Asphalt concrete core wall repairing structure
By setting upstream and downstream excavation areas on both sides of the asphalt concrete core wall and pouring anti-seepage walls, the problem of local layer defects and substandard width during construction was solved, efficient repair and reinforcement was achieved, the construction process was simplified, and the construction process was improved. Improve the anti-seepage performance and construction efficiency.
Patent Information
- Application Number
- CN202420372202.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-28
- Publication Date
- 2024-10-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction of asphalt concrete core walls, local or continuous layer defects and core wall widths that do not meet the design requirements due to environmental or human factors lead to unqualified construction quality and the need to dismantle and rebuild, seriously affecting the construction progress and difficulty.
By setting upstream and downstream excavation areas on both sides of the asphalt concrete core wall, and pouring an anti-seepage wall in the upstream excavation area to repair local defective areas, a symmetrical anti-seepage wall structure is formed to improve anti-seepage performance and construction efficiency.
It reduces the difficulty of repair construction, improves the reinforcement and anti-seepage effect, simplifies the construction steps, reduces the construction period and the workload of construction workers, and improves the repair effect and the overall anti-seepage performance of the dam body.
Smart Images

Figure CN221810564U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of core wall protection of earth-rock dams, in particular to an asphalt concrete core wall repair structure. Background Art
[0002] The main construction of asphalt concrete core dam includes the filling of dam shell materials and the filling of asphalt concrete core wall. As the anti-seepage body of the dam, the filling construction quality of the asphalt concrete core wall plays a vital role in the safety of the dam. Since the asphalt concrete core wall is layered and rolled, it is inevitable that several bonding layers will be formed. Most of these bonding layers can meet the design requirements under strict construction quality control. However, due to environmental or human factors, some local or continuous 1-2 or even more layers of asphalt concrete rolling bonding surfaces have defects, or the width of the asphalt concrete core wall is seriously smaller than the design requirements, which often leads to construction quality not meeting the requirements and needs to be excavated and re-stored to spread asphalt concrete, which seriously affects the construction period.
[0003] When the above situation occurs during on-site construction, the measure often adopted is demolition and reconstruction, which is obviously the most common and conventional solution, but it is also the most time-consuming and labor-intensive. Asphalt concrete is a viscoelastic material. The rolling section or the entire section with unqualified construction quality needs to be manually demolished. Due to the special properties of this material at room temperature, manual demolition of unqualified asphalt concrete will seriously affect the construction progress and increase the difficulty of construction. Summary of the invention
[0004] The purpose of the utility model is to provide a repair structure during the repair of the asphalt concrete core wall, so as to repair the local defective area of the dam body, reduce the difficulty of the repair construction, and improve the reinforcement and anti-seepage effect.
[0005] In order to achieve the above purpose, the utility model adopts the following scheme:
[0006] An asphalt concrete core wall repair structure comprises an upstream excavation area, a downstream excavation area and an anti-seepage wall formed by concrete pouring;
[0007] The upstream excavation area extends along the side wall of the upstream side of the asphalt concrete core wall from the top to the bottom of the asphalt concrete core wall, and a casting area is provided on one side of the upstream excavation area close to the asphalt concrete core wall, and a placement area for fixing a casting template is provided in the upstream excavation area;
[0008] The downstream excavation area is located at the downstream side of the asphalt concrete core wall, and the downstream excavation area and the upstream excavation area are symmetrically arranged along the center line of the asphalt concrete core wall;
[0009] The anti-seepage wall is formed in the casting area, and an anti-seepage surface for repairing the asphalt concrete core wall is arranged on the anti-seepage wall, and the anti-seepage surface is in contact with the side wall of the asphalt concrete core wall.
[0010] Preferably, the repair height of the asphalt concrete core wall is less than or equal to 1 meter, and the anti-seepage wall is cast in one time in the casting area. Such a setting is suitable for the working condition where cracks appear in the asphalt concrete core wall at a shallow layer from the top thereof, which is conducive to ensuring the overall strength and stability of the anti-seepage wall, reducing the risk of cracks appearing on the anti-seepage wall, and further improving the anti-seepage performance of the anti-seepage wall.
[0011] Preferably, the repair height of the asphalt concrete core wall is greater than 1 meter, and the anti-seepage wall is cast in layers in the casting area. Such a setting is suitable for the working condition where cracks appear in the asphalt concrete core wall deep from its top. The layered casting of the anti-seepage wall can better control the construction quality of each layer, thereby ensuring the molding quality of the entire anti-seepage wall and further improving the construction efficiency.
[0012] Preferably, the bonding surface formed by the layered casting of the anti-seepage wall is staggered with the layered casting bonding surface of the asphalt concrete core wall. In this way, the newly cast anti-seepage wall and the asphalt concrete core wall form a systematic anti-seepage structure, which complement each other and are superimposed layer by layer, thereby improving the repair effect and better ensuring the anti-seepage effect of the dam body.
[0013] Preferably, the aggregate gradation of the anti-seepage wall is the same as that of the asphalt concrete core wall. Such an arrangement is conducive to ensuring the structural strength of the anti-seepage wall while making the anti-seepage wall have good porosity and density, thereby complementing the asphalt concrete core wall to form an integrated anti-seepage structure.
[0014] Preferably, the amount of asphalt in the anti-seepage wall is increased by 9.5%-10.5% compared with the asphalt amount in the asphalt concrete core wall. Such a configuration is conducive to further improving the structural strength of the anti-seepage wall and enhancing the stability of the mixture in the anti-seepage wall.
[0015] Preferably, the thickness of the anti-seepage wall is 10cm-15cm.
[0016] Preferably, the vertical cross-sections of the upstream excavation area and the downstream excavation area are both trapezoidal, which is conducive to reducing the actual excavation workload and the earthwork workload of dam body backfilling while ensuring that there is sufficient construction space in the upstream excavation area and the downstream excavation area, thereby improving the efficiency of the repair construction.
[0017] Compared with the prior art, the asphalt concrete core wall repair structure provided by the utility model has the following substantial characteristics and progress: the asphalt concrete core wall repair structure aims at the problem that due to certain uncertain factors in construction, local or continuous 1-2 or even more layers of asphalt concrete core wall bonding surface defects and core wall width do not meet the design requirements. By setting upstream excavation areas and downstream excavation areas on both sides of the asphalt concrete core wall and laying anti-seepage walls in the pouring area of the upstream excavation area, the local defective areas of the dam body are repaired, the difficulty of repair construction is reduced, the reinforcement and anti-seepage effect is improved, the traditional rework thinking is broken through, and the reinforcement is carried out on the original basis. The construction is simple, the practicability is strong, the construction period is beneficial, the construction steps are simple, and the workload of construction workers is greatly reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of a delamination defect of an asphalt concrete core wall in an embodiment of the utility model.
[0019] Figure 2 It is a construction schematic diagram of an asphalt concrete core wall repair structure in an embodiment of the utility model.
[0020] Figure numerals: 1. Asphalt concrete core wall; 2. Transition material; 3. Rolled layer bonding surface defect; 4. Secondary lateral extrusion defect; 5. Upstream excavation area; 6. Downstream excavation area; 7. Anti-seepage wall; 8. Placement area; 9. Anti-seepage surface. DETAILED DESCRIPTION
[0021] The specific implementation of the utility model is described in detail below with reference to the accompanying drawings.
[0022] like Figure 1-2 As shown, an asphalt concrete core wall repair structure is proposed in the embodiment of the utility model, which is intended to repair the local defective areas of the dam body due to certain uncertain factors during construction, resulting in defects in the bonding surface of local or continuous 1-2 or even more layers of asphalt concrete core walls and the core wall width not meeting the design requirements, thereby reducing the difficulty of repair construction and improving the reinforcement and anti-seepage effect.
[0023] In the actual construction of rolled asphalt concrete core wall dam, the filling construction process of the core wall is relatively complicated, including the steps of batching, mixing, temperature control, transportation, formwork erection, warehousing and paving, and rolling of asphalt mixture. After the construction of the upper layer of asphalt concrete core wall 1 is completed, before paving the next layer of asphalt mixture, it is necessary to use a blowtorch or other heating tool to heat the surface layer of the asphalt concrete so that the upper layer of asphalt concrete and the lower layer of asphalt concrete can be better combined.
[0024] However, in actual construction, Figure 1As shown in the figure, due to inaccurate temperature control, non-conformity of construction workers' operation or other reasons, the rolling layer of asphalt concrete may cause defects in the bonding surface 3 (delamination at the bonding surface, water seepage at the bonding surface, etc.). It is also possible that the template installation width is smaller than the design requirement or the core wall is caused to have secondary lateral extrusion defects 4 when rolling the transition materials on both sides 2 due to the high temperature of the asphalt concrete, and the secondary lateral extrusion causes the core wall width to decrease.
[0025] An asphalt concrete core wall repair structure proposed in the embodiment of the utility model realizes the repair of local defective areas of the dam body by setting an upstream excavation area 5 and a downstream excavation area 6 on both sides of the asphalt concrete core wall 1, and laying an anti-seepage wall 7 in the pouring area of the upstream excavation area 5, thereby reducing the difficulty of repair construction, improving the reinforcement and anti-seepage effect, breaking through the traditional rework thinking, reinforcing on the original basis, and being simple to construct. It is highly practical, beneficial to the construction period, and the construction steps are simple, which greatly reduces the workload of construction workers.
[0026] like Figure 2 As shown, an asphalt concrete core wall repair structure includes an upstream excavation area 5, a downstream excavation area 6 and an anti-seepage wall 7 formed by concrete pouring. The upstream excavation area 5 extends from the top to the bottom of the asphalt concrete core wall 1 along the side wall on the upstream side of the asphalt concrete core wall 1. A pouring area is provided on one side of the upstream excavation area 5 close to the asphalt concrete core wall 1. A placement area 8 for fixing a pouring template is provided in the upstream excavation area 5.
[0027] The downstream excavation area 6 is located at the downstream side of the asphalt concrete core wall 1. The downstream excavation area 6 and the upstream excavation area 5 are arranged symmetrically along the center line of the asphalt concrete core wall 1.
[0028] like Figure 2 As shown, the anti-seepage wall 7 is formed in the casting area. The anti-seepage wall 7 is provided with an anti-seepage surface 9 for repairing the asphalt concrete core wall 1, and the anti-seepage surface 9 is in contact with the side wall of the asphalt concrete core wall 1.
[0029] The aggregate gradation of the anti-seepage wall 7 is the same as that of the asphalt concrete core wall 1. Such a setting is conducive to ensuring the structural strength of the anti-seepage wall 7 while making the anti-seepage wall 7 have good porosity and density, and then complementing the asphalt concrete core wall 1 to form an integrated anti-seepage structure. For example, the thickness of the anti-seepage wall 7 is 10cm-15cm. In the actual repair process, the appropriate thickness parameter of the anti-seepage wall 7 can be selected according to the thickness of the layer where the transition material 2 is located.
[0030] In order to further improve the structural stability of the anti-seepage wall 7, the amount of asphalt in the anti-seepage wall 7 is increased by 9.5%-10.5% compared with the asphalt amount of the asphalt concrete core wall 1. Such a setting is conducive to further improving the structural strength of the anti-seepage wall 7 and improving the stability of the mixture in the anti-seepage wall 7.
[0031] like Figure 2 As shown, the vertical cross-sections of the upstream excavation area 5 and the downstream excavation area 6 are both trapezoidal. Such a configuration is conducive to reducing the actual excavation workload and the earthwork workload of dam body backfilling while ensuring that there is sufficient construction space in the upstream excavation area 5 and the downstream excavation area 6, thereby improving the efficiency of the repair construction.
[0032] When using an asphalt concrete core wall repair structure proposed in the embodiment of the utility model, the same raw material and aggregate ratio as the original core wall is adopted, and the asphalt dosage is increased (about 9.5%-10.5%); the transition material 2 on the upstream and downstream sides of the unqualified asphalt concrete core wall 1 is excavated, and the impurities on the surface of the upstream side of the core wall are removed by preheating tools such as a blowtorch; a fixed template for pouring an anti-seepage wall 7 is set up 10-15 cm away from the upstream side of the asphalt concrete core wall 1, and different construction processes are selected for pouring the anti-seepage wall 7 according to the different depths of the defects on the asphalt concrete core wall 1.
[0033] For example, the repair height of the asphalt concrete core wall 1 is less than or equal to 1 meter, and the anti-seepage wall 7 is cast in the casting area at one time. Such a setting is suitable for the working condition where cracks appear in the asphalt concrete core wall 1 at a shallow layer from the top thereof, which is conducive to ensuring the overall strength and stability of the anti-seepage wall 7, reducing the risk of cracks appearing on the anti-seepage wall 7, and further improving the anti-seepage performance of the anti-seepage wall 7.
[0034] When the repair height of the asphalt concrete core wall 1 is greater than 1 meter, the anti-seepage wall 7 is cast in layers in the casting area. Such a setting is suitable for the working condition where cracks appear in the asphalt concrete core wall 1 deep from its top. The layered casting of the anti-seepage wall 7 can better control the construction quality of each layer, thereby ensuring the molding quality of the entire anti-seepage wall 7 and further improving the construction efficiency.
[0035] In order to further improve the anti-seepage effect of the anti-seepage wall 7, the bonding surface formed by the layered casting of the anti-seepage wall 7 is staggered with the layered casting bonding surface of the asphalt concrete core wall 1. In this way, the newly cast anti-seepage wall 7 and the asphalt concrete core wall 1 form a systematic anti-seepage structure, which complement each other and are superimposed layer by layer, thereby improving the repair effect and better ensuring the anti-seepage effect of the dam body.
[0036] The present invention is not limited to the specific technical solutions described in the above embodiments. In addition to the above embodiments, the present invention may also have other implementation modes. For those skilled in the art, any technical solutions formed by any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. An asphalt concrete core wall repair structure, characterized in that: It includes upstream excavation area, downstream excavation area and anti-seepage wall formed by concrete pouring; The upstream excavation area extends along the side wall of the upstream side of the asphalt concrete core wall from the top to the bottom of the asphalt concrete core wall, and a casting area is provided on one side of the upstream excavation area close to the asphalt concrete core wall, and a placement area for fixing a casting template is provided in the upstream excavation area; The downstream excavation area is located at the downstream side of the asphalt concrete core wall, and the downstream excavation area and the upstream excavation area are symmetrically arranged along the center line of the asphalt concrete core wall; The anti-seepage wall is formed in the casting area, and an anti-seepage surface for repairing the asphalt concrete core wall is arranged on the anti-seepage wall, and the anti-seepage surface is in contact with the side wall of the asphalt concrete core wall.
2. The asphalt concrete core wall repair structure according to claim 1, characterized in that: The repair height of the asphalt concrete core wall is less than or equal to 1 meter, and the anti-seepage wall is cast in one time in the casting area.
3. The asphalt concrete core wall repair structure according to claim 1, characterized in that: The repair height of the asphalt concrete core wall is greater than 1 meter, and the anti-seepage wall is cast in layers in the casting area.
4. The asphalt concrete core wall repair structure according to claim 3, characterized in that: The bonding surface formed by the layered pouring of the anti-seepage wall is staggered with the layered pouring bonding surface of the asphalt concrete core wall.
5. The asphalt concrete core wall repair structure according to claim 1, characterized in that: The aggregate gradation of the anti-seepage wall is the same as that of the asphalt concrete core wall.
6. The asphalt concrete core wall repair structure according to claim 5, characterized in that: The amount of asphalt in the anti-seepage wall is increased by 9.5%-10.5% compared with the asphalt amount in the asphalt concrete core wall.
7. The asphalt concrete core wall repair structure according to claim 1, characterized in that: The thickness of the anti-seepage wall is 10cm-15cm.
8. The asphalt concrete core wall repair structure according to claim 1, characterized in that: The vertical cross-sections of the upstream excavation area and the downstream excavation area are both trapezoidal.