Centering device for welding water supply pipeline

By designing a centering device for water supply pipeline welding, using fixed components and adjusting knobs to achieve centering of PE pipes, the leakage problem caused by insufficient toughness at the PE pipe connection part is solved, and the reliability of the connection and construction efficiency are improved.

CN221851219UActive Publication Date: 2024-10-18XINJIANG CONSTR ENG GRP NO 1 CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323520932.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-18
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

During the use of PE pipes, due to insufficient toughness of the connection parts, there are errors in alignment, and they are prone to leakage during local bends or collisions.

Method used

A centering device for water supply pipeline welding is designed, including left and right fixing components and fixing units. The centering of the PE pipe is achieved through threaded connections and adjusting knobs to ensure the reliability of the connection and protect the pipe through the lining pipe. Avoid damage.

Benefits of technology

It improves the reliability of PE pipeline connections, simplifies the construction process, reduces labor investment and quality hazards, enhances the stability of connections, and avoids leakage problems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221851219U_ABST
    Figure CN221851219U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of PE (Poly Ethylene) pipelines, in particular to a centering device for welding water supply pipelines, which comprises a left side fixing assembly, a right side fixing assembly and a fixing unit for fixing the fixing assemblies, the left side fixing assembly comprises a left side fixing sleeve I and a left side fixing sleeve II, and the left side fixing sleeve I is connected with the left side fixing sleeve II; the right side fixing assembly comprises a first right side fixing sleeve and a second right side fixing sleeve, the first right side fixing sleeve is connected with the second right side fixing sleeve, and the first left side fixing sleeve, the second left side fixing sleeve, the first right side fixing sleeve and the second right side fixing sleeve are each in threaded connection with two adjusting knobs. And once the PE pipe is locally bent, collided and the like, the hot melting part of the PE pipe is easy to leak.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of PE pipelines, in particular to a centering device for welding water supply pipelines. Background Art

[0002] PE pipe electric fusion sleeve is a commonly used pipe connection method. Its background technology mainly comes from the electric fusion connection technology of thermoplastic materials. Similar to the hot-melt sleeve technology, the electric fusion sleeve technology is also intended to solve the problems of water leakage and easy falling off in the traditional connection method of PE pipes.

[0003] The electric fusion sleeve is mainly made of polyethylene material. When installing, the sleeve needs to be pre-sleeved on the pipe, and then the electric fusion sleeve equipment is connected to high voltage electricity to generate high temperature to fuse the sleeve and the pipe together. In this process, the high-temperature current passes through the air between the sleeve and the pipe, instantly turning it into plasma, causing the outer surface of the pipe and the inner surface of the sleeve to quickly melt and fuse together to form a solid connection.

[0004] At present, the main pipeline is mainly connected by hot melt. The principle of hot melt connection is to place the mating surfaces of two PE pipes close to a heating tool to heat their flat end faces until they melt. After removing the heating tool, the two molten end faces are pressed together and kept under pressure until the joint cools down to form a whole. In actual use, this kind of PE pipe after hot melt has insufficient toughness at the connection part of the PE pipe and there is an error in the alignment. Once the PE pipe is partially bent or collided, the hot melt part of the PE pipe is prone to leakage. Utility Model Content

[0005] The utility model aims to provide a method for solving the problem that the hot-melt part of the PE pipe is prone to leakage due to errors in alignment, local bending and collision of the PE pipe, etc.

[0006] To achieve the above-mentioned purpose, the basic scheme provided by the utility model is: a centering device for welding water supply pipes, including a left-side fixing component, a right-side fixing component and a fixing unit for fixing the fixing component, the left-side fixing component includes a left-side fixing sleeve 1 and a left-side fixing sleeve 2, the left-side fixing sleeve 1 and the left-side fixing sleeve 2 are connected, the right-side fixing sleeve 1 and the right-side fixing sleeve 2 are connected, and two adjusting knobs are threadedly connected on the left-side fixing sleeve 1 and the left-side fixing sleeve 2 as well as the right-side fixing sleeve 1 and the right-side fixing sleeve 2.

[0007] The principle and beneficial effect of the utility model are as follows: two PE pipes that need to be hot-melt welded are respectively placed in the left fixed sleeve one and the left fixed sleeve two and the right fixed sleeve one and the right fixed sleeve two, and the adjustment knob is tightened to fine-tune the two PE pipes, and the two PE pipes are aligned through the fixing unit, thereby providing reliability of the connection between the pipes, and the installation is relatively simple, which speeds up the construction speed, reduces the labor input and reduces the quality risks compared with the traditional pipe connection.

[0008] Option 2, which is a preferred option of the basic option, the fixing unit includes two left-side fixing ends and two right-side fixing ends, the two left-side fixing ends are respectively fixedly connected to the left-side fixing sleeve 1 and the left-side fixing sleeve 2, the two right-side fixing ends are respectively fixedly connected to the right-side fixing sleeve 1 and the right-side fixing sleeve 2, and the two left-side fixing ends and the right-side fixing ends are both provided with connecting components for the spacing between the left-side fixing component and the right-side fixing component.

[0009] Option three is a preferred option of option two. The connecting assembly includes a fixing rod and two nuts. The fixing rod passes through the left fixing end and the right fixing end. The two nuts are respectively threadedly connected to the two ends of the fixing rod.

[0010] Option 4 is a preferred option of the basic option. The left fixed sleeve 1 and the right fixed sleeve 1 are both provided with an upper lining tube, and the left fixed sleeve 2 and the right fixed sleeve 2 are both provided with a lower lining tube. The upper lining tube and the lower lining tube are both against the adjusting knob. The upper lining tube and the lower lining tube are used to prevent the PE tube from being scratched by the adjusting knob, thereby protecting the PE tube. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 This is a front view of a centering device for welding water supply pipes according to the utility model;

[0012] Figure 2 It is a top view of a centering device for welding water supply pipes of the utility model;

[0013] Figure 3 The utility model is a left view of a centering device for welding water supply pipes. DETAILED DESCRIPTION

[0014] The utility model is further described in detail below through specific implementation methods:

[0015] The figure marks in the drawings of the specification include: 1 left side fixed sleeve 1, 2 left side fixed sleeve 2, 3 upper end liner tube, 4 lower end liner tube, 5 adjustment knob, 6 left side fixed end, 7 right side fixed sleeve 1, 8 right side fixed sleeve 2, 9 right side fixed end, 10 fixing rod, 11 nut.

[0016] Example

[0017] like Figure 1 and Figure 3 As shown: A centering device for welding water supply pipes, including a left fixing component, a right fixing component and a fixing unit for fixing the fixing component, the left fixing component includes a left fixing sleeve 1 and a left fixing sleeve 2, the two ends of the left fixing sleeve 1 and the left fixing sleeve 2 are butted against each other, the right fixing component includes a right fixing sleeve 7 and a right fixing sleeve 8, the two ends of the right fixing sleeve 7 and the right fixing sleeve 2 8 are butted against each other, the left fixing sleeve 1 and the left fixing sleeve 2 and the right fixing sleeve 1 7 and the right fixing sleeve 2 8 are all threaded with an adjusting knob 5, the fixing unit includes two left fixing ends 6, two right fixing ends 9 and a fixing unit for fixing the fixing component. As for the connecting components of the fixed ends, the two left fixed ends 6 are respectively welded to the left fixed sleeve 1 and the left fixed sleeve 2, and the two right fixed ends 9 are respectively welded to the right fixed sleeve 7 and the right fixed sleeve 8. The connecting components include a fixing rod 10 and two nuts 11. The fixing rod 10 movably passes through the left fixed end 6 and the right fixed end 9. The two nuts 11 are respectively threadedly connected to the two ends of the fixing rod 10. The left fixed sleeve 1 and the right fixed sleeve 7 are both provided with an upper end lining tube 3. The left fixed sleeve 2 and the right fixed sleeve 8 are both provided with a lower end lining tube 4. The upper end lining tube 3 and the lower end lining tube 4 are both against the adjusting knob 5.

[0018] The implementation method of this embodiment is as follows: when welding the PE pipe, first place the left-side fixed sleeve 2 and the right-side fixed sleeve 8 on the horizontal ground, then place the lower end liner pipe 4 on the left-side fixed sleeve 2 and the right-side fixed sleeve 8, then place the left-side PE pipe on the lower end liner pipe 4, then connect half of the electric fusion sleeve to the end of the PE pipe, then connect the end of the right-side PE pipe to the electric fusion sleeve and place it on the lower end liner pipe 4, place the left and right upper end liner pipes 3 on the PE pipe, then place the left-side fixed sleeve 1 and the right-side fixed sleeve 7 on the upper end liner pipe 3, pass the fixing rod 10 through the left-side fixed end 6 on the left-side fixed sleeve 1 and the right-side fixed end 9 on the right-side fixed sleeve 7, pass another fixing rod 10 through the left-side fixed end 6 on the left-side fixed sleeve 2 and the right-side fixed end 9 on the right-side fixed sleeve 8, keep the two fixing rods 10 horizontal, Make the centers of the left fixed sleeve 1 and the left fixed sleeve 2 and the right fixed sleeve 1 7 and the right fixed sleeve 2 8 as well as the upper liner tube 3 and the lower liner tube 4 on a horizontal line, so as to center the two PE pipes, and then screw in the two nuts 11 from both ends of the fixing rod 10 and respectively abut against the left fixed end 6 and the right fixed end 9, rotate the adjusting knob 5 to abut against the upper liner tube 3 and the lower liner tube 4, so as to fine-tune the PE pipe to complete the centering, turn on the electric fusion sleeve for heating, and weld the two PE pipes. After welding is completed, rotate the nut 11 in the opposite direction to remove the nut 11, and then take out the left fixed end 6 and the right fixed end 9 of the two fixing rods 10, rotate the adjusting knob 5 in the right direction to separate the adjusting knob 5 from the upper liner tube 3 and the lower liner tube 4, open the left fixed sleeve 1 and the right fixed sleeve 7, remove the upper liner tube 3, take out the PE pipe and place it in the corresponding position to complete the welding work.

[0019] The above is only an embodiment of the utility model, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the utility model, which should also be regarded as the protection scope of the utility model, and these will not affect the effect of the implementation of the utility model and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A centering device for water supply pipe welding, characterized in that: The invention comprises a left fixing assembly, a right fixing assembly and a fixing unit for fixing the fixing assembly, wherein the left fixing assembly comprises a left fixing sleeve 1 (1) and a left fixing sleeve 2 (2), wherein the left fixing sleeve 1 (1) and the left fixing sleeve 2 (2) are connected, and the right fixing assembly comprises a right fixing sleeve 1 (7) and a right fixing sleeve 2 (8), wherein the right fixing sleeve 1 (7) and the right fixing sleeve 2 (8) are connected, and two adjusting knobs (5) are threadedly connected to the left fixing sleeve 1 (1) and the left fixing sleeve 2 (2) and the right fixing sleeve 1 (7) and the right fixing sleeve 2 (8).

2. A centering device for water supply pipe welding according to claim 1, characterized in that The fixing unit comprises two left fixing ends (6), two right fixing ends (9) and a connecting assembly for connecting the fixing ends, wherein the two left fixing ends (6) are respectively fixedly connected to the left fixing sleeve 1 (1) and the left fixing sleeve 2 (2), and the two right fixing ends (9) are respectively fixedly connected to the right fixing sleeve 1 (7) and the right fixing sleeve 2 (8).

3. A centering device for water supply pipe welding according to claim 2, characterized in that The connection assembly comprises a fixing rod (10) and two nuts (11), wherein the fixing rod (10) movably passes through the left fixing end (6) and the right fixing end (9), and the two nuts (11) are respectively threadedly connected to the two ends of the fixing rod (10).

4. A centering device for water supply pipe welding according to claim 1, characterized in that The left fixed sleeve 1 (1) and the right fixed sleeve 1 (7) are both provided with an upper inner lining tube (3), and the left fixed sleeve 2 (2) and the right fixed sleeve 2 (8) are both provided with a lower inner lining tube (4), and the upper inner lining tube (3) and the lower inner lining tube (4) are both in contact with the adjustment knob (5).