Prefabricated laminated slab hoisting tool

Through the rigid connection between the frame and the L-shaped clamp arm structure, the problem of loose clamping of prefabricated composite panel hoisting devices in the existing technology under strong wind conditions is solved, achieving more stable clamping and efficient hoisting, and improving construction safety. and efficiency.

CN221917040UActive Publication Date: 2024-10-29SHANDONG ZHENGYANG CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420754482.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-12
Publication Date
2024-10-29
Estimated Expiration
2034-04-12

AI Technical Summary

Technical Problem

The existing prefabricated composite panel hoisting device loosens its clamping position in strong winds, which poses safety risks, is inconvenient to operate, and has limited clamping effect.

Method used

It adopts a frame and clamp arm structure. The frame is surrounded by four steel columns and four steel beams. The clamp arms are connected to the steel columns through fasteners. The clamp arms have an L-shaped structure and a large contact surface to ensure the safety of the prefabricated composite panels. Stable clamping, and improve lifting efficiency and safety through multiple equally spaced clamping arms.

Benefits of technology

It improves the clamping stability of the prefabricated composite panels, reduces the shaking of tooling in windy weather, increases the safety and efficiency of hoisting operations, avoids scratches on the prefabricated composite panels, and improves fault tolerance and integrity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221917040U_ABST
    Figure CN221917040U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of prefabricated laminated slab hoisting, in particular to a prefabricated laminated slab hoisting tool. Comprising a frame and clamping arms, the frame is defined by four steel columns and four steel beams, the frame covers the outer side of a prefabricated laminated slab, the steel beams are installed at the tops of the adjacent steel columns, lifting hooks are arranged at the tops of the steel beams, and the steel columns on the two sides of the frame are provided with the clamping arms extending towards the inner side of the frame respectively. The clamping arms on the two sides of the frame can act on the two sides of the prefabricated laminated slab correspondingly to clamp the prefabricated laminated slab, and the clamping arms are connected with the two steel columns on the same side through the two transverse columns. The two clamping arms are controlled to move in the direction close to each other, the two sides of the prefabricated laminated slab are stably clamped, the clamping arms are rigidly connected with the frame through the transverse columns, the length of the clamping arms is larger than the width of the prefabricated laminated slab, and the clamping arms and the side portions of the prefabricated laminated slab have large contact faces, so that the clamping stability of the prefabricated laminated slab is guaranteed, and the clamping efficiency is improved. And the condition that the tool shakes in windy weather is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated composite board hoisting, in particular to a prefabricated composite board hoisting tool. Background Art

[0002] The installation speed of prefabricated composite panels on the construction site is very fast because most of the work has been completed in the factory; during construction, it is only necessary to hoist the prefabricated panels to the designated location and make necessary adjustments; this can greatly shorten the construction period and save manpower and material resources;

[0003] For the hoisting of prefabricated composite panels, there is a hoisting device for prefabricated composite floor panels with an existing application number of CN202321598322.1. In this patent document, an installation box capable of adjusting the extension length of the rope is disclosed. The crane and the prefabricated composite panel are connected through the installation box, so that the prefabricated composite panel can be more stable during the suspension process. Specifically: the device includes a lifting main hook and a prefabricated panel. A lifting ring is hung at the lower part of the lifting main hook. A mounting box is provided at the bottom of the lifting ring. Both sides of the mounting box are laterally provided with fixed The fixed seat and the bottom of the fixed seat are both laterally symmetrically provided with a first slide rail, the bottom of the first slide rail on the adjacent side is slidably connected to the same slide seat, both ends of the bottom of the slide seat are vertically provided with suspension rods, the bottom of the suspension rods are provided with lifting components for lifting the prefabricated panels, multiple groups of truss steel bars are evenly distributed on the top of the prefabricated panels, cables are symmetrically slidably inserted on both sides of the bottom of the installation box, the bottom ends of the cables are provided with first auxiliary hooks, the lower parts of the first auxiliary hooks are respectively hung on the upper parts of the truss steel bars on the adjacent side, and a driving component for controlling the movement of the prefabricated panels is provided inside the installation box;

[0004] However, the connection between the lifting assembly and the installation box in the patent document is made by ropes, and the clamping positions of the multiple lifting assemblies on the prefabricated composite panels are too dispersed, which makes the operation inconvenient and the clamping effect is relatively limited. In the case of strong winds, the shaking degree of the ropes will increase, causing the clamping positions of the lifting assemblies on the prefabricated composite panels to loosen, posing a safety hazard. Utility Model Content

[0005] In order to solve the deficiencies in the above-mentioned prior art, the purpose of the utility model is to provide a prefabricated composite panel lifting tool, which ensures the clamping stability of the prefabricated composite panel by rigidly connecting the components and increasing the contact surface between the clamping components and the side of the prefabricated composite panel, thereby reducing the shaking of the tool in windy weather.

[0006] The technical solution adopted by the utility model to solve its technical problems is:

[0007] A prefabricated composite panel lifting tool is provided, comprising a frame and a clamping arm. The frame is surrounded by four steel columns and four steel beams. The frame covers the outer side of the prefabricated composite panel. The steel beams are installed on the tops of adjacent steel columns. A hook is arranged on the top of the steel beam, and the hook is connected to the crane through a rope. Clamping arms extending toward the inner side of the frame are respectively arranged on the steel columns on both sides of the frame. The clamping arms on both sides of the frame can act on both sides of the prefabricated composite panel respectively to clamp the prefabricated composite panel. The clamping arms are connected to two steel columns on the same side through two cross columns, and the cross columns and the steel columns can be locked in position through fasteners.

[0008] Furthermore, it is defined that the longer steel beams are located at the front and rear sides of the frame, and the clamping arms are arranged on the steel columns located at the left and right sides of the frame.

[0009] Furthermore, the clamp arm has an L-shaped structure, and a contact horizontal surface and a contact vertical surface are formed on the side of the clamp arm close to the prefabricated composite board. The contact horizontal surface abuts against the bottom surface of the prefabricated composite board, and the contact vertical surface abuts against the side surface of the prefabricated composite board, so that the prefabricated composite board can be held and clamped.

[0010] Furthermore, a plurality of clamp arms are slidably mounted on the steel column, and the plurality of clamp arms are vertically distributed at equal intervals on the side of the steel column, thereby increasing the number of prefabricated composite panels that can be clamped and leaving a spacing between the plurality of prefabricated composite panels to prevent the prefabricated composite panels from scratching each other, ensuring the integrity of the prefabricated composite panels and increasing the efficiency of lifting and handling.

[0011] Furthermore, a sleeve is welded on the steel column, and the cross column passes through the steel column and is slidably connected to the sleeve.

[0012] Furthermore, a thread groove is provided at one end of the cross column close to the clamp arm, and a nut is installed on the thread groove in a threaded engagement with the threaded buckle, and the end plane of the nut away from the prefabricated composite plate can abut against the inner side surface of the steel column.

[0013] Furthermore, lateral limit blocks are detachably fixedly mounted on both ends of the clamping arm.

[0014] Furthermore, the steel column and the steel beam are detachably fixedly connected via multiple sets of fasteners.

[0015] Compared with the prior art, the beneficial effects of the utility model are:

[0016] 1. The prefabricated composite panel lifting tooling of the utility model example controls the two clamping arms to move towards each other, so as to stably clamp the two sides of the prefabricated composite panel. Since the clamping arms are rigidly connected to the frame through cross columns and the length of the clamping arms is longer than the width of the prefabricated composite panel, the clamping arms have a larger contact surface with the sides of the prefabricated composite panel, thereby ensuring the clamping stability of the prefabricated composite panel and reducing the shaking of the tooling in windy weather.

[0017] 2. The prefabricated composite panel lifting tooling of the utility model example has multiple clamping arms that are evenly spaced and vertically distributed on the side of the steel column, which increases the number of prefabricated composite panels that can be clamped and leaves spacing between the multiple prefabricated composite panels to avoid the prefabricated composite panels from scratching each other. The integrity of the prefabricated composite panels is good and the lifting and handling efficiency is high.

[0018] 3. In the prefabricated composite panel lifting tooling of the utility model example, two horizontal columns are provided on the side of the clamp arm, and the horizontal columns can only slide on the steel columns along their own axial directions, so that the clamp arm and the outer wall of the prefabricated composite panel can be tightened by only rotating the nut on the horizontal column on one side, thereby improving the fault tolerance rate during the use of the tooling.

[0019] 4. In the prefabricated composite panel lifting tooling of the utility model example, the lateral limit block can limit the movement of the prefabricated composite panel in the extension direction of the clamp arm, thereby preventing the prefabricated composite panel from falling off, and the construction safety is high.

[0020] 5. In the prefabricated composite panel lifting tooling of the example of the utility model, the overall size of the frame corresponds to the size of the internal steel bars of the prefabricated composite panel. In extreme cases, even if the prefabricated composite panel is detached from between the two clamping arms, the frame itself can stabilize the prefabricated composite panel and prevent the prefabricated composite panel from falling off the frame, thereby increasing the safety of the lifting operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

[0022] Figure 1 The overall structure diagram of the prefabricated composite panel lifting tool provided in the embodiment of the utility model Figure 1 ;

[0023] Figure 2 A schematic diagram of the structure of the prefabricated composite panel lifting tooling part provided by the embodiment of the utility model;

[0024] Figure 3 The overall structure diagram of the prefabricated composite panel lifting tool provided in the embodiment of the utility model Figure 2 ;

[0025] Figure 4 This is a partial enlarged view of the steel column and steel beam provided in the embodiment of the utility model.

[0026] In the figure: 1 prefabricated composite plate, 11 steel column, 12 steel beam, 13 hook, 14 sleeve, 21 clamp arm, 22 cross column, 23 thread groove, 24 nut, 31 lateral limit block. DETAILED DESCRIPTION

[0027] The technical solution of the present utility model will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present utility model, rather than all of the embodiments.

[0028] The components of the embodiments of the present invention generally described and shown in the drawings herein can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention.

[0029] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.

[0030] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0031] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0032] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. It should also be noted that, for ease of description, only the parts related to the utility model are shown in the drawings.

[0033] Embodiment 1:

[0034] like Figure 1 and Figure 3-4As shown, this embodiment provides a prefabricated composite panel lifting tool, including a frame and a clamping arm 21, the frame is surrounded by four steel columns 11 and four steel beams 12, the steel columns 11 and the steel beams 12 are detachably fixedly connected by multiple sets of fasteners, the frame covers the outside of the prefabricated composite panel 1, the steel beams 12 are installed on the top of the adjacent steel columns 11, and the top of the steel beams 12 is provided with a hook 13, which is connected to the crane through a rope, and the steel columns 11 on both sides of the frame are respectively provided with clamping arms 21 extending toward the inner side of the frame, and the clamping arms 21 on both sides of the frame can act on both sides of the prefabricated composite panel 1 respectively to clamp the prefabricated composite panel 1, and the clamping arms 21 are connected to the two steel columns 11 on the same side through two cross columns 22, and the cross columns 22 and the steel columns 11 can be locked in position by fasteners.

[0035] like Figure 2 As shown, the clamp arm 21 is in an L-shaped structure, and a contact horizontal surface and a contact vertical surface are formed on one side of the clamp arm 21 close to the prefabricated composite board 1. The contact horizontal surface abuts against the bottom surface of the prefabricated composite board 1, and the contact vertical surface abuts against the side surface of the prefabricated composite board 1, so as to hold and clamp the prefabricated composite board 1.

[0036] The length of the clamp arm 21 is longer than the width of the prefabricated composite board 1 , so as to prevent the edges of the clamp arm 21 from scratching the prefabricated composite board 1 and thus prevent the integrity of the prefabricated composite board 1 from being damaged.

[0037] like Figure 2 As shown, lateral limit blocks 31 are detachably fixedly installed at both ends of the clamp arm 21 to limit the movement of the prefabricated composite board 1 in the extension direction of the clamp arm 21, thereby preventing the prefabricated composite board 1 from falling off, and ensuring high construction safety.

[0038] like Figure 3 As shown, the longer steel beams 12 are defined to be located at the front and rear sides of the frame, and the clamping arms 21 are arranged on the steel columns 11 located at the left and right sides of the frame, so that the clamping arms 21 can be arranged to be shorter to reduce the overall weight of the tooling.

[0039] When the prefabricated composite panel 1 is hoisted using the prefabricated composite panel hoisting tool of the present application;

[0040] First, place the frame on the ground and place the prefabricated composite board 1 between the two clamping arms 21; then control the two clamping arms 21 to move towards each other to stably clamp the two sides of the prefabricated composite board 1; finally, use a crane to lift the frame together with the prefabricated composite board 1 to the designated position; since the clamping arms 21 are rigidly connected to the frame through the cross columns 22, and the length of the clamping arms 21 is longer than the width of the prefabricated composite board 1, the clamping arms 21 have a larger contact surface with the side 1 of the prefabricated composite board, thereby ensuring the clamping stability of the prefabricated composite board 1 and reducing the shaking of the tooling in windy weather.

[0041] In order to increase the number of prefabricated composite panels that can be clamped by the tooling, such as Figure 1 As shown, multiple clamp arms 21 are slidably installed on the steel column 11, so that the multiple clamp arms 21 are vertically distributed at equal intervals on the side of the steel column 11, thereby increasing the number of prefabricated composite panels 1 that can be clamped and leaving a distance between the multiple prefabricated composite panels 1 to avoid the prefabricated composite panels 1 from scratching each other, thereby ensuring the integrity of the prefabricated composite panels 1 and increasing the efficiency of lifting and handling.

[0042] In order to improve the operability of the prefabricated composite panel lifting tooling, Figure 2 As shown, a thread groove 23 is provided at one end of the horizontal column 22 close to the clamp arm 21, and a nut 24 is installed on the thread groove 23 by threaded engagement, so that the nut 24 is away from the end plane of the prefabricated composite board 1 and abuts against the inner side surface of the steel column 11, and the clamp arm 21 is controlled to be pressed against the outer side wall of the prefabricated composite board 1. At the same time, multiple nuts 24 are rotated to control the two clamp arms 21 to move in a direction close to each other, and the self-locking characteristic of the thread structure is utilized to stably clamp the two sides of the prefabricated composite board 1.

[0043] Since two transverse columns 22 are provided on the side of the clamp arm 21, and the transverse column 22 can only slide on the steel column 11 along its own axial direction, the clamp arm 21 and the outer wall of the prefabricated composite panel 1 can be tightened by only rotating the nut 24 on the single-side transverse column 22, thereby improving the fault tolerance rate during the use of the tooling.

[0044] Among them, the overall size of the frame of the present application corresponds to the size of the internal steel bars of the prefabricated composite panel 1. In extreme cases, even if the prefabricated composite panel 1 is detached from between the two clamping arms 21, the frame itself can stably limit the prefabricated composite panel 1 to prevent the prefabricated composite panel 1 from falling off the frame, thereby increasing the safety of the lifting operation.

[0045] Embodiment 2:

[0046] The features of this embodiment that are the same as those of the first embodiment are not described in detail. The difference between this embodiment and the first embodiment is that: Figure 1 As shown, in this embodiment, a sleeve 14 is welded on the steel column 11, and the cross column 22 passes through the steel column 11 and is slidably connected with the sleeve 14. Since the cross column 22 passes through the steel column 11 and the sleeve 14 at the same time, the supporting performance of the cross column 22 is improved, and the safety of equipment use is increased.

[0047] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the utility model involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the concept of the utility model. For example, the above features are replaced with the technical features with similar functions disclosed in the present application (but not limited to) by each other to form a technical solution.

[0048] Except for the technical features described in the specification, the other technical features are known technologies to those skilled in the art. In order to highlight the innovative features of the present utility model, the other technical features will not be described in detail here.

Claims

1. A prefabricated composite panel lifting tool, characterized in that: The invention comprises a frame surrounded by four steel columns (11) and four steel beams (12), the frame covering the outside of the prefabricated composite panel (1), the steel beams (12) being installed on the tops of the adjacent steel columns (11), the tops of the steel beams (12) being provided with hooks (13), and the hooks (13) being connected to the crane via ropes; The steel columns (11) on both sides of the frame are respectively provided with clamping arms (21) extending inwardly of the frame. The clamping arms (21) on both sides of the frame can act on both sides of the prefabricated composite board (1) to clamp the prefabricated composite board (1). The clamping arms (21) are connected to the two steel columns (11) on the same side via two transverse columns (22).

2. The prefabricated composite panel lifting tool according to claim 1, characterized in that: The longer steel beam (12) is defined to be located at the front and rear sides of the frame, and the clamping arms (21) are arranged on the steel columns (11) located at the left and right sides of the frame.

3. The prefabricated composite panel lifting tool according to claim 1, characterized in that: The clamp arm (21) is in an L-shaped structure, and a horizontal contact surface and a vertical contact surface are formed on a side of the clamp arm (21) close to the prefabricated composite board (1), and the horizontal contact surface and the vertical contact surface can abut against the bottom surface and the side surface of the prefabricated composite board (1) at the same time.

4. The prefabricated composite panel lifting tool according to claim 1, characterized in that: A plurality of clamping arms (21) are slidably mounted on the steel column (11), and the plurality of clamping arms (21) are vertically distributed at equal intervals on the side of the steel column (11).

5. The prefabricated composite panel lifting tool according to claim 1, characterized in that: A sleeve (14) is fixedly mounted on the steel column (11), and a transverse column (22) passes through the steel column (11) and is slidably connected to the sleeve (14).

6. The prefabricated composite panel lifting tool according to claim 1, characterized in that: A thread groove (23) is provided at one end of the transverse column (22) close to the clamp arm (21), and a nut (24) is installed on the thread groove (23) in a threaded engagement manner. The end plane of the nut (24) away from the prefabricated composite plate (1) can abut against the inner side surface of the steel column (11).

7. The prefabricated composite panel lifting tool according to claim 1, characterized in that: Lateral limit blocks (31) are respectively detachably fixedly mounted on both ends of the clamping arm (21).

8. The prefabricated composite panel lifting tool according to claim 1, characterized in that: The steel column (11) and the steel beam (12) are detachably fixedly connected via multiple sets of fasteners.