Wind power blade pre-quilting seam hoisting tool

By designing pre-quilted lifting equipment for wind turbine blades and using structures such as load-bearing brackets and limit baffles, the problem of damage and posture of the fiberglass cloth cover during the hoisting and transfer process has been solved, and a safe and stable fiberglass cloth cover has been achieved. Hoisting and transfer improve laying efficiency and quality.

CN221821661UActive Publication Date: 2024-10-11TONGYU COUNTY SANYI WIND POWER EQUIP TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323581147.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-10-11
Estimated Expiration
2033-12-26

AI Technical Summary

Technical Problem

In the existing technology, the fiberglass cloth cover is easily damaged during hoisting and transportation, and it is difficult to maintain the posture, resulting in the need for secondary adjustments during laying, making it impossible to achieve safe hoisting.

Method used

A pre-quilted lifting tool for wind turbine blades is designed, including a lifting frame and a load-bearing bracket. The load-bearing bracket is equipped with a load-bearing surface, a limit baffle and an anti-separation block. Through these structures, the fiberglass cloth cover is stabilized. Hoisting and transporting to avoid deformation and damage.

Benefits of technology

It realizes the safe lifting and stable transfer of fiberglass cloth sets, avoids the problems of clamp damage and attitude adjustment, and improves the laying efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221821661U_ABST
    Figure CN221821661U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of wind power manufacturing equipment, and discloses a wind power blade pre-quilting seam hoisting tool. Comprising a lifting frame and a bearing bracket; the bearing bracket is fixedly installed on the lifting frame, a bearing face is formed on the upper end face of the bearing bracket, and the bearing face is used for bearing a pre-quilting sleeve material tray. In the wind power blade pre-quilting lifting tool provided by the utility model, the bearing bracket is arranged on the lifting frame, the bearing surface is formed on the bearing bracket, the pre-quilting sleeve material tray is arranged on the bearing surface, and the lifting frame is directly lifted in the lifting process, so that the pre-quilting sleeve material tray can be directly lifted, and the pre-quilting sleeve material tray can be directly lifted. The pre-quilting sleeve material tray located on the bearing bracket is integrally transferred and hoisted, it is guaranteed that the overall posture and shape of the glass fabric sleeve material cannot be deformed, meanwhile, the glass fabric sleeve material cannot be stressed, and the glass fabric sleeve material cannot be damaged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of wind power manufacturing equipment, in particular to a pre-quilting lifting tool for wind power blades. Background Art

[0002] With the continuous development of the wind power industry, it is necessary to lay a layer of glass fiber cloth at the root of the blade during the manufacture of wind turbine blades. In order to improve the laying efficiency, the glass fiber cloth is now made into a set of materials, and multiple layers are laid simultaneously. The set of materials is transported as a whole to the root of the mold blade for laying.

[0003] However, in the existing transportation scheme, the fiberglass cloth sleeve is still clamped by a hoist and then laid. Since the fiberglass cloth sleeve has a large mass after being formed into a whole sleeve, the clamp is easy to damage the fiberglass cloth sleeve during the clamping and transportation process. At the same time, it is difficult to ensure the posture of the fiberglass cloth sleeve, and the posture needs to be adjusted again during the subsequent laying. In summary, in the existing technology, it is impossible to safely hoist the fiberglass cloth sleeve. Utility Model Content

[0004] The main purpose of the utility model is to provide a wind turbine blade pre-quilting lifting tool, aiming to solve the problem that the glass fiber cloth sleeve cannot be safely lifted.

[0005] In order to achieve the above-mentioned purpose, the utility model provides a wind turbine blade pre-quilting lifting tool, comprising:

[0006] Lifting frame; and,

[0007] The bearing bracket is fixedly mounted on the hanging frame, and the upper end surface of the bearing bracket is formed with a bearing surface, and the bearing surface is used to bear the pre-quilted cover material tray.

[0008] Optionally, the bearing bracket includes a plurality of bearing support rods arranged at intervals in the horizontal direction, and the upper end surfaces of the plurality of bearing support rods jointly form the bearing surface.

[0009] Optionally, the bearing surface has a first limiting side;

[0010] The wind turbine blade pre-quilting lifting tool also includes a limiting baffle, which is fixedly mounted on the bearing bracket and is located on the first limiting side. The limiting baffle is used to limit the pre-quilting kit tray.

[0011] Optionally, a plurality of the limit baffles are provided, and the plurality of limit baffles are arranged at intervals along the first limit side.

[0012] Optionally, the bearing surface further has a second limiting side arranged opposite to the first limiting side;

[0013] Two of the limit baffles are provided, and the two limit baffles are respectively arranged on the first limit side and the second limit side, so as to jointly limit the pre-quilted cover material tray between the two limit baffles.

[0014] Optionally, the bearing surface further includes a material inlet and outlet side disposed adjacent to the first limiting side;

[0015] The wind turbine blade pre-quilting lifting tool also includes an anti-slip stopper, which is detachably mounted on the bearing bracket and is located at the material input and output side, and is used to limit the pre-quilting kit tray.

[0016] Optionally, a mounting hole is formed on the bearing bracket;

[0017] The anti-dropout stopper comprises an anti-dropout pin shaft, and the anti-dropout pin shaft is inserted and installed in the installation hole.

[0018] Optionally, the hanging frame includes:

[0019] connecting brackets; and

[0020] A hoisting beam is fixedly mounted to the upper end of the connecting bracket and extends horizontally, and a hoisting structure is formed on the hoisting beam;

[0021] Wherein, the bearing bracket is fixedly mounted to the lower end of the connecting bracket and is arranged opposite to the hoisting beam.

[0022] Optionally, the hanging frame further includes a reinforcement member, one end of which is fixedly connected to the connecting bracket, and the other end of which is fixedly connected to the bearing bracket.

[0023] Optionally, the lifting beam is provided with a plurality of lifting holes, and the plurality of lifting holes are arranged at intervals along the extension direction of the lifting beam, and the plurality of lifting holes form the lifting structure.

[0024] In the wind turbine blade pre-quilting lifting tool provided by the utility model, the load-bearing bracket is arranged on the lifting frame, a load-bearing surface is formed on the load-bearing bracket, and the pre-quilted sleeve material pallet is placed on the load-bearing surface. During the lifting process, the lifting frame is directly lifted, and the pre-quilted sleeve material pallet on the load-bearing bracket is transferred and lifted as a whole, ensuring that the overall posture and shape of the fiberglass cloth sleeve material will not be deformed. At the same time, the fiberglass cloth sleeve material will not be subjected to force and will not be damaged. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a three-dimensional structural schematic diagram of a wind turbine blade pre-quilting lifting tool provided by the embodiment of the utility model;

[0026] Figure 2 yes Figure 1 A schematic diagram of the front view of the structure of the pre-quilting lifting tooling for medium-sized wind turbine blades;

[0027] Figure 3 yes Figure 1 Schematic diagram of the side structure of the pre-quilting lifting tooling for medium-sized wind turbine blades.

[0028] Description of Figure Numbers:

[0029]

[0030] The realization of the purpose, functional features and advantages of the utility model will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0032] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back...), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0033] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the utility model, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or a scheme that satisfies both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the utility model.

[0034] With the continuous development of the wind power industry, it is necessary to lay a layer of glass fiber cloth at the root of the blade during the manufacture of wind turbine blades. In order to improve the laying efficiency, the glass fiber cloth is now made into a set of materials, and multiple layers are laid simultaneously. The set of materials is transported as a whole to the root of the mold blade for laying.

[0035] However, in the existing transportation scheme, the fiberglass cloth sleeve is still clamped by a hoist and then laid. Since the fiberglass cloth sleeve has a large mass after being formed into a whole sleeve, the clamp is easy to damage the fiberglass cloth sleeve during the clamping and transportation process. At the same time, it is difficult to ensure the posture of the fiberglass cloth sleeve, and the posture needs to be adjusted again during the subsequent laying. In summary, in the existing technology, it is impossible to safely hoist the fiberglass cloth sleeve.

[0036] See also Figure 1 The utility model provides a wind turbine blade pre-quilting lifting tool 100, comprising a lifting frame 1 and a bearing bracket 2; the bearing bracket 2 is fixedly installed on the lifting frame 1, and the upper end surface of the bearing bracket 2 is formed with a bearing surface, and the bearing surface is used to carry a pre-quilted set material tray.

[0037] In the wind turbine blade pre-quilting lifting tool 100 provided by the utility model, the load-bearing bracket 2 is arranged on the lifting frame 1, and a load-bearing surface is formed on the load-bearing bracket 2, and the pre-quilted sleeve material pallet is placed on the load-bearing surface. During the lifting process, the lifting frame 1 is directly lifted, and the pre-quilted sleeve material pallet on the load-bearing bracket 2 is transferred and lifted as a whole, ensuring that the overall posture and shape of the fiberglass cloth sleeve will not be deformed. At the same time, the fiberglass cloth sleeve will not be subjected to force and will not be damaged.

[0038] It should be noted that the bearing bracket 2 is used to bear the pre-quilted cover material pallet, and the bearing bracket 2 only needs to be able to hold the pre-quilted cover material pallet, for example, by using a bearing plate for bearing.

[0039] Specifically, in this embodiment, the bearing bracket 2 includes a plurality of bearing support rods 21 arranged at intervals in the horizontal direction, and the upper end surfaces of the plurality of bearing support rods 21 jointly form the bearing surface. In this embodiment, the pre-quilted cover material tray is jointly carried by the plurality of bearing support rods 21, and the plurality of bearing support rods 21 are arranged at intervals so as to form a gap between two adjacent bearing support rods 21. During the loading and unloading process, the pre-quilted cover material tray can be lifted and taken out from the gap, which is convenient for taking and placing the pre-quilted cover material tray.

[0040] On the other hand, when the pre-quilted cover material tray is placed on the bearing surface, there may be problems of incorrect placement, resulting in slipping and docking errors during subsequent transportation and retrieval;

[0041] Therefore, in this embodiment, the bearing surface has a first limiting side; the wind turbine blade pre-quilting lifting tool 100 also includes a limiting baffle 3, which is fixedly mounted on the bearing bracket 2 and is located on the first limiting side, and the limiting baffle 3 is used to limit the pre-quilted cover material tray. In this embodiment, the limiting baffle 3 is provided on one side of the bearing surface, and after the pre-quilted cover material tray is placed on the bearing surface, it can be abutted against the limiting baffle 3 to locate the position of the pre-quilted cover material tray on the bearing surface, so that the pre-quilted cover material tray is in the same posture and position each time it is transported.

[0042] Furthermore, a plurality of the limit baffles 3 are provided, and the plurality of limit baffles 3 are arranged at intervals along the first limit side. In this embodiment, the pre-quilted cover material tray is limited at the first limit side by the plurality of limit baffles 3, so as to ensure the reliability of the limit and avoid the single-point rotation of the pre-quilted cover material tray caused by the single-point limit.

[0043] In addition, the carrying surface is used to carry the pre-quilted cover material tray. During transportation, the pre-quilted cover material tray may shake and displace on the carrying surface, or even fall off.

[0044] Therefore, in this embodiment, the bearing surface further has a second limiting side arranged opposite to the first limiting side; two limiting baffles 3 are provided, and the two limiting baffles 3 are respectively arranged at the first limiting side and the second limiting side, so as to limit the pre-quilted cover material between the two limiting baffles 3. In this embodiment, the limiting baffles 3 are arranged on both opposite sides of the bearing surface, so that the pre-quilted cover material tray is clamped between the two limiting baffles 3 to prevent the pre-quilted cover material tray from falling off during transportation.

[0045] It should be noted that, in the specific embodiment provided by the present invention, the two limiting baffles 3 form a limiting group, and there are multiple limiting groups, and the multiple limiting groups are arranged at intervals to facilitate the simultaneous limiting of the pre-quilted set material tray at multiple points.

[0046] In addition, the bearing surface also includes a material inlet and outlet side that is adjacent to the first limiting side; the wind turbine blade pre-quilting lifting tool 100 also includes an anti-slip stopper 4, which is detachably mounted on the bearing bracket 2 and is located on the material inlet and outlet side, and the anti-slip stopper 4 is used to limit the pre-quilted sleeve material tray. In this embodiment, after the pre-quilted sleeve material tray is positioned, in the process of loading and unloading the tray, in order to prevent the pre-quilted sleeve material tray from slipping, the anti-slip stopper 4 is provided on the material inlet and outlet side. When loading and unloading, the anti-slip stopper 4 is removed so that the pre-quilted sleeve material tray is placed on the bearing bracket 2 from the material inlet and outlet side, and in the process of transportation, the anti-slip stopper 4 is installed on the bearing bracket 2 to prevent the pre-quilted sleeve material tray from detaching from the material inlet and outlet side.

[0047] It should be noted that there are various ways to detachably mount the anti-slip stopper 4 on the load-bearing bracket 2 , such as using a snap-on connection method, in which mutually cooperating snap-on grooves and snaps are provided on the anti-slip stopper 4 and the load-bearing bracket 2 .

[0048] In addition, a plurality of anti-slip stoppers 4 are provided, and the plurality of anti-slip stoppers 4 are arranged at intervals along the material inlet and outlet sides so as to stably limit the position of the pre-quilted cover material tray.

[0049] Specifically, in this embodiment, a mounting hole is formed on the bearing bracket 2; the anti-slip blocker 4 includes an anti-slip pin shaft, and the anti-slip pin shaft is plugged and installed in the mounting hole. In this embodiment, the anti-slip blocker 4 is installed by plugging the pin shaft on the bearing bracket 2, and the structure is simple and reliable.

[0050] Furthermore, a connecting structure is provided between the anti-dropout pin and the mounting hole so as to fix the anti-dropout pin in the mounting hole.

[0051] For example, an outer wall of the anti-dropout pin shaft is provided with an external thread, and an inner wall of the installation hole is provided with an internal thread, and the anti-dropout pin shaft is fixed to the installation hole by threaded connection.

[0052] On the other hand, see Figure 2The hoisting frame 1 includes a connecting bracket 11 and a hoisting beam 12; the hoisting beam 12 is fixedly mounted to the upper end of the connecting bracket 11 and extends in the horizontal direction, and a hoisting structure is formed on the hoisting beam 12; wherein, the load-bearing bracket 2 is fixedly mounted to the lower end of the connecting bracket 11 and is arranged opposite to the hoisting beam 12. In this embodiment, the hoisting beam 12 and the load-bearing bracket 2 are arranged opposite to each other, and a C-shaped opening structure is formed between the hoisting frame 1 and the load-bearing bracket 2. The load-bearing bracket 2 is hoisted by hoisting the hoisting beam 12, and the force point is set above the load-bearing bracket 2, so as to ensure the stability of the posture of the load-bearing bracket 2 and avoid its deviation.

[0053] For further information, see Figure 3 The hanging frame 1 further comprises a reinforcing member 13, one end of which is fixedly connected to the connecting bracket 11, and the other end of which is fixedly connected to the bearing bracket 2. This is to strengthen the connection between the hanging frame 1 and the bearing bracket 2.

[0054] It should be noted that, in this embodiment, the reinforcement member 13 is a connecting triangle plate, and the structure is stable and reliable.

[0055] In addition, the connecting bracket 11 includes a connecting main rod and a diagonal support rod, the lifting beam 12 is fixedly installed to the upper end of the connecting main rod, the supporting bracket 2 is fixedly installed to the lower end of the connecting main rod, and the two ends of the diagonal support rod are respectively fixedly connected to the connecting main rod and the supporting bracket 2 to form a triangular stable structure.

[0056] In addition, the hoisting beam 12 is provided with a plurality of hoisting holes 121, which are arranged at intervals along the extension direction of the hoisting beam, and the plurality of hoisting holes 121 form the hoisting structure. In this embodiment, a plurality of hoisting holes 121 are provided, and different hoisting holes 121 can be selected according to the different weights of the glass fiber cloth in the pre-quilted cover material tray on the bearing bracket 2 to stabilize the force of the pre-quilted cover material tray and prevent it from shaking.

[0057] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A wind turbine blade pre-quilting lifting tool, characterized in that: include: Lifting frame; as well as, A load-bearing bracket is fixedly mounted on the hanging frame, and an upper end surface of the load-bearing bracket is formed with a load-bearing surface, and the load-bearing surface is used to bear the pre-quilted cover material tray; Wherein, the bearing bracket comprises a plurality of bearing support rods arranged at intervals in the horizontal direction, and the upper end surfaces of the plurality of bearing support rods jointly form the bearing surface.

2. The wind turbine blade pre-quilting lifting tool according to claim 1, characterized in that: The bearing surface has a first limiting side; The wind turbine blade pre-quilting lifting tool also includes a limiting baffle, which is fixedly mounted on the bearing bracket and is located on the first limiting side. The limiting baffle is used to limit the pre-quilting kit tray.

3. The wind turbine blade pre-quilting lifting tool according to claim 2, characterized in that: A plurality of the limit baffles are provided, and the plurality of limit baffles are arranged at intervals along the first limit side.

4. The wind turbine blade pre-quilting lifting tool according to claim 2, characterized in that: The bearing surface also has a second limiting side arranged opposite to the first limiting side; Two of the limit baffles are provided, and the two limit baffles are respectively arranged on the first limit side and the second limit side, so as to jointly limit the pre-quilted cover material tray between the two limit baffles.

5. The wind turbine blade pre-quilting lifting tool according to claim 2, characterized in that: The bearing surface further includes a material inlet and outlet side disposed adjacent to the first limiting side; The wind turbine blade pre-quilting lifting tool also includes an anti-slip stopper, which is detachably mounted on the bearing bracket and is located at the material input and output side, and is used to limit the pre-quilting kit tray.

6. The wind turbine blade pre-quilting lifting tool according to claim 5, characterized in that: The bearing bracket is formed with a mounting hole; The anti-dropout stopper comprises an anti-dropout pin shaft, and the anti-dropout pin shaft is inserted and installed in the installation hole.

7. The wind turbine blade pre-quilting lifting tool according to claim 1, characterized in that: The hanging frame comprises: connecting brackets; and A hoisting beam is fixedly mounted to the upper end of the connecting bracket and extends horizontally, and a hoisting structure is formed on the hoisting beam; Wherein, the bearing bracket is fixedly mounted to the lower end of the connecting bracket and is arranged opposite to the hoisting beam.

8. The wind turbine blade pre-quilting lifting tool according to claim 7, characterized in that: The hanging frame also includes a reinforcement member, one end of which is fixedly connected to the connecting bracket, and the other end of which is fixedly connected to the bearing bracket.

9. The wind turbine blade pre-quilting lifting tool according to claim 7, characterized in that: The hoisting beam is provided with a plurality of hoisting holes, and the plurality of hoisting holes are arranged at intervals along the extension direction of the hoisting beam, and the plurality of hoisting holes form the hoisting structure.