A method, apparatus, equipment, and medium for generating energy-saving outsourcing solutions for public institutions.

By automatically matching a pre-set energy-saving measures library and an energy consumption decomposition tree, the problem of excessive upfront investment in public institution energy management projects has been solved. This has enabled the automated generation of energy-saving solutions and investment decision support, reducing the need for specialized personnel.

CN123118300APending Publication Date: 2026-11-17QINGDAO FEIYI ENERGY TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611345418.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-01
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In existing technologies, energy management projects for public institutions involve significant differences in building specifications and equipment, leading to excessive upfront investment in detailed research and design schemes, and making it difficult for general contractors to make investment decisions.

Method used

By pre-setting a library of energy-saving measures, an energy consumption decomposition tree is constructed, and energy-saving measures that meet the trigger conditions are automatically matched. Combined with energy consumption baseline calculation and investment payback period calculation, an energy-saving management plan is generated.

Benefits of technology

It enables the automated generation of energy-saving solutions, reduces upfront investment, decreases reliance on specialized personnel, improves the convenience of solution output and the feasibility of investment decisions, and prevents the risk of failing to meet energy-saving standards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123118300A_ABST
    Figure CN123118300A_ABST
Patent Text Reader

Abstract

This invention relates to the field of energy management technology, and particularly to a method, apparatus, equipment, and medium for generating energy-saving management schemes for public institutions. The method includes: S1, constructing an energy-saving measure library; S2, conducting on-site surveys and collecting information for each public institution under the management contract; S3, obtaining the breakdown of electricity consumption at each energy consumption node based on the energy consumption bill information collected in step S2, thereby completing the energy consumption baseline calculation; S4, traversing all energy-saving measures and matching those that meet the triggering conditions; S5, calculating the energy-saving rate of the energy consumption node; S6, calculating the investment and payback period; and S7, outputting the energy-saving management scheme. This invention pre-sets several energy-saving measures, enabling them to carry triggering conditions, the affected energy consumption nodes and their energy-saving rates, investment, and annual operation and maintenance cost changes. After obtaining on-site survey data, based on the energy-saving measure library, it can support a fully automated link of "survey data → measure matching → investment / return calculation → scheme output," which is beneficial for the general contractor of the management system to make investment decisions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of energy management technology, and in particular to a method, apparatus, equipment and medium for generating energy management schemes for public institutions. Background Technology

[0002] Currently, energy cost management contracts (EMCs) are being adopted by public institutions, often using a county-wide management model (a single package may contain dozens or even hundreds of projects). As a supplier in the air conditioning and communication control field, we position ourselves as a technical subcontractor for the EMC general contractor, providing "survey-solution" technical services. However, each project has different building, usage, and equipment specifications. Conducting detailed surveys and design schemes would result in excessively high upfront investment, making it impractical and inconvenient for the EMC general contractor to make investment decisions. Summary of the Invention

[0003] The purpose of this invention is to provide a method, apparatus, equipment, and medium for generating energy-saving management schemes for public institutions, thereby addressing the problems existing in the prior art. To achieve the above objective, this invention provides the following technical solution:

[0004] In a first aspect, the present invention provides a method for generating energy-saving outsourcing solutions for public institutions, comprising the following steps:

[0005] S1. For different operating conditions, pre-set several energy-saving measures, determine the triggering conditions of each measure, the energy consumption nodes it affects, its energy-saving rate, investment, and annual operation and maintenance cost changes, and build an energy-saving measure library;

[0006] S2. Conduct on-site inspections and collect information for each public institution under the trusteeship contract. The collected information includes basic project overview, energy consumption bills, cold and heat sources, transmission and distribution systems, terminal systems, refrigerant air conditioning systems, operation and management, and construction conditions.

[0007] S3. By constructing an energy consumption decomposition tree, the total electricity consumption of each building is decomposed layer by layer into energy consumption nodes that can be independently modified. Based on the energy consumption bill information collected in step S2, the sub-item electricity consumption of each energy consumption node is obtained, thereby completing the energy consumption baseline calculation.

[0008] S4. Input the data obtained from the survey and collection into the energy-saving measures library constructed in step S1, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions.

[0009] S5. If an energy consumption node is affected by multiple energy-saving measures, the energy-saving rate A of the energy consumption node is calculated using the energy-saving rate multiplication and superposition formula.

[0010] S6. Add up the investments of each hit measure to get the total investment of the plan. Calculate the annual electricity cost by multiplying the electricity consumption of each energy consumption node by the energy saving rate of that energy consumption node by the electricity price. Calculate the static payback period = total investment / (annual electricity cost - annual operation and maintenance cost change) and convert it into carbon emission reduction.

[0011] S7. Outputs include an energy-saving management plan that includes a list of measures, investment, static payback period, and carbon emission reductions.

[0012] As a further technical solution, the triggering conditions for each measure include a set of conditions that must be met and / or a set of conditions that can be met selectively. All conditions in the set of conditions that must be met must be met, while only one condition in the set of conditions that can be met selectively is required to be met.

[0013] As a further technical solution, in step S3, default values ​​are set for the proportion of HVAC power consumption to total building power consumption, the proportion of power consumption of internal system components, and the equivalent full-load operation hours of air conditioning.

[0014] If step S2 does not collect the individual electricity consumption of each energy consumption node, but collects the monthly electricity consumption of the past 12 months, the air conditioning energy consumption is obtained by the seasonal difference method.

[0015] If step S2 fails to collect the breakdown of electricity consumption at each energy consumption node, or fails to collect the monthly electricity consumption for the past 12 months, the air conditioning energy consumption shall be estimated using the meteorological heat load method.

[0016] The individual electricity consumption of each energy consumption node can be obtained by multiplying the obtained air conditioning energy consumption by the default value of the proportion of individual electricity consumption within the system.

[0017] As a further technical solution, each energy-saving measure is also configured with pre-dependent measures and mutual exclusion measures, which need to be verified in step S4.

[0018] As a further technical solution, in step S5, several collaborative reduction pairs are set for two energy-saving measures with overlapping energy-saving effects and a collaborative reduction matrix is ​​formed. Each collaborative reduction pair is set with a reduction coefficient f according to the degree of overlap. The actual energy saving rate B = energy saving rate A - the product of the energy saving rates of the two measures × reduction coefficient f.

[0019] As a further technical solution, each energy-saving measure is also equipped with a commitment reduction factor cf, and the final energy saving rate C = actual energy saving rate B × commitment reduction factor cf.

[0020] As a further technical solution, each energy-saving measure is equipped with three energy-saving rate levels: low, typical, and high, and each level has a confidence level. The appropriate energy-saving rate level is selected based on the confidence level.

[0021] Secondly, the present invention provides a device for generating energy-saving management schemes for public institutions, comprising:

[0022] The data acquisition module is used to collect information on basic project overview, energy consumption bills, cold and heat sources, transmission and distribution systems, terminal systems, refrigerant system air conditioning, operation management, and construction conditions.

[0023] The data storage module is used to store the information collected by the data acquisition module and the energy-saving measures library constructed.

[0024] The data processing module is used to calculate the breakdown of electricity consumption at each energy consumption node, thereby completing the energy consumption baseline calculation; it is used to input the data collected from the survey into the energy-saving measures library, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions; it is used to calculate the energy-saving rate of each energy consumption node; and it is used to calculate the investment, static payback period, and carbon emission reduction.

[0025] The solution output module is used to output energy-saving management solutions that include a list of measures, investment, static payback period, and carbon emission reductions.

[0026] Thirdly, the present invention provides an electronic device, the electronic device comprising:

[0027] At least one processor; and,

[0028] A memory communicatively connected to the at least one processor; wherein,

[0029] The memory stores a computer program that can be executed by the at least one processor to enable the at least one processor to perform the public agency energy conservation management scheme generation method as described in the first aspect.

[0030] Fourthly, the present invention provides a computer-readable storage medium storing a computer program, characterized in that, when the computer program is executed by a processor, it implements the method for generating energy-saving management schemes for public institutions as described in the first aspect.

[0031] The beneficial effects of the present invention are as follows:

[0032] (1) This invention pre-sets several energy-saving measures for different working conditions, enabling them to carry information such as triggering conditions, energy consumption nodes affected and their energy-saving rates, investment, and annual operation and maintenance cost changes, thereby pre-constructing an energy-saving measure library. After obtaining on-site survey data, based on the energy-saving measure library, it can support a fully automatic link of "survey data → measure matching → investment / return calculation → scheme output", making the scheme output more convenient, reducing the initial investment, and facilitating the investment decision-making of the general contractor.

[0033] (2) This invention realizes that the energy saving rate is not simply added together among different measures. Therefore, the HVAC energy saving measures library uses the "energy consumption decomposition tree" as the mounting skeleton. Multiple measures on the same node are multiplied and superimposed and the collaborative reduction is deducted. The promised energy saving rate is multiplied by the promised reduction coefficient, thus preventing the risk of "failure to meet the energy saving effect" from the source.

[0034] (3) At present, there is a serious shortage of senior professionals in energy-saving technology transformation. The method of this invention incorporates core technical capabilities into the method. Energy-saving measures are not manually selected, but automatically triggered by survey data and matched. This reduces the technical requirements for energy-saving solution personnel, enabling junior engineers to quickly produce professional technical solutions, making up for the current shortage of professional talents and helping the rapid advancement of energy trusteeship in public institutions. Attached Figure Description

[0035] The accompanying drawings, which form part of this specification, are used to provide a further understanding of the invention. The illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute a limitation thereof. It should also be understood that these drawings are for simplicity and clarity and are not necessarily drawn to scale. The invention will now be described and explained with additional features and details using the drawings, wherein:

[0036] Figure 1 A flowchart illustrating the method for generating energy-saving outsourcing solutions for public institutions in an embodiment of the present invention is shown. Detailed Implementation

[0037] The technical solutions in typical embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings.

[0038] Example 1

[0039] like Figure 1 As shown, this embodiment provides a method for generating energy-saving outsourcing solutions for public institutions, including the following steps:

[0040] S1. Construct a database of energy-saving measures.

[0041] For different operating conditions, several energy-saving measures are preset, and the system link (primary category) to which each measure belongs and the nature of the modification (secondary category: equipment replacement / equipment modification / intelligent control / strategy optimization / energy recovery / maintenance improvement / enabling measures), applicable system form, triggering conditions, energy consumption nodes affected and their energy saving rate, investment, annual operation and maintenance cost changes, pre-dependent measures and mutually exclusive measures, confidence level, and commitment reduction factor are determined, as shown in Table 2.

[0042] The energy-saving measures library can be constructed by experienced engineers based on the maturity of the technology, including the types of measures, applicable system forms, triggering conditions, energy consumption nodes affected and their energy-saving rates, investment, annual operation and maintenance cost changes, pre-dependent measures and mutually exclusive measures, confidence level, and commitment reduction factor.

[0043] Each measure is a structured master data record with the following field definitions. Taking A-01 (cooling plant group control and unit number optimization) as an example:

[0044] Field (Chinese name [machine code]) Meaning / Example Measure code id / name The measure has a unique code and name, such as A-01 / cooling plant group control and unit number optimization. Primary category cat1 / Secondary category cat2 Primary category (cold and heat sources, transmission and distribution systems, etc.) / Secondary category (control optimization, equipment replacement, etc.) Applicable system sys Applicable system form, such as ["centralized cooling station"], corresponds to the air conditioning system form (sys_form) in the survey field. Summary of Measures Explain in one sentence what you do and what problem you solve. Trigger condition Triggering condition (data-driven hit criterion): {all:[condition…], any:[condition…]}, a hit occurs if all conditions are met and any one of the conditions is met. Energy consumption nodes and energy saving targets The affected energy consumption node (machine code of the energy consumption tree) + three energy saving rate ranges: [{node, rate_low (low value), rate_typ (typical value), rate_high (high value)}], can be applied to multiple nodes. Investing in capex Investment Model: Basis (Pricing Method) / qty_field (Quantity Field) / low·typ·high (Unit Price) / min_total (Minimum Investment) Annual maintenance cost changes opex_delta Annual maintenance cost changes (RMB / year, positive indicates increase, negative indicates decrease) Equipment lifespan / construction period_d Equipment lifespan (years) / Construction period (days) shutdown for construction Explanation of whether machine shutdown is required for construction and its impact Pre-dependencies / mutual exclusions Pre-dependent measures (such as G-01 measurement) / mutually exclusive measures confidence Data confidence level (high / medium / low) affects grading and commitment. Commit factor The committed reduction factor, and the externally committed energy saving rate = rate_low (low energy saving rate) × commit_factor

[0045] Table 1 A-01 (Cooling Plant Group Control and Unit Count Optimization) serves as an example.

[0046]

[0047] Table 2 Energy Saving Measures

[0048] Each energy-saving measure is set with corresponding trigger conditions. The trigger conditions include a group of conditions that must be met and / or a group of conditions that can be met selectively. All conditions in the group of conditions that must be met must be met, while only one condition in the group of conditions that can be met selectively needs to be met. The trigger conditions set in this embodiment are shown in Tables 3 and 4.

[0049]

[0050] Table 3 Triggering Conditions

[0051]

[0052] Table 4 Triggering Conditions

[0053] Example 1: Group control and unit number optimization of A-01 chiller plant

[0054] all:[sys_form contains "centralized cooling station",chiller_count>=2,has_plant_control==false]

[0055] Group control is only recommended if the following conditions are met simultaneously: "centralized cooling station + multiple units (≥2 units) + no data center group control". (If group control is already in place, it will not be recommended again.)

[0056] Example 2: Replacement of the entire A-03 old and inefficient chiller unit.

[0057] all:[sys_form contains "centralized cooling station"]

[0058] any:[chiller_age>=15,chiller_cop<4.2]

[0059] Under the premise of centralized cooling stations, the replacement of units is triggered when either "unit age ≥ 15 years" or "COP < 4.2" is achieved (OR represents any aging indicator).

[0060] Example 3: A-04 Condenser Online Automatic Cleaning (Glue Ball Cleaning Device)

[0061] all:[sys_form contains "centralized cooling station"]

[0062] any:[cond_fouling belongs to ["General", "Significant scaling"], maintenance_level belongs to ["No maintenance", "Repair requested only"]]

[0063] If scaling is obvious or maintenance is lacking, it is recommended to use a cleaning ball to prevent dirt blockage from causing a drop in COP.

[0064] The energy consumption nodes affected are the individual energy consumption nodes to which the energy-saving measures are applied. Each affected energy consumption node is assigned one of three energy-saving rates: low, typical, and high. The appropriate energy-saving rate is selected based on the confidence level, as shown in Tables 5 and 6. A high energy-saving rate is selected when the confidence level is high, a typical energy-saving rate is selected when the confidence level is medium, and a low energy-saving rate is selected when the confidence level is low.

[0065]

[0066] Table 5. Energy Saving Rate of Measures at Each Energy Consumption Node

[0067]

[0068] Table 6. Energy Saving Rate of Measures at Each Energy Consumption Node

[0069] S2. Conduct on-site inspections and collect information for each public institution within the managed area contract. The collected information includes basic project overview, energy consumption bills, heat and cold source information, distribution system information, terminal system information, refrigerant system air conditioning information, operation and management information, and construction conditions information. The collected information must be mapped to data in the energy-saving measures database and be identifiable. For some information items, multiple preset values ​​can be used; simply click to select the option that best reflects the actual situation when filling in the information. For example, in Table 9, the scale / cleaning status of the cond_fouling condenser can be set to three selectable values: "Good," "Average," and "Significant Scale."

[0070] Information is collected using an information collection module. For example, in this embodiment, a site survey applet is used, but other modules capable of collecting and storing information can also be used.

[0071] Data collection methods include forms, automatic location filling, automatic inference from cities, drawings, voice interviews, bill photos, on-site confirmation, nameplate OCR, and maintenance interviews, etc. The method that is most convenient for site survey technicians should be chosen according to the actual situation.

[0072] The information collection module has 64 built-in fields, divided into 8 groups and paginated (each including the 8 types of data to be collected mentioned above). Each page contains several fields; each field also includes "machine code (English)" and "Chinese name". The field is presented to the surveyor in "Chinese name" and sent back to the backend in "machine code".

[0073] In this embodiment, the fields included in the project basic overview, energy consumption bill, cold and heat source, transmission and distribution system, terminal system, refrigerant system air conditioning type, operation management, and construction conditions are shown in Tables 7 to 14, respectively.

[0074] Field Encoding Field Name Data type / unit Required proj_name Project Name text Required proj_city City text Required climate_zone Building Climate Zone enum automatic building_type Construction Industry enum Required build_year Year of completion int / year Required area_total_m2 Building area number / ㎡ Required area_ac_m2 Air conditioning service area number / ㎡ Required occupancy_hours_d Average daily usage time number / h / d Required occupancy_days_y Annual usage days number / d / a Required

[0075] Table 7 Basic Project Overview Information (9 fields)

[0076] Field Encoding Field Name Data type / unit Required elec_bill_12m Monthly electricity consumption over the past 12 months (automatically summed to obtain the total). array

[12] / kWh Optional elec_price Comprehensive electricity price number / yuan / kWh Required gas_bill_12m Gas consumption by month over the past 12 months array

[12] / m³ Optional heat_bill_y Annual externally purchased heat number / GJ Optional has_submeter_hvac Is there separate metering for air conditioning? bool Required hvac_kwh_y Annual power consumption of air conditioner (actual measurement) number / kWh Optional

[0077] Table 8 Energy Consumption Bill Information (6 fields)

[0078] Field Encoding Field Name Data type / unit Required sys_form Air conditioning system type multi-enum Required chiller_count Number of chiller units int / Taiwan Required conditions chiller_capacity_kw Total cooling capacity of the chiller number / kW Required conditions chiller_type Refrigeration type enum Required conditions chiller_cop Nominal COP / EER of Refrigeration Unit number Required conditions chiller_age The chiller's service life int / year Required conditions chiller_vfd Is the chiller already equipped with inverter technology? bool Required conditions cond_fouling Condenser scaling / cleaning status enum Optional has_plant_control Does the machine room already have a group control system? bool Required heat_source Heating / Hot Water Source enum Optional boiler_kw Boiler rated power number / kW Optional dhw_demand Is there a stable demand for domestic hot water? bool Optional

[0079] Table 9 Cold and heat source information (12 fields)

[0080] Field Encoding Field Name Data type / unit Required pump_chw_kw Total power of chilled water pump motor number / kW Required conditions pump_cw_kw Total power of cooling water pump motor number / kW Required conditions ct_fan_kw Total power of cooling tower fan number / kW Required conditions pump_vfd Is the water pump frequency converter installed? bool Required conditions ct_vfd Has the cooling tower fan been frequency-controlled? bool Required conditions delta_t_chw Measured temperature difference between chilled water supply and return water number / ℃ Optional hydraulic_unbalance Are there any complaints about uneven heating / cooling? bool Required pipe_length_m Computer room and main pipeline length number / m Optional insulation_bad Insulation damage enum Optional

[0081] Table 10 Information on the power transmission and distribution system (9 fields)

[0082] Field Encoding Field Name Data type / unit Required fcu_count Number of fan coil units int / Taiwan Required conditions ahu_count Number of air conditioning units / fresh air handling units int / Taiwan Required conditions ahu_fan_kw Total power of air conditioning unit fan number / kW Required conditions ahu_vfd Is the air conditioning unit already inverter-driven? bool Required conditions fresh_air_m3h Total fresh air volume number / m³ / h Optional <![CDATA[has_co2_ctrl]]> <![CDATA[Is there on-demand CO2 ventilation]]> bool Optional terminal_ctrl End-of-line control method enum Required

[0083] Table 11 Terminal System Information (7 fields)

[0084] Field Encoding Field Name Data type / unit Required vrf_outdoor_count Number of outdoor units in a multi-split air conditioning system int / Taiwan Required conditions vrf_indoor_count Number of indoor units in a multi-split air conditioning system int / Taiwan Required conditions vrf_brand Multi-split air conditioning brands text Required conditions vrf_has_gateway Has the multi-split unit been connected to the centralized control gateway? bool Required conditions split_count Number of split air conditioners int / Taiwan Required conditions split_avg_kw Average cooling capacity of split-type air conditioners number / kW Optional split_eer_level Split-type air conditioner energy efficiency rating enum Required conditions split_age Average lifespan of split-type air conditioners int / year Required conditions split_has_ctrl Are split-type air conditioners already under centralized management? bool Required room_count Number of independent rooms / areas int / space Optional

[0085] Table 12 Refrigerant System Air Conditioning Information (10 fields)

[0086] Field Encoding Field Name Data type / unit Required temp_setpoint_summer Summer average set temperature number / ℃ Required temp_setpoint_winter Average winter set temperature number / ℃ Optional unattended_running Is there a phenomenon of no one turning on the machine? bool Required has_schedule_mgmt Is there work schedule control? bool Required maintenance_level Maintenance level enum Required has_ems Does an energy management platform already exist? bool Required fault_history Historical Fault Description text Optional

[0087] Table 13 Operation Management Information (7 fields)

[0088] Field Encoding Field Name Data type / unit Required power_capacity_margin Power distribution capacity margin enum Optional network_condition Network / communication conditions enum Required construction_window Construction period enum Optional special_requirement Special requirements (classified / epidemic prevention / cultural relic protection) text Optional

[0089] Table 14 Construction Condition Information (4 fields)

[0090] Note: "Required" means that the field must be filled in; "Optional" means that you can choose whether to fill in the field or not; "Conditional" means that the field must be filled in if the conditions are met. For example, in Table 12, if the air conditioner is a multi-split system, then the conditional fields related to multi-split systems are required fields.

[0091] This example uses "office buildings of Party and government organs" as a sample (selecting key fields), as shown in Table 15, to demonstrate how to fill in the fields and how the system matches them accordingly.

[0092] Field name (machine code) Example values Project Name (proj_name) Energy-saving renovation of the XX District Government Affairs Management Center City (proj_city) Hangzhou Building climate zones (climate_zone) Hot in summer and cold in winter Building type Party and government office buildings Building area (area_total_m2) 18000m² Air conditioning system form (sys_form) Centralized cooling station Number of chiller units (chiller_count) 3 units Total cooling capacity of the chiller (chiller_capacity_kW) 2400kW Chiller COP (chiller_cop) 5.2 Server age (chiller_age) 12 years Is a plant control system already in place? no Is the chilled water pump frequency converter (pump_vfd) enabled? no Comprehensive electricity price (elec_price) 0.78 yuan / kWh Monthly electricity consumption over the past 12 months (automatically summed to total) (elec_bill_12m) 1,800,000 kWh

[0093] Table 15 Filling Example for This Embodiment

[0094] After obtaining the field survey data, the data is first checked for range, missing items are indicated, and built-in default values ​​are set (as in step S3). This reduces the requirements for the survey and completes the necessary items, so that the subsequent matching of measures and energy saving rate calculation are based on a reliable data foundation, reducing the deviation of the scheme caused by input distortion from the source.

[0095] S3, Energy Consumption Baseline Calculation

[0096] An energy consumption decomposition tree is constructed, as shown in Table 16. The energy consumption decomposition tree decomposes the building's total electricity consumption layer by layer into nodes that can be independently modified. The energy saving rate is attached to the leaf nodes, and the energy saving rate of the parent node is calculated and aggregated from the child nodes from bottom to top. Each node in the tree carries both a "Chinese name" and a "machine code (English)"—the former is used for on-site communication, and the latter is used for interfacing with Excel fields; the two correspond one-to-one.

[0097] Machine coding Chinese name Parent node Are the leaves E_total Total electricity consumption of the building — no E_hvac Total power consumption of HVAC E_total no E_light illumination E_total yes E_socket Sockets / Office Equipment E_total yes E_lift elevator E_total yes E_other Other power sources E_total yes E_plant Cold and heat source computer room E_hvac no chiller Cold and heat source unit E_plant yes pump_chw chilled water pump E_plant yes pump_cw Cooling water pump E_plant yes ct Cooling tower fan E_plant yes ahu Air conditioning unit / fresh air handling unit E_hvac yes fcu Fan coil unit E_hvac yes vrf Multi-split air conditioner E_hvac yes split Split air conditioner E_hvac yes dhw Domestic hot water / heat source E_hvac yes

[0098] Table 16 Energy Consumption Decomposition Tree

[0099] Set a default estimation coefficient to provide a fallback estimate when survey data is missing.

[0100] The percentage of each item and the equivalent full-load operating hours (EFLH) of the equipment are built in as default coefficients to facilitate estimation when there are no item measurements, as shown in Tables 17 and 18.

[0101] System configuration (machine coding) Item percentages within the data center (node: percentage) Centralized cooling station chiller:0.52;pump_chw:0.12;pump_cw:0.1;ct:0.05;ahu:0.13;fcu:0.08 air-cooled module chiller:0.7;pump_chw:0.12;ahu:0.08;fcu:0.1 Multi-split air conditioner vrf:1.0 Split-type machine split:1.0 hot water system dhw:1.0

[0102] Table 17. Power consumption percentage of internal system components (default value, percentage of HVAC power consumption)

[0103] Equivalent Full-Load Operating Hours (EFLH) by Climate Zone (Cooling / Heating):

[0104] Climate Zone Cooling EFLH (hours) Heating EFLH (hours) severe cold 350 900 cold 600 700 Hot in summer and cold in winter 850 500 Hot in summer and warm in winter 1150 120 mild 400 300

[0105] Table 18 Equivalent Full-Load Operating Hours for Air Conditioning (Default Values, by Climate Zone)

[0106] The default values ​​for the proportion of HVAC energy consumption to total energy consumption for each building type (hvac_ratio_by_type, HVAC ratio) are shown in Table 19.

[0107] Construction Industry HVAC ratio Party and government office buildings 40% Government Service Center 45% School - Teaching Building 28% School - Dormitory 22% Hospital - Outpatient and Inpatient Services 45% Cultural venues 48% Sports venues 50% library 45% Courts and Procuratorates 42% Disease Control / Research 45% Other public institutions 40%

[0108] Table 19. Proportion of HVAC power consumption in total building power consumption (default value, by business type)

[0109] When individual metering is missing, use the following two methods to estimate E_hvac and the energy consumption of each node; once you have 12 months of electricity bills or individual metering data, you must overwrite the corresponding default data (if there are actual values, use the actual values).

[0110] Method A: Meteorological heat load method (design estimation)

[0111] Estimating annual air conditioning energy consumption based on building area, cooling / heating load per unit area, and EFLH (Extended Flame-Free Hypothesis) of the climate zone:

[0112] Annual cooling energy consumption E_cool≈Area (m²)×Cooling load index (W / m²)×EFLH_cooling (h) / 1000 / System SCOP;

[0113] Annual heating energy consumption E_heat≈Area (m²)×Heat load index (W / m²)×EFLH_heat (h) / 1000 / System energy efficiency;

[0114] E_hvac≈E_cool+E_heat.

[0115] Method B: Seasonal Difference Method (Reverse Deduction from Bills)

[0116] When there are 12 months of monthly electricity consumption, the average monthly electricity consumption in non-air conditioning seasons is used as the benchmark, and the seasonal increment is the air conditioning energy consumption:

[0117] Baseline monthly average = average monthly electricity consumption during the transition season; the default values ​​for the transition season are March, April, May, October, and November. That is, the sum of electricity consumption for these months divided by 5.

[0118] Cooling energy consumption ≈ Σ(summer monthly electricity consumption) − baseline monthly average × number of summer months;

[0119] Heating energy consumption ≈ Σ(winter monthly electricity consumption) − baseline monthly average × number of winter months;

[0120] E_hvac≈cooling energy consumption + heating energy consumption.

[0121] This example uses a government office building with an area of ​​18,000 m², characterized by hot summers and cold winters, and a comprehensive electricity price of 0.78 yuan / kWh (individual metering is missing):

[0122] (1) The building’s annual electricity consumption is approximately 1,800,000 kWh (≈100 kWh / m²·a); E_hvac [heating and ventilation] = 1,800,000 × 40% = 720,000 kWh.

[0123] (2) In the case of centralized cold station, E_hvac is decomposed into each computer room node according to plant_split (the sum of the proportions = 100%), as shown in Table 20.

[0124] Energy consumption node (Chinese name [encoding]) percentage Annual energy consumption (kWh) Heat and cold source unit (chiller) 52% 374,400 Chilled water pump [pump_chw] 12% 86,400 Cooling water pump [pump_cw] 10% 72,000 Cooling tower fan [ct] 5% 36,000 Air conditioning unit / fresh air handling unit [ahu] 13% 93,600 Fan coil unit (fcu) 8% 57,600

[0125] Table 20 Energy Consumption of Each Data Center Node

[0126] (3) The energy consumption of these nodes is the "baseline for energy saving rate" of subsequent measures: For example, the chiller node has a capacity of 374,400 kWh, and the A-02 host frequency converter takes an energy saving rate of 20%~30%~40% on it, which corresponds to an annual power saving of approximately 74,880~112,320~149,760 kWh.

[0127] S4. Input the survey and collection data into the energy-saving measure library constructed in step S1, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions. A single energy-saving measure can be matched, or multiple measures can be matched simultaneously. Each energy-saving measure also has pre-dependent measures and mutually exclusive measures configured, which need to be verified in step S4. For example, if two matched measures are mutually exclusive, only one can be selected; if a matched measure has pre-dependent measures, both must be matched.

[0128] S5, Superimposed calculation of energy saving rate

[0129] Multiple measures may be applied at the same energy consumption node. The energy savings cannot be directly added together, but are multiplied and summed to obtain the energy saving rate A.

[0130]

[0131] Note: The formula for multiplying and superimposing node energy saving rates (η_node is the node energy saving rate, η_i is the energy saving rate of the i-th hit measure on that node, and the value is taken according to the typical value rate_typ; when the confidence level is low, rate_low is used)

[0132] If a collaborative reduction pair (i,j) exists, the overlapping benefits between measures need to be further deducted:

[0133]

[0134] Note: Cooperative reduction: The "overlapping section energy" ΔE_ij of the two measures is included as (1−d_ij) (d_ij is taken from the reduction matrix).

[0135] The collaborative reduction matrix contains 37 reduction coefficients f (factor0~1) between measures, as shown in Table 21. Meaning: d represents "overlap severity"—d=0 indicates that the two measures are already set as mutually exclusive and will not co-occur (no further deduction required); the larger d is, the more severe the overlap in benefits, and the more deduction is needed; d=1 indicates that all overlap is deducted. Example: A-01|A-05 reduces by 0.5 (group control and cooling water temperature optimization partially overlap in benefits), A-02|A-03 reduces by 0.0 (already set as mutually exclusive).

[0136]

[0137] Table 21 Cooperative Reduction Matrix

[0138] Continuing with the example above, the annual energy consumption of the chiller (heat source / cooler host) node is 374,400 kWh. Assume that this node simultaneously implements two measures: A-01 group control (chiller energy saving rate 5%~8%~12%) and A-05 dynamic optimization of cooling water temperature / approximation (chiller energy saving rate 2%~4%~6%).

[0139] (1) Incorrect approach - direct addition: 8% + 4% = 12%, corresponding to 44,928 kWh (overestimated, because the benefits of the two measures overlap).

[0140] (2) Correct approach – multiplication and stacking (based on typical value rate_typ):

[0141] η_node=1-(1-0.08)x(1-0.04)=1-0.92x0.96=1-0.8832=0.1168=11.68%

[0142] Annual electricity savings at nodes = 374,400 x 11.68% ≈ 43,730 kWh

[0143] (3) Collaborative reduction: The multiplication formula has automatically deducted the overlapping cross term η_i·η_j=0.08×0.04=0.32% under the "independence assumption"; however, the two measures are not completely independent (part of the benefits come from the same physical effect), and the reduction matrix A-01|A-05=0.5 indicates that "the overlapping part is deducted by another 50%". Therefore, the actual energy saving rate B=11.68%−0.5×0.32%=11.52%, and the annual electricity saving ≈374,400×11.52%≈43,100kWh. (Overlap = Σ energy saving rate − multiplication rate ≥ 0; the larger d is, the more is deducted, d=0 no deduction, d=1 all deduction.)

[0144] (4) The final energy saving rate C promised to external parties (multiplied by the lower value rate_low by the commitment reduction factor cf(commit_factor); this factor is a safety margin set manually according to the measures).

[0145] Taking A-01 group control (chiller energy saving rate 5%) and A-05 cooling water temperature / approximation dynamic optimization (chiller energy saving rate 2%) as examples:

[0146] η_low=1-(1-0.05)x(1-0.02)=1-0.95x0.98=6.9%

[0147] η_commit = 6.9% x 0.7 (The commitment reduction factor for A-01 is 0.75, and the commitment reduction factor for A-05 is 0.65: (0.75 + 0.65) / 2) ≈ 4.83%

[0148] Key points: The energy saving rate decreases progressively through three levels of protection: "node multiplication → collaborative reduction → further discounting of commitments". In this example, the combination of A-01 and A-05 reduces the calculated typical value of 11.68% to the externally committed value of about 9.5%, which is a guarantee to prevent "failure to meet energy saving standards".

[0149] This embodiment achieves that the energy saving rate is not simply added together among different measures. Therefore, the HVAC energy saving measure library uses the "energy consumption decomposition tree" as the mounting skeleton. Multiple measures on the same node are multiplied and superimposed, and the collaborative reduction is deducted. The promised energy saving rate is then multiplied by the promised reduction coefficient, thus preventing the risk of "failure to meet energy saving standards" from the source.

[0150] S6. Calculate the investment and payback period

[0151] Single measure investment = max(unit price × pricing quantity, minimum investment); the total investment of the scheme is the sum of the investments of each hit measure. The annual electricity saving is obtained by multiplying the energy consumption of the node in the energy consumption decomposition tree by the energy saving rate of that node, and then adding the default electricity price of the factory to get the annual electricity cost saving. The static payback period = total investment / (annual electricity cost saving - annual operation and maintenance cost change), and the carbon emission reduction is calculated (co2_factor default 0.5366kgCO2 / kWh).

[0152] Six measures that were actually implemented using examples of Party and government office buildings (A-01 / A-05 / A-06 / E-07 / G-02 /

[0153] Taking G-03 as an example, the investment and return calculations are as follows (unit price; G-02 point sample not filled, calculated based on typical default value of 20 points), as shown in Table 22:

[0154] measure Pricing caliber quantity Unit price (yuan) Investment (RMB) A-01 Cold Storage Group Control Yuan / kW cooling capacity 2400kW 60 144,000 A-05 Cooling Water Temperature Optimization Yuan / project 1 15,000 15,000 A-06 Chilled Water Temperature Resetting Yuan / project 1 8,000 8,000 <![CDATA[G-02 Temperature / Humidity / CO2 Sensing Network]]> Yuan / point 20 points* 550 11,000 G-03 Cold Capacity Metering Yuan / Taiwan 3 units 9,000 27,000 E-07 Energy and Carbon Platform Connection Yuan / project (free) 1 0 0 total — — — 205,000

[0155] Table 22 Investment and Return Calculation

[0156] The following is a detailed calculation process for the annual electricity savings node by node (the energy saving rate is a typical value rate_typ).

[0157] Of the six hit measures, E-07 Energy Carbon Platform, G-02 Sensor Network, and G-03 Cooling Capacity Metering belong to the "Digital Enablement / Accounting Support" category. Their targets are empty, they are not connected to any energy consumption nodes, and they do not directly generate terminal electricity savings (their role is in energy saving M&V verification and continuous optimization). Therefore, only A-01 / A-05 / A-06, which are directly connected to nodes, are calculated. The annual energy consumption of each node in the centralized cooling station is: chiller 374,400, pump_chw 86,400, pump_cw 72,000, ct 36,000 kWh (totaling 568,800 kWh, i.e., E_hvac × centralized cooling station percentage), as shown in Table 23.

[0158] Energy consumption nodes Annual energy consumption (kWh) Hit rate (typical rate) Multiplication rate Cooperative reduction d Actual calculation rate Annual electricity savings at nodes (kWh) chiller 374,400 A-018%+A-054%+A-064% 15.21% 0.55 14.78% 55,336 pump_chw 86,400 A-0112% 12.00% — 12.00% 10,368 pump_cw 72,000 A-0112% 12.00% — 12.00% 8,640 ct 36,000 A-0115%+A-05-3% 12.45% 0.5 12.68% 4,563 total 568,800 — — — — 78,907

[0159] Table 23 Annual Electricity Savings at Node 23

[0160] Calculation process for each node (actual calculation rate = multiplied calculation rate − d × overlap; overlap = Σ energy saving rate − multiplied calculation rate):

[0161] (1) Chiller node (three measures; reduce A-01|A-05=0.5, A-01|A-06=0.6, take the mean d=0.55)

[0162] Multiplication rate = 1 - (1 - 0.08) x (1 - 0.04) x (1 - 0.04) = 1 - 0.92 x 0.96 x 0.96 = 15.21%

[0163] Overlap = (0.08 + 0.04 + 0.04) - 0.1521 = 0.79pp

[0164] Actual calculation rate = 15.21% - 0.55 x 0.79% = 14.78%

[0165] Node energy saving = 374,400 x 14.78% = 55,336 kWh

[0166] (2) pump_chw node (only A-0112%, no cooperative reduction pairs)

[0167] Actual calculation rate = 12.00% Node power saving = 86,400 x 12.00% = 10,368 kWh

[0168] (3) pump_cw node (A-0112% only, no cooperative reduction pairs)

[0169] Actual calculation rate = 12.00% Node power saving = 72,000 x 12.00% = 8,640 kWh

[0170] (4) CT node (A-01 15% + A-05 - 3%; A-05 has a negative energy saving rate on the cooling tower side:

[0171] The benefits of optimizing cooling water temperature are at the host unit level, with a slight increase in cooling tower energy consumption; this reduces the impact on A-01|A-05=0.5.

[0172] Multiplication rate = 1 - (1 - 0.15) x (1 - (-0.03)) = 1 - 0.85 x 1.03 = 12.45%

[0173] Overlap = (0.15 - 0.03) - 0.1245 = -0.45pp (Negative value: if the cross term is negative, the overlap is reduced to "add back")

[0174] Actual calculation rate = 12.45% - 0.5 x (-0.45%) = 12.68% Node power saving = 36,000 x 12.68% = 4,563 kWh

[0175] Summary: Annual electricity savings = 55,336 + 10,368 + 8,640 + 4,563 = 78,907 kWh (≈79,000 kWh).

[0176] E-07 / G-02 / G-03 are not directly included in the terminal power saving, but they support the energy saving verification and continuous optimization, and their investment is already included in the table above.

[0177] Annual electricity savings = 78,907 × 0.78 = 61,547 yuan; annual maintenance cost change opex_delta is taken as -8,000 yuan (maintenance costs are slightly reduced).

[0178] Net annual revenue = Annual electricity savings - Annual maintenance cost changes = 61,547 - (-8,000) = 69,547 yuan

[0179] Static payback period = Total investment 205,000 / 69,547 ≈ 2.95 years

[0180] Carbon emission reduction = 78,907 kWh x 0.5366 kg CO2 / kWh ≈ 42,341 kg CO2 ≈ 42.3 t CO2 / year

[0181] S7. Output energy-saving renovation plan, including a list of measures, investment, benefits and payback period.

[0182] Example 2

[0183] This embodiment provides a device for generating energy-saving outsourcing solutions for public institutions, including:

[0184] The data acquisition module is used to collect information on basic project overview, energy consumption bills, cold and heat sources, transmission and distribution systems, terminal systems, refrigerant system air conditioning, operation management, and construction conditions.

[0185] The data storage module is used to store the information collected by the data acquisition module and the energy-saving measures library constructed.

[0186] The data processing module is used to calculate the breakdown of electricity consumption at each energy consumption node, thereby completing the energy consumption baseline calculation; it is used to input the data collected from the survey into the energy-saving measures library, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions; it is used to calculate the energy-saving rate of each energy consumption node; and it is used to calculate the investment, static payback period, and carbon emission reduction.

[0187] The solution output module is used to output energy-saving management solutions that include a list of measures, investment, static payback period, and carbon emission reductions.

[0188] Example 3

[0189] This embodiment provides an electronic device, the electronic device comprising:

[0190] At least one processor; and,

[0191] A memory communicatively connected to the at least one processor; wherein,

[0192] The memory stores a computer program that can be executed by the at least one processor, which enables the at least one processor to perform a method for generating a public institution energy-saving management scheme as described in Embodiment 1.

[0193] Example 4

[0194] This embodiment provides a computer-readable storage medium storing a computer program, which, when executed by a processor, implements a method for generating a public institution energy-saving management scheme as described in Embodiment 1.

[0195] Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make possible changes and modifications to the technical solutions of the present invention by utilizing the methods and techniques disclosed above without departing from the spirit and scope of the present invention. Therefore, any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention shall fall within the protection scope of the technical solutions of the present invention.

Claims

1. A public institution energy saving hosting scheme generation method, characterized by, Includes the following steps: S1. For different operating conditions, pre-set several energy-saving measures, determine the triggering conditions of each measure, the energy consumption nodes it affects, its energy-saving rate, investment, and annual operation and maintenance cost changes, and build an energy-saving measure library; S2. Conduct on-site inspections and collect information for each public institution under the trusteeship contract. The collected information includes basic project overview, energy consumption bills, cold and heat sources, transmission and distribution systems, terminal systems, refrigerant air conditioning systems, operation and management, and construction conditions. S3. By constructing an energy consumption decomposition tree, the total electricity consumption of each building is decomposed layer by layer into energy consumption nodes that can be independently modified. Based on the energy consumption bill information collected in step S2, the sub-item electricity consumption of each energy consumption node is obtained, thereby completing the energy consumption baseline calculation. S4. Input the data obtained from the survey and collection into the energy-saving measures library constructed in step S1, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions. S5. If an energy consumption node is affected by multiple energy-saving measures, the energy-saving rate A of the energy consumption node is calculated using the energy-saving rate multiplication and superposition formula. S6. Add up the investments of each hit measure to get the total investment of the plan. Calculate the annual electricity cost by multiplying the electricity consumption of each energy consumption node by the energy saving rate of that energy consumption node by the electricity price. Calculate the static payback period = total investment / (annual electricity cost - annual operation and maintenance cost change) and convert it into carbon emission reduction. S7. Outputs include a list of measures, investment, static payback period, and energy-saving management plan for carbon emission reductions.

2. The method of claim 1, wherein, Each measure's triggering conditions include a set of conditions that must be met and / or a set of conditions that can be met selectively. All conditions in the set of conditions that must be met must be met, while only one condition in the set of conditions that can be met selectively is required to be met.

3. The method for generating a public institution energy-saving outsourcing solution as described in claim 1, characterized in that, In step S3, set the default values ​​for the proportion of HVAC power consumption to total building power consumption, the default values ​​for the proportion of power consumption of internal system components, and the default values ​​for equivalent full-load operation hours of air conditioning. If step S2 does not collect the individual electricity consumption of each energy consumption node, but collects the monthly electricity consumption of the past 12 months, the air conditioning energy consumption is obtained by the seasonal difference method. If step S2 fails to collect the breakdown of electricity consumption at each energy consumption node, or fails to collect the monthly electricity consumption for the past 12 months, the air conditioning energy consumption shall be estimated using the meteorological heat load method. The individual electricity consumption of each energy consumption node can be obtained by multiplying the obtained air conditioning energy consumption by the default value of the proportion of individual electricity consumption within the system.

4. The method for generating a public institution energy-saving outsourcing scheme as described in claim 1, characterized in that, Each energy-saving measure is also configured with prerequisite and mutually exclusive measures, which need to be verified in step S4.

5. The method for generating a public institution energy-saving outsourcing solution as described in claim 1, characterized in that, In step S5, several synergistic reduction pairs are set for two energy-saving measures with overlapping energy-saving effects and a synergistic reduction matrix is ​​formed. Each synergistic reduction pair is set with a reduction coefficient f according to the degree of overlap. The actual energy saving rate B = energy saving rate A - the product of the energy saving rates of the two measures × reduction coefficient f.

6. The method for generating a public institution energy-saving outsourcing solution as described in claim 5, characterized in that, Each energy-saving measure also has a commitment reduction factor cf, and the final energy saving rate C = actual energy saving rate B × commitment reduction factor cf.

7. The method for generating a public institution energy conservation outsourcing scheme as described in claim 1, characterized in that, Each energy-saving measure has three energy-saving rate levels: low, typical, and high, each with a confidence level. The appropriate energy-saving rate level can be selected based on the confidence level.

8. A device for generating energy-saving outsourcing solutions for public institutions, characterized in that, include: The data acquisition module is used to collect information on basic project overview, energy consumption bills, cold and heat sources, transmission and distribution systems, terminal systems, refrigerant air conditioning systems, operation management, and construction conditions. The data storage module is used to store the information collected by the data acquisition module and the energy-saving measures library constructed. The data processing module is used to calculate the individual power consumption of each energy consumption node, thereby completing the energy consumption baseline calculation. This is used to input the data collected from the survey into the energy-saving measures library, traverse all energy-saving measures, and match the energy-saving measures that meet the trigger conditions; Used to calculate the energy saving rate at each energy consumption node; used to calculate investment, static payback period, and carbon emission reduction; The solution output module is used to output energy-saving management solutions that include a list of measures, investment, static payback period, and carbon emission reductions.

9. An electronic device, characterized in that, The electronic device includes: At least one processor; and, A memory communicatively connected to the at least one processor; wherein, The memory stores a computer program that can be executed by the at least one processor, the computer program being executed by the at least one processor to enable the at least one processor to perform the public institution energy-saving management scheme generation method as described in any one of claims 1 to 7.

10. A computer-readable storage medium storing a computer program, characterized in that, When the computer program is executed by the processor, it implements the method for generating energy-saving management schemes for public institutions as described in any one of claims 1 to 7.