Novel PVC (polyvinyl chloride) plate-penetrating water stop sleeve

Through the design of pre-embedded pipe sections and adjustable pipe sections of the new PVC water-stopping casing, the problems of secondary pouring and height adjustment during the construction of balcony drainage pipes passing through the floor are solved, the casing is stabilized and height adjusted, and construction is simplified. Steps to improve waterproof quality and acceptance compliance.

CN221800865UActive Publication Date: 2024-10-01ZHUHAI NIANSHUN CONSTR CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420150813.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-22
Publication Date
2024-10-01
Estimated Expiration
2034-01-22

AI Technical Summary

Technical Problem

In high-rise buildings, when the balcony drainage pipes are constructed through the floor slabs, waterproof fine stone concrete needs to be poured twice to fix the casing, which makes the construction difficult and the quality difficult to guarantee. At the same time, the height of the casing must meet the acceptance specifications, which requires the construction workers to make multiple adjustments. Affect construction efficiency and quality.

Method used

Design a new type of PVC through-plate water-stop casing, including a pre-embedded pipe section, an adjustable pipe section and a water-stop ring. The pipe wall of the pre-embedded pipe section is equipped with fixed protrusions and thread structures, combined with the casing cover and asphalt grease, The embedded pipe sections are embedded before concrete pouring to ensure a fixed and adjustable height to avoid the impact of secondary pouring and meet acceptance requirements.

Benefits of technology

Through the setting of embedded pipe sections and fixed casing after concrete pouring, waterproofing construction is simplified and the waterproof quality is ensured. The height of the casing is adjusted through adjustable pipe sections to meet the acceptance specifications and improve construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221800865U_ABST
    Figure CN221800865U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of buildings, and particularly relates to a novel PVC (polyvinyl chloride) plate-penetrating water stop sleeve which comprises an embedded pipe section, an adjustable pipe section is arranged above the embedded pipe section, and a first thread structure is arranged on the embedded pipe section; according to the plate-penetrating water stop sleeve, through the arrangement of the first thread structure on the embedded pipe section, the embedded pipe section can be matched with the sleeve cover when concrete pouring is conducted on a floor, it is ensured that the embedded pipe section can be smoothly fixed to the floor, and the influence of concrete pouring on follow-up pipeline construction is avoided; and the embedded pipe section can be matched with the adjustable pipe section during pipeline construction, so that the distance between the highest position of the sleeve and a floor decoration finished surface can be adjusted, and the highest position of the sleeve needs to be higher than the distance between the floor decoration finished surface after construction is completed, so that the acceptance requirement is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of construction, and in particular relates to a novel PVC plate-penetrating water-stopping sleeve. Background Art

[0002] In high-rise buildings, balcony drain pipes need to pass through the floor slab to discharge rainwater or sewage into the drainage system downstairs. In the construction of drain pipes passing through the floor slab, it is required to leave pipe holes or reserved holes in the corresponding positions of the floor slab template before the floor slab construction; when the pipeline is constructed, it is necessary to place metal sleeves or plastic sleeves in the reserved holes of the floor slab to ensure that there will be no leakage after the drainage pipe construction is completed; when placing metal sleeves or plastic sleeves in the reserved holes, it is necessary to adjust the sleeve top elevation according to the finished elevation of the decoration floor (the specification is that the highest point of the sleeve is 50mm higher than the finished surface of the floor slab decoration), and then cast the fixed sleeve with waterproof fine stone concrete for the second time; after the sleeve is fixed, the drain pipe passes through the sleeve, and the gap between the sleeve and the drain pipe is sealed with hemp mixed cement slurry, and finally sealed with asphalt paste.

[0003] In the above-mentioned construction of the drainage pipe through the board, there are the following problems: First, it is necessary to cast waterproof fine stone concrete twice to fix the casing to ensure the waterproof quality after the pipeline construction; the construction process of the pipeline also requires secondary pouring of concrete, which makes the construction difficult and the quality difficult to guarantee. Second, the highest point of the casing required by the specification must be 50mm higher than the finished surface of the floor decoration. In order to make the setting of the casing meet the acceptance specifications, the construction personnel need to pay attention to the setting of the casing many times during the construction process; if the height difference between the highest point of the casing and the finished surface of the floor decoration is no more than 50mm after the subsequent construction is completed, it will cause the construction to fail to meet the acceptance specifications, making it impossible for the construction project to be quickly accepted. Utility Model Content

[0004] In view of this, the purpose of the utility model is to provide a new PVC plate-penetrating water-stopping sleeve that can solve the problems existing in the above-mentioned prior art.

[0005] In order to solve the above technical problems, the technical solution of the utility model is a new type of PVC through-board water-stop sleeve, including a pre-buried pipe section, a fixed protrusion on the pipe wall of the pre-buried pipe section, an adjustable pipe section is arranged above the pre-buried pipe section, a limiting protrusion is arranged on the pipe wall of the adjustable pipe section, a water-stop ring is arranged above the limiting protrusion, asphalt paste is filled above the limiting protrusion and the water-stop ring, and a closing cover is arranged below the pre-buried pipe section.

[0006] Preferably, the fixing protrusion is arranged in an annular shape, the fixing protrusion is located on the outer surface of the embedded pipe section, and a plurality of the fixing protrusions are arranged; the limiting protrusion is arranged in an annular shape, and the limiting protrusion is located on the inner surface of the adjustable pipe section.

[0007] Preferably, the embedded pipe section has a first thread structure, the adjustable pipe section has a second thread structure, and the embedded pipe section and the adjustable pipe section are movably connected by the first thread structure and the second thread structure.

[0008] Furthermore, the first thread structure is located at the top of the embedded pipe section, the first thread structure is an internal thread structure, the second thread structure is located at the bottom of the adjustable pipe section, the second thread structure is an external thread structure, and the first thread structure and the second thread structure are adapted to each other.

[0009] Preferably, the device further comprises a sleeve cover, wherein the sleeve cover has a third thread structure.

[0010] Furthermore, the sleeve cover is used in conjunction with the embedded pipe section, the sleeve cover is arranged above the embedded pipe section, the third threaded structure is located at the bottom end of the sleeve cover, the third threaded structure is an external threaded structure, and the third threaded structure and the first threaded structure are adapted to each other.

[0011] The technical effects of the utility model are mainly reflected in the following aspects: the through-plate water-stop sleeve is provided with a pre-buried pipe section, so that the sleeve is pre-buried in the early stage of concrete construction so that the pre-buried pipe section can be fixed in the concrete after the floor slab is poured; to solve the problem that waterproof fine stone concrete needs to be poured twice to fix the sleeve during pipeline construction to ensure the waterproof quality after pipeline construction. By setting the first threaded structure on the pre-buried pipe section, not only can the pre-buried pipe section cooperate with the sleeve cover when the concrete is poured on the floor slab, ensuring that it can be smoothly fixed to the floor slab and avoiding the influence of concrete pouring on subsequent pipeline construction; the pre-buried pipe section can also cooperate with the adjustable pipe section during pipeline construction, so that the distance between the highest point of the sleeve and the finished decorative surface of the floor slab can be adjusted, so that the distance between the highest point of the sleeve and the finished decorative surface of the floor slab after the construction is completed meets the acceptance requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a structural diagram of a new type of PVC plate-penetrating water-stopping sleeve of the utility model;

[0013] Figure 2 This is an exploded view of the local structure of a new type of PVC plate-penetrating water-stopping sleeve of the utility model;

[0014] Figure 3 This is a structural schematic diagram of a pre-buried pipe section and a casing cover in a new type of PVC plate-penetrating water-stop casing of the utility model;

[0015] In the figure: 1. embedded pipe section, 11. fixed protrusion, 12. first threaded structure; 2. adjustable pipe section, 21. limiting protrusion, 22. second threaded structure; 3. water stop ring; 4. asphalt paste; 5. closing cover; 6. casing cover, 61. third threaded structure; 7 drainage pipe; 8. floor slab. DETAILED DESCRIPTION

[0016] The specific implementation modes of the present invention are further described below in conjunction with the accompanying drawings to make the technical solutions of the present invention easier to understand and grasp.

[0017] In this embodiment, it should be understood that the terms "middle", "upper", "lower", "top", "right", "left end", "above", "back", "middle", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0018] In addition, in this specific embodiment, if the connection or fixing method between components is not specifically described, the connection or fixing method can be through bolt fixing or pin fixing, or pin shaft connection and the like commonly used in the prior art, and therefore, it will not be described in detail in this embodiment.

[0019] A new type of PVC plate-penetrating waterproof casing, including a pre-buried pipe section 1, referring to Figure 1 , the embedded pipe section 1 is arranged in the floor 8; the embedded pipe section 1 is placed in the installation position of the drainage pipe 7 for the floor 8 in the early stage of concrete construction and then the concrete is poured. The embedded pipe section 1 can be fixed in the floor 8 after the floor 8 is poured by embedding in the early stage of concrete construction; so as to solve the problem that the casing needs to be fixed by pouring waterproof fine stone concrete for the second time during pipeline construction to ensure the waterproof quality after pipeline construction. The wall of the embedded pipe section 1 has a fixing protrusion 11, which is arranged in an annular shape and is located on the outer surface of the embedded pipe section 1. There are several fixing protrusions 11; the fixing protrusion 11 can improve the structural connection strength between the embedded pipe section 1 and the floor 8, ensure that the connection and fixation of the embedded pipe section 1 are firm, not only can it prevent the embedded pipe section 1 from loosening and falling off after the concrete pouring of the floor 8 is completed, but also can ensure the waterproof quality of the connection between the casing and the floor 8 after the pipeline construction, simplifying the pipeline construction steps and ensuring the quality of pipeline construction.

[0020] Reference Figure 2The embedded pipe section 1 has a first thread structure 12, which is located at the top of the embedded pipe section 1 and is an internal thread structure. The first thread structure 12 can not only ensure that the embedded pipe section 1 can be smoothly fixed to the floor slab 8 when the floor slab 8 is poured with concrete, but also avoid the influence of concrete pouring on the subsequent pipeline construction (refer to Figure 3 ); It can also make the pre-buried pipe section 1 and the adjustable pipe section 2 cooperate during the pipeline construction, so that the distance between the highest point of the casing and the finished decorative surface of the floor 8 can be adjusted, so that after the construction is completed, the distance between the highest point of the casing and the finished decorative surface of the floor 8 must meet the acceptance requirements (refer to Figure 1 , 2 ).

[0021] It also includes a casing cover 6, which is used in conjunction with the pre-buried pipe section 1 when it is pre-buried in the early stage of concrete construction. Figure 3 Before the concrete construction of the floor 8, the sleeve cover 6 and the embedded pipe section 1 are combined, and then placed at the installation position of the drain pipe 7 to complete the concrete pouring; the setting of the sleeve cover 6 allows construction workers to pour concrete without having to worry about concrete entering the embedded pipe section 1, and avoids the situation where the subsequent pipeline construction sleeve cannot be used normally due to the solidification of concrete in the embedded pipe section 1. The sleeve cover 6 has a third threaded structure 61. The sleeve cover 6 is used in conjunction with the embedded pipe section 1, and the sleeve cover 6 is arranged above the embedded pipe section 1. The third threaded structure 61 is located at the bottom end of the sleeve cover 6. The third threaded structure 61 is an external threaded structure, and the third threaded structure 61 and the first threaded structure 12 are adapted to each other. The sleeve cover 6 and the embedded pipe section 1 are fixed by threaded connection, and when concrete is poured on the floor slab 8, the sleeve cover 6 and the embedded pipe section 1 cooperate to allow the embedded pipe section 1 to be embedded on the floor slab 8; when the concrete pouring of the floor slab 8 is completed or before the pipeline construction, the sleeve cover 6 can be removed from the embedded pipe section 1, so that the subsequent pipeline construction can proceed smoothly.

[0022] Reference Figure 1, an adjustable pipe section 2 is arranged above the embedded pipe section 1, a limiting protrusion 21 is provided on the pipe wall of the adjustable pipe section 2, a water stop ring 3 is arranged above the limiting protrusion 21, asphalt paste 4 is filled above the limiting protrusion 21 and the water stop ring 3, and a closing cover 5 is arranged below the embedded pipe section 1; specifically, during the pipeline construction, the water stop ring 3 is inserted into the drainage pipe 7, and the drainage pipe 7 passes through the embedded pipe section 1 and the adjustable pipe section 2, the water stop ring 3 is located between the limiting protrusion 21 and the drainage pipe 7, and the asphalt paste 4 is filled between the limiting protrusion 21 and the adjustable pipe section 2 and the drainage pipe 7 above the water stop ring 3. When installing the embedded pipe section 1 and the adjustable pipe section 2, liquid raw tape is applied to the connection between the two to prevent leakage; liquid raw tape is a paving material used to ensure a good sealing effect at the pipeline connection after the pipeline construction is completed, which will not be described in detail here. In addition, in the traditional pipeline construction, the gap between the casing and the drain pipe 7 is sealed with hemp mixed with cement slurry, and finally closed with asphalt paste 4; the casing adopts a water stop ring 3 to act on the gap between the casing and the drain pipe 7, and the water stop ring 3 replaces the mixture of hemp and cement slurry; while not affecting the sealing of the gap between the casing and the drain pipe 7 or even improving the sealing degree of the gap between the two, it also simplifies the steps of pipeline construction, further solves the difficulties of pipeline construction and ensures the quality of pipeline construction. The subsequent use of asphalt paste 4 to close the end is no different from that in traditional pipeline construction, and is not repeated here.

[0023] The limiting protrusion 21 is arranged in an annular shape and is located on the inner surface of the adjustable pipe section 2. The adjustable pipe section 2 has a second thread structure 22, which is located at the bottom end of the adjustable pipe section 2. The second thread structure 22 is an external thread structure, and the first thread structure 12 and the second thread structure 22 are adapted to each other. The embedded pipe section 1 and the adjustable pipe section 2 are movably connected by the first thread structure 12 and the second thread structure 22. The embedded pipe section 1 and the adjustable pipe section 2 are movably connected by the first threaded structure 12 and the second threaded structure 22, so that the construction personnel can adjust the distance between the highest point of the casing and the decorative finish surface of the floor 8 through the cooperation of the first threaded structure 12 and the second threaded structure 22, so as to adjust the distance between the highest point of the casing and the decorative finish surface of the floor 8 to meet the requirements of the acceptance specifications during the pipeline construction process; to solve the problem that during the pipeline construction, in order to make the setting of the casing meet the acceptance specifications, the construction personnel need to pay attention to the setting height of the casing many times during the construction process, and when the height difference between the highest point of the casing and the decorative finish surface of the floor 8 does not meet the acceptance specifications after the subsequent construction is completed, it will cause the construction to fail to meet the acceptance specifications, making the construction project unable to be quickly accepted.

[0024] The technical effects of the utility model are mainly reflected in the following aspects: the through-plate water-stop sleeve is provided with a pre-buried pipe section, so that the sleeve is pre-buried in the early stage of concrete construction so that the pre-buried pipe section can be fixed in the concrete after the floor slab is poured; to solve the problem that waterproof fine stone concrete needs to be poured twice to fix the sleeve during pipeline construction to ensure the waterproof quality after pipeline construction. By setting the first threaded structure on the pre-buried pipe section, not only can the pre-buried pipe section cooperate with the sleeve cover when the concrete is poured on the floor slab, ensuring that it can be smoothly fixed to the floor slab and avoiding the influence of concrete pouring on subsequent pipeline construction; the pre-buried pipe section can also cooperate with the adjustable pipe section during pipeline construction, so that the distance between the highest point of the sleeve and the finished decorative surface of the floor slab can be adjusted, so that the distance between the highest point of the sleeve and the finished decorative surface of the floor slab after the construction is completed meets the acceptance requirements.

[0025] Of course, the above are only typical examples of the present invention. In addition, the present invention can also have many other specific implementation methods. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention.

Claims

1. A new type of PVC plate-penetrating waterproof casing, characterized by: It includes a pre-buried pipe section, the pipe wall of the pre-buried pipe section is provided with a fixed protrusion, an adjustable pipe section is arranged above the pre-buried pipe section, the pipe wall of the adjustable pipe section is provided with a limiting protrusion, a water stop ring is arranged above the limiting protrusion, asphalt paste is filled above the limiting protrusion and the water stop ring, and a closing cover is arranged below the pre-buried pipe section.

2. A novel PVC plate-penetrating waterproof casing as claimed in claim 1, characterized in that: The fixing protrusion is arranged in an annular shape, and the fixing protrusion is located on the outer surface of the embedded pipe section, and a plurality of the fixing protrusions are arranged; the limiting protrusion is arranged in an annular shape, and the limiting protrusion is located on the inner surface of the adjustable pipe section.

3. A novel PVC plate-penetrating waterproof casing as claimed in claim 1, characterized in that: The pre-buried pipe section has a first thread structure, the adjustable pipe section has a second thread structure, and the pre-buried pipe section and the adjustable pipe section are movably connected by the first thread structure and the second thread structure.

4. A new type of PVC plate-penetrating waterproof casing as claimed in claim 3, characterized in that: The first thread structure is located at the top of the embedded pipe section, and the first thread structure is an internal thread structure. The second thread structure is located at the bottom of the adjustable pipe section, and the second thread structure is an external thread structure. The first thread structure and the second thread structure are adapted to each other.

5. A novel PVC plate-penetrating waterproof casing as claimed in claim 1, characterized in that: It also includes a sleeve cover, which has a third thread structure on it.

6. A novel PVC plate-penetrating waterproof casing as claimed in claim 5, characterized in that: The sleeve cover is used in conjunction with the embedded pipe section. The sleeve cover is arranged above the embedded pipe section. The third threaded structure is located at the bottom end of the sleeve cover. The third threaded structure is an external threaded structure. The third threaded structure and the first threaded structure are adapted to each other.

Citation Information

Cited By

  • Concealed cavity installation construction method for air conditioner condenser pipe

    CN119981435A