Slag charging and discharging equipment
By designing the slag loading and unloading equipment and using the combination of sliding rod, sliding shell and driving rope, the problem of inconvenient substrate loading and unloading in straw mushroom cultivation is solved, height adjustment and automated operation are realized, and planting efficiency and labor saving are improved.
Patent Information
- Application Number
- CN202420181342.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-01-25
AI Technical Summary
The laying and cleaning of substrates in straw mushroom cultivation mainly relies on manual labor, which results in inconvenience in loading and unloading materials on high planting racks, high labor intensity and low efficiency.
A slag loading and unloading equipment is designed. Through the combination of sliding rod, sliding shell, driving rope and driving motor, the height adjustment of the sliding shell and automatic loading and unloading of the substrate are realized. The combination of the moving wheel and the driving wheel improves the flexibility of the equipment. sex and efficiency.
This equipment makes the loading and unloading process of straw mushroom cultivation more convenient, saves manual labor and improves efficiency. Through the setting of the auxiliary shaft and cover, it avoids wear and dust from entering, and achieves more efficient substrate management.
Smart Images

Figure CN221821843U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of straw mushroom cultivation, in particular to a slag loading and unloading device. Background Art
[0002] The cultivation of straw mushrooms generally uses crushed bean cakes, corn cobs, cotton straw, rice straw, wheat straw, etc. as the substrate. When planting, first lay a support cloth on each layer of the planting rack, then lay a layer of substrate on the support cloth, and then plant straw mushrooms on the substrate. After the straw mushrooms are harvested, the substrate is cleaned and a new substrate is laid for the next planting. Currently, the laying and cleaning of the substrate are done manually, because many planting racks are high, it is inconvenient to load and unload manually, and the labor intensity is high and the efficiency is low. Utility Model Content
[0003] The technical problem to be solved by the utility model is to provide a slag loading and unloading device for the above-mentioned technical deficiencies. This structure is convenient for adjusting the height for better loading and unloading, and it saves time and effort and is more efficient.
[0004] The technical solution adopted by the utility model is: to provide a slag loading and unloading equipment, including a bottom plate; two ends of the bottom plate are respectively fixedly connected with a vertical slide bar 1 and a slide bar 2 for driving; the outer sides of the slide bar 1 and the slide bar 2 are slidably connected with a sliding shell, a telescopic unit is arranged in the slide bar 2, and the telescopic end of the telescopic unit is fixedly connected with the sliding shell; a sliding seat that slides vertically is arranged between the two sliding shells; a rope winding shaft is installed on the sliding seat, and a driving motor for driving the rope winding shaft is arranged on the sliding seat; a fixed rope is wound around the outer side of the rope winding shaft; the slide bar 1 and the slide bar 2 are slidably connected with a sliding shell, and a telescopic unit is arranged in the slide bar 2, and the telescopic end of the telescopic unit is fixedly connected with the sliding shell; a sliding seat that slides vertically is arranged between the two sliding shells; a rope winding shaft is installed on the sliding seat, and a driving motor for driving the rope winding shaft is arranged on the sliding seat; a fixed rope is wound around the outer side of the rope winding shaft; the slide bar 1 and The second slide bar is fixedly connected with a pull rope; the upper end of the slide shell is rotatably connected with a guide rope shaft; the other end of the pull rope is connected to the slide seat after passing the guide rope shaft; at the second slide bar, the lower end of the slide shell is fixedly connected with a driving rope; between the first slide bar and the second slide bar, two driving wheels are rotatably connected to the bottom plate; the upper end of the first slide bar is rotatably connected with a lifting wheel; the other end of the driving rope passes through two driving wheels and a lifting wheel along a "U"-shaped path, and finally the driving rope is fixedly connected to the lower end of the slide shell outside the first slide bar; a driving groove for passing the driving rope is opened on the first slide bar.
[0005] To further optimize the technical solution, the driving grooves of the slag loading and unloading equipment are opened at the left and right ends of the slide bar; the driving rope is in an inverted "U" shape at the driving groove and the pulling wheel.
[0006] To further optimize the technical solution, a support frame is fixedly connected to the outer side of the bottom plate of the slag loading and unloading equipment; and four moving wheels are fixedly connected to the outer side of the support frame.
[0007] To further optimize the technical solution, both sides of the slide seat of the slag loading and unloading equipment are fixedly connected with "U"-shaped clamping plates that are slidably connected to the sliding shell; the upper ends of the clamping plates are fixedly connected to the pull ropes.
[0008] To further optimize the technical solution, the guide rope shaft of the slag loading and unloading equipment is rotatably arranged on a slide; at the lower end of the guide rope shaft, a drive motor is installed on the slide; a sprocket is fixedly connected to the drive motor and one end of the guide rope shaft; a chain is meshed on the outer sides of the two sprockets.
[0009] To further optimize the technical solution, the number of the pull rope, fixed rope and driving rope of the slag loading and unloading equipment is two each; the other ends of the two fixed ropes are fixedly connected with mounting buckles.
[0010] To further optimize the technical solution, the left part of the slag loading and unloading equipment is slide bar 2, and the right part is slide bar 1; slide bar 2 is a hydraulic cylinder.
[0011] To further optimize the technical solution, the sliding shell of the slag loading and unloading equipment is rotatably connected with an auxiliary shaft for limiting the pull rope.
[0012] To further optimize the technical solution, a wire groove is opened at the upper end of the bottom plate of the slag loading and unloading equipment; a driving wheel is rotatably arranged at the left and right ends of the wire groove; and a cover is arranged on the wire groove.
[0013] To further optimize the technical solution, at the driving groove at the right end of the slag loading and unloading equipment, an upper end of the slide rod is fixedly connected to a connecting frame; and the pull ropes are fixedly connected to the connecting frame.
[0014] Compared with the traditional loading and unloading equipment, the utility model has the following beneficial effects:
[0015] 1. The cooperation of the moving wheel, the second slide bar, the sliding shell, the driving rope, the driving wheel, the driving groove, the lifting wheel and the first slide bar can drive two sliding shells to move up or down at the same time through the driving of the second slide bar, thus saving costs;
[0016] 2. The cooperation of the sliding shell, rope guide shaft, rope, clamp, sliding seat and rope winding shaft is convenient for adjusting the height for loading and unloading. The adjustment range of the sliding seat is larger, and the height adjustment of the equipment can be completed by more than 1.5 times with a smaller equipment height, which is more convenient for loading and unloading;
[0017] 3. The cooperation of the driving motor, sprocket, chain, rope reel and fixed rope facilitates the loading and unloading of materials and the rapid cleaning of the matrix, which saves time and effort and is more efficient.
[0018] 4. The setting of the auxiliary shaft prevents the pull rope from wearing the telescopic end of the slide rod 2 when the pull rope is deformed; the setting of the cover body is used to prevent a large amount of dust from entering; the setting of the connecting frame is used to separate the pull rope and the driving rope. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the structure of the utility model;
[0020] Figure 2It is a schematic diagram of a partial decomposition structure of the utility model;
[0021] Figure 3 It is a schematic diagram of the inner structure of the sliding shell of the utility model;
[0022] Figure 4 It is a schematic diagram of another perspective structural change in the sliding shell of the utility model;
[0023] Figure 5 This is a schematic diagram of the structure of the sliding shell of the utility model;
[0024] In the figure, 1, bottom plate; 2, moving wheel; 3, slide bar 1; 4, slide bar 2; 5, slide shell; 6, slide seat; 7, rope winding shaft; 8, driving motor; 9, fixed rope; 10, pull rope; 11, guide rope shaft; 12, driving rope; 13, driving wheel; 14, lifting wheel; 15, driving groove; 16, supporting frame; 17, clamping plate; 18, sprocket; 19, chain; 20, auxiliary shaft; 21, wire groove; 22, cover body; 23, connecting frame; 24, mounting buckle. DETAILED DESCRIPTION
[0025] The utility model is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0026] like Figure 1-5As shown, the slag loading and unloading equipment comprises a bottom plate 1; two ends of the bottom plate 1 are respectively fixedly connected with a vertical slide bar 1 3 and a slide bar 2 4 for driving; the outer sides of the slide bar 1 3 and the slide bar 2 4 are slidably connected with a slide shell 5, and a telescopic unit is arranged in the slide bar 2 4, and the telescopic end of the telescopic unit is fixedly connected to the slide shell 5; a slide seat 6 that slides vertically is arranged between the two slide shells 5; a rope winding shaft 7 is installed on the slide seat 6, and a driving motor 8 for driving the rope winding shaft 7 is arranged on the slide seat 6; a fixed rope 9 is wound around the outer side of the rope winding shaft 7; the slide bar 1 3 and the slide bar 2 4 are fixedly connected with a pull rope 10; the upper ends of the slide shells 5 are A guide rope shaft 11 is rotatably connected; the other ends of the pull ropes 10 are connected to the slide seat 6 after passing through the guide rope shaft 11; at the slide bar 2 4, a driving rope 12 is fixedly connected to the lower end of the slide shell 5; between the slide bar 1 3 and the slide bar 2 4, two driving wheels 13 are rotatably connected to the bottom plate 1; the upper end of the slide bar 1 3 is rotatably connected to a lifting wheel 14; the other end of the driving rope 12 passes through the two driving wheels 13 and a lifting wheel 14 along a "U"-shaped path, and finally the driving rope 12 is fixedly connected to the lower end of the slide shell 5 outside the slide bar 1 3; a driving groove 15 for passing the driving rope 12 is opened on the slide bar 1 3; the driving groove 15 is opened on the slide The left and right ends of the rod 3; the driving rope 12 is in an inverted "U" shape at the driving groove 15 and the lifting wheel 14; the outer side of the bottom plate 1 is fixedly connected to the support frame 16; the outer side of the support frame 16 is fixedly connected to four moving wheels 2; the left and right sides of the slide 6 are fixedly connected to the "U"-shaped card plate 17 that is slidably connected to the slide shell 5; the upper ends of the card plates 17 are fixedly connected to the pull rope 10; the guide rope shaft 11 is rotatably set on the slide 6; the lower end of the guide rope shaft 11, the drive motor 8 is installed on the slide 6; the drive motor 8 and one end of the guide rope shaft 11 are fixedly connected to the sprocket 18; the outer sides of the two sprockets 18 are meshed with one A chain 19; the number of the pull rope 10, the fixed rope 9 and the driving rope 12 is two; the other ends of the two fixed ropes 9 are fixedly connected with a mounting buckle 24; the left one is a slide bar 24, and the right one is a slide bar 13; the slide bar 24 is a hydraulic cylinder; the sliding shell 5 is rotatably connected with an auxiliary shaft 20 for limiting the pull rope 10; a wire groove 21 is opened at the upper end of the bottom plate 1; the driving wheel 13 is rotatably set at the left and right ends of the wire groove 21; a cover body 22 is set on the wire groove 21; at the driving groove 15 at the right end, the upper end of the slide bar 13 is fixedly connected with a connecting frame 23; the pull ropes 10 are fixedly connected to the connecting frame 23.
[0027] The fixed end of the slide bar 2 4 is fixedly connected with a pull rope 10, and the pull rope 10 is not arranged on the telescopic end of the slide bar 2 4;
[0028] When loading and unloading straw mushrooms, it is necessary to lay a support cloth on each layer of the planting rack, and then lay a layer of substrate on the support cloth, and then plant straw mushrooms on the substrate. After the straw mushrooms are harvested, the substrate is cleaned and a new substrate is laid for the next planting.
[0029] When the lifting wheel 14 is lifted, the lifting device 10 is lifted and the lifting wheel 14 is lifted, and the other end of the lifting wheel 14 is lifted ...
[0030] When the two sliding shells 5 move upward, the rope guide shaft 11 on the sliding shell 5 will rotate, the sliding shell 5 drives the pull rope 10, the pull rope 10 pulls the clamping plate 17 fixed thereon to slide upward, and the clamping plate 17 drives the rope winding shaft 7 installed on the sliding seat 6 to move upward. Figure 3 Change to Figure 4 As shown, the height of the slide 6 and the rope winding shaft 7 can be adjusted to different heights, which is more convenient for loading and unloading on the planting rack, and it is convenient to adjust the height for loading and unloading; and through the connection of the pull rope 10 with the slide bar 1 3 and the slide bar 2 4, when the sliding shell 5 moves up and down, the pull rope 10 stretches the slide 6 by more than 1.5 times the rising distance of the sliding shell 5, and the slide 6 can move to the upper part of the sliding shell 5, and the slide 6 can also move to the bottom plate 1. The adjustment range of the slide 6 is larger, and the height adjustment of the equipment by more than 1.5 times can be completed with a smaller equipment height, which is convenient for loading and unloading;
[0031] When loading is required, the device is moved to one end of the planting rack through the moving wheel 2, and the support cloth is placed on the other end of the planting rack; the slide 6 is moved to the height corresponding to the planting rack, and then the fixed rope 9 on the rope reel 7 is unwound through the driving motor 8, and then the fixed rope 9 is passed through the planting rack, and then the support cloth for placing the substrate is fixed through the mounting buckle 24, and then the driving motor 8 is turned on, and the rope reel 7 is driven by the sprocket 18 and the chain 19 to rotate and retract the fixed rope 9, and the fixed rope 9 drags the mop cloth to the planting rack and unfolds it; in the process of dragging the support cloth, the operator lays the substrate on the passing support cloth at a fixed position, so as to facilitate loading;
[0032] When it is necessary to unload materials, the device is moved to one end of the planting rack by the moving wheel 2; the slide 6 is moved to a height corresponding to the planting rack, and then the support cloth of the substrate to be cleaned is fixed by the mounting buckle 24, and then the driving motor 8 is turned on to drive the fixed rope 9 on the rope winding shaft 7 to reel in the rope, so that the support cloth can be pulled down from the planting rack together with the substrate, so as to quickly clean the substrate; time and labor are saved when unloading and loading materials, and efficiency is higher.
[0033] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation on the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the claims attached to the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the attached claims, or the equivalent forms of such scope and boundaries.
Claims
1. A slag loading and unloading device, characterized in that: The invention comprises a bottom plate (1); two ends of the bottom plate (1) are respectively fixedly connected with a vertical sliding rod (3) and a sliding rod (4) for driving; the outer sides of the sliding rod (3) and the sliding rod (4) are both slidably connected with a sliding shell (5); a telescopic unit is arranged inside the sliding rod (4); the telescopic end of the telescopic unit is fixedly connected with the sliding shell (5); a sliding seat (6) for sliding vertically is arranged between the two sliding shells (5); a rope winding shaft (7) is installed on the sliding seat (6); a driving motor (8) for driving the rope winding shaft (7) is arranged on the sliding seat (6); a fixed rope (9) is wound around the outer side of the rope winding shaft (7); The slide bar 1 (3) and the slide bar 2 (4) are both fixedly connected with a pull rope (10); the upper end of the slide housing (5) is rotatably connected with a guide rope shaft (11); the other end of the pull rope (10) is connected to the slide seat (6) after passing around the guide rope shaft (11); At the second slide bar (4), the lower end of the slide shell (5) is fixedly connected with a driving rope (12); between the first slide bar (3) and the second slide bar (4), two driving wheels (13) are rotatably connected to the bottom plate (1); the upper end of the first slide bar (3) is rotatably connected with a lifting wheel (14); the other end of the driving rope (12) passes around the two driving wheels (13) and the lifting wheel (14) along a "U"-shaped path, and finally the driving rope (12) is fixedly connected to the lower end of the slide shell (5) outside the first slide bar (3); and a driving groove (15) for passing the driving rope (12) is opened on the first slide bar (3).
2. The slag loading and unloading equipment according to claim 1 is characterized in that: The driving groove (15) is opened at the left and right ends of the slide bar (3); the driving rope (12) is in an inverted "U" shape at the driving groove (15) and the lifting wheel (14).
3. The slag loading and unloading equipment according to claim 1 is characterized in that: A support frame (16) is fixedly connected to the outside of the bottom plate (1); and four moving wheels (2) are fixedly connected to the outside of the support frame (16).
4. The slag loading and unloading equipment according to claim 1 is characterized in that: The left and right sides of the slide seat (6) are fixedly connected with "U"-shaped clamping plates (17) which are slidably connected to the slide housing (5); the upper ends of the clamping plates (17) are fixedly connected to the pull rope (10).
5. The slag loading and unloading equipment according to claim 4 is characterized in that: The guide rope shaft (11) is rotatably arranged on the slide seat (6); the driving motor (8) is installed on the slide seat (6) at the lower end of the guide rope shaft (11); the driving motor (8) and one end of the guide rope shaft (11) are both fixedly connected with a sprocket (18); and a chain (19) is meshed on the outer sides of the two sprockets (18).
6. The slag loading and unloading equipment according to claim 1 is characterized in that: The number of the pull rope (10), the fixing rope (9) and the driving rope (12) is two each; the other ends of the two fixing ropes (9) are fixedly connected with a mounting buckle (24).
7. The slag loading and unloading equipment according to claim 1 is characterized in that: The left one is slide bar 2 (4), and the right one is slide bar 1 (3); slide bar 2 (4) is a hydraulic cylinder.
8. The slag loading and unloading equipment according to claim 1 is characterized in that: The sliding housing (5) is rotatably connected with an auxiliary shaft (20) for limiting the position of the pull rope (10).
9. The slag loading and unloading equipment according to claim 1, characterized in that: A wire groove (21) is formed at the upper end of the bottom plate (1); a driving wheel (13) is rotatably arranged at the left and right ends of the wire groove (21); and a cover body (22) is arranged on the wire groove (21).
10. The slag loading and unloading equipment according to claim 1, characterized in that: At the driving groove (15) at the right end, the upper end of the slide rod (3) is fixedly connected to a connecting frame (23); the pull ropes (10) are fixedly connected to the connecting frame (23).