Non-parting integrally-poured rock-fill concrete arch dam structure

By integrally pouring the rockfill concrete arch dam structure without dividing joints, using prefabricated block formwork and integrated pouring of high self-compacting concrete, the problems of construction interference and slow speed caused by the joint design in the existing technology are solved, and the construction is simplified and improved. The effect of rockfill rate.

CN221895715UActive Publication Date: 2024-10-25遵义市水利水电勘测设计研究院有限责任公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420457130.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-11
Publication Date
2024-10-25
Estimated Expiration
2034-03-11

AI Technical Summary

Technical Problem

The joint design of the existing rockfill concrete arch dam increases the construction process and construction period, fails to give full play to the advantages of rockfill concrete materials, and has problems such as large construction interference, slow speed and low rockfill rate.

Method used

The arch dam structure is an integrally poured rockfill concrete arch dam structure without dividing joints. The upstream and downstream prefabricated block formwork is combined with the dam rockfill material. The integrated pouring of high self-compacting concrete is used to fill the gaps. The permanent transverse joints and temporary steel formwork are eliminated to simplify the construction process. Increase dam building speed.

Benefits of technology

It achieves seamless construction, simplifies the design and process, increases the construction speed and rockfill rate, avoids joint grouting of permanent transverse joints, and greatly promotes the development of rockfill concrete arch dam technology.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895715U_ABST
    Figure CN221895715U_ABST
Patent Text Reader

Abstract

The utility model discloses a non-parting integral pouring rock-fill concrete arch dam structure which comprises an upstream precast block formwork, a downstream precast block formwork is arranged below the upstream precast block formwork, and dam rock-fill materials are filled between the upstream precast block formwork and the downstream precast block formwork. Gaps of the dam rockfill material are filled with integrally-poured high self-compacting concrete. By fully utilizing the characteristic of low hydration heat of rock-fill concrete, continuous rock-fill and pouring of the dam are achieved, compared with existing dam body parting structural design, permanent transverse joints are not needed, joint grouting of the permanent transverse joints is not conducted, the dam body structural design is greatly simplified, the construction speed is increased, the construction period is shortened, and the construction cost is reduced. The problems of large construction interference, low construction speed, low rockfill rate and the like caused by too many dam body seams are solved, the rockfill concrete arch dam construction speed is increased, and the rockfill concrete arch dam construction method plays a great role in promoting the development of the rockfill concrete arch dam technology.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete arch dams, in particular to a seamless integrally cast rockfill concrete arch dam structure. Background Art

[0002] Rockfill concrete is a new type of large-volume concrete dam construction technology that uses large rockfill + high self-compacting concrete for pouring and bonding. This technology makes full use of local stones or excavated materials, which are directly piled into the warehouse as large-size aggregates to form a rockfill structure with certain gaps. Then, highly fluid self-compacting concrete is poured from the top of the rockfill, which fills the gaps in the rockfill with its own weight and forms a complete, dense, and high-strength large-volume concrete with the rockfill after hardening. Usually, the volume of the rockfill can reach about 55% of the rockfill concrete, which not only reduces the amount of cementitious materials used, but also helps absorb the heat generated by the concrete hydration reaction, and improves the material crack resistance, volume stability, and interlayer shear resistance of the rockfill concrete.

[0003] However, the current specifications related to rockfill concrete dams control the setting of transverse joints in the dam body. The maximum transverse joint setting spacing of rockfill concrete arch dams is 60m, which increases the construction process (joint grouting) and construction period to a certain extent, and fails to give full play to the advantages of rockfill concrete materials. Utility Model Content

[0004] The utility model aims to solve at least one of the technical problems existing in the prior art, and provides a seamless integrally cast rockfill concrete arch dam structure, which makes full use of the low hydration heat of rockfill concrete to enable continuous rockfill and casting of the dam. Compared with the existing dam body joint structure design, it is not necessary to set permanent transverse joints, so the joint grouting of permanent transverse joints will not be carried out, and the dam body structure design is greatly simplified, the construction speed and construction period are improved, and the problems of large construction interference, slow construction speed and low rockfill rate caused by too many dam body joints are solved. Concrete prefabricated block formwork is used as the permanent part of the dam body in the upstream and downstream of the dam body, and the hoisting and climbing process of the temporary steel formwork is cancelled. At the same time, the anti-seepage layer adopts the integrated casting technology, which greatly simplifies the dam construction process and improves the dam construction speed of the rockfill concrete arch dam, which plays a great role in promoting the development of rockfill concrete arch dam technology.

[0005] The utility model also provides the above-mentioned seamless integrally cast rockfill concrete arch dam structure, an upstream prefabricated block template, a downstream prefabricated block template is arranged below the upstream prefabricated block template, dam rockfill materials are filled between the upstream prefabricated block template and the downstream prefabricated block template, the gaps between the dam rockfill materials are filled with integrated cast high self-compacting concrete, a first positioning installation strip is fixedly connected to the right surface of the upstream prefabricated block template, and a second positioning installation strip is fixedly connected to the rear surface of the upstream prefabricated block template.

[0006] According to the seamless integrally cast rockfill concrete arch dam structure, the size of the upstream prefabricated block template structure is 50cm×30cm×30cm.

[0007] According to the seamless integral cast-in-one rockfill concrete arch dam structure, threaded holes are provided inside the first positioning and mounting strip, and the number of the threaded holes is multiple and linearly distributed for convenient overlapping.

[0008] According to the seamless integrally cast rockfill concrete arch dam structure, positioning holes are arranged inside the upstream prefabricated block template, and the number of the positioning holes is multiple and linearly distributed.

[0009] According to the seamless integrally cast rockfill concrete arch dam structure, the inner surface of the upstream prefabricated block template is threadedly connected with connecting bolts, and the connecting bolts are adapted to the threaded holes for quick overlap.

[0010] According to the seamless integral cast-in-place rockfill concrete arch dam structure, the lower surface of the upstream prefabricated block template is threadedly connected with a reinforcing bolt, and the lower end of the reinforcing bolt is threadedly connected to the downstream prefabricated block template to increase the supporting force and enhance the stability of the template.

[0011] According to the seamless integrally cast rockfill concrete arch dam structure, a limiting groove is provided on the front surface of the upstream prefabricated block template, and the second positioning and mounting strip is matched with the limiting groove.

[0012] According to the seamless integrally cast rockfill concrete arch dam structure, the number of the reinforcement bolts is multiple and distributed in a rectangular array.

[0013] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The utility model is further described below in conjunction with the accompanying drawings and embodiments;

[0015] Figure 1 This is the overall structural diagram of a seamless integrally cast rockfill concrete arch dam structure of the utility model;

[0016] Figure 2 This is a structural diagram of a prefabricated block formwork for a seamless integrally cast rockfill concrete arch dam structure of the utility model;

[0017] Figure 3 for Figure 2 A schematic diagram of the structure enlargement in the middle;

[0018] Figure 4 This is a comparison chart of the dam joint structure in the current specification.

[0019] Legend:

[0020] 1. Upstream precast block formwork; 2. Dam rockfill; 3. Integrated casting of high self-compacting concrete; 4. Downstream precast block formwork; 5. First positioning and mounting strip; 6. Threaded hole; 7. Positioning hole; 8. Connecting bolt; 9. Second positioning and mounting strip; 10. Reinforcement bolt; 11. Limiting groove; 12. Permanent transverse joint of the dam. DETAILED DESCRIPTION

[0021] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0022] Reference Figure 1-4 The utility model embodiment is a seamless integrally cast rockfill concrete arch dam structure, which includes an upstream precast block template 1, the upstream precast block template 1 has a structural size of 50cm×30cm×30cm, the masonry height of each casting bin is 4 precast blocks (0.3m×4=1.2m), the mortar masonry joint height between adjacent precast blocks is about 2cm, and the casting bin layer thickness of the rockfill concrete is about 1.3m. The masonry type of the precast block template adopts the "one straight and one straight" type, and the precast block concrete grade adopts C15 concrete with the same grade as the dam body. The precast block template is subsequently used as a part of the dam body and is not removed.

[0023] A downstream prefabricated block template 4 is arranged below the upstream prefabricated block template 1. The space between the upstream prefabricated block template 1 and the downstream prefabricated block template 4 is filled with dam rockfill 2. The dam rockfill 2 is made of dam shoulder excavation materials or blocks mined from the material field that meet the requirements. The particle size is generally not less than 300mm. Mechanical rockfill and artificial assisted rockfill can be used for storage in the warehouse, thereby increasing the rockfill rate and forming a rockfill body with natural gaps and good gradation. When stacking the rocks, space for the upstream anti-seepage layer of the dam should be reserved for subsequent integrated pouring with the dam body. Since the dam structure design considers the integral pouring structure type without seams, the rockfill is carried out in the manner of stacking the entire section of the dam body in the entire warehouse.

[0024] The gaps between the dam rockfill materials 2 are filled with integrated cast high self-compacting concrete 3, which is continuously cast in an "S-shape" from one dam end to the other dam end to the dam sealing arch by means of pumping concrete, etc., so that the dam anti-seepage concrete and the dam body are cast in an integrated manner, and no permanent transverse joints are set. The right surface of the upstream prefabricated block template 1 is fixedly connected with a first positioning installation strip 5, and the interior of the first positioning installation strip 5 is provided with threaded holes 6. The number of threaded holes 6 is multiple and linearly distributed, and the interior of the upstream prefabricated block template 1 is provided with positioning holes 7, which are fixed. The number of the positioning holes 7 is multiple and they are distributed linearly, the inner surface of the upstream prefabricated block template 1 is threadedly connected with a connecting bolt 8, and the connecting bolt 8 is adapted to the threaded hole 6, the rear surface of the upstream prefabricated block template 1 is fixedly connected with a second positioning mounting strip 9, the lower surface of the upstream prefabricated block template 1 is threadedly connected with a reinforcing bolt 10, and the lower end of the reinforcing bolt 10 is threadedly connected to the downstream prefabricated block template 4, the number of the reinforcing bolts 10 is multiple and they are distributed in a rectangular array, the front surface of the upstream prefabricated block template 1 is provided with a limiting groove 11, and the second positioning mounting strip 9 is adapted to the limiting groove 11.

[0025] Working principle: first, screw the reinforcing bolts 10 into the upper surface of the downstream prefabricated block template 4, and then fix the downstream prefabricated block template 4 to the upstream prefabricated block template 1 through the threaded connection of the reinforcing bolts 10 and the upstream prefabricated block template 1, and then insert the first positioning installation strip 5 into the adjacent upstream prefabricated block template 1 and then screw in the connecting bolts 8 to achieve overlap. After the overlap is completed, the dam rockfill 2 is first filled in the line between the upstream prefabricated block template 1 and the downstream prefabricated block template 4, and then the integrated cast high self-compacting concrete 3 is filled in. No permanent transverse joints are set, and no joint grouting of the permanent transverse joints is performed.

[0026] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A seamless integral cast rockfill concrete arch dam structure. It is characterized in that include: An upstream prefabricated block template (1), a downstream prefabricated block template (4) is arranged below the upstream prefabricated block template (1), dam rockfill (2) is filled between the upstream prefabricated block template (1) and the downstream prefabricated block template (4), the gaps between the dam rockfill (2) are filled with integrated cast high self-compacting concrete (3), a first positioning installation strip (5) is fixedly connected to the right surface of the upstream prefabricated block template (1), and a second positioning installation strip (9) is fixedly connected to the rear surface of the upstream prefabricated block template (1).

2. A seamless integrally cast rockfill concrete arch dam structure according to claim 1, It is characterized in that The structural dimensions of the upstream prefabricated block template (1) are 50cm×30cm×30cm.

3. The seamless integrally cast rockfill concrete arch dam structure according to claim 1, It is characterized in that The first positioning and mounting strip (5) is provided with threaded holes (6) inside, and the threaded holes (6) are multiple and linearly distributed.

4. The seamless integrally cast rockfill concrete arch dam structure according to claim 1, It is characterized in that Positioning holes (7) are arranged inside the upstream prefabricated block template (1), and the number of the positioning holes (7) is multiple and linearly distributed.

5. The seamless integrally cast rockfill concrete arch dam structure according to claim 3, It is characterized in that The inner surface of the upstream prefabricated block template (1) is threadedly connected with a connecting bolt (8), and the connecting bolt (8) is compatible with the threaded hole (6).

6. The seamless integrally cast rockfill concrete arch dam structure according to claim 1, It is characterized in that The lower surface of the upstream prefabricated block template (1) is threadedly connected with a reinforcing bolt (10), and the lower end of the reinforcing bolt (10) is threadedly connected to the downstream prefabricated block template (4).

7. The seamless integrally cast rockfill concrete arch dam structure according to claim 1, It is characterized in that A limiting groove (11) is provided on the front surface of the upstream prefabricated block template (1), and the second positioning and mounting strip (9) is adapted to the limiting groove (11).

8. The seamless integrally cast rockfill concrete arch dam structure according to claim 6, It is characterized in that The reinforcing bolts (10) are multiple in number and distributed in a rectangular array.