Overhanging I-shaped steel embedded part based on laminated slab

By using cantilevered I-beam embedded parts anchored by prefabricated parts and concrete layers in the composite plate structure, the problem of floor concrete cracking caused by the stress at the anchorage point of the cantilevered I-beam is solved, improving construction safety and overall integrity. stability, simplifying on-site construction and quality control.

CN221798745UActive Publication Date: 2024-10-01SHANDONG TIANQI REAL ESTATE GRP INC CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323424941.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-15
Publication Date
2024-10-01
Estimated Expiration
2033-12-15

AI Technical Summary

Technical Problem

In the composite slab structure, the anchorage point of the cantilevered I-beam is insufficient in anchorage length, which can easily cause the floor concrete to crack, reduce the strength and bearing capacity of the floor, and pose quality risks.

Method used

Design a cantilevered I-beam embedded part based on laminated plates. The prefabricated part and the concrete layer are jointly anchored. Two 18-diameter third-level steel anchors are welded on the straight side section of the U-shaped bolt. This is achieved through welding and concrete condensation. Limit fixation, increase the anchoring length and depth, and use prefabricated parts to be installed after production in the factory, reducing on-site construction and quality control problems.

Benefits of technology

It effectively improves the stability and construction safety of the cantilevered I-beam, reduces the quality reduction of the floor slab structure and the problems of concrete cracking, simplifies on-site construction and quality control, and improves the overall installation stability and construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798745U_ABST
    Figure CN221798745U_ABST
Patent Text Reader

Abstract

The utility model discloses an overhanging I-shaped steel embedded part based on a laminated slab, which comprises an arranged prefabricated part, a concrete layer is arranged on the prefabricated part, and a U-shaped bolt is fixed in the concrete layer; an embedded part is fixed in the prefabricated part, an embedded plate is welded to the embedded part, the embedded plate and the U-shaped bolt are installed through welding, a concrete layer is poured on the embedded plate, and the U-shaped bolt is limited and fixed through concrete condensation. According to the overhanging I-shaped steel embedded part based on the laminated slab, prefabricated parts are conveniently installed and used in the later period after being machined and manufactured in a factory, the problems that in a traditional cast-in-place concrete structure, all the prefabricated parts need to be completed on site, and quality control is difficult are solved, the steel anchors on the straight edge sections of the U-shaped bolts are the two 18-diameter three-level steel anchors, and the construction efficiency is improved. The problem that the quality of a floor slab structure is reduced due to the fact that the floor slab needs to penetrate is solved, the prefabricated part and the concrete layer are jointly anchored and stressed, and construction safety can be well guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cantilever scaffolding steel pre-embedded parts, in particular to a cantilever I-beam pre-embedded part based on a composite plate. Background Art

[0002] With the application of composite slabs in engineering construction, new requirements have been put forward for the pre-embedded cantilever steel of cantilever scaffolding. In traditional cast-in-place structures, the fixation of cantilever scaffolding I-beams relies on pre-embedded U-bolts in the floor slab, and the U-bolts are fixed to the building structure beams and slabs, pre-embedded to the bottom steel bars of the concrete beams and slabs, and welded or tied firmly, and there are certain requirements for the anchor length; but the composite slab structure divides the floor slab into two layers, the lower layer is the composite slab, which does not allow holes or chiseling, and the upper layer is a cast-in-place structure with an anti-cracking steel mesh. When the U-bolts supporting the cantilever external frame are anchored in the upper cast-in-place layer of the floor slab, due to the insufficient anchor length, the cantilever I-beam anchor point will tear the cast-in-place concrete when it is stressed, causing the floor slab to crack, which will not only reduce the strength of the floor slab, but also reduce the bearing capacity of the floor slab, resulting in quality risks. Therefore, it is necessary to develop a new type of embedded parts. Utility Model Content

[0003] The purpose of the utility model is to provide a cantilever I-beam embedded part based on a composite slab, so as to solve the problem raised by the above background technology that in the traditional cast-in-place structure on the market, the I-beam of the cantilever scaffolding is fixed by using U-bolts embedded in the floor slab in the early stage; but the composite slab structure divides the floor slab into two layers, the lower layer is the composite slab, which does not allow holes or chiseling, and the upper layer is a cast-in-place structure with an anti-cracking steel mesh. The U-bolts used to support the cantilever external frame are difficult to be reliably anchored in this layer. When the anchor point of the cantilever I-beam is stressed, the concrete of the cast-in-place layer of the composite slab will be torn, causing the floor slab to crack, which will not only reduce the strength of the floor slab, but also damage the main body of the floor slab and greatly reduce the bearing capacity of the floor slab.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a cantilever I-beam embedded part based on a composite plate, comprising a prefabricated part, a concrete layer is installed on the prefabricated part, and a U-shaped bolt is fixed inside the concrete layer;

[0005] An embedded part is fixed inside the prefabricated part, an embedded plate is welded on the embedded part, the embedded plate and the U-bolt are installed by welding, a concrete layer is poured on the embedded plate, and the U-bolt is limited and fixed by the solidification of the concrete.

[0006] Preferably, a composite plate is installed on the outer side of the prefabricated part, the embedded plate is fixed on the inner surface of the prefabricated part, a cast-in-place plate is arranged on the side of the concrete layer, and the concrete layer is formed by pouring concrete, so that the overall stability is greatly improved.

[0007] Preferably, the U-shaped bolt comprises: a straight edge section, a steel anchor and a threaded section, and the straight edge section is welded to the embedded plate, which reduces the inconvenience of quality control caused by on-site casting after welding.

[0008] Preferably, steel anchors are welded on the straight edge section, and the steel anchors are two 18-diameter third-level steel anchors. The steel anchors are fixed inside the concrete layer, and the steel anchors make the connection more stable.

[0009] Preferably, a threaded section is welded to the top of the steel anchor, and a washer runs through the threaded section, so that the washer facilitates fixing the pressure plate.

[0010] Preferably, a fixing bolt is threadedly connected to the threaded section, and a pressure plate is connected to the threaded section, and the fixing bolt facilitates the installation of the pressure plate.

[0011] Preferably, an I-beam is installed at the bottom of the pressure plate, and the I-beam is connected to the pressure plate through a screw rod. A nut is threadedly connected to the bottom end of the screw rod, so that the I-beam is easy to install.

[0012] Compared with the prior art, the utility model has the following beneficial effects: the cantilever I-beam embedded parts based on the composite plate are convenient for later installation and use after the prefabricated parts are processed and manufactured in the factory, which reduces the problem that all the traditional cast-in-place concrete structures need to be completed on site and the quality control is difficult. The steel anchors on the straight edge section of the U-bolt are two 18-diameter third-level steel anchors, which greatly enhance the stability of the U-bolt and reduce the problem of penetrating the floor slab and causing the quality of the floor slab to be reduced. The prefabricated parts and the concrete layer are used for joint anchoring and force bearing, which can well ensure the construction safety. The specific contents are as follows:

[0013] (1) The steel anchors on the straight edge of the U-bolt are two 18-diameter grade 3 steel anchors, which greatly enhance the stability of the U-bolt and reduce the need to penetrate the floor slab, which leads to the problem of reduced floor structure quality. Therefore, the U-bolt is fixed in the concrete layer, which reduces the problem of cracking the existing concrete when the I-beam anchor point is stressed in the later stage.

[0014] (2) During the construction period in the factory, the embedded parts and embedded plates are embedded according to the planned parts, and are produced together with the composite plates. The production of prefabricated parts is convenient for later installation and use after processing and manufacturing in the factory, which reduces the problem of traditional cast-in-place concrete structures that all need to be completed on site and quality control is difficult;

[0015] (3) Weld the straight edge section of the U-bolt to the surface of the embedded plate, connect it with the U-bolt by welding, increase the anchoring length and depth of the U-bolt in the overall floor slab, and increase construction safety;

[0016] (4) The fixing bolts on both sides of the pressure plate fix it and install it, which greatly improves the overall installation stability;

[0017] (5) The screw and nut cooperate to install the I-beam at the bottom of the pressure plate. After the I-beam is installed and fixed, it is convenient to erect the cantilever scaffolding outside the building later. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0019] Figure 2 This is a schematic diagram of the internal structure of the utility model;

[0020] Figure 3 This is a schematic diagram of the U-bolt structure of the utility model;

[0021] Figure 4 It is a schematic diagram of the partially split structure of the utility model;

[0022] Figure 5 For this utility model Figure 3 Enlarged structural diagram at A in the middle.

[0023] In the figure: 1. Prefabricated parts; 2. Composite plates; 3. Embedded parts; 4. Embedded plates; 5. Concrete layer; 6. Cast-in-place plates; 7. U-bolts; 701. Straight edge sections; 702. Steel anchors; 703. Threaded sections; 8. Pressure plates; 9. Washers; 10. Fixing bolts; 11. I-beams; 12. Screw rods; 13. Nuts. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] See also Figure 1-Figure 5 The utility model provides a technical solution: a cantilever I-beam embedded part based on a composite plate, including a prefabricated part 1, a concrete layer 5 is installed on the prefabricated part 1, U-bolts 7 are fixed inside the concrete layer 5, an embedded part 3 is fixed inside the prefabricated part 1, an embedded plate 4 is welded on the embedded part 3, the embedded plate 4 and the U-bolts 7 are installed by welding, a concrete layer 5 is cast on the embedded plate 4, and the U-bolts 7 are limited and fixed by concrete solidification.

[0026] Embodiment 1:

[0027] like Figure 1 and Figure 2The technical scheme shown in the utility model provides a technical scheme: a cantilever I-beam embedded part based on a composite plate, which discloses: a composite plate 2 is installed on the outside of the prefabricated part 1, the embedded plate 4 is fixed on the inner surface of the prefabricated part 1, and a cast-in-place plate 6 is arranged on the side of the concrete layer 5. First, the project technicians and on-site personnel are organized to determine the relevant data of the overall structure according to the engineering design drawings and related materials, and accurately draw the molding mold drawings. At this time, the prefabricated part 1 is produced according to the drawings. During the construction of the prefabricated part 1 in the factory, the embedded parts 3 and the embedded plates 4 are embedded according to the planned parts, and they are produced and formed together with the composite plate 2. The production of the component 1 is convenient for later installation and use after processing and manufacturing in the factory, which reduces the problem of difficult quality control in traditional cast-in-place concrete structures that all need to be completed on-site, saving construction time and labor, reducing the impact on the surrounding environment and the steps of on-site quality control. The technical personnel locate the operation position according to the arrangement of the I-beam 11, and avoid the conflict between the cantilever channel steel and the column and shear wall during the positioning process. By optimizing the layout, the cast-in-place beams and plates are used as the anchoring positions of the U-bolts 7 as much as possible, which enhances the overall stability and reduces the instability caused by fewer support points during the limit.

[0028] Embodiment 2:

[0029] like Figure 1-Figure 3 The technical scheme shown in the utility model provides a technical scheme: a cantilever I-beam embedded part based on a composite plate, discloses: a U-bolt 7, including: a straight edge section 701, a steel anchor 702 and a threaded section 703, the straight edge section 701 is welded on the embedded plate 4, the straight edge section 701 is welded with a steel anchor 702, and the steel anchor 702 is two 18-diameter third-level steel anchors 702, the steel anchor 702 is fixed inside the concrete layer 5, the concrete slurry and rust on the surface of the embedded plate 4 are cleaned, and after cleaning, the straight edge section 701 of the U-bolt 7 is welded to the surface of the embedded plate 4, and is connected to the U-bolt 7 by welding, so as to increase the anchoring length and depth of the U-bolt 7 in the overall floor slab, increase the construction safety, and after welding, it is in the cast-in-place plate 6 The U-bolt 7 is poured with concrete, and mechanical vibration is used during the pouring process. A special person is responsible for checking whether the U-bolt 7 is displaced or skewed. After the overall pouring is completed, maintenance treatment is required in time to improve the quality of the component. The poured concrete forms a concrete layer 5 after solidification. Since the steel anchor 702 on the straight edge section 701 of the U-bolt 7 is two 18-diameter third-level steel anchors 702, the stability of the U-bolt 7 is greatly enhanced, and the problem of penetrating the floor slab and causing the quality of the floor slab structure to be reduced is reduced. Therefore, the U-bolt 7 is fixed in the concrete layer 5, which reduces the problem of cracking the existing concrete when the anchor point of the I-beam 11 is subjected to force in the later stage, greatly enhancing the stability of the U-bolt 7. The prefabricated component 1 and the concrete layer 5 are used for joint anchoring and force bearing, which can well ensure the construction safety.

[0030] Embodiment three:

[0031] like Figure 1 , Figure 4 and Figure 5 The technical scheme shown in the utility model provides a technical scheme: a cantilever I-beam embedded part based on a composite plate, which discloses: a threaded section 703 is welded on the top of a steel anchor 702, a washer 9 is penetrated through the threaded section 703, a fixing bolt 10 is threadedly connected to the threaded section 703, a pressing plate 8 is connected to the threaded section 703, an I-beam 11 is installed at the bottom of the pressing plate 8, the I-beam 11 is penetrated and connected to the pressing plate 8 through a screw rod 12, a nut 13 is threadedly connected to the bottom end of the screw rod 12, and after the strength of the concrete layer 5 reaches the requirement, the fixing bolt 10 is screwed into the U-bolt 7 The threaded section 703 is connected to the washer 9 through the threaded section 703, and the washer 9 is inserted into the upper end. The washer 9 is connected to the pressure plate 8 through the threaded section 703. The washer 9 and the fixing bolts 10 are introduced into the pressure plate 8 in sequence. At this time, the pressure plate 8 is fixed and installed by the fixing bolts 10 on both sides of the pressure plate 8, so that the overall installation stability is greatly improved. After installation, the I-beam 11 is installed at the bottom of the pressure plate 8 using the screw 12 and the nut 13. After the I-beam 11 is installed and fixed, it is convenient to erect the external cantilever scaffolding of the building later. The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

[0032] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art may still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A cantilever I-beam embedded part based on a composite plate, comprising a prefabricated part (1), a concrete layer (5) being installed on the prefabricated part (1), and a U-shaped bolt (7) being fixed inside the concrete layer (5); It is characterized in that Also includes: An embedded part (3) is fixed inside the prefabricated part (1), an embedded plate (4) is welded to the embedded part (3), and the embedded plate (4) is installed with the U-shaped bolt (7) by welding; A concrete layer (5) is poured on the embedded plate (4), and the U-shaped bolts (7) are fixed in position through the setting of the concrete.

2. The cantilever I-beam embedded part based on the composite plate according to claim 1, Features: A composite plate (2) is installed on the outside of the prefabricated component (1), the embedded plate (4) is fixed on the inner surface of the prefabricated component (1), and a cast-in-place plate (6) is arranged on the side of the concrete layer (5).

3. The cantilever I-beam embedded part based on the composite plate according to claim 1, Features: The U-shaped bolt (7) comprises a straight edge section (701), a steel anchor (702) and a threaded section (703); the straight edge section (701) is welded to the embedded plate (4).

4. The cantilever I-beam embedded part based on the composite plate according to claim 3, Features: Steel anchors (702) are welded on the straight edge section (701), and the steel anchors (702) are two 18-diameter third-level steel anchors (702), and the steel anchors (702) are fixed inside the concrete layer (5).

5. The cantilever I-beam embedded part based on the composite plate according to claim 4, Features: A threaded section (703) is welded to the top of the steel anchor (702), and a washer (9) penetrates through the threaded section (703).

6. The cantilever I-beam embedded part based on the composite plate according to claim 5, Features: A fixing bolt (10) is threadedly connected to the threaded section (703), and a pressing plate (8) is connected to the threaded section (703).

7. The cantilever I-beam embedded part based on the composite plate according to claim 6, Features: An I-beam (11) is installed at the bottom of the pressing plate (8), and the I-beam (11) is connected to the pressing plate (8) through a screw rod (12), and a nut (13) is threadedly connected to the bottom end of the screw rod (12).