Sludge dredging device of slag extractor

By installing a water replenishing tank and a crank connection component inside the slag discharger, and using the crank to drive the dredge rod to clean the sludge, the problem of low water level and siltation blockage in the slag discharger is solved, ensuring smooth water channels, reducing manual cleaning work, and improving the stability and stability of the unit. Operating economy.

CN221801821UActive Publication Date: 2024-10-01WEIXIAN SHENZHEN ENERGY ENVIRONMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420182043.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-25
Publication Date
2024-10-01
Estimated Expiration
2034-01-25

AI Technical Summary

Technical Problem

After the existing slag discharging machine blows soot on the heating surface or the water tank is clogged, the water level will be low, the water seal will be destroyed, the negative pressure of the unit will be unstable, and the power consumption will be increased. Frequent manual water replenishment and sludge cleaning are required, which is time-consuming and labor-intensive, affecting the power plant. Economic operation.

Method used

Design a sludge dredging device for the slag discharger, which includes a water replenishing tank and a crank connection assembly installed inside the slag discharger. The crank is used to drive the dredging rod to reciprocate when the slag discharger is running to clean the silt and debris at the outlet of the water replenishing tank. to ensure smooth flow of waterways.

Benefits of technology

The internal water channel of the slag discharging machine is unobstructed, which reduces the workload of manual sludge cleaning, ensures the stable operation of the unit, reduces power consumption, avoids water seal damage, and improves the economic efficiency of operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221801821U_ABST
    Figure CN221801821U_ABST
Patent Text Reader

Abstract

The utility model provides a sludge dredging device of a slag extractor, the slag extractor comprises a water replenishing tank arranged in the slag extractor, the bottom of the water replenishing tank is provided with a water outlet in a body for replenishing water to the slag extractor, and two sides of the slag extractor are respectively provided with a first external driving crank and a second external driving crank. The crank connecting assembly comprises a first connecting rod, a second connecting rod and a third connecting rod, and the first end of the first connecting rod and the first end of the second connecting rod are fixedly installed on the outer side of the first external driving crank and the outer side of the second external driving crank correspondingly. The two ends of the third connecting rod are fixedly connected with the second end of the first connecting rod and the second end of the second connecting rod respectively; the first end of the dredging rod is fixedly connected with the third connecting rod, and the second end of the dredging rod penetrates through the water outlet of the water replenishing tank, so that sludge and impurities at the water outlet of the water replenishing tank in the slag extractor can be continuously cleaned, the stability of a unit is greatly improved, and the workload of manually cleaning sludge is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of slag dischargers, in particular to a slag discharger sludge dredging device. Background Art

[0002] At present, due to the different forms of incineration grate structures selected by various operating companies, the selection of slag dischargers is also uneven. The fly ash treatment process of waste heat boilers in the garbage incineration industry is: superheater, economizer fly ash, ash discharge valve, buried ash conveyor, and slag discharger. The types of slag dischargers currently on the market include: Seegers, Ebara, Martin, etc. After the soot blowing on the heating surface is completed or the water tank is blocked, the water level of the slag discharger will be low, destroying the water seal. At this time, the negative pressure of the unit will be unstable and the power consumption of the induced draft fan will increase. In severe cases, the operating personnel need to manually add water, which invisibly increases the workload of the operating personnel. In severe cases, a special person is required to clean the sludge every 30 minutes, which is extremely time-consuming and labor-intensive. In the long run, it will pose a major hidden danger to the economic operation of the power plant. Utility Model Content

[0003] The utility model aims to provide a slag discharger sludge dredging device, which can solve the problem of ensuring that the internal waterway of the slag discharger is unobstructed.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] A slag discharger sludge dredging device is provided, wherein the slag discharger comprises a water supply tank arranged inside the slag discharger, a water outlet in the body of the slag discharger for supplying water to the slag discharger is arranged at the bottom of the water supply tank, and a first external active crank and a second external active crank are arranged on both sides of the slag discharger, respectively, comprising:

[0006] A crank connecting assembly, the crank connecting assembly comprising a first connecting rod, a second connecting rod and a third connecting rod, wherein the first end of the first connecting rod and the first end of the second connecting rod are respectively fixedly mounted on the outside of the first external active crank and the outside of the second external active crank, and the two ends of the third connecting rod are respectively fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod;

[0007] A dredging rod, wherein the first end of the dredging rod is fixedly connected to the third connecting rod, and the second end of the dredging rod passes through the water outlet of the water replenishing tank.

[0008] In some embodiments, the upper side of the first end of the dredging rod is serrated.

[0009] In some embodiments, a guide member is further included, wherein the guide member is fixedly mounted on the water replenishing tank, and the dredging rod passes through the guide member, and the guide member is used to prevent the dredging rod from deviating when performing a reciprocating motion.

[0010] In some embodiments, the guide member is a rail-holding spring, which includes a cylindrical shell and a spring disposed in the cylindrical shell.

[0011] In some embodiments, the water replenishment tank has a float for controlling the water level, the side wall of the water replenishment tank has a water replenishment port, and the water replenishment tank is also provided with a water replenishment and desilting groove, the first end of the water replenishment and desilting groove is fixedly connected to the lower side of the water replenishment port, and the second end of the water replenishment and desilting groove is arranged at the bottom of the float.

[0012] In some embodiments, the outer side of the first external active crank and the outer side of the second external active crank are respectively fixedly connected with a first pin and a second pin, the first end of the first connecting rod and the first end of the second connecting rod are respectively fixedly connected with a first connecting rod tee and a second connecting rod tee, the first connecting rod tee is fixedly sleeved with the first pin, and the second connecting rod tee is fixedly sleeved with the second pin.

[0013] In some embodiments, two ends of the third connecting rod are respectively fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod through a connecting rod tee.

[0014] In some embodiments, angular connecting pieces are respectively provided between the third connecting rod and the first connecting rod and the second connecting rod.

[0015] In some embodiments, the dredging rod is curved.

[0016] The utility model also provides a slag discharger, comprising a water replenishing tank arranged inside the slag discharger and the slag discharger sludge dredging device.

[0017] The utility model has the following beneficial effects:

[0018] The utility model fixes the first end of the first connecting rod and the first end of the second connecting rod of the crank connecting assembly to the outside of the first external active crank and the outside of the second external active crank, respectively, and the two ends of the third connecting rod are fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod, respectively, the first end of the dredging rod is fixedly connected to the third connecting rod, and the second end of the dredging rod passes through the water outlet of the water supply tank. The dredging rod can be driven to move by utilizing the inherent motion trajectory of the crank when the slag discharger is running, so that the dredging rod makes reciprocating motion at the water outlet, and dredges the slag discharger water supply tank with silt or debris, ensuring that the internal waterway of the slag discharger is unobstructed and the stable operation of the unit is ensured. The slag discharger sludge dredging device of the utility model can continuously clean the sludge and debris at the water outlet of the water supply tank in the slag discharger, and there is no need for excessive human work to clean the sludge in the water supply tank of the slag discharger, which greatly improves the stability of the unit and reduces the workload of manual cleaning of sludge.

[0019] Other beneficial effects of the embodiments of the present invention will be further described below. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a side view of the main body of the slag discharger in the prior art;

[0021] Figure 2 It is a side view of the main body of the slag discharger in the embodiment of the utility model;

[0022] Figure 3 It is a top view of the main body of the slag discharger in the embodiment of the utility model;

[0023] Figure 4 This is a side view of the connecting rod structure in the embodiment of the utility model;

[0024] Figure 5 It is a side view of the connection between the dredging rod and the third connecting rod in the embodiment of the utility model;

[0025] Figure 6 It is a side view of the water replenishment tank in the embodiment of the utility model.

[0026] Reference numerals

[0027] 11-first pin shaft, 12-second pin shaft, 21-first external active crank, 22-second external active crank, 31-first connecting rod tee, 32-second connecting rod tee, 33-third connecting rod tee, 34-fourth connecting rod tee, 41-first connecting rod, 42-second connecting rod, 43-third connecting rod, 51-first angular connector, 52-second angular connector, 61-dredging rod, 71-rail pressure spring, 711-cylindrical shell, 712-spring, 81-water replenishment tank, 811-water outlet, 812-water replenishment port, 813-float, 814-water replenishment and dredging trough. DETAILED DESCRIPTION

[0028] The following is a detailed description of the implementation of the utility model. It should be emphasized that the following description is only exemplary and is not intended to limit the scope and application of the utility model.

[0029] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element. In addition, connection can be used for fixing as well as for coupling or communication.

[0030] It should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the utility model.

[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present utility model, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined.

[0032] In the prior art, the slag discharger is mainly used to separate solid materials of a certain particle size from a liquid and solid mixture. In a waste incineration power plant, it is used to discharge the ash and slag after the domestic waste is burned out in the incinerator. It is also used as a water seal between the conveying system and the slag hopper of the incinerator. The main functions of the slag discharger are to cool the high-temperature slag, drain the slag seal, and isolate the air flow.

[0033] The slag discharger is located below the grate outlet of the waste incinerator. There are usually two slag dischargers at the outlet of the incinerator. The slag falls into the slag discharger through the slag discharge channel, where it is extinguished and cooled. A ram is installed inside the slag discharger to discharge the slag, and the ram is powered by hydraulic cylinders on the left and right sides.

[0034] The slag from the incinerator enters the slag discharger through the slag discharger inlet and is pushed toward the slag discharger outlet through the slag discharger ram. Each push is only pushed a certain distance. After the driving cylinder reaches its stroke, the push mechanism returns to the initial position, and the pushed slag stays at the original position. After the push mechanism reaches the initial position, the next push stroke begins. After multiple push strokes, the pushed slag gradually accumulates and compresses and exposes the cooling water level inside the slag discharger for dehydration and discharge from the discharge port.

[0035] In order to reduce the situation that the sludge in the slag discharger blocks the water supply tank during operation, the sludge needs to be manually dredged and the water supply needs to be manually performed, and to maintain the normal operating negative pressure of the unit, the utility model provides a slag discharger sludge dredging device for online cleaning of sludge as the hydraulic cylinder of the slag discharger moves. The slag discharger includes a water supply tank arranged inside the slag discharger, and a water outlet in the body of the slag discharger is arranged at the bottom of the water supply tank to supplement water source to the slag discharger. The first external active crank and the second external active crank are respectively arranged on both sides of the slag discharger. The slag discharger sludge dredging device in this embodiment includes:

[0036] A crank connecting assembly, the crank connecting assembly comprising a first connecting rod, a second connecting rod and a third connecting rod, wherein the first end of the first connecting rod and the first end of the second connecting rod are respectively fixedly mounted on the outside of the first external active crank and the outside of the second external active crank, and the two ends of the third connecting rod are respectively fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod;

[0037] A dredging rod, wherein the first end of the dredging rod is fixedly connected to the third connecting rod, and the second end of the dredging rod passes through the water outlet of the water replenishment tank.

[0038] The device adopts the structural mode of mechanical connecting rod + hydraulic movement. In the prior art, the structure of the slag discharger body and the water supply tank is Figure 1 As shown, the side view of the slag discharger after the slag dredging device of the utility model is installed is Figure 2 , the top view is Figure 3 That is, a pin is welded at the active crank of the slag discharger, and then a connecting rod is used to cover the pin, and the connecting rod and the dredging rod are integrated. When the slag discharger is in operation, the silt or debris inside the water supply tank and the main body of the slag discharger are dredged through mechanical connecting rods at different locations in different areas to ensure that the waterway inside the main body of the slag discharger is unobstructed and the water seal inside the water supply tank will not be damaged when the slag discharger is in operation. In this way, the waterway is always in a smooth state during the continuous operation of the slag discharger, and the negative pressure of the unit is kept stable.

[0039] Specifically, the installation relationship of the various components of the slag discharger sludge dredging device in the embodiment of the utility model is as follows:

[0040] 1.1 Installation of the pin

[0041] The pin shaft of the utility model embodiment includes a first pin shaft 11 and a second pin shaft 12. Figure 3 As shown, the first pin 11 and the second pin 12 are respectively fixedly connected to the outside of the first external active crank 21 and the outside of the second external active crank 22. The fixing method is welding in the embodiment of the utility model, and it can also be other connection methods that meet the fixing requirements. The external active crank is a connecting device, which is connected to the main shaft of the slag discharger inside and connected to the hydraulic device outside, playing the role of power transmission. The pin is installed on the outside and will not affect the normal operation of the first external active crank 21 and the second external active crank 22 driven by the hydraulic power. The first pin 11 and the second pin 12 are pins of the same model in the embodiment of the utility model.

[0042] 1.2 Installation of connecting rod tee

[0043] The connecting rod tee of the embodiment of the utility model comprises a first connecting rod tee 31 and a second connecting rod tee 32. Figure 4As shown, specifically, the first end of the first connecting rod 41 and the first end of the second connecting rod 42 are fixedly connected to the first connecting rod tee 31 and the second connecting rod tee 32 respectively, and the two ends of the third connecting rod 43 are fixedly connected to the second end of the first connecting rod 41 through the first connecting rod tee 31 and the second end of the second connecting rod 42 through the second connecting rod tee 32 respectively. The first connecting rod tee 31 is fixedly sleeved on the first pin shaft 11, and the second connecting rod tee 32 is fixedly sleeved on the second pin shaft 12. The connecting rod tees can also be interchangeably mounted without any process. Some lubricating grease can be added to the connecting rod tee to reduce friction.

[0044] 1.3 Installation of crank connection assembly

[0045] The crank connecting assembly of the embodiment of the utility model comprises a first connecting rod 41, a second connecting rod 42, and a third connecting rod 43. Figure 4 As shown, the first connecting rod 41, the second connecting rod 42 and the third connecting rod 43, the first end of the first connecting rod 41 and the first end of the second connecting rod 42 are respectively fixedly installed on the outside of the first external active crank 21 and the outside of the second external active crank 22, and the two ends of the third connecting rod 43 are respectively connected and fixedly connected to the second end of the first connecting rod 41 and the second end of the second connecting rod 42 through the third connecting rod tee 33 and the fourth connecting rod tee 34. The fixed installation method in this embodiment is welding to achieve a reliable connection, and it can also be other connection methods that meet the fixing requirements.

[0046] 1.4 Installation of angle connectors

[0047] The angle connector of the utility model comprises a first angle connector 51 and a second angle connector 52. Figure 4 As shown, a first angular connector 51 is provided between the third connecting rod 43 and the first connecting rod 41, and the connection method in this embodiment is welding, and a second angular connector is provided between the third connecting rod 43 and the second connecting rod 42, and the connection method in this embodiment is welding. By welding the angular connector, a certain reinforcement effect can be achieved to prevent the first connecting rod 41 and the second connecting rod 42 from being unreliably connected when the first external active crank 21 and the second external active crank 22 drive the third connecting rod 43 to move synchronously with the hydraulic action.

[0048] 1.5 Installation of dredging rod 61

[0049] In the embodiment of the utility model, the dredging rod 61 is the main component, which plays the main role of dredging. The dredging rod 61 is a set of curved devices, and the upper side of the first end is a serrated shape with a wall-breaking effect, such as Figure 5As shown, the first end of the dredging rod 61 is fixedly connected to the third connecting rod 43, and the second end of the dredging rod 61 passes through the water outlet 811 of the water replenishment tank 81, so as to achieve the effect of dredging and adapt to water tanks of different sizes. The connection method between the dredging rod 61 and the third connecting rod 43 in the embodiment of the utility model is welding, and it can also be other connection methods that meet the fixing requirements. The welding point between the dredging rod 61 and the third connecting rod 43 needs to be associated with the layout of the water replenishment tank 81 on site, and there is no fixed welding position here.

[0050] 1.6 Installation of guide parts

[0051] like Figure 6 As shown, the guide member of the embodiment of the utility model is a rail-pressing spring 71, which includes a cylindrical shell 711 and a spring 712 disposed in the cylindrical shell 711. The rail-pressing spring 71 is fixed to the water replenishing tank 81, and the cylindrical shell 711 adjusts the trajectory of the action and plays a guiding role. The spring 712 in the body plays a buffering role. After the dredging rod 61 passes through the rail-pressing spring 71, the dredging rod 61 can be prevented from any deviation when performing a reciprocating action, thereby making the action smooth.

[0052] 1.7 Installation of water replenishment and desilting tank

[0053] like Figure 6 As shown, the slag discharger also includes a water replenishment tank 81 disposed inside the slag discharger, and the water replenishment tank 81 plays the role of water storage and buffering. The water replenishment tank 81 has a float 813 for controlling the water level, and the bottom of the water replenishment tank 81 is provided with a water outlet 811 in the body of the slag discharger for replenishing water. The side wall of the water replenishment tank 81 has a water replenishment port 812. The replenishment water source of the water replenishment tank 81 can be taken from the slag pool sewage reuse system or the industrial water system. Water is stored in the water replenishment tank 81, and water is replenished to the body of the slag discharger through the water outlet 811 at the bottom of the water replenishment tank 81, thereby ensuring that the slag discharger has sufficient water.

[0054] A water replenishment and desilting groove 814 is also provided in the water replenishment tank 81, which is used to change the direction of water flow, play a diversion role, and use the kinetic energy of water to clean the silt at the bottom of the float. The first end of the water replenishment and desilting groove 814 is fixedly connected to the lower side of the water replenishment port 812, and the second end of the water replenishment and desilting groove 814 is provided at the bottom of the float 813. The function of the water replenishment and desilting groove 814 is to change the direction of water replenishment, and to clean the silt at the bottom of the float 813 by using the flushing effect of water replenishment, thereby ensuring the effectiveness of the float 813.

[0055] The embodiment of the utility model further provides a slag discharger, comprising a water replenishment tank 81 arranged inside the slag discharger and a slag discharger sludge dredging device.

[0056] The installation process of this device is as follows: The slag discharger before installation is Figure 1 , Figure 3The top view of the slag discharger after installation. The pins are welded to both sides of the active crank, and then the connecting rod tee, connecting rod, dredging rod, etc. are installed in sequence, and initially fixed by inserting. At this time, the slag discharger can be slightly moved to observe whether there is any jamming, unsmoothness or mechanical friction during operation. After there is no problem, the angle connector is welded to the connecting rod. After the connection is stable, the slag discharger is moved again. After there is no jamming, unsmoothness or mechanical friction of the mechanical parts, the rail pressure spring 71 and the water replenishment and desilting groove 814 are connected to the water replenishment tank 81. At this time, the slag discharger can be operated continuously.

[0057] This utility model patent provides a device for uninterruptedly dredging the sludge and debris inside the slag discharger body, so that the unit can replenish water smoothly during operation, and will not be blocked by sludge, causing the water seal of the slag discharger to be damaged, affecting the negative pressure of the unit, and causing increased induced draft power consumption. Through mechanical connecting rods at different regional positions, the sludge or debris in the slag discharger water supply tank is dredged to ensure that there is no obstruction in the water channel inside the slag discharger body, and to ensure that the water seal inside the water tank will not be damaged when the slag discharger is in operation, to ensure the stable operation of the unit, and to achieve 24-hour uninterrupted cleaning of the slag discharger body sludge and debris, without the need for excessive manual cleaning of the sludge in the slag discharger water supply tank, which greatly improves the stability of the unit and reduces the workload of manual cleaning of sludge.

[0058] The above content is a further detailed description of the utility model in combination with specific / preferred embodiments, and it cannot be determined that the specific implementation of the utility model is limited to these descriptions. For ordinary technicians in the technical field to which the utility model belongs, without departing from the concept of the utility model, it can also make several substitutions or modifications to these described embodiments, and these substitutions or modifications should be regarded as belonging to the protection scope of the utility model. In the description of this specification, the description of the reference terms "an embodiment", "some embodiments", "preferred embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in combination with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily target the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In the absence of mutual contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples. Although the embodiments of the present invention and their advantages have been described in detail, it should be understood that various changes, substitutions and alterations may be made herein without departing from the scope of protection of the patent application.

Claims

1. A slag discharger sludge dredging device, the slag discharger comprising a water supply tank arranged inside the slag discharger, a water outlet in the body of the slag discharger for supplying water to the slag discharger is arranged at the bottom of the water supply tank, a first external active crank and a second external active crank are respectively arranged on both sides of the slag discharger, It is characterized in that include: A crank connecting assembly, the crank connecting assembly comprising a first connecting rod, a second connecting rod and a third connecting rod, wherein the first end of the first connecting rod and the first end of the second connecting rod are respectively fixedly mounted on the outside of the first external active crank and the outside of the second external active crank, and the two ends of the third connecting rod are respectively fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod; A dredging rod, wherein the first end of the dredging rod is fixedly connected to the third connecting rod, and the second end of the dredging rod passes through the water outlet of the water replenishing tank.

2. The slag discharger sludge dredging device according to claim 1, It is characterized in that The upper side of the first end portion of the dredging rod is serrated.

3. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that It also includes a guide member, which is fixedly mounted on the water replenishing tank. The dredging rod passes through the guide member, and the guide member is used to prevent the dredging rod from deviating when performing a reciprocating motion.

4. The sludge dredging device for a slag discharger according to claim 3, It is characterized in that The guide member is a rail-pressing spring, which includes a cylindrical shell and a spring arranged in the cylindrical shell.

5. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that The water replenishment tank is provided with a float for controlling the water level, the side wall of the water replenishment tank is provided with a water replenishment port, and the water replenishment and desilting groove is also provided in the water replenishment tank. The first end of the water replenishment and desilting groove is fixedly connected to the lower side of the water replenishment port, and the second end of the water replenishment and desilting groove is provided at the bottom of the float.

6. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that The first external active crank and the second external active crank are respectively fixedly connected with a first pin and a second pin, the first end of the first connecting rod and the first end of the second connecting rod are respectively fixedly connected with a first connecting rod tee and a second connecting rod tee, the first connecting rod tee is fixedly sleeved with the first pin, and the second connecting rod tee is fixedly sleeved with the second pin.

7. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that Two ends of the third connecting rod are respectively fixedly connected to the second end of the first connecting rod and the second end of the second connecting rod through a connecting rod tee.

8. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that Angle connecting pieces are respectively arranged between the third connecting rod and the first connecting rod and the second connecting rod.

9. The sludge dredging device for a slag discharger according to claim 1, It is characterized in that The dredging rod is in a curved shape.

10. A slag discharger, It is characterized in that It comprises a water replenishing tank arranged inside the slag discharger and the slag discharger sludge dredging device according to any one of claims 1-9.