deviation label of each process object are updated. Finally, the updated process status, start time parameters, critical path and progress deviation are synchronized to the progress simulation results of the main project BIM model to complete this local update.
[0086] For example, the start time parameters for dredging, foundation construction, and road construction are all postponed by 5 days. The path duration of the process paths containing the above processes is recalculated, the critical path is updated, the schedule deviation of the three process objects is updated to a delay of 5 days, the schedule simulation results are updated synchronously, and the other process objects are not affected.
[0087] See Figure 2 This is a schematic diagram of the full-process simulation of the BIM construction progress of a dredging project, showing the full-process progress simulation of the virtual entity area and the physical construction process area under normal progress scenarios. Figure 2In the upper virtual entity area, there are three virtual entities: L3-001 corresponds to the drawing handover, covering days 1 to 15, with a progress status of "completed"; L2-001 corresponds to the building demolition, covering days 1 to 18, with a progress status of "completed"; and L1-001 corresponds to the navigation safety assessment approval process, covering days 1 to 20, with a progress status of "completed". L2-001 and L1-001 trigger the S-001 dredging process in the lower entity construction process area via a dotted arrow (conjunction logic). The lower entity construction process area contains three entity construction process objects: S-001 dredging process starts on day 21, lasts for 10 days, with a progress status of "in progress"; S-002 foundation construction process starts on day 31, lasts for 15 days, with a progress status of "not started"; and S-003 road construction process starts on day 46, lasts for 8 days, with a progress status of "not started". The solid arrows between S-001, S-002, and S-003 indicate the order of construction. The three constitute the critical path, and the total construction period is 33 days.
[0088] Figure 3 This diagram illustrates the progress simulation before and after a 5-day delay in building demolition, using two vertical timelines on the left and right to show the changes in the progress simulation results before and after the delay. Figure 3 The left column shows the status before the delay: the completion time of the L2-001 building demolition plan is day 18, the positive trigger S-001 dredging operation starts on day 21, the S-002 foundation construction operation starts on day 31, the S-003 road construction operation starts on day 46, and the total duration of the critical path is 33 days. Figure 3 The right column shows the status after the delay: the actual completion time of L2-001 is postponed to day 23, a delay of 5 days. Through reverse linkage, the start time of S-001 is postponed to day 26, the start time of S-002 is postponed to day 36, and the start time of S-003 is postponed to day 51. The progress deviation of each process is +5 days. After the update, the total duration of the critical path becomes 38 days.
[0089] Figure 4 This diagram illustrates the mapping relationship and attributes between virtual entities and physical construction process objects, showcasing the attribute content and dependencies between three virtual entities and two physical construction process objects in a specific engineering scenario. Figure 4On the left are three virtual entities: L1-001 corresponds to the processing of the navigation safety assessment approval, belonging to the first level, with a planned completion time and actual completion time of 20 days, a progress status of "completed", a dependent process identifier of S-001, and a progress weight of 0.8; L2-001 corresponds to building demolition, belonging to the second level, with a planned completion time of 18 days and an actual completion time of 23 days, a progress status of "delayed", a dependent process identifier of S-001, an affected area of the construction area, and a progress weight of 0.9; L3-001 corresponds to the handover of drawings, belonging to the third level, with a planned completion time and actual completion time of 15 days, a progress status of "completed", and a dependent process identifier of S-002. Figure 4 On the right are two entity construction process objects: S-001 dredging process start time parameter is day 26, progress status parameter is not started; S-002 foundation construction process start time parameter is day 36, progress status parameter is not started. L1-001 and L2-001 point to S-001 through dependency arrows, and L3-001 points to S-002 through dependency arrows. S-001 and S-002 are connected by construction sequence arrows.
[0090] See Figure 5 The present invention also provides a virtual entity-based BIM construction progress full-process simulation system 100, used to execute the virtual entity-based BIM construction progress full-process simulation method described above. The virtual entity-based BIM construction progress full-process simulation system 100 includes: The model building module 101 is used to build the main body BIM model of the project. The main body BIM model of the project contains multiple entity construction process objects, and each entity construction process object has start time parameters and progress status parameters. The virtual mapping module 102 is used to construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction event and the identifier of the physical construction process object that it is constrained by. The linkage configuration module 103 is used to establish a linkage triggering mechanism between virtual entities and physical construction process objects based on the plan information; The simulation update module 104 is used to acquire progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; update the status of virtual entities based on the progress data, and synchronously update the progress simulation results of the main body BIM model of the project based on the updated status of the virtual entities through a linkage triggering mechanism.
[0091] Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of the equivalents of the application are intended to be included within the invention.
[0092] The above description is merely a specific embodiment of the present invention, enabling those skilled in the art to understand or implement the invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features of the invention herein.
Claims
1. A method for simulating a whole process of a virtual entity-based BIM construction progress, characterized in that, Includes the following steps: Step S1: Construct the main body BIM model of the project. The main body BIM model of the project contains multiple physical construction process objects. Each physical construction process object has start time parameters and progress status parameters. Step S2: Construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of the non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction events and the identifier of the physical construction process objects that they constrain. Step S3: Based on the plan information, establish a linkage triggering mechanism between virtual entities and physical construction process objects; Step S4: Obtain the progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; update the status of virtual entities based on the progress data, and through a linkage triggering mechanism, synchronously update the progress simulation results of the main body BIM model of the project based on the updated status of the virtual entities. 2.The virtual entity-based BIM construction progress whole-process simulation method according to claim 1, characterized in that, Step S1 includes the following steps: Step S11: Obtain the design data of the project and construct the main body BIM model of the project based on the design data. The main body BIM model of the project contains multiple physical construction process objects, and each physical construction process object corresponds to a physical construction process in the project. Step S12: Configure construction attributes for each entity construction process object. The construction attributes include the identifier of the entity construction process object and the construction content. Step S13: Based on the pre-acquired construction organization plan, determine the construction sequence relationship between each entity construction process object, and associate the construction sequence relationship with the corresponding entity construction process object; Step S14: Configure start time parameters and progress status parameters for each entity construction process object, wherein the start time parameter is assigned a value according to the construction organization plan, and the progress status parameter is initialized to not started. 3.The virtual entity-based BIM construction progress whole-process simulation method according to claim 2, characterized in that, Step S2 includes the following steps: Step S21: Obtain non-physical construction events of the project. Non-physical construction events are events in the project that do not form physical construction procedures but restrict the progress of physical construction procedures. Step S22: Based on the type of the mapped non-physical construction event, classify the non-physical construction events into three categories: procedure handling, site preparation, and design collaboration. Step S23: In the main BIM model of the project, construct virtual entities that correspond one-to-one with each non-physical construction event, and configure the virtual entities to the corresponding levels according to the type of non-physical construction event, where the first level corresponds to the procedure handling category, the second level corresponds to the site preparation category, and the third level corresponds to the design collaboration category.
4. The virtual entity-based BIM construction progress full-process simulation method according to claim 3, characterized in that, Step S2 also includes the following steps: Step S24: Determine the physical construction process object constrained by each non-physical construction event, and associate the identifier of the physical construction process object with the corresponding virtual entity; Step S25: Configure the progress status for each virtual entity. The progress status is initialized to not started. The progress status includes not started, in progress, completed, and delayed. Step S26: Bind the planning information of the corresponding non-physical construction event to each virtual entity. The planning information includes the event name of the non-physical construction event, the planned completion time, and the identifier of the associated physical construction process object.
5. The virtual entity-based BIM construction progress full-process simulation method according to claim 4, characterized in that, Step S3 includes the following steps: Step S31: Assign a unique identifier to each non-physical construction event, and establish a one-to-one mapping relationship between non-physical construction events and virtual entities based on the unique identifier; Step S32: Determine the dependency relationship between each virtual entity and the physical construction process object based on the identifier of the physical construction process object associated in the plan information bound to the virtual entity; Step S33: Configure positive triggering conditions for virtual entities and entity construction process objects that have a dependency relationship. The positive triggering condition is that when the progress status of the virtual entity is updated to "completed", the entity construction process object with a dependency relationship is triggered to start, and the progress status parameter of the corresponding entity construction process object is updated to "in progress".
6. The virtual entity-based BIM construction progress full-process simulation method according to claim 5, characterized in that, Step S3 also includes the following steps: Step S34: Configure reverse triggering conditions for virtual entities and physical construction process objects that have a dependency relationship. The reverse triggering condition is to calculate the delay duration when the actual completion time of the non-physical construction event corresponding to the virtual entity exceeds the planned completion time, and delay the start time parameter of the physical construction process object that has a dependency relationship by the delay duration. Step S35: Determine the critical path of the main body BIM model of the project based on the start time parameters of the physical construction process objects and the construction sequence relationship between the physical construction process objects; Step S36: A linkage triggering mechanism is formed between the virtual entity and the physical construction process object by positive triggering conditions and negative triggering conditions. The linkage triggering mechanism is used to update the critical path according to the delayed start time parameter when the start time parameter of the physical construction process object is delayed, and to mark the progress deviation of the physical construction process object according to the updated critical path.
7. The virtual entity-based BIM construction progress full-process simulation method according to claim 6, characterized in that, Step S35 determines the critical path of the main BIM model of the project, including: Based on the construction sequence relationship between the physical construction process objects, generate multiple process paths from the first physical construction process object to the last physical construction process object; Based on the start time parameters and duration of each physical construction process, the completion time of the last physical construction process corresponding to each process path is determined, and the time span between the start time of the first physical construction process and the completion time of the last physical construction process is determined as the path duration of the corresponding process path. The process path with the longest construction period is identified as the critical path before the update, and the critical path before the update is used as the critical path for the current maintenance of the main body BIM model of the project.
8. The virtual entity-based BIM construction progress full-process simulation method according to claim 7, characterized in that, The critical path for updating the main BIM model of the project in step S36 includes: In response to an update in the state of a virtual entity, the entity construction process object affected by the virtual entity is determined as the starting object for the update based on the dependency relationship between the virtual entity and the entity construction process object. Starting with the initial object, the subsequent entity construction process objects affected are determined level by level along the construction sequence relationship between entity construction process objects, forming a set of affected processes; and the start time parameters of each entity construction process object in the set of affected processes are updated simultaneously. Recalculate the path duration for process paths that include the affected process set, while keeping the path duration unchanged for process paths that do not include the affected process set; The critical path is updated based on the recalculated path duration, where the path duration is the time span from the start of the initial process to the completion of the final process. The updated critical path is compared with the original critical path to identify newly added critical process objects and process objects that have exited the critical path, and the schedule deviations of the corresponding entity construction process objects are updated. 9.The virtual entity-based BIM construction progress whole-process simulation method according to claim 8, characterized in that, Step S4 includes the following steps: Step S41: Obtain the progress data of each non-physical construction event, determine the progress status and actual completion time of the virtual entity based on the progress data, and update the status information of the virtual entity. Step S42: Determine whether the updated virtual entity meets the triggering conditions of the corresponding linkage triggering mechanism. When the positive triggering conditions are met, generate the start command for the corresponding entity construction process object; when the negative triggering conditions are met, generate the start time adjustment command for the corresponding entity construction process object. Step S43: In response to the start command or start time adjustment command, perform state propagation based on the dependency relationship between the virtual entity and the physical construction process object and the construction sequence relationship between the physical construction process objects, determine the local update object, and use the local update object as the local update scope of the main body BIM model of the project. Step S44: Invoke the critical path update process to perform a local update on the main body BIM model of the project corresponding to the local update object, and simultaneously update the progress simulation results of the main body BIM model of the project. 10.A virtual entity-based BIM construction progress whole-process simulation system, characterized in that, For executing the BIM construction progress full-process simulation method based on virtual entities as described in claim 1, the BIM construction progress full-process simulation system based on virtual entities includes: The model building module is used to build the main BIM model of the project. The main BIM model of the project contains multiple entity construction process objects, and each entity construction process object has start time parameters and progress status parameters. The virtual mapping module is used to construct virtual entities that map non-physical construction events in the main BIM model of the project, and bind the planning information of non-physical construction events to the virtual entities. The planning information includes the planned completion time of the non-physical construction event and the identifier of the physical construction process object that it is constrained by. The linkage configuration module is used to establish a linkage triggering mechanism between virtual entities and physical construction process objects based on the plan information; The simulation update module is used to acquire progress data of non-physical construction events, including the progress status and actual completion time of the non-physical construction events; it updates the status of virtual entities based on the progress data, and through a linkage triggering mechanism, it synchronously updates the progress simulation results of the main project BIM model based on the updated status of the virtual entities.