An Adaptive Correction Method for Cumulative Deviation of T-Codes for Metal Roof Supports

By acquiring measurement data and construction feedback data, correcting changes in measurement benchmarks and reversible displacements of supporting structures, predicting uncorrected deviations, constructing correction realization relationships, determining effective correction intervals and target correction command quantities, the problem of inaccurate control of T-code installation deviations for metal roof supports was solved, and closed-loop adaptive correction of cumulative deviations was achieved.

CN123116809APending Publication Date: 2026-11-17THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611286081.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies struggle to distinguish between changes in measurement reference, reversible displacement, and installation deviations, resulting in inaccurate control of installation deviations for metal roof support T-codes. They also fail to achieve closed-loop adaptive correction of accumulated deviations and lack a continuous update mechanism.

Method used

By determining the deviation between the T-code to be installed and the terminal target, obtaining measurement data and construction feedback data, correcting changes in measurement benchmarks and reversible displacements of the supporting structure, predicting uncorrected deviations, constructing correction realization relationships, determining effective correction intervals and target correction command quantities, generating correction layout coordinates, and updating correction command quantities and coordinates based on construction feedback.

Benefits of technology

It achieves the distinction between changes in measurement reference and reversible displacement, updates the correction relationship based on construction feedback, takes into account the continuous transition between adjacent T-codes and the terminal closure requirements, and realizes closed-loop adaptive correction of cumulative deviation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123116809A_ABST
    Figure CN123116809A_ABST
Patent Text Reader

Abstract

This invention provides an adaptive correction method for the cumulative deviation of T-codes for metal roof supports, belonging to the field of building construction surveying technology. The technical solution is as follows: determine the deviation between the T-code to be installed and the terminal target; acquire T-code measurement data, construction feedback data, and correction constraints; correct for changes in the measurement reference and reversible displacement of the support structure to obtain the reference state alignment deviation; predict the uncorrected deviation and determine the correction realization relationship; determine the remaining error budget and effective correction interval, construct bidirectional reachable correction constraints, and determine the target correction command quantity; generate correction layout coordinates, and update the target correction command quantity and correction layout coordinates based on post-construction measurement and feedback data. The beneficial effects of this invention are: it can distinguish between changes in the measurement reference, reversible displacement, and installation deviation; update the correction realization relationship based on construction feedback; take into account the continuous transition between adjacent T-codes and the terminal closure requirement; and achieve closed-loop adaptive correction of the cumulative deviation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction surveying technology, and in particular to an adaptive correction method for the cumulative deviation of T-codes for metal roof supports. Background Technology

[0002] Metal roofing systems are widely used in airport terminals, convention centers, stadiums, and industrial plants due to their lightweight, high assembly efficiency, and strong adaptability to large-span spatial structures and architectural designs. During metal roofing construction, the T-shaped supports are responsible for positioning, connecting, and transferring loads on the roof panels. Their installation accuracy directly affects the interlocking of the roof panels, the continuity of the joints, and the quality of the final closure of the construction section.

[0003] With the development of total station, three-dimensional coordinate measurement and digital layout technology, construction sites are gradually adopting design coordinate layout, batch re-measurement and deviation adjustment methods to control the position of T-codes, and using measurement data to assist construction personnel in correcting installation errors.

[0004] Existing T-code installation deviation control typically uses the difference between the design coordinates and the single measured coordinates as the basis for adjustment. It focuses on making local corrections to the current measuring point, making it difficult to distinguish between instrument resetting, changes in the measuring coordinate frame, and reversible displacements of the supporting structure caused by temperature and temporary loads. It is easy to misjudge changes in the measuring system or temporary structural deformations as permanent installation deviations.

[0005] Meanwhile, the adjustments issued on-site are affected by the T-code connection structure, the transmission error of adjustment tools, disturbances during the position fixing process, and the local elastic recovery of components. The actual effective correction amount and the target correction command amount are not consistently consistent. Existing methods typically lack a mechanism to continuously determine and update the correction realization relationship between the two based on construction feedback data. Furthermore, point-by-point correction fails to coordinate the continuous transition between adjacent T-codes, the remaining adjustment capacity, and the terminal closure target. Excessive concentration of correction amounts in the preceding T-codes may lead to a lack of feasible adjustment space in subsequent positions, and the deviations gradually accumulating along the construction sequence cannot be controlled and converged at the terminal position. After the measurement batch is updated, the state of the supporting structure changes, or the construction conditions change, the existing correction and layout coordinates are also difficult to become invalid and regenerated in a timely manner. The existing control process lacks joint forward and backward judgment of feasible correction paths, making it difficult to form a closed-loop adaptive correction process that continuously reaches the terminal target from the current actual construction state. Summary of the Invention

[0006] The purpose of this invention is to provide an adaptive correction method for the cumulative deviation of T-codes of metal roof supports, which can distinguish between changes in measurement reference, reversible displacement and installation deviation, update the correction relationship based on construction feedback, take into account the continuous transition of adjacent T-codes and the terminal closure requirements, and realize closed-loop adaptive correction of cumulative deviation.

[0007] This invention is achieved through the following measures: An adaptive correction method for cumulative deviation of T-codes in metal roof supports, characterized in that it includes: S1. Determine the deviation between the T-code to be installed and the terminal target, and obtain T-code measurement data, construction feedback data and correction constraints; S2. Based on the T-code measurement data, perform measurement reference change correction and support structure reversible displacement correction to obtain the reference state alignment deviation; S3. Predict the uncorrected deviation of the T-code to be installed based on the alignment deviation of the reference state, and determine the correction realization relationship based on the construction feedback data; S4. Subtract the value of the uncorrected deviation at the terminal position from the terminal target deviation to obtain the remaining error budget, and determine the effective correction interval by combining the correction constraint and correction realization relationship; S5. Construct bidirectional reachable correction constraints based on the effective correction interval, remaining error budget, and correction constraints, and determine the target correction command quantity under the bidirectional reachable correction constraints based on the correction realization relationship; S6. Generate the calibration layout coordinates of the T-code to be installed according to the target calibration command quantity, and update the target calibration command quantity and calibration layout coordinates according to the T-code measurement data and construction feedback data obtained after construction according to the calibration layout coordinates.

[0008] The invention also has the following specific features: Step S1 includes: Based on the metal roofing design documents and on-site construction records, the T-codes that have not yet been installed and whose installation positions have not yet been fixed within the construction section are identified as T-codes to be installed, and the T-codes at the terminal positions are identified as terminal T-codes. Based on the roof panel closure requirements and the connection requirements of adjacent construction sections, the target coordinates and preset correction direction of the terminal T-code are determined, and the coordinate difference obtained by subtracting the design coordinates of the terminal T-code from the target coordinates is projected along the preset correction direction to obtain the terminal target deviation. The spatial coordinates of the installed T-codes, external stable control points, and support structure follow-up reference points are acquired in batches to form T-code measurement data. By associating the T-code number, target correction instruction quantity, T-code measurement data before and after adjustment, and measurement batch, construction feedback data is formed. Based on the T-code connection structure, the allowable adjustment space on site, the adjustment capability of the adjustment tools, and the roof panel installation requirements, the correction constraints are determined, including the target correction command range, the effective correction range, the allowable variation range of the effective correction of adjacent T-codes, and the allowable residual at the terminal.

[0009] Step S2 includes: The measurement reference transformation parameters are determined based on the reference coordinates and measured coordinates of at least three non-collinear external stable control points, and the measured coordinates of the installed T-codes and the follow-up reference points of the support structure are corrected for measurement reference changes. The coordinates of the support structure follower reference point after the measurement benchmark change correction are compared with its reference coordinates to determine the total displacement of the support structure; the quasi-static displacement benchmark value is determined based on the coordinates of the support structure follower reference point in the restored state, and the difference between the total displacement of the support structure and the quasi-static displacement benchmark value is determined as the reversible displacement of the support structure. Select a support structure follow-up reference point located in the same structural response partition as the corresponding T-code, and determine the reversible displacement of the support structure at the location of the T-code by interpolation based on its spatial position relationship with the corresponding T-code. The coordinate difference between the T-code coordinates after the measurement reference change correction is obtained by subtracting the reversible displacement of the support structure at the location of the T-code, and then subtracting the design coordinates of the corresponding T-code from the obtained coordinates. The result is then projected along the preset correction direction of the corresponding T-code to obtain the reference state alignment deviation.

[0010] In step S3, predicting the uncorrected deviation of the T-code to be installed based on the alignment deviation of the reference state includes: The T-code with the largest serial number that has been installed in the current measurement batch is determined as the prediction starting point. The uncorrected deviation increment rate is determined based on the reference state alignment deviation of adjacent installed T-codes, the effective correction amount already implemented by the installed T-code with the larger serial number, and the cumulative design distance difference between adjacent installed T-codes. Before the prediction starting point, select multiple consecutive installed T-codes that belong to the same continuous construction sequence and the same structural response zone as the T-code to be installed, form a deviation prediction sample set, and determine the uncorrected deviation increment rate of the current construction position and its changing trend along the construction position based on the deviation prediction sample set. Starting from the actual installation status of the predicted starting point, and based on the uncorrected deviation increment rate, the changing trend, and the cumulative design distance of each T-code to be installed, the uncorrected deviation of each T-code to be installed is predicted according to the T-code construction sequence.

[0011] In step S3, the correction implementation relationship is determined based on the construction feedback data, including: The measurement reference change correction and the reversible displacement correction of the supporting structure are respectively applied to the T-code measurement data before and after the adjustment in the construction feedback data, so that the T-code measurement data before and after the adjustment are unified to the same reference state, and the effective correction amount is determined according to the alignment deviation of the reference state before and after the adjustment. From the construction feedback data, select construction feedback data that have the same or similar T-code connection structure, adjustment tools, construction conditions and structural response zones as the T-code to be installed, and form a local feedback sample set; Based on the corresponding target correction command quantity and effective correction quantity in the local feedback sample set, determine the correction realization relationship of converting the target correction command quantity into the effective correction quantity; When there are significant differences in the correction implementation relationship corresponding to different target correction command quantity intervals, the correction implementation relationship corresponding to each target correction command quantity interval is determined separately; when the correction implementation relationship is unstable, the determination of the target correction command quantity based on the correction implementation relationship is suspended, and a small-scale trial correction is implemented to obtain new construction feedback data.

[0012] Step S4 includes: Subtract the value of the uncorrected deviation at the terminal position from the terminal target deviation to obtain the remaining error budget, and determine the remaining error budget interval based on the remaining error budget and the terminal allowable residual in the correction constraint; For each T-code to be installed, under the condition that the correction realization relationship is stable, the target correction command range in the correction constraint is mapped to the effective correction range through the correction realization relationship, and the mapping result is intersected with the effective correction range in the correction constraint to determine the effective correction interval of the corresponding T-code to be installed. When the correction implementation relationship is a segmented correction implementation relationship, each target correction instruction quantum interval is mapped to the effective correction domain, and the intersection of the obtained effective correction sub-intervals with the effective correction range is calculated. Effective correction sub-intervals that overlap or have their endpoints connected are merged. When the mapping result does not overlap with the effective correction range, it is determined that there is no effective correction interval for the corresponding T-code to be installed, and the determination of the target correction instruction amount of the T-code to be installed based on the current correction implementation relationship is paused.

[0013] In step S5, a bidirectional reachable correction constraint is constructed based on the effective correction interval, the remaining error budget, and the correction constraint, including: The T-code with the largest serial number that has been installed in the current measurement batch is determined as the starting position, and the candidate effective correction value of the starting position is set to zero. Based on the forward reachable set of the previous T-code, the effective correction interval of the current T-code to be installed, and the allowable variation range of the effective correction amount of adjacent T-codes, the forward reachable set of each T-code to be installed is determined sequentially according to the T-code construction sequence. The effective correction interval of the T-code to be installed located at the terminal position is intersected with the remaining error budget interval to determine the backward reachable set of the T-code to be installed. Based on the backward reachable set of the next T-code, the effective correction interval of the current T-code to be installed, and the allowable variation range of the effective correction amount of the adjacent T-codes, the backward reachable sets of the remaining T-codes to be installed are determined in the opposite direction of the T-code construction sequence. The intersection of the forward reachable set and the backward reachable set of each T-code to be installed is obtained to determine the corresponding bidirectional reachable set. The bidirectional reachable set of each T-code to be installed, the allowable variation range of the effective correction amount of adjacent T-codes, and the remaining error budget interval together constitute the bidirectional reachable correction constraint.

[0014] In step S5, determining the target correction command quantity based on the correction realization relationship under the bidirectional reachability correction constraint includes: The reference effective correction amount for each T-code to be installed is determined based on the ratio of the cumulative design distance between each T-code to be installed and the starting position to the cumulative design distance between the terminal position and the starting position, and the remaining error budget. According to the T-code construction sequence, based on the target effective correction amount of the previous T-code, the allowable variation range of the effective correction amount of adjacent T-codes, and the bidirectional reachable set of the current T-code to be installed, a candidate selection set for the current T-code to be installed is determined, and the candidate effective correction amount with the smallest absolute difference from the corresponding reference effective correction amount is selected from the candidate selection set as the target effective correction amount. Based on the correction implementation relationship, the target effective correction amount is converted into a target correction instruction amount, and it is verified whether the target correction instruction amount is within the corresponding target correction instruction amount range; When the correction implementation relationship is a segmented correction implementation relationship, the target correction instruction quantity is determined in the corresponding target correction instruction quantum interval according to the effective correction sub-interval to which the target effective correction quantity belongs.

[0015] In step S6, generating the calibration lofting coordinates of the T-code to be installed according to the target calibration command quantity includes: The unit correction direction vector is determined according to the preset correction direction of each T-code to be installed. The design coordinates of each T-code to be installed and the displacement formed by its uncorrected deviation along the unit correction direction vector are added to obtain the predicted uncorrected reference coordinates. The predicted uncorrected reference coordinates, the displacement formed by the target correction command along the unit correction direction vector and the reversible displacement of the support structure are added to obtain the correction layout coordinates under the reference coordinate frame. When the space measurement equipment adopts the field measurement coordinate frame, the correction layout coordinates under the reference coordinate frame are converted into the correction layout coordinates under the field measurement coordinate frame according to the measurement reference transformation parameters. Input the corrected layout coordinates corresponding to the coordinate frame used by the spatial measurement equipment into the construction layout terminal, perform temporary positioning and position adjustment of the T-code to be installed, and complete the position fixation after the temporary positioning deviation does not exceed the construction layout tolerance.

[0016] In step S6, based on the T-code measurement data and construction feedback data obtained after construction according to the corrected layout coordinates, the target correction command quantity and the corrected layout coordinates are updated, including: After one or more T-codes are fixed in position, a new measurement batch is established to obtain T-code measurement data. The actual amount of target correction command issued is associated with the T-code measurement data before and after adjustment to form construction feedback data. The T-code measurement data is corrected for measurement reference change and reversible displacement of support structure to obtain reference state alignment deviation. The effective correction amount is determined based on the reference state alignment deviation before and after adjustment, and the correction realization relationship is updated. The T-code with the largest serial number that has been installed in the measurement batch is determined as the prediction starting point; when the space allowed for adjustment, the T-code connection structure, the adjustment tools, or the continuous installation conditions of the roof panels change, the correction constraints are reconfirmed. Based on the updated T-code measurement data, construction feedback data, and correction constraints, update the uncorrected deviation, remaining error budget, effective correction range, bidirectional reachable correction constraints, and target correction command quantity of the remaining T-codes to be installed, and regenerate the correction layout coordinates of the remaining T-codes to be installed.

[0017] The beneficial effects of this invention are: it can distinguish between changes in the measurement reference, reversible displacement and installation deviation, update the correction relationship based on construction feedback, take into account the continuous transition of adjacent T-codes and the terminal closure requirements, and realize closed-loop adaptive correction of cumulative deviation. This invention obtains the T-code deviation under a unified reference state by separately correcting for changes in the measurement benchmark and the reversible displacement of the supporting structure. Based on construction feedback data, it determines the correction realization relationship between the target correction command and the effective correction amount, and constructs a bidirectional reachable correction constraint by combining the effective correction interval, the remaining error budget, and the allowable variation range of the effective correction amounts of adjacent T-codes, thereby continuously determining the target correction command for each T-code to be installed. After construction, the correction realization relationship, the target correction command, and the correction layout coordinates are updated based on new measurement data and construction feedback data, achieving closed-loop adaptive correction of the cumulative deviation of the T-codes. Attached Figure Description

[0018] Figure 1 This is an overall flowchart of the adaptive correction method for the cumulative deviation of the T-code of the metal roof support provided in Embodiment 1 of the present invention. Detailed Implementation

[0019] To clearly illustrate the technical features of this solution, the following detailed implementation method will be used to describe the solution.

[0020] Example 1 This embodiment provides an adaptive correction method for the cumulative deviation of T-codes in metal roof supports. This method is used to identify, predict, and correct the cumulative deviation of T-codes when multiple T-codes are installed continuously along a predetermined construction direction within the same construction section. The T-codes are numbered sequentially according to the construction sequence. ,in, This represents the total number of T-codes within the construction section. This refers to the terminal T-codes located at the end positions. Based on the metal roofing design documents and on-site construction records, the design coordinates of each T-code, the T-codes to be installed, the terminal target deviation, and the correction constraints are determined. Among these, installed T-codes refer to those whose positions have been fixed. T-codes, or T-codes to be installed, refer to T-codes that have not yet been installed and whose installation locations have not yet been fixed.

[0021] exist During the continuous installation of the code, each The code is subject to unified construction standards, adjacent location relationships, The T-code connection structure and roof panel closure requirements are jointly constrained. Changes in measurement benchmarks, single-point installation errors, and changes in the condition of the supporting structure may gradually accumulate along the construction sequence, causing subsequent T-codes to deviate from the designed installation sequence. This embodiment continuously plans the correction process for subsequent T-codes to be installed based on the deviation of the terminal target, rather than only performing single-point corrections on the deviation of the current installation position.

[0022] On-site, spatial measurement equipment was used to acquire T-code measurement data, and data processing equipment was used to calculate reference state alignment deviation, predict uncorrected deviation, determine correction implementation relationship, and determine target correction command quantity. Construction personnel used adjustment tools to temporarily position and adjust the T-code to be installed according to the correction and layout coordinates, and then fixed the position after meeting the construction layout tolerance. The specific models of the spatial measurement equipment, data processing equipment, adjustment tools, and construction layout terminal are not limited.

[0023] External stability control points are established at locations unaffected by deformation of the supporting structure within the construction section. These points are used to identify changes in the measurement reference caused by the relocation of spatial measurement equipment or translation and rotation of the on-site measurement coordinate frame. Support structure follow-up reference points are established in support areas with the same or similar structural response to the corresponding T-codes. These points characterize the reversible displacement of the supporting structure caused by temperature changes, temporary construction loads, or stress changes during construction. Data acquired in each measurement batch... Record the spatial coordinates of the code, external stability control points, and supporting structure follow-up reference points, and record the corresponding object number, measurement time, measurement batch, and construction stage.

[0024] Before installation begins in the construction section, under the condition that the supporting structure is not subjected to temporary construction loads and its structural state is stable, initial measurements are taken of the external stability control points and the supporting structure's follow-up reference points. The initial coordinates of the external stability control points are determined as the reference coordinates, and the initial coordinates of the supporting structure's follow-up reference points are determined as the reference coordinates. This initial stable state is defined as the first recovery state, and the initial quasi-static displacement reference value is determined. Subsequently, until a new recovery state is confirmed, the most recently confirmed quasi-static displacement reference value is used.

[0025] The first The target correction command quantity of each T-code is denoted as After the T-code has been adjusted and fixed in position, the effective correction amount determined by the measurement reference change correction and the reversible displacement correction of the support structure is denoted as... The target correction command and the effective correction value use the same length unit and positive / negative direction. Positive values ​​are taken along the preset correction direction of the corresponding T-code, and negative values ​​are taken along the opposite direction. Due to T-code connection construction, adjustment tool transmission errors, position fixing process disturbances, and local elastic response of components, the target correction command and the effective correction value may not be consistent.

[0026] The T-code number, the actual target correction command amount, the T-code measurement data before and after adjustment, and the corresponding measurement batch association records are used to form construction feedback data. After unifying the reference state of the T-code measurement data before and after adjustment in the construction feedback data, the corresponding effective correction amount is determined, and a construction feedback sample is formed by the corresponding target correction command amount and effective correction amount. Based on the construction feedback samples that are the same as or similar to the T-code connection structure, adjustment tools, construction conditions, and structural response zones of the T-code to be installed, the correction realization relationship is determined and updated.

[0027] Based on the above construction objects, measurement objects, data sources and parameter definitions, the following steps are followed to implement adaptive correction of the cumulative deviation of the metal roof support T-code.

[0028] S1. Determine the deviation between the T-code to be installed and the terminal target, and obtain T-code measurement data, construction feedback data, and correction constraints, specifically including: Based on the metal roofing design documents and on-site construction records, the T-codes within the same construction section were numbered sequentially according to the predetermined construction order. ,in, This represents the total number of T-codes within the construction section. This refers to the terminal T-code located at the terminal position. Based on the actual installation status of each T-code, those T-codes that have not yet been installed and whose installation positions are not yet fixed are identified as T-codes to be installed.

[0029] Based on the roof panel closure requirements, design allowable deviations, and connection requirements between adjacent construction sections, the target coordinates and preset correction directions of the terminal T-codes are determined. The preset correction direction is determined based on the allowable displacement direction of the T-code connection structure and the impact of the corresponding displacement on the roof terminal closure state, preferably a direction that has a major influence on the terminal closure deviation and allows for positional adjustments. Following the same determination principle, the preset correction directions for each T-code to be installed are determined separately.

[0030] The first The design coordinates of the T-code are as follows The target coordinates when the terminal T-code meets the roof panel closure requirements or the connection requirements of adjacent construction sections are set as follows: The preset correction direction vector of the terminal T code is denoted as... Then the terminal target deviation Determined according to the following formula:

[0031] in, The design coordinates for the terminal T-code. It is a non-zero vector. The modulus of the preset correction direction vector is given by the symbol ".", which represents the vector dot product. The terminal target deviation is expressed in units of length, taking a positive value along the preset correction direction and a negative value in the opposite direction. The terminal target deviation is zero when the target coordinates of the terminal T-code coincide with the design coordinates.

[0032] By terminal The coordinate difference obtained by subtracting the design coordinates from the target coordinates of the code is projected along the preset correction direction. This converts the roof panel closure requirements or the connection requirements of adjacent construction sections into scalar targets used in subsequent correction calculations, thus avoiding the inclusion of coordinate components orthogonal to the preset correction direction in the terminal target deviation.

[0033] In the Within each measurement batch, spatial measurement equipment was used to acquire the spatial coordinates of the installed T-weights, external stable control points, and supporting structure servo reference points, and the corresponding object number, measurement time, measurement batch, and construction stage were recorded. This refers to the batch number measured.

[0034] The first The installed T-code is in the first The measured coordinates in each measurement batch are as follows: ; will the first The reference coordinates of the first external stability control point and the first The measured coordinates in each measurement batch are respectively denoted as follows: and ; will the first The reference coordinates of the first support structure follow-up reference point and the first The measured coordinates in each measurement batch are respectively denoted as follows: and The aforementioned spatial coordinates, object number, measurement time, measurement batch, and construction stage together constitute the T-code measurement data.

[0035] The external stability control points are set up in locations unaffected by deformation of the supporting structure within the construction section, and are used to characterize changes in the measurement reference caused by the resetting of the space measurement equipment or the translation and rotation of the on-site measurement coordinate frame; the supporting structure follow-up reference points are set up in the support area with the same or similar structural response as the corresponding T-code, and are used to characterize the displacement of the supporting structure caused by temperature changes, temporary construction loads, or changes in stress during the construction stage.

[0036] External stability control points and supporting structure motion reference points are used to characterize changes in the measurement system and changes in the state of the construction object, respectively, and they cannot be substituted for each other. It is preferable that the installed T-codes, external stability control points, and supporting structure motion reference points be measured within the same measurement batch; if simultaneous measurement is not possible, the measurement should be completed within the time window when the stability of the supporting structure is confirmed by re-measurement using the supporting structure motion reference points, to ensure the comparability of different measurement results.

[0037] For T-codes whose positions have been adjusted according to the target correction command, the corresponding T-code number, the actual target correction command amount, the T-code measurement data before and after adjustment, and the corresponding measurement batch are recorded together to form construction feedback data. Both the pre- and post-adjustment measurement batches include the corresponding external stability control point measurement data and the support structure follow-up reference point measurement data. This is to facilitate subsequent correction of the measurement benchmark changes and the reversible displacement of the support structure based on the T-code measurement data before and after adjustment, ensuring that the T-code positions before and after adjustment are unified to the same reference state.

[0038] The difference between the original measured coordinates before and after adjustment is not directly used as the effective correction amount. There may be changes in the measurement reference and reversible displacement of the supporting structure between the two measurements before and after adjustment. Therefore, after the corresponding correction is completed in subsequent steps, the effective correction amount actually formed by the position adjustment is determined according to the alignment deviation of the reference state before and after adjustment, and the correction realization relationship is determined according to the corresponding target correction command amount and effective correction amount.

[0039] The correction constraints are determined based on the T-code connection structure, the allowable adjustment space on site, the adjustment capability of the adjustment tools, the continuous installation requirements of the roof panels, the roof panel closure requirements, and the connection requirements between adjacent construction sections. These correction constraints include the target correction command range, the effective correction range, the allowable variation range of the effective correction amounts of adjacent T-codes, and the allowable residual at the terminal, and satisfy the following:

[0040] in, and The first The lower and upper limits of the target correction command quantity for each code are determined based on the controllable adjustment range of the adjustment tool, the allowable displacement range of the T-code connection part, and the accuracy of the construction operation. and The first The effective correction limit and upper limit of each code are determined based on the T-code connection structure, the allowable adjustment space on site, and the continuous installation requirements of the roof panel. and The first The lower and upper limits of the allowable change in effective correction between a code and the previous T code are determined based on the requirements for continuous installation of the roof panel, the requirements for smooth connection between adjacent support positions, and the limitation of local deformation.

[0041] Let the terminal allowable residual be denoted as ,and The terminal's allowable residual is determined based on the roof panel closure accuracy or the connection accuracy of adjacent construction sections, and is used to limit the allowable deviation range relative to the terminal target deviation after the terminal T-code has completed correction.

[0042] The aforementioned correction constraints are derived from the actual connection conditions of the T-codes, on-site adjustment capabilities, and roof panel installation requirements. This step determines the deviation between the T-codes to be installed and the terminal target, and obtains T-code measurement data, construction feedback data, and correction constraints with corresponding measurement batches. This provides a data foundation and constraints for subsequent calculation of reference state alignment deviation, prediction of uncorrected deviation, determination of correction implementation relationships, and determination of target correction command quantities.

[0043] S2. Based on the T-code measurement data, perform measurement reference change correction and support structure reversible displacement correction to obtain the reference state alignment deviation, specifically including: The initial stable state described at the beginning of this embodiment is used as the reference measurement state. According to the... Reference coordinates of each external stability control point in each measurement batch and measured coordinates The measurement reference transformation parameters for this measurement batch relative to the reference measurement state are determined. The measurement reference transformation parameters include a rotation matrix. Translation vector The solution is obtained by using at least three non-collinear external stability control points.

[0044] The rotation matrix is ​​determined based on the principle of minimizing the registration residual between the coordinates of each external stable control point after coordinate transformation and the corresponding reference coordinates. Translation vector :

[0045] in, The number of external stable control points involved in the calculation of the measurement reference transformation parameters, and It is the identity matrix; This indicates that the rotation matrix does not include mirror transformation; The L2 norm of a vector is used to represent the vector's L2 norm.

[0046] According to the measurement reference transformation parameters, the first Measured coordinates of T-codes in a batch of measurements Measured coordinates of the support structure's follow-up reference point Transforming to a reference coordinate frame determined by external stable control points, the T-code coordinates and the coordinates of the support structure's follower reference point after correction for the measurement reference change are obtained. The T-code coordinates after the measurement reference change correction are as follows:

[0047] The coordinates of the support structure's servo reference point after the measurement datum change correction are as follows:

[0048] Preferably, after determining the measurement reference transformation parameters, the registration residuals between the coordinates of each external stable control point after coordinate transformation and the corresponding reference coordinates are calculated. When the registration residual of any external stable control point exceeds the preset registration tolerance, the external stable control point is identified as an abnormal control point and excluded. Provided that there are at least three remaining external stable control points that are not collinear, the measurement reference transformation parameters are redefined. The preset registration tolerance is determined based on the measurement accuracy of the space measurement equipment, the layout distance of the external stable control points, and the allowable measurement error at the construction site.

[0049] Changes in the measurement datum refer to changes in the coordinate frame experienced by all measured objects within the same measurement batch. These changes can be caused by resetting the station of the space measurement equipment, altering the station location, or translational and rotational movements of the on-site measurement coordinate frame. Therefore, the measurement datum change should first be corrected based on external stable control points. Then, the support structure displacement should be determined based on the coordinates of the support structure's follow-up reference point after the measurement datum change correction is completed. This avoids including changes in the measurement system in the support structure displacement or T-weight installation deviations.

[0050] Furthermore, the first The coordinates of each support structure follow-up reference point after the measurement reference change correction is subtracted from its reference coordinates. The follow-up reference point of the support structure is obtained at the 1st Total displacement of the supporting structure in each measurement batch :

[0051] The total displacement of the supporting structure includes the reversible displacement component and the quasi-static displacement component. The reversible displacement component refers to the displacement component caused by temperature changes, temporary construction loads, or temporary stress states during the construction phase, which can be recovered or nearly recovered after the corresponding temporary influencing factors are eliminated. The quasi-static displacement component refers to the displacement component that continues to exist in multiple adjacent measurement batches after the corresponding temporary influencing factors are eliminated.

[0052] The quasi-static displacement component of the support structure reflects the actual state of the support structure after it has been formed and continues to exist. Subsequent T-weight installation needs to adapt to this actual state, and therefore it is not removed from the T-weight measurement results. The reversible displacement component of the support structure reflects the temporary structural state at the time of measurement and is removed when determining the installation deviation of the T-weight relative to the design position.

[0053] In the initial stable state described at the beginning of this embodiment, the initial quasi-static displacement reference value is determined based on the coordinates of the support structure's follower reference point after the measurement reference change correction. When the reference coordinates of the support structure's follower reference point... When taken from the initial steady state, the corresponding initial quasi-static displacement reference value is zero.

[0054] After the temporary construction load is removed or the phased stress state ends, the same supporting structure's moving reference point is continuously remeasured. When the coordinate change after correction of the measurement benchmark between adjacent remeasurement batches does not exceed a preset stability threshold, the corresponding support area is determined as the recovery state. The coordinate difference obtained by subtracting the reference coordinate from the coordinate of the supporting structure's moving reference point after correction of the measurement benchmark in this recovery state is determined as the new quasi-static displacement benchmark value. The preset stability threshold is determined based on the measurement accuracy of the space measurement equipment and the allowable state fluctuation of the supporting structure.

[0055] The first The quasi-static displacement reference value applicable to each measurement batch is denoted as... Until a new recovery status is confirmed, the most recently confirmed quasi-static displacement reference value shall be used; the newly determined quasi-static displacement reference value shall only be applied to the measurement batch after its confirmation time, and shall not retroactively modify the previously obtained reference state alignment deviation.

[0056] The first The support structure servo reference point is at the first The reversible displacement of the support structure at the follow-up reference point is obtained by subtracting the corresponding quasi-static displacement reference value from the total displacement of the support structure in each measurement batch. :

[0057] This step does not involve a safety status assessment of the support structure or a prediction of its deformation. Instead, it uses a follow-up reference point on the support structure to identify reversible displacements in the T-code measurement data caused by temporary structural conditions, thus avoiding misinterpreting temporary structural deformations as requiring permanent correction. Code installation deviation.

[0058] Furthermore, according to the first The structural response relationship between the T-code and each support structure follow-up reference point is established. Support structure follow-up reference points located within the same structural response partition as the T-code are selected to form a relationship with the T-code. The set of follow-up reference points corresponding to each code The structural response zoning is determined based on the connection relationship between supporting components, supporting boundaries, and structural divisions; the supporting structural follow-up reference points located on both sides of expansion joints, independent supporting boundaries, or different stress sections are not included in the same follow-up reference point set.

[0059] When the set of follow-up reference points When only one support structure follower reference point is included, the reversible displacement of the support structure at that support structure follower reference point is determined as the first... The support structure at the location of the code can undergo reversible displacement; when the set of follow-up reference points... When multiple support structure follow-up reference points are included, the relationship between each support structure follow-up reference point and the first... Interpolate the spatial relationship between the T codes to determine the first T code. The supporting structure at the location of the code can be reversibly displaced.

[0060] Preferably, the first Reversible displacement of the support structure at the location of each T-code Determined according to the following formula:

[0061] in, For the first The design coordinates of each code within the reference coordinate frame. For the first The reference coordinates of each supporting structure's follow-up reference point within the same reference coordinate frame. It is a positive parameter with a length unit, used to prevent the denominator from being zero when the T-code position coincides with the position of the support structure follow-up reference point.

[0062] The above interpolation method is a preferred method for determining the reversible displacement of the support structure at the location of the T-code. Other spatial interpolation methods that satisfy the response zoning constraints of the same structure can also be used.

[0063] After completing the correction for changes in the measurement reference, the first... indivual The coordinates after the measurement reference change correction are deducted. The supporting structure at the location of the code undergoes reversible displacement. The resulting coordinates are then subtracted from the design coordinates of the corresponding T-code. The obtained coordinate difference is then projected along the preset correction direction of the T-code to obtain the first... The T code in the first Reference state alignment deviation in each measurement batch :

[0064] in, For the first The non-zero preset correction direction vector of each T-code is determined based on the allowable displacement direction of the T-code connection structure and the influence of the corresponding displacement on the continuous installation state of the roof panel; subscript Indicates the preset correction direction; The unit of length is used, and positive values ​​are taken along the preset correction direction, while negative values ​​are taken in the opposite direction.

[0065] The reference state refers to the state in which the T-code measurement data has been unified to a reference coordinate frame determined by external stable control points, and the reversible displacement components of the supporting structure have been eliminated. The alignment deviation of the reference state retains the continuous structural state reflected by the quasi-static displacement components of the supporting structure, and is used to characterize the deviation of the T-code relative to the design position along the preset correction direction after excluding changes in the measurement system and temporary structural deformations.

[0066] For the pre-adjustment and post-adjustment T-code measurement data corresponding to the construction feedback data in S1, the measurement benchmark change correction and the reversible displacement correction of the supporting structure are performed in the manner described above. For the pre-adjustment and post-adjustment T-code measurement data corresponding to the same position adjustment, the same quasi-static displacement benchmark value is used for correction to unify the T-code positions before and after adjustment to the same reference state; when the pre-adjustment and post-adjustment T-code measurement data cannot be corrected using the same quasi-static displacement benchmark value, the corresponding data is not used to determine the effective correction amount and the correction realization relationship.

[0067] The T-code measurement data before and after adjustment, after being unified with the reference state, are used by S3 to determine the effective correction amount, and the correction implementation relationship is determined according to the corresponding target correction command amount and the effective correction amount.

[0068] S3. Predict the uncorrected deviation of the T-code to be installed based on the alignment deviation of the reference state, and determine the correction implementation relationship based on the construction feedback data, specifically including: For the construction feedback data generated by S1, the measurement benchmark change correction and the reversible displacement correction of the supporting structure are performed on the T-code measurement data before and after the same T-code adjustment. For data that can be corrected using the same quasi-static displacement benchmark value, the T-code positions before and after the adjustment are unified to the same reference state, and the corresponding reference state alignment deviation before and after the T-code adjustment is obtained; data that cannot be corrected using the same quasi-static displacement benchmark value is not used to determine the effective correction amount and the correction realization relationship.

[0069] The first The first T-code The reference state alignment deviations before and after the adjustment are denoted as follows: and The effective correction amount corresponding to this adjustment Determined according to the following formula:

[0070] in, This refers to the T-code sequence number of the construction feedback data that has already been generated. The order of adjustment for the same T code; For the first The code number The effective correction amount formed by this adjustment; and its corresponding target correction command amount are denoted as... The effective correction amount and the target correction command amount use the same length unit and positive / negative direction. Positive values ​​are taken along the preset correction direction of the corresponding T-code, and negative values ​​are taken along the opposite direction of the preset correction direction.

[0071] The effective correction amount is not a direct difference between the original measured coordinates before and after adjustment, but rather the positional change obtained after unifying the T-code measurement data before and after adjustment to the same reference state. When the same T-code is adjusted multiple times, and each adjustment has corresponding before and after values... When the code measurement data, adjustment direction, and T-code connection status remain unchanged, each adjustment will be used to form a construction feedback sample. If T-code repositioning, T-code connection status change, or adjustment direction change occurs during the adjustment process, the data before and after the status change will be assigned to different construction feedback sample groups. Data that cannot form a clear correspondence between the target correction command quantity and the effective correction quantity will not be used to determine the correction implementation relationship.

[0072] Furthermore, the first The T-code with the largest serial number installed in each measurement batch is denoted as _ ... ,in, This is the highest sequence number of the currently installed T-code. [The following is a list of numbers / items] The cumulative design distance of each code along the predetermined construction direction relative to the starting point of the construction section is denoted as: The uncorrected deviation increment rate is determined based on the reference state alignment deviation of adjacent installed T-codes in the same measurement batch, the effective correction amount implemented up to the measurement batch for the installed T-code with the larger serial number, and the cumulative design distance difference between adjacent installed T-codes. :

[0073] in, As of the date The first measurement batch The number of adjustments that have been implemented for each code; when the first... When an adjustment is not implemented at the end of a code, the sum of the effective correction values ​​is zero. Indicates deducting the first The amount of deviation change within a unit construction distance after the effective correction amount has been implemented for each code.

[0074] The uncorrected deviation refers to the deviation predicted based on the current actual installation state as the prediction starting point, assuming no additional corrections are applied to the T-code to be installed. It is not the assumed deviation obtained after canceling previously implemented corrections. The actual installation position of the previous T-code serves as the starting state for the construction positioning of the subsequent T-code. Therefore, when determining the first... When calculating the uncorrected deviation increment rate at the first code, only the first code is deducted. The individual code itself has already implemented effective corrections.

[0075] Furthermore, in From the previously installed T-codes, select multiple consecutively installed T-codes that belong to the same continuous construction sequence and the same structural response zone as the T-code to be installed. Codes are used to form a bias prediction sample set. T-codes located on the other side of expansion joints, independent support boundaries, construction interruption locations, or other locations where deviation changes are discontinuous are not included in the same deviation prediction sample set.

[0076] Based on the cumulative design distance corresponding to each sample, the deviation prediction sample set is... By performing local linear fitting on the uncorrected deviation increment rate in the data, the uncorrected deviation increment rate near the current construction location can be obtained. and its changing trend along the construction location Preferably, samples that are closer to the current construction location and have a more recent formation time are assigned a larger fitting weight.

[0077] Based on the uncorrected deviation increment rate and its changing trend, predict the first... Uncorrected deviation of a T-code to be installed :

[0078] in, subscript Indicates an uncalibrated state. This refers to the T-code sequence number recursively derived from the prediction starting point towards the T-code to be installed. The numerical value of the uncorrected deviation is represented as the uncorrected deviation prediction value.

[0079] When the effective prediction samples are insufficient to determine the trend of the uncorrected deviation increment rate, the effective uncorrected deviation increment rate closest to the current construction position is used as the constant prediction increment rate for subsequent T-codes to be installed. When no effective uncorrected deviation increment rate exists, uncorrected deviation prediction is paused until at least one set of effective reference state alignment deviations and cumulative design distance data for adjacent installed T-codes is obtained. After obtaining the new reference state alignment deviations, fitting and prediction are performed again.

[0080] Furthermore, based on the target correction command quantity in each construction feedback sample... and effective correction amount Select with the first Construction feedback samples with identical or similar T-code connection structures, adjustment tools, construction conditions, and structural response zones are used to form a local feedback sample set. .

[0081] The ratio between the target correction command and the effective correction is used to characterize the correction implementation relationship, and the first step is determined based on the local feedback sample set. The correction implementation coefficient corresponding to each T-code to be installed :

[0082] in, For the first The first T-code The construction feedback sample formed in the second adjustment is relative to the first... The feedback sample weights are assigned to each T-code to be installed. These feedback sample weights are non-negative and are determined based on the formation time, spatial location, and similarity of construction conditions of the construction feedback samples. At least one target correction command quantity in the local feedback sample set is not zero, and the feedback sample weight corresponding to this target correction command quantity is greater than zero.

[0083] The correction implementation coefficient This represents the proportion of the target correction command quantity converted into an effective correction quantity, the first... The target calibration command quantity of the T-code to be installed The corresponding expected effective correction amount is .

[0084] The correction realization relationship reflects the combined impact of T-code connection structure, adjustment tool transmission error, component local elastic response, and construction operation differences on the effective correction amount. Under normal circumstances, the correction realization coefficient is positive. When the correction realization coefficient is non-positive, below the preset effective coefficient lower limit, or exhibits abnormal changes relative to adjacent measurement batches, the correction realization relationship is determined to be unstable, and the determination of the target correction command amount based on the correction realization relationship is suspended.

[0085] When local feedback samples are insufficient, supplementary construction feedback samples with the same or similar T-code connection structure, adjustment tools, and construction conditions within the same construction section are selected. If a stable correction realization relationship still cannot be formed, new construction feedback data is obtained by implementing small-scale trial corrections. When there are significant differences in the correction realization relationship within different target correction command ranges, correction realization coefficients are determined separately for continuous target correction command ranges to form a segmented correction realization relationship.

[0086] Through the above processing, the uncorrected deviation prediction value of each T-code to be installed is obtained. And the corresponding correction implementation relationship. The uncorrected deviation prediction value is used in S4 to determine the uncorrected deviation and remaining error budget of the terminal position, and the correction implementation relationship is used to subsequently determine the target correction command amount based on the required effective correction amount.

[0087] S4. Subtract the value of the uncorrected deviation at the terminal position from the terminal target deviation to obtain the remaining error budget, and determine the effective correction interval by combining the correction constraints and correction realization relationship, specifically including: Based on the uncorrected deviation prediction values ​​of each T-code to be installed obtained from S3, extract the terminal T-code. In the Uncorrected bias prediction values ​​in each measurement batch and the terminal target deviation determined by S1 Subtracting the uncorrected bias prediction value, we obtain the first... Residual error budget for each measurement batch :

[0088] in, This represents the effective correction amount required for the terminal T-code to reach the terminal target deviation, starting from the current construction state. It uses the same length unit and positive / negative direction as the alignment deviation with the reference state. When... At that time, the terminal position needs to be effectively corrected along the preset correction direction; when At this time, the terminal position needs to be effectively corrected in the opposite direction to the preset correction direction; when At that time, the uncorrected deviation prediction of the terminal position is equal to the terminal target deviation.

[0089] The remaining error budget is not the arithmetic sum of the effective correction values ​​of each T-code to be installed. The effective correction value of each T-code to be installed changes point by point along the construction sequence. The effective correction value formed by the previous T-code serves as the basis for the subsequent T-code to satisfy the allowable variation range of the effective correction values ​​of adjacent T-codes. The effective correction value of the terminal T-code is used to satisfy the remaining error budget.

[0090] Furthermore, obtain the terminal allowable residual determined by S1. ,in, The difference between the deviation after terminal T-code correction and the terminal target deviation satisfies:

[0091] Based on the remaining error budget and terminal allowable residual Determine the remaining error budget interval :

[0092] in, This indicates the range of effective correction amounts allowed by the terminal T-code to satisfy the terminal target deviation and the terminal allowable residual. When At that time, the effective correction amount of the terminal T code is equal to the remaining error budget. ;when At that time, the effective correction amount of the terminal T code is within the remaining error budget interval. Take the value from the inside.

[0093] The terminal allowable residual is only used to limit the allowable deviation to be retained relative to the terminal target deviation after the terminal T-code has been corrected, and does not change the target correction command range, effective correction range, or allowable variation range of the effective correction amount of each T-code to be installed.

[0094] Furthermore, for the first There are 1 T-codes to be installed, among which... Obtain the target correction command range determined by S1. Effective correction range And the correction realization relationship determined by S3. When the first When the calibration implementation relationship of a code to be installed is in proportional form, the target calibration command quantity is... The corresponding expected effective correction amount is ,in, For the first The first T-code to be installed is in the... The calibration implementation coefficient in each measurement batch.

[0095] In correcting the implementation coefficient Under the condition that the value is positive and the correction realization relationship is stable, the target correction command range is mapped to the effective correction range through the correction realization relationship, and the mapping result is intersected with the effective correction range.

[0096] No. Lower limit of effective calibration for each T-code to be installed Determined according to the following formula:

[0097] No. The maximum effective correction amount for each T-code to be installed Determined according to the following formula:

[0098] Based on the effective correction lower limit and the effective correction upper limit, determine the first... Valid correction range for each T-code to be installed :

[0099] in, and The first The effective correction amount lower limit and effective correction amount upper limit that a T-code to be installed can form under the current correction constraints and correction implementation relationship.

[0100] The target correction command range defines the adjustment amount that can be issued and implemented on the construction site; the effective correction range defines the positional change that the T-code can undergo under the conditions of connection structure, allowable adjustment space on site, and continuous installation of roof panels; the correction realization relationship characterizes the correspondence between the target correction command amount and the effective correction amount. Therefore, the effective correction interval is the range of effective correction amounts that the T-code to be installed can use under the current construction conditions.

[0101] when At that time, determine the first Each T-code to be installed has a valid correction range; when If the effective correction range obtained by mapping the target correction command range to the relationship is not duplicated with the effective correction range determined by S1, it is determined that the T code to be installed does not have an effective correction interval.

[0102] When there is no valid correction range for the corresponding T-code to be installed, the determination of the target correction command quantity of the T-code to be installed based on the current correction realization relationship is paused, and the adjustment tool, T-code connection structure or connection status, on-site allowable adjustment space, construction feedback data and correction realization relationship are reviewed.

[0103] when When this occurs, it indicates that within the existing construction feedback sample's target correction instruction range and construction conditions, the target correction instruction has not formed an identifiable effective correction quantity; when When this occurs, it indicates an abnormal directional relationship between the target correction command quantity and the effective correction quantity.

[0104] In cases where the correction realization coefficient is zero or negative, instead of using the current correction realization relationship to determine the effective correction range, the construction status is reviewed or a small-scale trial correction is implemented to re-acquire construction feedback data and determine the correction realization relationship.

[0105] Furthermore, when S3 determines the segmented correction implementation relationship, the intersection of each target correction instruction quantum interval with the target correction instruction range determined by S1 is calculated. The intersection result is mapped to the effective correction domain according to the corresponding segmented correction implementation relationship, and the mapping result is intersected with the effective correction range to obtain the corresponding effective correction sub-interval.

[0106] When the effective correction sub-intervals overlap or their endpoints connect, the corresponding effective correction sub-intervals are merged; when there is an interval between adjacent effective correction sub-intervals that cannot be covered by continuously changing the target correction command amount, the interval is not crossed for merging.

[0107] Under the piecewise correction implementation relationship, the first A valid correction interval for a T-code to be installed can consist of one or more valid correction sub-intervals, and is represented as follows:

[0108] in, For the first The first T-code to be installed One effective correction sub-interval, To effectively correct the number of subintervals. When In this case, the effective correction interval is a single continuous interval. The effective correction interval referred to in this embodiment is a general term for the range of effective correction amounts allowed for the T-code to be installed. When using segmented correction to achieve the relationship, it can consist of multiple mutually separate effective correction sub-intervals.

[0109] This step determines the corresponding effective correction interval based on the target correction command range, effective correction range, and correction implementation relationship of each T-code to be installed. The allowable variation range of the effective correction amount of adjacent T-codes is a coupling constraint between different T-codes and cannot be directly satisfied by determining the effective correction interval of each T-code to be installed separately.

[0110] Therefore, this step does not determine whether the effective correction intervals of each T-code to be installed can form a continuous correction path, nor does it determine the specific effective correction amount of the terminal T-code or the target correction instruction amount of each T-code to be installed in this step.

[0111] Through the above processing, we obtain the first... Residual error budget for each measurement batch Remaining error budget interval and the effective correction range of each T-code to be installed S5 constructs bidirectional reachable correction constraints based on the effective correction interval, remaining error budget, and correction constraints, and determines the target correction command quantity under the bidirectional reachable correction constraints.

[0112] S5. Construct bidirectional reachable correction constraints based on the effective correction interval, remaining error budget, and correction constraints, and determine the target correction command quantity under the bidirectional reachable correction constraints according to the correction realization relationship, specifically including: The first The T-code with the highest serial number that has been installed in the measurement batch. The starting position is determined. The uncorrected bias prediction value obtained by S3 is... The actual installation state is taken as the prediction starting point. The positional changes caused by previous corrections are already included in the actual installation state. Therefore, the candidate effective correction amount of the starting position relative to the uncorrected deviation prediction result of this round is set to zero, and its forward reachable set is set accordingly. Determined as:

[0113] In this step, the variables within the effective correction interval represent the candidate effective correction amounts for each T-code to be installed relative to the uncorrected deviation prediction results of this round; in S3 Indicates the first The first T-code The effective correction amount actually formed by the adjustment is used for the current round of continuous correction path planning and historical construction feedback, respectively.

[0114] Furthermore, starting from the initial position, the forward reachable set of each T-code to be installed is determined sequentially according to the T-code construction order. For the first... There are 1 T-codes to be installed, among which... Based on the forward reachable set of the previous T-code, the effective correction interval of the current T-code to be installed, and the allowable variation range of the effective correction amount of adjacent T-codes determined by S1, the first T-code is determined. A forward reachable set of T-codes to be installed :

[0115] in, This represents the number of candidate effective corrections that can be achieved with the previous T-code. For the first The candidate valid correction values ​​for a T-code to be installed. The forward reachable set represents the set of values ​​obtained after sequentially satisfying the valid correction intervals of each T-code to be installed and the allowable variation ranges of the valid correction values ​​of adjacent T-codes, assuming the starting position remains unchanged and following the T-code construction sequence. The set of candidate effective correction quantities that can be achieved by the T-code to be installed.

[0116] The forward recursion does not distribute the remaining error budget equally among each T-code to be installed. Instead, it uses the candidate effective correction amount that the previous T-code can achieve as a basis to determine point by point whether the next T-code can continuously transition within the allowable range of variation of the effective correction amount of the adjacent T-code.

[0117] Furthermore, starting with the terminal T-code, the backward reachable set of each T-code to be installed is determined sequentially in the reverse direction of the T-code installation sequence. The effective correction range of the terminal T-code is then defined. The remaining error budget interval determined by S4 Find the intersection to obtain the backward reachable set of the terminal T-code. :

[0118] The backward reachable set This represents the set of candidate effective correction quantities that can be used when the terminal T code simultaneously satisfies its effective correction range, terminal target deviation, and terminal allowable residual.

[0119] For the There are 1 T-codes to be installed, among which... Based on the backward reachable set of the next T-code, the effective correction interval of the current T-code to be installed, and the first... The allowable variation range of the effective correction amount of adjacent T-codes corresponding to the first T-code is determined to determine the first T-code. A backward reachable set of T-codes to be installed :

[0120] in, For the first The candidate effective correction values ​​for each T-code that can continuously transition to the remaining error budget interval. The backward reachable set represents the set of T-codes determined in reverse by the terminal position. A set of candidate effective correction quantities for each T-code to be installed, which can be continuously transitioned to the remaining error budget interval by subsequent T-codes to be installed.

[0121] The forward reachable set is used to exclude candidate valid correction quantities that cannot be continuously reached from the current actual construction state, while the backward reachable set is used to exclude candidate valid correction quantities that cannot be continuously transitioned to the remaining error budget interval through subsequent T-codes to be installed.

[0122] Furthermore, the first Find the intersection of the forward reachable set and the backward reachable set of each T-code to be installed to obtain the corresponding bidirectional reachable set. :

[0123] The bidirectional reachable set represents a set of candidate effective correction quantities that can be continuously reached from the current actual construction state via the preceding T-codes to be installed, and can also be continuously transitioned to the remaining error budget interval via the subsequent T-codes to be installed.

[0124] The bidirectional reachability set of each T-code to be installed, the allowable variation range of the effective correction values ​​of adjacent T-codes, and the remaining error budget interval together constitute the bidirectional reachability correction constraint. Under the bidirectional reachability correction constraint, the candidate effective correction values ​​of each T-code to be installed are located within the corresponding bidirectional reachability set, the difference between the candidate effective correction values ​​of adjacent T-codes is located within the corresponding allowable variation range, and the candidate effective correction values ​​of the terminal T-code are located within the remaining error budget interval.

[0125] When the terminal If the backward reachable set of the code is empty, or if the bidirectional reachable set of any T-code to be installed is empty, it is determined that there is no complete continuous correction path within the current effective correction interval, the remaining error budget, and the allowable variation range of the effective correction amount of adjacent T-codes. The determination of the target correction command amount is paused, and the uncorrected deviation prediction value, correction realization relationship, effective correction interval, and on-site allowable adjustment conditions are reviewed.

[0126] Furthermore, assuming that the bidirectional reachability sets of each T-code to be installed are not empty, the target effective correction amount of each T-code to be installed is determined according to the T-code construction sequence. Based on the... The ratio of the cumulative design distance between the T-code to be installed and the starting position to the cumulative design distance between the terminal position and the starting position, along with the remaining error budget, is used to determine the reference effective correction amount. :

[0127] in, and The first The number of T-codes to be installed, the starting position, and the cumulative design distance of the terminal T-codes relative to the starting point of the construction section, and .

[0128] The reference effective correction value is only used as a reference value for selecting the target effective correction value from the bidirectional reachability set and does not constitute an independent constraint; when the reference effective correction value is inconsistent with the bidirectional reachability correction constraint, the bidirectional reachability correction constraint shall prevail.

[0129] The effective correction amount of the target corresponding to the starting position Setting it to zero serves as the initial value for the recursive calculation of the continuous correction path in this round, and does not imply re-correction of T-codes whose positions have already been fixed. For the th For each T-code to be installed, a candidate selection set is determined based on the target effective correction value of the previous T-code, the allowable variation range of the effective correction values ​​of adjacent T-codes, and the bidirectional reachability set of the current T-code to be installed. :

[0130] From the candidate selection set, select the candidate effective correction quantity with the smallest absolute difference from the corresponding reference effective correction quantity, and use it as the first... The target effective correction amount of the T-code to be installed :

[0131] When multiple candidate effective correction quantities exist with the same absolute difference from the reference effective correction quantity, the candidate effective correction quantity with the smaller absolute difference from the target effective correction quantity of the previous T code is preferred. Other selection methods can also be used to determine the target effective correction quantity from the candidate selection set, but the obtained target effective correction quantity will continue to satisfy the bidirectional reachability correction constraint.

[0132] Furthermore, based on the correction implementation relationship determined in S3, the target effective correction amount of each T-code to be installed is converted into a target correction command amount. When the... When the calibration implementation relationship of a T-code to be installed is in proportional form, its target calibration command quantity Determined according to the following formula:

[0133] in, The target correction command quantity is verified for range; when the target correction command quantity is within the range of the target correction command quantity determined in S1, the target correction command quantity is determined; when the verification fails, the target correction command quantity is not issued, and the corresponding effective correction interval and correction implementation relationship are reviewed.

[0134] When S3 determines a segmented correction implementation relationship, the corresponding target correction instruction quantum interval and correction implementation relationship are determined based on the effective correction sub-interval to which the target effective correction amount belongs, and the target correction instruction amount is calculated inversely within the target correction instruction quantum interval. When the same target effective correction amount corresponds to multiple target correction instruction amounts, the target correction instruction amount with the smaller absolute value is selected first.

[0135] When the correction achievement coefficient is positive, the target correction command and the target effective correction have the same positive and negative directions. When the remaining error budget is negative, the target effective correction and the target correction command can be negative, and the negative sign indicates that the position adjustment is performed in the opposite direction of the preset correction direction.

[0136] Through the above processing, the target effective correction amount of each T-code to be installed is obtained. and target correction command quantity The target correction command quantity is used by S6 to generate the correction lofting coordinates corresponding to the T-code to be installed.

[0137] S6. Generate the calibration layout coordinates of the T-code to be installed based on the target calibration command quantity, and update the target calibration command quantity and calibration layout coordinates based on the T-code measurement data and construction feedback data obtained after construction according to the calibration layout coordinates, specifically including: According to the Preset correction direction vector for each T-code to be installed Determine the corresponding unit correction direction vector :

[0138] in, It is a non-zero vector. It is used to uniformly represent the positive and negative directions of the target correction command quantity, the uncorrected deviation prediction value, and the effective correction quantity.

[0139] According to S3, the first The first T-code to be installed is in the... Uncorrected bias prediction values ​​in each measurement batch The design coordinates of the T-code to be installed Adding the displacement formed by the predicted uncorrected deviation value along the unit correction direction vector yields the predicted uncorrected reference coordinates within the reference coordinate frame. :

[0140] The predicted uncorrected reference coordinates represent the coordinates of the first, second, and third predictions without implementing any new corrections in this round. The coordinate positions of the T-code to be installed are expected to be formed in the reference state; the coordinate components orthogonal to the preset correction direction maintain the corresponding design coordinate components.

[0141] Furthermore, based on the target correction command quantity determined by S5 The reversible displacement of the support structure determined by S2 The predicted uncorrected reference coordinates, the displacement formed by the target correction command along the unit correction direction vector, and the reversible displacement of the support structure are added together to obtain the first... The calibration and layout coordinates of the T-code to be installed within the reference coordinate frame. :

[0142] Among them, the target correction command quantity This represents the amount of construction adjustment implemented relative to the predicted uncorrected reference coordinates along the preset correction direction; a positive value indicates positional adjustment along the preset correction direction, while a negative value indicates positional adjustment in the opposite direction. Reversible displacement of the supporting structure. Used to convert the correction target in the reference state into a coordinate position that matches the actual state of the support structure during layout.

[0143] The calibration and layout coordinates are the construction control coordinates for implementing the target calibration command quantity, and are not equivalent to the final reference state coordinates after the T-weights are fixed in position. Due to the influence of the T-weight connection structure and connection state, disturbances during the position fixing process, transmission errors of the adjustment tools, and local elastic recovery of the components, the actual effective calibration quantity corresponding to the target calibration command quantity may differ from the target calibration command quantity. This difference is based on the coordinates obtained after the position is fixed. The code measurement data and construction feedback data were determined.

[0144] Furthermore, when the space measurement equipment uses the field measurement coordinate frame for layout, the rotation matrix determined by S2 is used... Translation vector The calibration layout coordinates under the reference coordinate frame are converted into calibration layout coordinates under the field measurement coordinate frame. :

[0145] Wherein, rotation matrix Translation vector Used to transform field measurement coordinates to a reference coordinate frame; due to For rotation matrix, Since this is its inverse matrix, the aforementioned inverse transformation is used to determine the corrected layout coordinates under the field measurement coordinate frame. When the space measurement equipment directly uses the aforementioned reference coordinate frame for layout, the corrected layout coordinates under the reference coordinate frame are directly used. .

[0146] When only the spatial measurement equipment is reset or the field measurement coordinate frame changes, and the uncorrected deviation prediction value, the reversible displacement of the support structure, and the target correction command value remain unchanged, the correction and layout coordinates under the reference coordinate frame remain unchanged, and the correction and layout coordinates under the field measurement coordinate frame are updated according to the newly determined measurement reference transformation parameters.

[0147] When changes occur in the uncorrected deviation prediction value, the reversible displacement of the supporting structure, the correction constraint, or the target correction command, resulting in a change in the correction target, the correction layout coordinates under the reference coordinate frame are regenerated, and the correction layout coordinates under the field measurement coordinate frame are updated accordingly. If the re-measurement before layout shows that the magnitude of the change in the reversible displacement vector of the supporting structure exceeds the construction layout tolerance, the reversible displacement of the supporting structure is re-determined, and the corresponding correction layout coordinates are updated.

[0148] Furthermore, the number of the T-code to be installed, the target correction instruction quantity, the correction layout coordinates under the reference coordinate frame, the correction layout coordinates under the field measurement coordinate frame, and the corresponding measurement batch are associated and recorded. The correction layout coordinates corresponding to the coordinate frame used by the spatial measurement equipment are then input into the construction layout terminal.

[0149] Construction workers use adjustment tools to temporarily position and adjust the T-code to be installed according to the corrected layout coordinates. When the coordinate deviation between the temporary position of the T-code and the corrected layout coordinates does not exceed the construction layout tolerance, the position of the T-code is fixed, and the measurement data of the T-code is reacquired after the position is fixed. The construction layout tolerance is determined based on the measurement accuracy of the spatial measuring equipment, the installation accuracy of the T-code, and the continuous installation requirements of the roof panels.

[0150] Furthermore, after one or more T-codes have been fixed in position, the first... Each measurement batch acquires the spatial coordinates of the fixed T-weights, external stable control points, and supporting structure servo reference points, and records each... The actual amount of target correction instructions issued by the code. For adjustments before and after... Code measurement data code, will Code number, actual target correction command quantity issued, before and after adjustment The code measurement data and the corresponding measurement batch association records are used to form new construction feedback data.

[0151] For the The T-code measurement data obtained from each measurement batch are corrected for measurement reference changes and reversible displacement of the support structure to obtain the reference state alignment deviation of the corresponding T-code; the actual effective correction amount is determined based on the reference state alignment deviation before and after adjustment, and the actual effective correction amount and the corresponding actual target correction command amount are used to form a construction feedback sample to update the correction realization relationship.

[0152] When the quasi-static displacement reference value is redefined and the reference state reference used for the reference state alignment deviation changes, the confirmation time of the new quasi-static displacement reference value is used as the boundary of the deviation prediction sample. Only the reference state alignment deviation formed after the confirmation time is used to determine the new uncorrected deviation increment rate and its trend.

[0153] Before adjustment in the same construction feedback sample Code measurement data and adjustments When the code measurement data can be corrected using the same quasi-static displacement reference value, the construction feedback sample is used to update the correction relationship; when the T-code measurement data before and after adjustment cannot be corrected using the same quasi-static displacement reference value, the corresponding data is not used as a valid construction feedback sample.

[0154] Furthermore, the first Among the measurement batches, the T-code with the largest fixed position and sequence number is denoted as... The actual installation status of the T-code is then used as the new prediction starting point.

[0155] When the site allows for space adjustments, When changes occur in the code connection structure or connection status, adjustment tools, continuous installation conditions of roof panels, roof panel closure requirements, or connection requirements between adjacent construction sections, the correction constraints must be reconfirmed. Based on the changed construction conditions, the target correction command range, effective correction range, allowable variation range of effective correction amounts for adjacent T-codes, and allowable terminal residuals corresponding to the remaining T-codes to be installed must be redefined; correction constraints unaffected by the changes in construction conditions remain unchanged.

[0156] Based on the updated T-code measurement data, construction feedback data, and correction constraints, S3 to S5 are executed again to update the uncorrected deviation, remaining error budget, effective correction range, bidirectional reachable correction constraints, target effective correction amount, and target correction command amount of the remaining T-codes to be installed. The correction layout coordinates of the remaining T-codes to be installed are then regenerated based on the updated target correction command amount.

[0157] The updated target correction command quantities and correction stakeout coordinates only apply to T-weights whose positions have not yet been fixed. When S3 to S5 are re-executed and cause a change in the correction target under the reference coordinate frame, the correction stakeout coordinates of the remaining T-weights to be installed in the previous measurement batch are marked as invalid. When only the field measurement coordinate transformation relationship is updated, the correction stakeout coordinates under the reference coordinate frame remain valid, and only the correction stakeout coordinates under the original field measurement coordinate frame are marked as invalid. During construction, the valid correction stakeout coordinates corresponding to the current measurement batch are used.

[0158] When the updated correction realization relationship is determined to be unstable, or when the reconstructed bidirectional reachable correction constraint does not have a complete and continuous correction path, the determination of new target correction command quantity and the generation of new correction layout coordinates are paused, and the construction feedback data, correction constraints and on-site construction conditions are reviewed.

[0159] Furthermore, after the terminal T-code is fixed in position, the terminal T-code is determined in the terminal measurement batch according to the processing procedure described in S2. The final reference state alignment deviation When the following conditions are met: At that time, it is determined that the construction section meets the requirements of terminal target deviation and terminal allowable residual.

[0160] When the final reference state alignment deviation of the terminal T-code does not meet the above conditions, the automatic update of the target correction command quantity and correction lofting coordinates is paused, and the cause of the deviation is reviewed. For T-codes that still meet the position adjustment conditions after review, after releasing or adjusting their position fixed state, they are re-identified as T-codes to be installed, and the corresponding correction constraints are reconfirmed; if there are no T-codes that meet the position adjustment conditions, the process is transferred to manual review and rework.

[0161] Through the above processing, the target correction command quantity is converted into correction and layout coordinates that can be executed on the construction site. Based on the T-code measurement data and construction feedback data obtained after the position is fixed, the target correction command quantity and correction and layout coordinates of the remaining T-codes to be installed are continuously updated, thereby forming a closed-loop adaptive correction throughout the continuous installation process of T-codes.

[0162] Example 2 I. Experiment Preparation and Implementation Process This embodiment sets up eight independent test sections for the continuous installation of T-codes for metal roof supports. Each test section uses steel purlins of the same specifications, T-code connection structures, fasteners, and simulated roof panel connectors. The number of T-codes ranges from 27 to 34, and the length of the construction section ranges from 47.1 meters to 59.6 meters. The eight test sections are divided into four groups according to environmental and construction disturbance conditions. Each group includes one test section using the method of this invention and one control section using the conventional point-by-point correction method.

[0163] In this test, section A and control section E were constructed under normal temperature conditions and without significant temporary loads. Section B and control section F were constructed under conditions of rising temperatures due to sunlight, causing reversible displacement of the supporting structure that changes with temperature. Section C and control section G had temporary loads placed in the middle of the construction area to simulate temporary structural displacement caused by concentrated loads from roof panels, tools, and construction personnel. In section D and control section H, the spatial measurement equipment stations were reset during installation to simulate changes in the on-site measurement coordinate frame. The spatial measurement equipment had an angle measurement accuracy of 1 second and a distance measurement accuracy of 1 millimeter plus one millionth of the distance value. Four external stability control points were set up around each test section, and four to six supporting structure follow-up reference points were set up along the supporting structure.

[0164] Before construction begins, benchmark measurements are completed under conditions of no temporary load and stable support structure. The benchmark coordinates of external stability control points and reference coordinates of support structure follow-up reference points are recorded, and initial quasi-static displacement benchmark values ​​are established.

[0165] The terminal target deviation of each test section is set to zero, and the terminal residual is allowed to be ±2.0 mm. The range of target correction command quantity is determined based on the travel of the adjustment tool and the allowable displacement of the T-code connection part. The allowable variation range of the effective correction quantity of adjacent T-codes is determined based on the requirements for continuous installation and smooth connection of the roof panel.

[0166] The four test sections using the method of the present invention are established as a measurement batch after every four to six T-codes are completed, and the spatial coordinates of the installed T-codes, external stable control points and support structure follow-up reference points are acquired simultaneously.

[0167] First, the measurement reference change is corrected using external stable control points. Then, the reversible displacement of the support structure is identified and deducted based on the follow-up reference point of the support structure to obtain the reference state alignment deviation of each installed T-code.

[0168] The uncorrected deviation variation pattern is determined based on the reference state alignment deviation of adjacent installed T-codes and the effective correction amount already implemented, and the deviation of the remaining T-codes to be installed is predicted without implementing additional corrections.

[0169] For T-codes that have already been adjusted, record the actual target correction command quantity and the measurement data before and after the adjustment, determine the effective correction quantity, and update the correction realization relationship between the target correction command quantity and the effective correction quantity accordingly.

[0170] Subsequently, the remaining error budget is determined based on the uncorrected deviation of the terminal position and the terminal target deviation. The target correction command range is mapped to the effective correction interval, and forward and backward reachability analysis is performed in combination with the allowable variation range of the effective correction amount of adjacent T codes.

[0171] The corresponding target correction command quantity and correction layout coordinates are determined only when each T-code to be installed has a complete correction path that continuously reaches the terminal target from the current construction position. After the position of each batch of T-codes is fixed, the measurement data is reacquired and the target correction command quantity and correction layout coordinates of the remaining T-codes to be installed are updated.

[0172] The four comparison sections adopt a point-by-point adjustment method that directly compares the conventional design coordinates with the original measured coordinates. They do not separately identify changes in the measurement benchmark and reversible displacement of the supporting structure, do not establish a correction realization relationship based on construction feedback data, and do not conduct bidirectional reachability analysis on the terminal remaining error budget and the continuous transition of adjacent T-codes.

[0173] After the initial layout of the control section, new calibration layout coordinates are not automatically generated. If installation deviations or failure to meet terminal closure requirements occur, construction personnel will manually adjust the local T-codes based on the re-measurement results. After each test section is completed, the following statistics are compiled: the amount of non-installation displacement mistakenly included in the calibration, the average absolute difference between the target calibration command and the effective calibration, the change in the maximum adjacent effective calibration, the number of T-codes adjusted, the terminal residual, and the total calibration time.

[0174] Table 1: Verification data of adaptive correction for cumulative deviation of T-codes in metal roofing supports, Example 2

[0175] III. Data Analysis As shown in Table 1, the number of T-codes, the length of the construction section, and the initial terminal deviation of the test section and the control section of this invention are within a similar range and are basically comparable. The average corrected terminal residual of the four test sections of this invention is 1.275 mm, while the average corrected terminal residual of the control section is 8.700 mm, with the former being approximately 85.3% lower than the latter.

[0176] The terminal residuals of the four test sections of this invention were all less than the preset allowable terminal residual of 2.0 mm, and all passed the terminal closure acceptance on the first attempt; the terminal residuals of the four control sections all exceeded the allowable range.

[0177] The results show that simply adjusting the original coordinate deviation of the current T-code point by point cannot guarantee that the local adjustment results will be continuously transmitted to the terminal position along the construction sequence. However, the present invention incorporates the current actual construction status, the feasible correction range of each T-code to be installed, the continuous transition requirements of adjacent T-codes, and the terminal closure target into the same correction path through the residual error budget and bidirectional reachability correction constraints.

[0178] Regarding changes in the measurement benchmark and supporting structure condition, the average non-installation displacement error correction amount for the test section of this invention was 0.55 mm, while the average for the control section was 5.55 mm, a reduction of approximately 90.1%. Specifically, test section B under solar radiation heating conditions and test section C under temporary loading conditions exhibited peak reversible displacement values ​​of 5.4 mm and 6.3 mm for the supporting structure, respectively, but their non-installation displacement error correction amounts were only 0.6 mm and 0.7 mm, respectively; the corresponding control sections F and G reached 6.1 mm and 7.2 mm, respectively.

[0179] This comparison demonstrates that using external stable control points to correct changes in the measurement coordinate frame and using the supporting structure's follow-up reference points to identify temporary structural displacements can avoid converting displacement errors caused by resetting the measurement equipment, temperature deformation, and temporary construction loads into permanent T-code adjustments. Particularly under station resetting conditions, although the measurement reference change amplitude in test section D of this invention reached 4.1 mm, the terminal residual was still controlled at 0.9 mm, while the terminal residual in control section H was 7.9 mm, highlighting the necessity of separating the reference coordinate frame from the on-site measurement coordinate frame.

[0180] In the test section of this invention, the average absolute difference between the target correction command and the effective correction was 1.025 mm, compared to 4.350 mm in the control section, a reduction of approximately 76.4%. This indicates that continuously determining and updating the correction realization relationship based on actual construction feedback data can compensate for the inconsistency between the command and actual displacement caused by T-code connection structure, adjustment tool transmission errors, positional disturbances, and local elastic recovery. The correction realization coefficient of test section C under temporary surcharge conditions was relatively low, with an average absolute difference of 1.3 mm between the command and effective correction, but still significantly less than the 5.2 mm of the corresponding control section G. This suggests that the method does not assume that construction adjustments can be fully realized according to the command, but rather adaptively identifies the actual realization capability through on-site feedback.

[0181] The average change in the maximum adjacent effective correction amount in the test section of this invention was 2.275 mm, while that in the control section was 6.400 mm, a reduction of approximately 64.5%. The controlled change in adjacent effective correction amounts indicates that the forward reachable set and the backward reachable set can simultaneously exclude candidate correction amounts that cannot be continuously reached from the current construction state or cannot continue to transition to the terminal target, thus avoiding the concentration of correction amounts on a few adjacent T-codes.

[0182] Correspondingly, the average number of T-codes for recalibration in the test section of this invention was 2.75, compared to 10.25 in the control section, a reduction of approximately 73.2%; the average total calibration time was reduced from 140 minutes to 95.5 minutes, a reduction of approximately 31.8%. Although the test section of this invention requires three to four calibration and layout coordinate updates, this update is an orderly closed-loop update based on measurement data and construction feedback data, which actually reduces subsequent unplanned manual recalibration and terminal rework.

[0183] Therefore, the data in this embodiment can corroborate the following technical effects: Firstly, the changes in the measurement reference, the reversible displacement of the support structure, and the installation deviation of the T-code are separated to improve the reliability of deviation identification. Secondly, the correction implementation relationship is determined based on construction feedback data to ensure that the target correction command quantity matches the actual adjustment capacity on site; Third, the effective correction interval and bidirectional reachability correction constraint are used to control the continuous transition of adjacent T codes and bring the terminal deviation into the allowable range; Fourth, by measuring the batch update target correction command quantity and correction layout coordinates, a closed-loop adaptive correction is formed throughout the continuous installation process.

[0184] The technical features of this invention not described can be implemented by or using existing technology, and will not be repeated here. Of course, the above description is not a limitation of this invention, and this invention is not limited to the examples above. Any changes, modifications, additions or substitutions made by those skilled in the art within the scope of this invention should also be within the protection scope of this invention.

Claims

1. An adaptive correction method for the cumulative deviation of T-codes in metal roof supports, characterized in that, include: S1. Determine the deviation between the T-code to be installed and the terminal target, and obtain T-code measurement data, construction feedback data and correction constraints; S2. Based on the T-code measurement data, perform measurement reference change correction and support structure reversible displacement correction to obtain the reference state alignment deviation; S3. Predict the uncorrected deviation of the T-code to be installed based on the alignment deviation of the reference state, and determine the correction realization relationship based on the construction feedback data; S4. Subtract the value of the uncorrected deviation at the terminal position from the terminal target deviation to obtain the remaining error budget, and determine the effective correction interval by combining the correction constraint and correction realization relationship; S5. Construct bidirectional reachable correction constraints based on the effective correction interval, remaining error budget, and correction constraints, and determine the target correction command quantity under the bidirectional reachable correction constraints based on the correction realization relationship; S6. Generate the calibration layout coordinates of the T-code to be installed according to the target calibration command quantity, and update the target calibration command quantity and calibration layout coordinates according to the T-code measurement data and construction feedback data obtained after construction according to the calibration layout coordinates.

2. The adaptive correction method for cumulative deviation of metal roof support T-codes according to claim 1, characterized in that, Step S1 includes: Based on the metal roofing design documents and on-site construction records, the T-codes that have not yet been installed and whose installation positions have not yet been fixed within the construction section are identified as T-codes to be installed, and the T-codes at the terminal positions are identified as terminal T-codes. Based on the roof panel closure requirements and the connection requirements of adjacent construction sections, the target coordinates and preset correction direction of the terminal T-code are determined, and the coordinate difference obtained by subtracting the design coordinates of the terminal T-code from the target coordinates is projected along the preset correction direction to obtain the terminal target deviation. The spatial coordinates of the installed T-codes, external stable control points, and support structure follow-up reference points are acquired in batches to form T-code measurement data. By associating the T-code number, target correction instruction quantity, T-code measurement data before and after adjustment, and measurement batch, construction feedback data is formed. Based on the T-code connection structure, the allowable adjustment space on site, the adjustment capability of the adjustment tools, and the roof panel installation requirements, the correction constraints are determined, including the target correction command range, the effective correction range, the allowable variation range of the effective correction of adjacent T-codes, and the allowable residual at the terminal.

3. The adaptive correction method for cumulative deviation of metal roof support T-codes according to claim 1, characterized in that, Step S2 includes: The measurement reference transformation parameters are determined based on the reference coordinates and measured coordinates of at least three non-collinear external stable control points, and the measured coordinates of the installed T-codes and the follow-up reference points of the support structure are corrected for measurement reference changes. The coordinates of the support structure follower reference point after the measurement benchmark change correction are compared with its reference coordinates to determine the total displacement of the support structure; the quasi-static displacement benchmark value is determined based on the coordinates of the support structure follower reference point in the restored state, and the difference between the total displacement of the support structure and the quasi-static displacement benchmark value is determined as the reversible displacement of the support structure. Select a support structure follow-up reference point located in the same structural response partition as the corresponding T-code, and determine the reversible displacement of the support structure at the location of the T-code by interpolation based on its spatial position relationship with the corresponding T-code. The coordinate difference between the T-code coordinates after the measurement reference change correction is obtained by subtracting the reversible displacement of the support structure at the location of the T-code, and then projecting the coordinate difference obtained by subtracting the design coordinates of the corresponding T-code along the preset correction direction of the corresponding T-code to obtain the reference state alignment deviation.

4. The adaptive correction method for cumulative deviation of metal roof support T-codes according to claim 1, characterized in that, In step S3, predicting the uncorrected deviation of the T-code to be installed based on the alignment deviation of the reference state includes: The T-code with the largest serial number that has been installed in the current measurement batch is determined as the prediction starting point. The uncorrected deviation increment rate is determined based on the reference state alignment deviation of adjacent installed T-codes, the effective correction amount already implemented by the installed T-code with the larger serial number, and the cumulative design distance difference between adjacent installed T-codes. Before the prediction starting point, select multiple consecutive installed T-codes that belong to the same continuous construction sequence and the same structural response zone as the T-code to be installed, form a deviation prediction sample set, and determine the uncorrected deviation increment rate of the current construction position and its changing trend along the construction position based on the deviation prediction sample set. Starting from the actual installation status of the predicted starting point, and based on the uncorrected deviation increment rate, the changing trend, and the cumulative design distance of each T-code to be installed, the uncorrected deviation of each T-code to be installed is predicted according to the T-code construction sequence.

5. The adaptive correction method for cumulative deviation of metal roof support T-codes according to claim 1, characterized in that, In step S3, the correction implementation relationship is determined based on the construction feedback data, including: The measurement reference change correction and the reversible displacement correction of the supporting structure are respectively applied to the T-code measurement data before and after the adjustment in the construction feedback data, so that the T-code measurement data before and after the adjustment are unified to the same reference state, and the effective correction amount is determined according to the alignment deviation of the reference state before and after the adjustment. From the construction feedback data, select construction feedback data that have the same or similar T-code connection structure, adjustment tools, construction conditions and structural response zones as the T-code to be installed, and form a local feedback sample set; Based on the corresponding target correction command quantity and effective correction quantity in the local feedback sample set, determine the correction realization relationship of converting the target correction command quantity into the effective correction quantity; When there are significant differences in the correction implementation relationship corresponding to different target correction command quantity intervals, the correction implementation relationship corresponding to each target correction command quantity interval is determined separately; when the correction implementation relationship is unstable, the determination of the target correction command quantity based on the correction implementation relationship is suspended, and a small-scale trial correction is implemented to obtain new construction feedback data.

6. The adaptive correction method for cumulative deviation of T-codes in metal roof supports according to claim 1, characterized in that, Step S4 includes: Subtract the value of the uncorrected deviation at the terminal position from the terminal target deviation to obtain the remaining error budget, and determine the remaining error budget interval based on the remaining error budget and the terminal allowable residual in the correction constraint; For each T-code to be installed, under the condition that the correction realization relationship is stable, the target correction command range in the correction constraint is mapped to the effective correction range through the correction realization relationship, and the mapping result is intersected with the effective correction range in the correction constraint to determine the effective correction interval of the corresponding T-code to be installed. When the correction implementation relationship is a segmented correction implementation relationship, each target correction instruction quantum interval is mapped to the effective correction domain, and the intersection of the obtained effective correction sub-intervals with the effective correction range is calculated. Effective correction sub-intervals that overlap or have their endpoints connected are merged. When the mapping result does not overlap with the effective correction range, it is determined that there is no effective correction interval for the corresponding T-code to be installed, and the determination of the target correction instruction amount of the T-code to be installed based on the current correction implementation relationship is paused.

7. The adaptive correction method for cumulative deviation of metal roof support T-codes according to claim 6, characterized in that, In step S5, a bidirectional reachable correction constraint is constructed based on the effective correction interval, the remaining error budget, and the correction constraint, including: The T-code with the largest serial number that has been installed in the current measurement batch is determined as the starting position, and the candidate effective correction value of the starting position is set to zero. Based on the forward reachable set of the previous T-code, the effective correction interval of the current T-code to be installed, and the allowable variation range of the effective correction amount of adjacent T-codes, the forward reachable set of each T-code to be installed is determined sequentially according to the T-code construction sequence. The effective correction interval of the T-code to be installed located at the terminal position is intersected with the remaining error budget interval to determine the backward reachable set of the T-code to be installed. Based on the backward reachable set of the next T-code, the effective correction interval of the current T-code to be installed, and the allowable variation range of the effective correction amount of the adjacent T-codes, the backward reachable sets of the remaining T-codes to be installed are determined in the opposite direction of the T-code construction sequence. The intersection of the forward reachable set and the backward reachable set of each T-code to be installed is obtained to determine the corresponding bidirectional reachable set. The bidirectional reachable set of each T-code to be installed, the allowable variation range of the effective correction amount of adjacent T-codes, and the remaining error budget interval together constitute the bidirectional reachable correction constraint.

8. The adaptive correction method for cumulative deviation of T-codes in metal roof supports according to claim 7, characterized in that, In step S5, determining the target correction command quantity based on the correction realization relationship under the bidirectional reachability correction constraint includes: The reference effective correction amount for each T-code to be installed is determined based on the ratio of the cumulative design distance between each T-code to be installed and the starting position to the cumulative design distance between the terminal position and the starting position, and the remaining error budget. According to the T-code construction sequence, based on the target effective correction amount of the previous T-code, the allowable variation range of the effective correction amount of adjacent T-codes, and the bidirectional reachable set of the current T-code to be installed, a candidate selection set for the current T-code to be installed is determined, and the candidate effective correction amount with the smallest absolute difference from the corresponding reference effective correction amount is selected from the candidate selection set as the target effective correction amount. Based on the correction implementation relationship, the target effective correction amount is converted into a target correction instruction amount, and it is verified whether the target correction instruction amount is within the corresponding target correction instruction amount range; When the correction implementation relationship is a segmented correction implementation relationship, the target correction instruction quantity is determined in the corresponding target correction instruction quantum interval according to the effective correction sub-interval to which the target effective correction quantity belongs.

9. The adaptive correction method for cumulative deviation of T-codes in metal roof supports according to claim 1, characterized in that, In step S6, generating the calibration lofting coordinates of the T-code to be installed according to the target calibration command quantity includes: The unit correction direction vector is determined according to the preset correction direction of each T-code to be installed. The design coordinates of each T-code to be installed and the displacement formed by its uncorrected deviation along the unit correction direction vector are added to obtain the predicted uncorrected reference coordinates. The predicted uncorrected reference coordinates, the displacement formed by the target correction command along the unit correction direction vector and the reversible displacement of the support structure are added to obtain the correction layout coordinates under the reference coordinate frame. When the space measurement equipment adopts the field measurement coordinate frame, the correction layout coordinates under the reference coordinate frame are converted into the correction layout coordinates under the field measurement coordinate frame according to the measurement reference transformation parameters. Input the corrected layout coordinates corresponding to the coordinate frame used by the spatial measurement equipment into the construction layout terminal, perform temporary positioning and position adjustment of the T-code to be installed, and complete the position fixation after the temporary positioning deviation does not exceed the construction layout tolerance.

10. The adaptive correction method for cumulative deviation of T-codes in metal roof supports according to claim 9, characterized in that, In step S6, based on the T-code measurement data and construction feedback data obtained after construction according to the corrected layout coordinates, the target correction command quantity and the corrected layout coordinates are updated, including: After one or more T-codes are fixed in position, a new measurement batch is established to obtain T-code measurement data. The actual amount of target correction command issued is associated with the T-code measurement data before and after adjustment to form construction feedback data. The T-code measurement data is corrected for measurement reference change and reversible displacement of support structure to obtain reference state alignment deviation. The effective correction amount is determined based on the reference state alignment deviation before and after adjustment, and the correction realization relationship is updated. The T-code with the largest serial number that has been installed in the measurement batch is determined as the prediction starting point; when the space allowed for adjustment, the T-code connection structure, the adjustment tools, or the continuous installation conditions of the roof panels change, the correction constraints are reconfirmed. Based on the updated T-code measurement data, construction feedback data, and correction constraints, update the uncorrected deviation, remaining error budget, effective correction range, bidirectional reachable correction constraints, and target correction command quantity of the remaining T-codes to be installed, and regenerate the correction layout coordinates of the remaining T-codes to be installed.