Splash-proof and welding slag collecting device for bridge pier column construction

By designing the arc plate and welding slag collection component device, the problem of damage to the template caused by welding slag splash during welding operations is solved, the effective collection and protection of welding slag is achieved, and the construction safety and site cleanliness are improved.

CN221891098UActive Publication Date: 2024-10-25SHIJIAZHUANG INST OF RAILWAY TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323448269.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-18
Publication Date
2024-10-25
Estimated Expiration
2033-12-18

AI Technical Summary

Technical Problem

During the construction of bridge piers and columns, welding slag or sparks generated during welding or cutting operations can easily burn the building formwork, and existing technology cannot effectively protect and collect welding slag, resulting in untidy construction sites and potential safety hazards.

Method used

Design a device that includes two sets of symmetrically arranged splash-proof mechanisms. The arc-shaped plate and the welding slag collection component are used to collect and protect welding slag or sparks. The fixed components of the arc-shaped plate are magnetically matched with the steel bars. The arc-shaped plate is The design of the inner arc wall and the adjustment of the magnetic suction block achieve effective collection and protection of welding slag.

Benefits of technology

It effectively prevents the formwork from being burned, collects and stores welding slag, improves construction safety and site cleanliness, is suitable for steel work sites with different intervals, and is easy to disassemble and assemble.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221891098U_ABST
    Figure CN221891098U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of bridge construction, and relates to a device for welding, in particular to a device for preventing splashing and collecting welding slag in bridge pier column construction. The utility model discloses a device for preventing splashing and collecting welding slag in bridge pier column construction. The device comprises two groups of symmetrically arranged splashing prevention mechanisms, the splash-proof mechanism comprises arc-shaped plates, and a concave surface formed by splicing the two arc-shaped plates is a cambered surface; the outer arc wall of the arc plate is provided with a fixing assembly used for fixing the arc plate to a steel bar. The splash-proof mechanism further comprises a welding slag collecting assembly, and the welding slag collecting assembly is fixedly connected to the bottom of the arc-shaped plate. The two arc-shaped plates are spliced and arranged between the welding part and the formwork, heat can be effectively insulated, the situation that the formwork is burnt during steel bar welding or cutting operation is prevented, meanwhile, welding slag generated during welding and knocked-off welding slag can be blocked and collected into a welding slag collecting device, the protection range is wide, and the protection effect is good. The technical problems in the prior art are properly solved, and the device is convenient to disassemble and assemble, flexible and convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of bridge construction and relates to a device for welding, and specifically to a device for preventing splashing and collecting welding slag during the construction of bridge piers. Background Art

[0002] Welding, also known as fusion, is a manufacturing process and technology that joins metals or other thermoplastic materials such as plastics by heating, high temperature or high pressure. However, during the welding process, spattering welding slag will be generated. There are many reasons for the generation of welding slag, such as: there are debris such as oil, rust, paint, and moisture on the surface of the base material. During the welding process, these debris burn and hinder the flow of molten iron, making the molten iron too dispersed, resulting in more slag; or the welding current is too small, the arc blowing force is small, the slag and molten iron are mixed together, the temperature is too low, and the slag is not blown to both sides of the weld, resulting in more slag; or the electrode is damp, and the electrode coating absorbs too much moisture, which affects the protection effect during the welding process, resulting in too much slag.

[0003] The construction of bridge piers also involves welding or cutting of steel bars. However, in order to ensure construction quality and improve construction efficiency, building formwork is often set up during the construction of bridge piers. In order to reduce the weight of the climbing formwork, wooden formwork is generally used for the formwork panel. After the formwork is set up, if steel bar welding is carried out near the formwork, the spattering of welding slag generated by high temperature can easily burn the building formwork close to the welding point. After pouring concrete, the concrete surface of the burned building formwork will not only turn black, but also become pockmarked, seriously affecting the appearance quality of the concrete components. Sparks generated by cutting can also easily burn the formwork.

[0004] In order to solve the above problems, the prior art often uses 3mm steel plates cut into square baffles with a side length of 20cm to 30cm, and then welds 2 to 5m long handles on them with φ6.5 steel bars. During construction, the baffles are placed between the welding points and the template to separate and protect the template.

[0005] The above-mentioned prior art has the following technical problems: during welding or cutting operations, the directions of the splashing of welding slag or sparks are random. The above-mentioned method of separating the template with a baffle can protect the template covered by the baffle, but if the welding slag or sparks splash along the direction of the baffle surface, the baffle cannot play a protective role and will eventually cause damage to the template; in addition, at the end of welding at the welding point, the construction workers may knock off the excess welding slag of the welding part. If the welding slag is allowed to fall, it will not only cause the construction site to be untidy, but also bring hidden dangers to on-site personnel.

[0006] Therefore, it is necessary to improve the above technology and provide a device with better protection effect and for collecting and treating welding slag. Utility Model Content

[0007] In order to optimize the technical problems such as welding slag or spark splashing in the prior art, the present application provides a device for preventing splashing and collecting welding slag during the construction of bridge piers.

[0008] The present application provides a device for preventing splashing and collecting welding slag during bridge pier construction, which adopts the following technical solution:

[0009] A device for preventing splashes and collecting welding slag during bridge pier construction comprises two groups of symmetrically arranged splash-proof mechanisms; the splash-proof mechanism comprises an arc-shaped plate, and a concave surface formed by splicing two arc-shaped plates is an arc surface; a fixing component for fixing the arc-shaped plate to a steel bar is provided on the outer arc wall of the arc-shaped plate; the splash-proof mechanism also comprises a welding slag collecting component, and the welding slag collecting component is fixedly connected to the bottom of the arc-shaped plate.

[0010] In a specific possible implementation scheme, the welding slag collecting assembly includes a collecting convex plate, which is attached to and fixedly connected to the inner arc wall at the bottom of the arc plate; the concave surface formed by the two collecting convex plates is located on the same spherical surface.

[0011] In a specific feasible implementation scheme, the welding slag collection assembly includes a collecting inclined plate with an arc wall, the arc wall of the collecting inclined plate is in contact with and fixedly connected to the inner arc wall at the bottom of the arc plate, the side wall of the collecting inclined plate away from the arc plate is a corner formed by two straight walls, and the corner is higher than the arc wall itself.

[0012] In a specific possible implementation manner, a positioning plate is fixedly connected to the straight wall at the bottom of the arc-shaped plate, and the side wall of the positioning plate away from the arc-shaped plate is located in the same plane as the joint surface of the arc-shaped plate.

[0013] In a specific possible implementation scheme, the joint of the two arc-shaped plates is magnetically engaged.

[0014] In a specific feasible implementation scheme, the fixing assembly includes a fixing rod, one end of which is fixedly connected to the outer arc wall of the arc plate; a locking piece and a magnetic block are provided on the fixing rod, the magnetic block is slidably connected to the fixing rod and fixed by the locking piece; the magnetic block cooperates with the steel bar by magnetic attraction.

[0015] In a specific possible implementation manner, the back side of the magnetic block is a concave surface adapted to the steel bar.

[0016] In a specific possible implementation mode, a gripping rod is further provided at the bottom of the arc-shaped plate, and the gripping rod is vertically fixedly connected to the outer arc wall at the bottom of the arc-shaped plate.

[0017] In a specific possible implementation manner, the central angle corresponding to the inner arc wall of the arc-shaped plate is 90°.

[0018] The present application includes at least one of the following beneficial technical effects:

[0019] 1. The present application uses two arc-shaped plates spliced ​​together and placed between the welding part and the template, which can effectively insulate and prevent the template from being burned during steel bar welding or cutting operations. At the same time, the welding slag and the knocked-off welding slag can also be blocked and collected in the welding slag collection device. The protection range is wide, and the technical problems in the prior art are properly optimized. It is easy to disassemble and assemble, and is smart and convenient.

[0020] 2. The magnetic block of the present application is preferably slidably connected to the fixed rod and can be adjusted by a locking piece, so that the device of the present application can be applied to work sites with steel bars of different spacings, and has strong applicability.

[0021] 3. The joints of the two arc-shaped plates of the present application are preferably matched by magnetic attraction, which increases the stability of the device in use.

[0022] 4. The central angle of the inner arc wall of the arc-shaped plate of the present application is preferably 90°, which further increases the protection range of the device and can basically shield most of the spattered welding slag and sparks, thus providing good protection for the template. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a structural schematic diagram of the device of the present application applied to a template and steel bars.

[0024] Figure 2 It is a schematic diagram of the disassembled structure of the device of the present application.

[0025] Figure 3 It is a schematic diagram used to reflect the connection relationship between the collecting inclined plate and the curved plate.

[0026] Figure 4 It is a top view used to show the connection relationship between the collecting inclined plate and the curved plate.

[0027] Figure 5 It is a cross-sectional view used to reflect the sliding connection relationship between the magnetic block and the fixed rod.

[0028] Explanation of the accompanying drawings: 1. template; 2. steel bar; 3. splash-proof mechanism; 4. arc plate; 41. positioning plate; 411. upper plate; 412. lower plate; 42. gripping rod; 51. fixing rod; 511. dovetail groove; 512. slide groove; 52. magnetic block; 521. dovetail portion; 523. locking bolt; 61. collecting convex plate; 62. collecting inclined plate. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1-5 The present application is further described in detail with specific embodiments.

[0030] Example 1

[0031] This embodiment requests the disclosure of a device for preventing splashes and collecting welding slag during the construction of bridge piers, comprising two sets of splash-proof mechanisms 3, which are symmetrically arranged and fit together; the splash-proof mechanisms 3 include an arc plate 4, a fixing assembly, and a welding slag collecting assembly; the two arc plates 4 are fit together, and the fixing assembly is used to fix the arc plate 4 on the steel bar 2; the welding slag collecting assembly is located at the bottom of the arc plate 4.

[0032] The splash-proof mechanism 3 includes an arc plate 4, which ensures that the two arc plates 4 are assembled and matched, and a new arc plate is formed after the assembly, that is, the concave surface of the two arc plates 4 after assembly is an arc surface; when in use, the arc plate 4 is assembled between the welding part and the template 1, and the arc plate 4 has a certain covering effect on the welding part, thereby preventing welding slag or sparks from splashing. The central angle corresponding to the inner arc wall of the arc plate 4 is 90°, so that when the two arc plates 4 are assembled, the remaining raised side of the arc plate 4 can play a protective role in a larger range.

[0033] The fixing assembly includes a fixing rod 51 and a magnetic block 52. One end of the fixing rod 51 is vertically fixedly connected to the outer arc wall of the arc plate 4, and the other end extends in a direction away from the arc plate 4. A magnetic block 52 with magnetic properties is fixedly connected to the fixing rod 51, and the magnetic block 52 is magnetically matched with the steel bar 2.

[0034] The welding slag collection assembly includes a collection convex plate 61, the concave surface of which is a part of a spherical surface, and the side wall of the collection convex plate 61 is fitted and fixedly connected to the inner arc wall at the bottom of the arc plate 4; the concave surface formed by the two collection convex plates 61 is located on the same spherical surface. When welding slag falls onto the collection convex plate 61, the above design will cause the welding slag to gather at the connection between the arc plate 4 and the collection convex plate 61 due to its own gravity. When the two sets of anti-splash mechanisms 3 are disassembled after the welding operation, it is difficult to cause the welding slag to fall. The above welding slag collection assembly has a good collection and storage effect on welding slag.

[0035] Correspondingly, in order to increase portability, the splash-proof mechanism 3 further includes a gripping rod 42, which is vertically fixedly connected to the outer arc wall at the bottom of the arc-shaped plate 4, so as to facilitate the operator to carry and grip and fix.

[0036] The implementation principle of the embodiment of the present application is: before performing welding operations, the operator assembles the arc plate 4 so that the arc plate 4 is located between the template 1 and the welding part after assembly, and then the device is sucked onto the steel bar 2 through the magnetic block 52, and then the welding operation is started. The welding slag generated during welding splashes onto the inner arc wall of the arc plate 4 and falls into the welding slag collection component; after welding is completed, the knocked-off welding slag also falls into the welding slag collection component; then the operator removes the magnetic block 52 from the steel bar 2, and moves to the next welding place to repeat the above operation; after completing all welding operations, the operator can pour out the welding slag from the welding slag collection component for centralized treatment.

[0037] Example 2

[0038] The difference between this embodiment and embodiment 1 is that the welding slag collection assembly is different. In this embodiment, the welding slag collection assembly includes a collection inclined plate 62 with an arc wall. The collection inclined plate 62 has three side walls, one of which is an arc wall. The arc wall fits the inner arc wall at the bottom of the arc plate 4 and is fixedly connected without gaps; the other two side walls of the collection inclined plate 62 are straight walls, and the two straight walls meet at a corner away from the inner arc wall of the arc plate 4. The corner is higher than the arc wall, so that the welding slag falls as close to the inner arc wall of the arc plate 4 as possible, instead of accumulating at the joint of the two collection inclined plates 62; when the two sets of anti-splash mechanisms 3 are spliced, the straight walls of the two collection inclined plates 62 are spliced. The structure of the welding slag collection assembly of this embodiment is different from that of embodiment 1, but it can play the same role as the welding slag collection assembly in embodiment 1, which is a parallel scheme.

[0039] Example 3

[0040] The difference between this embodiment and the first embodiment is that the magnetism is slidably connected with the fixed rod 51 in this embodiment, and the specific sliding connection method is as follows: the part where the magnetic block 52 and the fixed rod 51 are slidably connected is the dovetail portion 521, and the fixed rod 51 is provided with a dovetail groove 511 along its length direction, and the magnetic block 52 is slidably connected in the dovetail groove 511 through the dovetail portion 521. In order to lock the dovetail block in the dovetail groove 511 to complete the fixation, the fixed rod 51 is also provided with a locking member, which is a locking bolt 523, and the specific fixing method is as follows: the fixed rod 51 is provided with a slide groove 512 along its length direction, the slide groove 512 is vertically connected with the dovetail groove 511, and the locking bolt 523 is slidably connected with the slide groove 512; the dovetail portion 521 of the magnetic block 52 is provided with a threaded groove, and the locking bolt 523 is threadedly connected with the threaded groove; the operator can control the sliding or fixing of the magnetic block 52 by adjusting the locking bolt 523. It should be noted that the magnetic block 52 can also be directly fixedly connected to the fixing rod 51, but this can only be used at the work site for fixing the steel bars 2, so the sliding connection method of this embodiment is more practical.

[0041] Example 4

[0042] This embodiment is based on the solution of Example 1 and also includes the following solution: In this embodiment, the side of the magnetic block 52 close to the steel bar 2 is a concave surface adapted to the steel bar 2, so that it is firmly magnetically attracted to the steel bar 2, ensuring the stability of the device fixation and also ensuring the stability of the operator during welding construction.

[0043] Example 5

[0044] This embodiment is based on the solution of embodiment 1 and also includes the following solution: in order to ensure the stability of the splicing, the splicing points of the two arc-shaped plates 4 in this embodiment are magnetically matched.

[0045] Example 6

[0046] In order to ensure that the operator can quickly fit the two curved plates 4 during installation, in the present embodiment, a positioning plate 41 is fixedly connected to the straight wall at the bottom of the curved plate 4, and the positioning plate 41 is away from the side wall of the curved plate 4 and fits with the curved plate 4; the positioning plate 41 includes an upper plate 411 and a lower plate 412, which are fixedly connected, the lower plate 412 is fixedly connected to the curved plate 4, the bottom of the upper plate 411 is fixedly connected to the top of the lower plate 412, the upper plate 411 is inclined in the direction away from the curved plate 4, and is also fixedly connected to the curved plate 4, such a design further prevents the welding slag in the welding slag collection assembly from splashing.

[0047] The above description is only a preferred specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can make equivalent substitutions or changes within the technical scope disclosed in the present application according to the technical solution and improved ideas of the present application, which should be covered by the protection scope of the present application.

Claims

1. A device for preventing splashing and collecting welding slag during bridge pier construction, characterized in that: The invention comprises two groups of symmetrically arranged splash-proof mechanisms (3); the splash-proof mechanism (3) comprises an arc-shaped plate (4), and the concave surface formed by splicing the two arc-shaped plates (4) is an arc surface; a fixing component for fixing the arc-shaped plate (4) to the steel bar (2) is provided on the outer arc wall of the arc-shaped plate (4); the splash-proof mechanism (3) further comprises a welding slag collecting component, and the welding slag collecting component is fixedly connected to the bottom of the arc-shaped plate (4).

2. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1 is characterized in that: The welding slag collecting assembly comprises a collecting convex plate (61), which is attached to and fixedly connected to the inner arc wall at the bottom of the arc-shaped plate (4); and the concave surface formed by the two collecting convex plates (61) being spliced ​​together is located on the same spherical surface.

3. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1 is characterized in that: The welding slag collection assembly comprises a collecting inclined plate (62) with an arc wall, the arc wall of the collecting inclined plate (62) is in contact with and fixedly connected to the inner arc wall at the bottom of the arc plate (4), and the side wall of the collecting inclined plate (62) away from the arc plate (4) is a corner formed by two straight walls, and the corner is higher than the arc wall itself.

4. A device for preventing splashing and collecting welding slag during bridge pier construction according to claim 2 or 3, characterized in that: A positioning plate (41) is fixedly connected to the straight wall at the bottom of the arc-shaped plate (4), and the side wall of the positioning plate (41) away from the arc-shaped plate (4) is located in the same plane as the joint surface of the arc-shaped plate (4).

5. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1 is characterized in that: The joint of the two arc-shaped plates (4) is magnetically engaged.

6. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1 is characterized by: The fixing assembly comprises a fixing rod (51), one end of which is fixedly connected to the outer arc wall of the arc-shaped plate (4); a locking piece and a magnetic block (52) are provided on the fixing rod (51); the magnetic block (52) is slidably connected to the fixing rod (51) and fixed by the locking piece; the magnetic block (52) is magnetically matched with the steel bar (2).

7. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 6, characterized in that: The back surface of the magnetic attraction block (52) is a concave surface adapted to the steel bar (2).

8. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1 is characterized by: The bottom of the arc-shaped plate (4) is also provided with a gripping rod (42), and the gripping rod (42) is vertically fixedly connected to the outer arc wall at the bottom of the arc-shaped plate (4).

9. The device for preventing splashing and collecting welding slag during bridge pier construction according to claim 1, characterized in that: The central angle of the inner arc wall of the arc-shaped plate (4) is 90°.