Protection device for power cable bridge to pass through building deformation joint

By arranging the protective structure of bridge hangers, waterstops and drainage pipes on the upper part of the expansion joint of the power cable bridge, the problem of water leakage when the cable bridge passes through the deformation joints of the building is solved, and the safety and service life of the cable are improved.

CN221828540UActive Publication Date: 2024-10-11CHINA TOBACCO SHAANXI IND
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420149707.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-22
Publication Date
2024-10-11
Estimated Expiration
2034-01-22

AI Technical Summary

Technical Problem

In the prior art, when the power cable bridge passes through the deformation joint of the building, the expansion joint lacks waterproof protection, causing water to enter the bridge, reducing the safety of the cable and shortening its service life.

Method used

A protective structure including a bridge hanger, a waterstop and a drainage pipe is designed. The bridge hanger vertically fixes the waterstop. The waterstop is connected with the drainage pipe. The water flows through the waterstop and is discharged to the rainwater drainage of the building. tube to avoid water accumulation.

Benefits of technology

It effectively prevents water leakage in the deformation joint from entering the expansion joint, improves the safety and service life of the cable, and ensures the stable operation of the cable in a humid environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221828540U_ABST
    Figure CN221828540U_ABST
Patent Text Reader

Abstract

The utility model provides a protection device for a power cable bridge to pass through a building deformation joint, and belongs to the technical field of building electrical. Comprising a bridge frame body penetrating through a deformation joint between floors of a building, the bridge frame body comprises a bridge frame body I and a bridge frame body II which are linearly connected, the bridge frame body I and the bridge frame body II are connected through a bridge frame expansion joint, the bridge frame expansion joint is located on the lower portion of the deformation joint, and the upper portion of the bridge frame expansion joint is protected through an expansion joint protection structure to avoid influences of the environment in the deformation joint. According to the utility model, the protection device is arranged at the upper part of the bridge expansion joint in the bridge penetrating through the deformation joint in the building, so that leaked water in the deformation joint can be prevented from flowing into the expansion joint, the influence on a power cable in the expansion joint is avoided, the safety of the power cable in the expansion joint is improved, and the service life is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building electrical engineering, and in particular relates to a protective device for a power cable bridge passing through a deformation joint of a building. Background Art

[0002] When the length of the straight section of a steel power cable bridge exceeds 30m, or the length of the straight section of a power cable bridge made of other materials such as aluminum alloy exceeds 15m, an expansion joint should be installed. This can act as a buffer when the power cable encounters a special environment where there is special vibration in the expansion joint or settlement joint of a building, avoiding the risk of the power cable shifting, twisting, or being pulled apart, and ensuring safe and reliable power supply from the cable. The bridge expansion joint should be installed in the middle of the expansion joint or the straight length of the bridge, and its connection should be made of a telescopic connecting plate or a telescopic plate, such as Figure 3 and 4 As shown. A bracket is set on each side of the expansion joint, and the distance between the bracket and the end of the expansion joint is less than 500mm. The expansion joint compensation shrinkage liner is set on the outside of the expansion joint, and the liner bolt holes are opened into strip holes. The length of the liner is the sum of the lengths of the two connecting plates plus 30mm. The fixing nut is located on the outside of the bridge, but it cannot be tightened. Soft copper wire is used for cross-connection grounding at both ends of the expansion joint, and an appropriate margin is left in the middle of the grounding wire.

[0003] Problems with the existing technology: With the improvement of people's awareness of hygiene, daily hygiene and cleaning have become the norm, and the water consumption has increased. Over time, the deformation joints are prone to water accumulation and leakage. In the existing technology, when the power cable passes through the deformation joint of the building, the expansion joint of the cable tray is often exposed. There is no relevant facility to waterproof the expansion joint of the cable tray. The accumulated water will flow into the expansion joint of the cable tray, reducing the safety of the power cable in the expansion joint, making the power cable easily affected by the leakage environment of the deformation joint, and in severe cases, it is easy to reduce the service life of the power cable. Therefore, it is necessary to propose improvements. Utility Model Content

[0004] The technical problem solved by the utility model is: to provide a protection device for a power cable bridge passing through a deformation joint of a building. The utility model arranges a protection device on the upper part of the expansion joint of the bridge in the bridge passing through the deformation joint in the building, thereby preventing water leakage in the deformation joint from flowing into the expansion joint, avoiding the influence on the power cable in the expansion joint, improving the safety of the power cable in the expansion joint and extending the service life.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] A protective device for a power cable bridge passing through a deformation joint of a building, comprising a bridge passing through the deformation joint between floor slabs of the building, wherein the bridge comprises a bridge frame I and a bridge frame II connected in a straight line, wherein the bridge frame I and the bridge frame II are connected via a bridge frame expansion joint, wherein the bridge frame expansion joint is located at the lower part of the deformation joint, and the upper part of the bridge frame expansion joint is protected by an expansion joint protection structure to avoid the influence of the environment in the deformation joint.

[0007] Among them, the expansion joint protection structure includes a bridge hanger, a waterstop and a drainage pipe. Bridge hangers are vertically fixed on both sides of the ends of the bridge frame I and the bridge frame II connected to the bridge expansion joint. Waterstops are fixedly supported on the upper parts of the four bridge hangers. The waterstop has an overall drainage concave arc structure. The lowest outlet of the waterstop is connected to the upper end of the drainage pipe, and the lower end of the drainage pipe is connected to the rainwater drainage pipe of the building.

[0008] Furthermore, the waterstop forms an angle of 45 degrees with the bottom of the bridge in the horizontal and vertical directions, and the waterstop forms a two-side slope from one side to the other side in the same direction as the bridge, and the slope of the waterstop is not less than 10%.

[0009] Furthermore, the drainage pipe is made of PVC pipe.

[0010] Furthermore, the lower end of the bridge hanger is fixedly connected to the bottom of one side of the corresponding bridge through a connecting seat.

[0011] The advantages of this utility model compared with the prior art:

[0012] 1. This solution provides a protective device on the upper part of the expansion joint of the bridge frame in the bridge frame passing through the deformation joint in the building, thereby preventing water leakage in the deformation joint from flowing into the expansion joint, avoiding the influence on the power cable in the expansion joint, improving the safety of the power cable in the expansion joint and extending the service life;

[0013] 2. The waterstop in this scheme forms a 45-degree angle with the bottom of the bridge in the horizontal and vertical directions during installation, and the waterstop forms a slope on both sides from one side to the other in the same direction as the bridge, so that the water falling on the waterstop can be discharged in time, avoiding water accumulation on the waterstop and extending its service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of the utility model in use state;

[0015] Figure 2 It is a three-dimensional structural schematic diagram of the utility model;

[0016] Figure 3 This is a schematic diagram of the connection structure between the telescopic joint of the bridge frame and the bridge frame in the utility model;

[0017] Figure 4 For this utility model Figure 3 AA section view in. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] It should be noted that, in this article, the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions. The elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0020] See also Figure 1-4 , describe the embodiments of the present utility model in detail.

[0021] Embodiment: A protective device for a power cable bridge passing through a deformation joint of a building, comprising a bridge passing through a deformation joint 10 between floor slabs 9 of the building, wherein the bridge comprises a bridge frame Ⅰ1 and a bridge frame Ⅱ2 connected in a straight line, wherein the bridge frame Ⅰ1 and the bridge frame Ⅱ2 are connected via a bridge frame expansion joint 3, wherein the bridge frame expansion joint 3 is located at the lower part of the deformation joint 10, and the upper part of the bridge frame expansion joint 3 is protected by an expansion joint protection structure 4 to avoid the influence of the environment in the deformation joint 10.

[0022] In this embodiment, a protective device is provided on the upper part of the expansion joint of the bridge frame in the bridge frame passing through the deformation joint in the building, so as to prevent water leakage in the deformation joint from flowing into the expansion joint and avoid affecting the power cables in the expansion joint, thereby improving the safety of the power cables in the expansion joint and extending the service life.

[0023] In one embodiment, if Figure 1 and 2As shown, the expansion joint protection structure 4 includes a bridge hanger 5, a waterstop 6 and a drain pipe 8. Bridge hangers 5 are vertically fixed on both sides of the ends of the bridge frame Ⅰ1 and the bridge frame Ⅱ2 connected to the bridge expansion joint 3. The upper parts of the four bridge hangers 5 are fixedly supported with waterstops 6. The waterstop 6 has a concave arc structure for drainage as a whole. The lowest outlet of the waterstop 6 is connected to the upper end of the drain pipe 8, and the lower end of the drain pipe 8 is connected to the rainwater drain pipe of the building, so that the water leaked from the deformation joint can flow to the rainwater drain pipe of the building through the PVC pipe for rapid discharge.

[0024] Preferably, the water stop 6 forms a 45-degree angle with the bottom of the bridge in the horizontal and vertical directions, and the water stop 6 forms a two-side slope type from one side to the other side in the same direction as the bridge, and the slope of the water stop 6 is not less than 10%. This structure allows water that falls on the water stop to be discharged in time, avoiding water accumulation on the water stop and extending the service life.

[0025] Preferably, the drainage pipe 8 is made of PVC pipe, which has good corrosion resistance and long service life.

[0026] Preferably, the lower end of the bridge hanger 5 is fixedly connected to the bottom of one side of the corresponding bridge through a connecting seat 7.

[0027] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

[0028] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A protective device for a power cable bridge passing through a deformation joint of a building, comprising a bridge passing through a deformation joint (10) between floor slabs (9) of a building, wherein the bridge comprises a bridge I (1) and a bridge II (2) connected in a straight line, wherein the bridge I (1) and the bridge II (2) are connected via a bridge expansion joint (3), wherein the bridge expansion joint (3) is located in the deformation joint (10), and wherein the bridge is characterized in that: The upper part of the bridge expansion joint (3) is protected by the expansion joint protection structure (4) to avoid the influence of the environment in the deformation joint (10).

2. The protective device for a power cable bridge passing through a building deformation joint according to claim 1 is characterized in that: The expansion joint protection structure (4) comprises a bridge frame hanger (5), a water stop (6) and a drainage pipe (8); bridge frame hangers (5) are vertically fixed on both sides of the ends of the bridge frame I (1) and the bridge frame II (2) connected to the bridge frame expansion joint (3); four bridge frame hangers (5) are fixedly supported on the upper parts thereof; the water stop (6) is an overall drainage concave arc structure; the lowest outlet of the water stop (6) is cooperatively connected to the upper end of the drainage pipe (8); and the lower end of the drainage pipe (8) is connected to the rainwater drainage pipe of the building.

3. The protective device for a power cable bridge passing through a building deformation joint according to claim 2 is characterized in that: The water stop (6) forms an angle of 45 degrees with the bottom of the bridge frame in the horizontal and vertical directions. The water stop (6) forms a two-side slope from one side to the other side in the same direction as the bridge frame. The slope of the water stop (6) is not less than 10%.

4. The protective device for a power cable bridge passing through a building deformation joint according to claim 2 is characterized in that: The drainage pipe (8) is made of PVC pipe.

5. The protective device for a power cable bridge passing through a building deformation joint according to claim 2 is characterized in that: The lower end of the bridge frame hanger (5) is fixedly connected to the bottom of one side of the corresponding bridge frame via a connecting seat (7).