Liquefied natural gas (LNG) ship insulating plate hanging bracket tool

By adopting the combined design of C-shaped structure and positioning components in the LNG ship hanger, the problem of sliding and safety hazards of the insulating panels during the hoisting process is solved, the stable fixation and efficient hoisting of the insulating panels are achieved, and the work safety and safety are improved. efficiency.

CN221894534UActive Publication Date: 2024-10-25ZHANGJIAGANG GREVO SHIPPING ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420740477.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-11
Publication Date
2024-10-25
Estimated Expiration
2034-04-11

AI Technical Summary

Technical Problem

The existing LNG ship insulation panel hanger has a simple structure and lacks a locking function, which causes the insulation panel to easily slide or fall during the hoisting process, posing safety hazards and causing poor hoisting effects.

Method used

A hanger tooling including a C-shaped hanger and a positioning component is designed. The bottom edge of the hanger is equipped with a limit baffle. The positioning component consists of a special-shaped baffle, a casing, a support rod, a chute, a connecting rod bracket, a crossbar, It consists of a pressure plate, a screw and a handle, through which the insulation board is fixed and stably supported.

Benefits of technology

Effectively fixes the insulation board, improves the safety and efficiency of hoisting, prevents sliding, adapts to insulation boards of different thicknesses, and protects the insulation board with rubber anti-slip pads.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221894534U_ABST
    Figure CN221894534U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of LNG ship building, in particular to an LNG ship insulating plate hanging bracket tool which comprises a hanging beam, hanging brackets are arranged on the left side and the right side below the hanging beam, two sets of hanging rods are welded to the upper end faces of the hanging brackets, the upper ends of the hanging rods are fixed to lug plates, the lug plates and the hanging beam are welded and fixed, and two sets of hanging rings are symmetrically welded to the upper end face of the hanging beam. By means of the design, the problems that most existing hanging brackets are of simple rectangular frame type structures, the structures are simple, the locking function is not achieved, hoisted insulation plates cannot be fixed, the insulation plates slide and even fall off due to inertia in the hoisting process, potential safety hazards exist, and the hoisting efficiency is high are solved. And the hoisting effect is not good enough. According to the utility model, the hanging bracket with the C-shaped structure is used for conveniently hanging an insulating plate, and meanwhile, the positioning assembly is matched to press and fix the insulating plate, so that the insulating plate is effectively fixed, the hanging safety is ensured, and the working efficiency and the safety are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of LNG ship construction, in particular to an LNG ship insulation board hanger tooling. Background Art

[0002] LNG ship, or liquefied natural gas ship, is a ship specially used to transport liquefied natural gas (LNG). This type of ship is known as the "crown jewel" of world shipbuilding and represents the high level of the shipbuilding industry. LNG ships have the advantages of high safety, high efficiency, high environmental protection, strong wind and wave resistance, etc., and play a pivotal role in the LNG industry chain. According to the structural form of the liquid cargo tank, LNG ships can be divided into independent tank type and membrane type. The independent tank type is to place cylindrical, tank-shaped, spherical and other shaped tanks inside the ship; while the membrane type adopts a double hull structure, and the inner shell is the load-bearing shell of the liquid cargo tank. Compared with the independent type, the membrane type has the advantages of high volume utilization and light structural weight. Therefore, newly built liquefied natural gas ships, especially large ones, mostly adopt membrane structures.

[0003] During the construction of LNG ships, the installation of insulation panels is an important step. Before installing the insulation panels, the insulation panels need to be hoisted. When hoisting the insulation panels, hangers are usually used to limit the support of the insulation panels. The hoisting process should be carried out slowly and steadily, avoiding sudden lifting or emergency stops to reduce the impact on the insulation panels and hoisting equipment. However, most of the existing hangers are simple rectangular frame structures with a relatively simple structure. They do not have a locking function and cannot fix the hoisted insulation panels. During the lifting process, the insulation panels will slide or even fall due to inertia, posing a safety hazard and the hoisting effect is not good enough. Therefore, it is an urgent need for the industry to develop a tooling that can efficiently and safely hoist insulation panels. Utility Model Content

[0004] In view of the existing deficiencies, the utility model provides an LNG ship insulation board hanger tooling, which solves the problems raised by the above-mentioned background technology. The tooling can fix the insulation board and hoist the insulation board to the designated position for installation by cooperating with the lifting beam and lifting equipment, thereby improving work efficiency and safety.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] An LNG ship insulation board hanger tooling comprises a hanging beam, hangers are arranged on the left and right sides below the hanging beam, two groups of hanging rods are welded to the upper end surface of the hanger, the upper ends of the hanging rods are fixed to ear plates, the ear plates are welded and fixed to the hanging beam, two groups of lifting rings are symmetrically welded to the upper end surface of the hanging beam, and positioning components are arranged on the inner sides of the two groups of hangers.

[0007] Furthermore, the hanger is configured as a C-shaped structure, and a limit baffle perpendicular to the hanger is fixedly provided on the front end surface of the bottom edge of the hanger.

[0008] Furthermore, the positioning assembly includes a special-shaped baffle, a sleeve, a support rod, a slide groove, a connecting rod bracket, a cross bar, a pressure plate, a screw and a handle. The support rod is fixed inside the hanger, and a sleeve is movably sleeved on the support rod. Two groups of connecting rod brackets with triangular structures are fixed on the right side of the sleeve ring surface. The upper ends of the two groups of connecting rod brackets are fixedly connected by a cross bar, and the lower end of the connecting rod bracket is connected to a pressure plate. A special-shaped baffle is fixed on the front side of the hanging beam, and a slide groove with an arc structure is opened inside the special-shaped baffle. The front end of the cross bar is fixedly connected to a screw, and the screw passes through the slide groove, and the front side of the screw is connected to a handle by threaded engagement.

[0009] Furthermore, a hinged joint is assembled at the connection between the lower end of the connecting rod bracket and the pressure plate.

[0010] Furthermore, a support plate is fixedly provided on the bottom surface of the inner wall of the hanger, and the width of the support plate is greater than the width of the hanger.

[0011] Furthermore, a layer of anti-skid pad made of rubber is pasted on the upper surface of the support plate and the lower surface of the pressing plate.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] 1. The utility model facilitates the hoisting of the insulating board through the C-shaped structure of the hanger, and can press and fix the insulating board with the positioning component, thereby achieving effective fixation of the insulating board, ensuring hoisting safety, and thus improving work efficiency and safety.

[0014] 2. The hanger of the utility model is set as a C-shaped structure, and a limit baffle perpendicular to it is fixed on the front end surface of the bottom edge of the hanger. The C-shaped hanger not only provides stable support, but also the C-shaped structure can better adapt to the shape of the insulation board. At the same time, the C-shaped hanger is convenient for installing the insulation board. When hoisting, just insert the hanger along one side of the insulation board to facilitate the unloading of the insulation board. The limit baffle at the front end of the bottom edge of the hanger enhances the positioning effect of the insulation board and prevents it from sliding during the hoisting process.

[0015] 3. The positioning assembly can be used to press and fix the insulation board from the upper side, which effectively fixes the insulation board and ensures the safety of hoisting. The sleeve on the support rod can rotate flexibly, and the pressure plate connected by the connecting rod bracket can rotate with the sleeve and adjust according to the thickness of the insulation board. The cooperation between the slide groove in the special-shaped baffle and the screw allows the pressure plate to form a stable pressure above the insulation board, thereby ensuring the stability of the insulation board during the hoisting process.

[0016] 4. A hinged joint is installed at the connection between the lower end of the connecting rod bracket and the pressure plate. The hinged joint forms a rotational connection between the connecting rod bracket and the pressure plate, so that the pressure plate can rotate at different angles. The bottom surface of the pressure plate can always fit closely with the surface of the insulating board, making the pressure plate more flexible in adapting to insulating boards of different thicknesses.

[0017] 5. A support plate is fixed on the bottom surface of the inner wall of the hanger, and the width of the support plate is greater than the width of the hanger. The support plate provides a stable supporting surface for the insulation board, which can increase the supporting area for insulation and ensure stable support for the insulation board. The design that the width of the support plate is greater than the width of the hanger enhances the stability of the support plate.

[0018] 6. A layer of rubber anti-skid pad is pasted on the upper surface of the support plate and the lower surface of the pressure plate, which not only increases the friction between the insulation board and prevents sliding, but also protects the insulation board from scratches and damage to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0020] Figure 2 It is a front view structural schematic diagram of the utility model.

[0021] Figure 3 It is a partial structural schematic diagram of the utility model.

[0022] Figure 4 It is a structural schematic diagram of the positioning component in the utility model.

[0023] Figure 5 This is a schematic diagram of the state of hoisting the insulation board according to the utility model.

[0024] In the figure: 1. hanging beam; 2. lifting ring; 3. hanging bracket; 31. limit baffle; 4. support plate; 5. positioning assembly; 51. special-shaped baffle; 52. sleeve; 53. support rod; 54. slide groove; 55. connecting rod bracket; 56. cross bar; 57. hinge joint; 58. pressure plate; 581. anti-slip pad; 59. screw; 510. handle; 6. ear plate; 7. hanging rod. DETAILED DESCRIPTION

[0025] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] Example:

[0027] like Figures 1 to 5 As shown, an LNG ship insulation board hanger tooling comprises a hanging beam 1, hangers 3 are arranged on the left and right sides below the hanging beam 1, two groups of hanging rods 7 are welded on the upper end surface of the hanger 3, the upper ends of the hanging rods 7 are fixed to the ear plates 6, the ear plates 6 are welded and fixed to the hanging beam 1, two groups of lifting rings 2 are symmetrically welded on the upper end surface of the hanging beam 1, and positioning components 5 are arranged on the inner sides of the two groups of hangers 3. This design solves the problem that the existing hangers 3 are mostly simple rectangular frame structures, the structure is relatively simple, and there is no locking function, so the hoisted insulation board cannot be fixed. During the lifting process, the insulation board will slide or even fall due to inertia, there are safety hazards, and the lifting effect is not good enough.

[0028] The hanger 3 is set to a C-shaped structure, and a limit baffle 31 perpendicular to the bottom front end of the hanger 3 is fixedly provided. The C-shaped hanger 3 not only provides stable support, but also the C-shaped structure can better adapt to the shape of the insulation board. At the same time, the hanger 3 with a C-shaped structure is convenient for installing the insulation board. When hoisting, it is only necessary to insert the hanger 3 along one side of the insulation board, which is convenient for unloading the insulation board. The limit baffle 31 at the front end of the bottom edge of the hanger 3 enhances the positioning effect of the insulation board and prevents it from sliding during the hoisting process.

[0029] The positioning assembly 5 includes a special-shaped baffle 51, a sleeve 52, a support rod 53, a slide 54, a connecting rod bracket 55, a cross bar 56, a pressure plate 58, a screw 59 and a handle 510. The support rod 53 is fixed inside the hanger 3. A sleeve 52 is movably sleeved on the support rod 53. Two groups of connecting rod brackets 55 with triangular structures are fixed on the right side of the annular surface of the sleeve 52. The upper ends of the two groups of connecting rod brackets 55 are fixedly connected by the cross bar 56. The lower end of the connecting rod bracket 55 is connected with a pressure plate 58. A special-shaped baffle 51 is fixed on the front side of the hanging beam 1. An arc-shaped slide 54 is opened inside the special-shaped baffle 51. The front end of the cross bar 56 is fixedly connected with a screw 59, and the screw 59 passes through the slide 54. The front side of the screw 59 is screwed with a handle 510. The positioning assembly 5 set in this design can press and fix the insulating plate from the upper side, realize the effective fixation of the insulating plate, and ensure the safety of hoisting. The sleeve 52 on the support rod 53 can rotate flexibly, and the pressure plate 58 connected by the connecting rod bracket 55 can rotate with the sleeve 52 and be adjusted according to the thickness of the insulating board. The cooperation between the slide groove 54 and the screw 59 in the special-shaped baffle 51 enables the pressure plate 58 to form a stable pressure above the insulating board, thereby ensuring the stability of the insulating board during the lifting process.

[0030] A hinge joint 57 is installed at the connection between the lower end of the connecting rod bracket 55 and the pressure plate 58. The hinge joint 57 forms a rotational connection between the connecting rod bracket 55 and the pressure plate 58, so that the pressure plate 58 can be rotated at different angles. The bottom surface of the pressure plate 58 can always fit tightly with the surface of the insulating board, making the pressure plate 58 more flexible in adapting to insulating boards of different thicknesses.

[0031] A support plate 4 is fixedly provided on the bottom surface of the inner wall of the hanger 3, and the width of the support plate 4 is greater than the width of the hanger 3. The support plate 4 provides a stable supporting surface for the insulating board, which can increase the supporting area for insulation and ensure stable support for the insulating board. The design that the width of the support plate 4 is greater than the width of the hanger 3 enhances the stability of the support plate 4.

[0032] A layer of rubber anti-skid pad 581 is pasted on the upper surface of the support plate 4 and the lower surface of the pressing plate 58, which not only increases the friction between the insulating plate and prevents sliding, but also protects the insulating plate from scratches and damage to a certain extent.

[0033] The working principle of the LNG ship insulation board hanger tooling is as follows: First, the hanging beam 1 is connected to the lifting equipment through the lifting ring 2. The hanging beam 1 is the main load-bearing structure, and it bears the lifting force of the lifting equipment through the lifting ring 2. Then the hanger 3 is inserted along one side of the insulation board, so that the insulation board is placed on the support plate 4 of the hanger 3. The design width of the support plate 4 is larger than the hanger 3, ensuring that the insulation board is stably supported. At the same time, the C-shaped structure of the hanger 3 and the limit baffle 31 at the bottom edge help to preliminarily position the insulation board to prevent it from sliding laterally during the lifting process. Then the positioning component 5 is used to further fix the insulation board. By turning the handle 510, the position of the screw 59 in the slide groove 54 of the special-shaped baffle 51 is adjusted, thereby driving the cross bar 56 and the connecting rod bracket 55 to move, and the pressure plate 58 at the lower end of the connecting rod bracket 55 moves accordingly, so that the pressure plate 58 is closely fitted with the surface of the insulation board, and then the handle 510 is tightened, and the sunshade pressure plate 58 applies a stable pressure to the insulation board from above, realizing a firm fixation of the insulation board. After the insulating board is fixed on the hanger 3, the lifting equipment lifts the entire tooling and the insulating board through the lifting ring 2. During the lifting and transportation process, since the insulating board is stably fixed in the tooling, it will not slide or fall due to inertia, thereby ensuring the safety of the lifting. After arriving at the destination, the hanger 3 tooling and the insulating board are placed together at the predetermined position, and the positioning assembly 5 is loosened by rotating the handle 510 in the opposite direction to fix the insulating board, and finally the insulating board is taken out from the hanger 3.

[0034] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not limitations on the implementation methods of the present invention. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made on the basis of the above description. It is impossible to list all the implementation methods here. All obvious changes or modifications derived from the technical solution of the present invention are still within the protection scope of the present invention.

Claims

1. An LNG ship insulation board hanger tool, comprising a hanging beam (1), characterized in that: Hangers (3) are provided on both left and right sides below the hanging beam (1); two groups of hanging rods (7) are welded to the upper end faces of the hanging brackets (3); the upper ends of the hanging rods (7) are fixed to the ear plates (6); the ear plates (6) are welded and fixed to the hanging beam (1); two groups of hanging rings (2) are symmetrically welded to the upper end faces of the hanging beam (1); and positioning components (5) are provided on the inner sides of the two groups of hanging brackets (3).

2. The LNG ship insulation board hanger tooling according to claim 1 is characterized in that: The hanger (3) is configured as a C-shaped structure, and a limit baffle (31) perpendicular thereto is fixedly provided on the front end surface of the bottom edge of the hanger (3).

3. The LNG ship insulation board hanger tooling according to claim 1 is characterized by: The positioning assembly (5) comprises a special-shaped baffle (51), a sleeve (52), a support rod (53), a slide groove (54), a connecting rod bracket (55), a cross bar (56), a pressure plate (58), a screw rod (59) and a handle (510). The support rod (53) is fixedly arranged inside the hanger (3). The support rod (53) is movably sleeved with a sleeve (52). Two groups of connecting rod brackets (55) with triangular structures are fixedly arranged on the right side of the annular surface of the sleeve (52). The two groups of connecting rod brackets The upper end of the connecting rod bracket (55) is fixedly connected via a cross bar (56), the lower end of the connecting rod bracket (55) is connected to a pressure plate (58), a special-shaped baffle (51) is fixedly provided on the front side of the suspension beam (1), an arc-shaped slide groove (54) is provided inside the special-shaped baffle (51), a screw rod (59) is fixedly connected to the front end of the cross bar (56), and the screw rod (59) passes through the slide groove (54), and the front side of the screw rod (59) is connected to a handle (510) by screwing.

4. The LNG ship insulation board hanger tooling according to claim 3 is characterized in that: A hinge joint (57) is installed at the connection between the lower end of the connecting rod bracket (55) and the pressure plate (58).

5. The LNG ship insulation board hanger tooling according to claim 3 is characterized by: A support plate (4) is fixedly provided on the bottom surface of the inner wall of the hanger (3), and the width of the support plate (4) is greater than the width of the hanger (3).

6. The LNG ship insulation board hanger tooling according to claim 5 is characterized in that: A layer of anti-skid pad (581) made of rubber is adhered to the upper surface of the support plate (4) and the lower surface of the pressing plate (58).