Water and soil conservation ecological revetment reinforcing equipment
By using arc-shaped guide plates, spring telescopic structures and limit frames in soil and water conservation ecological bank protection equipment, the problem of rapid adjustment of uneven construction positions is solved, construction speed and efficiency are improved, and automatic vertical positioning of arc-shaped guide plates is realized. and synchronous rotation to meet installation requirements at different angles.
Patent Information
- Application Number
- CN202420518346.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-18
AI Technical Summary
During the construction process, when the existing soil and water conservation ecological bank protection reinforcement equipment encounters an inclined or uneven position, it takes a long time to adjust the support rods to make the clamping device perpendicular to the horizontal plane, causing the construction speed to be affected.
A soil and water conservation ecological bank protection equipment including an arc guide plate, a spring telescopic structure and a limit frame is designed. The gravity and spring telescopic structure are used to realize the rapid positioning and rotation of the arc guide plate, reducing the position adjustment time, and through the stuck The slot and clamping plate mechanism realizes the synchronous rotation of the arc-shaped guide plate to meet the installation requirements at different angles.
Through the automatic vertical positioning and synchronous rotation of the arc-shaped guide plate, the adjustment time of the equipment in tilted or uneven positions is significantly reduced, the construction speed and efficiency are improved, and the possibility of tilting of the protective piles is reduced.
Smart Images

Figure CN221919410U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to ecological bank reinforcement equipment, in particular to soil and water conservation ecological bank reinforcement equipment, belonging to the technical field of ecological protection. Background Art
[0002] Soil erosion refers to the phenomenon that due to natural or human factors, rainwater cannot be absorbed locally and flows downstream, causing soil erosion, resulting in the loss of both water and soil. When protecting the bank, green plants are usually planted on the bank, and the roots and stems of the green plants are used to hold the soil for soil and water conservation, and protective nets are attached to the green plants; or plants are combined with civil engineering to protect the river slope. Ecological bank protection can achieve the purpose of soil consolidation and slope protection, prevent soil erosion, and meet the requirements of ecological environment restoration. It is the most ideal bank protection method for protecting water banks, water bodies and natural ecological water environment. It is currently being managed. Wooden piles will be used for ecological bank protection. The wooden piles will be pressed into the river bank and the interception net will be set up to cooperate with the planting of green plants.
[0003] During the installation of wooden piles, auxiliary equipment will be used for construction. For example, the existing utility model with application number: 202222935462.5 discloses a soil and water conservation ecological revetment reinforcement device, which relates to the technical field of revetment reinforcement equipment, including a fixing plate, a clamping cavity is opened in the middle of the fixing plate, and a clamping device for preventing the revetment wooden piles from tilting is arranged in the clamping cavity; a plurality of support rods are fixedly connected to the four corners of the bottom of the fixing plate, and the bottom of the support rods is sleeved in the top cavity of the support sleeve
[0004] In the process of reinforcement equipment application, it is inevitable to encounter inclined or uneven construction positions. At this time, it takes a long time to adjust the four support rods to make the clamping device perpendicular to the horizontal plane, resulting in a waste of time and affecting the construction speed. Utility Model Content
[0005] 1. Technical issues to be resolved
[0006] The purpose of the utility model is to provide a soil and water conservation ecological bank reinforcement equipment in order to solve the above-mentioned problems, so as to solve the problem encountered in the prior art that the construction position is inclined or uneven. At this time, it takes a long time to adjust the four support rods to make the clamping device perpendicular to the horizontal plane, resulting in a waste of time and affecting the construction speed.
[0007] (II) Technical solution
[0008] The utility model is implemented through the following technical scheme: a soil and water conservation ecological bank protection reinforcement equipment, including a fixed frame and a protection pile, two arc guide plates are arranged inside the fixed frame, a spring telescopic structure is arranged on one side of the arc guide plate, a mounting shaft is installed on one side of the spring telescopic structure, a limit frame is arranged between the two mounting shafts, an operating bolt is threadedly connected inside the limit frame, one of the arc guide plates is provided with two card slots, and the other arc guide plate is fixedly connected with two card plates on one side, the card plates are arranged inside the card slots, and under the action of the two card plates, the two arc guide plates are clamped together.
[0009] Preferably, one end of the installation shaft passes through the fixing frame and is rotatably connected to the fixing frame, one end of the installation shaft is fixedly connected to a hand wheel, and a plurality of ground nails are fixedly connected to the bottom of the fixing frame.
[0010] Preferably, the tops of the two arc-shaped guide plates are fixedly connected with flared guide plates, and the clamping plate is arranged on one side of the clamping slot.
[0011] Preferably, the fixing frame is provided with two sliding grooves, the limiting frame is arranged in a U shape, and two ends of the limiting frame are respectively arranged inside the two sliding grooves.
[0012] Preferably, an arc-shaped groove is provided at one end of the limit frame, and two telescopic rods are fixedly connected between the limit frame and the fixed frame. The two telescopic rods support and limit the slender limit frame to avoid the situation where the two ends of the limit frame cannot limit the two mounting shafts at the same time due to deformation of the limit frame, and one end of the operating bolt is rotatably connected to the fixed frame.
[0013] Preferably, the spring telescopic structure includes a mounting cross plate, which is fixedly connected to one side of the mounting shaft, and one side of the mounting cross plate is fixedly connected to two fixed tubes, both of which are provided with sliding rods, and a reset spring is sleeved on the outer side of the sliding rods.
[0014] Preferably, the two ends of the return spring are respectively fixedly connected with a fixing ring and a fixing pad, the fixing pad is fixedly connected to the fixing tube, the fixing ring is fixedly connected to the arc guide plate and the sliding rod, and when the installed cross plate is rotated, the arc guide plate is driven to rotate synchronously through the two fixing tubes, two sliding rods and two fixing rings, thereby meeting the need for the arc guide plate to automatically rotate and position under the influence of gravity.
[0015] The utility model provides a soil and water conservation ecological bank reinforcement device, which has the following beneficial effects:
[0016] 1. In the soil and water conservation ecological bank reinforcement equipment, the arc guide plate is much heavier than the flared guide plate due to material reasons. Therefore, the arc guide plate moves vertically to the horizontal plane under the action of gravity, while the flared guide plate remains on the top of the arc guide plate. The lower limit frame moves under the action of the operating bolt, and an arc groove is provided at one end of the moving limit frame, so that the limit frame can be sleeved on the outside of the circular installation shaft. The installation shaft is limited so that the installation shaft cannot rotate. At this time, the arc guide plate installed on the installation shaft through the spring telescopic structure is limited and cannot rotate, completing the positioning of the arc guide plate, using the influence of gravity to make the arc guide plate perpendicular to the horizontal plane, and quickly completing the positioning of the two arc guide plates that guide the installation of the protective piles, reducing the time cost investment required for adjusting the position of the arc guide plates.
[0017] 2. For the soil and water conservation ecological bank reinforcement equipment, before the arc guide plate is propped open by the protective pile, the clamping plate is arranged inside the clamping slot. Under the action of the two clamping plates, the two arc guide plates are clamped together and can rotate synchronously. Therefore, by operating the hand wheel fixedly connected to one end of the mounting shaft, when one mounting shaft rotates, the two arc guide plates rotate synchronously. The staff can manually adjust the angles of the two arc guide plates, and then operate the operating bolt to drive the limit frame to limit the mounting shaft to meet the installation needs of the protective piles at different angles. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0019] Figure 2 It is a structural schematic diagram of the fixing frame of the utility model;
[0020] Figure 3 For this utility model Figure 2 Schematic diagram of the C part structure;
[0021] Figure 4 It is a structural schematic diagram of the sliding rod of the utility model.
[0022]
Main component symbol description
[0023] 1. Fixed frame; 2. Ground nail; 3. Install the rotating shaft; 4. Install the horizontal plate; 5. Fixed pipe; 6. Sliding rod; 7. Fixed pad; 8. Reset spring; 9. Fixed ring; 10. Sliding groove; 11. Limiting frame; 12. Arc groove; 13. Operating bolt; 14. Telescopic rod; 15. Expanding guide plate; 16. Arc guide plate; 17. Slot; 18. Card plate; 20. Handwheel; 21. Protective pile. DETAILED DESCRIPTION
[0024] The utility model embodiment provides a soil and water conservation ecological bank protection reinforcement equipment.
[0025] See also Figure 1 , Figure 2 , Figure 3 and Figure 4 , including a fixing frame 1 and a protection pile 21, two arc-shaped guide plates 16 are arranged inside the fixing frame 1, a spring telescopic structure is arranged on one side of the arc-shaped guide plate 16, a mounting shaft 3 is installed on one side of the spring telescopic structure, a limit frame 11 is arranged between the two mounting shafts 3, an operating bolt 13 is threadedly connected to the limit frame 11, one side of one arc-shaped guide plate 16 is provided with two card slots 17, and one side of the other arc-shaped guide plate 16 is fixedly connected with two card plates 18.
[0026] When the utility model is used: the fixing frame 1 with a plurality of ground nails 2 fixedly connected at the bottom is inserted into the soil, so that the fixing frame 1 is installed in the river bank soil. When the fixing frame 1 is installed, since one end of the installation shaft 3 passes through the fixing frame 1 and is rotatably connected to the fixing frame 1, the installation shaft 3 can rotate inside the fixing frame 1. The installation shaft 3 rotates through the arc guide plate 16 installed by the spring telescopic structure. The top of the two arc guide plates 16 are fixedly connected with the flared guide plate 15. The arc guide plate 16 has a much greater mass than the flared guide plate 15 due to the material. Therefore, the arc guide plate 16 is vertical to the horizontal plane under the action of gravity, and the flared guide plate 15 remains on the top of the arc guide plate 16.
[0027] Two sliding grooves 10 are provided on one side of the fixing frame 1 , and two ends of a U-shaped limiting frame 11 are respectively arranged inside the two sliding grooves 10 . The two ends of the limiting frame 11 are limited so that they can only move inside the sliding grooves 10 . At this time, the rotating fixed frame 1 rotates the connected operating bolt 13. Because the operating bolt 13 penetrates the limit frame 11 and is threadedly connected to the limit frame 11, the two ends of the limit frame 11 are limited. Therefore, under the action of the operating bolt 13, the lower limit frame 11 moves. An arc groove 12 is opened at one end of the moving limit frame 11, so that the limit frame 11 can be sleeved on the outer side of the circular installation shaft 3. With the rotation of the operating bolt 13, the friction between the limit frame 11 and the installation shaft 3 increases, and the installation shaft 3 is limited so that the installation shaft 3 cannot rotate. At this time, the arc guide plate 16 installed by the spring telescopic structure of the installation shaft 3 is limited and cannot rotate, completing the positioning of the arc guide plate 16, and using the influence of gravity to make the arc guide plate 16 perpendicular to the horizontal plane, quickly completing the positioning of the two arc guide plates 16 that play a guiding role in the installation of the protective pile 21, reducing the time cost investment required for adjusting the position of the arc guide plate 16, and reducing the possibility of the protective pile 21 tilting after installation.
[0028] After the position of the arc-shaped guide plate 16 is adjusted, the protection pile 21 is inserted between the two expanded guide plates 15, and then the protection pile 21 is pushed into the space between the two arc-shaped guide plates 16. Figure 1As shown, the protective pile 21 opens the two arc-shaped guide plates 16, and the arc-shaped guide plates 16 move toward the mounting cross plate 4. During this process, the spring telescopic structure contracts, and the mounting cross plate 4 cooperates with the spring telescopic structure to limit the rotation of the arc-shaped guide plates 16, so that the moving arc-shaped guide plates 16 maintain the guiding effect on the downward movement of the protective pile 21, ensuring that the protective pile 21 is inserted into the soil in a posture perpendicular to the horizontal plane.
[0029] The installation horizontal plate 4 in the spring telescopic structure is fixedly connected to one side of the installation shaft 3, so the installation shaft 3 drives the installation horizontal plate 4 to rotate. A sliding rod 6 is arranged on one side of the two fixed tubes 5 fixedly connected to one side of the installation horizontal plate 4, and a reset spring 8 is sleeved on the outer side of the sliding rod 6. The fixed pad 7 fixedly connected to one end of the reset spring 8 is fixedly connected to the fixed tube 5, and the fixed ring 9 fixedly connected to the other end of the reset spring 8 is fixed together with the arc guide plate 16 and the sliding rod 6. Therefore, when the installation horizontal plate 4 rotates, the arc guide plate 16 is driven to rotate synchronously through the two fixed tubes 5, the two sliding rods 6 and the two fixed rings 9, so as to meet the need of the arc guide plate 16 to rotate and position automatically under the influence of gravity. And when the arc guide plate 16 moves toward the installation horizontal plate 4, the reset spring 8 is forced to shrink, and the fixed ring 9 pushes the sliding rod 6 to move inside the fixed tube 5, so as to meet the need of the arc guide plate 16 to move toward the installation horizontal plate 4.
[0030] Since one of the arc guide plates 16 has two slots 17 on one side, and the other arc guide plate 16 has two clamping plates 18 fixedly connected on one side, and the two clamping plates 18 are respectively arranged on one side of the two slots 17, before the arc guide plate 16 is opened by the protective pile 21, the clamping plate 18 is arranged inside the slot 17, and under the action of the two clamping plates 18, the two arc guide plates 16 are clamped together, and the two arc guide plates 16 can rotate synchronously, so by operating the hand wheel 20 fixedly connected to one end of the mounting shaft 3, when one mounting shaft 3 rotates, the two arc guide plates 16 rotate synchronously, and the staff can manually adjust the angles of the two arc guide plates 16, and then rotate the operating bolt 13 to drive the limit frame 11 to limit the mounting shaft 3, so as to meet the installation needs of the protective pile 21 at different angles.
[0031] Two telescopic rods 14 are fixedly connected between the limiting frame 11 and the fixing frame 1 , and the two telescopic rods 14 support and limit the slender limiting frame 11 to avoid deformation of the limiting frame 11 resulting in the two ends of the limiting frame 11 being unable to limit the two mounting shafts 3 at the same time.
[0032] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A soil and water conservation ecological bank reinforcement device, comprising a fixing frame (1) and a protection pile (21), characterized in that: Two arc-shaped guide plates (16) are arranged inside the fixing frame (1), a spring telescopic structure is arranged on one side of the arc-shaped guide plate (16), a mounting shaft (3) is installed on one side of the spring telescopic structure, a limiting frame (11) is arranged between the two mounting shafts (3), an operating bolt (13) is threadedly connected inside the limiting frame (11), two clamping grooves (17) are arranged on one side of one of the arc-shaped guide plates (16), and two clamping plates (18) are fixedly connected on one side of the other arc-shaped guide plate (16).
2. The soil and water conservation ecological bank reinforcement equipment according to claim 1 is characterized by: One end of the installation shaft (3) passes through the fixing frame (1) and is rotatably connected to the fixing frame (1); one end of the installation shaft (3) is fixedly connected to a hand wheel (20); and a plurality of ground nails (2) are fixedly connected to the bottom of the fixing frame (1).
3. The soil and water conservation ecological bank reinforcement equipment according to claim 1 is characterized by: The tops of the two arc-shaped guide plates (16) are fixedly connected to a flared guide plate (15), and the clamping plate (18) is arranged on one side of the clamping slot (17).
4. The soil and water conservation ecological bank reinforcement equipment according to claim 1 is characterized by: The fixing frame (1) is provided with two sliding grooves (10), the limiting frame (11) is arranged in a U shape, and the two ends of the limiting frame (11) are respectively arranged inside the two sliding grooves (10).
5. The soil and water conservation ecological bank reinforcement equipment according to claim 1 is characterized by: An arc-shaped groove (12) is formed at one end of the limiting frame (11); two telescopic rods (14) are fixedly connected between the limiting frame (11) and the fixing frame (1); and one end of the operating bolt (13) is rotatably connected to the fixing frame (1).
6. The soil and water conservation ecological bank reinforcement equipment according to claim 1 is characterized by: The spring telescopic structure comprises a mounting transverse plate (4), wherein the mounting transverse plate (4) is fixedly connected to one side of the mounting shaft (3), and two fixed tubes (5) are fixedly connected to one side of the mounting transverse plate (4), wherein a sliding rod (6) is arranged inside the two fixed tubes (5), and a return spring (8) is sleeved on the outer side of the sliding rod (6).
7. The soil and water conservation ecological bank reinforcement equipment according to claim 6 is characterized by: The two ends of the return spring (8) are respectively fixedly connected with a fixing ring (9) and a fixing pad (7); the fixing pad (7) is fixedly connected to the fixing tube (5); and the fixing ring (9) is fixedly connected to the arc-shaped guide plate (16) and the sliding rod (6).