Rapid in-place device for high-capacity transformer

The sliding installation method of the horizontal hydraulic rapid positioning device solves the problems of long power outage time and installation complexity during the replacement of large power transformers, achieving a faster and safer installation process, reducing costs and the need for large cranes rely.

CN221891316UActive Publication Date: 2024-10-25ANGANG CONSTR CONSORTIUM
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420248894.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-31
Publication Date
2024-10-25
Estimated Expiration
2034-01-31

AI Technical Summary

Technical Problem

The replacement process of large power transformers is complex and time-consuming, resulting in long power outages and affecting production and life in the power supply area. Moreover, there is a lack of mechanized lifting conditions during on-site installation, making it difficult to complete the installation quickly and safely.

Method used

A horizontal hydraulic rapid positioning device is adopted, and a hydraulic pump station is used to provide oil pressure through a combination of a clamping cylinder and a push cylinder to realize the sliding installation of the transformer, reducing reliance on large cranes, and designing a jaw iron and sliding shoe system to Reduce the moving resistance of the transformer.

Benefits of technology

It shortens the transformer replacement time, reduces construction costs and crane usage fees, provides a set of reusable rapid installation devices, and improves installation efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221891316U_ABST
    Figure CN221891316U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of industrial electrical equipment installation, and particularly relates to a high-capacity transformer rapid in-place device which comprises a clamping cylinder, a pushing cylinder, jaw iron and a distribution valve, the clamping cylinder is vertically arranged, the piston end of the clamping cylinder is connected with the jaw iron, a rod cavity and a rodless cavity corresponding to the clamping cylinder are respectively provided with an interface, and the pushing cylinder is connected with the jaw iron. The interface is connected with an oil outlet of a hydraulic pump station through a distribution valve; the side wall of the clamping cylinder is connected with one end of a cylinder barrel of the pushing cylinder through a connecting base and a long pin, the pushing cylinder is horizontally arranged, a rod cavity and a rodless cavity of the pushing cylinder are respectively provided with a connector, the connectors are connected with an oil outlet of a hydraulic pump station through a distribution valve, and the piston end of the pushing cylinder is connected with the driving sliding shoe through a short pin. The utility model has the advantages that: a pushing and sliding method is adopted to reduce a large amount of pressure occupied by the installation of a large power transformer on the use of an engineering construction equipment crane, so that the engineering operation progress can be ensured, and the machine-to-machine cost of using a large crane during the construction can be reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of industrial electrical equipment installation, and in particular relates to a fast-positioning device for a large-capacity transformer. Background Art

[0002] As the core equipment in the power distribution and transformation facilities, large power transformers are precisely manufactured, expensive, and have a long processing cycle. They are heavy, have a high center of gravity, and have large outer dimensions. Once a large power transformer has a major fault that cannot be repaired in the short term on site, it can only be solved by replacing the transformer. Traditional large power transformer replacement usually requires the following steps: power off the faulty transformer → remove the electrical line connection → drain the transformer oil → remove the peripheral accessories of the faulty transformer → load the accessories and evacuate the site → the faulty transformer body is moved out of the foundation platform through the hydraulic horizontal jacking device → the faulty transformer body is loaded and evacuated → the new transformer body and accessories are transported to the site through the hydraulic horizontal jacking device → key components are tested and qualified → the new transformer body is unloaded and put into place → the peripheral accessories of the new transformer are installed → vacuum hot oil circulation → standstill → high-voltage impact test → electrical line connection → restore power supply and operation. Due to the many operation links and long chains, the traditional replacement of a 220 kV transformer requires a total power outage of about 15 days, and the replacement of a set of 500 kV three-phase split transformers requires a power outage of about 40 days. During the transformer replacement operation, large-scale and long-term power outages and power restrictions will occur, which will have a very serious negative impact on the production and life of enterprises and residents in the power supply area. How to minimize the transformer replacement operation time and resume operation as soon as possible is extremely important to ensure the reliability of power supply of the power grid and reduce the impact on the production and life of enterprises and residents in the power supply area.

[0003] Generally, after large power transformers are produced by manufacturers, they are transported outside the factory to the construction site, where they need to be unloaded and installed. However, the unloading site environment is complex, the working space is narrow, and there are no conditions for mechanized lifting operations. How to safely and reliably install large power transformers is the guarantee for restoring power grid operation as soon as possible. Utility Model Content

[0004] The purpose of the utility model is to provide a large-capacity transformer rapid positioning device, overcome the shortcomings of the prior art, adopt a horizontal hydraulic rapid positioning device to promote the sliding method to reduce the installation of large power transformers on the construction equipment crane use of a large amount of pressure, that is, can ensure the progress of the project work, but also can reduce the construction of the use of large crane shift fees, the device can be used multiple times, is conducive to the overall reduction of installation costs.

[0005] To achieve the above purpose, the utility model is implemented through the following technical solutions:

[0006] A large-capacity transformer rapid positioning device comprises a clamping cylinder, a push cylinder, a jaw iron and a distribution valve. The clamping cylinder is vertically arranged, and the piston end thereof is connected with the jaw iron. Interfaces are respectively provided corresponding to the rod chamber and the rodless chamber of the clamping cylinder, and the interfaces are connected to one of the inlet / outlet oil ports of a hydraulic pump station through the distribution valve; the side wall of the clamping cylinder is connected to one end of the cylinder barrel of the push cylinder through a connecting seat and a long pin, the push cylinder is horizontally arranged, and the rod chamber and the rodless chamber of the push cylinder are respectively provided with interfaces, and the interfaces are connected to two of the inlet / outlet oil ports of the hydraulic pump station through the distribution valve, and the piston end of the push cylinder is connected to an active sliding shoe through a short pin.

[0007] The jaw iron is C-shaped, the top of the jaw iron is centrally connected to the piston end of the clamping cylinder, and the bottom opening of the jaw iron is buckled and connected to the lower edge of the wing plate of the parallel track.

[0008] The clamping cylinder and the push cylinder are both hydraulic cylinders, and the inner diameter of the cylinder is not less than 200 mm.

[0009] A handle is provided on the cylinder sleeve of the clamping cylinder.

[0010] A lifting ring is arranged on the cylinder sleeve of the push cylinder.

[0011] The clamping cylinder is arranged above the parallel rails.

[0012] The active sliding shoe is matched with the passive sliding shoe, and the transformer is located on the brackets on the active sliding shoe and the passive sliding shoe.

[0013] Compared with the prior art, the beneficial effects of the utility model are:

[0014] 1) The method of sliding by using a horizontal hydraulic quick-positioning device can reduce the pressure of large-scale occupation of construction equipment cranes during the installation of large power transformers, which can ensure the progress of engineering operations and reduce the shift costs of using large cranes in construction.

[0015] 2) It solves the installation of large power transformers in various restricted conditions. After the project is completed, the construction company can have a set of rapid installation tooling with mature technology and wide application. For all similar contents encountered in future projects, this method can be adopted. The device can be used multiple times to achieve overall reduction in installation costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of transformer loading in an embodiment of the utility model;

[0017] Figure 2 It is a schematic diagram of the structure of an embodiment of the utility model;

[0018] Figure 3 This is a schematic diagram of the plane layout of the large-capacity transformer in the implementation state of the utility model;

[0019] Figure 4 It is a schematic diagram of the translation into position of a large-capacity transformer of the utility model.

[0020] In the figure: 1-clamping cylinder, 2-push cylinder, 3-jaw iron, 4-distribution valve, 5-connecting seat, 6-long pin, 7-short pin, 8-active sliding shoe, 9-passive sliding shoe, 10-support seat, 11-handle, 12-lifting ring, 13-trailer, 14-parallel track, 15-support frame, 16-off-vehicle track, 17-transition track, 18-transformer, 19-installation foundation, 20-transformer quick-positioning device, 21-separate hydraulic jack. DETAILED DESCRIPTION

[0021] The technical solution of the present utility model will be clearly and completely described below in conjunction with specific embodiments. Obviously, the described embodiments are only part of the embodiments of the present utility model, rather than all of the embodiments.

[0022] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the specific embodiments required to be used in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the specific embodiments described below are some implementation methods of the utility model. For ordinary technicians in this field, other specific embodiments can be obtained based on these specific embodiments without paying creative work.

[0023] The components of the embodiments of the present invention generally described and shown in the specific embodiments herein can be arranged and designed in countless different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the specific embodiments is not intended to limit the scope of the utility model claimed, but only represents the selected embodiments of the utility model.

[0024] See Figure 1-4 , is a schematic structural diagram of an embodiment of a large-capacity transformer rapid positioning device of the utility model, comprising a clamping cylinder 1, a push cylinder 2, a jaw iron 3 and a distribution valve 4. The clamping cylinder 1 is vertically arranged, and its piston end is connected to the jaw iron 3. The rod chamber and the rodless chamber of the corresponding clamping cylinder 1 are respectively provided with interfaces, and the interfaces are connected to the oil outlet of the hydraulic pump station through the distribution valve 4; the side wall of the clamping cylinder 1 is connected to one end of the cylinder barrel of the push cylinder 2 through a connecting seat 5 and a long pin 6. The push cylinder 2 is horizontally arranged, and the rod chamber and the rodless chamber of the push cylinder 2 are respectively provided with interfaces, and the interfaces are connected to the oil outlet of the hydraulic pump station through the distribution valve 4, and the piston end of the push cylinder 2 is connected to the active sliding shoe 8 through a short pin 7.

[0025] The jaw iron 3 is C-shaped, and is centrally connected to the piston end of the clamping cylinder 1 . The bottom opening of the jaw iron 3 is buckled and connected to the lower edge of the wing plate of the parallel track 14 .

[0026] The clamping cylinder 1 and the push cylinder 2 are both hydraulic cylinders with an inner diameter of not less than 200 mm, which can provide sufficient horizontal push force. The cylinder sleeve of the clamping cylinder 1 is provided with a handle 11 for manual disassembly and movement. The cylinder sleeve of the push cylinder 2 is provided with a lifting ring 12 for lifting. The clamping cylinder 1 is set on a parallel track 14, which can be a departure track or a transition track.

[0027] The active sliding shoe 8 is matched with the passive sliding shoe 9, and the transformer 18 is located on the bracket 10 on the active sliding shoe 8 and the passive sliding shoe 9 to reduce the resistance of the transformer movement.

[0028] The utility model provides a large-capacity transformer for rapid placement, including off-vehicle track erection operation, off-vehicle lateral movement operation, transition track erection operation, center of gravity lowering operation, transformer placement operation and transition track extraction operation, and the specific operation steps are as follows: 1) Off-vehicle track erection operation, after the transformer 18 is transported to the right place, a support frame 15 with the same height as the box board of the trailer 13 is erected on the side of the trailer 13 close to the transformer room, the transformer 18 is lifted to a proper height on the trailer 13 by a jack, an off-vehicle track 16 spanning between the trailer 13 and the support frame 15 is installed, an active sliding shoe 8 and a passive sliding shoe 9 are arranged on the off-vehicle track 16, and a bracket 10 is placed on the active sliding shoe 8 and the passive sliding shoe 9 for fixing.

[0029] 2) Perform the off-vehicle lateral movement operation. Install the transformer quick-positioning device 20 on the track on the other side of the trailer 13. Use the transformer 18 quick-positioning device to push the transformer 18 from the trailer 13 to the support frame 15. Lift the transformer 18 again to an operating height of about 150 cm. Start the hydraulic pump station. When the transformer quick-positioning device 20 works normally and both sides are synchronized, continue to push the transformer 18 to the center of the support frame 15. Then use the hydraulic jack to lift the transformer 18, remove the off-vehicle track 16, and finally move the trailer 13 away.

[0030] 3) Transition track erection operation: Lay transition track 17 between the position of the unloaded transformer 18 and the installation foundation 19, and the transition track 17 and the transformer 18 foundation height are the same; use a separate hydraulic jack to lift and lower the transformer 18 head in turn, and pull out the wood layer by layer. When the height of the transformer 18 is about 15 cm from the ground, lay the transition track 17 rails, and install the transformer quick-positioning device 20 and the active and passive sliding shoes 8 and 9 again. Use the transformer quick-positioning device 20 to push the transformer 18 to the transformer installation foundation position, use the separate hydraulic jack to lift the transformer head in turn, and remove the off-vehicle track 16, the transformer quick-positioning device 20, and the active and passive sliding shoes 8 and 9.

[0031] 4) Perform gravity lowering operation, lift the transformer 18 with a jack, pull out the support frame 15 that is higher than the upper surface of the installation foundation 19, lay the transition track 17 that runs through the unloading position of the transformer 18 to the installation foundation 19, and lower the transformer 18 onto the transition track 17;

[0032] 5) Transformer positioning operation: Use the transformer quick positioning device 20 to push the transformer 18 onto the installation foundation 19; use a hydraulic jack to lower the transformer 18 to 5 cm from the surface of the foundation, pad it with a 5 cm chestnut board, and use an oil hydraulic jack to push the vertices of both ends of the transformer 18 sideways to align the center of the transformer 18 with the center of the foundation.

[0033] 6) Transition track extraction operation: Use a jack to lift the transformer 18, extract the transition track 17, and finally lower the transformer 18 to the installation foundation for installation. Finally, use a separate hydraulic jack to lift the transformer 18 to a height of about 5 cm, extract the pads, and then lower the transformer 18 so that the equipment falls to the center plane position of the foundation according to technical requirements. The owner's technical person in charge will accept the qualified, clean the site, and ensure that the work is completed, the materials are clean, and the site is clear, and the transportation process is completed.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A large-capacity transformer rapid placement device, characterized in that: It includes a clamping cylinder, a pushing cylinder, a jaw iron and a distribution valve. The clamping cylinder is vertically arranged, and its piston end is connected to the jaw iron. Interfaces are respectively provided for the rod chamber and the rodless chamber of the corresponding clamping cylinder, and the interfaces are connected to one of the inlet / outlet oil ports of the hydraulic pump station through the distribution valve; the side wall of the clamping cylinder is connected to one end of the cylinder barrel of the pushing cylinder through a connecting seat and a long pin. The pushing cylinder is horizontally arranged, and the rod chamber and the rodless chamber of the pushing cylinder are respectively provided with interfaces, and the interfaces are connected to two of the inlet / outlet oil ports of the hydraulic pump station through the distribution valve, and the piston end of the pushing cylinder is connected to the active sliding shoe through a short pin.

2. A large capacity transformer rapid placement device according to claim 1, characterized in that: The jaw iron is C-shaped, the top of the jaw iron is centrally connected to the piston end of the clamping cylinder, and the bottom opening of the jaw iron is buckled and connected to the lower edge of the wing plate of the parallel track.

3. A large capacity transformer rapid placement device according to claim 1, characterized in that: The clamping cylinder and the push cylinder are both hydraulic cylinders, and the inner diameter of the cylinder is not less than 200 mm.

4. A large capacity transformer rapid placement device according to claim 1, characterized in that: A handle is provided on the cylinder sleeve of the clamping cylinder.

5. A large capacity transformer rapid placement device according to claim 1, characterized in that: A lifting ring is arranged on the cylinder sleeve of the push cylinder.

6. A large capacity transformer rapid placement device according to claim 1, characterized in that: The clamping cylinder is arranged above the parallel rails.

7. A large capacity transformer rapid placement device according to claim 1, characterized in that: The active sliding shoe is matched with the passive sliding shoe, and the transformer is located on the brackets on the active sliding shoe and the passive sliding shoe.